Work Method Statement Ats

This work method statement outlines the preventative maintenance tasks of carrying out a generator load/ATS test at the One Lake Plaza JLT location on September 23, 2018. The engineer Yasir Mehmood and technician Depinder Rana are responsible for safely conducting the test under the supervision of the supervisor. The document details the procedures, permits, tools, equipment, and personal protective equipment required.

Uploaded by

YasirSwati
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views2 pages

Work Method Statement Ats

This work method statement outlines the preventative maintenance tasks of carrying out a generator load/ATS test at the One Lake Plaza JLT location on September 23, 2018. The engineer Yasir Mehmood and technician Depinder Rana are responsible for safely conducting the test under the supervision of the supervisor. The document details the procedures, permits, tools, equipment, and personal protective equipment required.

Uploaded by

YasirSwati
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PO Box 75615, Dubai 24hrs

United Arab Emirates Tel


www.gwbintl.com Fax

WORK METHOD STATEMENT


Client: Concordia
Location: One lake plaza JLT
Date: 23/09/2018

PERSURE Preventive Maintenance


SCOPE Carrying out Generator load/ATS test
PERSONNEL Engineer: Yasir Mehmood
INVOLVED Technician: Depinder Rana
RESPONSIBILITIES Supervisor to ensure:

 All activities are to be carried out correctly and safely.


 Supervision and periodic monitoring of the task.
 TBTs (Tool Box Talk) prior to the start of the task.
 Reporting of any emergencies/incident/near misses.
 Safe work procedures are followed with appropriate use select approved PPE.
 Operative must have to read and understand the risk assessment or
supervisor has to brief operative to ensure operative understand the risk
involved in activities.
 Operatives to check the work area to ensure that the work area is safe to
work in avoiding slips/trips and fall.
 PTW to be obtained prior to the start of the task by an authorized person.

KEY TOOLS & Common hand tools, AC/DC clamp meter, Hand tool
EQUIPMENT

A GROUP GWB International DMCC Registered and licensed as a FREEZONE Company under the
COMPANY OF PO Box 214111, Dubai, UAE Rules & Regulations of DMCCA, Dubai, United Arab Emirates
PO Box 75615, Dubai 24hrs
United Arab Emirates Tel
www.gwbintl.com Fax

Method of work.  Obtain necessary permit if necessary.


 The supervisor should give toolbox talk on the task.
 Inspect mechanical & physical condition.
 Confirm components are as per drawing.
 Check-up the mechanical On/Off operation of all MCCB,s.
 Check-up the other additional/ parallel operating controls for breakers.
 Start the emergency generator in manual mode.
 Check the On/Off operation of MCCB (in ATS circuit) electrically.
 Observe the external status indication lamp for the operation of the breaker.
 Check the all interlock and selection as per schematic.
 Switch-off the main power source (DEWA) MCCB/ACB for ATS.
 Observe the load transfer to the emergency power source (generator).
 Switch-on the main power source (DEWA) MCCB/ACB for ATS.
 Observe the load transfer to the main power source (DEWA).

METHOD OF  Normal access for the LV room.


ACCESS/EGRESS  Normal access for generator room.
LICENSE/PERMENT/  Electric work permit.
CERTIFICATE  Isolation work permit.
CONTROL  The supervisor will brief/ toolbox talk to operatives before starting of the
MEASURES (Falls task.
protection  Only competent staff to operate.
Emergency facility
 Use suitable PPE required for the task.
 Follow the site emergency response procedure.
 Continue to be supervision to be provided.
 Insulated tools.
 Permit of the work system.
PPE REQUIRMENTS  Safety goggles
 Safety shoes