A.K.S hivhare Infrastructure Pvt.Ltd .
Branch Office. Railway Station Road,BIAORA Distt. Rajgarh (M.P)
Head Office: 16, Eden Garden ChunaBhatti, Kolar Road,Bhopal (M.P.)
Tel:-:07374(0)230085, 230086Fax:230086, Mob.9425037549, E-mail-akshivhare@rediffmail.com
Ref No: AKSIPL/KJP/PM/40 Date : 04.05.2019
To,
The Team Leader,
M/S L.N.Malviya Infra Projects Pvt.Ltd
A/381, Siddhnath Swapn City,
Shujalpur
Subject: Rehabilitation & Up gradation of Intermediate lane flexible pavement to 2 lane with
paved Shoulders Rigid pavement on KHILCHIPUR - JIRAPUR Road from Km 5.500 to
Km 22.190 on Khilchipur to Jirapur section of newly declared NH -752 B in the state of
Madhya Pradesh on EPC mode
Contract Agreement no. :-04/2017-2018, Dated:26/02/2018
“Regarding Achieved of 3rd Milestone”
Dear Sir,
We are informing you that, we have achieved the 3rd milestone (70.0% Progress -405 day – dated
07.05.2019) of Khilchipur-Jirapur Road project on dated 03rd may 2019. The Physical progress of
project is 72.69% and financial progress is 72.72% (Progress report attached with this letter)
This is for your kind information and necessary action please.
Thanking you
Yours faithfully,
For A. K. Shivhare infrastructure Pvt ltd
Anshu Kumar Sharma
(Project Manager)
Enclosure: - Progress Report
Copy to: -
1. The Resident Engineer, L. N. Malviya infra Projects Pvt. Ltd., for information requested
and necessary action please.