ISSUED FOR INFORMATION
0       ISSUED FOR INFORMATION           JQR         JLM        DBA         May 8, 2019
BPP18-0009: EPC of New LPG and Propylene Spheres Piping, Electrical & Instrumentation
         Sizing Basis for LPG and Propylene Sphere Remote Retention Pond
                                                                               0
                          C-LPGP-PP-001
                          BRXX-X-XX01                                 Sheet No. 1 of 8
New LPG and Propylene Spheres Piping, Electrical & Instrument                                                           Sheet No.2 of 8
Sizing Basis for LPG and Propylene Sphere Remote Retention Pond                                                         Doc. No. BRXX-X-XX01 Rev. 0
                                                            TABLE OF CONTENTS
 Executive Summary ........................................................................................................................3
 1. Introduction ................................................................................................................................4
 2. Objective ......................................................................................................................................4
 3. Scope ............................................................................................................................................4
 4. Acronym ......................................................................................................................................4
 5. System Description .....................................................................................................................4
 6. Remote Retention Pond Sizing Guidelines ................................................................................5
 7. Remote Retention Pond Size Evaluation ...................................................................................5
 8. Conclusion and Recommendations............................................................................................7
 9. References ...................................................................................................................................7
 10. Attachment ................................................................................................................................8
New LPG and Propylene Spheres Piping, Electrical & Instrument                     Sheet No.3 of 8
Sizing Basis for LPG and Propylene Sphere Remote Retention Pond                   Doc. No. BRXX-X-XX01 Rev. 0
 Executive Summary
 The New LPG Sphere, S-1129, and New Propylene Sphere, S-1135, will provide PBR with the
 necessary product storage for LPG and Propylene that will be produced from RMP-2 units.
 Commissioning of S-1129 will allow LPG blending within the south spheres area without the need
 to transfer to north LPG spheres, thus enabling the refinery to simultaneously load to LPG vessels.
 After implementation of the project, the increase in storage capacity will provide the refinery
 enough buffers to handle the increase in LPG and Propylene production in case of product lifting
 delays thus avoiding unnecessary flaring of products. This project will also provide spare storage to
 receive high pressure LPG and Propylene in case of PRU-2 shutdown.
 As part of the project, contractor is tasked to prepare detailed engineering and construction of a
 remote retention basin for all the south spheres to provide adequate drainage in an event of PSV
 relief during a pool fire scenario.
 Proper design of drainage and spill containment system is important in LPG storage facilities as
 these handle large quantities of highly flammable liquids. When these products are accidentally
 released and ignited, pool fires can be formed which can result in overpressure due to vapor
 generation caused by the rapid boiling of liquid contents.
 Generally, the size of a remote retention facility is determined based on the largest volume
 calculated from the following scenarios below as cited in Section 5.2 of GP 09-01-01 (Spacing and
 Dikes for Storage Vessels and Tanks):
        The liquid volume remaining after initial vaporization from vessel spill or from the spillage
         of the vessel assuming that the vessel is full, and its contents are at a temperature equal to
         the lowest 24 hour mean temperature.
        Fifty percent (50%) of the volume of the vessel for vessels storing liquids with RVP of 100
         psia (690 kPa) or less.
        Twenty five percent (25 %) of the volume of the vessel for vessels storing liquids with RVP
         greater than 100 psia (690 kPa).
 From the criteria above, it has been identified that the size controlling scenario for the remote
 retention basin is from an LPG leak with estimated RVP of 623 kPaa. With the 5962 m3 being the
 largest LPG sphere capacity, the remote retention basin working capacity is estimated at 2980 m3
 (50% x 5962).
 Nonetheless, simulation results indicate that at ambient conditions, the likelihood of a propylene or
 LPG pool fire forming below the sphere is unlikely and that the leaking sphere contents will
 immediately vaporize. Thus, there is no expected accumulation of liquid in the event of propylene
 or LPG sphere leak.
 In consideration with the determined retention pond size, a holdup capacity of 1.9 hours is
 provided for accommodating firefighting wastewater in the remote retention basin. This
 information should be considered by the Owner when preparing operating and emergency
 firefighting response procedures.
New LPG and Propylene Spheres Piping, Electrical & Instrument                    Sheet No.4 of 8
Sizing Basis for LPG and Propylene Sphere Remote Retention Pond                  Doc. No. BRXX-X-XX01 Rev. 0
 1. Introduction
 The New LPG Sphere, S-1129, and New Propylene Sphere, S-1135, will provide PBR with the
 necessary product storage for LPG and Propylene that will be produced from RMP-2 units.
 Commissioning of S-1129 will allow LPG blending within the south spheres area without the need
 to transfer to north LPG spheres, thus enabling the refinery to simultaneously load to LPG vessels.
 After implementation of the project, the increase in storage capacity will provide the refinery
 enough buffers to handle the increase in LPG and Propylene production in case of product lifting
 delays thus avoiding unnecessary flaring of products. This project will also provide spare storage to
 receive high pressure LPG and Propylene in case of PRU-2 shutdown.
 As part of the project, EPC contractor is also tasked to prepare detailed engineering and
 construction of a remote retention basin for all the south spheres to provide adequate drainage in
 an event of PSV relief during a pool fire scenario.
 2. Objective
 This document intends to provide details on the sizing basis for the remote retention pond as part
 of the project scope.
 3. Scope
 Any information provided in the succeeding sections of this calculation is intended for use in this
 project only. Results of this calculation is not final and is based on available data at hand. When
 referring to this document, any new data unaccounted in the calculation should be evaluated and
 the calculation revisited for impact on the presented results.
 4. Acronym
 API     American Petroleum Institute
 DCS     Distributed Control System
 EPC     Engineering, Procurement and Construction
 GP      Global Practice (Exxon Mobil)
 LPG     Liquefied Petroleum Gas
 PBR     Petron Bataan Refinery
 PRU     Propylene Recovery Unit
 PRV     Pressure Relief Valve
 PSV     Pressure Safety Valve
 RVP     Reid Vapor Pressure
 5. System Description
 Proper design of drainage and spill containment system is important in LPG storage facilities as
 these handle large quantities of highly flammable liquids. When these products are accidentally
 released and ignited, pool fires can be formed which can result in overpressure due to vapor
 generation caused by the rapid boiling of liquid contents. A PRV is normally provided to ensure this
 excess pressure on the sphere is relieved and prevent unnecessary release of vessel contents after
 normal conditions have been restored.
New LPG and Propylene Spheres Piping, Electrical & Instrument                         Sheet No.5 of 8
Sizing Basis for LPG and Propylene Sphere Remote Retention Pond                       Doc. No. BRXX-X-XX01 Rev. 0
 6. Remote Retention Pond Sizing Guidelines
 In reference to Section 5.2 of GP-09-01-01, the remote retention pond size is governed by the
 largest volume requirement on the following scenarios below:
 6.1     The expected liquid volume remaining after initial vaporization, without taking any credit
         for aerosol formation, from the spillage of the vessel assuming that the vessel is full and its
         contents are at a temperature equal to the lowest 24 hour mean temperature which is at
         14°C as per D.S. No. 18-0009-01.
 6.2     Fifty percent (50%) of the volume of the vessel for vessels storing liquids with RVP of 100
         psia (690 kPa) or less.
 6.3     Twenty five percent (25 %) of the volume of the vessel for vessels storing liquids with RVP
         greater than 100 psia (690 kPa).
 7. Remote Retention Pond Size Evaluation
 7.1     Remaining liquid volume after initial vaporization at 14°C (Minimum Ambient
         Temperature)
         A process simulation using Aspen Hysys was made to determine the physical properties of
         the sphere contents at various conditions using the composition below:
         Propylene Product – 100%Vol Propylene
         LPG Product – 58% Vol Propane / 40% Vol Butane / 2%Vol Pentane
         The following were observed:
         Table 7.1-1: LPG and Propylene Condition Simulation Results
          Sphere Content                                 LPG                         Propylene
          Storage Pressure, kPag                         913                           1460
          Storage Temperature                    Ambient Min @ 14°C              Ambient Min @ 14°C
          Calculated RVP, kPaa                           623                           1573
          Boiling Point (@ 0 kPag), °C                   -15                            -47
          Liquid fraction @ Ambient Min                  0%                             0%
         *The determined conditions were taken from assumed LPG and Propylene composition. This table should
         be updated when plant data becomes available.
         Simulation results indicate that at ambient conditions, the likelihood of a propylene or LPG
         pool fire forming below the sphere is unlikely and that the leaking sphere contents will
         immediately vaporize. Thus, there is no expected accumulation of liquid in the event of
         propylene or LPG sphere leak.
         Further details in the simulation are provided in Attachment 1.
 7.2     Remote retention pond capacity as function of sphere capacity
         The table below provides the summarized geometric capacity of southern spheres:
         Table 7.2-1: Southern sphere geometric capacities
New LPG and Propylene Spheres Piping, Electrical & Instrument                              Sheet No.6 of 8
Sizing Basis for LPG and Propylene Sphere Remote Retention Pond                            Doc. No. BRXX-X-XX01 Rev. 0
                     Sphere                            Service                 Geometric Capacities, m3
                     S-1113                              LPG                            5535
                     S-1127                              LPG                            5962
                  S-1129 (New)                           LPG                            5962
                     S-1117                           Propylene                         3591
                     S-1119                           Propylene                         3591
                     S-1121                           Propylene                         3591
                     S-1123                           Propylene                         3591
                     S-1131                           Propylene                         4445
                     S-1133                           Propylene                         4445
                  S-1135 (New)                        Propylene                         4445
         Using the criteria specified in item 6.2 and 6.3 above, the size controlling scenario for the
         remote retention basin is from an LPG leak which is estimated to have an RVP of 623 kPaa.
         With LPG RVP below 690 kPaa, the remote retention basin working capacity is estimated at
         2980 m3 or fifty percent (50%) of the largest LPG sphere which is at 5962 m3.
 7.3     Additional remote retention basin considerations
         7.3.1 Firefighting wastewater loads
         Although there is little to no likelihood of liquid hydrocarbon that can accumulate in the
         remote retention basin, hydraulic load from firefighting wastewater should be considered.
         An analysis of firewater demand on the new and existing sphere was conducted. In the
         evaluation, firewater requirement is based on Section 10.3.1.3 and 10.3.3.3 of API 2510
         recommended application rate of 0.10 gpm/sq. ft (0.24 m3/hr /m2) plus the amount
         required for cooling of any adjacent sphere and a reserve capacity of 3 x 250 gpm (3 x 57
         m3/hr) additional cooling stream.
         When determining whether cooling water is needed for an adjacent vessel, the decision
         should be based on (a) the amount of radiant heat it will receive from an adjacent fire and
         (b) the maximum temperature that the unwetted shell section will reach when not cooled.
         Fig. 1 of API RP 2510A 2nd Edition provides a conservative estimate of the minimum safe
         distance between the center pool fire and adjacent vessel at which the maximum heat flux is
         at 7000 BTU/hr-sq. ft.
         A summary of the analysis made on the firewater requirement is shown on Table 7.3-1:
         Table 7.3-1: Southern sphere Firewater Requirements
                                                                                        Adjacent
                                              Sphere        Sphere       Sphere                     Total Firewater
                                                                                         Sphere
              Sphere           Service       Diameter,      Surface     Cooling*,
                                                                                        Cooling,
                                                                                                     Requirement,
                                                m          Area, m2      m3/hr                          m3/hr
                                                                                         m3/hr
              S-1113              LPG           22.5           1590         559           555           1114
              S-1127              LPG           22.5           1590         559          1028           1587
           S-1129 (New)           LPG           22.5           1590         559           709           1268
              S-1117           Propylene        19.0           1134         448           666           1114
              S-1119           Propylene        19.0           1134         448           943           1391
              S-1121           Propylene        19.0           1134         448           597           1045
              S-1123           Propylene        19.0           1134         448            0             448
              S-1131           Propylene        20.4           1307         490          1028           1518
              S-1133           Propylene        20.4           1307         490           986           1476
           S-1135 (New)        Propylene        20.4           1307         490           709           1198
         *Includes reserve firewater cooling capacity for 3 x 250 gpm (3 x 57 m3/hr).
New LPG and Propylene Spheres Piping, Electrical & Instrument                       Sheet No.7 of 8
Sizing Basis for LPG and Propylene Sphere Remote Retention Pond                     Doc. No. BRXX-X-XX01 Rev. 0
          As observed in Table 6.3-1, there is additional requirement for adjacent sphere cooling as
          there is not enough distance between the pool fire center and the nearest vessel. See
          Attachment 2 and 3 for further details.
          With the maximum firewater demand for the southern spheres estimated at 1587 m3/hr,
          the retention pond as sized in item 7.2 provide a hold-up duration of 1.9 hours only. Owner
          is advised to consider this limitation when preparing operating and emergency firefighting
          response procedures. Also, existing oily and stormwater handling facilities should also be
          assessed when the remote retention basin is to be connected to these systems.
 8. Conclusion and Recommendations
 8.1      There is little to no likelihood of liquid accumulation from leaks occurring from LPG and
          propylene spheres. Based on various considerations applied, it can be concluded that the
          minimum recommended remote retention pond working capacity is 2980 m3.
 8.2      Available holdup of 1.9 hours for accommodating firefighting wastewater in the remote
          retention basin should be considered by the owner when preparing operating and
          emergency firefighting response procedures. In order to help increase holdup duration,
          requirement for adjacent tank cooling should be carefully assessed during actual fire
          emergency. The following methods can be applied to determine if cooling is needed:
                 Check for any abnormal pressure and temperature reading if available thru field
                  instruments or via DCS.
                 Apply a firehose stream to the suspected vessel and then remove it, if the shell stays
                  wet a few seconds or longer; further cooling at that time is not needed.
                 If water boils when it is applied to the shell surface, cooling should proceed until the
                  metal temperature is below the boiling point of water.
 8.3      Existing oily and stormwater handling facilities should also be assessed when the remote
          retention basin is to be connected to these systems in the future.
 8.4      Although the determination on what constitute “adequate drainage” is generally subjective
          as described in Section 4.4.13.2.4.2 of API 521. The following items promote a condition of
          adequate drainage as outlined in Section 5.2 of API 2510:
                 The ground under and surrounding the sphere shall be graded to drain any liquid
                  spills to a safe area away from the vessel and piping. The grading shall be at a slope
                  of at least 1%.
                 The drainage system shall be designed to prevent liquid spilled from one sphere
                  from flowing under any other vessel and shall minimize the risk to piping from
                  spilled sphere contents.
                 The spill drainage area shall not contain equipment except as permitted by API
                  2510.
 9. References
       1. GP 09-01-01 V.2.0.0: Spacing and Dikes for Storage Vessels and Tanks
       2. API Std 2510 8th Edition: Design and Construction of LPG Installations
New LPG and Propylene Spheres Piping, Electrical & Instrument                  Sheet No.8 of 8
Sizing Basis for LPG and Propylene Sphere Remote Retention Pond                Doc. No. BRXX-X-XX01 Rev. 0
     3. API Publication 2510A 2nd Edition: Fire Protection Considerations for the Design and
        Operation of Liquefied Petroleum Gas (LPG) Storage Facilities
     4. API Std 521 6th Edition: Pressure Relieving and Depressuring Systems
 10. Attachment
     1. LPG and Propylene Simulation Results
     2. Firewater Demand Calculations
     3. LPG Fire Adjacent Sphere Cooling Identification