Hvac Schedule Site P PDF

The document outlines a tentative schedule for HVAC works at Site P from May 2015 to January 2017. It includes 31 tasks related to the supply, installation, and testing of HVAC equipment over multiple areas at the site. Key milestones include the completion of equipment supply by February 2016 and full installation/testing by September 2016. The schedule assumes timely receipt of drawings, site clearances, and coordination between different contractors.

Uploaded by

Sureshbabu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
846 views3 pages

Hvac Schedule Site P PDF

The document outlines a tentative schedule for HVAC works at Site P from May 2015 to January 2017. It includes 31 tasks related to the supply, installation, and testing of HVAC equipment over multiple areas at the site. Key milestones include the completion of equipment supply by February 2016 and full installation/testing by September 2016. The schedule assumes timely receipt of drawings, site clearances, and coordination between different contractors.

Uploaded by

Sureshbabu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Tentative Schedule for HVAC Works @ Site 'P'

ID Task Name Duration Start Finish 2016 2017


May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 Receipt of order 1 day Sat 30/5/15 Sat 30/5/15
2 Mobilization 60 days Mon 1/6/15 Sat 8/8/15
3 Receipt of GFC 25 days Mon 31/8/15 Mon 28/9/15 CLIENT
4 Submission of shop Drawing 21 days Tue 29/9/15 Thu 22/10/15
5 Approval of Drawings 10 days Fri 23/10/15 Tue 3/11/15
6 Supply 111 days Tue 29/9/15 Thu 4/2/16
7 Chiller 60 days Tue 29/9/15 Mon 7/12/15
8 Hot water generator 60 days Tue 29/9/15 Mon 7/12/15
9 Pumps(chilled,hot water) 60 days Tue 29/9/15 Mon 7/12/15
10 Air seperator 60 days Tue 29/9/15 Mon 7/12/15
11 Expansion Tank 60 days Tue 29/9/15 Mon 7/12/15
12 Pipes(chilled,hot water) 7 days Thu 29/10/15 Thu 5/11/15
13 Insulation(chilled,hot water) 30 days Thu 29/10/15 Wed 2/12/15
14 AHUs 67 days Fri 23/10/15 Fri 8/1/16
15 Ventilation Fans 67 days Fri 23/10/15 Fri 8/1/16
16 Fcu 30 days Fri 23/10/15 Thu 26/11/15
17 Dx Split Units 30 days Fri 23/10/15 Thu 26/11/15
18 Motorised Dampers 45 days Fri 23/10/15 Mon 14/12/15
19 Volume control dampers 45 days Fri 23/10/15 Mon 14/12/15
20 Guages 15 days Fri 23/10/15 Mon 9/11/15
21 Valve Package 60 days Fri 23/10/15 Thu 31/12/15
22 Ducting(GI) 75 days Wed 4/11/15 Fri 29/1/16
23 Ducting(ss) 75 days Wed 4/11/15 Fri 29/1/16
24 Ducting(Alu) 75 days Wed 4/11/15 Fri 29/1/16
25 Duct Insulation 60 days Wed 4/11/15 Tue 12/1/16
26 Duct Aquostic 60 days Wed 4/11/15 Tue 12/1/16
27 Grills and diffusers 60 days Wed 4/11/15 Tue 12/1/16
28 Electrical Panels 90 days Fri 23/10/15 Thu 4/2/16
29 Cable Tray and Cables 30 days Fri 23/10/15 Thu 26/11/15
30
31 Installation 258 days Fri 6/11/15 Thu 1/9/16
32 Chiller 20 days Tue 8/12/15 Wed 30/12/15
33 Hot water generator 10 days Tue 8/12/15 Fri 18/12/15
34 Pumps(chilled,hot water) 20 days Tue 8/12/15 Wed 30/12/15
35 Air seperator 10 days Tue 8/12/15 Fri 18/12/15
36 Expansion Tank 10 days Tue 8/12/15 Fri 18/12/15
37 Pipes(chilled,hot water)Plant Room 45 days Fri 6/11/15 Mon 28/12/15

Task Milestone External Tasks


Project: MSProj11
Split Summary External Milestone
Date: Mon 14/9/15
Progress Project Summary Deadline

** Above schedule is prepared considering timely receipt of input drawing,site clearences,Etc.


Tentative Schedule for HVAC Works @ Site 'P'
ID Task Name Duration Start Finish 2016 2017
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
38 Pipes(chilled,hot water)Inside Tunnel 45 days Wed 10/2/16 Fri 1/4/16 clearance from civil
39 Insulation(chilled,hot water) 50 days Tue 24/11/15 Wed 20/1/16
40 Insulation(chilled,hot water)Inside Tunnel45 days Sat 27/2/16 Tue 19/4/16 clearance from civil
41 AHUs 40 days Mon 11/1/16 Thu 25/2/16 pedestal by 05/01/2016
42 Ventilation Fans 30 days Mon 11/1/16 Sat 13/2/16 pedestal by 05/01/2016
43 Fcu 15 days Fri 27/11/15 Mon 14/12/15
44 Electrical Panels 18 days Fri 5/2/16 Thu 25/2/16
45 P1 Run tunnel and Pocket 75 days Mon 11/4/16 Wed 6/7/16
46 Ducting(GI) 50 days Mon 11/4/16 Tue 7/6/16 clearance from civil by 10/04/2016
47 Ducting(ss) 30 days Mon 11/4/16 Sat 14/5/16
48 Ducting(Alu) 25 days Mon 18/4/16 Mon 16/5/16
49 Duct Insulation 25 days Wed 8/6/16 Wed 6/7/16
50 Grills and diffusers 20 days Wed 8/6/16 Thu 30/6/16
51 Cable tray and Cables 30 days Mon 11/4/16 Sat 14/5/16
52 Upper Loop 80 days Sat 30/4/16 Mon 1/8/16
53 Ducting(GI) 50 days Sat 30/4/16 Mon 27/6/16 clearance from civil by 10/04/2016
54 Ducting(ss) 55 days Sat 30/4/16 Sat 2/7/16
55 Duct Insulation 45 days Fri 6/5/16 Mon 27/6/16
56 Duct Aquostic 10 days Fri 6/5/16 Tue 17/5/16
57 Grills and diffusers 25 days Mon 4/7/16 Mon 1/8/16
58 Lower Loop 75 days Mon 2/5/16 Wed 27/7/16
59 Ducting(GI) 45 days Mon 2/5/16 Wed 22/6/16 clearance from civil by 02/05/2016
60 Ducting(ss) 50 days Mon 2/5/16 Tue 28/6/16
61 Duct Insulation 36 days Sat 7/5/16 Fri 17/6/16
62 Duct Aquostic 10 days Wed 4/5/16 Sat 14/5/16
63 Grills and diffusers 25 days Wed 29/6/16 Wed 27/7/16
64 P2 Run Tunnel and Pocket 55 days Thu 30/6/16 Thu 1/9/16
65 Ducting(GI) 40 days Thu 30/6/16 Mon 15/8/16 clearance from civil by 01/
66 Ducting(ss) 30 days Thu 30/6/16 Wed 3/8/16
67 Duct Insulation 26 days Wed 6/7/16 Thu 4/8/16
68 Grills and diffusers 15 days Tue 16/8/16 Thu 1/9/16
69 Cable tray and Cables 25 days Thu 30/6/16 Thu 28/7/16
70 P3 Run Tunnel and Pocket 32 days Mon 1/2/16 Tue 8/3/16
71 Ducting(GI) 25 days Mon 1/2/16 Mon 29/2/16 clearance from civil by 01/02/2016
72 Ducting(ss) 21 days Mon 1/2/16 Wed 24/2/16
73 Duct Insulation 20 days Sat 6/2/16 Mon 29/2/16
74 Duct Aquostic 7 days Wed 3/2/16 Wed 10/2/16

Task Milestone External Tasks


Project: MSProj11
Split Summary External Milestone
Date: Mon 14/9/15
Progress Project Summary Deadline

** Above schedule is prepared considering timely receipt of input drawing,site clearences,Etc.


Tentative Schedule for HVAC Works @ Site 'P'
ID Task Name Duration Start Finish 2016 2017
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
75 Grills and diffusers 7 days Tue 1/3/16 Tue 8/3/16
76 Cable tray and Cables 30 days Mon 1/2/16 Sat 5/3/16
77 Commissioning 25 days Fri 2/9/16 Fri 30/9/16
78 Availabilty of Power supply 25 days Fri 2/9/16 Fri 30/9/16

Task Milestone External Tasks


Project: MSProj11
Split Summary External Milestone
Date: Mon 14/9/15
Progress Project Summary Deadline

** Above schedule is prepared considering timely receipt of input drawing,site clearences,Etc.