Session 2A Jonker
Session 2A Jonker
ANCOLD Guidelines
Marius Jonker and Dr Radin Espandar
GHD Pty Ltd
This paper provides a summary of the current state of practice for arch dam design criteria that have been
adopted by some international dam organizations, and where relevant, compares that with the criteria
provided in the updated ANCOLD Guidelines on Design Criteria for Concrete Gravity Dams, with the view
to provide a basis for consistent and unified design criteria for arch dams in Australia.
The paper draws on the authors’ experience with arch dams, including recent experience with a number of
arch dam safety reviews in Australia, their past experience with arch dams over 200 m height, as well as
their involvement with the development of the mentioned updated ANCOLD Guidelines.
Since the last arch dam was constructed in Australia, a number of international publications have been
released on arch dam design practices, providing general information and guidance for the design of new
dams and evaluation of the safety and structural integrity of existing arch dams. This paper compares these
publications and proposes criteria that are aligned with the ANCOLD gravity dam guidelines.
Keywords: Arch dams; Design Criteria
Lake Lanier 1925 USA 19 m 1926 One of the abutments (cyclopean masonry) washed out as a result of the
failure of soft rock in the abutment. The remainder of the dam was
unharmed
Vaughn Creek 1926 USA 19 m 1926 The dam failed during first filling as a result of seepage and poor materials
in the dam.
Alla Sella Zerbino Unknown Italy 12 m 1935 The dam failed as a result of overtopping and sliding on its foundation.
Le Gage 1955 France 46 m 1955 The dam developed extensive cracking on both faces after first filling,
which worsened for the next 6 years. After the failure of Malpasset Dam,
Le Gage Dam was abandon and a new thicker arch dam was constructed
upstream.
Malpasset 1954 France 66 m 1959 The dam failed due to movement of the left abutment, thought to be due to
sliding on a rock wedge formed by intersection of a fault with gneissic
foliation in the rock.
Idbar 1959 Yugoslavia 38 m 1960 The dam failed during first filling as a result of piping and erosion of the
foundation.
Vajont 1959 Italy 276 m 1963 A huge landslide-generated wave overtopped the dam wall by an estimated
100 m. The dam suffered little damage, but the reservoir was a total loss.
Arequipa Unknown Peru Unknown 1965 The dam body failed as a result of fractures caused by a vibrating penstock
which passed through the dam.
Matilija 1949 USA 50 m 1965 The dam was judged to be unsafe as a result of deterioration of the
concrete due to expansive aggregate and poor foundation conditions. The
dam was decommissioned.
Zeuzier 1957 Switzerland 156 m 1978 The dam began to deflect upstream due to riverward movement of the left
abutment.
Koelnbrein 1979 Austria 200 m 1981 Cracks and substantial leakage appeared in the lowest foundation gallery
when the reservoir was 80% full two years after first filling. Full uplift
pressure was observed over the entire base in the central portion of the
dam. Major repair was undertaken between 1989 and 1994.
Meihua (Plum) 1981 China 22 m 1981 The experimental dam failed shortly after filling as a result of structural
failure due to excessive uplift movement along a peripheral joint. Evidence
was observed of sliding both in the arch and downstream direction. The
scheme was abandoned after failure.
Leguaseca 1958 Spain 20 m 1987 The dam body failed structurally, apparently due to deterioration due to
both aging and the effects of freezing and thawing.
El Fraile Unknown Peru 61 m Unknown The dam experienced a major slide on one of the abutments during filling.
The dam did not collapse. A concrete thrust block abutment was
constructed and the dam was saved.
Tolla 1960 France 90 m Unknown The dam experienced severe cracking and was buttressed in response.
Cracking may have been the result of large temperature stresses.
Note 1: Data obtained from FERC (1999) & ICOLD (2001)
Note 1
Table 2 Incident and failures of arch dams during strong motion shaking
An arch dam may potentially fail as a result of: are cases of damage that did not result in dam failure.
• structural failure within the dam body due to Four cases involving dam body failure resulted from poor
overstressing of the concrete, or during earthquake construction materials or concrete material deterioration.
events due to excessive contraction joint opening Charlwood and Solymay (1995) reported 32 cases of
combined with cantilever tensile cracking, alkali aggregate reaction (AAR) in concrete arch dams.
• sliding along the dam-foundation interface, or Most of these dams were constructed prior to or while the
• movement of the abutment rock wedges formed by understanding of the AAR processes were still emerging.
rock discontinuities. A large number of arch dams subjected to AAR have
continued to function adequately, but in some cases
The above conditions could be the result of static loading
strengthening measures were required (Stewart Mountain,
during normal and flood conditions, and additional
Churchill and Gmued Dams), or partial replacement
dynamic loading during earthquake events.
(Matilija Dam), or complete replacement (Drum Afterbay
It is evident from Table 1 that concrete arch dams that Dam).
have performed well under normal operating conditions
As shown in Table 2 there are no known arch dam
will likely continue to do so unless something changes.
failures as a result of earthquake shaking. There is thus no
No arch dams are known to have failed statically within
direct empirical evidence to indicate how an arch dam
the dam body after five years of successful operation
would structurally fail under this type of loading. Payne
having reached its normal operating reservoir level,
(2002) conducted shaking table model studies to gain
although four incidents are shown where severe cracking
some insight as to how an arch dam might fail under
required remedial works.
earthquake shaking. In these tests:
Changes could result from plugging of drains leading to • failure initiated by horizontal (cantilever) cracking
an increase in foundation uplift pressures, possible across the lower central portion of the dam,
gradual creep that reduces the shear strength on potential • followed by diagonal cracking parallel to the
sliding surfaces, or degradation of the concrete from abutments,
alkali-aggregate reaction, freeze-thaw deterioration, or
• then cracking propagated through the model forming
sulphate attack.
isolated blocks within the dam, and
Under earthquake loading concrete arch dams will • eventually, the isolated blocks rotated and swung
respond according to the level and frequency of the downstream releasing the reservoir.
shaking, and the reservoir level at the time of shaking.
Unlike gravity dams, the most critical case for earthquake Vertical contraction joints possess very little or no tensile
loading of an arch dam might not be the reservoir full resistance and might repeatedly open and close during
scenario. A more severe overstress condition could result intense earthquake shaking. As postulated by Ghanaat
with the reservoir empty or partially filled. (2004), the contraction joint opening releases tensile arch
stresses but increases tensile cantilever stresses. The
Structural failure within the dam body increased cantilever stresses may exceed tensile strength
As shown in Table 1, there are no cases of failure within of the concrete or lift joints, causing horizontal cracks.
the arch dam bodies due to load overstressing, but there The resulting partially-free blocks bounded by the opened
contraction joints and cracked lift joints may become foundation. Sliding in the foundation typically occurs
unstable and cause failure of the dam (see Figure 1). along a single failure plane (plane sliding) or along the
line of intersection of two of these planes (wedge sliding).
To be kinematically capable of failure, the direction of
sliding surfaces must intersect or "daylight" a free surface
downstream from the dam. While it might be capable of
bridging a small unstable foundation block at the bottom,
large, unstable wedges of rock in the abutments could
endanger the safety of the arch dam.
For thin arch dams, sufficient movement may be
generated in the foundation during the shaking to cause
rupture of the dam body. Even if movement initiates but
does not cause dam failure, water forces acting on the
block planes may still increase as a result of the
movement. Stability analyses simulating post-earthquake
conditions are thus required to assess the likelihood of
post-earthquake instability.
Overtopping failure
Figure 1 Rotation of blocks caused by cracking and
opening of contraction joints (Ghanaat, 2004)
During large floods the arch wall could be subject to
overtopping and erosion of the abutments. Table 1
Dam-foundation interface failure includes one such case where overtopping erosion at the
contact zone resulted in sliding failure.
The dam-foundation interface includes the concrete-rock
contact, the concrete immediately above up to about the Although no arch dams are known to have failed statically
first lift joint, and the foundation rock typically 1 to 2 m due to overstressing within the dam body, a possibly more
immediately below the contact. serious condition occurs when there is an abutment
foundation block upon which the dam rests, that could
There are three types of potential sliding instability cases erode due to overtopping flows, or become unstable under
at the dam-foundation interface, i.e. sliding along the increased loading due to the flood conditions.
contact between the dam concrete and foundation rock,
within the concrete along lift joints, and along planes The loss of part of the abutment and foundation near or at
immediately below the contact. the toe of the arch wall could enable plane or wedge
sliding by exposing (daylighting) sliding planes, by
Sliding instability for the first two cases are less likely removing passive resisting rock, or by changing the
because of the wedging produced by arch action and deformations of the dam and redistribution of stress state
embedment of the structure into the rock. However, arch at the region and applying more forces to the wedge.
dams with relatively flat abutment slopes, or arch dams
with abutment thrust blocks supported by rock It is important to perform abutment stability analyses
foundations with inadequate shear strength, could be under flood loading considering the increase in dam thrust
susceptible to sliding along the foundation contact or on the foundation blocks and the increased hydrostatic
along planes immediately below the contact, in either or forces on the block bounding planes.
both the arch and downstream directions. Existing design references
Severe earthquake shaking could break the bond between A number of internationally recognised design guidelines
the dam and foundation, or cause movement along planes and manuals applicable to arch dams have been published
below the contact, especially if the foundation was not since 1953, as listed below. This list is not exhaustive and
excavated to radial lines and the excavation surfaces dip several other guidelines and manuals could be applied to
downstream on sections cut radial to the dam axis. arch dams, e.g. regarding site investigations, spillways,
Resulting sliding and rotation at the base could lead to outlet works and dam safety management practices.
loss of arch action and subsequently to instability.
United States Bureau of Reclamation
Foundation failure • Guide for Preliminary Design of Arch Dams (1977)
Actual arch dam failures have resulted from foundation • Design of Arch Dams (1977)
deficiencies, which included sliding of large blocks • Design Criteria for Concrete Arch and Gravity Dams
bounded by geologic discontinuities within the foundation (1977)
and abutments, or along planes of weakness (three failure
• Guidelines on Foundation and Geotechnical Studies
cases and three incidents shown in Table 1).
for Existing Concrete Dams (1999)
Although no arch dam foundations are known to have • State-of-Practice for the Nonlinear Analysis of
failed because of earthquake shaking, they have not been Concrete Dams at the Bureau of Reclamation (2006)
subjected to unprecedented seismic design loads.
United States Army Corps of Engineers
The most critical mode of foundation instability involves
• Arch Dam Design, EM 1110-2-2201 (1994)
sliding on discontinuities (joints, faults, shears, bedding
planes, foliation, clay seams, shale beds etc.) within the
• Response Spectra and Seismic Analysis for Concrete distributions in concrete dams and foundations, to
Hydraulic Structures, EM 1110-2-6050 (1999) establish ranges of shear and tensile strengths and
• Time-History Dynamic Analysis of Concrete cohesion values typical of concrete (parent concrete,
Hydraulic Structures, EM 1110-2-6051 (2003) bonded and unbonded joints), and concrete to rock
• Stability Analysis of Concrete Structures, interfaces (EPRI, 1992). In the absence of site specific
EM 1110-2-2000, (2005) testing, this document provides valuable information.
• Earthquake Design and Evaluation of Concrete The determination of the condition of the lift joints and
Hydraulic Structures, EM 1110-2-6053 (2007) the overall strength of the dam based on limited available
testing remains a challenge for dam engineers. Over the
Reclamation and USACE have also prepared the last 50 years Reclamation has performed strength and
following joint publication: frictional tests on numerous concrete dams of different
• Best Practices in Dam and Levee Safety Risk ages, with construction dates ranging from 1905 to 1993.
Assessment, Chapter 21 – Risk Analysis for Concrete Dolen (2011) processed the data of these tests and
Arch Dams, (2010) reported on the strength and frictional properties of parent
United States Federal Energy Regulation concrete and lift joints, grouping the results by dam ages.
Commission In the absence of site specific information this data
provides valuable information to understanding the joint
• Engineering Guidelines for the Evaluation of
strength in relation to construction practices over the
Hydropower Projects, Chapter 11 – Arch Dams (1999)
years.
ANCOLD Dolen presented ratios of bonded to unbonded lift joints
ANCOLD has no publications specifically for arch dams; for dams of different ages. A practical approach to
however ANCOLD (1998) contains guidance related to account for the portion of lift joints that are not bonded in
earthquake design of arch dams, while ANCOLD (2013) the global lift strength properties, as proposed by Dolen,
contains information that could be applied to materials consists of reducing the average test values based on the
and load conditions for concrete dams in general. estimated fraction of bonded lift joints.
The remainder of this paper draws to a large extent on the
Loads
information provided in the above references.
General
Material parameters
Reclamation, USACE, FERC and ANCOLD all have the
Reclamation, USACE, FERC and ANCOLD all have same design loads and generally the same definitions,
similar approaches in defining material properties and although some of the references define the load types in
they often refer to the same past studies and reports for more detail.
typical values.
Arch dams are designed for the same loads as gravity
The material parameters for both the dam wall and dams with the exception of the temperature load which
foundations are project and site specific. Due to limited has a significant influence in arch dam design.
space this paper cannot discuss this topic in sufficient
detail and the reader is therefore referred to the extensive The loads for which arch dams must be designed can be
coverage of this topic in the design references listed in the categorized as static or dynamic loads. Static loads are
previous section. However, it is emphasised that a sustained loads that do not change, or change very slowly
thorough knowledge must first be gained on a dam's compared to the natural periods of vibration of the
original design and its performance history and records, to structure, e.g. dead load, hydraulic load, loading from silt
provide a basis for evaluation and any further studies and and backfill materials, dynamic forces from flowing water
investigations that might be required. changing direction, uplift, forces from ice expansion or
impact, and stresses caused by temperature changes.
The dam and foundation material parameters should be
determined on the basis of field and laboratory Dynamic loads are transitory in nature and typically
investigations. In assigning strength and stiffness seconds in duration, e.g. earthquake-induced forces, blast-
parameters for the foundations, it is essential to firstly induced forces, fluttering nappe forces, or forces caused
derive a proper geological model for the foundations. This by the impact of ice, debris, or boats. Because of the
should be undertaken by a geologist with assistance where speed at which they act, the inertial and damping
appropriate, by a rock mechanics expert. In most cases, characteristics of the dam as well as its stiffness affect the
the required parameters will be determined by rock dam's behaviour.
defects rather than by the rock mass. Dead load
Where the field or laboratory determination of certain Dead load includes the weight of both the concrete and
material parameters is neither cost effective nor appurtenant structures (gates, bridges, and outlet works).
conclusive, the parameters can be estimated by existing The dead load is normally imposed on cantilever
correlation relations or using the same parameters in monoliths prior to the grouting of the contraction joints
similar projects. In these cases, their effects on the dam (no arch action) and should be taken into account when
response should be evaluated by parameter sensitivity analysing an arch dam, which is different to applying the
analyses. The USA Electric Power Research Institute self weight of a gravity dam. The weight of appurtenances
investigated the factors that influence uplift pressure is typically negligible compared to the dam itself;
however, massive outlet works and overflow ogee weir analysis for simplicity (FERC, 1999). However, if
spillways may have noticeable effects on the static and tailwater affects uplift pressure on a failure plane on
dynamic stresses. which sliding stability is being analysed, tailwater uplift
should still be considered.
Temperature load
Temperature loading is the most important difference Uplift and pore water pressures
between gravity and arch dams analysis. The temperature Uplift or pore water pressures develop when water enters
load in arch dams results from the differences between the the spaces and cracks within the body of an arch dam, as
closure temperature and concrete temperatures in the dam well as in the foundation joints, cracks, and seams.
during its operation.
During static loading conditions the effect of pore water
The closure temperature is the concrete temperature at the pressure is to reduce normal compressive stresses within
time of grouting of the contraction joints. It can also be the concrete and to increase the corresponding normal
considered as the stress-free temperature, i.e. there will tensile stresses should they exist. Considering the
not be any thermal stresses in the dam as long as the cumbersome process to include pore pressures in finite
temperature of the dam remains at the closure element models, combined with the relatively minor
temperature. However, once the average concrete change in stress, pore pressures and their effects within
temperature through the thickness exceeds the closure arch dams have often been ignored in the absence of any
temperature, the resulting positive temperature loading cracks. McKay & Lopez (2013) proposed a practical
will cause compressive stresses in the arches, which in methodology for including uplift and pore pressures.
turn will result in deflection into the reservoir. The
According to FERC (1999) uplift does not need to be
opposite happens when in the winter the concrete
considered in the stress analysis for thin arch dams. Uplift
temperature drops below the closure temperature and the
should always be considered in the sliding stability
arches experience tension which causes downstream analysis and be applied as external loads on both faces of
deflection. tensile cracks at the dam-foundation interface. In the
There are two ways which are generally adopted for absence of field data and seepage analysis, uplift can be
defining the internal concrete temperature causing loading represented as described in ANCOLD (2013).
and thermal stress: conduct steady state temperature
Silt load
calculations based upon water and air face temperatures
(such as USACE (1994) or Stucky and Derron (1957) for The need to apply silt pressure in arch dam analysis
nonlinear distribution of temperature through the dam depends on the sediment depth. According to FERC
thickness), or assume a cyclic variation of ambient (1999) for U-shaped and broad base arch dams, sediment
temperature with respect to time (seasonal variations) and depth of less than 0.25 of the dam height produces
conduct a harmonic temperature analysis, with due regard negligible deformations and stresses, and thus their effects
being given to the time dependant temperature condition may be ignored. For V-shaped dams the effects of silt
of the reservoir water. pressure may be ignored if the depth of sediment is less
than 0.33 of the dam height.
In the case of old arch dams where construction
methodology, vertical joint treatment and construction Ice load
timing are unknown, a practical approach is to adopt the Although uncommon in Australia, ice can produce
average ambient temperature as the closure temperature. significant loads against the face of an arch dam and must
However, it would be advisable to undertake a sensitivity be considered where reservoir freezing can be expected.
analysis using the average summer and average winter Static ice loads is produced by the ice in contact with the
temperatures as the closure temperature. dam when the reservoir is completely frozen, and
Further details about temperature loading are contained in dynamic ice loads by sheets of ice colliding with the dam.
USACE (1994) and Stucky and Derron (1957). Hydraulic loading of spillways
Hydrostatic hydraulic loads Forces produced by discharge through a spillway located
Reservoir and tailwater loads on an arch wall are usually insignificant and typically
ignored. USACE (1992) provides methods for
Water loads include hydrostatic pressures on the dam determining spillway pressures if hydrodynamic forces
faces resulting from the reservoir and tailwater during the
could affect the dam.
normal and flood conditions. Unlike a gravity dam for
which higher reservoir levels would result in more critical Arch dams with overflow spillways can also be subject to
cases, an arch dam may experience higher tensile stresses forces produced by a fluttering nappe, which is caused by
on the downstream face under low reservoir levels. resonance between air trapped in the cavity between the
nappe and the downstream face of the dam, as well as by
As tailwater acts in the opposite direction than the
spillway gates that transfer dynamic loading to the top of
headwater, it reduces the deformations caused by the
the dam. Such vibrations could be of importance to the
headwater and thus reduces both tensile and compressive
safety of tall and thin arch dams. The phenomenon, and
stresses below the tailwater levels. This effect is methods to prevent such vibrations, is thoroughly
negligible when the tailwater depth is less than 20% of the described in ICOLD (1996).
dam height. Below this level it is generally considered
conservative to then ignore tailwater loads in the stress
Hydrodynamic hydraulic loads ANCOLD (1998) guidelines) is the highest adopted
magnitude the dam is required to withstand. The dam is
As the dynamic interaction that occurs between the
allowed to respond nonlinearly and suffer significant
reservoir and the dam during an earthquake can have a
damage, but without a catastrophic failure. The SEE to be
significant effect on the earthquake response of the dam,
it must be considered in the dynamic analysis. Because used in the analysis of arch dams is defined in ANCOLD
the inertia force of a structure is a function of acceleration (1998), which is currently under review.
and mass, hydrodynamic interaction has a larger influence For preliminary linear response spectra analysis, site-
on thinner, less massive dams. There are three specific response spectra of earthquake ground motions
formulations for modelling hydrodynamic interaction: should be developed by experienced seismologists. The
• use of lumped mass (e.g. determined using the spectra should be developed for 5% damping, and
relationships or factors provided to obtain response
Generalised Westergaard theory of added mass to
spectra for higher damping ratios (as high as 10%) if
model incompressible fluid);
required for the analysis. These relationships or factors
• incompressible fluid finite element equivalent added may be based on a documented site-specific study;
mass; and alternatively, the relationships presented by Newmark and
• compressible fluid added mass, added damping and Hall (1982) may be used.
added forces with and without reservoir absorption.
For more detailed linear and non-linear time-history
Westergaard’s theory of added mass, as developed in
analysis, acceleration time histories of ground motions
1931, is reasonably appropriate only when assuming
should be developed consistent with the latest guidelines
incompressible reservoir acting on a rigid straight gravity
as for example contained in FERC (1999) and USACE
dam perpendicular to a wide valley, and with a vertical
(2003). Acceleration time histories should be developed
upstream face. For curved surfaces like arch dams, a
for three components of motion (two horizontal and one
Generalized Westergaard Method accounts for dam
vertical). Time histories may be either (a) recorded or
curvature and dam flexibility (Kuo, 1982). This method
simulated-recorded time histories or (b) response
assumes that the hydrodynamic pressure at any point on
spectrum matched time histories. For recorded or
the upstream face is proportional to the total acceleration
simulated-recorded time histories, a minimum of three
acting normal to the dam at that point. The application of
sets of recordings should be used.
the Generalised Westergaard method is described in more
detail in FERC (1999) and Reclamation (2006). Recorded earthquake ground motions at Pacoima Dam
during the 1994 Northridge earthquake indicated that the
Incompressible fluid formulations ignore the
seismic input for arch dams might vary along the dam
compressibility of water and assume the reservoir floor
foundation interface. At present time scarcity of data
and the upstream extent of the reservoir are rigid and
prevents a realistic definition of such non-uniform free-
ignore accelerations at these locations. Thus, the pressures
field motions for arch dams, even though procedures for
induced on the dam from accelerations applied to the
handling non-uniform input have been developed. In view
reservoir bottom are ignored.
of these difficulties, the use of standard uniform seismic
Modern finite element analysis (FEA) software input is currently still acceptable.
incorporates compressible water effects, which model the
interaction between dam and reservoir and the proper Loading Combinations
transmission of pressure waves in the upstream- Arch dams are designed for two groups of loading
downstream direction. The use of compressible water combinations. The first group combines all the static
effects is described in USACE (1999 & 2003) and loads and the second group takes into account the effects
Reclamation (2006). of earthquake. In addition, depending on the probability
Fluid elements are used to model the reservoir-dam and of occurrence of the cases in each group, they are
reservoir-foundation interaction more accurately. A three- categorised as Usual, Unusual, and Extreme loading
dimensional mesh of fluid elements is developed to combinations.
represent the reservoir. The use of fluid elements is Table 3 on the next two pages presents a summary of the
described in Reclamation (2006). static and dynamic loading combinations used by
Earthquake load Reclamation, USACE, FERC and ANCOLD, including
the loading combination categories. Although having a
Arch dams are expected to respond linearly under the similar approach, they differ with regard to categorising
Operational Basis Earthquake (OBE), assuming certain loading combinations. The designer should
continuous monolithic action along the entire length of however assess each load case to ensure that it is
the dam. If damage did occur, it should be possible to applicable to the project and that it is properly classified
repair it while the dam remains operational. under one of the three categories.
The SEE (Safety Evaluation Earthquake, to replace
Maximum Design Earthquake in the update of the
Note 1
Table 3 Summary of loading combinations
USACE (1994) Reclamation (1977 & 2006) FERC (1999) ANCOLD (1998) Note 2 ANCOLD (2013) Note 2 Proposed for arch dams
Static Usual
D + Tw + Hx + U Reclamation (2006): D + Tw + Hx + S + I + U D + Tw + Hn+ S/B + I + U D + Hn+ S/B + U + I D + Tw + Hx + S/B + U + I
D + Ts + Hx + U D + Hn+ Tw + U D + Ts + Hx + S + U D + Ts + Hn+ S/B + U D + H50 + S/B + U D + Ts + Hx + S/B + U
D + Hn+ Tx + U D + Hn+ Ts + U PQ: D + Hn+ S/B + U + I (If Hx is uncertain, check for Hl and Hf.)
Reclamation (1977): D + H50 + Tx + S/B + U
D + Tw + Hx + S + I + U D + Hn+ Tx + S/B + U + I
D + Ts + Hx + S + U
D + Hn+ Tx + S + I + U
D + Hl + Tx + S + I + U
Static Unusual
Note 3 Note 4
D + Hs + Tx + U Reclamation (2006): D + Hl + Tx + S + U D + Tw + Hf + S/ B + U D + H500-H2000 + S/B + U D + H500-H2000 + Tx + S/B + U
D + Hl + Tx + U Note 4 D + Hl + Ts + U Note 4 D + He + Tx + S + U Note 4 D + Ts + Hf + S/B + U PQ: D + H50 + S/B + U PQ: D + H50 + Tx + S/B + U
D + He + Tx + U Note 4 D + Hf + Tw + U D + Ts + Hf + S + U D + H100 + S/B + Ubd D + H100 + Tx + S/B + Ubd
Reclamation (1977): D + Tw + Hf + S + I + U D + H100 (1 gate closed) + S/B + U D + H100 (1 gate closed) + Tx + S/B + U
D + Hf + Tx + U D + Tx + Hf + S + I + U D + H100 + S/B + U + Wind seiche D + H100 + Tx + S/B + U + Wind seiche
and wave action and wave action
D + Hl / He + Tx + S/B + U Note 4
Static Extreme
D + Hf + Tx + U D + Hf + S/B + U + I D + Hf + Tx + S/B + U + I
D + H100(>1 gate closed) + S/B + U D + Hf + Tw + S/B + U + I
D + Hlw + S/B + U D + Hf + Ts + S/B + U + I
D + H100(>1 gate closed) + Tx + S/B + U
D + Hlw + Tw + S/B + U
Dynamic Unusual
OBE + D + Hn+ Tx + U OBE + D + Tw + Hn+ S/B + I + U OBE + D + Hc + S/B + U OBE + D + Hn+ Tw + S/B + U
OBE + D + He + Tx + U OBE + D + Ts + Hn+ S/B + U OBE + D + Hn+ Ts + S/B + U
OBE + D + Tw + He+ S/B + I + U OBE + D + He / Hl + Tw + S/B + U
OBE + D + Ts + He+ S/B + U OBE + D + He / Hl + Ts + S/B + U
Table 3 continued
USACE (1994) Reclamation (1977 & 2006) FERC (1999) ANCOLD (1998) Note 2 ANCOLD (2013) Note 2 Proposed for arch dams
Dynamic Extreme
SEE + D + Hn + Tx + U Reclamation (2006): SEE + D + Tw + Hx + S + I + U SEE + D + Hc + S/B + U SEE + D + Hn+ S/B + U SEE + D + Hn+ Tw + S/B + U
SEE + D + Hn + Tc + U SEE + D + Ts + Hx + S + U SEE + D + Hn+ Ts + S/B + U
SEE + D + Hn + Tw + U SEE + D + He / Hl + Tw + S/B + U
SEE + D + Hn + Ts + U SEE + D + He / Hl + Ts + S/B + U
Reclamation (1977):
SEE + D + Tw + Hx + S + I + U
SEE + D + Ts + Hx + S + U
SEE + D + Hn + Tx + S + I + U
SEE + D + Hl + Tx + S + I + U
Hn: Usual (normal) reservoir level with associated tailwater level H50: 1in 50 AEP reservoir level with associated tailwater level Tx: Temperature at the time D: Dead load including appurtenances
Hx: Reservoir level at the time with associated tailwater level H100: 1in 100 AEP reservoir level with associated tailwater level Ts: Summer temperature U: Uplift
Hl: Lowest operating reservoir level with associated tailwater level H500: 1in 500 AEP reservoir level with associated tailwater level Tw: Winter temperature Ubd: Uplift with blocked drains
He: Empty reservoir level with no tailwater level H2000: 1in 2000 AEP reservoir level with associated tailwater level S: Silt (if applicable)
Hc: Critical reservoir level with associated tailwater level B: Backfill against dam (if applicable)
Hf: Maximum flood reservoir level with associated tailwater level I: Ice (if applicable)
Hlw: Landslide generated wave reservoir level with normal tailwater level PQ: Post earthquake
Notes:
1. This table contains a collation of loading combinations proposed by the respective publications. Not all the cases would apply to a specific dam and the design should use judgement in selecting the
combinations and categorising them.
2. The combinations for ANCOLD (1998) and ANCOLD (2013) were developed for gravity dams and are included here with the view to achieve proposed combinations for arch dams that are reasonably
consistent with these ANCOLD guidelines.
3. This case applies only to dams that are normally at a low level or empty, such as flood retention dams.
4. For flood retention dams these cases should be considered under Usual Static.
5. Uplift should be determined by the reservoir level and tailwater level taking into account any foundation drains.
6. Silt, backfill against the dam and ice should be included only if applicable.
Table 4 Summary of factors of safety
USACE Reclamation ANCOLD ANCOLD Proposed for
Parameter FERC (1999) Range
(1994) (1977 & 2006) (1998) Note 1 (2013) Note 1 arch dams
Static Usual
3.0-not more
Compression 4.0 than 10.3 MPa 2.0 4.0 3.3 2.0-4.0 3.3
(4.0) Note 2
Not more than
Tension 1.0 1.0 1.0 1.0 1.0 1.0
1.03 MPa
Sliding 2.0 3.0 1.5 (2.0) Note 3 1.5 – 2.0 1.5 / 2.0 / 3.0 Note 4 1.3-3.0 1.5 / 2.0 / 3.0 Note 4
Static Unusual
2.0 not more
Compression 2.5 than 15.5 MPa 1.5 2.7 2.0 1.5-2.7 2.0
(2.7) Note 2
Not more than
Tension 1.0 1.0 1.0 1.0 1.0 1.0
1.55 MPa
Sliding 1.3 2.0 1.5 1.3 – 1.5 1.3 / 1.5 / 2.0 Note 4 1.3-2.0 1.3 / 1.5 / 2.0 Note 4
Static Extreme (maximum flood condition only)
Note 5 Note 5 Note 5
Compression 1.5 1.3 1.3-1.5 2.0
Note 5 Note 5 Note 5
Tension 1.0 1.0 1.0 1.0
Note 5 Note 5 Note 5
Sliding 1.1 1.1 / 1.3 / 1.5 Note 4 1.1-1.5 1.3 / 1.5 / 2.0 Note 4
Dynamic Unusual (cases including OBE)
2.0 not more
Compression 2.5 than 15.5 MPa - 2.7 2.0 2.0-2.7 2.0
(2.7) Note 2
Not more than
Tension 1.0 - 1.0 1.0 1.0 1.0
1.55 MPa
Sliding 1.3 2.0 - 1.3 – 1.5 1.3 / 1.5 / 2.0 Note 4 1.3-2.0 1.3 / 1.5 / 2.0 Note 4
Dynamic Extreme (cases including SEE)
Compression 1.5 1.0 (1.3) Note 2 1.1 1.3 1.3 1.1-3.0 1.3
Tension 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Sliding 1.1 1.0 1.1 1.2 – 1.4 1.1 / 1.3 / 1.5 Note 4 1.0-1.5 1.1 / 1.3 / 1.5 Note 4
Notes:
1. These guidelines were developed for gravity dams.
2. Values in brackets are for the foundations.
3. Value in brackets is for internal shear.
4. Factors are for “Residual strength c’ and ’ well-defined” / “Peak strength c’ and ’ well-defined” / “Peak strength c’ and ’ not well-defined”
(refer ANCOLD (2013) for further explanation of these conditions).
5. These references included maximum flood in the static unusual category.
6. The factor of safety for allowable tensile strength should be applied to the concrete under consideration, i.e. either the parent or lift joint strength.