Name % Complete Cost Baseline Cost Cost Variance

The project to set up a new office has experienced significant delays and cost overruns. Setting up the new office, which is only 26% complete, has incurred a cost variance of $18,784 due to delays in material supply, miscommunication in procurement, and issues with the installation of phone/internet connections. Transferring back office data and finalizing the project closure have also exceeded their baseline costs without any work being completed. Several roles have been overallocated to address requirements that were not fully defined upfront and additional tasks caused by delays.

Uploaded by

Satnam Singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
101 views4 pages

Name % Complete Cost Baseline Cost Cost Variance

The project to set up a new office has experienced significant delays and cost overruns. Setting up the new office, which is only 26% complete, has incurred a cost variance of $18,784 due to delays in material supply, miscommunication in procurement, and issues with the installation of phone/internet connections. Transferring back office data and finalizing the project closure have also exceeded their baseline costs without any work being completed. Several roles have been overallocated to address requirements that were not fully defined upfront and additional tasks caused by delays.

Uploaded by

Satnam Singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

$20,000.

00
$18,000.00
$16,000.00
$14,000.00
$12,000.00
$10,000.00
$8,000.00
$6,000.00
$4,000.00
$2,000.00
$0.00
Defining Selecting New Setting up the Transferring Final closure of
requirements Office Site new office back office data project

Cost Variance

Name % Cost Baseline Cost


Complete Cost Variance

Defining 92% $24,396.67 $22,206.67 $2,190.00


requirements

Selecting New 53% $12,222.00 $11,592.00 $630.00


Office Site

Setting up the 26% $34,700.00 $15,916.00 $18,784.00


new office

Transferring back 0% $3,240.00 $0.00 $3,240.00


office data

Final closure of 0% $1,928.00 $0.00 $1,928.00


project
$2,500.00

$2,000.00 $2,240.00
$1,500.00 $1,680.00
$1,000.00 $1,400.00
$1,120.00
$500.00 $800.00
$480.00
$200.00
$0.00
$360.00
$0.00
$0.00
$0.00
$0.00
$384.00
$0.00
$0.00
$0.00$0.00
$0.00$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$200.00
$0.00

Cost Variance

Name Cost Baseline Cost


Cost Variance

Office manager $15,280.00 $14,800.00 $480.00

Telecommunications $2,400.00 $2,200.00 $200.00


administrator

Mailroom administrator $1,200.00 $1,200.00 $0.00

Chief relocation officer $12,000.00 $11,640.00 $360.00

Webmaster $1,152.00 $1,152.00 $0.00

project manager $11,586.67 $11,586.67 $0.00

Cleaners $768.00 $384.00 $384.00

Security Administrator $1,200.00 $1,200.00 $0.00

Environmental Engineer $1,120.00 $1,120.00 $0.00

Network Support $4,480.00 $3,360.00 $1,120.00


Manager

Movers $5,376.00 $3,136.00 $2,240.00

Finance manager $800.00 $0.00 $800.00

Architect $200.00 $0.00 $200.00


Senior Accountant $1,680.00 $0.00 $1,680.00

Assistant manager $1,400.00 $0.00 $1,400.00

Delay and cost overrun are inherent part of most projects. In our project till now, most of the

delay happened in setting up new office as this phase is just complete less than one-third

(26%) of what the actual planned timeline should be. Initially in defining requirement, the

requirement required to initiate is still not fully defined as there is some permits are needed

to be approved by government and incomplete new phone line requirement which takes

more resource and time caused extra 400 dollars than as planned. Due to this, Project

manager and office manager are overallocated. Moreover, updating the company

information like company letter heads, business cards, contact and fax number, etc. on our

website and other modes of communication with suppliers/contractors takes at least more 5

days from now and even worse the assigned resources are schedule for upcoming tasks.

Moreover, for phase setting up new office, the planned cost is $15,916.00. However, in interior

work and setup communication channel at new place delayed because of the delay in material supply

and miscommunication in procurement plan. While ordering new the phone and internet connections

are already done, but the work of installation is pending as the work does not went according to

proper procurement plan. This is because the local company agreed to provide the service of

installation at as per plan but due change in new location space and misunderstanding the blueprints

of new office by them. Change in procurement cost us more and network support manager was unable

to deliver the task on time which lead the cost went to 3200. More alarming thing, till now date the

interior work is just started and the exterior work about to start, however there was 2 times money is

spent as it should be spent. We got approval for office and now ordering the chairs, desk and other

furniture’s/equipment but this required more time to finish. The delay in creating purchase order,
new invoices and set payment terms for suppliers/contractors required two more days and senior

account manager is stuck with approval for new order from management and delay in getting and

clearing payments.