Bwsi Group of Companies Project Monitoring Sheet For Pipelaying Activity Responsible Person Attachments/ Forms Signatories Duration (Days) Seq No

This document provides a project monitoring sheet for a pipeline laying project with 20 main activities. It lists the activity, responsible person, required attachments or forms, required signatories, and estimated duration in days for each step. Key activities include capex proposal, permit acquisition from local government, purchasing and delivery of materials, awarding the contract, and issuing a notice to proceed to mark the official start of construction.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
139 views4 pages

Bwsi Group of Companies Project Monitoring Sheet For Pipelaying Activity Responsible Person Attachments/ Forms Signatories Duration (Days) Seq No

This document provides a project monitoring sheet for a pipeline laying project with 20 main activities. It lists the activity, responsible person, required attachments or forms, required signatories, and estimated duration in days for each step. Key activities include capex proposal, permit acquisition from local government, purchasing and delivery of materials, awarding the contract, and issuing a notice to proceed to mark the official start of construction.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

BWSI GROUP OF COMPANIES PROJECT MONITORING SHEET FOR PIPELAYING

Seq
Activity Responsible Person Attachments/ Forms Signatories Duration(Days)
No.

1 Capex Proposal AM/BM Job Order/ Business Plan AM/BM 1


2 Actual Measurement BE 3
Hydraulic Analysis( if necessary) BE Hydraulic Simulation Recommendation BE/ VP for Engineering
3 Capex Estimation BE Drawing & Estimate BE/Purchasing/BM 3
4 Capex Estimates Review PMDM SOP/ BOM/ Network Map PMDM 2
5 Capex Estimates Approval PMDM SOP/ BOM/ Network Map PMDM 1
6 Capex Proposal Preparation BM SOP/ BOM/ Network Map BM 2
7 Capex Proposal Review
7.1 Area Manager AM Capex Proposal AM 1
7.2 EA to the SVP EA to the SVP Capex Proposal EA to the SVP 1
8 Capex Proposal Approval
8.1 up to PhP 500,000 SVP Capex Proposal SVP 7
8.2 PhP 501,000-PhP 6,000,000 PRES Capex Proposal PRES 7
8.3 more than PhP 6,000,000 BOD Capex Proposal BOD 7
9 Preparation of Capex Approval Transmittal Memo EA to the SVP Approved Capex SVP 1
10 Receipt of Capex Approval Transmittal Memo BE/BM/PMDM Approved Capex 1
MRS Form / Purchase Requisition
11 Preparation of MRS and/or PR BE Form/ Approved CAPEX (Transmittal BE/BM/Warehouseman/AM 1
Memo)/BOM
12 Permit Acquisition
Signed & Sealed Drawing Plans & Barangay Captain/ Municipal
Barangay & Municipal BE
Estimates/Letter Engineer
7
Signed & Sealed Drawing Plans &
Provincial BE
Estimates/Letter
Provincial Engineer 14
Signed & Sealed Drawing Plans &
DPWH BE
Estimates/Letter
DPWH Engineer 30

13 Purchasing and Delivery of Mat'ls to Branch


PVC Pipes Purchasing Dept 30
Fittings and Materials Purchasing Dept/ Central Warehouse 45
14 Awarding of Contract SVP/PMDM

12.1 up to PhP 500,000 MD

12.2 more than PhP 500,000 MD


*Mechanics in awarding of contract
Ma’am MTMP and CMS will choose projects that will be
14.1 VP for Operation/ EA to the SVP 1
awarded to FUSECON Inc.( Effective June 1, 2018)
Ma’am MTMP and CMS will choose projects that will be
14.2 awarded to Construction for Pipelaying Projects VP for Operation/ EA to the SVP 1
Department.
Ma’am MTMP and CMS will assign projects for frequent
14.3 VP for Operation/ EA to the SVP 1
or regular contractor. ( Effective June 1, 2018)
For the remaining projects, it will be subjected for bidding VP for Operation/ EA to the SVP/ Bid Forms/ Quotations by the
14.4 PMDM Contractors
14
or negotiation with the accredited contractors.
15 Preparation of Contract, NOA PMDM NOA & Contract agreement 1

16 Contract, NOA Signing SVP/ PMDM NOA & Contract agreement SVP / PMDM / Contractor 1
17 Preparation of Advance Payment Billing
*For New/Infrequent Contractor (Provisions for Contract agreement/ Billing Documents/
Advance Payment Guarantee Bond/
17.1 submission of bonds are needed upon releasing the PMDM
Performance Bond/ Contractor's All Risk
1
Advance Payment) Insurance
*For Regular/Frequent Contractor (No provisions for
17.2 submission of bonds needed upon releasing the Advance PMDM Contract agreement/ Billing Documents 1
Payment)
BE/Branch
18 Project Stakeout Representative/PMDM/Contractor/AM
1

BE/Branch
19 Preconstruction Meeting Representative/PMDM/Contractor/AM
1

20 Preparation and Issuance of NTP PMDM NTP PMDM/ Contractor 1

15.1 up to PhP 500,000 PMD

15.2 more than PhP 500,000 PMD

* The start of project will be based on date of issuance of


20.1 BE/Contractor
NTP or upon the realease of advance payment.
21 Mobilization of Contractor (from receipt of NTP) Contractor 1
22 Construction Stage BE/Contractor
BE/OS/BM/ Assigned
OS/Assigned Plumber Daily Accomplishment Report (DAR) Plumber/ Contractor
Representative
BE/OS/BM/ Assigned
BE/OS/BM/ Assigned Plumber Site Inspection Checklist Plumber/ Contractor
22.1 Project monitoring/ documentation/ inspection Representative
BE/PMDM/Contractor's
BE Field Advisory Notice
Representative
BE/Contractor
BE Hydro Test Form
Representative/BM/PMDM
DAR OS/BM/ Contractor's Rep
22.2 Preparation of Progress billing BE Hydro Test Form BE/Contractor's Rep. 2 days after inspection
Billing forms & Docs BM/AM/Accounting
23 Project Close Out Guidelines

23.1 Punch-listing PMDM/Contractor/BE Punchlist form BE/PMDM/ Contractor 1 To be conducted two days after project completion

23.2 Rectification of Punch List Contractor Punchlist form BE/PMDM./ Contractor 3 Contractor to start one day after the punch-listing

23.3 Final Inspection PMDM/BE/ BM/ OS/Contractor Final Inspection Report BE/PMDM/ Contractor 1

23.4 Final Quantification PMDM/Contractor/BE Final Quantification BM/BE 1 To be conducted one day after punch-list rectification is completed

23.5 Materials Inventory BE/Contractor/ Warehouseman/ BA Materials Inventory form Warehouseman/BM/ BE 1 To be conducted one day after final quantification is completed

23.6 Turnover of Unused Materials Contractor/ Warehouseman MRW Contractor/ Warehouseman 1 To be conducted one day after materials inventory is completed

DAR
Hydro Form
24 Preparation of Final Billing BE
Billing Forms & Docs
BE/PMDM /Accounting 3

Certificate of Completion

To be submitted 15 days after turn-over of unused materials by the contractor to


25 Submission of Actual Capex Expenditures Report to PLO BE/BA Schedule of Materials and Labor BM/BA 1
branch office is completed

Billing Forms & Docs

Certificate of Final Acceptance (*if the


project has already lapsed for 1 year
26 Preparation of Retention Billing BE upon project completion) BE/PMDM 2

Letter of Work Guarantee (*if the project


has not yet lapsed for 1 year upon
project completion)
27 Submission of As-built Drawings Contractor As-Built Plans BE/PMDM To be submitted 30 days after project completion
NO. ACTIVITIES/PERSON RESPONSIBLE

1 PRE-CONSTRUCTION MEETING

2 PROJECT STAKE-OUT

BRANCH ENGINEER (B.E)

BRANCH MANAGER (BM)


PROJECT
3 INSPECTION/MONITORING
OPERATIONS SUPERVISOR (O.S)

PLUMBER (*ASSIGNED BY B.M OR O.S IN


THE ABSENCE OF B.M/O.S/B.E)

4 BIDDING

5 NEGOTIATED CONTRACT

6 EXCAVATION/BACKFILLING

7 PIPELAYING

8 PIPE FITTING

9 HYDROTESTING

10 RESTORATION