PRADHAN MANTRI GRAM SADAK YOJANA FOR 2016-17
Name of Road :
                  Generalised per km cost                            Package No. :
                  For 1st Year
Sl No SOR 2016-17            Item of work           Qntty Unit Rate     Amount
        Ref No.
  1     15.1 A    Restoration of rain cuts          45.00 cum 101.00    4545.00
 2       15.2.I     Maintenance of earthen shoulder     250.00 sqm    62.00    15500.00
                    (stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   0.00   sqm   6976.00     0.00
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 0.00     sqm   165.00      0.00
                    (Repair to pot holes and removal of
 5       15.7.I     loose material)
                    Maintenance   of Hume pipe            4    no    1238.00   4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          0.38   m     148.00     56.24
 8       15.11      Maintenance of 200 m stones and 1.00    km       326.00     326.00
                    Km stones
 9       15.12.I    Cutting branches of trees from    20    no        64.00    1280.00
                    roadway
 10     15.12.II    Cutting of shrubs from roadway    40    no        4.00      160.00
 11     15.12.III   Trimming grass and weeds from   270.00 sqm        1.00      270.00
                    shoulder
 12      15.13      White washing of parapet walls of   10.00 sqm     13.00     130.00
                    CD works
                    Total                                                      27682.74
                                                                     Say Rs.   27683.00
                    For 2nd Year
 1       15.1 A     Restoration of rain cuts            54.00 cum    101.00    5454.00
 2       15.2.I     Maintenance of earthen shoulder     300.00 sqm    62.00    18600.00
                    ( stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   0.00   sqm   6976.00     0.00
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 0.00     sqm   165.00      0.00
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4    no    1238.00   4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          0.76   m     148.00     112.48
 8       15.11      Maintenance of 200 m stones and     1.00   km    326.00     326.00
                    Km stones
Sl No SOR 2016-17             Item of work             Qntty Unit   Rate      Amount
        Ref No.
  9      15.12.I  Cutting branches of trees from        20    no    64.00     1280.00
                  roadway
 10     15.12.II  Cutting of shrubs from roadway         40    no   4.00       160.00
 11     15.12.III Trimming grass and weeds from        337.50 sqm   1.00       337.50
                  shoulder
 12       15.13    White washing of parapet walls of   10.00 sqm    13.00      130.00
                   CD works
                   Total                                                      31815.48
                                                                    Say Rs.   31815.00
Sl No SOR 2016-17              Item of work             Qntty Unit    Rate     Amount
        Ref No.
                    For 3rd Year
 1      15.1 A      Restoration of rain cuts            63.00 cum    101.00     6363.00
 2       15.2.I     Maintenance of earthen shoulder     350.00 sqm    62.00    21700.00
                    ( stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   8.78   sqm   6976.00   61249.28
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 70.31 sqm      165.00    11601.15
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4    no    1238.00    4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          1.52   m     148.00     224.96
 8       15.11      Maintenance of 200 m stones and 1.00    km       326.00     326.00
                    Km stones
 9      15.12.I     Cutting branches of trees from    20    no        64.00     1280.00
                    roadway
 10     15.12.II    Cutting of shrubs from roadway    40    no        4.00      160.00
 11     15.12.III   Trimming grass and weeds from   337.50 sqm        1.00      337.50
                    shoulder
 12      15.13      White washing of parapet walls of   10.00 sqm     13.00     130.00
                    CD works
                    Total                                                      108787.39
                                                                     Say Rs.   108787.00
                    For 4th Year
 1      15.1 A      Restoration of rain cuts            72.00 cum    101.00     7272.00
 2       15.2.I     Maintenance of earthen shoulder     400.00 sqm    62.00    24800.00
                    (stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   10.54 sqm    6976.00   73527.04
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 93.75 sqm      165.00    15468.75
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4    no    1238.00    4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          1.90   m     148.00     281.20
 8       15.11      Maintenance of 200 m stones and     1.00   km    326.00     326.00
                    Km stones
 9      15.12.I     Cutting branches of trees from       20    no     64.00     1280.00
                    roadway
Sl No SOR 2016-17             Item of work             Qntty Unit   Rate      Amount
        Ref No.
 10     15.12.II  Cutting of shrubs from roadway         40    no   4.00       160.00
 11     15.12.III Trimming grass and weeds from        337.50 sqm   1.00       337.50
                  shoulder
 12       15.13    White washing of parapet walls of   10.00 sqm    13.00      130.00
                   CD works
                   Total                                                      128997.99
                                                                    Say Rs.   128998.00
Sl No SOR 2016-17              Item of work             Qntty Unit    Rate     Amount
        Ref No.
                    For 5th Year
 1      15.1 A      Restoration of rain cuts            81.00 cum    101.00     8181.00
 2       15.2.I     Maintenance of earthen shoulder     450.00 sqm    62.00    27900.00
                    ( stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   15.81 sqm    6976.00   110290.56
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 117.19 sqm     165.00    19336.35
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4   no     1238.00    4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50  km     927.00     463.50
 7      15.10.II    Maintenance of RCC railing          1.90   m     148.00     281.20
 8       15.11      Maintenance of 200 m stones and 1.00    km       326.00     326.00
                    Km stones
 9      15.12.I     Cutting branches of trees from    20    no        64.00     1280.00
                    roadway
 10     15.12.II    Cutting of shrubs from roadway    40    no        4.00      160.00
 11     15.12.III   Trimming grass and weeds from   562.50 sqm        1.00      562.50
                    shoulder
 12      15.13      White washing of parapet walls of   10.00 sqm     13.00     130.00
                    CD works
                    Total                                                     173863.11
                                                                    Say Rs. 173863.00
                                                                5 Years Total 471146.00
                    For 5th Year
 1      15.1 A      Restoration of rain cuts            81.00 cum    101.00     8181.00
 2       15.2.I     Maintenance of earthen shoulder     450.00 sqm    62.00    27900.00
                    ( stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   15.81 sqm    6976.00   110290.56
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 117.19 sqm     165.00    19336.35
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4    no    1238.00    4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          1.90   m     148.00     281.20
 8       15.11      Maintenance of 200 m stones and     1.00   km    326.00     326.00
                    Km stones
 9      15.12.I     Cutting branches of trees from       20    no     64.00     1280.00
                    roadway
 10     15.12.II    Cutting of shrubs from roadway       40    no     4.00      160.00
Sl No SOR 2016-17           Item of work               Qntty Unit   Rate     Amount
        Ref No.
 11     15.12.III Trimming grass and weeds from        562.50 sqm   1.00      562.50
                  shoulder
 12      15.13     White washing of parapet walls of   10.00 sqm    13.00     130.00
                   CD works
                   Total                                                     173863.11
                                                                   Say Rs. 173863.00
                                                               5 Years Total 753796.00
 4
      ASM/CO/2016/3692
N MANTRI GRAM SADAK YOJANA FOR 2016-17
                                                  Remarks
                                         total 6% raincuts for 1st
                                         year
                                         total 10 % for 1st year
                                         not required
                                         not required
                                         maintenance to be done
                                         twice a year
                                         maintenance to be done
                                         once in 2 years
                                         considering 2% requiring
                                         maintenance
                                         considering 12% of the
                                         total area requiring grass
                                         trimming
                                         total 7.2% raincuts for 2nd
                                          year
                                         total 12 % for 1st year
                                         not required
                                         not required
                                         maintenance to be done
                                         twice a year
                                         maintenance to be done
                                         once in 2 years
                                         considering 4% requiring
                                         maintenance
        Remarks
considering 15% of the
total area requiring grass
trimming
         Remarks
total 8.4% raincuts for 3rd
 year
total 14 % for 3rd year
total 2.5% requiring
maintenance for 3rd year
total 1.5% requiring
maintenance for 3rd year
maintenance to be done
twice a year
maintenance to be done
once in two years
considering 8% requiring
maintenance
considering 15% of the
total area requiring grass
trimming
total 9.6% raincuts for 1st
year
total 16 % for 4th year
total 3% requiring
maintenance for 4th year
total 2% requiring
maintenance for 4th year
maintenance to be done
twice a year
maintenance to be done
once in two years
considering 10% requiring
maintenance
        Remarks
considering 15% of the
total area requiring grass
trimming
        Remarks
total 10.8% raincuts for
1st year
total 18 % requiring
maintenance for 5th year
total 4.5 % requiring
maintenance for 5th year
total 2.5 % requiring
maintenance for 5th year
maintenance to be done
twice a year
maintenance to be done
once in two years
considering 10% requiring
maintenance
considering 25% of the
total area requiring grass
trimming
total 10.8% raincuts for
1st year
total 18 % requiring
maintenance for 5th year
total 4.5 % requiring
maintenance for 5th year
total 2.5 % requiring
maintenance for 5th year
maintenance to be done
twice a year
maintenance to be done
once in two years
considering 10% requiring
maintenance
        Remarks
considering 25% of the
total area requiring grass
trimming
                           PRADHAN MANTRI GRAM SADAK YOJANA FOR 2016-17
                                     Name of Road :
                  Generalised per km cost                            Package No. :
                  For 1st Year
Sl No SOR 2016-17            Item of work           Qntty Unit Rate     Amount
        Ref No.
  1     15.1 A    Restoration of rain cuts          45.00 cum 101.00    4545.00
 2       15.2.I     Maintenance of earthen shoulder     250.00 sqm    62.00    15500.00
                    (stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   0.00   sqm   6976.00     0.00
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 0.00     sqm   165.00      0.00
                    (Repair to pot holes and removal of
 5       15.7.I     loose material)
                    Maintenance   of Hume pipe            4    no    1238.00   4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          0.38   m     148.00     56.24
 8       15.11      Maintenance of 200 m stones and 1.00    km       326.00     326.00
                    Km stones
 9       15.12.I    Cutting branches of trees from    20    no        64.00    1280.00
                    roadway
 10     15.12.II    Cutting of shrubs from roadway    40    no        4.00      160.00
 11     15.12.III   Trimming grass and weeds from   270.00 sqm        1.00      270.00
                    shoulder
 12      15.13      White washing of parapet walls of   10.00 sqm     13.00     130.00
                    CD works
                    Total                                                      27682.74
                                                                     Say Rs.   27683.00
                    For 2nd Year
 1       15.1 A     Restoration of rain cuts            54.00 cum    101.00    5454.00
 2       15.2.I     Maintenance of earthen shoulder     300.00 sqm    62.00    18600.00
                    ( stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   0.00   sqm   6976.00     0.00
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 0.00     sqm   165.00      0.00
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4    no    1238.00   4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          0.76   m     148.00     112.48
 8       15.11      Maintenance of 200 m stones and     1.00   km    326.00     326.00
                    Km stones
Sl No SOR 2016-17             Item of work             Qntty Unit   Rate      Amount
        Ref No.
  9      15.12.I  Cutting branches of trees from        20    no    64.00     1280.00
                  roadway
 10     15.12.II  Cutting of shrubs from roadway         40    no   4.00       160.00
 11     15.12.III Trimming grass and weeds from        337.50 sqm   1.00       337.50
                  shoulder
 12       15.13    White washing of parapet walls of   10.00 sqm    13.00      130.00
                   CD works
                   Total                                                      31815.48
                                                                    Say Rs.   31815.00
Sl No SOR 2016-17              Item of work             Qntty Unit    Rate     Amount
        Ref No.
                    For 3rd Year
 1      15.1 A      Restoration of rain cuts            63.00 cum    101.00     6363.00
 2       15.2.I     Maintenance of earthen shoulder     350.00 sqm    62.00    21700.00
                    ( stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   8.78   sqm   6976.00   61249.28
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 70.31 sqm      165.00    11601.15
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4    no    1238.00    4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          1.52   m     148.00     224.96
 8       15.11      Maintenance of 200 m stones and 1.00    km       326.00     326.00
                    Km stones
 9      15.12.I     Cutting branches of trees from    20    no        64.00     1280.00
                    roadway
 10     15.12.II    Cutting of shrubs from roadway    40    no        4.00      160.00
 11     15.12.III   Trimming grass and weeds from   337.50 sqm        1.00      337.50
                    shoulder
 12      15.13      White washing of parapet walls of   10.00 sqm     13.00     130.00
                    CD works
                    Total                                                      108787.39
                                                                     Say Rs.   108787.00
                    For 4th Year
 1      15.1 A      Restoration of rain cuts            72.00 cum    101.00     7272.00
 2       15.2.I     Maintenance of earthen shoulder     400.00 sqm    62.00    24800.00
                    (stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   10.54 sqm    6976.00   73527.04
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 93.75 sqm      165.00    15468.75
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4    no    1238.00    4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          1.90   m     148.00     281.20
 8       15.11      Maintenance of 200 m stones and     1.00   km    326.00     326.00
                    Km stones
 9      15.12.I     Cutting branches of trees from       20    no     64.00     1280.00
                    roadway
Sl No SOR 2016-17             Item of work             Qntty Unit   Rate      Amount
        Ref No.
 10     15.12.II  Cutting of shrubs from roadway         40    no   4.00       160.00
 11     15.12.III Trimming grass and weeds from        337.50 sqm   1.00       337.50
                  shoulder
 12       15.13    White washing of parapet walls of   10.00 sqm    13.00      130.00
                   CD works
                   Total                                                      128997.99
                                                                    Say Rs.   128998.00
Sl No SOR 2016-17              Item of work             Qntty Unit    Rate     Amount
        Ref No.
                    For 5th Year
 1      15.1 A      Restoration of rain cuts            81.00 cum    101.00     8181.00
 2       15.2.I     Maintenance of earthen shoulder     450.00 sqm    62.00    27900.00
                    ( stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   15.81 sqm    6976.00   110290.56
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 117.19 sqm     165.00    19336.35
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4   no     1238.00    4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50  km     927.00     463.50
 7      15.10.II    Maintenance of RCC railing          1.90   m     148.00     281.20
 8       15.11      Maintenance of 200 m stones and 1.00    km       326.00     326.00
                    Km stones
 9      15.12.I     Cutting branches of trees from    20    no        64.00     1280.00
                    roadway
 10     15.12.II    Cutting of shrubs from roadway    40    no        4.00      160.00
 11     15.12.III   Trimming grass and weeds from   562.50 sqm        1.00      562.50
                    shoulder
 12      15.13      White washing of parapet walls of   10.00 sqm     13.00     130.00
                    CD works
                    Total                                                     173863.11
                                                                    Say Rs. 173863.00
                                                                5 Years Total 471146.00
                    For 5th Year
 1      15.1 A      Restoration of rain cuts            81.00 cum    101.00     8181.00
 2       15.2.I     Maintenance of earthen shoulder     450.00 sqm    62.00    27900.00
                    ( stripping of excess soil)
 3       15.3.I     Repair of pot holes by removal of   15.81 sqm    6976.00   110290.56
                    failed material and filling with
                    75mm BM
 4      15.3.IV     Maintenance of Bituminous surface 117.19 sqm     165.00    19336.35
                    (Repair to pot holes and removal of
                    loose material)
 5       15.7.I     Maintenance of Hume pipe              4    no    1238.00    4952.00
                    culverts
 6        15.9      Maintenance of Road signs           0.50   km    927.00     463.50
 7      15.10.II    Maintenance of RCC railing          1.90   m     148.00     281.20
 8       15.11      Maintenance of 200 m stones and     1.00   km    326.00     326.00
                    Km stones
 9      15.12.I     Cutting branches of trees from       20    no     64.00     1280.00
                    roadway
 10     15.12.II    Cutting of shrubs from roadway       40    no     4.00      160.00
Sl No SOR 2016-17           Item of work               Qntty Unit   Rate     Amount
        Ref No.
 11     15.12.III Trimming grass and weeds from        562.50 sqm   1.00      562.50
                  shoulder
 12      15.13     White washing of parapet walls of   10.00 sqm    13.00     130.00
                   CD works
                   Total                                                     173863.11
                                                                   Say Rs. 173863.00
                                                               5 Years Total 753796.00
 4
N MANTRI GRAM SADAK YOJANA FOR 2016-17
                                                  Remarks
                                         total 6% raincuts for 1st
                                         year
                                         total 10 % for 1st year
                                         not required
                                         not required
                                         maintenance to be done
                                         twice a year
                                         maintenance to be done
                                         once in 2 years
                                         considering 2% requiring
                                         maintenance
                                         considering 12% of the
                                         total area requiring grass
                                         trimming
                                         total 7.2% raincuts for 2nd
                                          year
                                         total 12 % for 1st year
                                         not required
                                         not required
                                         maintenance to be done
                                         twice a year
                                         maintenance to be done
                                         once in 2 years
                                         considering 4% requiring
                                         maintenance
        Remarks
considering 15% of the
total area requiring grass
trimming
         Remarks
total 8.4% raincuts for 3rd
 year
total 14 % for 3rd year
total 2.5% requiring
maintenance for 3rd year
total 1.5% requiring
maintenance for 3rd year
maintenance to be done
twice a year
maintenance to be done
once in two years
considering 8% requiring
maintenance
considering 15% of the
total area requiring grass
trimming
total 9.6% raincuts for 1st
year
total 16 % for 4th year
total 3% requiring
maintenance for 4th year
total 2% requiring
maintenance for 4th year
maintenance to be done
twice a year
maintenance to be done
once in two years
considering 10% requiring
maintenance
        Remarks
considering 15% of the
total area requiring grass
trimming
        Remarks
total 10.8% raincuts for
1st year
total 18 % requiring
maintenance for 5th year
total 4.5 % requiring
maintenance for 5th year
total 2.5 % requiring
maintenance for 5th year
maintenance to be done
twice a year
maintenance to be done
once in two years
considering 10% requiring
maintenance
considering 25% of the
total area requiring grass
trimming
total 10.8% raincuts for
1st year
total 18 % requiring
maintenance for 5th year
total 4.5 % requiring
maintenance for 5th year
total 2.5 % requiring
maintenance for 5th year
maintenance to be done
twice a year
maintenance to be done
once in two years
considering 10% requiring
maintenance
        Remarks
considering 25% of the
total area requiring grass
trimming