MINUTES FOR PROGRESS REVIEW MEETING
URBAN DEVELOPMENT AUTHORITY
Project                           :      Urban Regeneration Project - City of Colombo
                                         Construction of 4100 Housing Units – Kolonnawa Project
Consultant                        :      State Engineering Corporation of Sri Lanka
Contractor                        :      IVRCL Assets & Holdings Ltd
Meeting No.                       :      75
Date                              :      10.00 am
Venue                             :      Site Meeting Room - Kolonnawa
Present
           1.    Eng. T. Jeewanath                   Project Engineer / UDA
           2.    Eng. G.J.B. Silva                   Project Manager / SEC
           3.    Mr. S.P.D. Nisansala                Resident Engineer / SEC
           4.    Mr. P. Umakanth                     Project In-charge / IVRCL
           5. Mr. A. Karthikeyan                     Electrical Engineer / IVRCL
           6. Mr.Gururaj patil                       Senior Engineer / IVRCL
           7. Mr. A.Dilipkumar                       Senior Engineer / IVRCL
75.2. Design Progress
  Description of
                        Tower 1       Tower 2        Tower 3    Tower 4                 Remarks
     design
                                                                            Constr. Dwg.were issued on
Architectural              IC           IC             IC          IC
                                                                            25.07.2017
Structural design of                                                        Constr. Dwg.were issued on
                           IC           IC             IC          IC
Sub-structure                                                               17.07.2012
Structural design of                                                        Constr. Dwg.were issued on
                           IC           IC             IC          IC
Super-structure                                                             26.07.2012
Sump Design                                     CR                          SEC commented on 22.01.2017
                                                                            Revise Constr. Dwg. for Tower 4
Electrical Design         CR            CR             CR          IC
                                                                            were issued on 22.11.2017
Plumbing Design           AC            AC             AC          AC       SEC commented on 21.03.2017
Fire Design               AC            AC             AC          AC       SEC commented on 14.07.2017
External Water                                                              Constr. Dwg.were issued on
                          AC            AC             AC          AC
Supply                                                                      21.10.2017 with conditions.
                                                                            SEC commented on 26.10.2017 &
External Sewerage         AC            AC             AC          AC
                                                                            need to resubmitted
                                                                            SEC commented on 26.10.2017&
Storm Water               AC            AC             AC          AC
                                                                            need to resubmitted
External Road
                          AC            AC             AC          AC       SEC commented on 05.01.2018
Design
IC - Issued for Construction, AC - Approved with Comments, UR - Under Review
CR - Commented and need Resubmission, IR - Incomplete and need Resubmission, NS - Not Submitted
75.3. Construction Progress
75.3.1. Substructure
                                                            1
                                        Progress from
                                   01.11.2017 to 11.12.2017           Comp/
  Tower         Activity
                                                                      Total
                              Scheduled    Completed Balance
               Piling             -              -          -         198/198
               Hacking             -            -           -         198/198
Tower -1
               PCC                 -            -           -          80%
               Raft                -            -           -          75%
               Piling              -            -           -         148/148
               Hacking             -            -           -         148/148
Tower -2
               PIT                 -            -           -         148/148
               PDA                                                      4/4
               Piling              -            -           -         148/148
               Hacking             -            -           -         148/148
Tower -3       PIT                 -            -           -         148/148
               PDA                                         03           0/3
               MLT                                          -           1/1
               Sub
Tower-4        Structure           -            -           -          100%
               work
Total No of Piles                                                     602/602
75.3.2. Super Structure
75.3.2.1. Tower 4
                                         Scheduled     Cumulative        Progress      Cumulative
              Description                                                  from        completed
                                            up to     completed up
                                                                       01.11.2017 to      up to
                                         11.12.2017   to 01.11.2017     11.12.2017     11.12.2017
Walls & Slab Concrete
       Ground walls,1st floor slab         100%           100%                -          100%
     1st Floor Walls, 2nd floor slab       100%           100%                -          100%
     2nd Floor Walls, 3rd floor slab       100%           100%                -          100%
     3rd Floor Walls, 4th floor slab       100%           100%                -          100%
      4th Floor Walls, 5th floor slab      100%           100%                -          100%
      5th Floor Walls, 6th floor slab      100%           100%                -          100%
      6th Floor Walls, 7th floor slab      100%           100%                -          100%
      7th Floor Walls, 8th floor slab      100%           100%                -          100%
      8th Floor Walls, 9th floor slab      100%           100%                -          100%
     9th Floor Walls, 10th floor slab      100%           100%                -          100%
    10th Floor Walls, 11th floor slab      100%           100%                -          100%
  11th Floor Walls, Terrace floor slab     100%           100%                -          100%
 M/R, W/T , Open to sky area walls &
                                           100%           93%              7%            100%
              Parapet walls
Stair Cases
       Ground Floor to 1st Floor           100%           100%                -          100%
         1st Floor to 2nd Floor            100%           100%                -          100%
         2nd Floor to 3rd Floor            100%           100%                -          100%
         3rd Floor to 4th Floor            100%           100%                -          100%
         4th Floor to 5th Floor            100%           100%                -          100%
         5th Floor to 6th Floor            100%           100%                -          100%
         6th Floor to 7th Floor            100%           100%                -          100%
         7th Floor to 8th Floor            100%           100%                -          100%
                                                      2
          8th Floor to 9th Floor     100%        100%       -      100%
         9th Floor to 10th Floor     100%        100%       -      100%
         10th Floor to 11th Floor    100%        100%       -      100%
       11th Floor to Terrace Floor   100%        100%       -      100%
Block work
              Ground Floor           100%        100%      -       100%
                 1st Floor           100%        100%      -       100%
                2nd Floor            100%        100%      -       100%
                3rd Floor            100%        100%      -       100%
                 4th Floor           100%        100%      -       100%
                 5th Floor           100%        100%      -       100%
                 6th Floor           100%       99.75%    0%      99.75%
                 7th Floor           100%        100%      -       100%
                 8th Floor           100%        100%      -       100%
                 9th Floor           100%        100%      -       100%
                10th Floor           100%        100%      -       100%
                11th Floor           100%        100%      -       100%
              Terrace Floor          100%         85%     15%      100%
Internal Plastering
              Ground Floor           100%       99.85%    0.15%    100%
                 1st Floor           100%        100%        -     100%
                2nd Floor            100%        100%        -     100%
                3rd Floor            100%        100%        -     100%
                 4th Floor           100%        100%        -     100%
                 5th Floor           100%        100%        -     100%
                 6th Floor           100%         99%      0%      99%
                 7th Floor           100%        100%        -     100%
                 8th Floor           100%        100%        -     100%
                 9th Floor           100%        100%        -     100%
                10th Floor           100%        100%        -     100%
                11th Floor           100%        100%        -     100%
External Plastering
              Ground Floor           100%        99.0%      1%     100.0%
                 1st Floor           100%       100.0%       -     100.0%
                2nd Floor            100%       99.5.0%    0.5%   100.00%
                3rd Floor            100%       100.0%       -     100.0%
                 4th Floor           100%       100.0%       -     100.0%
                 5th Floor           100%       100.0%       -     100.0%
                 6th Floor           100%         98%       0%      98%
                 7th Floor           100%       99.75%    0.25%    100.0%
                 8th Floor           100%       99.75%    0.25%    100.0%
                 9th Floor           100%       99.75%    0.25%    100.0%
                10th Floor           100%       99.75%    0.25%    100.0%
                11th Floor           100%       99.75%    0.25%    100.0%
Electrical Work
              Ground Floor           100%        85%      10%      95%
                 1st Floor           100%        90%      5%       95%
                2nd Floor            100%        90%      5%       95%
                3rd Floor            100%        90%      5%       95%
                 4th Floor           100%        90%      5%       95%
                 5th Floor           100%        90%      5%       95%
                 6th Floor           100%        90%      7%       97%
                 7th Floor           100%        90%      9%       99%
                 8th Floor           100%        90%      5%       95%
                                            3
                9th Floor     100%       96%     1%     97%
               10th Floor     100%       98%     1%     99%
               11th Floor     100%       98%     1%     99%
Plumbing Work(Water supply)
             Ground Floor     100%       85%    14.5%   99.5%
                1st Floor     100%       95%     4.5%   98.5%
               2nd Floor      100%       95%     4.5%   98.5%
               3rd Floor      100%       95%     4.5%   98.5%
                4th Floor     100%       95%     4.5%   98.5%
                5th Floor     100%       95%     4.5%   98.5%
                6th Floor     100%       95%     4.5%   98.5%
                7th Floor     100%       95%     4.5%   98.5%
                8th Floor     100%       95%     4.5%   98.5%
                9th Floor     100%       95%     4.5%   98.5%
               10th Floor     100%       95%     4.5%   98.5%
               11th Floor     100%       95%     3.5%   98.5%
Plumbing Work(Sewer & waste
water)
             Ground Floor     100%       95%     4%     99%
                1st Floor     100%       99%     0%     99%
               2nd Floor      100%       99%     0%     99%
               3rd Floor      100%       99%     0%     99%
                4th Floor     100%       99%     0%     99%
                5th Floor     100%       99%     0%     99%
                6th Floor     100%       99%     0%     99%
                7th Floor     100%       99%     0%     99%
                8th Floor     100%       99%     0%     99%
                9th Floor     100%       99%     0%     99%
               10th Floor     100%       99%     0%     99%
               11th Floor     100%       99%     0%     99%
Skim Coat (Internal)
             Ground Floor     100%        78%   21%     99%
                1st Floor     100%        99%   0%      99%
               2nd Floor      100%        99%   0%      99%
               3rd Floor      100%        99%   0%      99%
                4th Floor     100%        99%   0%      99%
                5th Floor     100%        99%   0%      99%
                6th Floor     100%        95%   1%      96%
                7th Floor     100%        99%   0%      99%
                8th Floor     100%        99%   0%      99%
                9th Floor     100%       100%    -      100%
               10th Floor     100%       100%    -      100%
               11th Floor     100%        99%   0%      99%
Internal Painting
             Ground Floor     100%        0%    93%     93%
                1st Floor     100%       75%    22%     97%
               2nd Floor      100%       95%    2%      97%
               3rd Floor      100%       95%    2%      97%
                4th Floor     100%       95%    3%      98%
                5th Floor     100%       95%    3%      98%
                6th Floor     100%       75%    5%      80%
                7th Floor     100%       95%    3%      98%
                8th Floor     100%       95%    3%      98%
                9th Floor     100%       95%    3%      98%
                                     4
             10th Floor    100%       95%    3%     98%
             11th Floor    100%       95%    3%     98%
Floor Rendering
           Ground Floor    100%        50%    -     100%
              1st Floor    100%       100%    -     100%
              2nd Floor    100%       100%    -     100%
              3rd Floor    100%       100%    -     100%
              4th Floor    100%       100%    -     100%
              5th Floor    100%       100%    -     100%
              6th Floor    100%       100%    -     100%
              7th Floor    100%       100%    -     100%
              8th Floor    100%       100%    -     100%
              9th Floor    100%       100%    -     100%
             10th Floor    100%       100%    -     100%
             11th Floor    100%       100%    -     100%
Waterproofing
           Ground Floor    100%       100%   100%   100%
               1st floor   100%       100%     -    100%
              2nd floor    100%       100%     -    100%
              3rd floor    100%       100%     -    100%
               4th floor   100%       100%     -    100%
               5th floor   100%       100%     -    100%
               6th floor   100%        90%    0%    90%
               7th floor   100%       100%     -    100%
               8th floor   100%       100%     -    100%
               9th floor   100%       100%     -    100%
              10th floor   100%       100%     -    100%
              11th floor   100%       100%     -    100%
Tiling
            Ground Floor   100%       18%    79%    97%
               1st floor   100%       95%    2%     97%
              2nd floor    100%       95%    3%     98%
              3rd floor    100%       95%    3%     98%
              4th Floor    100%       95%    3%     98%
              5th Floor    100%       95%    3%     98%
              6th Floor    100%       75%    4%     79%
              7th Floor    100%       95%    1%     96%
              8th Floor    100%       95%    3%     98%
              9th Floor    100%       95%    3%     98%
             10th Floor    100%       95%    3%     98%
              11th Floor   100%       95%    3%     98%
Doors & Windows
           Ground Floor    100%       40%    55%    95%
             1st floor     100%       88%    7%     95%
             2nd floor     100%       90%    5%     95%
             3rd floor     100%       90%    5%     95%
             4th floor     100%       90%    5%     95%
             5th floor     100%       90%    5%     95%
             6th floor     100%       88%    4%     92%
             7th floor     100%       90%    7%     97%
             8th floor     100%       90%    7%     97%
                                  5
                 9th floor                  100%       90%     8%     98%
                10th floor                  100%       92%     6%     98%
                11th floor                  100%       92%     6%     98%
Sanitary Fixtures
       Ground Floor – 11th Floor            100%       72%    16.8%   88.8%
Common area
Floor Rendering (GF – 11th Floor)
                Corridor                    100%       98%    1%      99%
                Staircase                   100%       80%    17%     97%
Internal Plastering(GF – 11th Floor)
                Corridor                    100%       99%    0.5%    99.5%
                Staircase                   100%       98%    1.5%    99.5%
Internal Painting (GF – 11th Floor)
                Corridor                    100%       70%    15%     85%
                Staircase                   100%       45%    35%     80%
Skim Coat (GF – 11th Floor)
                Corridor                    100%       85%    8%      93%
                Staircase                   100%       85%    12%     97%
Electrical Work (GF – 11th Floor)
                Corridor                    100%       80%    15%     95%
                Staircase                   100%       70%    25%     95%
Doors & Windows(GF – 11th Floor)
                Corridor                    100%       55%    38%     93%
External Painting
        Ground Floor – 11th Floor           100%        40%   32%     72%
External Sewerage Line (Manhole)            100%        65%   20%     85%
Lift installation                           100%        45%   33%     78%
Open to sky area roof work                  100%        70%   20%     90%
Road                                        100%        15%    0%     15%
Storm water drain                           100%        30%   40%     70%
Fire doors                                  100%        60%   35%     95%
Roof floor leveling screed                  100%       100%     -     100%
Earthling protection system                 100%        60%   40%     100%
Lighting protection system                  100%        30%   20%     50%
Water proofing(roof floor)                  100%         0%   92%     92%
Heat insulation (roof floor)                100%         0%   35%     35%
Lift water proofing                         100%         0%    0%      0%
Water proofing(Two lift machine room roof   100%       0%      0%      0%
slab))
Overhead water tank water proofing          100%       30%    50%     80%
Fire hydrant & Fire alarm                   100%        0%    75%     75%
Transformer for tower 2,3 & 4               100%       0%     100%    100%
(structure)
Transformer fixing for tower 2,3 & 4        100%        0%     0%      0%
Transformer for sump & tower 1              100%        0%     0%      0%
Generator room(structure)                   100%       40%    57%     97%
External water supply                       100%        5%    60%     65%
Pavement works                              100%       15%    65%     80%
75.3.2.2. Water Sump
                                                   6
                                         Scheduled    Cumulative         Progress       Cumulative
               Description                                                 from        completed up
                                           up to     completed up
                                                                       01.11.2017 to        to
                                         1112.2017   to 01.11.2017      11.12.2017      11.12.2017
Piling work                                100%      100% (24/24)            -         100% (24/24)
PIT                                        100%       98% (23/24)          2%          100% (24/24)
PDA                                        100%          100% (1/1)          -          100% (1/1)
Excavation                                 100%            100%              -            100%
Pile Hacking                               100%            100%              -            100%
Structural work                            100%            35%             43%             78%
75.3.3. Overall Physical Progress
As at 26.01.2018
  Structure           Scheduled (%)         Actual (%)            Delay (Days)
   Tower 1                17.92               13.21                    28
   Tower 2                10.05               10.05                     -
   Tower 3                10.05               10.05                     -
   Tower 4                 100                95.25                   352
Actual Overall Physical Progress of the Project – 32.66%
Scheduled Overall Physical Progress of the Project – 35.97%
74.4. Construction issues
      No                            Description                                    Response
74.4.1.             UDA and SEC instruct to complete lift IVRCL inform that they will complete lift
                    machine room wall & slab.             machine room wall & slab immediately.
74.4.2.             UDA and SEC highlighted the delay of IVRCL agreed to start the work from
                    sump construction.                   22/09/2017.
74.4.3.             As the method of external painting IVRCL inform that paint supplier will give
                    changed, it was informed by the SEC to warranty for the texture paint.
                    take necessary actions to obtain the
                    warranty for the painting work.
74.4.4.             UDA instructed IVRCL to prepare a IVRCL agreed & inform that they will give
                    schedule for inspection floors.   floors to 2nd inspection from 06/11/2017.
74.5. Safety issues
      No                            Description                                    Response
                                                     7
74.5.1.              SEC stated that they instructed through a To be continued.
                     log note to start fogging to control mosquito
                     spreading. (Repeat 10)
74.6. Other issues
      No                            Description                                   Response
74.6.1.              IVRCL was informed to improve the site    All floors were cleaned and to be continued
                     cleaning (Repeat 12)
Next meeting will be held on 11th December 2017 at Maligawaththa Site Meeting Room at 10.00 am.
Prepared by :
  S.P.D.Nisansala
  Resident Engineer (SEC)
Checked by:
  G.J.B.Silva
  Project Manager (SEC)