Gujarat Ugvcl To 19-20
Gujarat Ugvcl To 19-20
Tariff Order
Truing up for FY 2017-18,
Mid-Term Review of ARR for FY 2019-20 to 2020-21
and Determination of Tariff for FY 2019-20
For
Tariff Order
Truing up for FY 2017-18,
Mid-Term Review of ARR for FY 2019-20 to FY 2020-21
And Determination of Tariff for FY 2019-20
For
ABBREVIATIONS
A&G Administration and General Expenses
AB Cable Aerial Bunched Cable
APR Annual Performance Review
ARR Aggregate Revenue Requirement
CAGR Compound Annual Growth Rate
CAPEX Capital Expenditure
CERC Central Electricity Regulatory Commission
Control Period FY 2016-17 to FY 2020-21
DGVCL Dakshin Gujarat Vij Company Limited
DISCOM Distribution Company
EHV Extra High Voltage
FPPPA Fuel and Power Purchase Price Adjustment
FY Financial Year
GEB Gujarat Electricity Board
GERC Gujarat Electricity Regulatory Commission
GETCO Gujarat Energy Transmission Corporation Limited
GFA Gross Fixed Assets
GoG Government of Gujarat
GSECL Gujarat State Electricity Corporation Limited
GUVNL Gujarat UrjaVikas Nigam Limited
HT High Tension
JGY Jyoti Gram Yojna
kV Kilo Volt
kVA Kilo Volt Ampere
kVAh Kilo Volt Ampere Hour
kWh Kilo Watt Hour
LT Low Tension Power
MCLR Marginal Cost of Funds based Lending Rate
MGVCL Madhya Gujarat Vij Company Limited
MTR Mid-Term Review
MUs Million Units (Million kWh)
MW Mega Watt
MYT Multi Year Tariff
O&M Operation & Maintenance
PF Power Factor
PFC Power Finance Corporation
PGCIL Power Grid Corporation of India Limited
PGVCL Paschim Gujarat Vij Company Limited
PPA Power Purchase Agreement
PPPA Power Purchase Price Adjustment
R&M Repair and Maintenance
RE Revised Estimate
RLDC Regional Load Despatch Centre
SBAR State Bank Advance Rate
SBI State Bank of India
SLDC State Load Despatch Centre
UGVCL Uttar Gujarat Vij Company Limited
WRLDC Western Regional Load Despatch Centre
YoY Year on Year
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
CONTENTS
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
LIST OF TABLES
Table 2-1: ARR proposed by UGVCL for FY 2017-18 True up ................................................................. 8
Table 2-2: Revenue Surplus/(Gap) as claimed by UGVCL ....................................................................... 9
Table 2-3: Mid-Term Review for FY 2019-20 and FY 2020-21 as projected by UGVCL .......................... 9
Table 4-1: Category-wise sales for FY 2017-18 ...................................................................................... 48
Table 4-2: Energy sales approved in truing up for FY 2017-18 ............................................................... 49
Table 4-3: Distribution Losses.................................................................................................................. 49
Table 4-4: Distribution Losses approved for truing up for FY 2017-18 .................................................... 50
Table 4-5: Energy requirement and Energy balance as submitted by UGVCL for FY 2017-18 .............. 50
Table 4-6: Energy requirement approved by the Commission for truing up for FY 2017-18 ................... 51
Table 4-7: Power Purchase Cost claimed by UGVCL for FY 2017-18 .................................................... 51
Table 4-8: Power Purchase Cost submitted by UGVCL for FY 2017-18 ................................................. 52
Table 4-9: Power Purchase Cost as per the audited accounts for FY 2017-18 ...................................... 53
Table 4-10: Power Purchase Cost approved by the Commission for truing up for FY 2017-18 .............. 53
Table 4-11: Gain/ (Loss)on account of Distribution Losses for FY 2017-18 as submitted by UGVCL .... 54
Table 4-12: Approved Gain/ (Loss) on account of Distribution Losses for FY 2017-18 .......................... 54
Table 4-13: Approved gain / (loss) – power purchase expenses for truing up for FY 2017-18 ............... 55
Table 4-14: O&M Expenses claimed in the truing up for FY 2017-18 ..................................................... 55
Table 4-15: O&M Expenses and Gain / Loss claimed in the truing up for FY 2017-18 ........................... 56
Table 4-16: Employee Cost claimed by UGVCL in the truing up for FY 2017-18.................................... 56
Table 4-17: Employee Cost approved in the truing up for FY 2017-18 ................................................... 57
Table 4-18: R&M Expenses claimed by UGVCL for the truing up for FY 2017-18 .................................. 58
Table 4-19: R&M Expenses approved for the truing up for FY 2017-18 ................................................. 58
Table 4-20: A&G Expenses claimed by UGVCL in the truing up for FY 2017-18.................................... 59
Table 4-21: A&G Expenses approved in the truing up for FY 2017-18 ................................................... 60
Table 4-22: Other Expenses Capitalized as claimed by UGVCL in the truing up for FY 2017-18 .......... 60
Table 4-23: Other Expenses Capitalized approved in the truing up for FY 2017-18 ............................... 61
Table 4-24: Approved O&M expenses and Gain / Loss in the truing up for FY 2017-18 ........................ 61
Table 4-25: Capital expenditure claimed by UGVCL for FY 2017-18 ...................................................... 61
Table 4-26: Proposed Capitalisation and sources of funding by UGVCL for FY 2017-18 ....................... 68
Table 4-27: Approved Capitalisation and sources of funding in the truing up for FY 2017-18 ................ 69
Table 4-28: Fixed assets & depreciation computed by UGVCL for FY 2017-18 ..................................... 70
Table 4-29: Gain / Loss due to deprecation claimed in the truing up for FY 2017-18 ............................. 71
Table 4-30: Approved fixed assets & depreciation for FY 2017-18 ......................................................... 71
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-31: Gain / Loss due to Depreciation approved in the truing up for FY 2017-18 ......................... 72
Table 4-32: Interest and Finance Charges claimed by UGVCL in the truing up for FY 2017-18 ............ 72
Table 4-33: Interest and Finance Charges claimed by UGVCL in the truing up for FY 2017-18 ............ 72
Table 4-34: Gain / (Loss) claimed due to Interest & Finance Charges for FY 2017-18 .......................... 73
Table 4-35: Interest and Finance Charges approved by the Commission in the truing up for FY 2017-
18 ............................................................................................................................................................. 74
Table 4-36: Gain / (Loss) approved in the truing up for FY 2017-18 ....................................................... 74
Table 4-37: Interest on Working Capital claimed by UGVCL in the truing up for FY 2017-18 ................ 75
Table 4-38: Interest on working capital claimed by UGVCL in the truing up for FY 2017-18 .................. 75
Table 4-39: Interest on working capital approved in the truing up for FY 2017-18 .................................. 76
Table 4-40: Bad Debts claimed by UGVCL in the truing up for FY 2017-18 ........................................... 76
Table 4-41: Bad Debts Written Off for FY 2017-18 .................................................................................. 76
Table 4-42: Gain/ (Loss)due to Bad Debts approved in the Truing up for FY 2017-18 ........................... 77
Table 4-43: Return on Equity claimed by UGVCL in the truing up for FY 2017-18 ................................. 77
Table 4-44: Return on Equity claimed by UGVCL in the truing up for FY 2017-18 ................................. 78
Table 4-45: Return on Equity approved for FY 2017-18 .......................................................................... 78
Table 4-46: Approved Gain / Loss due to Return on Equity in the truing up for FY 2017-18 .................. 79
Table 4-47: Taxes claimed by UGVCL in the truing up for FY 2017-18 .................................................. 79
Table 4-48: Gain / (Loss) claimed due to provision for taxes for FY 2017-18 ......................................... 79
Table 4-49: Approved Gain / Loss due to tax in the truing up for FY 2017-18 ....................................... 80
Table 4-50: Non-Tariff Income claimed by UGVCL in the truing up for FY 2017-18 ............................... 80
Table 4-51: Gain / (Loss) claimed due to Non-Tariff Income for FY 2017-18 .......................................... 80
Table 4-52: Approved Gain / losses due to Non-Tariff Income in the truing up for FY 2017-18 ............. 81
Table 4-53: Revenue submitted in the truing up for FY 2017-18 ............................................................. 81
Table 4-54: Revenue approved in the truing up for FY 2017-18 ............................................................. 82
Table 4-55: ARR approved in truing up for FY 2017-18 .......................................................................... 83
Table 4-56: Revenue Surplus/ (Gap) for FY 2017-18 .............................................................................. 85
Table 4-57: Revenue Surplus/(Gap) approved in the truing up for FY 2017-18 ...................................... 86
Table 5-1: Mid-Term Review for FY 2019-20 and FY 2020-21................................................................ 88
Table 5-2: Historical Trend in Category-wise Units sold .......................................................................... 89
Table 5-3: Category-wise Growth rate of Units Sold ............................................................................... 90
Table 5-4: Category-wise number of Consumers .................................................................................... 90
Table 5-5: Growth rate of Number of Consumers .................................................................................... 90
Table 5-6: Category-wise of Connected Load ......................................................................................... 91
Table 5-7: Growth Rate of Connected Load ............................................................................................ 91
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-39: Energy requirement projected and approved for each DISCOM for .................................. 120
Table 5-40: Approved Power Purchase Cost for FY 2019-20 ............................................................... 121
Table 5-41: Approved Power Purchase Cost for FY 2020-21 ............................................................... 123
Table 5-42: Transmission charges approved by the Commission for period ........................................ 126
Table 5-43: GUVNL Costs approved by the Commission for the period FY 2019-20 and FY 2020-21 127
Table 5-44: SLDC charges approved by the Commission for FY 2019-20 and FY 2020-21 ................ 127
Table 5-45: Fixed cost of DISCOMs for the period FY 2019-20 and FY 2020-21 ................................. 127
Table 5-46: Variable cost for DISCOMs and Trading Units for the period FY 2019-20 and FY 2020-
21 ........................................................................................................................................................... 128
Table 5-47: Total Cost of Power for DISCOMs for FY 2019-20 and FY 2020-21.................................. 128
Table 5-48: Category Wise sales approved and existing average tariff in Rs./kWh .............................. 129
Table 5-49: Revenue with existing Tariffs for FY 2019-20 and FY 2020-21 with approved sales ......... 130
Table 5-50: Aggregate Revenue Requirement for Power Purchase for FY 2019-20 and FY 2020-21 . 131
Table 5-51: Total Revenue (Gap) for FY 2019-20 and FY 2020-21 ...................................................... 131
Table 5-52: Energy Requirement and Percentage Energy required for FY 2019-20 and FY 2020-21 . 131
Table 5-53: Allocation of Gap for FY 2019-20 ....................................................................................... 131
Table 5-54: Allocation of Gap for FY 2020-21 ....................................................................................... 132
Table 5-55: Bulk Supply Tariff for FY 2019-20....................................................................................... 132
Table 5-56: Bulk Supply Tariff for FY 2020-21....................................................................................... 132
Table 5-57: Capital Expenditure loan in the Mid-Term Review for FY 2019-20 and FY 2020-21 ......... 133
Table 5-58: Funding of Capitalisation projected in Mid-Term Review ................................................... 135
Table 5-59: Approved CAPEX vs Actual CAPEX & Actual Capitalization for FY 2016-17 and FY 2017-18
............................................................................................................................................................... 136
Table 5-60: Approved CAPEX, Capitalization and Funding for the FY 2019-20 and FY 2020-21 ........ 136
Table 5-61: O&M expenses projected for the FY 2019-20 and FY 2020-21 ......................................... 137
Table 5-62: Consolidated Employee Cost of all DISCOMs ................................................................... 138
Table 5-63: O&M expenses approved in the Mid-Term Review ............................................................ 139
Table 5-64: Depreciation projected for the Control Period FY 2019-20 to FY 2020-21 ........................ 140
Table 5-65: Depreciation approved in the Mid-Term Review ................................................................ 141
Table 5-66: Interest and Guarantee Charges projected in the Mid-Term Review ................................. 141
Table 5-67: Approved Interest and Finance Charges in the Mid-Term Review..................................... 142
Table 5-68: Interest on Working Capital projected in the Mid-Term Review ......................................... 143
Table 5-69: Interest on Working Capital approved in the Mid-Term Review ......................................... 143
Table 5-70: Provision for Bad and Doubtful debts projected for the FY 2019-20 and FY 2020-21 ...... 144
Table 5-71: Bad and Doubtful Debts Written-off approved in the .......................................................... 144
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-72: Return on Equity projected for the Mid-Term Review......................................................... 145
Table 5-73: Approved Return on Equity for the Mid-Term Review ........................................................ 145
Table 5-74: Income Tax projected in the Mid-Term Review .................................................................. 146
Table 5-75: Income Tax approved in the Mid-Term Review .................................................................. 146
Table 5-76: Non-Tariff Income projected in the Mid-Term Review ........................................................ 147
Table 5-77: Non-Tariff income approved for FY 2019-20 and FY 2020-21 ........................................... 147
Table 5-78: Aggregate Revenue Requirement for the FY 2019-20 and FY 2020-21 ............................ 147
Table 6-1: Sales (MUs) and Revenue (Crs.) from existing tariff projected for FY 2019-20 ................... 149
Table 6-2: Approved Sales (MUs) and Revenue from existing tariff for FY 2019-20 ............................ 149
Table 6-3: Projected Revenue from FPPPA Charges for the FY 2018-19 ............................................ 150
Table 6-4 FPPPA Charges for the FY 2019-20 ..................................................................................... 150
Table 6-5: FPPPA Charges for the FY 2019-20 .................................................................................... 151
Table 6-6: Approved Revenue from FPPPA Charges for the FY 2019-20 ............................................ 151
Table 6-7: Other Consumer related Income for FY 2019-20 ................................................................. 152
Table 6-8: Approved other consumer related Income for FY 2019-20 .................................................. 152
Table 6-9: Projected Agriculture Subsidy for FY 2019-20 ..................................................................... 152
Table 6-10: Approved Agriculture Subsidy for FY 2019-20 ................................................................... 153
Table 6-11: Projected Revenue for FY 2019-20 .................................................................................... 153
Table 6-12: Approved Total Revenue for FY 2019-20 ........................................................................... 153
Table 6-13: Approved Mid-Term Review ARR for FY 2019-20 ............................................................. 154
Table 6-14: Estimated Revenue (Gap)/Surplus for FY 2019-20 at Existing Tariff for UGVCL .............. 154
Table 6-15: Consolidated (Gap)/Surplus computed for FY 2019-20 ..................................................... 155
Table 8-1: Base price of power purchase .............................................................................................. 164
Table 9-1: Allocation matrix for segregation of wheeling and retail supply for UGVCL for the FY 2019-
20 ........................................................................................................................................................... 166
Table 9-2: Allocation of ARR between wheeling and retail supply business for UGVCL for FY 2018-
19 ........................................................................................................................................................... 166
Table 9-3: Wheeling Charges for FY 2019-20 ....................................................................................... 167
Table 9-4: Cross subsidy surcharge for FY 2019-20 ............................................................................. 168
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
CORAM
ORDER
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
1.1 Background
Uttar Gujarat Vij Company Ltd., (hereinafter referred to as “UGVCL” or the “Petitioner”)
has on 30th November, 2018 filed a petition under Section 62 of the Electricity Act,
2003, read with Gujarat Electricity Regulatory Commission (Multi-Year Tariff)
Regulations, 2016, for the Truing up of FY 2017-18, Mid-Term Review of ARR for FY
2019-20 to FY 2020-21 and Determination of retail supply tariff for FY 2019-20.
After technical validation of the petition, it was registered on 04th December, 2018 and
as provided under Regulation 29.1 of the GERC (MYT) Regulations, 2016, the
Commission has proceeded with this tariff order.
Distribution Companies:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Gujarat Urja Vikas Nigam Limited (GUVNL), a holding company, is responsible for
purchase of electricity from various sources and supply to Distribution Companies and
also other activities including trading of electricity.
The Government of Gujarat, vide Notification dated 3rd October, 2006, notified the final
opening balance sheets of the transferee companies as on 1st April, 2005. The value
of assets and liabilities, which stand transferred from the erstwhile Gujarat Electricity
Board to the transferee companies, include Uttar Gujarat Vij Company Limited
(UGVCL). Assets and liabilities (gross block, loans and equity), as on the date
mentioned in the notification, have been considered by the Commission in line with the
Financial Restructuring Plan (FRP), as approved by Government of Gujarat.
The Petitioner filed its Petition for Truing-up of FY 2016-17 and determination of tariff
for FY 2018-19 on 15th January, 2018. After technical validation of the petition, it was
registered on 17th January, 2018 (Case No. 1699/2018). The Commission vide Order
dated 31st March, 2018 approved truing up for FY 2016-17 and determined the tariff
for FY 2018-19.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Also, Regulation 16.2(vi) of the GERC (MYT) Regulations, 2016 provides for annual
determination of tariff for Generating Company, Transmission Licensee ,SLDC,
Distribution Wires Business and Retail Supply Business for each financial year, within
the control period, based on the approved forecast and results of the truing up exercise.
In accordance with Section 64 of the Electricity Act, 2003, the Commission directed
UGVCL to publish its application in the abridged form to ensure public participation.
The public notice was issued in the following newspapers on 08th December, 2018
inviting objections / suggestions from its stakeholders on the Mid-Term Review Petition
filed by it.
The petitioner also placed the public notice and the petition on the website
(www.ugvcl.com) for inviting objections and suggestions on its petition. The interested
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission also placed the petition and additional details received from the
petitioner on its website (www.gerc.in.org) for information and study of all the
stakeholders. The Commission also issued a notice for public hearing in the following
newspapers in order to solicit wider participation by the stakeholders.
The status of stakeholders who submitted their written suggestion / objections, those
who remained present in public hearing, those who could not attend the public hearings
and those who made oral submissions is given in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The issues raised by the objectors, along with the response of UGVCL and the
Commission’s views on the response, are dealt with in Chapter 3 of this Order.
UGVCL has approached the Commission with the present petition for Truing up of FY
2017-18, Mid-Term review of ARR for FY 2019-20 and FY 2020-21 and determination
of retail supply tariff for FY 2019-20.
The Commission has undertaken Truing up for the FY 2017-18, based on the
submissions of the Petitioner. The Commission has undertaken the computation of
Gain and losses for FY 2017-18, based on the audited annual accounts.
While truing up of FY 2017-18, the Commission has been primarily guided by the
following principles:
Controllable parameters have been considered at the level approved as per the
MYT Order, unless the Commission considers that there are valid reasons for
revision of the same.
Uncontrollable parameters have been revised, based on the actual performance
observed.
The Truing up for the FY 2017-18 has been considered, based on the GERC (MYT)
Regulations, 2011.
Mid-Term review for FY 2019-20 and FY 2020-21 and Determination of Tariff for FY
2019-20 have been considered as per the GERC (Multi-Year Tariff) Regulations, 2016.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
1. The First Chapter provides a background of the Petitioner, the petition and
details of the public hearing process and approach adopted for this Order.
2. The Second Chapter provides a summary of the petition.
3. The Third Chapter deals with the Public hearing process including the
Objections raised by Stakeholders, UGVCL’s response and the Commission’s
views on the response.
4. The Fourth Chapter deals with the Truing up for FY 2017-18.
5. The Fifth Chapter deals with Mid-Term Review of ARR for FY 2019-20 and FY
2020-21 and
6. The Sixth Chapter deals with Determination of retail supply tariff for FY 2019-
20.
7. The Seventh Chapter deals with compliance of the Directives and issue of
fresh directives for UGVCL.
8. The Eighth Chapter deals with fuel and power purchase adjustments.
9. The Ninth Chapter deals with wheeling and cross subsidy surcharges.
10. The Tenth Chapter deals with tariffs for FY 2019-20.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
2.1 Introduction
This chapter deals with highlights of the petition as submitted by UGVCL for truing up
of FY 2017-18, Mid-Term Review for Aggregate Revenue Requirement for FY 2019-
20 and FY 2020-21 and determination of retail supply tariff for FY 2019-20.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The above revenue Surplus/(Gap) arising based on the true up for FY 2017-18
mentioned above shall be added in the ARR for the FY 2019-20.
Table 2-3: Mid-Term Review for FY 2019-20 and FY 2020-21 as projected by UGVCL
(Rs. Crore)
2019-20 2019-20 2020-21 2020-21
Sr.
Particulars (Approved in (Projected in (Approved in (Projected in
No.
MYT Order) MTR) MYT Order) MTR)
1 Cost of Power Purchase 9760.79 11156.97 10499.76 11835.84
Operations& Maintenance
2 495.19 840.71 523.51 942.07
Expenses
2.1 Employee Cost 473.43 734.53 500.51 829.82
2.2 Repair & Maintenance 98.91 98.91 104.57 104.57
Administration & General
2.3 84.60 84.60 89.44 89.44
Charges
2.4 Other Debits - - - -
2.5 Extraordinary Items - - - -
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission has noted the response of the Petitioners which is self explanatory.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioners submitted that minimum Average eight hours power supply is provided to
agriculture sector. Further, a policy related to power supply to agriculture sector has
also been formulated by Gujarat Urja Vikas Nigam Ltd as per guidelines from GoG for
uniform power supply to agriculture sector in the State and DISCOMs have been
implementing the same by ensuring minimum average eight hours 3 phase power
supply to agriculture sector. Moreover, during cropping seasons as per the requirement
in order to save standing crops, more than 8 hours of power supply is also provided to
agriculture sector. In case power supply to Ag Sector is given less than 8hrs during the
day due to technical constraints related issues in that case the shortfall in power supply
of previous day is compensated during the subsequent period. It is the endeavor of the
Distribution Companies to provide the quality power and best possible services well
within the time limits specified in Regulations.
Commission’s view:
The Commission has always emphasised on providing quality power supply and is of
view that Petitioners should take every measure to deliver quality power supply.
Petitioners submitted that it estimated Sales, No. of consumers and Connected load
based on the growth rates in the past and sale to agriculture metered category are
projected based on methodology done in past. This has been done as per Tariff
Regulation notified by the Commission
Commission’s view:
The Commission has carried out the Mid-Term Review after due diligence and
prudence check.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioners submitted that every Year, certain billing amount of some consumers are
ascertained to be non recoverable and is charged in P&L of the Company under the
head of other debits for the respective year.
Commission’s view:
The Commission has approved the actual Bad and Doubtful Debts written off in
accordance with the provision of the GERC (MYT) Regulations, 2016.
5. Overload Feeders:
The objector sought information on overloaded feeders.
Loading on any of the feeder is highly dynamic phenomena. However, feeders having
either more length or found to be overloaded on sustained basis are bifurcated on
priority. Information on Nos. of Feeders bifurcated during last three years and proposed
to be bifurcated during rest of the period of 2018-19 is provided along with expenditure
details.
Commission’s view:
The Commission is of the view that adequate planning is to be carried out for load
management in accordance with provisions of the GERC Distribution Code, 2004, so
that overload condition of the feeders is avoided.
The National Tariff Policy mentions to have rationalization of tariff of various consumer
categories such that it is more aligned to the cost of supply and in a band of +/-20 %
to the average cost of supply. In order to ensure uniform tariff rates for all four State
Gujarat Electricity Regulatory Commission Page 13
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The present tariff of agriculture is highly subsidized and hence further categorization is
not appropriate.
Commission’s view:
Irrigation to agricultural field through micro/drip irrigation system requires less energy
consumption compared with normal mode of irrigation. Thus such agriculture
consumers are automatically benefitted. Giving benefit to one class of consumer will
result into increase in tariff of other class of consumers.
Commission’s view:
The Petitioner had filed Petition No. 1087/2011 on the said issue and the Commission
has disposed of the petition.
Commission’s view:
The Commission has no role to play in this matter as the scheme is introduced by the
State Government.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Efficient utitization of electrical energy helps in less energy consumption for the same
quantum of work. This phenomenon is equally applicable to the agricultural
consumers. A demonstrative project was undertaken by replacing old pump sets with
efficient pump sets. If the metered agricultural consumer installs energy efficient pump
set, energy consumption as well as energy bill can be reduced.
Commission’s view:
The Energy Efficient Pump Set scheme is in place in the area of PGVCL under
Demand Side Management Programme was introduced by PGVCL. It is experienced
that consumers are not coming forward to avail the benefits of this scheme. The
objector being a consumers organisation should make the consumers aware about
benefits of the said scheme by opting it.
LTP-V tariff category is to incentivize use of surface water sources such as river, canal,
dam etc. and supplying water directly to the field of farmers for irrigation only. Further
this is to motivate the farmers for utilization of surface water and thereby to promote
energy and water conservation particularly for the consumers in the command area of
Sardar Sarovar project area and such other mini irrigation system. Mainly such projects
or system requires 24 hours power supply and therefore a separate tariff category is
provided. Since specific tariff is provided for surface water irrigation, the same cannot
be extended for filling up the ‘houze’ etc. prepared in farm for water collection
Commission’s view:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission determines the tariff in accordance with provisions of the Electricity
Act, 2003 which provides that no undue preferences to any consumer of electricity will
be shown while determining the tariff.
The basic nature of FPPPA/PPPA is 'adjustment' related to power purchase cost i.e.
pass through of increase or decrease, as the case may be, in the power purchase cost
over the base power purchase cost. The PPPA charge is being levied on the consumer
categories on account of the change in the cost of power purchase, which comprises
almost 85 to 93% of the Distribution Licensee's Aggregate Revenue Requirement. Any
expense pertaining to the regulated business of the Distribution Licensee has to be
recovered from all consumers in some manner; therefore the PPPA charges are
recovered in the form of an incremental energy charge (Rs/kwh) recovered as per
formulae approved by the Commission.
Commission’s view:
The cost of Power Purchase varies with variation in the cost of coal freight and other
energy sources which is recovered through FPPPA charges. If such FPPPA revisions
are not carried out on quarterly basis, huge burden will get imposed on the consumers
at the time of truing up.
Commission’s view:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Feeder Management system has totally failed. Post of Feeder Managers should be
totally free from the routine work. No sincere efforts have been made towards reduction
of Technical losses.
The Commission has approved distribution loss trajectory for the entire MYT control
period from FY 2016-17 to FY 7020-71. Except PGVCL, other three DISCOMs have
projected same distribution losses as approved by the Commission in MYT Order
dated 31.03.2017, while PGVCL has projected lower distribution losses in the Mid-
Term Review than approved in the MYT Order dated 31.03.2017. Distribution losses
being controllable factor, the Petitioners have given appropriate treatment to the
deviation from approved loss in the true up petition for FY 2017-18. It is also submitted
that as Transmission losses are beyond the control of Distribution Company, the actual
transmission losses are considered by the Petitioners.
Commission’s view:
While appreciating the efforts made by the Petitioners in achieving loss reduction up
to target level, the Commission is of the view that sustained and concerted efforts
should be continued to further reduce the losses than the approved in the MYT Order
dated 31.03.2017.
15. Power purchase ceiling rate
The ceiling rate of power purchase during the year has to be decided along with Tariff.
No response is furnished.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission approves base power purchase cost. Any variation in power
purchase cost due to variation in cost of coal/ other energy sources is recovered
through FPPPA charges to avoid tariff burden at the time of truing up. However, at this
time of true up, the Commission examines the purchase cost on prudent basis and as
per Regulations.
16. Remove the row of Interest on Working Capital from ARR Table and
consider Return on Equity at 12%
The Interest on working Capital is not grantable and the row to be removed from ARR
format. It is also stated that the ROE at 14% is too high. It should be reconsidered and
reduced to 12%.
In true up petition for FY 2017-18, no claim for Interest on working capital is proposed
and RoE is worked out as per the GERC (MYT) Regulations, 2016.
Commission’s view:
As the Petitioners have huge amount of Security Deposit with them, which they use for
Working Capital requirement the Working Capital requirement works out to be negative
and accordingly, interest on Working Capital is not calimed by the Petitioners and
approved as NIL by the Commission. Further, RoE is approved as per provisions of
the GERC (MYT) Regulations, 2016.
No response is furnished.
Commission’s view:
The Commission has after due diligence approved the Power Purchase Cost for FY
2019-20 and 2020-21 considering actual fixed and variable cost of FY 2017-18. The
issue is discussed in the relevant section of Chapter 5 of this Order.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
No response is furnished.
Commission’s view:
Commission’s view:
The Commission has already provided directive to Distribution Utilities to adhere to the
time lines specified in the GERC (SoP) Regulations, 2005 for replacement of faulty
meters.
It is a basic commercial principle for any organization to recover its fixed costs through
recovery of fixed charges. In case of DISCOMs even with the proposed tariff, only 36
% fixed cost is recovered through fixed charges. Therefore it is not possible for
DISCOMs to abolish fixed charges
Commission’s view:
The Commission noted the response of the Petitioners and agrees with the response.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The compliance of directive is submitted to the Commission from time to time. Actual
expenditure incurred under various schemes vis-à-vis approved by the Commission is
provided in the petition.
Commission’s view:
The compliance of directives is discussed in detail in Chapter 7 of this Order where the
Commission’s observation on the compliance is also deliberated in the said Chapter
7.
Petitioners have furnished various activities carried out for loss reduction in JGY
feeders.
Commission’s view:
The Commission is of the view that thorough energy audit need to be carried out on
JGY feeders having higher distribution losses as per the directives issued in previous
tariff orders and as discussed during previous meetings of Co-ordination Forum.
Commission’s view:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The consumer charter is prepared for all categories of consumers including agriculture
consumers.
Commission’s view:
The Commission noted the objection of the Objector and the response of the
Petitioners.
Commission’s view:
The Commission noted the objection of the Objector and response of the Petitioners..
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission has approved the FPPPA formula through its order dated 29.10.2013
and accordingly any incremental power purchase cost compared to base year power
purchase cost would be a Power Purchase Price Adjustment only.
Commission’s view:
The Commission noted the response of the Petitioners and is in agreement with the
same.
Commission’s view:
The Commission, after careful consideration, has decided to delete the provision of
Prompt Payment Discount from the Tariff Schedule to avoid confusion.
The petition is filed for Truing up of FY 2017-18, Mid-Term Review of FY 2019-20 and
FY 2020-21 and Determination of Tariff for FY 2019-20. No tariff increase has been
sought.
Commission’s view:
The Commission, after due diligence and prudence check of financials and submission
of Petitioners, has made certain decisions which are deliberated in Chapter 9 of this
Order.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The consumers of LTP-V/HTP-V category are provided with 24 hours power supply
while agriculture consumers are being provided 8 hours power supply on rotation
basis. As the hours of power supply are different for these categories of consumers, it
is not viable to keep tariff rate same.
Commission’s view:
The tariff rates are decided by the Commission. Prior to year 2001, agriculture
consumers were supplied power without meter. After the year 2001, power supply to
agriculture consumers is supplied with meter and accordingly, electricity bill is prepared
based on readings. Agriculture consumers who are supplied power without meters are
charged based on their contracted demand and such consumers are considered under
A-1 category.
Further, agriculture connections are provided under Normal scheme and Tatkal
scheme. Estimates provided under Normal scheme and Tatkal scheme are also
different and tariff rates for agriculture connections under Normal scheme and Tatkal
scheme are different as decided by the Commission. Agriculture connections provided
under Normal scheme are considered under A-2 category while agriculture
connections provided under Tatkal scheme are considered under A-3 category.
Further, the consumers under Tatkal scheme shall be eligible for normal metered tariff
on completion of five years period from the date of commencement of supply.
Commission’s view:
The Commission has noted the objection of the Objector and the response of the
Petitioners.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
As per Tariff Policy, tariff should be within range of +/- 20% of cost to serve and
therefore, it is not viable to provide any more concession to agriculture consumers.
Commission’s view:
Sick industrial units should be provided with special dispensation in the tariff at
maximum Rs. 4.40 per unit (including all charges but not limited to demand charges,
Time of Use Charge (TOU), Fuel Surcharge, Energy Charges, Meter Charges, P.F.
adjustment/rebate charges, Security Deposit for additional Load etc.). Sick units should
also be given relief to pay cross subsidy (at present it is Rs. 2.51/unit)
Commission’s view:
This issue is being dealt with separately by the Commission in the petition filed by the
Objector.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
similar tariff and there may not be any discrimination, which is also one of the objectives
of the EA 2003.
The four Distribution Companies are incorporated on the basis of zonal configuration.
Since the 80% - 90% of the total cost incurred by DISCOMs is for Power Purchase,
the same plays a major role in determining the Annual Revenue Requirement as well
as Gap / (Surplus) for the DISCOM for a particular year. Since the consumer profile
and consumption profiles are different in the four Distribution Companies, the revenue
earning capabilities of each of the DISCOMs differs resulting in different Annual
Revenue Requirement.
Therefore, it is necessary to build a mechanism to bring them to a level playing field.
This is achieved through differential Bulk Supply tariff (BST) to each of the DISCOMs
which is approved in the MYT Order. In this way, it becomes possible to ensure uniform
retail consumer tariffs in the four DISCOMS. Moreover, performance of all the
Distribution Companies is monitored by the Commission and accordingly Distributions
Loss is approved by the Commission.
Commission’s view:
Response of the Petitioners is self-explanatory.
Commission’s view:
The Commission has taken appropriate decision regarding this in the Tariff Philosophy
chapter of this Order.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission timely reviews performance of Petitioners through data submitted as
part of SoP Reports and RIMs reports and necessary directives are also issued in case
performance is not found satisfactory. Further, during meetings of State Advisory
Committee and State Co-Ordination Forum, such performance parameters are
deliberated. Minutes of the said Meetings along with SoP and RIMs reports are
available on the Commission’s website.
Revenue Gap and distribution losses of PGVCL out of four Petitioners are highest
during 2017-18. It is requested to not to approve any parameter which is above the
limit of approved parameters.
Commission’s view:
The Commission appreciates the efforts being made by the Petitioners in achieving
the target of loss reduction. However, loss reduction activity being continuous,
sustained and concerted efforts should be made to reduce the losses in coming years
also.
All the four Distribution Companies are catering to different mix of consumers having
different characteristics of geographical area. Comparing losses of one DISCOM with
another is not appropriate. Instead, comparison of current year’s performance in loss
reduction activities with that of previous years is more appropriate.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission in the true up orders of previous year did not consider provision made
for salary increase on account of 7th Pay Commission Order and decided to consider
Pay revision at the time of actual pay out. Accordingly, the Commission has considered
the impact of actual pay out of 7th Pay Commission Order.
Commission’s view:
The response of the Petitioner is self-explanatory. However, a separate study on
principles of Merit Order Despatch was conducted and no discrepancies were found in
MoD. The said report was made available to the consumers.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
As explained by the Petitioners, incremental power purchase cost over the base power
purchase cost is to be recovered through FPPPA charges over and above the base
FPPPA charges (i.e. Rs. 1.43/unit for FY 2017-18). Detailed clarification has been
provided in past years Tariff Orders and also in the Chapter 8 of this Order.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
1.49/unit. As per approved FPPPA formula, any increase in power purchase cost
during the year over and above base power purchase cost of Rs. 4.27/unit is to be
recovered through FPPPA over and above base FPPPA of Rs. 1.49/unit on quarterly
basis. As per projected ARR for FY 2019-20, the weighted average power purchase
cost is worked out to Rs.4.34/unit as against earlier approved base power purchase
cost of Rs. 4.22/unit. Thus, the incremental power purchase cost of Rs. 0.12/unit for
FY 2019-20 (i.e. Rs. 4.34 - 4.22) will be recovered through FPPPA over and above
base FPPPA of Rs. 1.49/unit. Therefore, estimated revenue from FPPPA for FY 2019-
20 is considered at Rs. 1.63/unit for FY 2019-20 (i.e. grossing up by approved losses)
and accordingly revenue gap has been worked out.
Commissions’ view:
As explained by the Petitioners, incremental power purchase cost over the base power
purchase cost is to be recovered through FPPPA charges over and above the base
FPPPA charges (i.e. Rs. 1.49/unit for FY 2017-18). Detailed clarification has been
provided in past years Tariff Orders and also in the Chapter 8 of this Order.
Commission’s view:
Electricity Duty is the subject matter of the State Government.
Commission’s view:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission is of view that the issue of source wise planning to purchase power
from renewable sources of energy to meet RPO obligation is very much relevant to this
petition and the Petitioners should have responded in this regard. In this petition, the
Petitioners have furnished source wise planning of purchase of power for FY 2019-20
and FY 2020-21 in the Power Purchase Cost section. The Commission has considered
quantity of purchase of power from renewable sources in accordance with RPO targets
fixed by the Commission.
Commission’s view:
46. To allow 100% of contract demand for rooftop solar for HT consumers
The objector requested to allow 100 % of capacity for rooftop Solar with reference to
contract demand for HT consumers, out of total generation 25 to 35 % generation may
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commissions’ view:
Commissions’ view:
GUVNL has already started procuring renewable energy power through competitive
bidding for four State Owned DISCOMs.
Commissions’ view:
Not to allow RESCO model in GERC (Net Metering Rooftop Solar PV Grid Interactive
Systems) Regulations, 2016 was a decision taken after deliberations and inviting
comments/ suggestion from the stakeholders. However, the Commission is of the view
that this matter is not a part of this Tariff petition.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commissions’ view:
Commissions’ view:
The Commission noted the objection of the Objector. The Commission is of the view
that this matter may be dealt separately and not as a part of this Tariff petition.
Commission’s view:
Power purchase on behalf of all four Discoms is undertaken by GUVNL on the basis
of requirement of each Discom. In the process, the surplus power is sold by GUVNL
on behalf of DISCOMs and proceeds from the sale are passed on to Discom which
ultimately pass on to general mass of consumers.
Commission’s view:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
For the Petitioners to procure power only as per demand of the consumers is difficult
considering the fact that it is not possible to predict exact demand of the consumers.
Further, the Petitioners have to supply power 24x7x365 to consumers as per
provisions of the Electricity Act, 2003. The revenue from sale of power to GUVNL is
reduced from the power purchase cost and thus consumers are given benefit out of
the revenue earned from sale of power by GUVNL.
As per the tariff order of the Commission, FPPPA charge is a part of tariff. In case of
Agricultural consumers, the FPPPA charges payable by the Agriculture consumers is
not recovered from the consumers but it is being compensated by State Government.
Revenue received from Agriculture consumers is mentioned in the Annual Accounts of
the Petitioners for FY 2017-18 which is inclusive of FPPPA subsidy and the subsidy
for tariff compensation from Government for FY 2017-18, as tabulated below;
Similarly, Subsidy received from the State Government towards the Water Works
connections is also mentioned in the Annual Accounts as shown below:
It may be noted that FPPPA subsidy received from State Government and subsidy for
the Water Works connections have been duly considered in the Revenue from Sale of
Power for respective category of consumers both in Annual Accounts of the Company
and also in the True up proposal.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The response of the Petitioners is self-explanatory.
PGCIL and POSOCO charges are applicable in accordance with Order / Regulations
of Hon'ble CERC. PGCIL and GETCO charges and losses both are separate matter
and governed as per the Order/ Regulations of Hon'ble CERC and GERC respectively
and therefore appropriate treatment is given for the losses and charges.
Commission’s view:
GETCO losses are considered to work out total energy requirement and thus, per unit
power purchase cost to determine gain/ loss on account of distribution loss. However,
PGCIL and GETCO Charges are part of power purchase cost, considering distribution
utilities as beneficiaries of State and National transmission system, and thus part of
ARR to determine gap/ surplus of the truing up year.
Return on Equity is claimed as per the relevant provisions of MYT Regulations and as
explained in the petition, for assessing actual return on equity for FY 2017-18,
Company has considered the opening balance of equity of FY 2017-18 equivalent to
the closing balance of equity of FY 2016-17 as approved by the Commission in the
True up order dated 31st March, 2018 and normative addition during FY 2017-18
based on actual capitalization
Commission’s view:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
GERC (MYT) Regulations, 2016, where actual equity employed is more than 30% of
capital cost approved by the Commission, the amount of equity for the purpose of tariff
is limited to 30% and the balance is considered as loan, thereby capping the equity at
30% of the capital cost approved by the Commission.
Commission’s view:
During prudence check of the submission from licensee, whenever required the
Commission asks licensee to provide additional details and clarification and all such
additional information received from licensee in tariff determination exercise are placed
on the Commissions’ website and made it available to all the stakeholders. Non-Tariff
Income is reduced from ARR to work out at Revenue Gap/ Surplus while carrying out
truing up exercise so that consumers get the benefit of the Non-Tariff Income.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The response of the Petitioners is self-explanatory.
This is the suggestion to the Commission and any modification to be made by the
Commission should be revenue neutral to the Company.
Commission’s view:
The Commission has dealt with this issue appropriately in the tariff Schedule attached
to this order.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
While appreciating the efforts of the Petitioners to achieve loss reduction target, the
Commission is of view as part of compliance of directives, where Petitioners have been
submitting identified high loss making JGY feeders and steps to reduce losses of such
feeders, the Petitioners should continue identifying high loss making feeders and target
shall be set for loss reduction and steps should be taken to achieve the set target.
Collection efficiency
DISCOM
(%)
DGVCL 100.08
MGVCL 100.05
PGVCL 100.00
UGVCL 100.00
Commission’s view:
The response of the Petitioner is self-explanatory.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
As explained by the Petitioners, incremental power purchase cost over the base power
purchase cost is to be recovered through FPPPA charges over and above the base
FPPPA charges (i.e. Rs. 1.43/unit for FY 2017-18).
Commission’s view:
PGCIL and GETCO Charges are part of power purchase cost, considering the
distribution utilities as beneficiaries of State and National transmission system, and
thus part of ARR to determine gap/ surplus of the truing up year. SLDC Charges as
shown in A & G expenses in the accounts have been considered in Power Purchase
Cost. GUVNL cost is included in Power Purchase Cost.
63. Quantum of UI/DSM sales not submitted, sale of bulk supply not
considered in energy balance and DSM charges are less and SLDC charges are
different for four DISCOMs.
Details regarding quantum of UI/DSM sales to GUVNL along with UI charges borne by
the petitioners are not submitted. Sale of bulk supply power is also not considered in
energy balance and DSM charges are less. It is also submitted that SLDC charges are
different for four DISCOMs.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
DSM charges depend on system frequency. Treatment of DSM charges i.e. cost and
revenue is given while determining Power Purchase Cost. It is also to mention that
SLDC charges are levied based on contracted capacity which is different in case of
four DISCOMs and therefore, SLDC charges are different. Moreover, sale of bulk
supply in case of PGVCL is sale of power to KPT. It is not considered in energy balance
so as to not distribute power purchase cost of KPT amongst other consumers.
Commission’s view:
The Commission has approved the proposal after prudence check considering
revenue from different sources.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission has always endeavoured to reduce the cross subsidy as provided
under the Electricity Act, 2003 and the Tariff Policy.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
DGVCL has shown written off amount as Extra Ordinary Items as part of O & M
expenses in the Petition and also in the annual accounts.
67. No reason provided for deviation from MYT parameters and CAPEX
The Petitioners have not specified reasons for deviation in Mid-Term Review from MYT
parameters and CAPEX
Commission’s view:
The Commission has approved CAPEX after prudence check in accordance with the
provisions of the GERC (MYT) Regulations, 2016.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission, with an intention of monitoring the progress of implementation of
DSM Programmes, has asked the Petitioners to submit quarterly reports in which
energy saving due to implementation of the DSM Programmes is also included.
69. Tariff Proposal not in accordance with law and incomplete formats
The tariff proposals submitted by the Petitioner is not in accordance with the Electricity
Act, 2003, National Electricity Policy and other notifications. Further, the formats of the
Petitions are not complete.
Commission’s view:
As provided in Tariff Policy, the Commission has to initiate tariff determination exercise
suo-motu in the absence of filing by the licensee or incomplete filing so as to decide
the tariff timely. Information gaps observed, if any, during processing of the petitions
are sought to be made good from the Petitioners and these are placed on the
Commission’s website for the stakeholders to study.
Commission’s view:
The accounts of the Petitioners, being Government owned undertakings, are audited
by the Statutory Auditors appointed by the C & AG. Further, the accounts of the
Petitioners are subject to supplementary audit by the C & AG. Moreover, the C & AG
also conduct issue based performance/ propriety audit of the Petitioners. The
Commission, therefore, does not find any merit in the objector’s submission.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission noted the response of the Petitioners.
Commission’s view:
The response of the Petitioners is self-explanatory.
Commission’s view:
O & M expenses are approved in accordance with relevant provisions of the GERC
(MYT) Regulations, 2016 as detailed in Chapter 4 of this Order.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
----------
Commission’s view:
Delayed Payment Charges is a penalty and cannot be equated with Bank Interest
Rates.
Commission’s view:
Necessary directive to meter all Distribution Transformer Centres has already been
issued and the Commission has periodically reviewed progress made by the
Petitioners in metering Distribution transformers.
76. Allow Bank Guarantee towards Security Deposit and not to levy Security
Deposit from consumers who have pre-paid meters.
The Objector requested to allow Bank Guarantee towards Security Deposit for all the
categories of consumers. It is also requested to refund Security Deposit collected from
consumers when smart pre-paid meters are installed.
Commission’s view:
The said option to furnish Security Deposit in the form of irrevocable Bank Guarantee
is available for the consumers whose Security Deposit exceeds Rs. 25 Lakhs.
However, the Commission is of the view that the matter is related to Regulations on
Security Deposit and may be dealt separately.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
Tariff determination is based on overall Average Cost to Serve. Consumers are being
connected at different voltage level according to their load requirement and as per
relevant provisions of the Electricity Supply Code. Therefore, the Commission is of the
view that consumer being supplied at a certain voltage level by virtue of its load
requirement, Cost of Supply at EHV level is necessary and accordingly directive to
work out Cost of Supply at EHV level was given in past year’s Tariff Order.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Objector has objected against the petition filed by the Petitioner for determination
of tariff for FY 2019-20.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s view:
The Commission has noted the response of the Petitioner. The Commission carries
out tariff determination exercise in accordance with relevant Regulations
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
4 Truing up of FY 2017-18
UGVCL, in its submission for True-up of FY 2017-18, has furnished details of the actual
energy sales, expenditure and revenue, based on the audited annual accounts for FY
2017-18. The Petitioner has stated that the truing up for FY 2017-18 is based on the
comparison of the actual performance of FY 2017-18 with the approved aggregate
revenue requirement for FY 2017-18 in the MYT Order dated 31st March, 2017 to
arrive at the Gain/(Loss), as per the GERC (MYT) Regulations.
The Commission has analysed the components of the actual energy sales, expenses,
revenue and computed Gain/(Loss) in the process of truing up for FY 2017-18.
Commission’s Analysis
The Commission, in the MYT Order, dated 31st March, 2017, had approved the energy
sales of 18946 MUs for FY 2017-18 against which, UGVCL has submitted the actual
sales of 20137 MUs.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
As can be observed from the Table above that the actual energy sales to LT categories
are lower than those approved by the Commission for FY 2017-18 in the MYT Order
dated 31st March, 2017. However energy sales in Industrial HT category is higher by
36.09% than approved in the MYT Order dated 31st March, 2017.
Overall, the actual energy sales of UGVCL is higher by 1191 MUs, against what is
approved in the MYT Order dated 31st March, 2017. As energy sales depend upon
factors, which are related to income level and overall growth of the economy, it remains
largely uncontrollable in nature.
The Commission approves the energy sales of 20137 MUs as detailed in the Table
below:
The Petitioner has submitted that the actual distribution losses for FY 2017-18 are
8.31%, as against the approved losses of 9.90% in the MYT Order dated 31st March,
2017 as given in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Petitioner submitted that as per the GERC (MYT) Regulations, 2016 the
distribution losses need to be treated as controllable and any gain or loss has to be
dealt with, accordingly, as per the provisions of the MYT Regulations.
The Petitioner submitted that it has achieved significant reduction in distribution losses
during recent years and shall continue its efforts to reduce the distribution losses
further.
Commission’s Analysis
UGVCL has contended that the actual distribution losses are 8.31% for FY 2017-18,
as against 9.90% approved in the MYT Order dated 31st March, 2017.
The Commission considers distribution losses as controllable as per the GERC (MYT)
Regulations, 2016. Accordingly, the Commission considers the distribution losses of
9.90% as shown in the Table below for computation of Gain/ (Loss) due to variance in
distribution losses.
UGVCL has submitted the energy requirement for FY 2017-18 based on the actual
energy sales and the actual distribution losses, as given in the Table below.
Table 4-5: Energy requirement and Energy balance as submitted by UGVCL for FY
2017-18
Approved Actual
Sr.
Particulars Unit in the MYT Claimed in
No.
Order Truing up
1 Energy Sales MUs 18946 20137
2 MUs 2082 1824
Distribution Losses
% 9.90% 8.31%
3 Energy Requirement MUs 21028 21961
4 Local Power Purchase by Discom MUs 50
5 Power Purchase at T<>D periphery from GUVNL 21911
5 Transmission Losses MUs 842 853
5 Total Energy to be input to Transmission System MUs 21870 22764
6 Pooled Losses in PGCIL System MUs 336 396
7 Total Energy Requirement MUs 22206 23210
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s Analysis
UGVCL has computed the energy requirement based on the distribution losses of
8.31%, actual energy sales of 20137 MUs and transmission losses of 3.75%
The Commission had approved the distribution losses of 9.90% and the transmission
losses of 3.85% in the MYT Order dated 31st March, 2017.
Accordingly, the Commission has worked out the energy requirement of 23210 MUs
for truing up of FY 2017-18 as shown in the Table below:
Table 4-6: Energy requirement approved by the Commission for truing up for FY
2017-18
Approved Actual Approved
Sr.
Particulars Unit in MYT Claimed in in truing
No.
Order truing up up
1 Energy Sales MUs 18946 20137 20137
2 MUs 2082 1824 1824
Distribution Losses
% 9.90% 8.31% 8.31%
3 Energy Requirement MUs 21028 21961 21961
4 Transmission Losses MUs 842 853 853
Total Energy to be input to
5 Transmission System MUs 21870 22764 22764
6 Pooled Losses in PGCIL System MUs 336 396 396
7 Total energy requirement MUs 22206 23210 23210
Power Purchase Cost given above is the net power purchase cost after considering
the SLDC Charges, net UI/ DSM Charges Payable/Receivable and the revenue from
sale of power to GUVNL. UGVCL has submitted the break-up of actual power purchase
cost incurred during FY 2017-18, as shown in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
UGVCL submitted that the total power purchase cost for FY 2017-18 consists of the
basic power purchase cost, transmission charges payable to GETCO and PGCIL,
SLDC charges and the DISCOM’s share of GUVNL cost.
The quantum of power purchase depends upon sales during the year as well as the
losses in the system. Though the actual distribution losses in UGVCL distribution
network have been lower than the approved level and the sales are higher than that
approved by the Commission and hence, the overall quantum of power purchased was
higher than the approved quantum of power required.
As per the GERC (MYT) Regulations, 2016 the Commission has categorised the
variation in the price of fuel and/or price of power purchase according to the FPPPA
formula approved by the Commission as an uncontrollable factor. Further, the
Commission has also identified the variation in the number or mix of consumers or
quantity of electricity sold to consumers as an uncontrollable factor. Thus, the variation
in these factors affects the power purchase expenses and results into either a loss or
gain. Accordingly, any gain or loss on this account is to be entirely passed on to the
consumers as per the methodology approved by the Commission.
In addition to the above, there is an incidence of lower power purchase cost on account
of the lower Distribution loss as compared to the loss approved by the Commission.
These gain has resulted in lower power purchase expenses as the quantum of power
required to be purchased to meet the same level of demand would be lower hence
resulting in the gain.
The increase or reduction in quantum of power purchase and power purchase cost
due to variation in distribution loss is a controllable factor which would result in
Gain/Loss under the GERC (MYT) Regulations, 2016 and is dealt with accordingly.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s Analysis
The Commission has examined the actual quantum of power purchased and the power
purchase cost during FY 2017-18, based on the actual energy sales and the
distribution losses submitted by UGVCL. The sales and the quantum of power
purchase and the power purchase cost are as per the audited annual accounts for FY
2017-18. The Commission has observed that the Petitioner has, in the audited
accounts included the SLDC charges of Rs. 3.49 Crore in A & G Expenses. Since the
same is a part of Power Purchase Cost, it is reduced from A & G Expenses and
included in the Power Purchase Cost. After addition of SLDC charges of Rs. 3.49
Crore, deduction of Income of Rs. 87.55 Crore towards Sale of Power to GUVNL and
UI/DSM Expenses or Income, the Power Purchase Cost works out to Rs. 9004.23
Crore as shown in the Table below:
Table 4-9: Power Purchase Cost as per the audited accounts for FY 2017-18
(Rs. Crore)
Sr. No. Particulars Amount
1 Power Purchased from GUVNL 9142.76
2 Power Purchased from CPP/Wind Farms 11.04
3 Power Purchased from Solar 22.70
4 UI/DSM Charges (Expense) 5.95
5 SLDC Charges 3.49
6 Total Power Purchase 9185.94
7 Power sold to GUVNL (Income) 87.55
8 UI/DSM Charges (Income) 94.16
9 Net Power Purchase Cost (6-7-8) 9004.23
The Commission approves the power purchase cost of Rs. 9004.23 Crore for FY 2017-
18 as per the audited annual accounts.
Table 4-10: Power Purchase Cost approved by the Commission for truing up for FY
2017-18
(Rs. Crore)
Approved in the Actual Claimed Approved in
Particulars
MYT Order in Truing up Truing up
Total Power Purchase Cost 8866.95 9004.23 9004.23
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
MYT Order dated 31st March, 2017. The gain is considered as controllable variation.
The calculation of gain on account of lower distribution losses as submitted by UGVCL
is shown in the Table below:
Table 4-11: Gain/ (Loss)on account of Distribution Losses for FY 2017-18 as submitted
by UGVCL
With
With Actual
Sr. Approved
Particulars Unit Distribution
No. Distribution
Losses
Losses
1 Energy Sales MUs 20136.78 20136.78
2 MUs 2212.59 1824.28
Distribution Losses
% 9.90% 8.31%
3 Energy Requirement MUs 22349.37 21961.06
4 Saving due to Distribution Losses MUs - 388.31
5 Average Cost of Power Purchase Rs./kWh - 3.88
6 Gain/(Loss) Due to Dist. Losses Rs. Crore - 150.64
Commission’s Analysis
The Commission has approved distribution losses at 9.90% for FY 2017-18 in the MYT
Order dated 31st March, 2017 against which UGVCL has achieved distribution losses
of 8.31%. However, as discussed in Section 4.2, the Commission approves 9.90% as
the distribution loss for truing up of FY 2017-18.
The total Gain / (Loss) on account of lower distribution losses are computed in the
Table below:
Table 4-12: Approved Gain/ (Loss) on account of Distribution Losses for FY 2017-18
(Rs. Crore)
with
Approved
Sl. Approved
Particulars Units for truing
no. Distribution
up
Losses
1 Energy Sales MUs 20136.78 20136.78
2 MUs 2212.59 1824.28
Distribution Losses
% 9.90% 8.31%
3 Energy Requirement MUs 22349.37 21961.06
4 Saving due to Distribution Losses MUs - 388.30
5 Average Power Purchase Cost Rs./Unit - 3.88
6 Gain/(Loss) due to Dist. Losses - 150.64
The total gain on account of lower distribution losses, as computed by the Commission
of Rs. 150.64 Crore is attributable to controllable factors.
While computing the Gain / (Loss) due to change in distribution losses, the
Commission has considered the distribution losses at 9.90% of actual energy sales to
Gujarat Electricity Regulatory Commission Page 54
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
arrive at change in energy requirement at the distribution periphery and did not
consider the transmission losses to factor the efficiency of distribution activities only.
The Commission considered change in power purchase cost as uncontrollable and
attributable to the variation in cost and quantum of power due to variations in sales and
transmission losses, while variations in quantum of power due to distribution losses
are considered as controllable. Accordingly, Gain/Loss computed on account of power
purchase are shown in the Table below:
Table 4-13: Approved gain / (loss) – power purchase expenses for truing up for FY
2017-18
(Rs. Crore)
Gain/(Los
Approve Gain/(Loss)
Approved s) due to
d in Deviatio due to
Particulars in the MYT Controlla
Truing n + (-) Uncontrolla
Order ble
up ble Factors
Factors
Total Power Purchase Cost 8,866.95 9,004.23 (137.28) 150.64 (287.92)
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioner’s submission
UGVCL has compared the O&M expenses actually incurred during FY 2017-18 with
the expenses approved by the Commission in the MYT Order dated 31st March, 2017
and arrived at gain/ (loss) as shown in the Table below:
Table 4-15: O&M Expenses and Gain / Loss claimed in the truing up for FY 2017-18
(Rs. Crore)
Actual Gain/(Loss) Gain/(Loss)
Approved
Sr. Claimed due to due to
Particulars in the MYT
No. in Truing Controllabl Uncontrollabl
Order
up e Factors e Factors
1 Employee Cost 423.58 531.92 (82.56) (25.78)
Repairs & Maintenance
88.50 61.36 27.14
2 Expenses
Administration & General
75.69 99.22 (23.53)
3 Expenses
4 Other Debits - - -
5 Extraordinary Items - -
Net Prior Period Expenses
- -
6 /(Income)
7 Other Expenses Capitalised (144.72) (69.19) (75.53)
8 Total O & M Expenses 443.05 623.31 (78.95) (101.31)
Table 4-16: Employee Cost claimed by UGVCL in the truing up for FY 2017-18
(Rs. Crore)
Gain/(Loss) Gain/(Loss)
Approved Actual
Sr. due to due to
Particulars in the MYT Claimed in
No. Controllable Uncontrollable
Order Truing up
Factors Factors
1 Employee Cost 423.58 531.92 (82.56) (25.78)
Petitioner’s submission
UGVCL has submitted that the actual employee cost for FY 2017-18 was Rs. 531.92
Crore which excludes the provision made towards 7th Pay Commission of Rs. 54.80
but includes the actual amount paid towards 7th Pay Commission of Rs. 25.78 Crore
and Rs. 60.91 Crore of Re-measurement of defined benefits plans. The Commission
in the MYT Order dated 31st March, 2017 and True Up Order of FY 2016-17 dated 31st
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
March, 2018 had not approved the provision made for respective years towards the
impact of 7th Pay Commission considering that actual payment is not made and had
ruled that as and when the actual expenses are incurred, the Commission would
consider such claims, which would be accounted for during the true up of annual
account of the respective year as uncontrollable factor. The employee cost was
incurred on the basis of the guidelines issued by the competent authorities like the
State Government and that the entire expenditure estimated is a legitimate expenditure
and any variation is purely beyond its control. Accordingly, UGVCL has estimated a
loss of Rs. 82.56 Crore on account of controllable factors and Rs. 25.78 Crore on
account of uncontrollable factors.
Commission’s Analysis
UGVCL has compared the actual employee cost of Rs. 531.92 Crore incurred during
FY 2017-18 with Rs. 423.58 Crore approved in the MYT Order dated 31st March, 2017.
The actual employee cost, as per the audited annual accounts for FY 2017-18 is Rs.
525.81 Crore before capitalization of Rs. 59.85 Crore. Further, the Petitioner has
submitted that the aforesaid employee cost excludes Rs. 54.80 Crore towards
Provision for 7th Pay Commission but includes Rs. 25.78 Crore towards the actual
payout on account of wage revision. The Petitioner has added the Re-measurement
of the Defined Benefit Plans of Rs. 60.91 Crore as appearing in the Statement of P&L
for the year ended 31st March, 2018 being the component of employee cost to arrive
at claimed figure of Rs. 531.92 Crore.
Therefore, the Commission considers Rs. 531.92 Crore as employee expenses for the
purpose of true up of FY 2017-18. The Commission considers the employee cost as a
controllable expense, which is in line with the MYT Regulations. Further, the actual
payments towards the 7th Pay Commission of Rs. 25.78 Crore has been considered
as uncontrollable.
The Commission, accordingly, approves the employee cost at Rs. 531.92 Crore in the
truing up for FY 2017-18.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-18: R&M Expenses claimed by UGVCL for the truing up for FY 2017-18
(Rs. Crore)
Approved Actual Gain/(Loss) Gain/(Loss)
Sr. in the Claimed due to due to
Particulars
No. MYT in Truing Controllable Uncontrolla
Order up Factors ble Factors
Repairs & Maintenance
1 88.50 61.36 27.14
Expenses
Petitioner’s submission
UGVCL has submitted that the assets of UGVCL are old and require regular
maintenance to ensure uninterrupted operations. It has been further submitted that
UGVCL has been trying its best to ensure uninterrupted operations of the system by
undertaking necessary expenditure for R&M activities. UGVCL has worked out a gain
of Rs. 27.14 Crore due to controllable factors as provided in the GERC (MYT)
Regulations, 2016.
Commission’s Analysis
The actual R&M expenses incurred during FY 2017-18 are Rs. 61.36 Crore, as per the
audited annual accounts. The Commission has observed that R&M expenditure
incurred by UGVCL is lower than the amount approved in the MYT Order dated 31st
March, 2017. The R&M expenses is a controllable item of expenditure under the GERC
(MYT) Regulations, 2016.
The Commission accepts the contention of UGVCL and accordingly approves the R&M
expenses at Rs. 61.36 Crore in the truing up for FY 2017-18.
Table 4-19: R&M Expenses approved for the truing up for FY 2017-18
(Rs. Crore)
Gain/(Loss) Gain/(Loss)
Approved Approved
Sr. due to due to
Particulars in the MYT in truing
No. Controllable Uncontrolla
Order up
Factors ble Factors
Repairs & Maintenance
1 88.50 61.36 27.14
Expenses
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-20: A&G Expenses claimed by UGVCL in the truing up for FY 2017-18
(Rs. Crore)
Gain/(Loss
Actual Gain/(Loss)
Approved ) due to
Sr. Claimed due to
Particulars in the MYT Uncontroll
No. in Truing Controllabl
Order able
up e Factor
Factors
Administration & General
1 75.69 99.22 (23.53)
Expenses
Petitioner’s submission
UGVCL has submitted that the A&G expenses are categorised as controllable
expenses in the GERC (MYT) Regulations, 2016 and the actual A&G expenses, when
compared with the approved value, resulted in a loss of Rs. 23.53 Crore for FY 2017-
18.
Commission’s Analysis
The Commission verified the audited annual accounts of UGVCL and observed that
actual A&G Expenses as per audited annual accounts is Rs. 171.91 Crore before
Capitalization of Expenses of Rs. 9.34 Crore. It is further observed that this amount
has included Repairs & Maintenance Expenses of Rs. 61.36 Crore, SLDC Charges of
Rs. 3.49 Crore, Bad Debts Written Off of Rs. 0.31 Crore, CSR Expenses of Rs. 0.35
Crore and Provision for Bad & Doubtful Debts of Rs. 7.18 Crore in A & G Expenses.
While the Commission has dealt with the R&M Expenses separately in Para 4.6.1.2
above, SLDC Charges are included in Power Purchase Cost approved at Table 4.9 of
this Order. The Commission has also dealt with the Bad Debts Written Off separately
in this Order. Accordingly, the Commission has excluded these items of expenditure
from A & G Expenses along with CSR Expenses and Provision for Bad & Doubtful
Debts in terms of the GERC (MYT) Regulations, 2016 to arrive at the net A & G
Expenses of Rs. 99.22 Crore and approves the same. The Commission observes that
the actual A&G expenses of Rs. 99.22 Crore is higher than Rs. 75.69 Crore approved
in the MYT Order dated 31st March, 2017 by Rs. 23.53 Crore.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-22: Other Expenses Capitalized as claimed by UGVCL in the truing up for FY
2017-18
(Rs. Crore)
Approved Actual Gain/(Loss) Gain/(Loss)
Sr. in the Claimed due to due to
Particulars
No. MYT in Truing Controllable Uncontrollable
Order up Factors Factors
Other Expenses
(144.72) (69.19) (75.53)
1 Capitalized
Commission’s Analysis
The Commission has observed that the other expenses capitalised represent the
capitalisation of Employee Cost and A&G Expenses, as seen from the annual accounts
for FY 2017-18. The actual other expenses capitalised is Rs. 69.19 Crore, as per the
audited annual accounts for FY 2017-18.
The Commission, accordingly, approves the Other Expenses Capitalised at Rs. 69.19
Crore against Rs. 144.72 Crore approved in the MYT Order dated 31st March, 2017.
The Commission allows Rs. 75.53 Crore as loss due to uncontrollable factors as shown
in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-23: Other Expenses Capitalized approved in the truing up for FY 2017-18
(Rs. Crore)
Approved Gain/(Loss) Gain/(Loss)
Approved
Sr. in the due to due to
Particulars in truing
No. MYT Controllable Uncontrollabl
up
Order Factors e Factors
Other Expenses
1 (144.72) (69.19) (75.53)
Capitalized
The total O&M expenses approved in the truing up for FY 2017-18 and the Gain /
(Loss) due to controllable and uncontrollable factors are detailed in the Table below:
Table 4-24: Approved O&M expenses and Gain / Loss in the truing up for FY 2017-18
(Rs. Crore)
Actual Gain/(Los Gain/(Loss
Approved
Claimed Approved s) due to ) due to
in the Deviation
Particulars in in truing Controlla Uncontroll
MYT + (-) (2-4)
Truing up ble able
Order
up Factors Factors
1 2 3 4 5 6 7
Employee Cost 423.58 531.92 531.92 (108.34) (82.56) (25.78)
Repairs & Maintenance
88.50 61.36 61.36 27.14 27.14
Expenses
Administration &
75.69 99.22 99.22 (23.53) (23.53)
General Expenses
Other Debits - - - -
Extraordinary Items - - - -
Net Prior Period
- - - -
Expenses /(Income)
Other Expenses
(144.72) (69.19) (69.19) (75.53) (75.53)
Capitalised
Total O & M Expenses 443.05 623.31 623.31 (180.26) (78.95) (101.31)
Actual
Approved in
Particulars Claimed in Deviation
the MYT Order
Truing up
Distribution Schemes
Normal Development Scheme 175.00 241.70 (66.70)
System Improvement Scheme 35.00 24.54 10.46
HVDS in selected sub-division 5.50 4.93 0.57
Underground cables 100.00 0.07 99.93
Plan Load management Transformer 4.00 0.00 4.00
Others (VDS) 0.65 1.02 (0.37)
Gujarat Electricity Regulatory Commission Page 61
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Actual
Approved in
Particulars Claimed in Deviation
the MYT Order
Truing up
Total 320.15 272.26 47.89
Rural Electrification Schemes Plan -
TASP (Wells) & Petapara 35.00 22.65 12.35
Scheduled Caste Sub Plan(Wells) 5.00 0.16 4.84
Scheduled Caste Sub Plan(lighting) 3.00 1.63 1.37
Electrification of Hutments 5.00 12.21 (7.21)
Kutir Jyoti Scheme 0.50 59.25 (58.75)
Dark Zone 150.00 90.18 59.82
Sagarkhedu 4.50 2.03 2.47
Solar home light 25.00 0.00 25.00
Total 228.00 188.11 39.89
Central Government Schemes- Plan
DDUJGY 60.00 43.65 16.35
R-APDRP Part A 2.05 0.00 2.05
IPDS 51.00 40.77 10.23
SCADA Part A 0.21 7.54 (7.33)
SCADA Part B 0.00 1.14 (1.14)
Smart Grid 14.00 3.46 10.54
Total 127.26 96.56 30.70
Other Schemes (Non Plan) -
RE (Tatkal) 6.00 6.05 (0.05)
AG Normal (SPA) 60.00 45.50 14.50
Energy Conservation 0.10 0.08 0.02
Total 66.10 51.63 14.47
Other New Schemes
Automation and Computerization 4.35 0.00 4.35
Civil Work / New Building 16.00 0.06 15.94
GIS in Cities 0.20 3.44 (3.24)
Other Schemes (Earthing) 0.87 0.00 0.87
Other Repairing Work/Civil Work 2.00 1.26 0.74
New Furniture and Fixtures 2.00 0.00 2.00
Vehicles 0.50 1.79 (1.29)
DSM 2.00 0.71 1.29
DISS 10.00 0.00 10.00
Solar Pump 5.00 13.49 (8.49)
Total 42.92 20.75 22.17
Capital Expenditure Total 784.43 629.31 155.12
Petitioner's Submission
UGVCL has submitted that the actual capital expenditure incurred during FY 2017-18
is Rs. 629.31 Crore which is lower by Rs. 155.12 Crore than what was approved in the
MYT Order dated 31st March, 2017. UGVCL has explained the scheme wise deviation
in the capital expenditure as below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
than envisaged, therefore, company had to incur Rs. 241.70 Crore against
approved Rs. 175.00 Crore.
4. Other (VDS) Scheme: Agriculture Voluntary disclosure scheme (AG VDS) was
announced in year 2017-18. Expenditure of Rs. 1.02 Crore is incurred for releasing
the load of Agriculture connection under the scheme.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
during 2017-18. Further, payment shall be made to M/s Chemtrols based on the
achievement of the milestones of this turnkey project.
7. Smart Grid Project: The broad scope of the pilot project is (1) AT&C Loss
Reduction (2) Peak Load Management, (3) AMI for Industrial, commercial &
residential consumers, (4) Outage Management and (5) Demand Side
Management and Demand Response and ToU tariff for consumers. The PO was
awarded to M/s Genus power in June-17. M/s Genus has started activity like site
survey, consumer details gathering after 3 months and mobilization advance has
been given to M/s Genus in Dec-17. The actual cost incurred is Rs. 3.46 Crore
against approved cost of Rs. 14.00 Crore. The timeline for completion of the
project is 18 months and M/s Genus has started hardware and meter purchasing
after Apr-18. So only Rs. 3.46 Crore has been expend during 2017-18. At present,
total 20358 single phase and 2021 three phase meters are installed. Control room
hardwares are installed and only MDM software application work is in process.
8. High Voltage Distribution System (HVDS): The Company is having large nos.
of Low Tension category consumers. To eliminate low voltage distribution and to
have better voltage profile as well as for reduction of technical loss and associated
commercial loss, the Company has proposed to shift over on High Voltage
Distribution System by erecting small capacity transformers matching with the
connected load of individual consumer or very small group of consumers in a
phased manner. The Company has started to do some of the work on its own. The
Company is desirous to implement HVDS scheme in its distribution area and shall
endeavour to achieve the approved target. The cost is decreased with reference
to the approved due to as the L.T. network has been reduced year by year.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
10. Demand Side Management: Government of Gujarat has been started domestic
efficient lighting programme. This programme is implemented by EESL at Gujarat
to provide energy efficient 9W LED lighting for grid connected consumers in the
state of Gujarat on 26.05.2016 for General Lighting Purpose (GLP), Manufacturing
and Service Industries (MSI) and Residential Category consumers of DISCOM in
the entire operational area after approval of Hon'ble Commission. At present Up
to March-2018, Total 79.50 lacs of 9W LED bulb have been sold in UGVCL
licensee area. The claim may be raised by EESL during this Year. The combo
project of replacement of 50W five star rated energy efficient fan and 20W LED
tube light has been started by Government of Gujarat for grid connected
consumers in the state of Gujarat on 26.01.2017. Hence UGVCL has projected 2
Crore, for F.Y. 2019-20 and F.Y. 2020-21. This programme is also implemented
by EESL at Gujarat. At present Up to March-2018, Total 2.65 lacs of 20W LED
tube light and 1.62 lac of 50W five star rated energy efficient fan has been sold in
UGVCL licensee area. No any ongoing Project at present in this activity, but
expenditure is done as per Invoice received from EESL of “UJALA Gujarat”
project, hence total approved amount is not used.
11. Din Dayal Upadhyay Gramin Jyoti Yojna (DDUGJY): It is to state that, under
this scheme various activities were covered like New Feeder / Feeder Bifurcation,
LT Line Augmentation, Aerial Bunch Cables, Consumer Meter Replacement, New
Connections, HVDS etc. DPR was submitted in March – 2015 based on the SOR
rate which was approved in May – 2016. Funding mechanism for the said scheme
is 60% grant from REC and 40% from own fund. Hence, considering the same,
Capital Expenditure was proposed. Further, for the proposed work, tenderization
process done by respective field offices and letter of award given to contractors.
Based on the actual labour and supply rate expenditure was booked, which was
less than the proposed rate of DPR. Hence, actual capital expenditure is
decreased from Rs. 60.00 Crore to Rs. 43.65 Crore due to actual execution of
work based on the rates of supply and labour work orders, even though progress
of scheme was 72%.
12. Integrated Power Development Scheme (IPDS): It is to state that, under this
scheme various activities were covered like New Feeder / Feeder Bifurcation,
Underground Cable work, Distribution Transformers, LT Line Augmentation, Aerial
Bunch Cables, Consumer Meter Replacement, New Connections, HVDS etc. DPR
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
was submitted in February – 2015 based on the SOR rate which was approved in
Mar – 2016. Funding mechanism for the said scheme is 60% grant from REC and
40% from own fund. Hence, considering the same, Capital Expenditure was
proposed. Further, for the proposed work, tenderization process done by
respective field offices and letter of award given to contractors. Based on the
actual labour and supply rate expenditure was booked, which was less than the
proposed rate of DPR. Further, for the partial turnkey work of overhead to
underground network electrification work, AT was issued in June-18 which covers
work of almost Rs. 27.0 Crore. Hence, actual capital expenditure is decreased
from Rs. 51.00 Crore to Rs. 40.77 Crore due to actual execution of work based on
the rates of supply and labour work orders, even though progress of scheme was
62%.
Commission’s Analysis
The capital expenditure approved in MYT Order dated 31st March, 2017 for FY 2017-
18 is Rs. 784.43 Crore. The actual capital expenditure incurred is Rs. 629.31 Crore,
which is lower by Rs. 155.12 Crore than the CAPEX approved in the MYT Order dated
31st March 2017.
The Commission observed that there is good growth in terms of number of consumers
and load and therefore there is an increase in expenditure under the Normal
Development scheme as compared to the amount approved in the MYT, the company
incurred Rs. 241.70 Crore as against 175.00 Crore approved. In the underground cable
work as the necessary DPR was not approved there was no expenditure. Further it is
observed that in IPDS and DDUGJY capital expenditure was less than the planned
expenditure by Rs. 10.23 Crore and Rs. 16.35 Crore respectively. UGVCL submitted
that very little work like capital expenditure on replacement of single phase meters and
SMC box replacements was carried and as a result capex booking against projection
is less.
The Commission further observed that actual expenditure was less than the target
expenditure as work performed in schemes like HVDS in selected s/dn and TAPS
(Wells) was less than targeted work. UGVCL has submitted that expenditure under
electrification of hutments and kutirjyoti scheme was Rs. 12.21 Crore and Rs. 59.25
Crore respectively.
The Commission also looked at ‘Dark Zone ‘ scheme and observed that expenditure
under this scheme was Rs. 90.18 Crore as compared to approved expenditure of Rs.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
150.00 Crore, the actual average cost per Ag well is decreased even though physically
100% Agriculture well target was completed.
The Commission also observed that UGVCL has incurred capital expenditure under
Scheme for Solar Pumps and DSM.
The Commission further observed that most of the capital expenditure schemes by the
DISCOMs are of continuous and on-going nature. These are based on yearly targets
set for meeting the supply obligation, providing quality and reliable power to the
consumers, reduction in losses, release of agriculture connections, etc. Generally,
there are no pre-defined timelines as the schemes are further bifurcated into various
works under the scheme. Nevertheless, the licensee shall be more realistic in
projecting the capital expenditure.
The Commission, verified the audited annual accounts of UGVCL and has
observed that UGVCL has incurred actual capital expenditure of Rs. 629.31
Crore and the capitalisation of Rs. 672.04 Crore. The Commission, therefore
approves the same in the truing up for FY 2017-18.
Table 4-26: Proposed Capitalisation and sources of funding by UGVCL for FY 2017-18
(Rs. Crore)
Approved for Claimed in
Sr.
Schemes 2017-18 in MYT truing up for
No.
Order 2017-18
1 Capitalization 784.43 672.04
2 Less: Consumer Contribution 89.95 117.84
3 Less: Grants 277.10 33.36
4 Balance CAPEX 417.38 520.84
5 Debt @ 70% 292.17 364.59
6 Equity @ 30% 125.21 156.25
Commission’s Analysis
It is observed that UGVCL has claimed the funding of Capitalization net of Consumer
Contribution and Govt. Grant through mix of Debt and Equity by observing the 70:30
ratio as provided in the GERC (MYT) Regulations, 2016.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission has noted that under Government Grants and Consumer
Contribution MGVCL has considered Rs. 33.36 Crore and Rs. 117.84 Crore
respectively, which are in conformity with audited annual accounts for FY 2017-18.
The CAPEX, therefore, approves the funding of Capitalization as given in the Table
below:
Table 4-27: Approved Capitalisation and sources of funding in the truing up for FY
2017-18
(Rs. Crore)
Approved in Actual Approved
Sr.
Schemes the MYT Claimed in for Truing
No.
Order Truing up up
1 Capex 784.43 629.31 629.31
2 Capitalization 784.43 672.04 672.04
3 Less: Consumer Contribution 89.95 117.84 117.84
4 Less: Grants 277.10 33.36 33.36
5 Balance Capitalization 417.38 520.84 520.84
6 Debt @ 70% 292.17 364.59 364.59
7 Equity @ 30% 125.21 156.25 156.25
4.6.3 Depreciation
UGVCL has claimed Rs. 262.25 Crore towards depreciation in the truing up for FY
2017-18 against the depreciation of Rs. 331.74 Crore approved in the MYT Order
dated 31st March, 2017.
Petitioner’s submission
The Petitioner submitted that it had been charging the Depreciation on the fixed assets
of the Company, on the useful life of the assets at the rates prescribed under Schedule
XIV to the Companies Act, 1956. The Company being engaged in the business of
Electricity Distribution, the provisions of the Electricity Act, 2003 would be applicable
and would supersede the provisions of the Companies Act, 2013.
While claiming Depreciation UGVCL has quoted the provisions of the GERC (MYT)
Regulations, 2016 and the directives given by the Commission in the MYT Order dated
31st March, 2017 as given hereunder:-
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-28: Fixed assets & depreciation computed by UGVCL for FY 2017-18
(Rs. Crore)
Sr. Approved in Actual Claimed
Particulars
No. MYT Order in Truing up
1 Gross Block at the Beginning of the year 6019.33 4223.75
2 Additions during the Year (Net) 784.43 672.04
3 Depreciation for the Year 331.74 262.25
4 Average Rate of Depreciation 5.17% 5.75%
UGVCL has further submitted that actual depreciation for FY 2017-18, as against the
value approved in the MYT, resulted in a net uncontrollable gain of Rs. 69.49 Crore as
shown in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-29: Gain / Loss due to deprecation claimed in the truing up for FY 2017-18
(Rs. Crore)
Gain/(Loss) Gain/(Loss) due
Approved Actual
due to to
Particulars in MYT Claimed in
Controllable Uncontrollable
Order Truing up
Factors Factors
Depreciation 331.74 262.25 69.49
Commission’s Analysis
It is observed that the Petitioner has taken Opening GFA as per Audited accounts
which is readjusted as per Ind AS. However, the Commission has considered the
Opening Balance of GFA as per last true up for FY 2016-17 and accordingly the
Closing Balance of GFA as on 31.03.2017 has been considered as Opening Balance
of GFA as on 1.04.2017.
The net addition during the year of Rs. 672.04 Crore is confirmed from the audited
annual accounts for FY 2017-18. The depreciation as per P&L Account for FY 2017-
18 is Rs. 262.25 Crore.
The Commission, accordingly, approves Depreciation at Rs. 262.25 Crore in the
truing up for FY 2017-18 as shown in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-31: Gain / Loss due to Depreciation approved in the truing up for FY 2017-18
(Rs. Crore)
Gain/(Loss) Gain/(Loss)
Approved Approved
due to due to
Particulars in the MYT in truing
Controllabl Uncontrollable
Order up
e Factors Factors
Depreciation 331.74 262.25 69.49
Table 4-32: Interest and Finance Charges claimed by UGVCL in the truing up for FY
2017-18
(Rs. Crore)
Approved in the Actual Claimed
Particulars Deviation
MYT Order in Truing up
Interest and Finance Charges 136.61 127.71 8.90
Petitioners’ submission
UGVCL has submitted that for assessing the actual Interest charges on loans in FY
2017-18, they have considered Opening Balance of loans for FY 2017-18 same as the
Closing Balance of Loans approved by the Commission for FY 2016-17 in the Tariff
Order dated 31st March, 2018. The loan addition in FY 2017-18 is computed at Rs.
364.59 Crore towards funding of CAPEX for FY 2017-18. As per the GERC (MYT)
Regulations, 2016 repayment during the year has been considered equal to the
depreciation for the financial year.
UGVCL has considered the weighted average rate of interest of 8.54% as against
7.27% approved in the MYT Order dated 31st March, 2017 for FY 2017-18.
In addition to the above, UGVCL has considered the interest on security deposits as
per the provisions of the GERC (MYT) Regulations, 2016. The details of interest and
finance charges claimed by UGVCL are as given in the Table below:
Table 4-33: Interest and Finance Charges claimed by UGVCL in the truing up for FY
2017-18
(Rs. Crore)
Approved Actual
Sr.
Particulars in the MYT Claimed in Deviation
No.
Order Truing up
1 Opening Loans 603.62 560.29
2 Additions during the year 292.17 364.59
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Approved Actual
Sr.
Particulars in the MYT Claimed in Deviation
No.
Order Truing up
3 Repayment during the year 331.74 262.25
4 Closing Loans 564.05 662.63
5 Average Loans 583.84 611.46
6 Interest on Loan 42.44 52.23 (9.79)
7 Interest on Security Deposit 93.33 75.48 17.85
8 Guarantee Charges 0.83 - 0.83
9 Total Interest & Finance Charges 136.61 127.71 8.89
10 Weighted Average Rate of Interest 7.27% 8.54%
UGVCL has further submitted that interest and finance charges are categorised as
uncontrollable as per the GERC (MYT) Regulations, 2016 and accordingly worked out
deviation in the actual vis-à-vis the approved expenses under uncontrollable factors,
as given in the Table below:
Table 4-34: Gain / (Loss) claimed due to Interest & Finance Charges for FY 2017-18
(Rs. Crore)
Gain/(Loss Gain/(Loss) due
Approved Actual
) due to to
Particulars in the MYT Claimed in
Controllab Uncontrollable
Order Truing up
le Factors Factors
Interest and Finance
136.61 127.71 8.90
Charges
Commission’s Analysis
The Commission observed that the Closing Balance of Loans approved in true up
Order for FY 2016-17 is Rs. 560.29 Crore and the same has to be taken as the Opening
Loans Balance for FY 2017-18.
The capitalisation and funding of CAPEX have been approved for FY 2017-18, as per
Table 4.27 of this Order.
The normative addition of loans during FY 2017-18 has been considered at Rs. 364.59
Crore as approved in Table 4.27 of this Order. The interest on security deposits of Rs.
75.48 Crore is as per audited accounts for FY 2017-18.
The repayment of loan is Rs. 262.25 Crore in the truing up for FY 2017-18, which is
equivalent to the depreciation, approved in Table 4.30 of this Order. The guarantee
charges and other finance charges, as per audited accounts for FY 2017-18 are Rs.
Nil.
UGVCL has submitted details of the actual loan portfolio and the rate of interest
applicable for each loan portfolio for FY 2017-18. The Commission has worked out the
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-35: Interest and Finance Charges approved by the Commission in the truing up
for FY 2017-18
(Rs. Crore)
Sr. Approved in the MYT Approved in Truing
Particulars
No. Order up
1 Opening Loans 603.62 560.29
2 Additions during the year 292.17 364.59
3 Repayments during the year 331.74 262.25
4 Closing Loans 564.04 662.63
5 Average Loans 583.84 611.46
6 Interest on Loan 42.44 60.92
7 Interest on Security Deposit 93.33 75.48
8 Guarantee Charges 0.83 -
9 Total Interest & Finance Charges 136.60 136.40
10 Weighted Average Rate of Interest 7.27% 9.96%
The Commission, accordingly, approves the interest and finance charges at Rs. 136.40
Crore in the truing up for FY 2017-18.
As per the GERC (MYT) Regulations, 2016, the Commission is of the view that the
parameters which impact interest and finance charges should be treated as
uncontrollable. The Commission, accordingly, approves the Gain / Loss on account of
interest and finance charges in the truing up for FY 2017-18, as detailed in the Table
below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-37: Interest on Working Capital claimed by UGVCL in the truing up for FY
2017-18
(Rs. Crore)
Approved in the Actual Claimed in
Particulars
MYT Order Truing up
Interest on Working Capital - -
Petitioner’s submission
UGVCL has submitted that working capital has been calculated and the rate of interest
is considered as the rate equal to the weighted average of the 1 year MCLR of State
Bank of India during the year plus 250 basis points, as per the GERC (MYT)
Regulations, 2016. This rate works out to 10.50%.
The detailed computation of Working Capital requirement as per the provisions of the
GERC (MYT) Regulations, 2016 and interest on working capital is as given in the Table
below:
Table 4-38: Interest on working capital claimed by UGVCL in the truing up for FY
2017-18
(Rs. Crore)
Approved Actual
Sr.
Particulars in the MYT Claimed in
No.
Order Truing up
1 O&M Expenses 36.92 52.00
2 Maintenance Spares 60.19 42.00
3 Receivables 816.28 827.00
4 Less: Amount held as Security Deposit from Consumers 1,204.28 1,200.00
5 Total Working Capital (290.89) (279.00)
6 Rate of Interest on Working Capital 11.70% 10.50%
7 Interest on Working Capital - -
Commission’s Analysis
The Commission has examined the computation of normative working capital under
the GERC (MYT) Regulations, 2016. The working capital requirement works out to be
negative during FY 2017-18. As the working capital requirement works out to be
negative, there cannot be any interest on working capital. Accordingly, neither any
interest is claimed by UGVCL nor any interest is approved by the Commission.
The detailed computation of the Working Capital and interest thereon is given in the
Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-39: Interest on working capital approved in the truing up for FY 2017-18
(Rs. Crore)
Actual Approved
Sr.
Particulars Claimed in in Truing
No.
Truing up up
1 O&M Expenses 52.00 51.94
2 Maintenance Spares 42.00 56.81
3 Receivables 827.00 827.40
4 Less: Amount held as Security Deposit from Consumers 1,200.00 1,200.10
5 Total Working Capital (279.00) (263.95)
6 Rate of Interest on Working Capital 10.50% 10.50%
7 Interest on Working Capital - -
The Commission, accordingly, approves the interest on working capital as Nil in the
truing up for FY 2017-18.
Table 4-40: Bad Debts claimed by UGVCL in the truing up for FY 2017-18
(Rs. Crore)
Sr. Approved in the Actual Claimed in
Particulars
No. MYT Order Truing up
1 Bad Debts Written Off 0.70 0.31
Petitioner’s submission
UGVCL submitted that comparison of the actual Bad Debts Written Off with the amount
approved in the MYT Order dated 31st March, 2017 resulted in a gain of Rs. 0.39 Crore
on account of controllable factors, as shown in the Table below:
Commission’s Analysis
The Commission has observed that UGVCL has claimed Rs. 0.31 Crore towards Bad
& Doubtful Debts Written off during FY 2017-18.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission verified from the audited annual accounts that UGVCL has made a
provision of Rs. 7.18 Crore for bad debts and has also written off Rs. 0.31 Crore
towards Bad & Doubtful Debts. Regulation 94.9 of the GERC (MYT) Regulations, 2016
specifies that the Commission may allow bad debts written off as a pass through in the
aggregate revenue requirement subject to prudence check. The Commission notes
that the Provision for Bad & Doubtful Debts is towards the future write offs and
accordingly, the actual write offs only are considered as a pass through in the ARR as
per the GERC (MYT) Regulations, 2016.
The Commission, therefore, approves Rs. 0.31 Crore towards bad and doubtful debts
written off in the truing up for FY 2017-18.
The deviation on account of bad debts written off is Rs. 0.39 Crore and the Commission
considers the same as gain due to controllable factors, as detailed in the Table below:
Table 4-42: Gain/ (Loss)due to Bad Debts approved in the Truing up for FY 2017-18
(Rs. Crore)
Gain/(Loss
Gain/(Loss)
Approved Approved ) due to
Sr. due to
Particulars in the MYT in Truing Uncontroll
No. Controllable
Order up able
Factors
Factors
1 Bad Debts Written Off 0.70 0.31 0.39
UGVCL has claimed Rs. 179.73 Crore towards return on equity in the truing up for FY
2017-18 as against Rs. 181.11 Crore approved in the MYT Order dated 31st March
2017, as given in the Table below:
Table 4-43: Return on Equity claimed by UGVCL in the truing up for FY 2017-18
(Rs. Crore)
Approved in the Actual Claimed in
Particulars
MYT Order Truing up
Return on Equity 181.11 179.73
Petitioner’s submission
UGVCL has computed return on equity considering the rate of 14% on the average of
opening and closing equity, taking into account the additions during the year as given
in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-44: Return on Equity claimed by UGVCL in the truing up for FY 2017-18
(Rs. Crore)
Sr. Approved in the Actual Claimed
Particulars
No. MYT Order in Truing up
1 Opening Equity 1231.02 1205.68
2 Additions during the year 125.21 156.25
3 Closing Equity 1356.23 1361.93
4 Average Equity 1293.63 1283.81
5 Rate of Return on the Equity 14% 14%
6 Return on Equity 181.11 179.73
Commission’s analysis
UGVCL has furnished the Opening Equity of Rs. 1205.68 Crore for FY 2017-18 and
submitted Equity addition as Rs. 156.25 Crore during FY 2017-18. The actual Opening
Equity as on 01.04.2017 was Rs. 1205.68 Crore being the Closing Balance of Equity
approved in the True Up for FY 2016-17.The Commission has approved the normative
Equity addition of Rs. 156.25 Crore in Table 4.27 of this Order
The Commission has computed the Return on Equity in the truing up for FY 2017-18
considering the rate of 14% as provided in the GERC (MYT) Regulations, 2016 as
detailed in the Table below:
The Commission approves the Return on Equity at Rs. 179.73 Crore in the truing
up for FY 2017-18.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-46: Approved Gain / Loss due to Return on Equity in the truing up for FY
2017-18
(Rs. Crore)
Gain/(Loss) Gain / (Loss)
Approved Approved
due to due to Un
Particulars in the MYT in Truing
Controllable controllable
Order up
Factors Factors
Return on Equity 181.11 179.73 0 1.37
4.6.8 Taxes
UGVCL has claimed Rs. 14.38 Crore towards income tax for FY 2017-18, as against
Rs. 17.14 Crore approved in the MYT Order dated 31st March, 2017, as given in the
Table below:
Petitioner’s submission
UGVCL has submitted that income tax being a statutory expense, any variation on this
account is uncontrollable. UGVCL has claimed a gain of Rs. 2.76 Crore on this
account, as given in the Table below:
Table 4-48: Gain / (Loss) claimed due to provision for taxes for FY 2017-18
(Rs. Crore)
Approved Actual Gain /(Loss) Gain / (Loss)
in the Claimed due to due to Un
Particulars
MYT in Truing Controllable Uncontrollable
Order up Factors Factors
Income Tax (MAT) 17.14 14.38 2.76
Commission’s Analysis
The Commission has obtained the copies of the Challans of Tax payer’s counterfoil,
26 AS and also verified from the audited annual accounts of the company and found
that the licensee has paid/provided income tax of Rs. 14.38 Crore.
The Commission, accordingly, approves the Income Tax of Rs. 14.38 Crore in the
truing up for FY 2017-18.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 4-49: Approved Gain / Loss due to tax in the truing up for FY 2017-18
(Rs. Crore)
Approved Gain /(Loss) Gain / (Loss)
Approved
in the due to due to
Particulars in Truing
MYT Controllable Uncontrollable
up
Order Factors Factors
Tax on Income 17.14 14.38 2.76
UGVCL has claimed the actual Non-Tariff Income at Rs.138.68 Crore in the truing up
for FY 2017-18, as against Rs. 146.76 Crore approved in the MYT Order dated 31st
March 2017, as detailed in the Table below:
Table 4-50: Non-Tariff Income claimed by UGVCL in the truing up for FY 2017-18
(Rs. Crore)
Approved in the MYT Actual Claimed in
Particulars
Order Truing up
Non-Tariff Income 146.76 138.68
Petitioner’s submission
The Petitioner has Claimed the actual Non-Tariff Income of Rs. 138.68 Crore, as
against Rs. 146.76 Crore approved in the MYT Order dated 31st March, 2017. This has
resulted in a uncontrollable gain of Rs. 8.08 Crore, as detailed in the Table below:
Table 4-51: Gain / (Loss) claimed due to Non-Tariff Income for FY 2017-18
(Rs. Crore)
Actual Gain /(Loss) Gain / (Loss)
Approved
Claimed due to due to Un
Particulars in the MYT
in Truing Controllable Uncontrollable
Order
up Factors Factors
Non-Tariff income 146.76 138.68 8.08
Commission’s Analysis
The Commission observed that as per audited annual accounts the Non-Tariff Income
is Rs. 139.78 Crore which includes interest on staff loans (Rs. 1.10 Crore) for FY 2017-
18.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission, approves the Non-Tariff Income at Rs. 138.68 Crore after negating
the interest on staff loan of Rs. 1.10 Crore in the truing up for FY 2017-18.
The deviation in non-tariff income is considered as uncontrollable. The Commission,
accordingly, approves the Gain / losses on account of non-tariff income in the truing
up for FY 2017-18, as detailed in the Table below:
Table 4-52: Approved Gain / losses due to Non-Tariff Income in the truing up for FY
2017-18
(Rs. Crore)
Gain
Approved Gain / (Loss)
Approve /(Loss)
in the due to Un
Particulars d in due to
MYT Uncontrollable
Truing up Controllab
Order Factors
le Factors
Non-Tariff income 146.76 138.68 8.08
Commission’s Analysis
The Commission has verified the total revenue for FY 2017-18 from the audited
accounts. The actual revenue from category-wise sales, as per audited accounts, is
Rs. 9311.51 Crore. This includes the revenue from sale of power to GUVNL of Rs.
87.55 Crore and DSM charges Income of Rs. 94.16 Crore. Since these have been
adjusted against the power purchase cost for the FY 2017-18, as shown in Table 4.9
of this Order, the net revenue from sale of power works out to Rs. 9129.81 Crore.
It is further observed that other operating income as per audited annual accounts is
Rs. 825.49 Crore, which includes Rs. 26.49 Crore towards Delayed Payment Charges
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
and Rs. 542.26 Crore towards Agriculture Subsidy. After excluding these two
elements, the other consumer related income works out to of Rs. 256.74 Crore
The Commission has considered Agriculture Subsidy separately while Delayed
Payment Charges Income and Delayed Payment Charges Expenditure are not
considered as per the GERC (MYT) Regulations, 2016.
The aforesaid Agriculture Subsidy has been claimed as a separate item of revenue.
The Commission, accordingly, approves the total revenue of Rs. 9928.81 Crore,
including consumer related income of Rs. 256.74 Crore and Agriculture Subsidy
of Rs. 542.26 Crore in the truing up for FY 2017-18.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
23.1 The approved aggregate gain or loss to the Generating Company or Transmission
Licensee or SLDC or Distribution Licensee on account of uncontrollable factors shall
be passed through as an adjustment in the tariff of the Generating Company or
Transmission Licensee or SLDC or Distribution Licensee over such period as may be
specified in the Order of the Commission passed under these Regulations.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
23.3 Nothing contained in this Regulation 23shall apply in respect of any gain or loss
arising out of variations in the price of fuel and power purchase, which shall be dealt
with as specified by the Commission from time to time.
Regulation 24. Mechanism for sharing of Gain or Loss on account of controllable
factors
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioner’s Submission
The Petitioner submitted that the Commission in the MYT Order dated 31st March,
2017 has approved Aggregate Revenue Requirement of Rs.9830.54 Crore for FY
2017-18.
As per the mechanism specified in the GERC (MYT) Regulation 2016, UGVCL propose
to pass on a sum of 1/3rd of total gain on account of controllable factors i.e. Rs. 24.03
Crore out of Rs. 72.08 Crore and total loss on account of uncontrollable factors i.e. Rs.
(314.79) Crore to the consumers.
The past revenue (Gap) / Surplus of Rs. 126.99 Crore, for FY 2015-16 is also adjusted
in the approved Aggregate Revenue Requirement. Accordingly, UGVCL has arrived at
the revised Aggregate Revenue Requirement for FY 2017-18 at Rs. 9994.31 Crore as
shown in above Table.
This revised Aggregate Revenue Requirement is compared against the revised income
under various heads including Revenue with Existing Tariff of Rs. 9129.81 Crore, Other
Consumer related Income of Rs. 256.74 Crore and Agriculture Subsidy of Rs. 542.26
Crore. GUVNL profit of Rs. 126.05 Crore for FY 2017-18 is allocated amongst four
DISCOMs with UGVCL’s share being Rs. 30.98 Crore. Accordingly, the Total Revenue
considering all these elements works out to Rs. 9959.79 Crore. Revenue Gap of
UGVCL for FY 2017-18 after considering all the above adjustments is computed at Rs.
34.52 Crore.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s Analysis
The Commission compared the actual performance of UGVCL with the values
approved in the MYT Order dated 31st March 2017. The Commission also verified the
Tariff Order dated 31st March, 2017 in Petition No. 1622 of 2016 and observed that the
Petitioner has claimed the Surplus of Rs. 126.99 Crore of FY 2015-16 approved by the
Commission in the said Order while determining tariff for FY 2017-18.
The Commission has arrived at the revised ARR and revenue (Gap), based on the
expenses and the Gain / (Loss) approved in the truing up for FY 2017-18 and the
earlier year’s Surplus. The revenue Surplus/ (Gap) as approved by the Commission
for FY 2017-18 is summarised in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
5.1 Introduction
In terms of Regulation 16.2 (i) of the GERC (MYT) Regulations, 2016, a Mid-Term
Review of the Annual Revenue Requirement shall be undertaken for the Generating
Company, Transmission Licensee, SLDC and Distribution Licensee on an application
that shall be filed by utilities along with the petition for truing up for the second year of
the control period and tariff determination for the fourth year of the control period.
5.2.1 Summary of the petition for Mid-Term review for the remaining
control period, FY 2019-20 and FY 2020-21
UGVCL has projected its Revised Aggregate Revenue Requirement for FY 2019-20
and FY 2020-21 as part of Mid-Term Review process for the remaining years of the
control period of the GERC (MYT) Regulations, 2016.
The comparison of revised projections for FY 2019-20 and FY 2020-21 vis-a-vis the
figures approved by the Commission in the MYT order dated 31st March, 2017 is given
in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Mid-Term Review covers the following items of ARR for the remaining years of
control period i.e., FY 2019-20 and FY 2020-21.
Energy projection
Consumer profile
Distribution loss
Energy Requirement and energy balance
Power purchase – Bulk supply tariff
Transmission charges
Capital expenditure and Funding of CAPEX.
Operations and Maintenance Expenses
Gujarat Electricity Regulatory Commission Page 88
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Depreciation
Interest on loan and Finance Expenses
Interest on Working Capital
Return on Equity
Provision for Tax
The Commission has analysed the energy sales and components of expenditure and
discussed the same hereunder.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-9: Projected Energy sales for FY 2018-19, 2019-20 and 2020-21
(MUs)
Sr. Projection
Sales
No FY 2018-19 FY 2019-20 FY 2020-21
LOW TENSION
1 RGP 2254 2418 2594
2 GLP 48 51 54
3 Non-RGP & LTMD 1889 2025 2170
4 Public Water Works 760 816 877
5 Agriculture-Unmetered 6313 6313 6313
6 Agriculture-Metered 2927 3119 3301
7 Street Light 54 56 58
Sub-Total 14245 14798 15366
HIGH TENSION
1 Industrial HT 7241 8170 9218
2 Railway Traction 0 0 0
Sub Total 7241 8170 9218
TOTAL 21487 22968 24584
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Residential (RGP)
UGVCL has projected the energy sales to Residential category for FY 2019-20 and FY
2020-21 as given below:
(MUs)
Category 2018-19 2019-20 2020-21
Residential (RGP) 2254 2418 2594
Petitioner’s submission:
UGVCL has submitted that the company has witnessed a remarkable growth in the
units sold in the last five years in this category. The CAGR between FY 2012-13 and
FY 2017-18 was 7.26%. The company expects this trend to continue in FY 2019-20
and FY 2020-21.
Commission’s Analysis:
The Commission considered the growth rate of 8.14% which was the historical growth
rate for 5 years (FY 2010-11 to FY 2015-16) in the MYT Order dated 31 Match, 2017.
The Petitioner expects the 5 year growth of 7.26% to continue during the rest of the
control period, FY 2019-20 and FY 2020-21 which is considered reasonable and the
Commission, therefore, approves the energy sales at 2418 MUs for FY 2019-20 and
2594 MUs for FY 2020-21 in the Mid-Term Review.
The Commission approves the energy sales to Residential category at 2418 MUs
and 2594 MUs for FY 2019-20 and FY 2020-21 respectively at a growth rate of
7.26% against 2573 MUs and 2783 MUs approved in the MYT order for respective
years .
Table 5-10: Sales approved for Residential category in the Mid-Term Review
(MUs)
Category 2019-20 2020-21
Residential (RGP) 2418 2594
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s Analysis:
The Petitioner has worked out actual 3 Year CAGR of 6.44% and expects this trend to
continue.
The rate 6.44% adopted by the Petitioner is considered reasonable by the
Commission, and accordingly, the Commission approves the energy sales at 51 MUs
for FY 2019-20 and 54 MUs for FY 2020-21 in the Mid-Term Review.
The Commission approves the energy sales to GLP category at 51 MUs and 54
MUs for FY 2019-20 and FY 2020-21 respectively at a growth rate of 6.44% against
57 MUs and 61 MUs approved in the MYT order for respective years.
Table 5-11: Sales approved for GLP category in the Mid-Term Review
(MUs)
Category 2019-20 2020-21
GLP 51 54
Commission’s Analysis:
The Commission had considered the 3 year growth rate of 5.50% (3 Years CAGR
between FY 2012-13 to FY 2015-16) for Non-RGP and LTMD category for FY 2019-
20 and FY 2020-21 in MYT Order dated 31st March 2017. In the Mid-Term Review,
UGVCL has adopted 7.17% growth rate(3 Years CAGR).
The Commission considers it reasonable to adopt the 3 year CAGR of 7.17% over the
sales of FY 2017-18 and has worked out the projected sales of these categories (Non-
RGP & LTMD).
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-12: Approved Sales for Non-RGP & LTMD Category together in the Mid-Term
Review
(MUs)
Category 2019-20 2020-21
Non-RGP & LTMD 2025 2170
The Commission approves the energy sales to Non-RGP & LTMD category at
2025 MUs and 2170 MUs for FY 2019-20 and FY 2020-21 respectively against 1929
MUs and 2035 MUs approved in the MYT order for respective years at a growth
rate of 7.17%.
Petitioner’s Submission:
UGVCL has submitted that the 2 year CAGR for this category was coming out to be
7.73% and y-o-y at 9.82% which is on a higher side when compared to the 3 year
CAGR of 7.39%. Therefore, a more realistic growth rate at 3 year CAGR has been
considered. The company expects this trend to continue in FY 2019-20 and FY 2020-
21.
Commission’s Analysis:
The Commission had approved the sales of 846 MUs & 918 MUs for FY 2019-20 and
FY 2020-21 respectively considering the growth rate of 8.52% (2 Years CAGR) in the
MYT Order dated 31st March, 2017. However considering the actual growth during the
3 years period, the Petitioner has projected lower sales. The growth rate of 7.39%
adopted by UGVCL is therefore, considered reasonable for FY 2019-20 and FY 2020-
21 and accordingly, the Commission accepts the sales projection as given in the Table
below:
Table 5-13: Sales approved for Public Water Works in the Mid-Term Review
(MUs)
The Commission approves the energy sales to Public Water Works category at
816 MUs and 877 MUs for FY 2019-20 and FY 2020-21 respectively against 846
MUs and 918 MUs approved in the MYT order for respective years at a growth
rate of 8.52%.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Agriculture
Petitioner’s Submission:
UGVCL has submitted that based on Government & internal targets the Company is
planning to release new connections under this category but only under the metered
category. For the unmetered category the company has decided not to release any
new connections and has accordingly assumed a growth rate of 0% to project the
sales, no. of consumers and connected load during the control period.
The Company has planned new connections under metered category during the
balance control period as under:
In order to estimate the consumption, UGVCL has gone with the same methodology
as was followed by the Commission in its previous tariff orders i.e. estimating the
overall consumption assuming an average consumption, calculated based on the
weighted average consumption of the metered category during the past years. UGVCL
has calculated the weighted average consumption based on the data available for the
last five years in order to achieve a more reasonable consumption estimate. This
approach is same as adopted and approved by the Commission in the MYT Order.
Thus, based on the figures arrived at as above, the total sales for each year has been
calculated based on the average connected load per consumer for metered and
unmetered categories combined in FY 2017-18 and the number of new connections to
be added during each year. The year wise addition of new metered connections during
the control period in the service area of the company has been presented in the Table
below:
No. of Averag
Agriculture HP MW Per HP Additional
Connecti e HP of
Metered Increase Increase Consumption Sale (MUs)
ons Discom
2018-19 11100 20 218643 163 873 191
2019-20 11150 20 219628 164 873 192
2020-21 10600 20 208795 156 873 182
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s Analysis:
The Commission had approved the energy consumption of 6219 MUs for Unmetered
Consumers for FY 2019-20 and FY 2020-21 in the MYT Order dated 31st March, 2017.
UGVCL has now projected 6313 MUs for FY 2019-20 and FY 2020-21. The
Commission approves the sales for Unmetered Consumers at 6313 MUs for the FY
2019-20 and FY 2020-21 at the same level of FY 2017-18.
As regards the Metered Consumers, UGVCL has projected the sales of 3119 MUs and
3301 MUs for FY 2019-20 and FY 2020-21 respectively at a consumption of 873
kWh/HP/Annum as against 928 kWh/HP/Annum considered in MYT Order dated 31st
March, 2017 which is the weighted average consumption of Metered Consumers
during FY 2010-11 and FY 2015-16. After detailed examination of the average
consumption of Metered Consumers submitted by UGVCL, the Commission
considered the average consumption for Metered Consumers at 873 kWh/HP/Annum,
being the average consumption as given in Table below:
2013-14 Details
Number of Consumers (Nos.) 106859
Connected Load (HP) 1721872
Consumption (MUs) 1332
2014-15
Number of Consumers (Nos.) 129011
Connected Load (HP) 2073220
Consumption (MUs) 1893
2015-16
Number of Consumers (Nos.) 154386
Connected Load (HP) 2464610
Consumption (MUs) 2330
2016-17
Number of Consumers (Nos.) 171337
Connected Load (HP) 2856094
Consumption (MUs) 2407
2017-18
Number of Consumers (Nos.) 195034
Connected Load (HP) 3145500
Consumption (MUs) 2736
From the above, the total avg. connected load for 5 years works out to 2452259.26 HP
[(1721872+2073220+2464610+285094+3145500)/5] and the total average
consumption works out to 2140 MUs [(1332+1893+2330+2407+2736)/5]. Based on
this, the weighted average consumption of Metered Consumers in UGVCL area for the
FY2013-14 to 2017-18 works out to 873 kWh/HP/Annum.
Gujarat Electricity Regulatory Commission Page 97
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The consumption (sales) to Agricultural category both for un-metered and metered
category would be as below:)
Table 5-16: Approved Sales for Agriculture Consumers in the Mid-Term Review
(MUs)
Category 2019-20 2020-21
Un-metered 6313 6313
Metered 3119 3301
Total 9432 9614
The Commission approves the sales to Agriculture Category at 9432 MUs and
9614 MUs for FY 2019-20 and FY 2020-21 respectively.
Public Lighting
Petitioner’s Submission:
UGVCL has submitted that the 5 year CAGR observed between FY 2012-13 and FY
2017-18 was 3.81% and it is expected that this trend will continue in FY 2019-20 and
FY 2020-21 also.
Commission Analysis:
UGVCL has projected the sales at a growth rate (5 Years CAGR) of 3.81%. The
Commission had approve the sales for this category at 66 MUs and 58 MUs for FY
2019-20 and FY 2020-21 respectively in the MYT Order dated 31st March 2017
considering 5 Years CAGR 5.97%. UGVCL has projected the sales for FY 2019-20
and FY 2020-21 at 56 MUs and 58 MUs respectively at a 5 Year CAGR of 3.81%. The
Commission considers the projected sales as reasonable and approves the sales for
FY 2019-20 and FY 2020-21 as below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission approves the sales to Public Lighting Category at 56 MUs and
58 MUs for FY 2019-20 and FY 2020-21 respectively.
Industrial HT
Petitioner’s Submission:
UGVCL has submitted that this category has observed a constant variation in sales in
the last five years due to presence of open access, slowdown in the economy, etc. The
5-year and 4-year CAGR are higher at 11.22% and 16.66% respectively whereas the
y-o-y growth is also higher at 20.95%. Therefore, a more realistic 3-year CAGR of
12.82% is considered as reasonable. The company expects this trend to continue in
FY 2019-20 and FY 2020-21 also.
Commission’s Analysis:
It is observed that the growth in sales of this category was 11.22% during the 5 year
period (FY 2012-13 to FY 2017-18), 12.82% during 3 year period ( FY 2015-16 to FY
2017-18) and 20.95% during the FY 2017-18 over FY 2016-17. It is also observed that
there is an increasing trend in this category. The growth rate of number of consumers
has been consistently decreasing. (5 year CAGR at 8.04%, 3 year CAGR at 7.76%
and FY 17 over FY 16 at 6.95%).
The actual sales for this category during FY 2017-18 was 6418 MUs. Sales projected
by the Petitioner for the FY 2019-20 and FY 2020-21 is 8170 MUs and 9218 MUs by
taking the growth rate of 12.82% against the sales actually approved by the
Commission for FY 2019-20 and 2020-21, 4889 MUs and 4977 MUs in the MYT Order
dated 31st March, 2017 considering Y-o-Y Growth Rate of 1.81%. The Commission
considered rate of 12.82% (3 Year CAGR) as reasonable and approves the sales for
the purpose of Mid-Term Review.
Accordingly, the energy sales approved for Industrial HT category for FY 2019-20 and
FY 2020-21 applying the growth rate of 12.82% over the sales of FY 2017-18 is given
in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-18: Approved Sales for Industrial HT category in the Mid-Term Review
(MUs)
SI. No. Category 2019-20 2020-21
1 Industrial HT 8170 9218
Railway Traction
UGVCL has submitted that no projection has been made for sales, consumers and
connected load for the control period as the consumer has moved out of the company’s
consumer base.
Commission’s Analysis:
The Commission approved the energy sales of “0” MUs for FY 2019-20 and FY 2020-
21 respectively in the MYT Order. Against this, UGVCL has not projected sales,
consumers and connected load for FY 2019-20 and FY 2020-21. As the consumer has
moved out of the company’s consumer base, the Commission approves the Nil sales
for Railway Traction as below:
Total Energy sales for FY 2019-20 and FY 2020-21 approved by the Commission
based on the above analysis is summarised in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioner’s Submission:
UGVCL has submitted that the company has, through its constant endeavours, tried
to reduce its losses in the past. These efforts shall continue and will be enhanced.
However, loss reduction is a slow process and becomes increasingly difficult as the
loss levels come down.
Commission’s Analysis:
The Commission in the MYT Order dated 31st March 2017, considered distribution
losses at 9.70% during FY 2019-20 and 9.60% during FY 2020-21 and the distribution
losses projected by UGVCL is 9.70% for FY 2019-20 and 9.60% for FY 2020-21.Thus,
there is no change in the distribution losses approved by the Commission in the MYT
Order and the losses projected by UGVCL in the Mid-Term Review for FY 2019-20 and
FY 2020-21. Hence, the Commission approves the distribution losses of 9.70% for FY
2019-20 and 9.60% for FY 2020-21.
Petitioner’s Submission:
UGVCL has submitted that to arrive at the total energy requirement, the total sales in
MUs as projected have been grossed up by factoring in transmission and distribution
losses. Intra-state transmission losses are assumed as per the projection by GETCO
in its MTR Petition for FY 2019-20 and FY 2020-21. The inter-state transmission losses
viz. PGCIL pooled losses are assumed at same level as in FY 2017-18 for the entire
control period. Further, the distribution losses are taken as per the projections above.
Based on the information provided above, Energy Balance of the Company for FY
Gujarat Electricity Regulatory Commission Page 101
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s Analysis:
Based on the energy sales and the distribution losses approved by the Commission in
Paragraphs 5.4 and 5.5 above, the energy requirement is arrived at as given in the
Table below:
Energy Balance projected by UGVCL is given in Table 5-22 above. UGVCL has
considered Transmission losses at 3.85% which is the same as approved by the
Commission in the MYT Order dated 31st March, 2017. The pooled losses in PGCIL
system are considered at 396.26 MUs for FY 2019-20 and FY 2020-21 same as the
actual for FY 2017-18 by UGVCL. The Commission considers the Transmission losses
at 3.85% and pooled losses in PGCIL system as projected by UGVCL to arrive at the
Energy Balance in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioner’s submission
The existing contracted capacity tied up by GUVNL as on 31st March 2018 is 22616
MW. Given below are the names of the existing power plants, their operational
parameters, capacity allocated to GUVNL, their fixed cost along with the variable cost
of generation per unit as per actual of FY 2017-18:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Plant Fixed
Sr. Capacity Auxiliary Variable
Load Cost
No Name of the Station allocated to Consumpti Cost
Factor (Rs.
. GUVNL (MW) on (%) (Rs./kWh)
(%) Crore)
8 GSECL Gandhinagar 1-4 420 10.00% 61.97% 204 3.74
9 GSECL Wanakbori 1-6 1,260 9.00% 85.00% 448 3.29
10 GSECL Sikka Expansion 500 9.00% 70.00% 629 3.65
11 GSECL Kutch Lignite 1-3 215 12.00% 52.31% 207 2.16
12 GSECL Kutch Lignite 4 75 12.00% 42.72% 62 1.98
13 GSECL Ukai Hydro 305 0.60% 11.71% 42 -
14 GSECL Kadana Hydro 242 1.00% 13.72% 73 -
15 BECL 500 6.50% 85.00% 879 2.15
16 Dhuvaran CCPP III 376 3.00% 0.94% 159 5.77
Sub Total 6,017 3894
IPP's
Gujarat State Energy
1 156 3.00% 0.15% 49 6.11
Generation
Gujarat State Energy
2 351 0.00% 6.08% 180 5.19
Generation Expansion
Gujarat Industries Power
3 165 3.00% 0.00% - 4.5
Co Ltd (165 MW)
Gujarat Industries Power
4 250 10.00% 71.59% 129 1.71
Co Ltd (SLPP)
Gujarat Mineral
5 250 10.00% 57.38% 124 1.26
Development Corp.
Gujarat Industries Power
6 42 3.00% 29.42% 5 2.27
Co Ltd (145 MW)
Gujarat Industries Power
7 250 10.00% 75.29% 273 1.88
Co Ltd (SLPP - Exp)
8 GPPC Pipavav 702 3.00% 2.80% 325 4.37
Sub Total 2,166 1085
Central Sector
1 NPC-Tarapur (1 & 2) 160 10.00% 42.73% - 2.08
2 NPC-Tarapur (3 & 4) 274 10.00% 59.81% - 3.1
3 NPC-Kakrapar 125 12.50% 52.60% - 2.39
4 NTPC-Vindhyachal - I 230 9.00% 87.98% 23 1.62
5 NTPC-Vindhyachal - II 239 6.50% 91.75% 128 1.52
6 NTPC-Vindhyachal - III 266 6.50% 95.29% 212 1.52
7 NTPC-Korba 360 6.50% 89.91% 23 1.46
8 NTPC-Korba –II 96 6.50% 91.19% 98 1.43
9 NTPC-Kawas 187 3.00% 43.80% 113 2.56
10 NTPC-Jhanor 237 3.00% 55.42% 132 2.39
11 NTPC-Sipat-I 540 6.50% 89.04% 519 1.3
12 NTPC-Sipat – II 273 6.50% 90.03% 250 1.35
13 NTPC-Kahlagaon 141 6.50% 78.80% 106 2.31
14 NTPC-Vindhyachal – IV 240 6.50% 90.40% 280 1.51
15 NTPC-Mauda 240 6.50% 85.00% 320 2.79
16 NTPC-Vindhyachal – V 93 6.50% 100.00% 118 1.57
17 NTPC-Mauda II 294 5.75% 85.05% 380 2.5
18 SSNL 232 0.00% 7.18% - 2.03
19 Mundra UMPP CGPL 1,805 0.00% 73.93% 1,129 1.66
Sub Total 6,032 3831
Others
1 Captive Power 8 0.00% 2.85% - 2.13
- Renewable
1 Wind Farms 3,695 0.00% 20.61% - 3.78
2 Solar 1,116 0.00% 17.84% - 11.45
Gujarat Electricity Regulatory Commission Page 104
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Plant Fixed
Sr. Capacity Auxiliary Variable
Load Cost
No Name of the Station allocated to Consumpti Cost
Factor (Rs.
. GUVNL (MW) on (%) (Rs./kWh)
(%) Crore)
3 Small/Mini Hydal 10 0.00% 65.00% - 3.39
4 Biomass 30 0.00% 80.00% 40 4.17
Competitive Bidding
1 Adani Power Ltd 2,000 0.00% 45.79% 975 1.81
2 Essar Power Bid 2 1,000 0.00% 28.13% 354 1.92
3 ACB India Ltd 200 0.00% 80.48% 201 0.82
4 Power Exchange 342 0.00% 100.00% - 4.5
Short term power
5 342 0.00% 100.00% - 3.5
purchase
Sub Total 8,401 1570
Total 22,616 10380
The capacity addition plan which includes capacity additions of GSECL, Central
stations and IPPs is presented in the Table below with details of the capacity allocated
to GUVNL and their unit wise tentative commissioning schedule. It is submitted that
the PPA is already signed for the stations listed below and are expected to get
commissioned during the FY 2019-20 to FY 2020-21.
The capacity addition envisaged against these petitions during FY 2019-20 to FY 2020-
21 is around 1,995 MW. The operational parameters, annual fixed cost and variable
cost per unit for these plants is given below. The Annual fixed cost and the availability
from the envisaged capacity during FY 2019-20 to FY 2020-21 have been considered
on pro-rata basis depending upon the tentative date of commissioning:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
While the Commission has defined the RPO targets for FY 2017-18 to FY 2021-22
through the Second Amendment to the RPO Regulations, GUVNL/DISCOMS
proposes to purchase renewable power up to tied up RE capacity only for each of the
respective years as per the PPA price. The Petitioner has submitted that it is very
difficult to meet such high level of RPO targets and it will not be appropriate to show
RE purchase in the absence of any firm PPA. Hence, GUVNL/ DISCOM has only
considered RE purchase based on actual tied up capacity.
The year wise purchase from RE sources based on actual tied up capacity has been
detailed below:
Table 5-26: Procurement from RE for Meeting Projected RPO
Particulars FY 2019-20 FY 2020-21
Solar Wind Others Total Solar Wind Others Total
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioner’s submission:
UGVCL has submitted that in order to optimise the power purchase cost, GUVNL has
worked out a comprehensive Merit Order Dispatch (MOD) available from tied up
generating capacities. The dispatch from individual generating stations is worked out
based on the merit order of the variable cost of each generating unit as shown below:
The NPC power plants, renewable and hydro plants have been considered as must
run power plants.
During merit order despatch, at least 5% availability of each plant has been
considered to take care of the peak loads and peak season requirements.
Availability of Thermal Stations has been considered at 85% / 80% as defined in
Regulations (CERC/GERC) and performance in previous years.
The Fixed & Variable Cost for existing GSECL, IPP, Renewables and Central
Sector plants is taken as per actuals of FY 2017-18 as base power purchase cost
Based on the above factors, the plant-wise dispatchable energy and cost of
purchase by GUVNL from various plants of GSECL, Central generating stations, IPPs
and other sources, the generation fixed cost due to the capacity contracted,
and variable cost of generation per unit are given in the Table below. The dispatchable
energy (MUs) based on the allocated capacity and merit order stacking consists both
for supplying power to DISCOMs as well as for trading purpose.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Central Sector
1 NPC-Tarapur (1 & 2) 539 539 - 2.08 112 112
2 NPC-Tarapur (3 & 4) 1,292 1,292 - 3.10 401 401
3 NPC-Kakrapar 504 504 - 2.39 120 120
4 NTPC-Vindhyachal – I 1,613 1,613 23 1.62 261 284
5 NTPC-Vindhyachal – II 1,796 1,796 128 1.52 273 401
Gujarat Electricity Regulatory Commission Page 108
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Others
1 Captive Power 2 2 - 2.13 - -
Renewable
1 Wind Farms 6,671 6,671 - 3.78 2522 2522
2 Solar 1,744 1,744 - 11.45 1997 1997
3 Small/Mini Hydal 55 55 - 3.39 19 19
4 Small/Mini Hydal (New) 44 44 - 3.29 14 14
5 Biomass 210 210 40 4.17 88 128
6 Solar(New) 950 950 - 2.66 253 253
7 Wind (New) 589 589 - 2.44 144 144
8 Others (New) 14 14 - 6.66 9 9
Sub Total 10,280 10,280 40 5,045 5,085
TOTAL 108944 99680 11900 24734 36634
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
IPPs
Gujarat State Energy
1 2 2 49 6.11 1 50
Generation
Gujarat State Energy
2 187 154 180 5.19 80 260
Generation Expansion
Gujarat Industries Power Co
3 - - - 4.5 - -
Ltd (165 MW)
Gujarat Industries Power Co
4 1,411 1,411 129 1.71 241 370
Ltd (SLPP)
Gujarat Mineral Development
5 1,131 1,131 124 1.26 143 267
Corp.
Gujarat Industries Power Co
6 105 105 5 2.27 24 29
Ltd (145 MW)
Gujarat Industries Power Co
7 1,484 1,484 273 1.88 279 552
Ltd (SLPP - Exp)
8 GPPC Pipavav 167 167 325 4.37 73 398
9 Mundra UMPP CGPL 11,689 11,689 1,129 1.66 1943 3072
10 Adani Power Ltd 8,023 8,023 975 1.81 1450 2425
11 Essar Power Bid 2 2,464 2,464 354 1.92 473 827
12 ACB India Ltd 1,410 1,410 201 0.82 116 317
13 Power Exchange 3,000 150 - 4.50 68 68
14 Short Term Power Purchase 3,000 3,000 - 3.50 1050 1050
Sub Total 34073 31190 3744 5939 9683
Central Sector
1 NPC-Tarapur (1 & 2) 539 539 - 2.08 112 112
2 NPC-Tarapur (3 & 4) 1,292 1,292 - 3.10 401 401
3 NPC-Kakrapar 504 504 - 2.39 121 121
4 NTPC-Vindhyachal – I 1,613 1,613 23 1.62 262 285
5 NTPC-Vindhyachal – II 1,796 1,796 128 1.52 273 401
6 NTPC-Vindhyachal – III 2,076 2,076 212 1.52 316 528
7 NTPC-Korba 2,651 2,651 23 1.46 387 410
8 NTPC-Korba –II 717 717 98 1.43 103 201
9 NTPC-Kawas 696 696 113 2.56 178 291
10 NTPC-Jhanor 1,116 1,116 132 2.39 267 399
11 NTPC-Sipat-I 3,938 3,938 519 1.30 512 1031
12 NTPC-Sipat – II 1,445 1,445 250 1.35 194 444
13 NTPC-Kahlagaon 910 910 106 2.31 210 316
14 NTPC-Vindhyachal – IV 1,777 1,777 280 1.51 269 549
15 NTPC-Mauda 1,671 1,671 320 2.79 466 786
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Others
1 Captive Power 2 2 - 2.13 - -
Renewable
1 Wind Farms 6,671 6,671 - 3.78 2522 2522
2 Solar 1,744 1,744 - 11.45 1997 1997
3 Small/Mini Hydal 55 55 - 3.39 19 19
4 Small/Mini Hydal (New) 44 44 - 3.29 14 14
5 Biomass 210 210 40 4.17 88 128
6 Solar(New) 2,161 2,161 - 2.54 549 549
7 Wind (New) 1,058 1,058 - 2.44 258 258
8 Others (New) 177 177 - 6.9 122 122
Sub Total 12,123 12,123 40 5,567 5,607
TOTAL 112459 105652 11923 26401 38323
Petitioner’s submission:
UGVCL has submitted that the total power purchase cost for the company for the
remaining control period, FY 2019-20 to FY 2020-21 consists of: Transmission
Charges, GUVNL cost and SLDC fees and charges.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The total power purchase cost consists of the cost of power purchase from various
generating stations, transmission charges of PGCIL and GETCO, SLDC charges,
GUVNL costs and trading units.
The total fixed costs, due to the capacity contracted, are passed on to the
DISCOMs as shown in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-31: Projected Fixed cost for DISCOMs for FY 2019-20 and FY 2020-21
(Rs. Crore)
The Table below shows the total variable cost for FY 2019-20 to FY 2020-21
Table 5-32: Projected Variable cost for DISCOMs and trading of energy from FY 2019-20
and FY 2020-21
(Rs. Crore)
Total Variable
Variable GUVNL Dispatched Discom Variable
Year Variable Cost Rs./
Cost Cost (MUs) (MUs) Cost
Cost kWh
2019-20 24734 399 25132 99680 2.52 99680 25132
2020-21 26401 423 26824 105652 2.54 105652 26824
Table 5-33: Projected Net Power Purchase cost for FY 2019-20 and FY 2020-21
(Rs. Crore)
The Objective of the differentiation of the BST between DISCOMs is due to the fact
that the revenue from tariffs for each DISCOMs are different due to different consumer
mix and therefore, it is necessary to build a mechanism in the projections to bring them
to a level playing field. The basic objective of Bulk Supply Tariff is that:
GUVNL shall purchase power from various sources in bulk and supply power
in bulk to DISCOMs for onward retail supply.
To ensure uniform retail consumer tariffs in four state owned DISCOMs.
Since each of the DISCOMs were incorporated on the basis of earlier zonal
system, the consumer mix and consumption mix is different for each DISCOM.
Consequently, the revenue earning capability of each DISCOM is different.
Gujarat Electricity Regulatory Commission Page 113
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
As mentioned in Para 5.8.1, UGVCL has submitted that GUVNL has entered into
contracts for the existing capacity with GSECL, Central Generating Companies, IPPs,
renewable energy sources, Hydro, Solar, Wind, Other RE Sources, IPPs and Power
tied up through competitive bidding etc. The details of the existing plants are given in
Table 5-24. GUVNL has also entered into contract for additional capacity likely to be
commissioned during FY 2019-20 and FY 2020-21. The details of additional plants
likely to be commissioned during FY 2019-20 and FY 2020-21 are given in Table 5-25.
The capacity approved by the Commission in the MYT Order dated 31st March, 2017
and projected by petitioner in Mid-Term Review from each of the sources are
summarised in the Table below:
Table 5-34: Capacity Contracted Source – Wise by GUVNL in the MYT Order and Now
Submitted by UGVCL for the period FY 2019-20 and FY 2020-21
(MW)
2019-20 2020-21
SI.
Particulars Approved in Projected in Approved in Projected in
No.
MYT Order the MTR MYT Order the MTR
1 GSECL 6817 6817 8417 6817
2 IPPs 2001 2166 2001 2166
3 Central Generating
5577 6740 5654 7216
Stations
4 Renewable 3409 4863 3409 4863
5 Competitive Bidding 5005 3884 5005 3884
6 Others – CPP 8 8 8 8
7 Total 22817 24478 24494 24954
The power purchase for the period FY 2019-20 and FY 2020-21 is based on the energy
requirement of UGVCL / four DISCOMs approved by the Commission.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The source wise Power available and dispatchable units based on the merit despatch
in the MYT Order and as projected in Mid-Term Review for FY 2019-20 and FY 2020-
21 are given in the Table below:
Table 5-35: Energy Available & Dispatchable as approved in MYT order and projected
in MTR for FY 2019-20
Approved in the MYT Order Projected in MTR
Sr.
Particulars Available Dispatch Availabe Dispatch
No.
MUs MUs MUs MUs
GSECL
1 GSECL Gandhinagar – 5 1339 84 1,314 1,314
2 GSECL Wanakbori – 7 1339 84 1,341 1,341
3 GSECL Utran Expan 1910 32 250 159
4 GSECL Dhuvaran – 7 362 45 191 191
5 GSECL Dhuvaran – 8 382 48 361 361
6 GSECL Ukai 3890 243 4,133 4,133
7 GSECL Ukai Expan 3294 395 3,500 3,500
8 GSECL Gandhinagar 3-4 2649 166 2,052 166
9 GSECL Wanakbori 1-6 8035 502 8,538 8,538
10 GSECL Sikka Expansion 3189 3189 2,790 199
11 GSECL Kutch Lignite 1-3 1243 1243 867 867
12 GSECL Kutch Lignite 4 463 463 247 247
13 GSECL Ukai Hydro 478 478 311 311
14 GSECL Kadana Hydro 287 287 288 288
15 BECL 3084 3084 3,481 3,481
16 Dhuvaran CCPP III 1917 32 30 30
17 GSECL Wanakbori Ext U#8 5608 330 5,614 5,614
Sub Total 39471 10704 35,308 30,740
IPP's
Gujarat State Energy
1 795 13 2 2
Generation
Gujarat State Energy
2 1845 31 187 154
Generation Expansion
Gujarat Industries Power Co
3 - - - -
Ltd (165 MW)
Gujarat Industries Power Co
4 1433 1433 1,411 1,411
Ltd (SLPP)
Gujarat Mineral Development
5 1577 1577 1,131 1,131
Corp.
Gujarat Industries Power Co
6 214 4 105 105
Ltd (145 MW)
Gujarat Industries Power Co
7 1265 1265 1,484 1,484
Ltd (SLPP - Exp)
8 GPPC Pipavav 472 60 167 167
9 Mundra UMPP CGPL 12649 12649 11,689 11,689
10 Adani Power Ltd 14892 14892 8,023 8,023
11 Essar Power Bid 2 7446 7446 2,464 2,464
12 ACB India Ltd 1489 1489 1,410 1,410
13 Power Exchange - - 3,000 150
14 Short Term Power Purchase - - 3,000 1,187
Sub Total 44077 40859 34,073 29,377
Central Sector
Gujarat Electricity Regulatory Commission Page 115
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Others
1 Captive Power 6 6 2 2
Renewable
1 Wind Farms 4280 4280 6,671 6,671
2 Solar 1368 1368 1,744 1,744
3 Small/Mini Hydal 45 45 55 55
4 Small/Mini Hydal (New) - - 44 44
5 Biomass 1 1 210 210
6 Solar(New) 3832 3832 950 950
7 Wind (New) 3331 3331 589 589
8 Others (New) 663 663 14 14
Sub Total 13526 13526 10,280 10,280
TOTAL 131154 96426 1,08,944 99,680
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-36: Energy Available & Dispatchable as approved in MYT order and projected in MTR
for FY 2020-21
Approved in the MYT Order Projected in MTR
Sr.
Particulars Available Dispatch Available Dispatch
No.
MUs MUs MUs MUs
GSECL
1 GSECL Gandhinagar – 5 1339 84 1,314 1,314
2 GSECL Wanakbori – 7 1339 84 1,341 1,341
3 GSECL Utran Expan 1910 32 250 159
4 GSECL Dhuvaran – 7 362 45 191 191
5 GSECL Dhuvaran – 8 382 48 361 361
6 GSECL Ukai 3890 243 4,133 4,133
7 GSECL Ukai Expan 3294 854 3,500 3,500
8 GSECL Gandhinagar 3-4 2649 166 2,052 166
9 GSECL Wanakbori 1-6 8035 502 8,538 8,538
10 GSECL Sikka Expansion 3189 3189 2,790 844
11 GSECL Kutch Lignite 1-3 1243 1243 867 867
12 GSECL Kutch Lignite 4 463 463 247 247
13 GSECL Ukai Hydro 478 478 311 311
14 GSECL Kadana Hydro 287 287 288 288
15 BECL 3084 3084 3,481 3,481
16 Dhuvaran CCPP III 1917 32 30 30
17 GSECL Wanakbori Ext U#8 5608 330 5,614 5,614
18 Dhuvaran STPS 11217 660 - -
Sub Total 50688 11824 35,308 31,384
IPP's
Gujarat State Energy
1 795 13 2 2
Generation
Gujarat State Energy
2 1845 31 187 154
Generation Expansion
Gujarat Industries Power Co
3 1433 1433 1,411 1,411
Ltd (SLPP)
Gujarat Mineral Development
4 1577 1577 1,131 1,131
Corp.
Gujarat Industries Power Co
5 214 4 105 105
Ltd (145 MW)
Gujarat Industries Power Co
6 1265 1265 1,484 1,484
Ltd (SLPP - Exp)
7 GPPC Pipavav 472 60 167 167
8 Mundra UMPP CGPL 12649 12649 11,689 11,689
9 Adani Power Ltd 14892 14892 8,023 8,023
10 Essar Power Bid 2 7446 7446 2,464 2,464
11 ACB India Ltd 1489 1489 1,410 1,410
12 Power Exchange - - 3,000 150
13 Short Term Power Purchase - - 3,000 3,000
Sub Total 44077 40859 34,073 31,190
Central Sector
1 NPC-Tarapur (1 & 2) 1072 1072 539 539
2 NPC-Tarapur (3 & 4) 1836 1836 1,292 1,292
3 NPC-Kakrapar 814 814 504 504
4 NTPC-Vindhyachal – I 1467 1467 1,613 1,613
Gujarat Electricity Regulatory Commission Page 117
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Sr.
Particulars Available Dispatch Available Dispatch
No.
MUs MUs MUs MUs
Others
1 Captive Power 6 6 2 2
Renewable
1 Wind Farms 4280 4280 6,671 6,671
2 Solar 1368 1368 1,744 1,744
3 Small/Mini Hydal 45 45 55 55
4 Small/Mini Hydal (New) - - 44 44
5 Biomass 1 1 210 210
6 Solar (New) 5332 5332 2,161 2,161
7 Wind (New) 3809 3809 1,058 1,058
8 Others (New) 699 699 177 177
Sub Total 15540 15540 12,123 12,123
TOTAL 146031 101205 112459 105652
The availability and dispatchable energy from all sources projected by UGVCL in the
Mid-Term Review for FY 2019-20 and FY 2020-21 and as approved by the
Commission in the MYT Order dated 31st March, 2017 are summarised below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-37: Availability and Dispatchable as approved in MYT Order and as Projected in
MTR for FY 2019-20 and FY 2020-21
(MUs)
As discussed in Para 5.8.1, GUVNL has entered into contract for the existing capacity
with GSECL, Central generating stations, IPPs, renewable energy sources and power
tied up through competitive bidding. The details of existing plants etc., are given in
Table 5-24.
GUVNL has also entered in to contract for new capacity that is likely to be
commissioned during FY 2019-20 and FY 2020-21. The details of new plants likely to
be commissioned during FY 2019-20 and FY 2020-21 are given in Table 5-25.
The details of capacity contracted by GUVNL, from the existing plant and the additional
plants envisaged during FY 2019-20 and FY 2020-21 with operational parameters,
fixed and variable costs are given in Tables 5-27 and 5-28.
As discussed in Para 5.8.2, in order to optimize the Power Purchase Cost GVUNL has
worked out a comprehensive merit order despatch (MOD).
The quantum of power dispatchable (to be purchased) is arrived at based on the
energy available from various sources less energy requirement by the four DISCOMs
and energy that could be traded by GUVNL as given in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-38: Energy requirement and Energy dispatchable as projected by the DISCOMs
Though the availability is in the order of 108944 MUs and 112459 MUs during FY 2019-
20 and FY 2020-21, the despatch is limited to 99680 MUs and 105652 MUs as above
to meet the total requirement of the four DISCOMs.
The projected dispatchable energy is about 91.49% of the projected available energy
during FY 2019-20 (the available energy being 108944 MUs and dispatchable energy
99680 MUs) and 93.95% during FY 2020-21 (the available energy being 112459 and
dispatchable energy 105652 MUs) as shown in Tables 5-37.
The Commission in the analysis of energy sales projected by DISCOMs has approved
energy sales and energy requirement of each DISCOM.
The energy requirement projected and energy requirement approved for each
DISCOM by the Commission are summarised below:
Table 5-39: Energy requirement projected and approved for each DISCOM for
(MUs)
Energy Requirement
Sr.
DISCOM 2019-20 2020-21
No.
Projected Approved Projected Approved
1 DGVCL 22552 22552 23688 23688
2 MGVCL 12523 12523 13256 13256
3 PGVCL 37757 37757 40028 40028
4 UGVCL 26849 26849 28680 28680
Total requirement of four
5 99680 99680 105652 105652
DISCOMs
Tradable energy projected by
6 - - - -
GUVNL
7 Total Despatch units 99680 99680 105652 105652
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
5.9.4 Power Purchase Cost for the period FY 2019-20 and FY 2020-21
UGVCL has submitted the power purchase costs as given in Table 5.33.
It is observed that Petitioner has not projected the purchase of power in accordance
with the RPO requirement. The Commission has therefore, worked out the purchase
of power from renewable sources in accordance with the RPO Regulations. Further,
while considering the power purchase requirement, the merit order dispatch has been
applied as specified in Para 5.8.2 above. It is also observed by the Commission that
the Petitioner inadvertently not considered fixed cost of Utran Expansion for FY 2020-
21. The Commission has considered the same.
Also, the fixed cost and variable cost for GSECL stations, IPPs, renewable and Central
plants are taken as per actuals of FY 2017-18 as base power purchase cost. The
approved requirement of power for all the DISCOMs put together, the Trading Units
and revised dispatchable units for the FY 2019-20 and FY 2020-21 as discussed above
are given in the Tables below:
IPPs
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Central Sector
1 NPC-Tarapur (1 & 2) 539 539 0 2.08 112 112
2 NPC-Tarapur (3 & 4) 1,292 1,292 0 3.10 400 400
3 NPC-Kakrapar 504 504 0 2.39 121 121
4 NTPC-Vindhyachal – I 1,613 1,613 23 1.62 262 285
5 NTPC-Vindhyachal – II 1,796 1,796 128 1.52 273 401
6 NTPC-Vindhyachal – III 2,076 2,076 212 1.52 316 528
7 NTPC-Korba 2,651 2,651 23 1.46 387 410
8 NTPC-Korba –II 717 717 98 1.43 103 201
9 NTPC-Kawas 696 696 113 2.56 178 291
10 NTPC-Jhanor 1,116 1,116 132 2.39 267 399
11 NTPC-Sipat-I 3,938 3,938 519 1.30 513 1032
12 NTPC-Sipat – II 1,445 1,445 250 1.35 194 444
13 NTPC-Kahlagaon 910 910 106 2.31 210 316
14 NTPC-Vindhyachal – IV 1,777 1,777 280 1.51 269 549
15 NTPC-Mauda 1,671 1,671 320 2.79 466 786
16 NTPC-Vindhyachal – V 765 765 118 1.57 120 238
17 NTPC-Mauda II 2,063 2,063 380 2.50 516 896
18 SSNNL 146 146 0 2.03 30 30
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Others
1 Captive Power 2 2 0 2.13 0 0
Renewable 0 0 0 0.00
1 Wind Farms 6,671 6,671 0 3.78 2520 2520
2 Solar 1,744 1,744 0 11.45 1997 1997
3 Small/Mini Hydal 55 55 0 3.39 19 19
4 Small/Mini Hydal (New) 44 44 0 3.29 15 15
5 Biomass 210 210 40 4.17 88 128
6 Solar (New) 3738 3,738 0 2.66 996 996
7 Wind (New) 1353 1,353 0 2.44 330 330
8 Others (New) 438 438 0 6.66 292 292
Sub Total 14256 14,256 40 6256 6,296
TOTAL 112920 99680 11900 24572 36472
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Variab
Fixed Variabl Total
Availa le
Sr. Dispatch Cost e Cost Cost
Particulars be Cost
No. (MUs) (Rs. (Rs. (Rs.
(MUs) (Rs.
Crore) Crore) Crore)
/Unit)
10 GSECL Sikka Expansion 2,790 844 629 3.65 308 937
11 GSECL Kutch Lignite 1-3 867 867 207 2.16 187 394
12 GSECL Kutch Lignite - 4 247 247 62 1.98 49 111
13 GSECL Ukai Hydro 311 311 42 0.00 0 42
14 GSECL Kadana Hydro 288 288 73 0.00 0 73
15 BECL 3,481 3,481 879 2.15 748 1627
16 Dhuvaran CCPP III 30 30 159 5.77 17 176
GSECL Wanakbori Ext
17 5,614 5,614 905 2.94 1651 2555
U#8
Sub Total 35,308 29,821 4,798 8,805 13,603
IPPs
Gujarat State Energy
1 2 2 49 6.11 1 50
Generation
Gujarat State Energy
2 187 154 180 5.19 80 260
Generation Expansion
Gujarat Industries Power
3 0 0 0 4.50 0 0
Co Ltd (165 MW)
Gujarat Industries Power
4 1,411 1,411 129 1.71 241 370
Co Ltd (SLPP)
Gujarat Mineral
5 1,131 1,131 124 1.26 142 266
Development Corp.
Gujarat Industries Power
6 105 105 5 2.27 24 29
Co Ltd (145 MW)
Gujarat Industries Power
7 1,484 1,484 273 1.88 279 552
Co Ltd (SLPP - Exp)
8 GPPC Pipavav 167 167 325 4.37 73 398
9 Mundra UMPP CGPL 11,689 11,689 1,129 1.66 1943 3072
10 Adani Power Ltd 8,023 8,023 975 1.81 1450 2425
11 Essar Power Bid 2 2,464 2,464 354 1.92 473 827
12 ACB India Ltd 1,410 1,410 201 0.82 115 316
13 Power Exchange 3,000 150 0 4.50 68 68
Short Term Power
14 Purchase / Power 3,000 150 0 3.50 53 53
Exchange
Sub Total 34,073 28,340 3,744 4,941 8,685
Central Sector
1 NPC-Tarapur (1 & 2) 539 539 0 2.08 112 112
2 NPC-Tarapur (3 & 4) 1,292 1,292 0 3.10 400 400
3 NPC-Kakrapar 504 504 0 2.39 121 121
4 NTPC-Vindhyachal – I 1,613 1,613 23 1.62 262 285
5 NTPC-Vindhyachal – II 1,796 1,796 128 1.52 273 401
6 NTPC-Vindhyachal – III 2,076 2,076 212 1.52 316 528
7 NTPC-Korba 2,651 2,651 23 1.46 387 410
8 NTPC-Korba –II 717 717 98 1.43 103 201
Gujarat Electricity Regulatory Commission Page 124
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Variab
Fixed Variabl Total
Availa le
Sr. Dispatch Cost e Cost Cost
Particulars be Cost
No. (MUs) (Rs. (Rs. (Rs.
(MUs) (Rs.
Crore) Crore) Crore)
/Unit)
9 NTPC-Kawas 696 696 113 2.56 178 291
10 NTPC-Jhanor 1,116 1,116 132 2.39 267 399
11 NTPC-Sipat-I 3,938 3,938 519 1.30 513 1032
12 NTPC-Sipat – II 1,445 1,445 250 1.35 194 444
13 NTPC-Kahlagaon 910 910 106 2.31 210 316
14 NTPC-Vindhyachal – IV 1,777 1,777 280 1.51 269 549
15 NTPC-Mauda 1,671 1,671 320 2.79 466 786
16 NTPC-Vindhyachal – V 765 765 118 1.57 120 238
17 NTPC-Mauda II 2,063 2,063 380 2.50 516 896
18 SSNNL 146 146 0 2.03 30 30
19 NTPC-Lara U#1 551 551 110 1.50 83 193
NTPC-Gadarwara Stage-I
20 1,067 1,067 152 1.50 160 312
U#1
NTPC-Gadarwara Stage-I
21 1,067 1,067 152 1.50 160 312
U#2
22 NTPC-Lara U#2 551 551 110 1.50 83 193
23 NPC Kakrapar Ext U#1 139 139 10 2.38 33 43
24 NPC Kakrapar Ext U#2 139 139 10 2.38 33 43
25 NTPC-Khargone U#1 863 863 172 1.50 129 301
26 NTPC-Khargone U#2 863 863 172 1.50 129 301
Sub Total 30,955 30,955 3,590 5,547 9,137
Others
1 Captive Power 2 2 0 2.13 0.43 0.43
Renewable 0 0
1 Wind Farms 6,671 6,671 0 3.78 2520 2,520
2 Solar 1,744 1,744 0 11.45 1997 1,997
3 Small/Mini Hydal 55 55 0 3.39 19 19
4 Small/Mini Hydal (New) 44 44 0 3.29 15 15
5 Biomass 210 210 40 4.17 88 128
6 Solar(New) 5387 5,387 0 2.54 1368 1,368
7 Wind (New) 1939 1,939 0 2.44 473 473
8 Others (New) 483 483 0 6.90 333 333
Sub Total 16536 16536 40 6812 6852
TOTAL 116872 105652 12173 26105 38277
The Commission has considered the despatchable and available energy from the
sources considered by the Petitioner to arrive at projection of Power Purchase Cost
for FY 2019-20 and FY 2020-21, however, the Petitioner shall follow the Merit Order
Principles and Prudence Practices while availing power from different sources.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Transmission cost include the cost to be paid to PGCIL for regional transmission and
cost of GETCO for intra-state transmission.
Transmission charges of PGCIL are approved by the CERC and to be paid by GUVNL
on the basis of calculation of Regional Energy Account of Western Region by WRLDC,
hence the Commission accepts the projection of UGVCL/GUVNL for PGCIL charges.
These charges are escalated at 5.72% y-o-y considering the actual charges of FY
2017-18 as the base.
The Petitioner has submitted that the Transmission charges of GETCO have been
considered as per the MYT Order of GETCO for FY 2019-20 and FY 2020-21. The
Commission has considered the Transmission charges of GETCO as approved in the
MYT Order dated 31st March, 2017. The Commission accordingly approves the
Transmission Charges payable to PGCIL and GETCO as given in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-43: GUVNL Costs approved by the Commission for the period FY 2019-20 and
FY 2020-21
Table 5-44: SLDC charges approved by the Commission for FY 2019-20 and FY 2020-21
(Rs. Crore)
SI. No. Particulars 2019-20 2020-21
1 SLDC Charges 29 33
The total fixed cost consists of the fixed cost of the energy procured from various
sources, transmission costs of PGCIL and GETCO, SLDC Charges & fees and Trading
Costs approved by the Commission. These are aggregated to arrive at the total fixed
cost of power purchase for all DISCOMs.
The fixed costs due to capacity contracted by GUVNL are passed on to DISCOMs as
given in the Table below:
Table 5-45: Fixed cost of DISCOMs for the period FY 2019-20 and FY 2020-21
(Rs. Crore)
Fixed GETCO PGCIL SLDC Total Fixed DISCOMS
Year
Cost Cost Charges Charges Cost Fixed Cost
2019-20 11,900 4115 2077 29 18121 18121
2020-21 12,173 4502 2181 33 18888 18888
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-46: Variable cost for DISCOMs and Trading Units for the period FY 2019-20 and
FY 2020-21
Table 5-47: Total Cost of Power for DISCOMs for FY 2019-20 and FY 2020-21
(Rs. Crore)
Total
Total Fixed
Year Variable Total Cost
Cost
Cost
2019-20 18121 24971 43092
2020-21 18888 26528 45416
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-48: Category Wise sales approved and existing average tariff in Rs./kWh
DGVCL MGVCL PGVCL UGVCL
2019- 2020- Averag 2020- Averag Averag
2019-20 2020-21 Averag Averag 2019-20 2020-21 Averag 2019-20
Average Average 20 21 e Tariff 21 e Tariff e Tariff
Sr. e Tariff e Tariff e Tariff
Category Tariff Tariff Rs./kW Rs./kW Rs./kW
No. Rs./kW Rs./kW Rs./kW
Sales Sales Rs./kWh Rs./kWh Sales Sales Sales Sales h Sales Sales h h
h 2019- h 2020- h (2019-
(MUs) (MUs) 2019-20) 2020-21) (MUs) (MUs) (MUs) (MUs) (2020- (MUs) (MUs) (2019- (2020-
20) 21) 20)
21) 20) 21)
1 RGP 3400 3690 3.88 3.89 2801 2979 3.73 3.74 3996 4205 3.64 3.65 2418 2594 3.56 3.57
2 GLP 68 77 4.13 4.12 66 70 4.23 4.23 136 146 4.10 4.10 51 54 4.33 4.32
Non-RGP
3 5927 6,350 5.09 5.11 1,628 1716 5.42 5.44 3,744 3920 5.30 5.31 2,025 2,170 5.53 5.55
and LTMD
Public
4 Water 268 295 3.66 3.66 363 409 3.38 3.38 876 945 3.44 3.43 816 877 3.62 3.62
Works
Agriculture
5 417 417 1.41 1.41 475 475 1.41 1.41 4570 4570 1.42 1.42 6313 6313 1.41 1.41
Unmetered
Agriculture
6 461 499 1.19 1.19 933 1023 0.96 0.96 3601 4060 1.09 1.08 3119 3301 0.89 0.89
metered
7 Street Light 70 76 4.25 4.25 63 64 4.07 4.07 81 81 4.07 4.07 56 58 4.09 4.09
Industrial
8 8687 8901 5.40 5.45 4116 4339 5.35 5.39 12666 13932 5.11 5.15 8170 9218 5.08 5.06
HT
Railway
9 - - - - - - - - - - - - - - - -
Traction
10 Total 19297 20304 10446 11076 29668 31859 22968 24584
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid- Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-49: Revenue with existing Tariffs for FY 2019-20 and FY 2020-21 with approved sales
(Rs. Crore)
DGVCL MGVCL PGVCL UGVCL TOTAL
Sr. No. DISCOM
2019-20 2020-21 2019-20 2020-21 2019-20 2020-21 2019-20 2020-21 2019-20 2020-21
1 RGP 1318 1434 1044 1114 1456 1536 862 927 4680 5010
2 GLP 28 32 28 29 56 60 22 23 134 144
3 Non-RGP and LTMD 3019 3242 883 933 1983 2082 1119 1205 7003 7462
4 Public Water Works 98 108 123 138 301 325 296 318 817 889
Agriculture Unmetered 59 59 67 67 649 649 889 889 1664 1664
5 Agriculture Metered 55 59 90 99 392 439 278 295 815 892
6 Public Lighting 30 32 26 26 33 33 23 24 111 115
7 Industrial HT 4690 4852 2202 2338 6477 7174 4152 4662 17521 19026
8 Railway Traction 0 0 0 0 0 0 0 0 0 0
9 Total 9296 9817 4462 4745 11346 12299 7641 8343 32745 35204
Approved Sales
FPPPA @ 1.61 Rs./kWh
for FY 2019-20
10 3107 3208 1682 1750 4777 5034 3698 3884 13263 13876
and @ 1.58 Rs./kWh
for FY 2020-21
11 Other Income 235 235 109 109 215 215 203 203 763 763
12 Agriculture Subsidy 49 49 78 80 452 460 522 512 1100 1100
13 Grand Total 12687 13309 6331 6684 16790 18008 12063 12942 47871 50943
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-50: Aggregate Revenue Requirement for Power Purchase for FY 2019-20 and
FY 2020-21
(Rs. Crore)
Sr. No. Particulars 2019-20 2020-21
A Total Revenue of DISCOMS (A) 47871 50943
1 DGVCL 12687 13309
2 MGVCL 6331 6684
3 PGVCL 16790 18008
4 UGVCL 12063 12942
B Expenditure Other than Power Purchase (B) 5816 6296
5 DGVCL 991 1069
6 MGVCL 1001 1057
7 PGVCL 2609 2863
8 UGVCL 1214 1307
Amount available with the DISCOM for Power
C Purchase (A-B) 42055 44647
9 DGVCL 11695 12240
10 MGVCL 5330 5627
11 PGVCL 14180 15144
12 UGVCL 10849 11635
Table 5-52: Energy Requirement and Percentage Energy required for FY 2019-20 and
FY 2020-21
2019-20 2020-21
Sr. Energy Energy
DISCOM
No. Required Percentage Required Percentage
(MUs) (MUs)
1 DGVCL 22552 23% 23688 22%
2 MGVCL 12523 13% 13256 13%
3 PGVCL 37757 38% 40028 38%
4 UGVCL 26849 27% 28680 27%
Total 99680 100% 105652 100%
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioner’s submission
UGVCL has projected capital expenditure of Rs. 643.35 Crore for FY 2019-20 and Rs.
541.26 Crore for FY 2020-21 in Mid-Term Review against Rs. 541.81 Crore and Rs.
541.26 Crore approved in the MYT Order dated 31st March, 2017 as detailed in the
Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-57: Capital Expenditure loan in the Mid-Term Review for FY 2019-20 and FY 2020-21
(Rs. Crore)
2019-20 2020-21
Approved Approved
as per Projected as per Projected
Particulars
MYT in MTR MYT in MTR
Order Order
A Distribution Schemes
Normal Development Scheme 177.00 208.14 180.00 180.00
System Improvement Scheme 40.00 40.00 40.00 40.00
HVDS in selected Sub-division 4.50 4.50 4.50 4.50
Under Ground Cables 100.00 100.00 100.00 100.00
Plan Load Management Transformer 4.00 4.00 4.00 4.00
Others (VDS) 0.65 0.65 0.65 0.65
Total 326.15 357.29 329.15 329.15
B Rural Electrification Schemes – Plan - -
TASP(Wells & Petapara) 20.00 20.00 20.00 20.00
Schedule Caste Sub Plan (Wells) 4.00 4.00 3.00 3.00
Schedule Caste Sub Plan (lighting) 2.50 2.50 2.50 2.50
Electrification of Hutments 4.00 4.00 4.00 4.00
Kutir Jyoti Scheme 0.45 0.45 0.40 0.40
Dark Zone 100.00 140.00 100.00 100.00
Sagarkhedu 4.50 4.50 4.00 4.00
Sardar Krushi Jyoti (SKJY) Scheme - 16.40 - -
Solar home light 15.00 15.00 15.00 15.00
Total 150.45 206.85 148.90 148.90
C Central Government Scheme - Plan - -
Din Dayal Upadhyay Gramin Jyoti Yojana
- - - -
(DDUGJY)
RAPDRP Part A 2.05 2.05 2.05 2.05
Integrated Power Development Scheme
- - - -
(IPDS)
SCADA Part A 0.21 0.21 0.21 0.21
Smart grid 2.00 2.00 2.00 2.00
Total 4.26 4.26 4.26 4.26
D Non Plan Schemes - -
RE Non Plan (Tatkal) 2.00 2.00 1.00 1.00
AG Normal (SPA) 30.00 30.00 30.00 30.00
Energy Conservation 0.10 0.10 0.10 0.10
Total 32.10 32.10 31.10 31.10
E Other New Schemes - -
Automation and computerisation 4.35 4.35 4.35 4.35
Civil work New Building 12.00 12.00 12.00 12.00
GIS in cities 0.20 0.20 0.20 0.20
Other Schemes (earthing) 0.80 0.80 0.80 0.80
Other Repairing work / Civil work 2.00 2.00 2.00 2.00
New Furniture and Fixtures 1.00 1.00 1.00 1.00
Vehicles 0.50 0.50 0.50 0.50
DSM 2.00 2.00 2.00 2.00
DISS 5.00 15.00 - -
Solar Pump 5.00 5.00 5.00 5.00
Total 32.85 42.85 27.85 27.85
F Capital Expenditure Total 545.81 643.35 541.26 541.26
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
UGVCL has furnished the justification for revision in the capital expenditure as given
below:
(A) Revised Capex : Looking to the present infrastructure growth among the
peripheral area of Ahmedabad and Gandhinagar hence the revision of capex for
the year 2019-20 is increased to Rs. 208.14 Crore from Rs. 177.00 Crore for FY
2019-20.Following is the revised Capex for the year FY 2019-20:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
projected Rs. 124.00 Crores, Rs. 123.00 Crores for the FY 2019-20 and FY 2020-
21 respectively.
Commission’s Approval
The Commission accepts the justification given by UGVCL for the projected capital
expenditure in the Mid-Term Review for FY 2019-20 and FY 2020-21 and approves
the capital expenditure of Rs. 643.35 Crore and Rs. 541.26 Crore for these years
respectively. The Commission has approved the scheme wise CAPEX as proposed by
the Petitioner for FY 2019-20 and FY 2020-21. While truing up, Petitioner is required
to submit the details of scheme wise CAPEX including target and actual date of
commissioning. The Commission shall allow such CAPEX after prudence check in
respect to cost incurred, time taken to complete the project and cost benefit analysis.
The Petitioner shall also justify the competitiveness of the cost incurred.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Commission’s Analysis
The Commission has observed that UGVCL has proposed capitalization of the entire
capital expenditure proposed to be incurred during FY 2019-20 and FY 2020-21. The
Commission has verified the actual capitalization against capital expenditure incurred
during the first two financial years of the control period of the MYT and has observed
that the Petitioner has achieved more than 90% capitalization during FY 2016-17 and
more than 100% capitalization during FY 2017-18 as can be seen from the table below
Table 5-59: Approved CAPEX vs Actual CAPEX & Actual Capitalization for FY 2016-17
and FY 2017-18
(Rs. in Crore)
Particulars 2016-17 2017-18
Approved CAPEX in MYT Order 813.66 784.43
Actual CAPEX 517.82 629.31
Capitalization 474.83 672.04
In view of the above, the Commission approves the capitalization and funding thereof
proposed by UGVCL as given in the table below:
Table 5-60: Approved CAPEX, Capitalization and Funding for the FY 2019-20 and FY
2020-21
(Rs. Crore)
Particulars 2019-20 2020-21
CAPEX 643.35 541.26
Capitalization 643.35 541.26
Less: Consumer contribution 72.65 73.20
Less: Grants 129.95 122.90
Balance Capitalisation 440.75 345.16
Debt @ 70% 308.53 241.61
Equity @ 30% 132.23 103.55
UGVCL has projected the O&M expenses at Rs. 840.71 Crore for FY 2019-20 and
Rs.942.07 Crore for FY 2020-21 in the Mid-Term Review petition. The O&M expenses
approved for these years in the MYT Order dated 31st March 2017 and the revised
projection submitted by UGVCL are given in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-61: O&M expenses projected for the FY 2019-20 and FY 2020-21
(Rs. Crore)
2019-20 2020-21
Sr.
Particulars Approved Projected Approved Projected
No.
in MYT in MTR in MYT in MTR)
1 Employee Cost 473.43 734.53 500.51 829.82
2 Repair & Maintenance 98.91 98.91 104.57 104.57
Administration & General
3 84.60 84.60 89.44 89.44
Charges
4 Other Debits 0.00 0.00 0.00 0.00
5 Extraordinary Items 0.00 0.00 0.00 0.00
Net Prior Period Expenses /
6 0.00 0.00 0.00 0.00
(Income)
7 Other Expenses Capitalised (161.75) (77.33) (171.00) (81.76)
Operation & Maintenance
8 495.19 840.71 523.51 942.07
Expenses
Petitioner’s Submission
UGVCL has submitted that the O&M Expenses consist of Employee Cost,
Administration & General Expenses, Repairs and Maintenance Expenses, Other
Debits, Extraordinary Items, and Net Prior Period Income/Expenses.
Regulation 94.8 of GERC MYT Regulations, 2016 states the following methodology for
projection of O&M Expenses:
The increase in O&M expenses is on two counts (i) inflationary increase and (ii)
increase in the scale of distribution network operation due to increase in network
length, load handling capacity and number of consumers being served, etc. as
compared to base years. The escalation factor of 5.72% per annum takes care of only
the change in O&M expenses on account of inflationary increase. However, it is not
addressing the issue of escalation in O&M expenses due to increased scale of
distribution operations which is beyond the control of the distribution licensee.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The growth in the Employee expenses at 3-year CAGR for the period from FY 2014-
15 to FY 2017-18 excluding the impact of 7th Pay Commission is shown in the following
Table:
UGVCL submitted that considering the above, the actual Employee expenses of FY
2017-18 excluding the impact of 7th Pay Commission is escalated at 12.42% for FY
2019-20 and FY 2020-21. Further, the actual impact of 7th Pay Commission in FY 2017-
18 was there only for the part of the year and that too for only a part of the employees
and is therefore expected to be substantially higher in subsequent years when the
impact is considered for full year for all employees. Considering this, the impact of 7 th
Pay Commission is considered at 20% of salary component for FY 2019-20 and FY
2020-21.
UGVCL submitted that the A&G and R&M expenses for FY 2019-20 and FY 2020-21
are computed as per the GERC (MYT) Regulations, 2016 according to which the
Operation and Maintenance expenses shall be derived on the basis of the average of
the actual Operation and Maintenance expenses for the three (3) years ending 31st
March, 2015. The average of such Operation and Maintenance expenses shall be
considered as Operation and Maintenance expenses for the financial year ended 31st
March, 2014 and shall be escalated year on year at the escalation factor of 5.72% to
arrive at Operation and Maintenance expenses for subsequent years up to FY 2020-
21. Accordingly, the A&G and R&M expenses for FY 2019-20 and FY 2020-21 have
been computed.
The expenses capitalised for FY 2017-18 have been escalated at 5.72% to derive the
expenses capitalised for FY 2019-20 and FY 2020-21.
Other Debits, Extraordinary Items and Net Prior Period Expense/ (Income) are not
considered for projection.
Commission’s Analysis
The Commission examined the O&M expenses incurred by UGVCL during FY 2017-
18 component wise. The GERC (MYT) Regulations, 2016 provides for escalation of
O&M Expenses viz, Employee Cost, Repairs and Maintenance Expenses,
Gujarat Electricity Regulatory Commission Page 138
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Administration and General Expenses and Expenses Capitalized @ 5.72% p.a. for FY
2017-18 onwards.
The Commission, accordingly, approves the R&M Expenses, A&G Expenses and
Expenses Capitalised with 5.72% escalation p.a for FY 2019-20 and FY 2020-21 over
the actuals incurred under these heads during FY 2017-18 as trued up in this Order.
The Other Debits are not projected by the Petitioner and therefore, not considered by
the Commission in this Order.
The Commission noted that there is a revision in the Pay Scale of employees of the
Petitioner on account of 7th Pay Commission. It is also noted by the Commission that
only a part of the employees availed the revised salary and that too for a part of the
year during FY 2017-18. On a query from the Commission, the Petitioner vide e-mail
dated 27.02.2019 confirmed that during FY 2017-18, all non-technical employees and
Class III and IV technical employees opted the revised salary and Class I and II
technical employees did not opt the revised salary. It is clarified by the Petitioner that
the revised salary was paid from 1st August, 2017. It is also clarified that no arrears
was paid to the employees during FY 2017-18 on account of revision of salary.
In view of above, the Commission has considered eight months actual paid out amount
due to revision in salary annualised for twelve months plus the pre-revised annual
salary for FY 2017-18 to escalate @ 5.72% Y-o-Y to arrive at employee expenses for
FY 2019-20 and FY 2020-21. The Commission shall consider actual employee
expenses as uncontrollable to the extent of actual payout on account of revision in
salaries and allowances while truing up of FY 2019-20 and FY 2020-21.
Accordingly, the approved O&M expenses are given in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
5.12.2 Depreciation
UGVCL has projected Depreciation at Rs.248.47 Crore for FY 2019-20 and Rs. 273.65
Crore for FY 2020-21 based on the revised capital expenditure projected in the Mid-
Term Review for these years. The depreciation approved for these years in the MYT
order dated 31st March, 2017 and revised projections submitted by UGVCL are given
in the Table below:
Table 5-64: Depreciation projected for the Control Period FY 2019-20 to FY 2020-21
(Rs. Crore)
2019-20 2020-21
Sr.
Particulars Approved Projected Approved Projected
No.
in MYT in MTR in MYT in MTR
1 Gross Block in Beginning of the year 7419.87 5511.90 7965.68 6155.25
2 Additions during the Year (Net) 545.81 643.35 541.26 541.26
3 Depreciation for the Year 399.19 248.47 427.81 273.65
4 Average Rate of Depreciation 5.19% 4.26% 5.19% 4.26%
Petitioner’s Submission
UGVCL has considered the Closing Gross Block of fixed assets of FY 2017-18 as the
Opening Gross Block of fixed assets of FY 2018-19. The addition during 2018-19 to
2020-21 has been projected considering projected capitalisation for the same for each
year. Depreciation has been calculated taking into consideration the Opening Balance
of assets at the beginning of the year and the projected capitalisation. The depreciation
for assets which have completed 12 years from the Transfer Scheme of the State
Government effective from 1st April 2005, has been computed considering the balance
depreciation (difference of GFA as on 1st April, 2017 less accumulated depreciation)
spread equally over the remaining useful life of these assets (23 years considering
useful life of 35 years). This methodology is in line with the GERC (MYT) Regulations,
2016 and the directives of the Commission. The depreciation for the other assets has
also been computed in accordance with the rates specified in the GERC (MYT)
Regulations, 2016.
Commission’s Analysis
The Commission has observed that the Petitioner has computed the depreciation
based on the proviso to Regulation 39(b) of the GERC(MYT), Regulations, 2016.
Accordingly, the Commission has approved the Depreciation as given in the Table
below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission approves the Depreciation at Rs. 248.47 Crore for FY 2019-20
and Rs. 273.65 Crore for FY 2020-21 in the Mid-Term Review.
UGVCL has projected the interest and finance charges including interest on security
deposit from consumers and guarantee charges at Rs. 189.21 Crore for FY 2019-20
and Rs. 201.94 Crore for FY 2020-21 in the Mid-Term Review petition. The interest
charges approved for these years in the MYT Order dated 31st March, 2017 and the
revised projections submitted in the Mid-Term Review are given in the Table below:
Table 5-66: Interest and Guarantee Charges projected in the Mid-Term Review
(Rs. Crore)
Sr. 2019-20 2020-21
No. Particulars Approved Projected Approved Projected
in MYT in MTR in MYT in MTR
1 Opening Loans 452.67 699.05 293.72 759.11
2 Additions during the Year 240.25 308.53 241.61 241.61
3 Repayments during the Year 399.19 248.47 427.81 273.65
4 Closing Loans 293.72 759.11 107.53 727.07
5 Average Loans 373.19 729.08 200.63 743.09
6 Weighted Average Rate of Interest 0.07 0.11 0.07 0.11
7 Interest on Loan 27.13 76.63 14.59 78.10
8 Interest on Security Deposit 112.93 112.58 124.22 123.84
9 Guarantee Charges 0.83 0.00 0.83 0.00
10 Total Interest & Financial Charges 140.89 189.21 139.64 201.94
Petitioner’s submission
UGVCL has submitted that it has considered the Closing Balance of loans for FY 2017-
18 as the Opening Balance of FY 2018-19. The normative loan addition in FY 2018-19
to FY 2020-21 is computed as per the Capex funding plan. Repayment of loan is
considered equivalent to depreciation and the rate of interest has been taken as the
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
weighted average rate of interest on the actual loan portfolio being 10.51%. The
interest on security deposit has been considered at 7.75% prevailing RBI bank rate as
approved by the Commission in the MYT Order dated 31st March, 2017. Security
Deposit is projected based on year on year growth rate of 10% over the actuals for FY
2017-18 for the remaining control period. Other finance charges comprising guarantee
and bank charges are proposed same as actuals of FY 2017-18.
Commission’s Analysis
The Opening Balance of loans for FY 2018-19 is taken as per actual normative Closing
Balance for FY 2017-18. The Commission has approved the capitalisation and funding
of capital expenditure in Table 5-60 above. The Commission has considered the
weighted average rate of interest of 9.96% based on the actual loan portfolio submitted
by UGVCL vide e-mail dated 19.01.2019 for FY 2017-18, as per the GERC (MYT)
Regulations, 2016.
In respect of Interest on Security Deposit, UGVCL has proposed the bank rate of
7.75%. However, the RBI bank rate was 6.25% as on 07.02.2019 and the Commission
has applied this rate on the average balance of security deposit to arrive at the interest
on security deposit. The growth in deposit is considered at 10.00% p.a. as proposed
by UGVCL. The repayment of loan is considered equivalent to depreciation approved
in Table 5-65 above accordance with the GERC (MYT) Regulations, 2016. The
guarantee and other bank charges are considered at the level of actuals for FY 2017-
18. Considering all the above, the Commission has computed the interest and finance
charges in the Mid-Term Review as detailed in the Table below:
Table 5-67: Approved Interest and Finance Charges in the Mid-Term Review
(Rs. Crore)
Sr. No. Particulars 2018-19 2019-20 2020-21
1 Opening Loans 662.63 699.05 759.11
2 Additions during the year 257.22 308.53 241.61
3 Repayments during the year 220.80 248.47 273.65
4 Closing Loans 699.05 759.11 727.07
5 Average Loans 680.84 729.08 743.09
6 Rate of Interest 9.96% 9.96% 9.96%
7 Interest Charges 67.83 72.64 74.03
8 Opening Security Deposit 1257.76 1383.54 1521.89
9 Additions during the year 125.78 138.35 152.19
10 Closing Security Deposit 1383.54 1521.89 1674.08
11 Average Security Deposit 1320.65 1452.72 1597.99
12 Rate of Interest on Security Deposit 6.25% 6.25%
13 Interest on Security Deposit 90.79 99.87
14 Guarantee Charges 0.00 0.00
15 Interest and Finance Charges (7+13+14) 163.43 173.91
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission approves the Interest and Finance charges at Rs. 163.43 Crore
for FY 2019-20 and Rs. 173.91 Crore for FY 2020-21 in the Mid-Term Review.
UGVCL has not claimed Interest on Working Capital as the Security Deposit available
is higher than the allowable normative Working Capital.
Commission’s Analysis
The Commission has examined the computation of Interest on Working Capital
submitted by DGVCL. Based on the approved O & M Expenses, GFA, Total Revenue
and Average Security Deposit the Commission has computed the Working Capital and
Interest on Working Capital, as detailed in the Table below;
Table 5-69: Interest on Working Capital approved in the Mid-Term Review
(Rs. Crore)
2019-20 2020-21
Sr.
Particulars Approved Approved Approved Approved
No.
in MYT in MTR in MYT in MTR
1 O & M Expenses 41.27 59.26 43.63 62.64
2 Maintenance Spares 74.20 69.69 79.66 76.12
3 Receivables 885.95 1005.29 923.15 1078.50
Less : Amount held as Security
4 Deposit 1457.18 1452.72 1602.90 1597.98
from Consumers
5 Total Working Capital (455.77) (318.48) (556.47) (380.72)
Rate of Interest on Working
6 11.70% 10.65% 11.70% 10.65%
Capital
7 Interest on Working Capital - - - -
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
UGVCL has considered the provision for bad and doubtful debts at Rs. 0.31 Crore for
FY 2019-20 and Rs. 0.31 Crore for FY 2020-21 in the Mid-Term Review petition. The
provision approved for these years in the MYT order dated 31st March 2017, and the
revised provision submitted in the Mid-Term Review are given in the Table below:
Table 5-70: Provision for Bad and Doubtful debts projected for the FY 2019-20 and FY
2020-21
(Rs. Crore)
2019-20 2020-21
Sr.
Particulars Approved Projected Approved Projected
No.
in MYT in MTR in MYT in MTR
1 Provision for Bad Debts 0.70 0.31 0.70 0.31
Petitioner’s Submission
UGVCL has submitted that it has considered the provision for bad & doubtful debts for
the remaining control period FY 2019-20 and FY 2020- as actuals of FY 2017-18.
UGVCL has further submitted that it is a very legitimate expenditure which is
associated with the business risk and is a consumer related expense as UGVCL is in
a distribution business.
Commission’s Analysis
Regulations 94.9 of the GERC (MYT) Regulations, 2016, specifies that the
Commission may allow bad debts written off as a pass through, in the ARR. The
allowable actual bad debts written off were Rs. 0.31 Crore as per audited annual
accounts for FY 2017-18.
The Commission approves the bad and doubtful debts written off at the level of actual
bad debts written off FY 2017-18 for FY 2019-20 and FY 2020-21 in the Mid-Term
Review. However, actual bad debts written off shall be allowed by the Commission
after prudence check at the time of truing up for FY 2019-20 and FY 2020-21.
The approved bad and doubtful debts written off in the Mid-Term Review is given in
the Table below:
Table 5-71: Bad and Doubtful Debts Written-off approved in the Mid-term Review
(Rs. Crore)
Sl. No. Particulars 2019-20 2020-21
1 Bad and Doubtful Debts Written off 0.31 0.31
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
UGVCL has projected the Return on Equity at Rs. 215.36 Crore for FY 2019-20 and
Rs. 231.86 Crore for FY 2020-21 @14% in the Mid-Term Review petition. The Return
on Equity approved for these years in the MYT Order dated 31st March, 2017 and the
revised projection submitted in the Mid-Term Review are given in the Table below:
Petitioner’s Submission
UGVCL has submitted that Return on Equity has been computed @ 14% on average
Equity based on the Opening Balance of Equity and normative additions during the
year, which has been arrived at by considering 30% of the capitalization net of
consumer contribution and grants as funded from Equity.
Commission’s Analysis
The Commission has computed Return on Equity @14% on the average Equity of
Opening and Closing Balance with additions during the year approved in Table 5-60
above as given in the Table below:
The Commission approves Return on Equity at Rs. 215.36 Crore for FY 2019-20
and Rs. 231.86 Crore for FY 2020-21 in the Mid-Term Review.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
UGVCL has considered Income Tax at Rs. 14.38 Crore for FY 2019-20 and FY 2020-
21 in the Mid-Term Review against Rs. 17.14 Crore for each year approved in the MYT
Order dated 31st March 2017 as detailed in the Table below:
Petitioner’s Submission
UGVCL has submitted it has considered Income Tax as per the actual Income Tax
paid in FY 2017-18 as per the audited accounts.
Commission’s Analysis
Regulation 41.1 of the GERC (MYT) Regulations, 2016, specifies that the Commission
in the MYT Order shall provisionally approve income tax payable for each year of the
control period, if any, based on the actual income tax paid as per the latest audited
accounts available for the applicant, subject to prudence check. The latest audited
accounts available for UGVCL is for FY 2017-18 and the Income Tax for FY 2017-18
is Rs. 14.38 Crore.
The Commission accordingly approves the Income Tax as per actual Income Tax paid
for FY 2017-18 in the Mid-Term Review for these years as given in the Table below:
UGVCL has projected the Non-Tariff Income at Rs. 138.68 Crore for. FY 2019-20 and
FY 2020-21 in the Mid-Term Review against Rs. 146.76 Crore approved for these
years in the MYT Order dated 31st March, 2017 as detailed in the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 5-76: Non-Tariff Income projected in the Mid-Term Review
(Rs. Crore)
2019-20 2020-21
Sr. Approved Approved
Particulars Projected Projected
No. in MYT in MYT
in MTR in MTR
Order Order
1 Non-Tariff Income 146.76 138.68 146.76 138.68
Petitioner’s Submission
UGVCL has submitted that it has considered Non-Tariff Income for the remaining
control period for FY 2019-20 and FY 2020-21 under respective heads (excluding
Delayed Payment Charges as per Regulation 97.2 of the GERC (MYT) Regulations,
2016) same as the actual figures of FY 2017-18.
Commission’s Analysis
The Commission has approved the actual Non-Tariff Income of Rs. 138.68 Crore at
Table 4-52 of this Order in the True up of FY 2017-18 which excludes the Delayed
Payment Charges. Accordingly, the Commission approves Non-Tariff Income in the
Mid-Term Review as given in the Table below:
Table 5-78: Aggregate Revenue Requirement for the FY 2019-20 and FY 2020-21
(Rs. Crore)
Approved for Mid-Term Review
Sr. No. Particulars
2019-20 2020-21
1 Cost of Power Purchase 11128.50 11843.65
2 Operations & Maintenance Expenses 711.06 751.74
2.1 Employee Cost 608.92 643.75
2.2 Repairs & Maintenance Expenses 68.58 72.50
2.3 Administration & General Expenses 110.90 117.24
2.4 Other Debits 0.00 0.00
2.5 Extraordinary Items 0.00 0.00
2.6 Net Prior Period Expenses / (Income) 0.00 0.00
2.7 Other Expenses Capitalised (77.33) (81.76)
3 Depreciation 248.47 273.65
4 Interest & Finance Charges 163.43 173.91
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Approved for Mid-Term Review
Sr. No. Particulars
2019-20 2020-21
5 Interest on Working Capital 0.00 0.00
6 Bad Debts Written off 0.31 0.31
7 Sub-Total [1 to 6] 12251.77 13043.26
8 Return on Equity 215.36 231.86
9 Provision for Tax / Tax Paid 14.38 14.38
10 Total Expenditure (7 to 9) 12481.51 13289.50
11 Less: Non-Tariff Income 138.68 138.68
12 Aggregate Revenue Requirement (10 - 11) 12342.83 13150.82
The Commission approves the revised ARR at Rs. 12342.83 Crore for FY 2019-
20 and Rs. 13150.82 Crore for FY 2020-21 in the Mid-Term Review.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 6-1: Sales (MUs) and Revenue (Crs.) from existing tariff projected for FY 2019-20
Petitioner’s submission
UGVCL submitted that it has considered sale of 22967.58 MUs to different categories
of consumers as per MTR petition as shown in the Table above and the existing retail
tariff to work out the revenue from sale of power at Rs. 7640.78 Crore for FY 2019-20.
Commission’s Analysis
The Commission observed UGVCL has considered the category-wise sales for FY
2019-20, as approved in Table 5.19 of this Order. Taking into consideration the same
and the exiting tariff for each category, the Commission has computed the revenue
from sale of power for FY 2019-20 as detailed in the Table below:
Table 6-2: Approved Sales (MUs) and Revenue from existing tariff for FY 2019-20
Sr. No. Particulars Units Amount in Rs. Crore
A LT Consumers
1 RGP 2418.12 861.90
2 GLP 50.79 21.98
3 Non-RGP & LTMD 2024.59 1118.68
4 Public Water Works 816.42 295.87
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Sr. No. Particulars Units Amount in Rs. Crore
5 Agriculture-Metered 3118.88 278.44
6 Agriculture-Unmetered 6312.65 889.25
7 Street Light 56.19 22.98
LT Total (A) 14797.64 3489.10
B HT Consumers
1 Industrial HT 8169.94 4151.68
2 Railway Traction 0.00 0.00
HT Total (B) 8169.94 4151.68
Grand Total (A + B) 22967.58 7640.78
Table 6-3: Projected Revenue from FPPPA Charges for the FY 2018-19
(Rs. Crore)
Particulars Amount
Rate of FPPPA (Rs./.kWh) 1.63
Sales (MUs) 22967.58
FPPPA charges in Rs. Crore 3743.72
Petitioner’s submission
UGVCL has submitted that In the True up Order for FY 2016-17 dated 31st March,
2018, the Commission has considered the base power purchase cost at Rs. 4.22/unit
and base FPPPA at Rs. 1.49/unit. As per the approved FPPPA formula, any increase
in power purchase cost during the year over and above base power purchase cost of
Rs. 4.22/unit is to be recovered through FPPPA over and above base FPPPA of Rs.
1.49/unit on quarterly basis. As per projected ARR for FY 2019-20, the weighted
average power purchase cost is worked out to Rs. 4.34/unit as against base power
purchase cost of Rs. 4.22/unit. Thus, the incremental power purchase cost of Rs.
0.12/unit for FY 2019-20 (i.e. Rs. 4.34 - 4.22)will be recovered through FPPPA over
and above base FPPPA of Rs. 1.49/unit. Therefore, estimated revenue from FPPPA
for FY 2019-20 is considered at Rs. 1.63/unit for FY 2019-20 (i.e. grossing up by
approved losses), as shown below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Sr. No. Particulars 2018-19 2019-20
6 SLDC Charge 8 16
7 Total Power Purchase Cost 38838 43240
8 Total Energy Requirements 91973 99680
9 Power purchase Cost (Rs. /kWh) 4.22 4.34
10 Increase in Power Purchase Cost 0.12
Additional FPPPA Charges (Grossed up by
11 0.14
Loss)
12 Existing FPPPA Charges (Rs./kWh) 1.49
13 Revised FPPPA Charges (Rs./kWh) 1.63
Commission’s Analysis
The Commission allows FPPPA charges FY 2019-20 at 1.61 Rs. per kWh considering
the Fixed Cost and variable Cost as approved at Table 5.46 and 5.47 of this Order as
shown in Table below:
Accordingly, the Commission allows FPPPA charges and revenue therefrom on the approved
sales of 22967.58 MUs for FY 2019-20 at 1.61 Rs./kWh as shown in the Table below:
Table 6-6: Approved Revenue from FPPPA Charges for the FY 2019-20
(Rs.Crore)
Particulars Amount
Rate of FPPPA considered (Rs./.kWh) 1.61
Sales (MUs) 22967.58
Base FPPPA Charges (Rs. Crore) 3697.78
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Petitioner’s submission
UGVCL has submitted that the revenue from other consumer related income
comprises of revenue on account of charges other than the basic charges applicable
to the Consumers. These include income on account of meter rent, wheeling charges,
inspection charges and miscellaneous charges.
Commission’s Analysis
The Commission has observed that UGVCL has projected the other consumer related
income for FY 2019-20 as actuals of FY 2017-18 excluding the meter rent.
The Commission, accordingly, approves the other consumer related income at Rs.
203.30 Crore for FY 2019-20.
Table 6-8: Approved other consumer related Income for FY 2019-20
(Rs. Crore)
Particulars 2019-20
Other Income Consumer Related 203.30
UGVCL submitted that the annual Agricultural Subsidy that was being received by the
erstwhile GEB from the State Government will continue to be received by the four
DISCOMs i.e. Rs 1100 Crores. The share of Agricultural Subsidy for FY 2019-20 is
considered on pro-rata basis of agriculture consumption.
Commission’s Analysis
The Commission considered the Agriculture Subsidy as claimed by the Petitioner.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission considered the the Agriculture subsidy claimed by the Petitioner
The Commission, accordingly, approves Agricultural Subsidy as Rs.521.64
Crore for FY 2019-20.
The total expected revenue for UGVCL comprises of revenue from sale of power at
existing tariff, FPPPA charges, other consumer related income and Agriculture
Subsidy. Total revenue for FY 2019-20 is shown in the Table below:
Table 6-11: Projected Revenue for FY 2019-20
(Rs. Crore)
Sr. No. Particulars Amount
1 Revenue with Existing Tariff 7640.78
2 Base FPPPA Charges @ 163 paisa/kWh 3743.72
3 Other Income (Consumer related) 203.3
4 Agriculture Subsidy 521.64
5 Total Revenue including subsidy (1 to 4) 12109.44
Commission’s Analysis
The total revenue as estimated by the Commission for FY 2019-20 is shown in the
Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 6-13: Approved Mid-Term Review ARR for FY 2019-20
(Rs. Crore)
Sr. No. Particulars Amount
2019-20
1 Cost of Power Purchase 11128.50
2 Operations & Maintenance Expenses 711.06
2.1 Employee Expenses 608.92
2.2 Repairs & Maintenance 68.58
2.3 Administration & General Expenses 110.90
2.4 Other Debits 0.00
2.5 Extraordinary Items 0.00
2.6 Net Prior Period Expenses / (Income) 0.00
2.7 Other Expenses Capitalised (77.33)
3 Depreciation 248.47
4 Interest & Guarantee Charges 163.43
5 Interest on Working Capital 0.00
6 Provision for Bad Debts 0.31
7 Sub-Total [1 to 6] 12251.77
8 Return on Equity 215.36
9 Provision for Tax / Tax Paid 14.38
10 Total Expenditure (7 to 9) 12481.51
11 Less: Non-Tariff Income 138.68
12 Aggregate Revenue Requirement (10 - 11) 12342.83
Table 6-14: Estimated Revenue (Gap)/Surplus for FY 2019-20 at Existing Tariff for
UGVCL
(Rs. Crore)
Approved by
Sr. Projected
Particulars the
No. by UGVCL
Commission
1 Aggregate revenue requirement 12526.72 12342.83
2 Revenue (Gap)/ Surplus from True up of FY 2017-18 (34.52) (43.20)
3 Total aggregate revenue requirement (1-2) 12,561.25 12386.03
4 Revenue with existing tariff 7640.78 7640.78
5 PPPA charges @ 161 paisa/kWh 3743.72 3697.78
6 Other income (Consumer related) 203.30 203.30
7 Agriculture Subsidy 521.64 521.64
8 Total revenue including subsidy (4+5+6+7) 12109.44 12063.51
9 (Gap)/Surplus (8-3) (451.81) (322.53)
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
UGVCL has stated that there is a pending Ag. Subsidy of Rs. 1665 Crore against
subsidy for FY 2017-18 from Government of Gujarat. As per Section 65 of the
Electricity Act, 2003, the subsidy was required to be released in advance. GUVNL has
requested Government of Gujarat for release of outstanding subsidy amount.
Accordingly, after consideration of the amount of outstanding subsidy, the resultant
Surplus works out to Rs. 815.83 Crore (1665-849.17) for FY 2019-20.
It is observed that there is a Surplus of Rs. 187.87 Crore against the true up of FY
2017-18, which is due to disallowance of Rs. 440.40 Crore claim of DGVCL on account
of non-recovery of dues pending before various adjudicating authorities on the amount
receivable from M/s Essar Steel India Limited. Therefore, this Surplus is not allowed
to be passed through at this stage.
Further, the remaining surplus is on account of Mid-Term Review sought by the
Petitioners and approval of the Commission based on the various parameters and
Regulations of the third MYT period. The Commission feels that it may not be
reasonable that such surplus to be passed through in the tariff as in response of
representations of certain category of consumers, the Commission has made some
changes in slab rate, optional tariff and reduction in Lift Irrigation tariff. Similarly, there
are certain changes likely in the energy sales of high value consumers due to Open
Access, uncertainty in power market, impact of revision in employee cost of DISCOMs
on account of 7th Pay Commission etc. Hence, the Commission may consider such
variations in the ARR of respective year true up.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
7 Compliance of directives
Compliance:
UGVCL has submitted the progress report on providing Meters on Distribution
Transformers as on September, 2018 as under:
Distribution Transformer Metering SEPT.18
DTR with Single
Metered No. of
No. of No. of
Consumer DTs % DT
Discom Category Distribution DTs Pending
which is metered Metered
Transformer metered
considered as physically
DTR with Meter
UGVCL Industrial 7235 2333 4902 7235 100.00 0
GIDC 1490 363 1127 1490 100.00 0
Urban 13792 640 13152 13792 100.00 0
JGY 29744 3129 26615 29744 100.00 0
AG. DOM 225403 142608 82795 225403 100.00 0
Total 277664 149073 128591 277664 100.00 0
Commission’s comments:
DISCOMs are directed to identify the feeders with more than 50 % loss level and 5%
loss reduction should be targeted for such feeders.
Compliance:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
UGVCL has submitted the status of Distribution losses of JGY Feeders as under:
UGVCL has submitted that in JGY category overall % distribution losses are reduced
from 22.23% (2012-13) to 18.96% (2017-18) i.e reduced by 3.27% in last five years.
Also in 54 Nos of JGY High losses feeders having more than 50% distribution losses
is in reducing trends as per above table and out of 54 Nos of feeders up to Aug-18, 22
Nos of JGY feeders losses are reducing trends compared to target and 33 Nos of JGY
feeders losses are in reducing trend compared to previous year same period.
Company has made full efforts for reducing distribution losses on JGY feeders.
Commission’s comments:
The Commission has directed UGVCL to submit a report about actions taken to reduce
technical and commercial losses on HT system and LT system including different
feeders, transformers (DTC) on monthly basis to the Commission so as to monitor the
losses
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Compliance: .
UGVCL submitted that the Cmpany has carried out activities like replacement of stop
meters, provided Static meters in place of slow and sluggish old electromechanical
meters, provided SMC, provided Aerial Bunch Conductor in place of open bare
conductors, increase in HT/LT ratio, adoption of high voltage distribution system
(HVDS), preventive and regular maintenance, Load Balancing, publicity campaign on
theft of electricity as a social and economic crime and people informed of the provisions
in electricity laws, public relation and awareness campaigns by utility, etc. As per BIS
guideline, from FY: 2018-19 our utility is implemented to install star rated distribution
transformer so that level 2 in agriculture feeders. Also by constant monitoring from
higher authority and respective officers on all the high losses feeders allocated, the
micro plan has already been implemented for further reduction of losses on feeders.
In this context, following specific activities has been carried out on feeders by the
Company:
Commission’s comments:
The Commission directed to ensure correct functioning of the meters so that the energy
consumption is reflected correctly and accordingly correct revenue is earned from the
consumers against cost of supply.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Compliance:
UGVCL has submitted that the faulty or improperly functioning meters are replaced
regularly based on the monthly generated reports. This is a continuous process as new
faulty meters are added during the month and the replacement of the same is also
being carried out during the month.
Commission’s comments:
The Commission noted the compliance submitted by the Petitioner and directed to
continue efforts to replace the defective energy meters as planned. Utilities may also
conduct a study to understand the nature of fault and take up the issue with the
manufacturers of such meters for mitigation.
Compliance:
GUVNL has tied up adequate capacity on long term basis which can successfully meet
the entire power demand including peak demand. However, availability of power from
imported coal based projects has been highly varying during last 2 years specifically
after Hon’ble Supreme Court’s Order dated 11.4.2017.
As per the directive of the Commission and in order to ensure procurement of power
at competitive rates and to optimize overall power purchase cost, GUVNL in
consultation with SLDC, had invited bids well in advance in Jan-18 and tied up around
300 MW power for the period of March 2018 to May 2018 and also tied up 200-1025
MW for the period of September 2018 to December 2018 by inviting tender in July-18
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
In addition, GUVNL had invited bid for tie up of 500 MW power under Flexible Coal
Utilization Scheme of Ministry of Power wherein supply is already commenced from
Jan-18 which has enabled savings in coal transportation cost and ensured supply at
competitive rates. GUVNL has also invited second bid for tie-up of 1000 MW power
under flexible coal utilization scheme.
Commission’s comments:
The Commission noted the compliance of the Petitioner. It is further directed to sale
Surplus power in the market looking to the availability of significant amount of cheaper
RE power in the State by optimizing grid operations in consultation with SLDC/GUVNL
so as end consumer gets benefited.
Compliance:
On behalf of 4 DISCOMs, GUVNL has engaged a consultant to carry out a detailed
study as per above directive of the Commission. The study work is under progress and
the study report shall be submitted to the Commission in due course upon successful
completion of study.
Commission’s comments:
DISCOMs are directed to ensure timely completion of the study and submit the report
by 30th June, 2019.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Compliance:
In order to achieve multiple objectives of addressing the energy requirement of farmers
and to promote de-centralized renewable energy generation, the State Government
decided to utilize solar resources available in the State for the benefits of the farmers
and accordingly notified the Scheme namely Suryashakti Kisan Yojna (SKY) to be
implemented on pilot basis.
Commission noted compliance of the Petitioner and directed to submit the outcome of
pilot project.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Compliance:
On behalf of 4 DISCOMs, GUVNL has engaged a consultant to carry out a detailed
study as per above directive of the Commission. The study work is under progress and
the study report shall be submitted to the Commission in due course upon successful
completion of study.
Commission’s comments:
DISCOMs are directed to ensure timely completion of the study and submit the report
by 30th June, 2019
Petitioner is directed to report the outcome of HVDS implementation along with the
petition of next Tariff Order.
Directive 2:
Petitioner is directed to keep the FPPPA information available on their website for all
the quarters of a year till the truing up exercise of that particular year is completed.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
is the average power purchase cost per unit of delivered energy (including
transmission cost), computed based on the operational parameters
approved by the Commission or principles laid down in the Power Purchase
Agreements in Rs./kWh for all the generation sources as approved by the
PPCA Commission while determining ARR and who have supplied power in the
given quarter and transmission charges as approved by the Commission for
transmission network calculated as total power purchase cost billed in Rs.
Million divided by the total quantum of power purchase in Million Units made
during the quarter.
is the approved average base power purchase cost per unit of delivered
energy (including transmission cost) for all the generating stations
considered by the Commission for supplying power to the company in
PPCB Rs./kWh and transmission charges as approved by the Commission
calculated as the total power purchase cost approved by the Commission in
Rs. Million divided by the total quantum of power purchase in Million Units
considered by the Commission.
is the weighted average of the approved level of Transmission and
Distribution losses (%) for the four DISCOMs / GUVNL and TPL applicable
for a particular quarter or actual weighted average in Transmission and
Loss in %
Distribution losses (%) for four DISCOMs / GUVNL and TPL of the previous
year for which true-up have been done by the Commission, whichever is
lower.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Table 8-1: Base price of power purchase
As mentioned above the base Power Purchase cost for the DISCOMs is Rs. 4.32/kWh.
GUVNL/DISCOMs may claim difference between actual power purchase cost and
base power purchase cost approved in the Table above as per the approved FPPPA
formula mentioned above.
Information regarding FPPPA recovery and the FPPPA calculations shall be kept on
the website of the Licensee / GUVNL.
For any increase in FPPPA, worked out on the basis of above formula, beyond ten (10)
paise per kWh in a quarter, prior approval of the Commission shall be necessary and
only on approval of such additional increase by the Commission, the FPPPA can be
billed to consumers.
FPPPA calculations shall be submitted to the Commission within one month from the
end of the relevant quarter.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The Commission has approved base power purchase cost for FY 2019-20 as Rs.
4.32/unit as stated above. Thus, there is an increase of Rs. 0.10/unit in the base
power purchase cost of DISCOMs for FY 2019-20 over that of for FY 2018-19. The
Commission finds it appropriate to increase the base FPPPA by Rs. 0.12/unit
after grossing up the incremental base power purchase cost of Rs. 0.10/unit with
the approved loss. Accordingly, the base FPPPA for FY 2019-20 is approved as
Rs. 1.61/unit (1.49+0.12).
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
UGVCL has provided the allocation matrix for allocation of costs between wires
business and retail supply business as notified in the GERC (MYT) Regulations, 2016
(Regulation 87) as shown in the table below:
Table 9-1: Allocation matrix for segregation of wheeling and retail supply for UGVCL
for the FY 2019-20
Sr. Retail Supply
Allocation Matrix Wire Business
No. Business
1 Power Purchase Expenses 0% 100%
2.1 Employee Expenses 60% 40%
2.2 Repairs & Maintenance Expenses 90% 10%
2.3 Administration & General Expenses 50% 50%
2.4 Other Debits 50% 50%
2.5 Extraordinary Items 50% 50%
2.6 Net Prior Period Expenses / (Income) 25% 75%
2.7 Other Expenses Capitalized 55% 45%
3 Depreciation 90% 10%
4 Interest & Finance charges 90% 10%
5 Interest on Working Capital & Security Deposit 10% 90%
6 Bad Debts Written off 0% 100%
7 Income Tax 90% 10%
8 Return on Equity 90% 10%
9 Non-tariff income 10% 90%
Based on the above allocation the approved ARR for wires business and retail supply
business for FY 2019-20 are computed as shown in the table below:.
Table 9-2: Allocation of ARR between wheeling and retail supply business for UGVCL
for FY 2018-19
(Rs. Crore)
Sr. Wire Retail Supply
Particulars Distribution
No. Business Business
1 Power Purchase Expenses 11128.50 - 11128.50
2 O & M Expenses 711.06 439.99 271.07
2.1 Employee Expenses 608.92 365.35 243.57
2.2 Repairs & Maintenance Expenses 68.58 61.72 6.86
2.3 Administration & General Expenses 110.90 55.45 55.45
2.4 Other Debits - - -
2.5 Extraordinary Items - - -
2.6 Net Prior Period Expenses /(Income) - - -
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Sr. Wire Retail Supply
Particulars Distribution
No. Business Business
2.7 Other Expenses Capitalized (77.33) (42.53) (34.80)
3 Depreciation 248.47 223.62 24.85
4 Interest & Finance Charges 72.64 65.38
7.26
5 Interest on Security Deposit 90.79 9.08 81.72
6 Interest on Working Capital - - -
7 Bad Debts Written Off 0.31 - 0.31
Contribution to Contingency
8 - - -
Reserves
9 Total Revenue Expenditure 12251.77 738.06 11513.71
10 Return on Equity Capital 215.36 193.82 21.54
11 Income Tax 14.38 12.94 1.44
12 Aggregate Revenue Requirement 12481.51 944.83 11536.68
14 Less: Non-Tariff Income 138.68 13.87 124.81
15 Aggregate Revenue Requirement 12342.83 930.96 11411.87
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
The losses in HT and LT network are 10% and 5.05% respectively, with respect to
energy input to the segment of the system. In case injection at 11 kV levels and drawal
at LT level envisages use of both the networks i.e. 11 kV and LT, in that case, the
combined loss works out to 12.75% of the energy injection at 11 kV network.
The above wheeling charges payable shall be uniform in all the four distribution
companies, DGVCL, MGVCL, PGVCL and UGVCL.
Where,
The cross subsidy surcharge based on the above formula is worked out as shown in
the Table below:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Thus, Cross Subsidy Surcharge as per Tariff Policy, 2016 works out to Rs. 1.87 /kWh
for the four State owned Distribution companies viz. DGVCL, MGVCL, PGVCL and
UGVCL.
However, Tariff Policy, 2016 provides that the surcharge shall not exceed 20% of the
tariff applicable to the category of the consumers seeking Open Access.
In view of above, the Commission decided to restrict the Cross Subsidy Surcharge
leviable from the consumers of the four State Owned Distribution Companies, seeking
Open Access, for FY 2019-20 at Rs. 1.36 /kWh.
Accordingly, Cross Subsidy Surcharge for HT Category = 1.36 Rs. /kWh for FY 2019-
20.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
10.1. Introduction
The Commission is guided by the provisions of the Electricity Act, 2003, the National
Electricity Policy (NEP), the Tariff Policy, the Regulations on Terms and Conditions of
Tariff issued by the Central Electricity Regulatory Commission (CERC) and GERC
(MYT) Regulations, 2016 notified by the Commission.
Section 61 of the Act lays down the broad principles, and guidelines for determination
of retail supply tariff. The basic principle is to ensure that the tariff should progressively
reflect the cost of supply of electricity and reduce the cross subsidies amongst
categories within a period to be specified by the Commission.
10. RATE AG
This tariff is applicable to services used for irrigation purposes only excluding
installations covered under LTP- Lift Irrigation category.
Proposed Provision
“Tariff Schedule”
10. RATE AG
This tariff is applicable to services used for irrigation purposes only excluding (i)
installations covered under LTP- Lift Irrigation category, (ii) Floriculture, (iii)
Horticulture, (iv) Sericulture, (v) Fishries, (vi) Dairy, (vii) Tissue Culture activities, (viii)
Nursery.
Commission’s Analysis
The Commission has examined the proposal of the Licensee. Since, no detail was
produced by the Petitioner in the proposed change, the Commission has decided not
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
to accept proposal of the Petitioner at this stage. Accordingly, there will be no change
in Tariff Schedule.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
have at present any electricity connection form a co-operative society and take
advantage of Lift Irrigation wherein under one single connection a group of farmers
stand to benefit. This will also reduce their waiting period and on the other hand utilities’
list of pending applications will also get reduced, if a group of farmers form a co-
operative society and opts for Lift Irrigation under LTP-Lift Irrigation category / HTP V
category. This will help utilities in reducing their losses also. Accordingly, the
Commission considers to offer a tariff of Rs. 1.50/unit to the consumers of these
categories. With this modification, there will be impact of Rs. 0.71 Crore in the revenue
of the four DISCOMs.
With changes in Tariff as mentioned at Para 10.3.2 and 10.3.3, the total reduction is
expected to be Rs. 6.02 Crore in the Revenue of the four DISCOMs in FY 2019-20.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
COMMISSION’S ORDER
The Commission approves the Aggregate Revenue Requirement for FY 2019-20 and FY
2020-21 in the Mid Term Review for UGVCL as shown in the Table below:
The retail supply tariffs for UGVCL distribution area for FY 2019-20 determined by the
Commission are annexed to this Order. This Order shall come into force with effect from the
1st May 2019. The revised rate shall be applicable for the electricity consumption from the 1 st
May, 2019 onwards.
Place: Gandhinagar
Date: 24/04/2019
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
GENERAL
1. The tariff figures indicated in this tariff schedule are the tariff rates payable by the
consumers of Distribution Licensees viz. DGVCL, MGVCL, PGVCL and UGVCL.
2. These tariffs are exclusive of Electricity Duty, tax on sale of electricity, taxes and other
charges levied by the Government or other competent authorities from time to time which
are payable by the consumers, in addition to the charges levied as per the tariff.
3. All these tariffs for power supply are applicable to only one point of supply.
4. The charges specified are on monthly basis. Distribution Licensee may decide the period
of billing and adjust the tariff rate accordingly.
5. Except in cases where the supply is used for purposes for which a lower tariff is provided
in the tariff schedule, the power supplied to any consumer shall be utilized only for the
purpose for which supply is taken and as provided for in the tariff.
6. The various provisions of the GERC (licensee’s power to recover expenditure incurred in
providing supply and other miscellaneous charges) Regulations, except Meter Charges,
will continue to apply.
7. Conversion of Ratings of electrical appliances and equipments from kilowatt to B.H.P. or
vice versa will be done, when necessary, at the rate of 0.746 kilowatt equal to 1 B.H.P.
8. The billing of fixed charges based on contracted load or maximum demand shall be done
in multiples of 0.5 (one half) Horse Power or kilo watt (HP or kW) as the case may be.
The fraction of less than 0.5 shall be rounded off to next 0.5. The billing of energy charges
will be done on complete one kilo-watt-hour (kWh).
9. The Connected Load for the purpose of billing will be taken as the maximum load
connected during the billing period.
10. The Fixed charges, minimum charges, demand charges, and the slabs of consumption of
energy for energy charges mentioned shall not be subject to any adjustment on account
of existence of any broken period within billing period arising from consumer supply being
connected or disconnected any time within the duration of billing period for any reason.
11. Contract Demand shall mean the maximum kW / kVA for the supply of which licensee
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
PART - I
SCHEDULE OF TARIFF FOR SUPPLY OF ELECTRICITY
AT LOW AND MEDIUM VOLTAGE
1. RATE: RGP
This tariff is applicable to all services in the residential premises which are not covered under
‘Rate: RGP (Rural)’ Category.
Single-phase supply- Aggregate load up to 6 kW
Three-phase supply- Aggregate load above 6 kW
PLUS
1.2 ENERGY CHARGES: FOR THE TOTAL MONTHLY CONSUMPTION:
(OTHER THAN BPL CONSUMERS)
(a) First 50 units 305 Paise per Unit
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
**The consumer who wants to avail the benefit of the above tariff has to produce a copy of the
Card issued by the authority concerned at the sub-division office of the Distribution Licensee.
The concessional tariff is only for 30 units per month.
This tariff is applicable to all services for residential premises located in areas within Gram
Panchayat as defined in the Gujarat Panchayats Act.
PLUS
2.2 ENERGY CHARGES: FOR THE TOTAL MONTHLY CONSUMPTION:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
**The consumer who wants to avail the benefit of the above tariff has to produce a copy of the
Card issued by the authority concerned at the sub-division office of the Distribution Licensee.
The concessional tariff is only for 30 units per month.
Note: If the part of the residential premises is used for non-residential (commercial) purposes
by the consumers located within ‘Gram Panchayat’ as defined in Gujarat Panchayat Act, entire
consumption will be charged under this tariff.
3. RATE: GLP
This tariff is applicable to the educational institutes and other institutions registered with the
Charity Commissioner or similarly placed authority designated by the Government of India for
such intended purpose and research and development laboratories.
4. RATE: NON-RGP
This tariff is applicable to the services for the premises those are not covered in any other tariff
categories and having aggregate load up to and including 40 kW.
Consumer under this category may opt to be charged as per category – ‘RATE:LTMD’.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
PLUS
4.2 ENERGY CHARGES:
5. RATE: LTMD
This tariff is applicable to the services for the premises those are not covered in any other tariff
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
This tariff shall also be applicable to consumer covered in category- ‘Rate: Non-RGP’ so opts
to be charged in place of ‘Rate: Non-RGP’ tariff.
(i) For first 40 kW of billing demand Rs. 90/- per kW per month
(a) (ii) Next 20 kW of billing demand Rs. 130/- per kW per month
PLUS
5.2 ENERGY CHARGES:
For the entire consumption during the month 460 Paise per Unit
PLUS
For all the reactive units (KVARH) drawn during the month 10 paise per KVARH
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
This tariff is applicable for aggregate load up to 40 kW and using electricity exclusively during
night hours from 10:00 PM to 06:00 AM next day. (The supply hours shall be regulated
through time switch to be provided by the consumer at his cost.)
PLUS
6.2 ENERGY CHARGES:
For entire consumption during the month 260 Paise per Unit
NOTE:
1. 15% of the contracted demand can be availed beyond the night hours prescribed as per
para 6 above.
Gujarat Electricity Regulatory Commission Page 181
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
2. 10% of total units consumed during the billing period can be availed beyond the night hours
prescribed as per para 6 above.
3. In case the consumer failed to observe condition no. 1 above during any of the billing
month, then demand charge during the relevant billing month shall be billed as per Non-
RGP category demand charge rates given in para 4.1 of this schedule.
4. In case the consumer failed to observe condition no. 2 above during any of the billing
month, then entire energy consumption during the relevant billing month shall be billed as
per Non-RGP category energy charge rates given in para 4.2 of this schedule.
5. In case the consumer failed to observe above condition no. 1 and 2 both during any of the
billing month, then demand charge and entire energy consumption during the relevant
billing month shall be billed as per Non-RGP category demand charge and energy charge
rates given in para 4.1 and 4.2 respectively, of this schedule.
6. This tariff shall be applicable if the consumer so opts to be charged in place of Non-RGP
tariff by using electricity exclusively during night hours as above.
7. This option can be exercised to shift from NON-RGP tariff category to NON-RGP NIGHT
tariff or from NON-RGP NIGHT tariff category to NON-RGP tariff four times in a calendar
year by giving not less than 15 days’ advance notice in writing before commencement of
billing period.
This tariff is applicable for aggregate load above 40 kW and using electricity exclusively
during night hours from 10.00 PM to 06.00 AM next day. (The supply hours shall be
regulated through time switch to be provided by the consumer at his cost.)
PLUS
7.2 ENERGY CHARGES:
For entire consumption during the month 260 Paise per Unit
PLUS
For all reactive units (KVARH) drawn during the month 10 Paise per KVARH
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
NOTE:
1. 15% of the contracted demand can be availed beyond the night hours prescribed as per
para 7 above.
2. 10% of total units consumed during the billing period can be availed beyond the night
hours prescribed as per para 7 above.
3. In case the consumer failed to observe condition no. 1 above during any of the billing
month, then demand charge during the relevant billing month shall be billed as per LTMD
category demand charge rates given in para 5.1 of this schedule.
4. In case the consumer failed to observe condition no. 2 above during any of the billing
month, then entire energy consumption during the relevant billing month shall be billed as
per LTMD category energy charge rates given in para 5.2 of this schedule.
5. In case the consumer failed to observe above condition no. 1 and 2 both during any of the
billing month, then demand charge and entire energy consumption during the relevant
billing month shall be billed as per LTMD category demand charge and energy charge
rates given in para 5.1 and 5.2 respectively, of this schedule.
6. This tariff shall be applicable if the consumer so opts to be charged in place of LTMD tariff
by using electricity exclusively during night hours as above.
7. This option can be exercised to shift from LTMD tariff category to LTMD-NIGHT tariff or
from LTMD-NIGHT tariff category to LTMD tariff four times in a calendar year by giving not
less than 15 days’ advance notice in writing before commencement of billing period.
Applicable for supply of electricity to Low Tension Agricultural consumers contracting load up
to 125 HP requiring continuous (twenty-four hours) power supply for lifting water from surface
water sources such as canal, river, & dam and supplying water directly to the fields of farmers
for agricultural irrigation only.
PLUS
Energy charges
(b) 150 Paise per Unit
For entire consumption during the month
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
9. RATE: WWSP
This tariff shall be applicable to services used for water works and sewerage pumping
purposes.
9.1 Type I – Water works and sewerage pumps operated by other than local authority:
PLUS
9.2 Type II – Water works and sewerage pumps operated by local authority such as
Municipal Corporation, Gujarat Water Supply & Sewerage Board located outside Gram
Panchayat Area will also attract this tariff:
PLUS
9.3 Type III – Water works and sewerage pumps operated by Municipalities / Nagarpalikas
and Gram Panchayats or Gujarat Water Supply & Sewerage Board for its installations
located in Gram Panchayats:
Applicable to all the water works consumers having connected load of 50 HP and above for
the energy consumption during the Off-Peak Load Hours of the Day.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
10. RATE: AG
This tariff is applicable to services used for irrigation purposes only excluding installations
covered under LTP- Lift Irrigation category.
ALTERNATIVELY
10.1.2 METERED TARIFF:
Energy Charges: For entire consumption 60 Paise per Unit per month
Energy Charges: For entire consumption 80 Paise per Unit per month
NOTE: The consumers under Tatkal Scheme shall be eligible for normal metered tariff as
above, on completion of five years period from the date of commencement of supply.
10.2 No machinery other than pump water for irrigation (and a single bulb or CFL up to 40
watts) will be permitted under this tariff. Any other machinery connected in the
installation governed under this tariff shall be charged separately at appropriate tariff
for which consumers shall have to take separate connection.
10.3 Agricultural consumers who desire to supply water to brick manufacturing units shall
have to pay Rs. 100/HP per annum subject to minimum of Rs. 2000/- per year for each
brick Mfg. Unit to which water is supplied in addition to existing rate of HP based /
metered agricultural tariff.
10.4 Such Agricultural consumers shall have to pay the above charges for a full financial
year irrespective of whether they supply water to the brick manufacturing unit for full
or part of the Financial Year.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
Agricultural consumers shall have to declare their intention for supply of the water to
such brick manufacturing units in advance and pay charges accordingly before
commencement of the financial year (i.e. in March every year).
11. RATE: SL
11.1 Tariff for Street Light for Local Authorities and Industrial Estates:
This tariff includes the provision of maintenance, operation and control of the street lighting
system.
For all the units consumed during the month: 405 Paise per Unit
For all the kVAh units consumed during the month: 305 Paise per Unit
The consumer shall arrange for renewal, maintenance and replacement of lamp, associated
Fixture, connecting wire, disconnecting device, switch including time switch etc. at his cost by
person authorised by him in this behalf under Rule-3 of the Indian Electricity Rules, 1956 /
Rules issued by CEA under the Electricity Act, 2003.
Maintenance of the street lighting conductor provided on pole to connect the street light shall
be carried out by Distribution Licensee.
11.2 Tariff for power supply for street lighting purposes to consumers other than the
local authorities and industrial estates:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
For all units consumed during the month 405 Paise per kWh
The consumer shall arrange for renewal, maintenance and replacement of lamp, associated
Fixture, connecting wire, disconnecting device, switch including time switch etc. at his cost by
person authorised by him in this behalf under Rule-3 of the Indian Electricity Rules, 1956 /
Rules issued by CEA under the Electricity Act, 2003.
Maintenance of the street lighting conductor provided on pole to connect the street light shall
be carried out by Distribution Licensee.
This tariff is applicable to services of electricity supply for temporary period at the low voltage.
A consumer not taking supply on regular basis under a proper agreement shall be deemed to
be taking supply for temporary period.
Note: Payment of bills is to be made within seven days from the date of issue of the bill. Supply
would be disconnected for non-payment of dues on 24 hours’ notice.
This tariff is applicable to consumers who use electricity exclusively for Electric Vehicle
Charging installations.
Other consumers can use their regular electricity supply for charging electric vehicle under
same regular category i.e. RGP, RGP (RURAL), GLP, LTMD, NON-RGP NIGHT, LTMD-
NIGHT, etc. as the case may be.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
PART - II
TARIFFS FOR SUPPLY OF ELECTRICITY AT HIGH TENSION
(3.3 KV AND ABOVE, 3-PHASE 50 HERTZ), AND EXTRA HIGH TENSION
The following tariffs are available for supply at high tension for large power services for
contract demand not less than 100 kVA
This tariff will be applicable for supply of electricity to HT consumers contracted for 100 kVA
and above for regular power supply and requiring the power supply for the purposes not
specified in any other HT Categories.
(a) For first 500 kVA of billing demand Rs. 150/- per kVA per month
(b) For next 500 kVA of billing demand Rs. 260/- per kVA per month
(c) For billing demand in excess of 1000 kVA Rs. 475/- per kVA per month
PLUS
14.2 ENERGY CHARGES
(c) For billing demand above 2500 kVA 430 Paise per Unit
PLUS
14.3 TIME OF USE CHARGES:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
(b) For Billing Demand above 500 kVA 85 Paise per Unit
If the power factor of the consumer’s installation in any month is above 95%, the consumer
will be entitled to a rebate at the rate of 0.5% (half percent) in excess of 95% power factor on
the total amount of electricity bill for that month under the head “Energy Charges”, arrived at
using tariff as per para 14.2 of this schedule, for every 1% rise or part thereof in the average
power factor during the month above 95%.
The maximum demand in kW or kVA, as the case may be, shall mean an average kW / kVA
supplied during consecutive 30/15 minutes or if consumer is having parallel operation with the
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
grid and has opted for 3 minutes, period of maximum use where such meter with the features
of reading the maximum demand in KW/KVA directly, have been provided.
The contract demand shall mean the maximum KW/KVA for the supply, of which the supplier
undertakes to provide facilities from time to time.
For the consumer eligible for using supply at any time during 24 hours, entire consumption
shall be billed at the energy charges specified above. However, the energy consumed during
night hours of 10.00 PM to 06.00 AM next morning shall be eligible for concession at the rate
of 40 Paise per unit.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
(a) The highest of the actual maximum demand registered during the calendar year.
(b) Eighty-five percent of the arithmetic average of contract demand during the year.
(c) One hundred kVA.
14.11.5 Units consumed during the off-season period shall be charged for at the flat rate of
430 Paise per unit.
14.11.6 Electricity bills paid during off-season period shall not be taken into account towards
the amount payable against the annual minimum bill. The amount paid by the
consumer towards the electricity bills for seasonal period only under the heads
“Demand Charges” and “Energy Charges” shall be taken into account while
determining the amount payable towards the annual minimum bill.
Applicability: This tariff shall be applicable for supply of energy to HT consumers contracting
for 100 kVA and above, requiring power supply for Water Works and Sewerage pumping
stations run by Local Authorities and GW & SB. GIDC Water Works.
(a) For first 500 kVA of billing demand Rs. 115/- per kVA per month
(b) For next 500 kVA of billing demand Rs. 225/- per kVA per month
(c) For billing demand in excess of 1000 kVA Rs. 290/- per kVA per month
For billing demand in excess of contract demand Rs. 360 per kVA per month
PLUS
15.2 ENERGY CHARGES:
(c) For billing demand above 500 kVA and up to 2500 kVA 455 Paise per Unit
(d) For billing demand above 2500 kVA 465 Paise per Unit
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
PLUS
15.3 TIME OF USE CHARGES:
(b) For Billing Demand above 500 kVA 85 Paise per Unit
If the power factor of the consumer’s installation in any month is above 95%, the consumer
will be entitled to a rebate at the rate of 0.5% (half percent) in excess of 95% power factor on
the total amount of electricity bill for that month under the head “Energy Charges”, arrived at
using tariff as per para 15.2 of this schedule, for every 1% rise or part thereof in the average
power factor during the month above 95%.
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
This tariff shall be applicable to a consumer taking supply of electricity at high voltage,
contracting for not less than 100 kVA for temporary period. A consumer not taking supply on
regular basis under a proper agreement shall be deemed to be taking supply for temporary
period.
For billing demand up to contract demand Rs. 18/- per kVA per day
For billing demand in excess of contract demand Rs. 20/- per kVA per day
PLUS
16.2 ENERGY CHARGES:
PLUS
16.3 TIME OF USE CHARGES:
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
If the power factor of the consumer’s installation in any month is above 95%, the consumer
will be entitled to a rebate at the rate of 0.5% (half percent) in excess of 95% power factor on
the total amount of electricity bill for that month under the head “Energy Charges”, arrived at
using tariff as per para 16.2 of this schedule, for every 1% rise or part thereof in the average
power factor during the month above 95%.
17 RATE: HTP-IV
This tariff shall be applicable for supply of electricity to HT consumers opting to use electricity
exclusively during night hours from 10.00 PM to 06.00 AM next day and contracted for regular
power supply of 100 kVA and above.
PLUS
17.2 ENERGY CHARGES:
For all units consumed during the month 225 Paise per Unit
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
If the power factor of the consumer’s installation in any month is above 95%, the consumer
will be entitled to a rebate at the rate of 0.5% (half percent) in excess of 95% power factor on
the total amount of electricity bill for that month under the head “Energy Charges”, arrived at
using tariff as per para 17.2 of this schedule, for every 1% rise or part thereof in the average
power factor during the month above 95%.
NOTE:
1. 15% of the contracted demand can be availed beyond the night hours prescribed as
per para 16 above.
2. 10% of total units consumed during the billing period can be availed beyond the night
hours prescribed as per para 16 above.
3. In case the consumer failed to observe condition no. 1 above during any of the billing
month, then demand charge during the relevant billing month shall be billed as per
HTP-I category demand charge rates given in para 14.1 of this schedule.
4. In case the consumer failed to observe condition no. 2 above during any of the billing
month, then entire energy consumption during the relevant billing month shall be billed
as per HTP-I category energy charge rates given in para 14.2 of this schedule.
5. In case the consumer failed to observe above condition no. 1 and 2 both during any of
the billing month, then demand charge and entire energy consumption during the
relevant billing month shall be billed as per HTP-I category demand charge and energy
charge rates given in para 14.1 and 14.2 respectively, of this schedule.
6. This tariff shall be applicable if the consumer so opts to be charged in place of HTP-I
tariff by using electricity exclusively during night hours as above.
7. This option can be exercised to shift from HTP-I tariff category to HTP-IV tariff or from
HTP-IV tariff category to HTP-I tariff four times in a calendar year by giving not less
than 15 days’ advance notice in writing before commencement of billing period
18 RATE: HTP- V
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
sources such as canal, river and dam, and supplying water directly to the fields of farmers for
agricultural irrigation only.
PLUS
18.2 ENERGY CHARGES:
For all units consumed during the month 150 Paise per Unit
If the power factor of the consumer’s installation in any month is above 95%, the consumer
will be entitled to a rebate at the rate of 0.5% (half percent) in excess of 95% power factor on
the total amount of electricity bill for that month under the head “Energy Charges”, arrived at
using tariff as per para 18.2 of this schedule, for every 1% rise or part thereof in the average
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
This tariff is applicable for power supply to Railway Traction at 132 kV/66 kV.
(a) For billing demand up to the contract demand Rs. 180 per kVA per month
(b) For billing demand in excess of contract demand Rs. 425 per kVA per month
NOTE: In case of the load transfer for traction supply due to non-availability of power supply
at preceding or succeeding point of supply or maintenance at Discom’s level, excess demand
over the contract demand shall be charged at normal rate at appropriate point of supply.
Normal Demand Charges will also apply in case of bunching of trains. However, Discoms shall
charge excess demand charges while raising the bills and Railways have to give convincing
details and documentary proof of bunching of trains if they want to be charged at the normal
demand charges. If satisfactory proof of bunching of trains is provided, Discom shall consider
that occasion for normal demand charges, otherwise excess demand charges will be
applicable specified as above at 19.1 (b).
PLUS
19.2 ENERGY CHARGES:
For all units consumed during the month 500 Paise per Unit
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
If the power factor of the consumer’s installation in any month is above 95%, the consumer
will be entitled to a rebate at the rate of 0.5% (half percent) in excess of 95% power factor on
the total amount of electricity bill for that month under the head “Energy Charges”, arrived at
using tariff as per para 19.2 of this schedule, for every 1% rise or part thereof in the average
power factor during the month above 95%.
This tariff is applicable to consumers who use electricity exclusively for Electric Vehicle
Charging installations.
Other consumers can use their regular electricity supply for charging electric vehicle under
same regular category i.e. HTP-I, HTP-II, HTP-III, HTP-IV, HTP-V, RAILWAY TRACTION as
the case may be.
For billing demand up to contract demand Rs. 25/- per kVA per Month
For billing demand in excess of contract demand Rs. 50/- per kVA per Month
PLUS
April 2019
Uttar Gujarat Vij Company Limited
Truing up for FY 2017-18, Mid-Term Review of FY 2019-20 and FY 2020-21
and Determination of Tariff for FY 2019-20
April 2019