Configuration Checklist For SAP PP
The following give you an overview of the configuration
checklist for SAP PP and their IMG Path.
SPRO
1) Define Distribution Keys
IMG -> Production Planning for Process Industries -> Master
Data -> Material List -> Item Data -> Item Data from related
areas -> Define Distribution Keys
2) Determine Person responsible for Resource
IMG -> Production Planning for Process Industries -> Master
Data -> Resource -> General Data -> Determine Person
responsible
3) Define Planner Group
IMG -> Production Planning for Process Industries -> Master
Data -> Master Recipe -> Define Capacity Planner
4) Define Capacity Planner
IMG -> Production Planning for Process Industries -> Master
Data -> Resource -> Capacity Requirement Planning ->
Determine Capacity Planner
5) Determine Standard Value Parameter
IMG -> Production Planning for Process Industries -> Master
Data -> Resource -> General Data -> Standard Value ->
Define Parameter
6) Define Setup Groups and Setup Group Categories
IMG -> Production Planning for Process Industries -> Master
Data -> Master Recipe -> Data for operations and phases ->
Define set up groups and set up group categories
7) Define copy setting between plants-Process
IMG -> Production Planning for Process Industries -> Process
Management -> Tools -> Define copy setting between plants
8) Define Set Up Control Recipe destination
IMG -> Production Planning for Process Industries -> Process
Management -> Control Recipe/PI sheet -> Set up control
recipe destination
9) Define MRP controller
IMG -> Material Management -> Consumption based Planning
-> Master Data -> Define MRP controller
10) Special Procurement
IMG -> Material Management -> Consumption based Planning
-> Master Data -> Define Special procurement types
11) Define Floats (Scheduled Margin Key)
IMG -> Material Management -> Consumption based Planning
-> Planning -> Define Floats (Scheduled Margin Key)
12) Define Splitting of Forecast requirements for MRP-
IMG -> Material Management -> Consumption based Planning
-> Evaluation -> Forecast -> Define Splitting of forecast
requirements of MRP
13) Maintain Correction Factors for Forecast
IMG -> Material Management -> Consumption based Planning
-> Planning -> Procurement -> Maintain Correction factors for
forecast
14) Carry Out Overall Maintenance of Plant Parameters
Maintaining plant parameters in MRP
IMG -> Material Management -> Consumption based Planning
-> Plant Parameters -> Carry out overall maintenance of plant
parameters
15) Define Planning Horizon
IMG -> Material Management -> Consumption based Planning
-> Planning -> MRP calculation -> Define Planning Horizon
16) Activate Requirement Planning
IMG -> Material Management -> Consumption based Planning
-> Planning -> Activate Requirement Planning
17) Define Range of Coverage Profiles (Dynamic Safety
Stock)
IMG -> Material Management -> Consumption based Planning
-> Planning -> MRP calculation -> Define range of coverage
profile (Dynamic Safety Stock)
18) Define Stock in Transfer and Blocked Stock Availability
IMG -> Material Management -> Consumption based Planning
-> Planning -> MRP calculation -> Stocks -> Define Stock in
transfer and blocked stock
19) Define MRP Areas
IMG -> Material Management -> Consumption based Planning
-> Master Data -> MRP areas -> Define MRP areas
20) Carry out maintenance of MRP groups
IMG -> Material Management -> Consumption based Planning
-> MRP groups-> Carry out maintenance of MRP groups
21) Define Scope of total Planning - MRP
IMG -> Material Management -> Consumption based Planning
-> Planning -> Define Scope of total Planning
22) Define Order Types
IMG -> Production Planning for Process Industries -> Process
Order -> Master Data -> Order -> Define Order Type
23) Define Order Type Dependent parameters
IMG -> Production Planning for Process Industries -> Process
Order -> Master Data -> Order -> Define Order Type
Dependent parameters
24) Define Production Scheduler
IMG -> Production Planning for Process Industries -> Process
Order -> Master Data -> Bill of Material -> Define Production
Scheduler
25) Define Checking Control - Process Order
Define Availability Check Define Checking Control
IMG -> Production Planning for Process Industries -> Process
Order -> Operations -> Availability Check -> Define Checking
Control
26) Define Checking Rule for backorder processing
IMG -> Production Planning for Process Industries -> Process
Order -> Operations -> Availability Check -> Define Checking
rule for back order processing
27) Define Stock and batch determination for good movement
IMG -> Production Planning for Process Industries -> Process
Order -> Operations -> Define Stock and batch determination
for good movement
28) Specify Scheduling Parameters
IMG -> Production Planning for Process Industries -> Process
Order -> Operations -> Scheduling -> Specify Scheduling
Parameters
29) Define Reduction Strategies
IMG -> Production Planning for Process Industries -> Process
Order -> Operations -> Scheduling -> Resource data -> Define
Reduction Strategy
30) Define Confirmation Parameters
Define Order Confirmation
IMG -> Production Planning for Process Industries -> Process
Order -> Operations ->
Confirmation -> Define Confirmation Parameters
31) Define Valuation of Goods Received
IMG -> Production Planning for Process Industries -> Process
Order -> Integration -> Define Valuation of goods received
32) MRP creation indicator
IMG -> Material Management -> Consumption based Planning
-> Planning -> Define creation indicator
33) Define safety stock
IMG -> Material Management -> Consumption based Planning
-> Planning -> MRP calculation -> Stocks -> Define Safety
Stocks
34) Define alternative determination of Production
IMG -> Production Planning for Process Industries -> Process
Order -> Operations -> BOM selection -> Define alternate
determination of production
35) Define no. ranges
IMG -> Production Planning for Process Industries -> Process
Order -> Master data -> Order -> Number Ranges -> Define
number ranges for orders
36) Define no. ranges
Following Number ranges you need to define :
In OPPQ you need to define Number Ranges for :
Planned Orders
Reservations / Dependent Requirements
Purchase Requisitions
MRP Lists
Simulative Dependent Requirements
Similarly you need to define Number Range for :
Production Order in CO82
Confirmations in CO80
Reservations in CO83
Operations in CO81
Capacity Requirements in CO84
Same way you need to maintain all other number ranges in
Production Server manually. However first you need to
transfer Number range object through Transport Request.