This document summarizes a project to lay a new 600mm diameter mild steel pipe across the 70m wide Simpang Kiri river in Batu Pahat, Johor, Malaysia to replace an existing damaged pipe. The project cost RM1.79 million and was completed in November 2004. A 50m long steel truss supported by spun piles was used to lay the new pipe across the river, providing the longest span steel truss in Johor state. Services provided for the project included feasibility studies, engineering design, tender documentation, and construction supervision.

Uploaded by

Ahmad Zubir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
120 views1 page

Man

This document summarizes a project to lay a new 600mm diameter mild steel pipe across the 70m wide Simpang Kiri river in Batu Pahat, Johor, Malaysia to replace an existing damaged pipe. The project cost RM1.79 million and was completed in November 2004. A 50m long steel truss supported by spun piles was used to lay the new pipe across the river, providing the longest span steel truss in Johor state. Services provided for the project included feasibility studies, engineering design, tender documentation, and construction supervision.

Uploaded by

Ahmad Zubir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

MS ISO 9001:2000 REG.NO.

AR 2636

PROJECT:-
PROPOSED NEW ‘S-BEND’ FOR 600MM DIAMETER MILD STEEL PIPE AT SG. SIMPANG
KIRI (FROM KG. PARIT ISMAIL TO KG. PARIT AWANG) IN BATU PAHAT, JOHOR

LOCATION :- OWNER :-
Sg. Simpang Kiri, Batu Pahat SAJ Holdings Sdn Bhd

PROJECT COST :- COMPLETION DATE:-


RM1.79 Million November 2004

DESCRIPTION :-
This project involved the laying of a new exposed 600mm dia. M.S. Pipe crossing a 70m wide Simpang Kiri
river, to replace an existing 525mm dia M.S. Pipe which was damaged due to the loss of a pipe support in the
river. A 50m span long steel truss supported by spun piles was used to lay the new pipe across the river.
This is the longest span steel truss ever in the state of Johor.

SERVICES PROVIDED :-
:
1. Feasibility study of pipe crossing methods.

2. Detailed engineering design and tender documents preparation.

3. Construction supervision of the entire project.

NEW 600MM DIA. MILD STEEL PIPE CROSSING SG. SIMPANG KIRI, BATU PAHAT, JOHOR

WISMA SSP, LEVEL 8-18, NO. 1 JALAN SR 8/3 SERDANG RAYA SEKSYEN 8 TEL NO.: 03-89433366(HL) FAX NO.: 03-89432691/2707
43300 SERI KEMBANGAN SELANGOR DARUL EHSAN MALAYSIA EMAIL : sspsb@sspsb.com.my WEB SITE : www.sspsb.com.my

You might also like