Steel =3 to 5 kg / sft
Cement =.5bags/ sft
RMC =.05 m3/sft
Block =12.5 nos /sqm
Electrical cast = Rs 133/sft
Plumbing cost = Rs 126/sft
Fire fighting cost = Rs 40/sft
External development = Rs 94.5/sft
Civil works-Structure = RS 751.25/sft
Finishing works = RS 467.50/sft
200 mm in cm 1:6 =0.124Bags /sqm
200 mm in cm 1:4 =0.206 bags/sqm
150 mm in cm 1:6 =0.093 bags/sqm
150mm in cm 1:4 =0.144 bags/sqm
100 mm in cm 1:4 =0.103 bags/sqm
Ceiling plastering =0.11 bags/sqm
Wall plastering =0.09 bags/sqm
Rough plastering =0.09 bags/sqm
Duct plastering =0.09 bags/sqm
External plastering =0.175 bags/sqm
lathen plastering =0.55 bags/sqm
stucco plaster =0.175 bags/sqm
100 mm plaster band =0.012 bags/rmt
pcc 1: 4: 8 =3.4 bags/cum
pcc 1:5:10 =2.52 bags/cum
pcc 1:3:6 =4.2 bags/cum
pcc 1:2:4 =6.02 bags/cum
230 mm brick =0.876 bags/cum
115 mm brick work =0.218 bags/cum
vdf 100 mm thick =0.82 bags/sqm
granolithic flooring =40 mm 0.35 bags/sqm
granolithic flooring =20 mm 0.28 bags/sqm
anti-skid =0.28 bags/sqm
ceramic =0.28 bags/sqm
vertified tile flooring =0.28 bags/sqm
vertified tile dado =0.27 bags/sqm
cerami dado =0.27 bags/sqm
marble flooring =0.3 bags/sqm
100 mm ht marble skerting =0.027 bags/rmt
marble glading =0.27 bags/sqm
terracota tle flooring =0.3 bags/sqm
mangalore tile =0.3 bags/sqm
Door frame fixing =0.17 bags/sqm
water proofing for sunken slab =0.23 bags/sqm
water proofing for walls =0.23 bags/sqm
water proofing for balcony/toilets =0.65 bags/sqm
Anti terminate treatment chemical Name is chloropyrifoc 20% . Diluting5 Lit
of Chemical with 95 Lit of water and usage is 7.5 Sqm Per liter {Diluted} .To
Provide 1” Dia hole And Deep1Foot
Labour Productivity thump rule :-
Brick work
1 mason 1 Men mazdoor 1.25 sqm
1 Women Mazdoor
Wall Plastering 1 mason
1 Men mazdoor 10 sqm
1 Women Mazdoor
Ceiling Plastering 1 mason
1 Men mazdoor 8 sqm
1 Women Mazdoor
External Plastering 1 mason
1 Men mazdoor 8 sqm
1 Women Mazdoor
Block work 8” 1 mason
1 Men mazdoor 10 sqm
1 Women Mazdoor
Block work 6” 1 mason
1 Men mazdoor 8 sqm
1 Women Mazdoor
Block work 4” 1 mason
1 Men mazdoor 8 sqm
1 Women Mazdoor
Carpenter 1 Skilled
1 Un skilled 4 Sqm
Bar bender 1 Skilled
1 UN skilled 200Kg
Tile work 1 Mason
1M Mazdoor 10 Sqm
Paint
Painter skilled OBD 600 Sft
Emulsion 800 Sft
Putty 600 Sft
Primer 800 Sft
Miscellineous thumb rule in construction :-
External Painting
Ace-Low quality
Apex-Medium Quality
Apex ultima –High Quality
One Sqm =10.763Sft
One Cum =35.314 Cft
One Acres=4046.873 Sqm=43560.17 Sft=4840.019Yards
One Cubic meter = 1000 litere
One Meter =3.280Feet
One Mile =1609.344 meter
One Acre = 100 cent
One ground =2400 Sft=5.51 cent
½ ground =2.75 cent
One Mile =8 Furlong
One cement bag =1.25 Cft
One Forma box =1*1*1.25 feet
THUMB RULES FOR CONCRETE MIX DESIGN
FOR ADDING 4 LITERS OF WATER IN 1 CU.M FRESHLY MIXED CONCRETE
1. The slump value will be increased by 25 mm.
2. The compressive strength of concrete will be decreased by 1.5 to 2.0 N/mm2
3. The shrinkage potential will be increased by 10%.
4. 1/4 bag of cement will be wasted.
IF THE TEMPERATURE OF FRESHLY MIXED CONCRETE IS INCREASED BY 1%,
THEN
1. 4 liters of water per cu.m will give equal slump.
2. The air content will be decreased by 1%.
3. The compressive strength of concrete will be decreased by 1.0 to 1.5 N/mm2.