Online Bookstore Systems Analysis and Design 63.67 Days? Fri 8/31/07 ##########
Online Bookstore Systems Analysis and Design 63.67 Days? Fri 8/31/07 ##########
0 Online Bookstore Systems Analysis and Design 63.67 days? Fri 8/31/07 ##########
1 Business Case for Online Bookstore Implementation Approved by Executive Management 0 days Fri 8/31/07 Fri 8/31/07
2 Analysis and Requirements 3 days? Fri 8/31/07 Tue 9/4/07
3 Bookstore Data Requirements 3 days? Fri 8/31/07 Tue 9/4/07
4 Review Existing Materials 1 day? Fri 8/31/07 Fri 8/31/07 1
5 Conduct User Base Requirements Sessions 1 day? Mon 9/3/07 Mon 9/3/07 4
6 Develop User Needs Assessment and Complete Business Process Flow 1 day? Tue 9/4/07 Tue 9/4/07 5
7 Data Requirements Assessment Complete 0 days Tue 9/4/07 Tue 9/4/07 6
8 Technical Infrastructure Requirements 2 days? Fri 8/31/07 Mon 9/3/07
9 Review Current Infrastructure 1 day? Fri 8/31/07 Fri 8/31/07 1
10 Project Future Demand 1 day? Mon 9/3/07 Mon 9/3/07 9
11 Technical Infrastructure Requirements Assessment Complete 0 days Mon 9/3/07 Mon 9/3/07 10
12 Analysis and Requirements Complete 0 days Tue 9/4/07 Tue 9/4/07 6,10
13 Assessment of Solutions 6.67 days? Wed 9/5/07 Thu 9/13/07
14 Develop RFP 1 day? Wed 9/5/07 Wed 9/5/07 12
15 Determine Weightings to be Given to Responses 1 day? Thu 9/6/07 Thu 9/6/07 14
16 Issue RFP 1 day? Fri 9/7/07 Fri 9/7/07 15
17 Evaluate Responses 0.67 days? Mon 9/10/07 Mon 9/10/07 16
18 Perform Vendor Response/Requirements Gap Analysis 1 day? Mon 9/10/07 Tue 9/11/07 17
19 Invite Top Candidates to Demo 1 day? Tue 9/11/07 Wed 9/12/07 18
20 Select Best Fit Vendor Solution 1 day? Wed 9/12/07 Thu 9/13/07 19
21 Assessment of Solutions Complete 0 days Thu 9/13/07 Thu 9/13/07 20
22 Procure Solution 1 day? Thu 9/13/07 Fri 9/14/07 21
23 Design Online Bookstore Solution 11.5 days? Fri 9/14/07 Tue 10/2/07
24 Iteration Planning 1.5 days Fri 9/14/07 Tue 9/18/07
25 Conduct User and Team Training 0.5 days Fri 9/14/07 Mon 9/17/07 22
26 Define Iterations 0.5 days Mon 9/17/07 Mon 9/17/07 25
27 Define Test Approach 0.5 days Mon 9/17/07 Mon 9/17/07 25
28 Review and Baseline Iteration Plan 0.5 days Mon 9/17/07 Tue 9/18/07 27,26
29 Iteration Planning Complete 0 days Tue 9/18/07 Tue 9/18/07 28
30 Implementation Prototyping 2.5 days Mon 9/17/07 Wed 9/19/07
31 Develop Scenarios 0.5 days Mon 9/17/07 Mon 9/17/07 25
32 Map Scenarios to Package Transactions 0.5 days Mon 9/17/07 Tue 9/18/07 31
33 Define the Scenario Steps 0.5 days Mon 9/17/07 Tue 9/18/07 31
34 Specify and Prototype Reports 0.5 days Tue 9/18/07 Tue 9/18/07 33
35 Specify External Interfaces 0.5 days Mon 9/17/07 Tue 9/18/07 31
36 Build Package Prototype 0.5 days Tue 9/18/07 Tue 9/18/07 35
37 Exercise/Review Package Prototype 1 day Tue 9/18/07 Wed 9/19/07 36
38 Implementation Prototyping Complete 0 days Wed 9/19/07 Wed 9/19/07 37
Page 1
ID Task Name Duration Start Finish Predecess
Page 2
ID Task Name Duration Start Finish Predecess
Page 3
ID Task Name Duration Start Finish Predecess
117 Conduct Deployment Briefings 1 day Thu 11/15/07 Fri 11/16/07 116
118 Conduct Training 1 day Fri 11/16/07 Mon 11/19/07 117
119 Complete Process Review 1 day Fri 11/16/07 Mon 11/19/07 117
120 Deployment Preparation Complete 0 days Mon 11/19/07 Mon 11/19/07 119
121 Installation and Handover 5 days Mon 11/19/07 Mon 11/26/07
122 Install Application Software 1 day Mon 11/19/07 Tue 11/20/07 120
123 Convert Static and Acquire New Data 1 day Tue 11/20/07 Wed 11/21/07 122
124 Convert Dynamic Data 1 day Tue 11/20/07 Wed 11/21/07 122
125 Perform Production Tests 1 day Wed 11/21/07 Thu 11/22/07 123,124
126 Cut Over to New Application 1 day Thu 11/22/07 Fri 11/23/07 125
127 Create Maintenance Guide 1 day Fri 11/23/07 Mon 11/26/07 126
128 Installation and Handover Complete 0 days Mon 11/26/07 Mon 11/26/07 127
129 Finalize Deployment Phase 2 days? Mon 11/26/07 Wed 11/28/07
130 Perform Lessons Learned Meeting 1 day? Mon 11/26/07 Tue 11/27/07 128
131 Close Project File 1 day? Tue 11/27/07 Wed 11/28/07 130
132 Finalize Deployment Phase Complete 0 days Wed 11/28/07 Wed 11/28/07 131
133 Deployment Complete 0 days Wed 11/28/07 Wed 11/28/07 131
134 Online Bookstore Implementation Complete 0 days Wed 11/28/07 Wed 11/28/07 133
Page 4
Resource Names March 11 May 1 June 21 August 11 October 1 November 21 January 11 March
3/4 3/25 4/15 5/6 5/27 6/17 7/8 7/29 8/19 9/9 9/30 10/21 11/11 12/2 12/23 1/13 2/3 2/24
Page 5
Resource Names March 11 May 1 June 21 August 11 October 1 November 21 January 11 March
3/4 3/25 4/15 5/6 5/27 6/17 7/8 7/29 8/19 9/9 9/30 10/21 11/11 12/2 12/23 1/13 2/3 2/24
Page 6
Resource Names March 11 May 1 June 21 August 11 October 1 November 21 January 11 March
3/4 3/25 4/15 5/6 5/27 6/17 7/8 7/29 8/19 9/9 9/30 10/21 11/11 12/2 12/23 1/13 2/3 2/24
Information Systems Information Systems
Information Systems Information Systems
10/15
System Analysis and Design Te System Analysis and Design Team,Information Systems
System Analysis and Design Te System Analysis and Design Team,Information Systems
System Analysis and Design Te System Analysis and Design Team,Information Systems
System Analysis and Design Te System Analysis and Design Team
11/5
Information Systems
Page 7
Resource Names March 11 May 1 June 21 August 11 October 1 November 21 January 11 March
3/4 3/25 4/15 5/6 5/27 6/17 7/8 7/29 8/19 9/9 9/30 10/21 11/11 12/2 12/23 1/13 2/3 2/24
Information Systems Information Systems
System Analysis and Design Te System Analysis and Design Team
11/19
11/26
Page 8