AN
OVERVIEW
OF
TANAHU HYDROPOWER PROJECT
Presented by:
Achyut Ghimire
TANAHU HYDROPOWER PROJECT
TRADE TOWER, THAPATHALI, KATHMANDU
Date: June 1, 2016
OUT LINE OF THE PRESENTATION
INTRODUCTION
OBJECTIVE OF PROJECT
LOCATION OF PROJECT
SALIENT FEATURES
FINANCIAL INDICATORS
PROJECT FINANCING
SOCIAL AND ENVIRONMENTAL ISSUES
INTRODUCTION
Pre-feasibility study was conducted by NEA in 2001.
Upgraded feasibility study carried out by JICA in a period
from February 2005 to June 2007.
Installed capacity of 122 MW was identified in pre-
feasibility study and optimized to 127 MW in upgraded
feasibility study.
Installed capacity of 140 MW (Maximum) established in
detail engineering study.
Tanahu Hydropower Limited (THL) was established in 2012
as a subsidiary company of Nepal Electricity Authority (NEA)
as special purpose vehicle (SPH) to execute Tanahu
Hydropower Project.
INTRODUCTION CONT…
Project site located 150 km west of Kathmandu on Seti
River near Damauli of Tanahu District. The project is seasonal
storage type capable of supplying peak power for minimum of
6 hours daily in dry season.
Power will be evacuated through 36 km long 220 kV D/C
transmission line to New Bharatpur sub-station.
Estimated Annual energy 585.7 GWh (Primary Energy:
266.2 GWh, Secondary Energy: 319.5 GWh) for first 10 year
and estimated that it will decreased by 16% after 10 years.
Will be equipped with sediment flushing system
Construction will be started in mid of 2017 and will be
completed in end of 2021.
OBJECTIVE OF PROJECT
Objective of Tanahu Hydropower Project are:
To construct hydropower plant having installed
capacity of 140 MW
To construct 220 kV Damauli Bharatpur
transmission line
Implementation of Rural Electrification in 17
VDC of Tanahu District.
Community development program in project area
Resettlement of project affected households
LOCATION MAP
PROJECT SITE IN GOOGLE MAP
LOCATION OF PROJECT
Located within:
Longitude: 84°17’30” to 84°04’00” E
Latitude: 28°00’00” to 27°55’15” N
Project site lies in middle reach of the Seti River.
Catchment area at the dam site is 1,502 sq.km.
Dam will be at1 km upstream of confluence of Seti &
Madi river
Powerhouse will be at 3 km downstream of confluence.
Gross storage capacity of reservoir = 295.1 million
cu.m.
The design discharge is 127.4 cu.m./sec
PROJECT FINANCING
The project is being funded as per below:
ADB :150 Million USD
JICA: 183 Million USD
EIB: 85 Million USD
GoN/NEA: 87 Million USD
ADB loan will be used for the head works, rural
electrification, transmission line, environment and social
safeguard program, Project Supervision Consultant.
JICA loan for water ways and power house including hydro-
mechanical and electromechanical equipments.
GON/NEA fund for pre-construction infrastructure like
access road, bridge, construction power, land acquisition etc.
UPDATED SALIENT FEATURES OF PROJECT
UPDATED SALIENT FEATURES OF PROJECT Cont…
FINANCIAL INDICATORS OF PROJECT
-Estimated Economic Internal Rates of Return
(EIRR) 12.3 % (EIRR> Opportunity cost of
Capital, i.e. 10%).
- Estimated Financial Internal Rates of Return
(FIRR) 10.3 % taking 8% interest rate for loan).
-Repayment period: 25 years after commissioning
Loan Life Coverage Ratio (LLCR)= 2.0 with
expected interest rate of 8% (i.e LLCR>1.0)
GENERAL LAYOUT OF THE PROJECT
CURRENT ACTIVITIES OF THE PROJECT
Contract agreement concluded with Project Supervision
Consultant (PSC) M/S Lahmeyer International in
association with Manitoba Hydro Int. for twelve years.
PSC Consultant responsible for design review, bid
processing, construction supervision and will assist in O/M
phase for five years after commissioning.
Project has entered in pre-qualification stage.
Recently obtained generation license from Department of
Electricity Development (DOED).
Applied for PPA with NEA.
Applied for transmission line construction license at
DOED.
CURRENT ACTIVITIES OF THE PROJECT
Construction of RCC bridge over Seti River completed.
Construction of access road from National highway to
nearby to Project site is ongoing.
Construction of camp facilities on going
Construction of construction power supply for Project
ongoing.
Detail survey of Damauli Bharatpur 220 kV
transmission line for power evacuation completed.
Demarcation survey for land acquisition of reservoir
area completed.
CONSTRUCTION OF PROJECT
Three major Packages for the Construction of the
Project
Package 1: Head Works
Package 2: Water ways, Power House and
related equipments (Hydromechanical and
Electromechanical)
Package 3: Transmission line and substation
Environmental and Social Management Unit (ESMU)
established to address the social and environmental
issues in relation to the project.
SOCIAL AND ENVIRONMENTAL ISSUES
EIA of Upper Seti Project conducted and approved in 2009.
IEE of Damauli Bharatpur 220 kV transmission line conducted
and approved in 2010.
Project affected households (HH): 758
Project affected private land: 112 Hectare (93 Hectare to be
permanently acquired, 19 to be leased).
7.5 Hectare acquired till date.
Project affected people: 4257
HH to be physically displaced: 86 , (25 HH displaced during
land acquisition of camp facilities and access road).
Physically displaced peoples: 538
Affected number of trees: 4776
Suspension bridges displacement: 7
HEAD WORKS AREA
COMPLETED RCC BRIDGE OVER SETI RIVER
UNDER CONSTRUCTION ACCESS ROAD TO SITE
ACCESS ROAD UNDER CONSTRUCTION
SUBSTATION FOR CONSTRUCTION POWER UNDER
CONSTRUCTION