DIL DIH pipes
According to Sir Lur, DIH and DIL pipe lines ay sa trench papadaanin
para walang obstruction
T-6008A
Outlet pipe will be elevated; papadaanin sa taas ng firepro pump
house.
Ask Sir Lur for updated dev plan. As of
10/25/18 there's still no updated dev plan
Ask Sir Lur for updated dev plan. As of
10/25/18 there's still no updated dev plan
                                                         UNIT 600
                                                           LMO
  TANK TAG      CAPACITY (M3)         MATERIAL   TL-TL
T-6001A             220                SS 304L   9144
T-6001B             220                SS 304L   9144
T-6001C             220                SS 304L   9144
T-6001D             220                SS 304L   9144
T-6001E             220                SS 304L   9144
T-6001F             220                SS 304L   9144
T-6001G             220                SS 304L   9144
T-6001H                220             SS 304L   9144
          TRUCK UNLOADING DATA
                 8 trucks/shift
              30 trucks/delivery
            4.5 hrs/shift unloading
      FILTER (TO LMO TANKS) DATA
F-6015A
F-6015B
          FILTER (OUTGOING) DATA
F-6002A
F-6002B
UNIT 600
  LMO
           I.DIAMETER    FOUNDATION HEIGHT (mm)
               5820               600
               5820               600
               5820               600
               5820               600
               5820               600
               5820               600
               5820               600
               5820               600
                          PUMP DATA
           P-6014A
                             Loading to LMO tanks
           P-6015B
                        PUMP DATA (LOBE)
           P-6003A
                             To Pharma Day Tanks
           P-6003B
Note 1: According to Sir Lur, LMO dimennsions
was changed as per their last discussion.
Note2: LMO tanks still have walkways
Note3: Unloading pumps quantity was
changed to 4. 1 pump is to 2 tanks.
Note 4: Confirmed if LMO tanks are already
fabricated . Ask if it is possible to change
nozzle inlet orientation since space is not
enough
Note1 confirmation: No change in dimensions.
Note2 confirmation: LMO confirmed still have
walkway
Note3 confirmation: Still waiting for
confirmation .
Note4 confirmation: Fabrication will be on site
so according to Sir Stewart it's still possible to
change inlet nozzle orientation.
                                                          UNIT 600
                                                           MTSA
  TANK TAG       CAPACITY (M3)        MATERIAL    TL-TL
T-6004A               40              ALUMINUM    6600
T-6004B               40              ALUMINUM    6600
T-6004C               40              ALUMINUM    6600
T-6004D               40              ALUMINUM    6600
T-6004E               40              ALUMINUM    6600
T-6004F               40              ALUMINUM    6600
              TRUCK UNLOADING DATA
       3 min pumping time from MTSA drums (4)
                  3 trucks/delivery
                  10 hrs/operation
         240 drums/delivery ; 3 trucks/delivery
           FILTER (TO LMO TANKS) DATA
NONE
NONE
             FILTER (OUTGOING) DATA
NONE
NONE
  UNIT 600
     MTSA
HLL        NLL    I.DIAMETER (mm)
5912      4917          3200
5912      4917          3200
5912      4917          3200
5912      4917          3200
5912      4917          3200
5912      4917          3200
                                    PUMP DATA
                 P-6006A
                 P-6006B
                 P-6106A
                 P-6106B
                 P-6206A
                 P-6206B
                                    PUMP DATA
                 P-6007A
                 P-6007B
  FOUNDATION HEIGHT (mm)
           600                   Note1: Foundation height was 200 mm as
           600                   proposed by Gemsum but according to Sir Lur
           600                   it should be chnaged to 600 mm for easy
           600                   maintenance.
           600
           600                   Note2: The N7 (drain) orientation should be
                                 placed under the tank since they will place a
PUMP DATA                        trench in MTSA tank area.
                                 Note1 confirmation: Still waiting for Sir
     Loading to MTSA tanks
                                 Rocky's approval
PUMP DATA                        Note2 confirmation: Retain N7 orientation.
    TO PHARMA DAY TANKS      `
was 200 mm as
according to Sir Lur
0 mm for easy
ntation should be
e they will place a
aiting for Sir
 N7 orientation.
T-6013A Located inside the RW Tank Farm
T-6013B Located near Finished Product Warehouse
Note1: There will be a third overhead tank.
Still has no confirmed dimensions and
location.
Note2: Modular tanks has still no
confirmed nozzle orientation and location.
Confirmed with Engineering according to
Sir Lur.
Note1 confirmation: 3rd overhead tank
fabrication on hold. Still unknown location.
Note2 confirmation: Ask Sir Stewart for
drawings with nozzle location.
                                                        UNIT 600
                                                         DIH DIL
          TANK TAG   CAPACITY (M3)   MATERIAL   TL-TL
        T-6010A           44          SS 304    6650
        T-6010B           44          SS 304    6650
        T-6010C           44          SS 304    6650
        T-6010D           44          SS 304    6650
(DIH)   T-6012            44          SS 304    6650
                 TRUCK UNLOADING DATA
               FILTER (TO LMO TANKS) DATA
        NONE
        NONE
                 FILTER (OUTGOING) DATA
        NONE
        NONE
  UNIT 600
   DIH DIL
HLL        NLL      I.DIAMETER (mm)
5990       4992           3350
5990       4992           3350
5990       4992           3350
5990       4992           3350
5990       4992           3350
                                      PUMP DATA
                                      PUMP DATA
                  P- 6011A (DIL)
                  P-6011B (DIL)
                  P-6012A (DIH)
                  P-6012B (DIH)
  FOUNDATION HEIGHT (mm)
           1500            Note1: Already fabricated. Ask sir Rey for As
           1500            built drawing
           1500
           1500
           1500
                           Note1confirmation: Still waiting for Sir Rey's
                           reply
PUMP DATA
     From DI Water Plant
PUMP DATA
Ask sir Rey for As
aiting for Sir Rey's
                                                     UNIT 600
                                                    RW Service
                                  SERVICE
           To Engineering Future
           VB-1a (To XXXXX)
           Soapery Day Tanks
           To Raw Materials Warehouse
           Pharma Day tank
           Raw Materials Tank Farm 1
           Raw Materials Tank Farm 2
           Raw Material Tank Farm 3
           Gym and indoor facilities 1
           Gym and indoor facilities 2
           Gym and indoor facilities 3
           Administration building
           Hazardous plant and RW tank farm
           Finshed goods WH 1 (Existing) for domestic and process
           used (T&W Production)
           Anything Warehouse
           Parking Area (employees and guests) and clinic
           Engineering Office (Existing)
           VB-16 (XXXXX)
           Casino Production Bldg
           Finished Goods WH 2 (Existing)
           Finished Goods WH 3 (Existing)
           VB-20 (XXXXX)
                                                UNIT 600
                                               RW Service
P&ID Tag                            SERVICE
VB-2c      DIH to soapery day tanks
VB-4b      DIH to pharma day tank
VB-2c      DIH To Hazardous day tank
vb-2c      DIH to T&W Production
VB-2c      DIH to FandB Produuction
VB-2c      DIL to Casino Production
VB-2b      DIL to soapery day tank
VB-4c      DIL to Pharma Day Tanks
VB-21b     DIL to Hazardous Day tank
VB-9       RW to Gym and Indoor facilities 2
VB-8       RW to Gym and Indoor Facilities 1
VB-6       RW Raw Mat Tank Farm 2
VB-7       RW Raw Mat Tank Farm 3
VB-3       Raw Mat Warehouse
VB-4a      Pharma Day tank
VB-5       Raw Material tank farm 1
VB-10      To Gym and Indoor Facilities 3
VB-11      Administration Building
VB-2a      RW Soapery Day tanks
VB-12   RW To hazardous plant and raw water tank farm
VB-13   RW to finished oods WH1
VB-14   RW to anything warehouse
VB-15   RW to parking area
VB-8    RW To Engineering office
VB-16   RW to XXXX (updated 1025 loc near guardhouse)
VB-17   DIH Casino prod bldg
VB-18   RW to finished goods WH2
        RW to finished goods WH3 (updated 102518 loc at casino
VB-19   warehouse)
        RW to XXXXX (updated1025 loc opposite casino WH; near
VB-20   area 6146 sqm)
        RW to XXXX (updated 1025 loc at plug end for future
VB-1a   connection)
        RW To Engineering Future (updated 1025 loc above main
VB-1    distribution area)
        Modified VB tag
        Present in current P&ID but not present in DevPlan
        Coincides with P&ID and Devplan
                                                  New VB
        vb-23a
        vb-23b
        vb-22b
        vb-22a
T 600
ervice
         CONSUMPTION (CU.M/HR)
                 4.92
                  13.6
                  1.09
                  13.8
                  0.09
                  0.09
                  0.09
                  2.02
                  2.02
                  2.02
                  16.1
                 12.37
                 3.02
                  0.27
                 0.645
                  0.37
                 2.69
                 3.51
                 0.98
                                          VB3
e
         CONSUMPTION (CU.M/HR)
                  15
                  20
                  7.5            vb-21a   wala sa p&ID pero meron sa dev
                  7.5
                  7.5
                  9.9            vb-24b
                  10
                  10
                  10             vb-21b
                 2.02
                 2.02
                 0.09
                 0.09
                 1.09
                 13.8
                 0.09
                 2.02
                 16.1
                 13.6
                       12.37
                                            wala sa devplan ni PARAGSA
                        3.02
                        0.27
                       0.645
                        0.37
                        2.69                vb-24a
                        3.51
                        0.98
w VB
       DIH to finish goods warehouse bldg
       DIL to finish goods warehouse bldg
       DIL to WH 04
       DIH to WH 04
          Note1: Confirm service areas with PARAGSA/Sir
          Stewart
          Note1confirmation: Confirm with IPI Realty but
          as per Sir Stewart, there are no changes.
          10.25.18 Sir Lur gave a copy of PARAGSA's
          latest plan.
wala sa p&ID pero meron sa devplan
ni PARAGSA   See "PARAGSA"" dwg file for explanation.