Ae/Aee RWS, Mandal: Yedapally
Ae/Aee RWS, Mandal: Yedapally
Providing pipe line for water supply with HDPE pipes as per IS 4984/1995 with its ammedments and revisions thereon with
supplyof pipes and trench excavation for earth work excavation in all types of soils except hard rock which required partial blasting
Cost of Materials
A Cost of pipes including 16.32% CED & 4 % 14.88 38.00 48.53 67.50 66.33 95.83
VAT
C 120% - 75% extra for narrow foundation 4.89 4.89 13.58 13.58 13.58 13.58
D Lowering laying and jointing of pipes 1.80 2.30 4.54 4.54 5.40 5.40
AE/AEE
RWS, Mandal: Yedapally
SPECIFICATION REPORT ACCOMPANYING THE DETAILED LINE ESTIMATE
FOR PROVIDING PWS SCHEME
AT MANTHANI( BC COLONY) (V) ARMOOR (M)
1) INTRODUCTION:- The Habitation is located in Armoor mandal and is 10 km from the mandal head
quarters. The SCs population of the village as per 2001 cencus is 4350
2) Existing water facilities:- There are 1 Nos Hand pumps in the habitation, out of which 1 No is working
working.
3) NECESSITY OF THE SCHEME:- The existing OHSR unable to serve to The BC Colony, the population
of BC Colony about 1000 and drinking water problem arises in the locality To over come the drinking
water problem the following provisions are made in this estimate.
4) CONCLUSION:-With the above Items of work, the line estimate is preapared with common SSR 2005-
06 worked out to Rs 2.50 Lakhs.
Pumping main
0.46 6.35
Dia of pumpingmain 0.76( B )
1 2 3 4 5 6
TOTAL 250000.00
For pannel Board consisting of above components for 3- phase motor 1 No #REF! each #REF!
suitable up to 7.5 HP with DOL starter and suitable range of capacitor
and switch fuse units as above
3 Supply of Galvanised mild steel pipes (Medium class) of 50 mm dia 45 M #REF! #REF!
Nominal bore confirming to IS 1239/part - 1 1990 constinuosley welded
ERW/HFTW type and screwel at both ends as per IS 554 and end fitted
with socket (Heavy class) as per IS 1239/part - II / 1992 and the end
fitted with plastic ring exact length of 3.00 Mt + 5% etc., complete.
4 Supply and delivery of PVC insulated and PVC shealthed flexible - 3 60 M #REF! #REF!
Core Flat type submersible cable suitable for submersible pump set
conductors composed of ennealed high conductivity copper wire,
confirming to IS 694 with its revisions and Ammendments from time to
time, etc., complete 3 Core 2.5 Sqmm
5 Supply and delivery of 50 mm dia GI Non Return vlave confirming ISI 1 No #REF! each #REF!
specification
6 Supply and delivery of 7/20 Serivce wire of Reputed make etc., 90 M #REF! #REF!
complete.
7 Supply and delivery of G.I Bend heavy duty 'C' class threaded at both 1 No #REF! each #REF!
ends of 50x90mm with arm length of 20 cm
8 Supply and delivery of 50 mm dia MS clamp set 450 mm length, 12 mm 2 Nos #REF! each #REF!
thick plate, 75 mm vide with 6 Nos of 16 mm bolts & nuts
9 Supply and delivery of mild steel threaded flanges 50 mm dia MS flange 1 No #REF! each #REF!
set (2nos) of 150 mm dia 12 mm thick of (flange) with 4 nos 15 mm dia
bolts & nuts
10 Supply and fixing of MS bore well cover to suit 165 mm dia bore well 1 No #REF! each #REF!
including all charges complete.
11 Installation Errection Earthing testing and Commissioning of 1 Job #REF! each #REF!
Submersible pump set including conveyance of all materials to work site
including fixing of G.I pipes valves, specials and all other related items
but excluding cost of GI pipes, valves, and specials etc., with a trial run
of one week.
TOTAL #REF!
Sl. Description of item Qty. Rate Per Amount
No.
Dy.Executive Engineer Assistant Engineer
(PR)RWS Sub Division:Armoor (PR)RWS Mandal:Armoor
DETAILED SUB - ESTIMATE FOR PROVIDING PUMPING MAIN TO PWS SCHEME
AT MANTHANI( BC COLONY) (V) ARMOOR (M)
Sl.No Description of item Qty Rate Per Amount
1 2 3 4 5 6
Providing pipe line for water supply with HDPE pipes as per
IS 4984/1995 with its ammedments and revisions thereon
with supplyof pipes and trench excavation for earth work
excavation in all types of soils except hard rock which
required partial blasting and depositing on bank with initial
lead of 10 mts and lift of 2mts laying of pipes carefully into
trench and laying in alingment and gradient jointing the
pipeline with materials including refilling the trench with
excavated soils removal of surplus earth from the soil
testing the pipeline to hydraulic field test pressure including
TOT charges but excluding CED, APGST charges on pipes
complete for finished item of work. (Trench size is
0.30X.45M for 32 mm dia, 0.40x0.90 for 63 to 75mm dia
pipe, 0.70x1.00 for 90 to 140mm dia and 0.80x110 for
160mm to 200mm dia).
75 mm dia 6kg/cm2 PE-80 Grade HDPE Pipe line 600.00 M #REF! 1 Rmt #REF!
TOTAL #REF!
a) 75 mm dia 4kg/cm2 PE-80 Grade HDPE Pipe line 750.00 M #REF! 1 Rmt #REF!
2 Cost of plat form for public stands posts in distribution 10 Nos 1182.92 1 Each 11829.00
system including earth work excavation for foundation
suppling and fixing of precasted RCC circular ring of
prefabricated 900 mm dia 0.30m height ,RCC Prefabricated
central stand post of 150 mm dia 2.0 mt height CC (1:2:4)
bed inside ring and excavated of stand posts duly using
15mm dia G I pipes 2.5Mts long and couplings beds
( 2nos) Elbows (1No) Barrel nipple (2nos) Bibcock (1 no
and saddle piece including clamps and connecting charges
to distribution pipe line etc., complete for finished item of
work.
TOTAL #REF!
For foundation 1xII/4 3.50 3.50 2.50 24.04 Cum 44.46 1 Cum 1069.00
c Up to 5.00m To 6.00m above G L 1x4 0.23 0.23 0.40 0.085 Cum 3681.37 1 Cum 312.00
Up to 5.00m above G L 4x2 1.98 0.23 0.30 1.093 Cum 6337.07 1 Cum 6926.00
a for bottom slab 1xII/4 1.50 1.50 0.15 0.26 Cum 3623.19 1 Cum 960.00
b for conical slab 1xII 5.50+1.5 0.125 3.09 4.24 Cum ### 1 Cum 57170.00
0 2
c for Ring beam 1xII 1.50 0.30 0.45 0.64 Cum 5729.27 1 Cum 3643.00
6 VRCC (1:2:4) mix using 20mm Machine crushed granite metal including
cost and conveyance of all materials and labour charges but excluding
cost of steel and fabrication charges of steel.
18 Snowcem paint in two coats over primary cost using janatha cem in
single coat in C/C of all materials, scafoding and centering charges
complete.
For conical Side walls 1xII 5.50+1.5 0.00 3.09 33.96
0
Sl. Description of work No L B D Qty Rate Per Amt.
No.
2
For top slab projection 1xII 5.50 0.00 0.10 1.73
for Ring beam sides 1xII 1.50 0.00 1.14 5.37
for bottom slab 1xII / 1.20 1.20 0.00 1.13
For Columns 4
4x4 0.23 0.00 5.40 19.87
For Braces 4x2 1.98 1.06 0.00 16.79
78.85 Sqm 380.89 10 Sqm 3003.00
19 Painting the Name board on OHSR with Telugu letters with aproved
matter as per Department instructions including all charges etc.
complete
TOTAL 210000.00
1 2 3 4 5 6
1 1.00 Cum Earth work excavation and depsiting on bank with 28.50 1 Cum 28.50
an initial lead of 10M and lift 2M in ordinary
gravetly soils etc., complete as per S.S. 20-B
2 1.00 Cum C.C. (1:4:8) mix. Using 40mm gauge H.G. Metal
including cost and coveyance of all matrial and
labour charges etc., complete for finished item of
work
0.92 Cum Cost of 20mm guage H.G. Metal 520.30 1 Cum 478.68
0.46 Cum Cost of Sand 240.60 1 Cum 110.68
0.46 Cum Labour Mixing charges of cement morter 19.50 1 Cum 8.97
0.40 nos Mason 1st class + 70% 2nd class 142.70 1 Each 57.08
1.80 nos Man Mazdoor 106.00 1 Each 190.80
1.40 nos Women Mazdoor 106.00 1 Each 148.40
0.166 MT Cost of cement 2600.00 1 MT 431.60
1426.20
Add 4 % TOT Charges 57.05
TOTAL 1483.25
4 1.00 Cum C.C. (1:11/2:3) mix. Using 20mm gauge H.G. Metal
including cost and coveyance of all matrial and
labour charges etc., complete for finished item of
work
0.92 Cum Cost of 20mm guage H.G. Metal 855.80 1 Cum 787.34
0.46 Cum Cost of Sand 240.60 1 Cum 110.68
0.46 Cum Machine Mixing charges of cement morter 31.50 1 Cum 14.49
1.00 Cum Add vibrating charges 32.00 1 Cum 32.00
0.40 nos Mason 1st class + 70% 2nd class 142.70 1 Each 57.08
2.10 nos Man Mazdoor 106.00 1 Each 222.60
3.50 nos Women Mazdoor 106.00 1 Each 371.00
0.441 MT Cost of cement 2600.00 1 MT 1146.60
TOTAL 2741.78
5 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Raft.
1 2 3 4 5 6
1.00 Cum Centring Charges 121.00 1 Cum 121.00
2862.78
Add 4 % TOT Charges 114.51
TOTAL 2977.29
6 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Column up 5.0M
7 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Column up 5.0M to 8.0M
1.00 Cum Cost of Plain C.C(1 11/2.3) 2741.78 1 Cum 2741.78
1.00 Cum Centring Charges 744.10 1 Cum 744.10
1.00 No Add Lift charges 53.90 1 Cum 53.90
3539.78
Add 4 % TOT Charges 141.59
TOTAL 3681.37
7 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Braces up to 5.0m
1.00 Cum Cost of Plain C.C(1 11/2.3) 2741.78 1 Cum 2741.78
12.03 Sqm Centring Charges 278.60 1 Sqm 3351.56
6093.34
Add 4 % TOT Charges 243.73
TOTAL 6337.07
7 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Braces 5.0m to 6.0m
1.00 Cum Cost of Plain C.C(1 11/2.3) 2741.78 1 Cum 2741.78
12.03 Sqm Centring Charges 278.60 1 Sqm 3351.56
1.00 No Add Lift charges 53.90 1 Cum 53.90
6147.24
Add 4 % TOT Charges 245.89
TOTAL 6393.13
8 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Bottom Ring beam
1.00 Cum Cost of Plain C.C(1 11/2.3) 2741.78 1 Cum 2741.78
8.89 Sqm Centring Charges 305.20 1 Sqm 2713.23
1.00 No Add Lift charges 53.90 1 Cum 53.90
5508.91
Add 4 % TOT Charges 220.36
TOTAL 5729.27
Sl.N0. Quantity Description of Item Rate Per Amount
1 2 3 4 5 6
9 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Bottom Slab
1.00 Cum Cost of Plain C.C(1 11/2.3) 2741.78 1 Cum 2741.78
8.82 Kg Add cost of impervious water proofing compound 18.40 1 Kg 162.29
6.67 Sqm Centring Charges 788.40 10 Sqm 525.86
1.00 No Add Lift charges 53.90 1 Cum 53.90
3483.83
Add 4 % TOT Charges 139.35
TOTAL 3623.19
10 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Side walls conical portion
1.00 Cum Cost of Plain C.C(1 11/2.3) 2741.78 1 Cum 2741.78
8.82 Kg Add cost of impervious water proofing compound 18.40 1 Kg 162.29
16.00 Sqm Centring Charges 624.50 1 Sqm 9992.00
1.00 No Add Lift charges 53.90 1 Cum 53.90
12949.97
Add 4 % TOT Charges 518.00
TOTAL 13467.97
11 1.00 Cum RCC (1:1 1/2 :3) mix using 20mm guage H.G.
Metal including cost and conveyence of all material
and labour charges including centring curing But
excluding cost of steel and fabrication charges
Side walls straight portion
1.00 Cum Cost of Plain C.C(1 11/2.3) 2741.78 1 Cum 2741.78
8.82 Kg Add cost of impervious water proofing compound 18.40 1 Kg 162.29
16.00 Sqm Centring Charges 624.50 1 Sqm 9992.00
1.00 No Add Lift charges 53.90 1 Cum 53.90
12949.97
Add 4 % TOT Charges 518.00
TOTAL 13467.97
12 1.00 Cum C.C. (1:2:4) mix. Using 20mm gauge H.G. Metal
including cost and coveyance of all matrial and
labour charges etc., complete for finished item of
work
0.92 Cum Cost of 20mm guage H.G. Metal 855.80 1 Cum 787.34
0.46 Cum Cost of Sand 240.60 1 Cum 110.68
0.46 Cum Machine Mixing charges of cement morter 31.50 1 Cum 14.49
1.00 Cum Add vibrating charges 32.00 1 Cum 32.00
0.40 nos Mason 1st class + 70% 2nd class 142.70 1 Each 57.08
2.10 nos Man Mazdoor 106.00 1 Each 222.60
3.50 nos Women Mazdoor 106.00 1 Each 371.00
0.331 MT Cost of cement 2600.00 1 MT 860.60
TOTAL 2455.78
13 1.00 Cum RCC (1:2 :4) mix using 20mm guage H.G. Metal
including cost and conveyence of all material and
labour charges including centring curing But
excluding cost of steel and fabrication charges
Top slab
1.00 Cum Cost of Plain C.C(1 11/2.3) 2455.78 1 Cum 2455.78
10.00 Sqm Centring Charges 416.60 1 Sqm 4166.00
1.00 No Add Lift charges 53.90 1 Cum 53.90
6675.68
Add 4 % TOT Charges 267.03
Sl.N0. Quantity Description of Item Rate Per Amount
1 2 3 4 5 6
TOTAL 6942.71
1 2 3 4 5 6
Dy.Executive Engineer Assistant Engineer
(PR)RWS Sub Division:Armoor (PR)RWS Mandal:Armoor
LEAD STATEMENT AS PER 2005-2006 SSR
Add Deduct Add machine
Place of Availability Lead in Conveyance Initial cost Add S/
Sl.No. Name of the Material Unit blasting stacking crushing Total
of Material kM charges of Material charges
charges charges charges
1 2 3 4 5 6 7 8 9 10 11
1 Sand for mortar 1 Cum Jankampet 18 136.40 72.00 0.00 3.80 0.00 36.00 240.60
2 40MM Metal 1 Cum Munipally 17 146.60 282.00 53.00 6.30 0.00 45.00 520.30
3 20 MM Metal 1 Cum Munipally 17 146.60 494.00 53.00 6.30 123.50 45.00 855.80
4 Bricks 1000Nos Local 5 168.30 1350.00 0.00 6.20 0.00 35.00 1547.10
*NOTE* 1) The above quaries are nearer to site to the best of my knowledge.
2) The above leads are correct to the best of my knowledge.
3) The quaries requires full blasting.
2 Fiiling founds with Cement Concrete In CM(1:4:8) prop. Using with 40mm
guage HG broken stone metal including cost and conveyance of all labour
and metrilas charges etc complete
For foundation 1x1 1.36 1.36 0.15 0.28
0.28 cum 1483.25 1.00 1 cum 411.51
3 Const of Brick Masonary in CM(1:6) Prop using 2nd class brilcks including
cost and conveyance of all charges etc complete
Long wall 1x2 1.36 0.23 0.90 0.56
Cross wall 1x2 0.90 0.23 0.90 0.37
0.94 cum 1524.03 1.00 1 cum 1425.95
4 RCC in cm(1:2:4) prop using 20mm guage metal including cost and conveyance
of all charges including of all charges. But excluding cost and conveyance of steel
and fabrication charges etc., complete.
Roof slab over chambers 1x1 1.36 1.36 0.075 0.14
Deduct Manhole portion 1x1 0.30 0.30 0.075 0.01
0.15 cum 2455.78 1.00 1 cum 357.24
6 Add cost of steel and fabrications charges. 10.00 Kgs 35.15 1.00 Kg 351.52
TOTAL= 3307.92
2 S/d of 80 mm dia x0.90 m CI D/F pipes 3 Nos 838.57 1.00 Each 2516.00
3 S/d of 80 mm dia x0.60 m CI D/F pipes 3 Nos 641.06 1.00 Each 1923.00
5 S/d of 80 mm dia CI sluice valve PN - 1.0 2 Nos 1705.00 1.00 Each 3410.00
TOTAL 40000.00
1 2 3 4 5 6
1 1 Job Cost of plat form for public stands posts in
distribution system including earth work excavation
for foundation suppling and fixing of precasted
RCC circular ring of prefabricated 900 mm dia
0.30m height ,RCC Prefabricated central stand
post of 150 mm dia 2.0 mt height CC (1:2:4) bed
inside ring and excavated of stand posts duly
using 15mm dia G I pipes 2.5Mts long and
couplings beds ( 2nos) Elbows (1No) Barrel nipple
(2nos) Bibcock (1 no and saddle piece including
clamps and connecting charges to distribution pipe
line etc., complete for finished item of work.
1 No Cost of 900 mmdia RCC Prefabricated circular ring 295.00 1 Each 295.00
0.30 mt height
1 No Cost of 150 mmdia RCC Prefabricated central 250.00 1 Each 250.00
stand post 2.00m height