Processing of Occupancy Permit

This document provides information about processing an occupancy permit from the city government of Iligan City, Philippines. It lists the office location and contact details, service hours, eligibility requirements, and step-by-step process which takes approximately 2 hours and 25 minutes. Applicants must submit proof of an approved building permit along with completion forms signed by engineers. City inspectors will then inspect the property and ensure it matches the approved plans before issuing a certificate of occupancy.

Uploaded by

Fham Bihira
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
297 views1 page

Processing of Occupancy Permit

This document provides information about processing an occupancy permit from the city government of Iligan City, Philippines. It lists the office location and contact details, service hours, eligibility requirements, and step-by-step process which takes approximately 2 hours and 25 minutes. Applicants must submit proof of an approved building permit along with completion forms signed by engineers. City inspectors will then inspect the property and ensure it matches the approved plans before issuing a certificate of occupancy.

Uploaded by

Fham Bihira
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Seminary Road, Brgy.

Del Carmen, Iligan City, 9200


Tel.: (063) 221-4645 / 221-4638 email : ceo_iligan@yahoo.com

Frontline service : PROCESSING OF OCCUPANCY PERMIT

Schedule of Availability of Service : 8:00AM-5:00 PM Daily (No noon break) excluding Saturdays, Sundays and Holidays.
On Mondays provision of services starts after flag raising

Who may Avail of the Service : Those who will apply for Occupancy Permit, whose Building Permit is already approved and the structure
is already completed and ready for occupancy use.

What are the Requirements : 1) 1 photocopy of approved Building, Electrical, Plumbing and Mechanical permit application
2) 1 set of approved plan
3) Completion forms (Building, Electrical, Plumbing and Mechanical)duly signed by the Engineers who sign
in application forms

Duration : 2 hours and 25 mins.

How to Avail of the Service :


DURATION OF
APPLICANT/ ACTIVITY UNDER
STEP SERVICES PROVIDER PERSON IN CHARGE FEES FORM/S
CLIENT NORMAL
CIRCUMSTANCES

1 Submit filled-out Received/reviewed all the requirements and issue Certificate of 30 mins. Engineering Assistant Completion
completions Occupancy to be process Per Building,
together with assessment Electrical,
other Schedule for inspection on the site 5 mins. Building Inspector is based on Plumbing,
requirements schedule of Mechanical
Conduct final inspection on site and evaluate the structure if it 1 hour Engineer II, Building Electrical, Mechanical fees and other
conform to the approved plans and specification based in the Inspector, Master Plumber stipulated in documents
approved Building Permit. the National
Engineer II, Building Electrical, Mechanical Building
Assessment of Payment 30 mins. Inspector, Master Plumber Code

If there is deficiency, returned to owner for correction 10 mins. OIC-Building Division

Issued statement of account for payment 10 mins.


END OF TRANSACTION