THE AUTHORITY ON SUSTAINABLE BUILDING
www.level.org.nz
Gully trap construction
© BRANZ 2009
waste pipes (may discharge through the back of the
chamber) but must be watertight
grating must ‘pop-up’ in the event of surcharge
concrete surround if gully is likely to suffer damage
every residential building must have at least one
gully, the rim of which is 150 mm below the overflow
level of the lowest fixture
pipe bedding material
flow