Work Order Template

The document is a work order from Aman Group Limited to Buhler (Bangladesh) Pvt Ltd to grind and reflute two pieces of crumbler roller. The total cost is 69,000 Taka including a 15% VAT. Buhler must deliver the rollers within two weeks to Aman Feed Mill in Sirajgong. Payment of 100% will be made upon delivery if the quality meets the specifications stated in the work order.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
260 views1 page

Work Order Template

The document is a work order from Aman Group Limited to Buhler (Bangladesh) Pvt Ltd to grind and reflute two pieces of crumbler roller. The total cost is 69,000 Taka including a 15% VAT. Buhler must deliver the rollers within two weeks to Aman Feed Mill in Sirajgong. Payment of 100% will be made upon delivery if the quality meets the specifications stated in the work order.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Aman Group Limited

2 Ishakha Avenue
Sector 6, Uttara, Dhaka 1230

IE/WO/SL7/6/18 27-Jun-18

To
Buhler (Bangladesh) Pvt Ltd.
171/1 Tejgoan Industrial Area, Dhaka 1208

Subject: Grinding and Refluting of fluted roll

Dear sir,
With referance to your offer dated 1-March, 2018, and our discussion on the above subject matter,
the undersigned is pleased to place you the work order for recutting teeth of 2 pcs crumbler roller.
The work job will meet the followidng the specifications:

1 Grinding and Refluting of fulted Crumbler roller


2 Shaft aligment of roller

Unit price Total Price


SL No Particulars Quantity
(Tk) (Tk)
1 Gringing and refluting of fluted roll 30000 2 60000
2 VAT 15% 4500 2 9000
Total 69000

Delivery Terms and Conditions:

Place of Delivery : Aman Feed Mill, Ullapara, Sirajgong by Factory cost


Ref. Quality Certification : As per specifications stated in work order
Quality Certification by : Mr. Shamsuzzaman, Sr. Manager, Maintenance, AFL
Date of delivery : 2-weeks
Service warrenty : N/A
Payment mode : 100% payment along with work order

If the terms and conditions are accepted, your requested to start job. The price
will be deducted accordingly if the quality is not found as per stated specifications.

Thanking You

Managing Director
Aman Group
2 Ishakha Avenue
Sector 6, Uttara, Dhaka 1230
Tel: 8802-79110691-3
Fax: 8802-8920510