0% found this document useful (0 votes)
366 views1 page

Construction Safety Demolition Guide

This document is a demolition permit application that requests information about the job such as the date, requesting person, work order number, job description, and safety checks. It requires sign off from responsible contractors in different areas like electrical, piping, and fire mains. The permit must be approved by the contractor site manager and construction manager before the demolition can take place.

Uploaded by

Balogun Isaac
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
366 views1 page

Construction Safety Demolition Guide

This document is a demolition permit application that requests information about the job such as the date, requesting person, work order number, job description, and safety checks. It requires sign off from responsible contractors in different areas like electrical, piping, and fire mains. The permit must be approved by the contractor site manager and construction manager before the demolition can take place.

Uploaded by

Balogun Isaac
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

CM CBA 108Demolition

Construction Safety User Manual

Demolition Permit
PLANT Date Permit Requested: Person Requesting Permit: Project or Plant Work Order #: Description of Job Intended: Area for Sketch: (Use back side for larger sketches) Expiration Date:

Safety Check: Is this a high-risk job? Special shoring required? Special dewatering required? Were plant drawings used to verify risk? Are lockouts required? Are hot work permits required? Is pathogen pail needed? Submitted By:

Yes

No

(Contractor Planner) Site Sign-OffResponsible Person, by Area: Electrical Piping Fire Mains Yard/Miscellaneous Confined Space Power, control, camera, and lighting conduit/wire Water, sewage, storm, process piping Sprinkler systems/alarms Miscellaneous yard/building items Air monitoring/safety watch for working in critical excavations (required by law)

Contractor Site Manager/Date (for approval)

P&G Construction Manager/Date (for authorization)

108-1

October 2000