STRENGTHENING OF BEAM IN PROGRESS
PANEL – AFTER REPAIR
BEAMS – AFTER FIBRE WRAPPING
GROUND FLOOR – AFTER REPAIR
GROUND FLOOR – BEFORE REPAIR
GROUND FLOOR – AFTER REPAIR
APPROACH & JETTY STRUCTURE
ISSUE
• Chloride induced corrosion of steel, resulting in de-lamination of concrete and
reduction in reinforcement size.
CHALLENGE
• Due to tidal variation, the maximum duration of dry period available for work was 6
hours at a stretch. As a result all the materials were modified to set within that period
and were also insensitive to moisture
• The scaffolding provided had to be suspended from the deck with anchors
• Work had to be carried out round the clock
CONCLUSION
• Numerous retrofit schemes are available for retrofitting.
• A Multiplicity of factors influence the selection of the retrofit
solution.
• Hence, no general rule. Needs good understanding of local and
global level interaction.
• Summary of global-local consequence of retrofit methods give
quick-look guide to potential user.
SUMMARY OF EFFECT OF RETROFIT ON LOCAL &
GLOBAL RESPONSE
SUMMARY OF EFFECT OF RETROFIT ON LOCAL & GLOBAL
RESPONSE