Air Handling Units (AHU) Pre-Commissioning Tests
**Ref document: As Built Drawings, O&M, Any Previous test results available
No Description
1 Check Starter panel and verify breakers are in good working
condition, Ammeter, Voltmeter, BMS, etc. Check whether the
Single Line Diagram is available inside the Panel
2 Check the operation of the VSD panel
3 Check whether the Chilled water piping & Condenser water piping
installed with the motorised valves, Balancing Valves, etc as
per approved As Built drawings
4 Check Fire Dampers are open
5 Check air filters are clean
6 Check BMS and Fire Signal connections
7 Start AHU and run for 10 minutes
8 Measure air flow in the supply main duct
9 Measure air flow in the return main duct
10 Measure air flow in the fresh air duct
11 Measure static pressure in Main Supply air duct
12 Measure Chilled water temperature in and out
13 Measure Condenser water temperature in and out
14 Measure the Chilled Water Flowrate and Condenser water
flowrate
15 Calculate cooling capacity of AHU based on the parameters measured
above
16 Measure Noise Level inside and outside Room
17 Check condensate water free flow and into floor trap
18 Verify tap point inside AHU Room
19 Verify the measured values against the specified values