LAHORE DEVELOPMENT AUTHORITY (LDA)                                                                                                                                                         LAHORE ORANGE LINE METRO TRAIN PROJECT                                                                                                                                                                                              Weekly Project Management Dashboard Report
PACKAGE-I (DERA GUJJRAN TO CHAUBURJI, 0+600 TO 14+200)
Reporting Date:              December 7, 2015
                                        Project and Contract Data                                                                                                                    Variation / Extension of Time Claims Status                                                                                                                             Payment Status                                                                                   Executive Summary
                                                                                                                                                                                                                                                                                                                                                                                                                                            1) The detailed Design of Bridge over railway was
 Project Name and ID                           :   LAHORE ORANGE LINE METRO TRAIN PROJECT                                          Contract Price                                                                              Approved Variations/IPCs                      Adjusted Contract Price
 Employer                                      :   PUNJAB TRANSPORT DEPARTMENT                                                                                      Total Amount of Submitted Variations                                                                                                       Total Certified              Total Paid                         Outstanding                              Remarks             done and submitted to Pakistan Railways for
                                                                                                                                        (A)                                                                                              (B)                                         (A+B)
 Project Management Firm                       :   PROJECT MANAGEMENT UNIT-LDA                                                                                                                                                                                                                                                                                                                                                              review and grant of NOC.
 Engineer                                      :   NESPAK, CEC (JV)                                                                                                                                                                                                                                                                                                                                                                         2) Design of bridge over ring road is being
 Contract Type                                 :   ITEM RATE
 Contract Duration                             :   310 DAYS                                                                                                                                                                                                                                                                                                                                                                                 changed from balanced cantilever to continuous
 Original Contract Value                       :   PKR 21,409,884,451                                                             PKR 21,409,884,451                                                              -                                                   -              21,409,884,451.00           1,369,124,437.00                             -                                            -                                box girder bridge
 Revised Contract Value                        :   NOT APPLICABLE
 Anticipated Contract Value                    :   NOT APPLICABLE
                                                                                                                                                                                                                                                                                                                                                                                                                                            3) Preparation of tender design for depot is in
 Commencement Date                             :   25-Oct-15                                                                                                                                                                                                                                                                                                                                                                                progress.
 Original Completion Date                      :   30-Aug-16                                                                                                                                                                                                                                                                                                                                                                                4) Confirmatory geotechnical investigations is
 Revised Completion Date                       :   NOT APPLICABLE
                                                                                                                                                                                                                                                                                                                                                                                                                                            completed.
                                                                              Project Time Status                                                                                                                                                                                               Cost Performance                                                                                                                            5) Coordination with WASA is being done for
                                                                                                                                                                                                                                                                                                                                                                                                                                            resolving drainage  issues at GPO and Lakshmi
                                                                                                                                                                                                                                                                                                                                                                                                                                                             21-Aug-16
                                                                                                                                                                                            Budgeted Total Cost
                                                                                                                                                                                                                      Planned Value Cost     Performed Value Cost         Commulative Planned       Commulative Performance
                                                                                                                                                                                                                                                                                                                                      Remaining Total Cost
                                                                                                                                                                                                                                                                                                                                                                    Cost Performance
                                                                                                                                                                                                                                                                                                                                                                                                                Remarks
                                                                                                                                                                                                                                                                                                                                                                                                                                            chowk.                  -9
              11.61%                                                                                  88.39%                                                                                                             (Dec, 15-W1)             (Dec, 15-W1)               Value Cost                      Cost                                                         Index
      0%               10%              20%               30%             40%                50%
                                                                                               `                60%               70%               80%             90%          100%
                                                                                                                                                                                                                                                                                                                                                                                            Cost Performance is in line with plan and is
                                                                                                                                                                                             21,409,884,451.00          459,467,382.00            293,918,321.00               1,292,977,088                1,943,243,139                  19,466,641,312                   1.00
                                                                 Time Elapsed = 37 Days           Remaining Duration = 274 Days                                                                                                                                                                                                                                                             satisfactory
                           Schedule Performance                                                                                                                                                                              Gross Works Done - Planned vs Actual                                                                                                                                                                                                  Key Risks
                                                                                                                                                                                                                                                                                                                                                                                                                                                                     External
                                                                                                                 3,500,000,000                                                                                                                                                                                                                                                                                           25,000,000,000     1) Procurement of Form Work for U-TUB
                                                                           100.00%                                                                                                                                                 Works Completion Analaysis                                                                                                                                                                               and Transoms.
                                                                                                                                                                                                                                                                                                                                                                                                                                            2) Site Safety which requires continuous
                                                                                                                 3,000,000,000
           5.59%                                                                                                                                                                                                                                                                                                                                                                                                                            Monitoring.
                                                                                                                                                                                                                                                                                                                                                                                                                         20,000,000,000
                                                                                                                                                                                                                                                                                                                                                                                                                                            3) Variations in quantum of works as per Site
             8.72%
                                                                                                                 2,500,000,000                                                                                                                                                                                                                                                                                                              Requirements.
                                                                                                                                                                                                                                                                                                                                                                                                                                            4) Frequent Changes/Modification keeping in
           Total Required %                                                                                                                                                                                                                                                                                                                                                                                              15,000,000,000     view Site Conditions.
           Planned to Date %                                                                                     2,000,000,000
                                                                                                                                                                                                                                                                                                                                                                                                                                            5) Environmental Risks require Continuous
           Actual to Date %
                                                                                                                                                                                                                                                                                                                                                                                                                                            sprinkling of water and other mitigation
       Planned %                                        5.59%                                                    1,500,000,000                                                                                                                                                                                                                                                                                                              measures.
                                                                                                                                                                                                                                                                                                                                                                                                                         10,000,000,000
                                                                                                                                                                                                                                                                                                                                                                                                                                            6) Weather Condition like Fog/Rain.
           Actual %                                     8.72%
      Ahead/Delay                                       3.13%                                                    1,000,000,000
      Delay in Days                                       0                                                                                                                                                                                                                                                                                                                                                              5,000,000,000
                             As Per the Construction Plan submitted by Habib                                        500,000,000
                             Construction Service, the Project progress is
                             ahead what was originally planned.
           Remarks
                                                                                                                             -                                                                                                                                                                                                                                                                                           -
                                                                                                                                         Sep, 15            Oct, 15          Nov, 15      Dec, 15 (W1)     Dec, 15 (W2)       Dec, 15 (W3)     Dec, 15 (W4)         Jan, 16            Feb, 16             March, 16         April, 16         May, 16           June, 16             July, 16        Aug, 16
                                                                                                        Planned Cost                         -              569,780        832,939,926     459,467,382     519,580,323        492,833,669      483,378,325       1,835,580,324      2,677,423,887        3,207,850,309    2,527,740,114     1,755,672,047     1,943,268,389        2,138,294,198   2,535,285,774
                                                                                                        Actual Cost                     97,552,253        508,567,718     1,043,204,847    293,918,321                                                                                                                                                                                                                                                         Critical Issues
                             Issued Documents                                                           Cummulative Plan Cost                -              569,780        833,509,706    1,292,977,088    1,812,557,411     2,305,391,080    2,788,769,405      4,624,349,729      7,301,773,616    10,509,623,925       13,037,364,039    14,793,036,086   16,736,304,475     18,874,598,673     21,409,884,447                           1) Land Acquisition
                                                                                                        Cummulative Actual Cost         97,552,253        606,119,971     1,649,324,818   1,943,243,139                                                                                                                                                                                                                                     2) Shifting of Utilities
SN           Description           Raised By        Issued To.             No.                                                                                                                                                                                                                                                                                                                                                              3) Court Cases regarding Land Acquisition.
 1                                PM NESPAK
                                                                                                                                                                    Summary of Main Construction Activities                                                                                                                               Visitor Report / Discussions / Meetings
      Construction Dwgs                               CE-LDA        SA-292/PK-1/037
 2    Construction Dwgs           PM NESPAK           CE-LDA        SA-292/PK-1/038                             Item Description                            Units         Executed                 Total              % Complete                              Remarks                           S No.                  Executive Name                         Discussions                                      Comments
 3    Construction Dwgs           PM NESPAK           CE-LDA        SA-292/PK-1/039       Piles (1200mm)                                  Viaduct           No                 1573                3579                   43.95%      Progress is ahead of Planned Work                              1      PD - LDA                             Site Visit w.r.t. Quality & Workmanship    Improve site safety
                                                                                          Piles (760, 1000, 1200 mm)                    Cut & Cover         No                   0                 3147                    0.00%                                                                     2      CM - NESPAK                          Site Visit w.r.t. Quality & Workmanship    Satisfactory, Improve safety conditions
                                                                                          Pile Cap                                                          No                  82                  448                   18.30%      Progress is ahead of Planned Work                              3      Representatives of M/S CEC           Site Visit w.r.t. Quality & Workmanship    Satisfactory with minor observations
                                                                                          Piers                                                             No                   2                  448                    0.45%      Progress is slightly behind the Plan
                                                                                          Transoms (Precast)                                                No
                                                                                          Transoms (Cast Insitu)                                            No
                                                                                          U-Girders (Precast)                                               No
                                                                                          U-Girders (Cast Insitu)                                           No
                                        HSE
                                                                                          Elevated Beams                                                    No
                                                                                          Columns (Stations)                                                No                                                                                                                                                                COST                                                                 TIME
SN.                    Incident                    Responsibility        Impact           Pedestrian Bridges                                                No
                                                                                          Station Roof Structure                                            No
      Transit mixer hit pedestrian who
                                                                                          Architectural Works                                               No                                                                                                                                                                                                                                                                                            Management Report Approval
 1    slipped due to slush. Time 2000hrs             M/s HCS        Casualty on spot      Drainage of Station                                               No                                                                                                                                                     RED                Legend:                                       RED                        Legend :
      Date 26/11/2015
                                                                                                                                                                                                                                                                                                                                      1. Colour the circle                                                     1) Colour the circle          Prepared By:     Designation   Checked By:    Designation
                                                                                          Granular Sub-Base                                                 CM                                                                                                                                                                        with RED if EAC is >
                                                                                                                                                                                                                                                                                                                                                                                                               with RED if delay
                                                                                                                                                                                                                                                                                                                                      2% than the
                                                                                          Asphaltic Base                                                    CM                                                                                                                                                                                                                                                 is > 30 days.               Asif Iqbal /        Progress                      Project
                                                                                                                                                                                                                                                                                                                                      approved Budget                                                                                                                       Saeed Akhtar
      An excavator hit a site worker. Time                                                Wearing Course                                                                                                                                                                                                                              2.Colour the circle                                                      2) Colour the circle        Ubaid Iqbal          Officer                    Coordinator
 2                                                   M/s HCS         Died in Hospital                                                                       CM                                                                                                                                                                                                                  AMBER
      0300hrs Date 02/12/2015                                                                                                                                                                                                                                                                                    AMBER
                                                                                                                                                                                                                                                                                                                                      with AMBER if EAC                                                        with AMBER if delay
                                                                                                                                                                                                                                                                                                                                      is ± 2% than the                                                         is between 15 to 30
                                                                                                                                                                                                                                                                                                                                      approved Budget                                                          days.
                                                                                                                                                                                                                                                                                                                                      3. Colour the circle                                                     3) Colour the circle
                                                                                                                                                                                                                                                                                                                                      with GREEN if EAC
                                                                                                                                                                                                                                                                                                                 GREEN                                                                                         with GREEN if delay
                                                                                                                                                                                                                                                                                                                                      is < 2% than the                          GREEN
                                                                                                                                                                                                                                                                                                                                      approved Budget                                                          is < 15 days.
                                                                                                                                                                                                                                                                                                                                                                                                                                                                LAHORE DEVELOPMENT AUTHORITY
                                                                                                                                                                                                                                                                                                                                                                                                                                                                      Ph no:+92 (042) 35401370