ANNEX
ANNEX 2-15
2-15
INITIAL ENVIRONMENTAL EXAMINATION REPORT (IEER) OUTLINE
IEER OUTLINE
(Maximum of about 75 pages)
NOTE: REFER TO ANNEX 2-7a (EIS SCOPING AND PROCEDURAL SCREENING CHECKLIST)
AS BASIS FOR DETERMINING SIMILAR OR EQUIVALENT SPECIFIC
CONTENTS/REQUIREMENTS OF EACH SECTION
Project Fact Sheet
Table of Contents
Executive Summary
1) Brief Project Description
2) Brief Summary of Project’s IEE Process
3) Summary of Baseline Characterization
4) Summary of Impact Assessment and Environmental Management Plan
5) Summary of Environmental Monitoring Plan
DRAFT MAIN IEER
1. BASIC PROJECT INFORMATION
2. DESCRIPTION OF THE PROJECT’S IEE PROCESS -
2.1. Terms of Reference of the IEE Study (if scoping was done with EMB)
2.2. IEE Team
2.3. IEE Study Schedule
2.4. IEE Study Area
2.5. IEE Methodology
3. PROJECT DESCRIPTION
3.1. Project Location, Area, ECA category (if applicable)
3.2. Project Rationale
3.3. Project Development Plan, Process/Technology and Project Components
Description of Project Phases (Activities/Environmental Aspects, Associated Wastes and
3.4.
Built-in Pollution Control Measures)
3.4.1. Pre-construction/ Pre-operational phase
3.4.2. Construction/Development phase
3.4.3. Operational phase
3.4.4. Abandonment phase
3.5. Manpower Requirements
3.6. Project Cost
3.7. Project Duration and Schedule
BASELINE ENVIRONMENTAL CONDITIONS, IMPACT ASSESSMENT AND
4.
MITIGATION
The Land (Discuss only relevant modules or modules likely to be affected by project
4.1.
impacts) - Land use, Pedology, Geology, Geomorphology, Terrestrial biology
The Water (Discuss only relevant modules or modules likely to be affected by project
4.2.
impacts – Hydrology, Oceanography, Water Quality, Freshwater Biology, Marine Biology
4.3. The Air - ((Discuss only relevant modules or modules likely to be affected by project
159
ANNEX 2-15
impacts - Meteorology, Air Quality, Noise
4.4. The People
5. ENVIRONMENTAL MANAGEMENT PLAN
5.1. Impacts Management Plan
5.2. Emergency Response Policy and Generic Guidelines (if applicable)
5.3. Environmental Monitoring Plan
Note: Attach under this section the filled out Project Environmental Monitoring and Audit
Prioritization Scheme (PEMAPS) Questionnaire in Annex 2-7d of the RPM
5.4. Institutional Plan for EMP Implementation
6. BIBLIOGRAPHY/REFERENCES
7. ANNEXES
7.1. Scoping Checklist (optional, since Scoping is not required for IEEs)
7.2. Original Sworn Accountability Statement of Proponent
7.3. Original Sworn Accountability Statement of IEE Preparer
7.4. Baseline Study Support Information
160