COMPUTATION OF LABOR
(1 working day          =               8    hours)
                                       1ST FLOOR
                                       Activity No. A
                                Site Clearing and Grubbing
Manual Clearing
                                                    2
       Manhour Capability =            0.03     m
                                                    2
       Total Area              =       200      m
       No. of Persons          =        3
       No. of Days             =       0.25     day(s)
                        say    =         1      day(s)
                                    Activity No. B
               Delivery of materials for Field Office and Construction
       No. of Persons       =         5
       No. of Days          =         5      day(s)
                                       Activity No. C
                                       Mobilization
       No. of Persons          =        3
       No. of Days             =        2       day(s)
                                       Activity No. D
                                    Delivery of materials
       No. of Persons          =         3
       No. of Days             =         3      day(s)
                                       Activity No. E
                                   Layout and batterboard
                                                     2
       Manhour Capability      =       0.02     hr/m
       Total Area              =      200.00 m2
       No. of Persons          =        3
       No. of Days             =       0.17     day(s)
                      say      =         1      day(s)
                                   Activity No. F
               Fabrication of Rebars for Column, CF and WF (1st flr)
       Manhour Capability =        10.00    kg/hr
       Total No. of kg      =     706.97 kg
       No. of Persons       =        3
       No. of Days          =      2.95     day(s)
                      say =          3      day(s)
                                    Activity No. G
                     Excavating of column footing and wall footing
                                               3
        Manhour Capability =         1.35    m /m day
                                               3
        Total Volume        =       26.64    m
        No. of Persons      =         4
        No. of Days         =        4.93    day(s)
                       say =           5     day(s)
                                    Activity No. H
                 Fabrication of Forms, scaffolding for columns (1st flr)
                                                    2
        Manhour Capability =        1.42     MH/m
        Total Area           =     296.19 m2
        No. of Persons       =        3
        No. of Days          =      8.67     day(s)
                       say =          9      day(s)
                                       Activity No. I
                 Installation of rebars for column, CF and WF (1st flr)
        Manhour Capability =          10.00     MH/kg
        Total No. of kg       =      706.97 kg
        No. of Persons        =         8
        No. of Days           =       1.10      day(s)
                       say =            2       day(s)
                                     Activity No. J
               Fabrication of Forms, scaffolding and staging for stairway
                                                2
        Manhour Capability =         1.42     m /hr
        Total Area           =     102.84 m2
        No. of Persons       =        3
        No. of Days          =       3.02     day(s)
                       say =           4      day(s)
                                      Activity No. K
                Soil poisoning and excavating of septic tank and catch basin
Soil poisoning
         No. of Persons     =          3
         No. of Days        =         2.00     day(s)
Excavation
                                                   3
         Manhour Capability =         1.35     m /m day
                                                   3
        Total Volume           =     51.99     m
        No. of Persons         =       6
        No. of Days            =      6.42     day(s)
                         say   =        7      day(s)
                         say   =        9      day(s)
                                  Activity No. L
                           Concreting of CF and WF
                                                                  3
Equipment Capability (1 bagger conc. Mixer)     =        6.80    m /day
                                            3
Pouring                =       5.00     m /hr
                                            3
Total Volume           =      49.10     m
No. of Persons         =        14
No. of Days            =       9.41     day(s)
                 say   =        10      day(s)
                                  Activity No. M
                      Concreting of footing of septic tank
                                                                  3
Equipment Capability (1 bagger conc. Mixer)     =         6.80   m /day
                                            3
Pouring                =       5.00     m /hr
                                            3
Total Volume           =       1.08     m
No. of Persons         =        4
No. of Days            =       0.18     day(s)
                 say   =         1      day(s)
                            Activity No. N
                  Fabrication of rebars for stairway
Manhour Capability =       10.00     kg/hr
Total No. of kg     =      33.19     kg
No. of Persons      =        3
No. of Days         =       0.14     day(s)
               say =          1      day(s)
                               Activity No. O
                                  Dummy
No. of Days            =        0       day(s)
                           Activity No. P
       Installation of Forms, scaffolding for columns (1st flr)
                                       2
Manhour Capability =       0.85      m /hr
                                            2
Total Area             =      250.29    m
No. of Persons         =        6
No. of Days            =       8.86     day(s)
                 say   =         9      day(s)
                               Activity No. Q
                                  Dummy
No. of Days            =        0       day(s)
                          Activity No. R
                  Laying of CHB for wall (1st flr)
                                    2
Manhour Capability =      1.25     m /hr
                                           2
Total Area             =     444.09    m
No. of Persons         =       10
No. of Days            =      8.88     day(s)
                 say   =        9      day(s)
                                  Activity No. S
                         Concreting of column (1st flr)
                                                                  3
Equipment Capability (1 bagger conc. Mixer)     =       6.80   m /day
                                           3
Pouring                =      5.00     m /hr
                                           3
Total Volume           =     22.46     m
No. of Persons         =       8
No. of Days            =      3.37     day(s)
                 say   =        4      day(s)
                            Activity No. T
                 Fabrication of rebars for slab (1st flr)
Manhour Capability =        10.00    kg/hr
Total No. of kg     =      1203.28 kg
No. of Persons      =         4
No. of Days         =        3.76    day(s)
               say =           4     day(s)
                          Activity No. U
            Laying of CHB for septic tank and catch basin
                                      2
Manhour Capability =       1.25     m /hr
                                      2
Total Area          =     27.00     m
No. of Persons      =       3
No. of Days         =      1.80     day(s)
               say =         2      day(s)
                              Activity No. V
                                 Dummy
No. of Days            =       0       day(s)
                             Activity No. W
          Stripping of forms & scaffolding of columns (1st flr)
                                        2
Manhour Capability =         2.35     m /hr
Total Area           =      250.29 m2
No. of Persons       =        6
No. of Days          =       4.44     day(s)
               say =           5      day(s)
                              Activity No. X
                                  Dummy
No. of Days            =      0.00     day(s)
                 say   =        0      day(s)
                             Activity No. Y
                           Earthfilling for slab
                                         3
Manhour Capability =         1.22      m /m day
                                            3
Total Volume           =     146.12     m
No. of Persons         =       4
No. of Days            =      7.49      day(s)
                 say   =        8       day(s)
                              Activity No. Z
                  Installation of rebars for slab (1st flr)
Manhour Capability =          10.00    kg/hr
Total No. of kg       =      2431.32 kg
No. of Persons        =         8
No. of Days           =        7.60    day(s)
               say =             8     day(s)
                            Activity No. A'
               Installing of electrical conduits (1st flr)
                                           2
Manhour Capability =         1.33     hr/m
                                            2
Total Area             =     131.25     m
No. of Persons         =       6
No. of Days            =      3.64      day(s)
                 say   =        4       day(s)
                          Activity No. B'
                  Spreading, tamping and grading
                                     3
Manhour Capability =      2.09     m /hr
                                            3
Total Volume           =     146.12     m
No. of Persons         =       3
No. of Days            =      2.91      day(s)
                 say   =        3       day(s)
                          Activity No. C'
       Roughing in plumbing and water pipe connections (1st flr)
Manhour Capability
  Pipes             =        1     hr/pc         81.00     pcs
  Clean-outs        =        2     hr/pc         15.00     pcs
No. of Persons      =        6
No. of Days         =      2.31    day(s)
               say =         3     day(s)
                          Activity No. D'
        Fabrication of forms, scaffolding for beams (1st flr)
                                      2
Manhour Capability =       1.42     m /hr
                                             2
Total Area             =       15.94     m
No. of Persons         =         4
No. of Days            =       0.71      day(s)
                 say   =         1       day(s)
                              Activity No. E'
                 Installation of rebars for beam (1st flr)
Manhour Capability =          10.00    kg/hr
Total No. of kg       =      358.95 kg
No. of Persons        =         8
No. of Days           =       1.12     day(s)
               say =            2      day(s)
                                  Activity No. F'
                           Concreting of slab (1st flr)
                                                                   3
Equipment Capability (1 bagger conc. Mixer)     =         6.80    m /day
                                             3
Pouring                =        5.00     m /hr
                                             2
Total Volume           =       131.25    m
No. of Persons         =         15
No. of Days            =        0.38     day(s)
                 say   =          1      day(s)
                            Activity No. G'
         Installation of forms, scaffolding for beams (1st flr)
                                        2
Manhour Capability =         0.65     m /hr
                                             2
Total Area             =       15.94     m
No. of Persons         =         8
No. of Days            =       0.77      day(s)
                 say   =         1       day(s)
                           Activity No. H'
    Fabrication of forms, scaffolding & staging for slab(2nd flr)
                                      2
Manhour Capability =       1.42     m /hr
                                            2
Total Area             =      56.63     m
No. of Persons         =        4
No. of Days            =      2.51      day(s)
                 say   =        3       day(s)
                              Activity No. I'
                 Installation of rebars for beam (1st flr)
Manhour Capability =          10.00    kg/hr
Total No. of kg       =      358.95 kg
No. of Persons        =         6
No. of Days           =       1.50     day(s)
               say =            2      day(s)
                            Activity No. J'
                 Fabrication of rebar for slab (2nd flr)
Manhour Capability =        10.00    kg/hr
Total No. of kg     =      221.16 kg
No. of Persons      =         3
No. of Days         =       0.92     day(s)
               say =          1      day(s)
                              Activity No. K'
                                 Dummy
No. of Days            =       0       day(s)
                           Activity No. L'
      Installation of forms, scaffolding & staging for stairway
                                       2
Manhour Capability =        0.65     m /hr
                                            2
Total Area             =      10.00     m
No. of Persons         =        5
No. of Days            =      0.77      day(s)
                 say   =        1       day(s)
                                  Activity No. M'
                          Concreting of beam (1st flr)
                                                                 3
Equipment Capability (1 bagger conc. Mixer)     =        6.80   m /day
                                                3
Pouring                =       5.00     hr/m
                                            3
Total Volume           =       3.21     m
No. of Persons         =        4
No. of Days            =       0.97     day(s)
                 say   =         1      day(s)
                            Activity No. N'
    Installation of forms, scaffolding & staging for slab (2nd flr)
                                       2
Manhour Capability =         0.65    m /hr
                                          2
Total Area             =     56.63    m
No. of Persons         =       4
No. of Days            =     5.44     day(s)
                 say   =       6      day(s)
                            Activity No. O'
               Installing of electrical wirings (2nd flr)
                                        2
Manhour Capability =         1.33     m /hr
                                          2
  THHN conduit         =    56.625    m
No. of Persons         =       4
No. of Days            =     2.35     day(s)
               say     =       3      day(s)
                              Activity No. P'
                 Installation of rebars for slab(2nd flr)
Manhour Capability =          10.00    kg/hr
Total No. of kg      =       221.16 kg
No. of Persons       =          4
No. of Days          =        1.38     day(s)
               say =            2      day(s)
                          Activity No. Q'
      Roughing in plumbing and water pipe connections (2nd flr)
Manhour Capability
  Pipes             =       1      hr/pc          40      pcs
  Clean-outs        =       2      hr/pc          15      pcs
No. of Persons      =       4
No. of Days         =      2.19    day(s)
               say =         3     day(s)
                          Activity No. R'
         Stripping of forms & scaffolding of beams (1st flr)
                                     2
Manhour Capability =       1.95    m /hr
                                          2
Total Area             =     15.94    m
No. of Persons         =       3
No. of Days            =     2.59     day(s)
                 say   =       3      day(s)
                             Activity No. S'
                  Installation of rebars for stairway
Manhour Capability =        10.00     kg/hr
Total No. of kg     =       33.19     kg
No. of Persons      =         10
No. of Days         =        8.30     day(s)
               say =           9      day(s)
                                  Activity No. T'
                   Concreting of slab and beams (2nd flr)
                                                              3
Equipment Capability (1 bagger conc. Mixer)     =     6.80   m /day
                                              3
Pouring                =     5.00     hr/m
                                          2
Total Volume           =    51.00     m
No. of Persons         =      10
No. of Days            =     0.22    day(s)
                 say   =       1     day(s)
                        Activity No. U'
                     Concreting of stairway
                                    3
Manhour Capability =    0.91     m /m day
                                          3
Total Volume           =     1.55     m
No. of Persons         =      2
No. of Days            =     0.85    day(s)
                 say   =       1     day(s)
                           Activity No. V'
                  Laying of CHB for Wall (2nd flr)
                                      2
Manhour Capability =       1.25     m /hr
                                          2
Total Area             =    344.12    m
No. of Persons         =      5
No. of Days            =    13.76    day(s)
                 say   =      14     day(s)
                          Activity No. W'
           Stripping of forms & scaffolding of stairway
                                     2
Manhour Capability =       1.95    m /hr
                                          2
Total Area             =    102.84    m
No. of Persons         =      4
No. of Days            =     3.30    day(s)
                 say   =       4     day(s)
                           Activity No. X'
                  Plastering of CHB Walls (1st flr)
                                         2
Manhour Capability =       1.67     hr/m
                                          2
Total Area             =    888.17    m
No. of Persons         =      5
No. of Days            =    13.30     day(s)
                 say   =      14      day(s)
                          Activity No. Y'
       Fabrication of forms, scaffolding for columns (2nd flr)
                                           2
Manhour Capability =       1.42     MH/m
                                          2
Total Area             =    116.48    m
No. of Persons         =      3
No. of Days            =     6.91     day(s)
                 say   =       7      day(s)
                           Activity No. Z'
     Stripping of Forms, scaffolding & staging for slab (2nd flr)
                                     2
Manhour Capability =       1.86     m /hr
                                          2
Total Area             =    56.63     m
No. of Persons         =      6
No. of Days            =    1.27      day(s)
                 say   =      2       day(s)
                             Activity No. A''
                Fabrication of rebars for column (2nd flr)
Manhour Capability =         10.00     MH/kg
Total No. of kg       =     1550.62 kg
No. of Persons        =         6
No. of Days           =       3.23     day(s)
               say =            4      day(s)
                           Activity No. B''
       Installation of forms, scaffolding for columns (2nd flr)
                                       2
Manhour Capability =        0.85      m /hr
                                          2
Total Area             =    116.48    m
No. of Persons         =      6
No. of Days            =     5.71     day(s)
                 say   =       6      day(s)
                            Activity No. C''
                                Dummy
No. of Days            =      0       day(s)
                              Activity No. D''
                Installation of rebars for column (2nd flr)
Manhour Capability =          10.00     kg/hr
Total No. of kg        =     1550.62 kg
No. of Persons         =         4
No. of Days            =       4.85     day(s)
               say =             5      day(s)
                             Activity No. E''
                                  Dummy
No. of Days            =      0.00    day(s)
                 say   =        0     day(s)
                            Activity No. F''
Fabrication of Forms, scaffolding and staging for beams and slab (roof)
                                       2
Manhour Capability =         1.42    m /hr
                                          2
Total Area             =     56.63    m
No. of Persons         =       4
No. of Days            =     2.51     day(s)
                 say   =       3      day(s)
                            Activity No. G''
          Fabrication of rebars for slab and beam (roof deck)
Manhour Capability =        10.00     kg/hr
Total No. of kg     =      2542.15 kg
No. of Persons      =         3
No. of Days         =       10.59     day(s)
               say =         11       day(s)
                                 Activity No. H''
                        Concreting of Column (2nd flr)
                                                                3
Equipment Capability (1 bagger conc. Mixer)    =       6.80   m /day
                                              3
Pouring                =      5.00    hr/m
                                          3
Total Volume           =     10.29    m
No. of Persons         =       10
No. of Days            =      2.16    day(s)
                 say   =        3     day(s)
                              Activity No. I''
Installation of forms, scaffolding and staging for beams and slab (roof)
                                         2
Manhour Capability =          0.65     m /hr
                                          2
Total Area             =     56.63    m
No. of Persons         =       4
No. of Days            =     5.44     day(s)
                 say   =       6      day(s)
                          Activity No. J''
       Roughing in plumbing and water pipe connections (roof)
Manhour Capability
  Pipes             =       1      hr/pc          76      pcs
  Clean-outs        =       2      hr/pc           9      pcs
No. of Persons      =       3
No. of Days         =     3.92     day(s)
               say =        4      day(s)
                             Activity No. K''
          Installation of rebars for slab and beam (roof deck)
Manhour Capability =         10.00     kg/hr
Total No. of kg       =     2542.15 kg
No. of Persons        =        5
No. of Days           =      12.71     day(s)
               say =           13      day(s)
                              Activity No. L''
                       Installing of electrical works
Manhour Capability
  THHN conduit                0.267    hr/m
No. of Persons     =            3
No. of Days        =           5.35    day(s)
               say =             6     day(s)
                          Activity No. M''
        Stripping of forms & scaffolding of columns (2nd flr)
                                      2
Manhour Capability =       2.35     m /hr
                                           2
Total Area             =     116.48    m
No. of Persons         =       5
No. of Days            =      2.48     day(s)
                 say   =        3      day(s)
                                  Activity No. N''
                        Concreting of beam (roof deck)
                                                                  3
Equipment Capability (1 bagger conc. Mixer)     =      6.80      m /day
                                               3
Pouring                =      5.00     hr/m
                                           3
Total Volume           =      12.54    m
No. of Persons         =        10
No. of Days            =       1.88    day(s)
                 say   =         2     day(s)
                                 Activity No. O''
                         Concreting of slab (roof deck)
                                                                3
Equipment Capability (1 bagger conc. Mixer)    =        6.80   m /day
                                                 3
Pouring                =         5.00    hr/m
                                             2
Total Volume           =        161.50   m
No. of Persons         =          16
No. of Days            =         0.44    day(s)
                 say   =           1     day(s)
                                 Activity No. P''
                           Installation of down spout
Manhour Capability
  Pipes                =          1      hr/pc
No. of Persons         =          3
No. of Days            =         1.21    day(s)
               say     =           2     day(s)
                             Activity No. Q''
                  Installation of fabricated door jamp
Manhour Capability =         40.00     bd.ft./day
Total Area           =       80.00     bd.ft.
No. of Persons       =         2
No. of Days          =        1.00     day(s)
               say =            1      day(s)
                                Activity No. R''
                                    Dummy
No. of Days            =          0       day(s)
                           Activity No. S''
                  Plastering of CHB Walls (2nd flr)
                                         2
Manhour Capability =        1.67    hr/m
                                             2
Total Area             =        688.24   m
No. of Persons         =          4
No. of Days            =        12.88    day(s)
                 say   =          13     day(s)
                                Activity No. T''
                                    Dummy
No. of Days            =          0      day(s)
                              Activity No. U''
               Installation of fabricated doors & windows
Manhour Capability
Doors                 =          2     sets/day       19          sets
windows               =        1.00    set/hr         23          sets
No. of Persons        =          3
No. of Days           =        4.13    day(s)
               say =             5     day(s)
                           Activity No. V''
   Stripping of forms, scaffolding and staging for beams and slab
                                      2
Manhour Capability =        1.86    m /hr
                                              2
Total Area              =       56.63     m
No. of Persons          =         8
No. of Days             =       0.95      day(s)
                 say    =         1       day(s)
                           Activity No. W''
           Installation of ceiling frame and ceiling board
                                           2
Manhour Capability =        1.00      hr/m
                                              2
Total Area              =      161.50     m
No. of Persons          =        3
No. of Days             =       6.73      day(s)
                 say    =         7       day(s)
                        Activity No. X''
                     Installation of railings
Manhour Capability =      0.5      hr/m
No. of Persons     =       3
No. of Days        =     1.67     day(s)
               say =       2       day(s)
                                Activity No. Y''
                       Installation of electrical fixtures
Manhour Capability
  Lighting Fixtures =            1.25     hr/set             98   sets
  Convenience Outlet =           1.25     hr/set             39   sets
  Panel Board        =           1.15     hr/set              1   sets
  Utility Box        =          0.19      hr/set             57   sets
  Switches           =           1.25     hr/set             18   sets
No. of Persons       =            3
No. of Days          =          17.70     day(s)
               say =              18      day(s)
                                Activity No. Z''
                                Painting Works
                                              2
Manhour Capability =             0.43    hr/m
                                              2
Total Area              =      1576.41    m
No. of Persons          =         6
No. of Days             =       14.12     day(s)
                 say    =        15       day(s)
                                Activity No. A'''
                            Installation of tile works
Manhour Capability      =        25.00     pcs/day
Total Area              =       1340.00 pcs
No. of Persons          =          3
No. of Days             =        2.23      day(s)
               say      =          3       day(s)
                                Activity No. B'''
                                    Dummy
No. of Days             =         0       day(s)
                                Activity No. C'''
                       Installation of Plumbing fixtures
Manhour Capability
  Lavatory              =          8      hr/set           2   sets
  Water closet          =         8       hr/set           2   sets
  Kitchen sink          =         14      hr/set           0   sets
  Kitchen faucet        =          2      hr/set           0   sets
  Gate valve            =          8      hr/set           2   sets
  Faucet                =          2      hr/set           5   sets
  Floor drain           =          2      hr/set           4   sets
No. of Persons          =          3
No. of Days             =        2.75     day(s)
               say      =          3      day(s)
                           Activity No. D'''
   Clearing of Site For Final Inspection & Transfers to the Owner
                                          2
Manhour Capability =        0.30     hr/m
                                              2
Total Area              =       131.25    m
No. of Persons          =         5
No. of Days             =       10.94     day(s)
                 say    =         11      day(s)