Contractor: Kevin Levene
Telephone: 1(876) 378-9660
Preliminaries
Description Amount
Setting up of building $35,000
Removal of rubbish and completion $30,000
Excavation and Earth work 160 ft * $600 $99,000
per ft
Casting foundation 165 ft * $400 per ft $66,000
Back fill with selected excavation material $30,000
around all foundation and column
Steel work @ $45,000 per tonne $45,000
total $305,000
1|Page
Block Work
Description Amount
Block work 2,500 block @ $8,000 per $200,000
100
Box and cast include lintel and beam
and columns
Column box and case 677ft * $450 $304,650
total $504,650
2|Page
Decking
Description Amount
Setting up of decking and board work $180,000
9sq @ $20,000 per sq
Steel work 1 tonne @$45,000 per tonne $45,000
Casting decking 81 sq yd @ $750 per sq $60,750
yd
Total $285,750
3|Page
Casting
Description Amount
Casting of floor 76 sq yd @ $750 per sq $57,000
yd
Flashing all wall and door edge $95,450
Rendering all wall and door and window $170,000
edge
total $322,450
4|Page
Electrical material
Quantity Materials Unit price Price total
10 flush plug and cover
10 handy box
12 octagon box
14 receptacles
16 way breaker pan
12 switches
6 wall case
7 single switch plate
2 double switch plate
2 triple switch plate
1 60 double amp breaker
4 15 amp breaker
3 20 amp single pole breaker
1 30 amp breaker
1 G-O-5 breaker
3 3 ¾ pot head
1 metre box
6 10 mm male cupling
50 20 mm cupling
30 20 male cupling
5|Page
6 10 mm cupling
4 30 Amp Strip connector bars
4 Bundle of 20 mm pipes
6 Roll of 2.5 wires
5 Roll of 1.5 wires
160 ft 10 mm red
80 ft 10 mm black
15 32mm electrical pipe
8 32 electrical bend
15 32 mm cupling
- Total
6|Page
Foundation material estimate
Amount material Unit price Total price
1 Tonne steel $91,500.00
½ Tonne 3/8 steel $540.00 $48,600.00
50 LBs Binding wire $90.00 $4,500.00
150 bags Cement $940.00 $141,000.00
1 load Sand $66,500.00
1 load Gravel $38,000.00
- Total - $390,100.00
Block work estimate
2000 Block $90.00 $180,000.00
50 bags Cement $940.00 $47,000.00
2 box 2 in cc concrete nails $147.00 $14,700.00
- Total - $241,700
7|Page
Decking
1 load Sand $66,500.00
1 load Gravel $38,000.00
20 2*4*14 treated lumber $1000.00 $20,000.00
30 1*3*14 Rough pitch pine $451.25 $13,537.00
30 5/8 ply $2,700 $81,000.00
100 Cement $940.00 $94,000.00
100 LB 2 ½ inch Head nail $97.09 $9,709.00
10 LB 3 inch Head Nail $94.74 $947.40
6 LB 4 inch Head Nail $98.18 $589.08
- Total - $324,282.48
8|Page
Flashing, rendering and floor estimate
Amount Material Unit Price Price
4 yd Rendering sand
40 bags Cement
9|Page
Item Description Qty Unit Rate Amount
Engineering Service
Electrical installation
All electrical work should include all
necessary chasing of walls, installation
of conduits, wiring oxogonal boxes,
junction boxes, p.v.c wire connectors
and make good all work disturbed and
done by an approved electrician
allow a ps of $240,000.00 to be used to
A complete all necessary electrical works Sum $ 240,000.00
including wiring switches, light outlets,
plugs outlets
allow provision of Government
B electrical inspection certificate fees
plumbing installation
provide the following to complete
plumbing installation and accessories
complete with American standard band
all a ps of $ 55,000.00 to be used to
A complete all necessary plumbing work Sum $55,000.00
Drainage
Manhole
Man hole 900mm × 900mm × 900mm
A deep complete with 150 mm thick
block, steel bars render and metal cover 2 No $28,000.00 $56,000.00
Trapped gully Basin
B Trapped gully basin 350mm × 350mm ×
400mm deep complete with 150mm
thick block, steel bars render and metal 2 no $12,500.00 $$25,000
cover
Septic tank
C $100,000.00
To supply and construct septic tank and
reed bed
Total