SPE 126108 HP/HT Well Intervention by Coil Tubing-East Coast Case Histories
SPE 126108 HP/HT Well Intervention by Coil Tubing-East Coast Case Histories
This paper was prepared for presentation at the SPE Oil and Gas India Conference and Exhibition held in Mumbai, India, 20–22 January 2010.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been
reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect any position of the Society of Petroleum Engineers, its
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Society of Petroleum Engineers is prohibited. Permission to
reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
Abstract
    Coil tubing is a single string of pipe, which can intervene into wells and perform specific jobs without mobilizing a rig.
The basic applications are cleaning wellbore/perforations, stimulating selective zones, controlling wells, milling/drilling
cement/tools/fish downhole, conveying tools in deviated/horizontal wells, gas lifting, setting cement plugs below production
packer, and many other applications.
    Operating coiled tubing units in HPHT and ultra HPHT wells requires conformance of specific parameters for safety and
successful operations. Challenges of the operations and treatment design are exacerbated considering the environment
downhole. The conditions become more severe in ultra HPHT environment if the well is deviated or approaches horizontal.
    Intervention and treatment in ultra HPHT and in highly deviated or in horizontal wells requires special procedures,
techniques and tools. The requirements include modified procedures as well as equipment and products to withstand the BHST
temperatures for the entire operation.
    As an example of complications in HPHT wells, on the east coast of India, bottomhole static temperatures could go as
high as 507°F and mud weight could vary between 14 and 19 ppg in deviated wells. Experience has shown that conventionally
calculated bottomhole circulating temperature alone is inadequate to determine the working temperature downhole. However,
with the help of computer-aided temperature simulation and all the above techniques, many successful CTU operations have
been executed under these difficult conditions.
    Using case histories for illustration, this paper will share best practices developed from 4 years of successful interventions
in HPHT and ultra-HPHT wells. These practices will include HPHT coil tubing intervention considerations, modified
procedures, special techniques and product choices.
Introduction
     Coil tubing is being used by the oil industry for last 5 decades. As the technology advanced and operators are trying to
penetrate deeper for hydrocarbon and pushing and extending the boundaries, challenges exacerbated while reaching HPHT and
Ultra HPHT environment with safety and success. Drilling and production at east coast of India, especially at Krishna-
Godavary basin, often encounters high pressure and high temperatures. Reservoir pressure and temperature may go up to
18,000 psi and 507 0F respectively as estimated. So far the maximum pressure and temperature encountered for CT operations
were 13500 psi and 467 0F respectively at 5600 meter measure depth (5228m TVD) at KG basin. The case histories presented
in this paper are from the KG basin located at the east coat of India. The planning for the jobs started during April 2005 and
the jobs started executing from end of April 2006. The paper discusses on challenges encountered during the execution of
these HPHT coil tubing intervention operations in these deviated wells. For example, at the KG field, one well had BHT of
467 0F at a MD of 5602 meter, reservoir pressure was around 13,000 psi and the mud weight was 14.8 ppg. These extreme
well conditions had led to the variation in existing practices and development of modified techniques that made the operations
successful. The various jobs performed on this well were: 1) Perforation wash, 2) Matrix stimulation 3) Clean up & Fishing
job and 4) Abrasive Cutting of stuck pipe.
     This paper illustrates on lessons learned during the design and execution of these jobs. There were some concerns on the
mud properties due to suffering of severe shearing inside small diameter CT, which is discussed and resolved in the paper
later. In addition, logistic and space restrictions challenges during the operations were also enumerated.
     As the job is being called and the objectives consolidate, the relevant well data is being collected. For the HPHT
application, one more extra step is being practiced to validate the collected data since the bottom hole conditions are extreme
in nature compared to the conventional wells. The primary and most important consideration in the design process is to run in
and pull out the CT from the well safely and undamaged. During data collection process, error can lead to the failure and even
catastrophic consequences in these extreme conditions.
     The available data is then being feed in to the tuned software to simulate the job and obtain the boundaries and limitations
of the operation. Extensive simulation by the properly tuned software is proven to be essential. Available resources are the key
components to consider. Then all the available resources are being assessed to ascertain the workability of the resources within
the boundaries and limitations with sufficient safety factors. If any fluid is being planned to pump down the hole, also being
sampled and tested in the lab for its effectiveness and compatibility with all other well bore fluids and formation fluids it may
encounter.
     The next part of the planning process embarks into the final stage of forecasting the outcome of the operation by utilizing
the tuned simulating software extensively. As far as the coil is concerned, operating limits degradation due to high
temperature, elongation due to temperature (thermal expansion) and tensile stress (due to length of the coil hanging or from
other sources), collapse rating degradation due to high temperature and elongation, collapse due to high well bore pressure, in-
situ fatigue induced by the corrosive gases, etc., being simulated extensively. For example, in the Case History I, thermal
elongation was around 11 feet and stress elongation was around 6 feet during RIH and around 8 feet during pull out, in total 19
feet elongation the CT suffered. The circulating temperature along the well bore also not linear. After simulating the
temperature along the well bore, it was observed that the hot spot exists far above the end of the CT. Figure-13 illustrated the
temperature profile along the well bore as predicted from the temperature simulator. It could be seen that the hot spot of the
temperature was around 600 meter above the bottom. As a result, it is not the bottom part of the CT suffered the temperature
most; it is way above the bottom suffered the temperature degradation of the CT strength. After extensive simulation, the
operating limits/boundaries are being established and feasibilities of the job assessed. The results are compared with the initial
objective desired. Afterwards recommendations are being made for any additional requirement (resources and materials) to
execute the jobs in best possible ways.
     Moreover, the challenges often emerge from logistics rather than designing. For an Ultra HPHT job, the required coil
posses thicker wall thickness and longer length compared to the conventional coils, which in turns exhibit weight of 25 MT to
45 MT depending on the CT size. Many cases the cranes on the offshore rigs have limitation of capacity, i.e., 25-30 MT. Due
to the properties of the CT for these jobs, the gooseneck also requires extended and this provide additional obstacle to enter
thru the V doors. Many times it requires parting the gooseneck from the injector head to make it enter thru the V door. Figure-
1 illustrates a typical CTU assembly for better understanding the rig up.
Case Histories:
    As mentioned above, the 1st such well was drilled in the KG basin and had a depth of 5602 meters MD with a ‘S’ profile
having 29.4 deg maximum deviation. Figure-2 & Figure-3 illustrate more detail about the well. It was drilled with 14.8 ppg
water based mud and cemented at a temperature of 467 0F. Afterwards 3-1/2” DST string was run to test the well. The
reservoir was tight sandstone gas bearing with high condensate ratio. It was perforated and tested in 14.4 ppg calcium bromide
brine. The four jobs, mentioned in the ‘Introduction’ were performed in this well. Selection of the appropriate equipment was a
good challenge. Below is a brief list of the major equipment used for the jobs.
    1) The 1-1/2 inch coil string had length 5710 meter, thickness varied from 0.156 to 0.175 inch having 80,000 psi yield
strength, internally tapered, was hydro tested at 15,000 psi after manufacturing, 2) heavy duty injector with extra pull
capability, 100 kLbs 3) quad BOP of 15 kpsi, 4 ) dual stripper assembly, 5) 15 kpsi riser and connector and fully automated
control cabin and heavy duty power pack with/and 6) all other valves and accessories.
    Selection of coiled string is always a crucial challenge for the HPHT or ultra HPHT environments due to the reduced
collapse resistance caused by the temperature and elongation. Since stronger injectors are being used, the coils are more
susceptible to the ovality development and hence the collapse rating reduces more. To overcome these challenges, a thorough
premonition was sketched with all possible worst case scenarios. The best size of the CT could be 1-3/4 inch or bigger, but
there was a crane limitation to lift the 5700 meter coil tubing on the rig. Thus 1-1/2 inch size of the coil was selected.
Including all these considerations, tubing force analysis was performed utilizing the computer aided simulator to optimize the
coil tubing size, strength rating and wall thickness accordingly. These differs from the thumb rules industry practices.
Application of the accurate computer simulation provided a huge flexibility and perfections to the design and selection of the
equipment.
    As a consequence, the injector head also to be capable of handling this heavy coil tubing with sufficient margin. The
stripper generally suffers from high temperature. Though high temperature rubber elements are also available for these
strippers, it is always good to have a cooler before the stripper so the longibility of the stripper increases. The power pack and
all other related equipment also should be capable of handling such high temperature and load. The details are enumerated in
the individual case histories below.
    The major challenges were:
     - The reservoir pressure was over 12500 psi, the brine (well bore fluid) weight was 14.4 ppg and the BHT was 467 0F at
       the TD and the temperature was 400-450 0F for the CTU operations around the testing objects.
     - Space restriction for rigging up pressure control equipment and the Injector Head on the rig floor in a conventional
       manner.
     - Obstruction caused by the presence of low height V door.
     - It was a new operation for the operator on that rig. Innovation for both CTU and Rig crews involved together in an
       operation of these profiles for the first time. The jobs were performed close to the CTU design/operating limits.
   Results:
      Other than the above difficulties, the job went as planned. The mud was replaced and the fish was pushed down to the
   hold up depth and made clearance for further operations. The CT pulled out successfully.
Operational/Technical Learning
   • Detailed job planning by an experienced hand can make the operations and meet the objectives more efficiently and
       reduce the operations timing.
   • Experienced operations hands are also important and crucial to achieve the objectives efficiently for the HPHT
       operations.
   • Modular CTU equipment provided better rig space management for the offshore applications.
   • The operations would be more flexible if bigger size of the CT could be used.
   • The abrasive cutting job was used first time in India. As the earlier attempt to cut the string by chemical cutter at the
       required depth was failed due to very high temperature, the “Abrasive Cutting” job was found suitable for the
       purpose. During the job, a minimum of 0.5 bbl/min to 0.75 bbl/min flow rates were maintained to have the maximum
       cutting velocity.
   • Another factor was very essential to these HP/HT wells, was to maintain the density of sand carrier fluid, i.e., gelled
       brine at 14.2 ppg at bottom of the hole.
   • Logistical challenges exhibited more dominating then technical in many instances/cases. Thus during the planning
       phase, pre-feasibility study to be performed and required arrangement to be made for saving rig time.
Conclusion
   - The objectives for each of the interventions were achieved
6                                                                                                                SPE 126108
    -   The CT was run in and pulled out successfully based on the method adapted, i.e., tune and use the CT simulator
        extensively for various options and scenarios to optimize the operations
    -   The abrasive cut was successful, which was evident by the pressure communication inside and out side of the tubing.
        In addition, there was presence of barite in the returns indicating the same. (Note: tube was stuck in barite).
    -   Due to the ultra HPHT conditions (>350 0F), collapse pressure rating reduced substantially compared to the
        conventional operations
    -   After these jobs, for last four years, the CT was being applied successfully to intervene these type of HPHT wells
    -   It was possible to achieve the successes using CT having less OD and less wall thickness compared to the HPHT jobs
        were performed around the North Sea using 1-3/4 inch OD CT. The operator was financially quite benefited using
        lower specification of CT for the higher degree of HPHT environment and using less deck space.
Acknowledgements
Thanks to BJ Services for the permission to publish this paper. The views and opinions expressed are solely by the author and
do not necessarily reflect those of any of the companies involved. Also thanks to the below personnel for their extended help
and contribution to the success:
    1. Robert Proctor – BJ Services
    2. Damian O'brien – BJ Services
    3. Samir Kale – BJ Services
    4. Henry Leigh – BJ Services
    5. Greg Dean – BJ Services
    6. Matthew Barrett – BJ Services
    7. Jose Moniz – BJ Services
    8. Ronnie Ogg – BJ Services
    9. Ronny Weible – BJ Services
    10. Carlos Aguilera - BJ Services
    11. Wallace Walters - BJ Services
    12. Stan Loving – Thru Tubing Solutions
    13. Kim Marmon – Thru Tubing Solutions
Nomenclature
API > American Petroleum Institute
psi > pounds per square inch
kpsi > thousands of pounds per square inch
MD > measured depth
TVD > true vertical depth
CTU > Coil Tubing Unit
CT > Coil Tubing
bbl > barrel
ppg > pound mass per gallon
BHT > bottom hole temperature
BHST > bottom hole static temperature
BHCT > bottom hole circulating temperature
HPHT > high pressure high temperature
HT > high temperature
TD > target depth
SOBM > Synthetic oil based mud
BHA> bottom hole assemblies
OD > outside diameter
DST > Drill Stem Test
RCT > Radial Cutting Torch
HSD > High Shot Density
in > inch
MT > Metric Ton
kLbs > Kilo pounds
BOP > well control Blowout Preventor
RIH > run in hole
References:
David Stiles, Mark Trigg: “Mathematical Temperature Simulators for Drilling Deepwater HTHP Wells”, paper SPE/IADC-105437,
    presented at the 2007 SPE/IADC Drilling Conference in Amsterdam, The Netherlands.
SPE 126108                                                                                                                7
Syed Haidher, Samir Kale, Sami Affes, Suresh Kumar: “HPHT Cement System Design - East Coast Case History”, paper SPE-104048,
     Presented at the 2006 IADC conference in Mumbai, India.
Coil Tubing Operations and Procedures Manual – BJ Services
Figure-1 Figure-2
  Figure-3                                                        Figure-4
8                          SPE 126108
Figure-5 Figure-6
Figure-7 Figure-8
    Figure-9   Figure-10
SPE 126108               9
Figure-11 Figure-12
Figure-13