UK Process & Standards
Richard Lane
UK & EU BIM Task Group
29 November 2016
We (eventually) agreed common stages through working with:
  • Institutions representing design professionals;
  • Repeat public & private sector clients;
  • Other institutions (outside construction industry)
                                                         Delivery   Operation
We developed standards that described the project lifecycle…
From the ‘Delivery’ stage
                            • PAS1192-2
                              • Information management for the
                                capital / delivery phase;
                              • ‘…specific guidance for the
                                information management
                                requirements associated with
                                projects delivered using BIM…’
At handover from ‘delivery’ to ‘operations’…
         • BS 8536-1
           • Involve the operator and the
             operations team and their supply
             chain from the outset;
           • Extend the involvement of the supply
             chain for the project’s delivery through
             to operations and defined periods of
             aftercare.
And into ‘operations’…
               • PAS1192-3
                 • Information management for the
                   operational phase;
                 • Integrating the management of
                   information across the longer term
                   activity of asset management with the
                   shorter term activity of asset
                   construction for a portfolio of assets
                   should deliver real savings.
Departmental case study
Ministry of Justice Case
Engagement workshops
• 3 x workshops from 2011 to January 2012:
  • Delivery Management;
  • Commercial processes;
  • Technical.
Coordinated process map completed January 2012
• Why is the information required? (purposes /
  questions)
• When is the information required? (decision
  point / workstage)
• What information is required? (information
  type and level of detail)
• Who is responsible for preparing the
  information (roles & responsibilities)
• How will the information be delivered
  (exchange format and process)
BIM implementation strategy published March 2012
Early adopter project March 2012 – early 2013
• ~20% savings in capital
  delivery cost
BIM library developed 2013
Design for Manufacture strategy developed early 2015
  Design for Manufacture strategy implemented 2017?
• ~Targeted savings
  of 30% cost, 50%
  programme