0% found this document useful (0 votes)
778 views2 pages

Environmental Report Guide

This document outlines the sections and contents required for an Initial Environmental Examination Report (IEER) with a maximum length of 75 pages. The IEER sections include: an executive summary with 5 key points; a project description; baseline environmental conditions and impact assessment; an environmental management plan with impact mitigation, emergency response, monitoring, and implementation plans; references; and annexes. The project description must include location, rationale, development plan, project phases and activities, waste generation, pollution controls, manpower, costs, and schedule. The baseline and impacts section must discuss relevant environmental aspects like land, water, air, and people.

Uploaded by

gabinuang2
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
778 views2 pages

Environmental Report Guide

This document outlines the sections and contents required for an Initial Environmental Examination Report (IEER) with a maximum length of 75 pages. The IEER sections include: an executive summary with 5 key points; a project description; baseline environmental conditions and impact assessment; an environmental management plan with impact mitigation, emergency response, monitoring, and implementation plans; references; and annexes. The project description must include location, rationale, development plan, project phases and activities, waste generation, pollution controls, manpower, costs, and schedule. The baseline and impacts section must discuss relevant environmental aspects like land, water, air, and people.

Uploaded by

gabinuang2
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ANNEX

ANNEX 2-15
2-15
INITIAL ENVIRONMENTAL EXAMINATION REPORT (IEER) OUTLINE

IEER OUTLINE
(Maximum of about 75 pages)

NOTE: REFER TO ANNEX 2-7a (EIS SCOPING AND PROCEDURAL SCREENING CHECKLIST)
AS BASIS FOR DETERMINING SIMILAR OR EQUIVALENT SPECIFIC
CONTENTS/REQUIREMENTS OF EACH SECTION

Project Fact Sheet


Table of Contents
Executive Summary
1) Brief Project Description
2) Brief Summary of Project’s IEE Process
3) Summary of Baseline Characterization
4) Summary of Impact Assessment and Environmental Management Plan
5) Summary of Environmental Monitoring Plan

DRAFT MAIN IEER


1. BASIC PROJECT INFORMATION

2. DESCRIPTION OF THE PROJECT’S IEE PROCESS -


2.1. Terms of Reference of the IEE Study (if scoping was done with EMB)
2.2. IEE Team
2.3. IEE Study Schedule
2.4. IEE Study Area
2.5. IEE Methodology

3. PROJECT DESCRIPTION
3.1. Project Location, Area, ECA category (if applicable)
3.2. Project Rationale
3.3. Project Development Plan, Process/Technology and Project Components
Description of Project Phases (Activities/Environmental Aspects, Associated Wastes and
3.4.
Built-in Pollution Control Measures)
3.4.1. Pre-construction/ Pre-operational phase
3.4.2. Construction/Development phase
3.4.3. Operational phase
3.4.4. Abandonment phase
3.5. Manpower Requirements
3.6. Project Cost
3.7. Project Duration and Schedule

BASELINE ENVIRONMENTAL CONDITIONS, IMPACT ASSESSMENT AND


4.
MITIGATION
The Land (Discuss only relevant modules or modules likely to be affected by project
4.1.
impacts) - Land use, Pedology, Geology, Geomorphology, Terrestrial biology
The Water (Discuss only relevant modules or modules likely to be affected by project
4.2.
impacts – Hydrology, Oceanography, Water Quality, Freshwater Biology, Marine Biology
4.3. The Air - ((Discuss only relevant modules or modules likely to be affected by project

159
ANNEX 2-15

impacts - Meteorology, Air Quality, Noise


4.4. The People

5. ENVIRONMENTAL MANAGEMENT PLAN


5.1. Impacts Management Plan
5.2. Emergency Response Policy and Generic Guidelines (if applicable)
5.3. Environmental Monitoring Plan
Note: Attach under this section the filled out Project Environmental Monitoring and Audit
Prioritization Scheme (PEMAPS) Questionnaire in Annex 2-7d of the RPM
5.4. Institutional Plan for EMP Implementation

6. BIBLIOGRAPHY/REFERENCES
7. ANNEXES
7.1. Scoping Checklist (optional, since Scoping is not required for IEEs)
7.2. Original Sworn Accountability Statement of Proponent
7.3. Original Sworn Accountability Statement of IEE Preparer
7.4. Baseline Study Support Information

160

You might also like