Sizing of Instrument Air
I want to share you how to size or select minimum capacity of air compressor and instrument air
dryer. Air compressor is usually used as feed air for:
Instrument air (for instrumentation or feed air for nitrogen generator)
Utility air (for utility station)
Instrument Air Requirement for Instrumentation
Instrument air is required in operation of control valve and shut down valve. The rules below is used
to calculated instrument air requirement for instrumentation:
Control valve (CV) – steady state condition: 1 scfm/valve
Control valve (CV) – transient condition: 6.25 scfm/valve
Shut down valve (SDV) – steady state condition: 0
Shut down valve (SDV) – transient condition: 4.8 scfm/valve
Here is calculation of instrument air requirement:
Instrument air (normal demand, scfm) = 95% CV at steady state + 5% CV at transient +
10% SDV at transient
Instrument air (peak demand, scfm) = 70% CV at steady state + 30% CV at transient +
20% SDV at transient
Instrument Air Requirement for Nitrogen Generator Feed
Air feed for nitrogen generator is usually from instrument air dryer. The feed requirement depends on
the required purity of nitrogen. The higher the purity, the higher flow rate of instrument air to nitrogen
generator. Inlet compressed air requirement to nitrogen generator is expressed as air factor. For
general rule:
Nitrogen purity 99.5% : air factor 2.9
Nitrogen purity 99% : air factor 2.5
Nitrogen purity 98% : air factor 2.3
Nitrogen purity 97% : air factor 2.1
Nitrogen purity 95% : air factor 1.9
Utility Air Requirement
Utility air requirement for utility station is about 0.5 scfm/utility hose. Number of utility station is at
least one per 30 m radius.
Sizing of Instrument Air Dryer and Compressor Capacity
After we define air requirement based on its purpose, then this is the step to determine instrument
air dryer capacity:
1. Calculate required instrument air to nitrogen generator based on its purity
2. Calculate required dry air = instrument air for instrumentation + instrument air to nitrogen
generator package
3. Calculate required air to instrument air dryer, considering air loss for regeneration. It is
usually 1.15 times value from Step 2
4. Calculate air compressor capacity = value from Step 3 plus utility air requirement
You may also add 20% safety factor.
Example
Let’s continue with example. For example, we have:
Control valves: 5 unit
Shut down valve: 5 unit
Capacity of nitrogen generator package: 25 scfm with purity 98%
Number of utility hose: 10 unit
Instrument Air Requirement
Instrument air (peak demand, scfm) = 70% CV at steady state + 30% CV at transient + 20% SDV at
transient
Instrument air (peak demand) = 70% x (5 x 1 scfm) + 30% x (5 x 6.25 scfm) + 20% x (5 x 4.8 scfm)
Instrument air (peak demand) = 17.67 scfm
Utility Air Requirement
Utility air requirement = number of hose x 0.5 scfm
Utility air requirement = 10 x 0.5 scfm = 5 scfm
Then we can continue using four steps above.
1. Instrument air to nitrogen generator package = 2.3 (air factor for 98% purity) x capacity of
nitrogen generator package = 2.3 x 25 scfm = 57.5 scfm
2. Dry air requirement = dry air for instrumentation + dry air for nitrogen generator package =
17.67 scfm + 57.5 scfm = 75.175 scfm
3. Air to instrument air dryer = 1.15 x 75.175 = 86.45 scfm
4. Compressor capacity = Dry air requirement + utility air requirement = 86.45 + 5 scfm = 91.45