DPR
DPR
1. Report................................................01-17
2. Hydraulics Calculations.......................18-27
3. Soil Report.........................................28-53
4. Design
i.Superstructure Design..................... 54-170
Contents
1.0 EXECUTIVE SUMMARY ............................................................................................................ 2
1.1 Introduction................................................................................................................................... 2
1.2 Project Background....................................................................................................................... 2
1.3 Salient Features of the Proposed Road: ...................................................................................... 3
1.4 Abstract of Cost Estimates:......................................................................................................... 4
2.0 PROJECT BACKGROUND........................................................................................................... 5
2.1 State Profile................................................................................................................................. 5
2.2 District Profile............................................................................................................................. 6
2.3 Manipur – Roadway Network..................................................................................................... 6
3.0 PROJECT DESCRIPTION............................................................................................................. 8
3.1 General........................................................................................................................................ 8
3.2 Existing Right of Way (ROW).................................................................................................... 8
3.3 Settlements................................................................................................................................. 8
3.4 Terrain Classification................................................................................................................. 8
3.5 Geology and Soil Types............................................................................................................. 8
3.6 Existing Bridge .......................................................................................................................... 8
4.0 DRAFT DESIGN STANDARD ................................................................................................... 10
4.1 Design Standards: PSC Girder Structures.................................................................................10
5.0 COST ESTIMATE........................................................................................................................14
5.1 General...................................................................................................................................... 14
5.2 Methodology .............................................................................................................................14
5.3 Estimation of Quantities............................................................................................................ 14
5.4 Material Sources .......................................................................................................................15
5.5 Analysis of unit rates ................................................................................................................17
5.6 Abstract of Cost Estimate ......................................................................................................... 17
Page: 1
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
National Highways & Infrastructure Development Corporation Ltd. is the employer and executing
agency for the consultancy services and the standards of output required from the appointed
consultants are of international level both in terms of quality and adherence to the agreed time
schedule.
1 At km 95.50 over the Irang river on Imphal to Jiribam road (NH-37, Old NH-53)
Pursuant to Clause 10.2 of the Terms of Reference (TOR), this Draft Detailed Project Report is
being submitted for Imphal-Jiribam road section (length- 220 Km ) on NH-37(old NH-53) in the
State of Manipur.
Page: 2
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
Alignment : The horizontal alignment of the Minimum Design Speed Considered - 25 kmph
existing road is curvilinear.
There are some sub-standard
stiff curve and also deficiency
in transition length as per
MoRT&H standards.
Cross-Section : Carriageway: 4m Proposed Bridge & Approach Road Cross Sections
Total width: 5.6m :
For Bridge Portion (Each part of Twin Bridge)
a)Carriageway width - 9.5m
b)Crash barrier – 0.5m on either side
c)Footpath – 1.5m on single side
d)Railing – 0.5m on single side
e)Total width – 12.5m
CBR Considered : - 8%
Pavement Design : - Flexible Pavement-15 Years
Life
(Approach Road)
Protection Work : Nil Bed & Bank Protection on Approach
Page: 3
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
Page: 4
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
Page: 5
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
Page: 6
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
.
Plate – 2.2: Roadway Network in Manipur
Page: 7
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
Page: 8
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
ation to potholes
Plate – 3.1: View of existing Bridge condition near proposed Bridge location
Page: 9
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
i) The overall width of the deck slab will be kept twin of 12.5m with 9.5m width carriageway.
ii) The span type and arrangement will be proposed considering site constraint, optimize the pier
number and aesthetics.
iii) Environmental loadings such as earth pressure, water current, seismic forces and temperature
effect will be taken as per IRC/BIS Codes. IS-1893 will be followed in evaluating dynamic increment
of earth pressure.
The Structural planning of new bridges or culverts will be guided by the layout of existing
structures.
The preliminary designs of proposed structures will be carried out in accordance with the provisions
of the following IRC Codes/guidelines.
Page: 10
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
IRC:87-2011 - Guidelines for the Design & Erection of False work for
Road Bridges
IRC:89-1997 -
Guidelines for design and construction of river training
and control works for road bridges (1st Revision)
Where IRC Codes are silent relevant BIS Codes will be followed. And where even BIS codes are
silent, international codes / MOST, MORTH guidelines will be adopted.
The project road falls in Seismic Zone V, as per the classification specified in IRC:6-2017. All
bridges will be designed for Seismic forces as per clause 219.1 of the said code.
The Soil parameters used in the preliminary design of foundations for Bridges will be taken from the
report of soil investigation and information obtained from local authorities / existing bridge design
data.
The following soil parameters will be used for material for back fill behind abutment of bridges and
culverts and the abutment structure will be designed accordingly.
= 30°
= 20°
d = 18 KN/m3
sub = 10 KN/m3
A 600 mm thick granular material filter behind abutment and fin wall and adequate weep holes in
abutment walls and fin wall will be provided for proper drainage.
(f) FOUNDATIONS:
For this Open foundation / Pile Foundation has been adopted based on the geotechnical investigation
data for the bridge.
Page: 11
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
(g) SUBSTRUCTURE:
RC wall type piers and wall type / spill through type abutment will be provided in the bridges,
matching the requirements and site conditions. Their design will be carried out in conformity with
IRC-78-2014. The shape, size and alignment will be considered from aesthetic and hydraulic aspects.
(h) SUPERSTRUCTURE:
I) Type & Span arrangement of superstructure has been chosen considering alignment,
obstruction due to at grade intersection, space constraint and other site constraints. Generally,
Precast or Pre fabricated type superstructure such as: PSC Box Girder, PSC I-Girder, Steel-
Concrete composite T-girder, Steel-Concrete composite Box-girder, steel truss girder, steel
bow string girder, and Precast RC T-girder has been considered in selecting the
superstructure. In this case, PSC I-Girder has been used.
II) BEARINGS:
Pot-PTFE bearings will be used in this bridge as required for specific span & Elastomeric
bearings for Arrester Block.
III) RAILINGS:
Reinforced concrete railings in M-30 grade concrete following MoRT&H standard will be
provided.
Reinforced concrete crash barrier in M-40 grade concrete following MoRT&H standard will
be provided.
V) EXPANSION JOINTS:
Buried type expansion/strip seal joints as per MoRT&H standard will be used.
R.C. approach slabs, 3.50m long and 300mm thick in M-30 concrete will be used at either
end of the bridges and culverts to ensure riding comfort and to reduce vehicular surcharge
on the abutment walls. One end of the approach slab is supported on R.C. bracket projecting
out, from dirt wall while the rest of the slab is placed on compacted soil as per the guidelines
issued by MoRT&H. A leveling course, 150mm thick in M-15 grade concrete will be
used under the approach slab.
4 nos. of 100mm dia drainage spout has been used for deck drainage in one side of
carriageway per span of the Twin Structure.
Page: 12
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
Fe-500 high yield strength deformed bars conforming to IS-1789 will be used as
reinforcement in all R.C. works. Uncoated stress relieved low relaxation strands conforming
to IS-14268 will be used in PSC works.
Page: 13
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
5.2 Methodology
Cost estimate methodology involves the following:
B. Approach Road
A. Bridge
1. Structure Cost
2. Drainage Work
4. Miscellaneous
B. Approach Road
Page: 14
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
The sources of materials are given in tabulated form in Table no. 5.1
Coarse Aggregates
Hard stone aggregate, fulfilling the requirements of concrete works, base, sub base and asphaltic
works are considered from Stone Quarry located at 60Km from Project road .Its available from
Noney.
Sand
Coarse Sand is available from Noney an average lead of 60 km from project road.
Fine aggregates are available Noney with an average lead of 60 km from project Road.
Bitumen
Bitumen of viscosity grade VG-40 is available from Numaligarh Refinery, Assam in bulk or packed
condition. Distance from Numaligarh Refinery, Assam to bridge location lead is 417 km.
Cement
Cement to be used in the construction work shall be any of the following types with the prior approval
of the Engineer:
The chloride content in cement shall in no case exceed 0.05 percent by mass of cement. Also, total
sulphur content calculated as sulphuric anhydride (SO3) shall in no case exceed 2.5 percent and 3.0
percent when tri-calcium aluminates present by mass is upto 5 or greater than 5 respectively. Cement
will be available at Imphal with an average lead of 107.5km from project Road.
Page: 15
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
Reinforcement
For plain and reinforced concrete (PCC and RCC) or pre-stressed concrete (PSC) works, the
reinforcement/un-tensioned steel as the case may be shall consists of the following grades of
reinforcing bars as shown in the table below. Steel will be available at Imphal with an average lead of
107.5km from project road has been considered.
Characteristic
Grade Bar Type conforming to Elastic Modulus
Strength fy( MPa
Designation governing IS Specification GPa
)
Table 5.1
Av.Lead
Sl. No. Material Place (Km.)
Numaligarh
8 Bitumen Refinery,
Assam 417
Page: 16
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction services in respect of 4 laning with paved shoulder of Imphal-Jiribam road section
Final Detailed
(length- 220km) on NH-37(old NH-53): proposed bridge over River Irang in the State of Project Report
Manipur.
Table 5.2
Page: 17
HYDRAULICS OF IRANG RIVER
CH._95.500 KM
18
CH._95.500KM
19
Detailed Hydraulic Calculations
Introduction:
The length of a bridge, its depth of foundation etc. are dependent on the maximum recorded quantum of
water or flood discharge which has passed through the river or the channel over which the bridge is
proposed and as such the design discharge is very important not only from economic consideration but
also from safety or stability consideration. Therefore, the design discharge, which might be the recorded
dischrge during the past 50-100 years, shall be ascertained very carefully.
There are various methods for the estimation of flood discharge like:
1. Catchment-Run-off Method from rainfall and other characteristics of the catchment by the use of
empirical formulae or by Rational Method.
2. By using Empirical Formulae.
3. From hydraulic characteristics of the stream such as the conveyance factor and slope of the stream.
4. From area of cross-section and velocity as observed on the stream at the bridge site.
5. From recorded flood discharge near the bridge site.
The use of a particular method depends upon (i) the desired objective, (ii) the available data and (iii) the
importance of the project. Further the Rational Method is found to be suitable for peak flow prediction in
2
small catchments upto 50 km in area. It finds considerable application in urban drainage designs and in
the design of small bridges and culverts.
Below, the flood discharge is estimated only by the first two methods written above. The third method
cannot be used for the hydraulic calculations as it is not possible to measure the velocity of the stream at
the bridge site as the stream is dry now. The fourth or last method is not used as the recorded flood
discharge near the bridge site is not available.
20
Table 4.1 (IRC:SP: 13-2004): Maximum Value of P :-
Sl. No. Characteristics of the catchment Value of P
1 Steep, bare rock and also city pavements 0.90
2 Rock, steep but wooded 0.80
3 Plateaus, lightly covered 0.70
4 Clayey soils, stiff and bare 0.60
5 Clayey soils, lightly covered 0.50
6 Loam lightly cultivated or covered 0.40
7 Loam largely covered 0.30
8 Sandy soil, light growth 0.20
9 Sandy soil, heavy brush 0.10
#N/A = 0.38
Hence, from curve 'f' for catchment area of 100492 hectares = 0.53
21
Cross-Sectinal Area-Bed Slope Method
Since the Bridge is provided across a defined stream, we estimate flood discharge from the conveyance factor & slope of the stream
applying Manning's Velocity Formula. As the flood rises above the bank line, the cross section of the river is divided in to three
subsections and velocity is calculated as per Cl-5.7, SP-13:2004.
Main section
22
Cross-Section at Chainage 433.268 m U/S :
Sub section 1
Main section
Area of
Level Avg. water Hydraulic
Segment Cross Wetted Velocity,V= Discharge,Q
Distance Level Difference depth below radius,R= 2/3 1/2
Points Length, L Section, Perimeter,P (R xS )/n =VxA
(m) (m) with HFL for each A/P 3
(m) A (m) (m/s) (m /s)
HFL(m) segment(m) (m)
(in sqm)
1 -28.354 225.044
0.419 0.792 0.606
2 -27.351 223.518 1.526 1.003 0.763 0.77 1.83
Left bank Total 0.77 1.83
2 -27.351 223.518 1.526
3 -21.769 220.553 4.491 5.582 3.009 16.79 6.32
4 -18.168 220.409 4.635 3.601 4.563 16.43 3.60
5 -13.119 219.546 5.498 5.049 5.067 25.58 5.12
6 0.000 219.454 5.590 13.119 5.544 72.73 13.12 4.446 3.824 823.390
7 5.910 219.593 5.451 5.910 5.521 32.63 5.91
8 11.152 220.090 4.954 5.242 5.203 27.27 5.27
9 14.579 220.409 4.635 3.427 4.795 16.43 3.44
10 17.797 225.044 0.000 3.218 2.318 7.46 5.64
Total 215.32 48.43 Total discharge 823.996
23
Cross-Section at Chainage 350.784 m D/S :
Sub section 1
Main section
Area of
Level Avg. water Hydraulic
Segment Cross Wetted Velocity,V= Discharge,Q
Distance Level Difference depth below radius,R= 2/3 1/2
Points Length, L Section, Perimeter,P (R xS )/n =VxA
(m) (m) with HFL for each A/P 3
(m) A (m) (m/s) (m /s)
HFL(m) segment(m) (m)
(in sqm)
Discharge :-
At D/S = 572.11 m3/s
At U/S = 824.00 m3/s
At ± 0.0 = 645.31 m3/s
Discharge to be taken (Ref.: Cl.-6.2.1,IRC:SP:13-2004) = 824.00 m3/s
Design Discharge = 824.00 m3/s
24
Fixing of Bridge Length:
3
Calculated Regime width for discharge of 824.00 m /s = 137.79 m
Ref.: Cl.-6.2.1,IRC:SP:13-2004
Regime width considering a restriction of 30 % = 96.453 m
2) Existing Bridge:
i) There is a 1x42.672 M _RCC T-Girder Bridge at the proposed Bridge location in bad condition
ii)Type of existing bridge = BOX
ii) Length of existing bridge = 42.672 m
3) Bank to bank distance:
Bank to bank distance: = 46 m
From the above three data and also considering the suitable abutment location and site condition,the proposed bridge has
been fixed as the details given below:
Overall length of Bridge: = 123.04 m
Span Arrangement = 3x41 M _PSC T-GIRDER
Total Bridge length (dirt wall inner to inner) = 123.040 m
25
Afflux Calculation with Orifice Formula:-
From IRC:SP:82-2008
Q=W(Dd+h)U
823.9957639 = 137.790 x (Dd+h)u
5.980083924 = (5.928 +h) * u
h = (5.980 / u ) - 5.9
u = 1.0070601 ok
h= 0.010 m ok
26
Scour Depth Calculation :
From IRC-78 , % increment of discharge with respect to catchment area = 10 %
Maximum Discharge = 793.37
Total incremented discharge as per code (for scour calculation) = 872.71 m3/s
27
SOIL RREPORT
CHAINAGE -95.500 KM
3X40.0M PSC T-GIRDER
IRANG RIVER
28
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
1.1. STRATUM – I :
The soil in this layer is characterized by stiff to very stiff, brownish/ yellowish grey, silty clay /
clayey silt with sand mixture. Rock fragments are observed at lower reaches. The average
“N” value of this layer is 18. The soil properties of this layer revealed from routine laboratory
test on “UDS” as well as “SPT” samples as collected from this layer are presented below.
Bulk Density, gms/cc 1.99 Specific gravity 2.69
Dry Density, gms/cc 1.68 Natural Water Content, % 18
Liquid limit % 32 Void ratio 0.940
Plastic limit % 19 GRAIN SIZE
Gravel % 07
TRSH-UU: Sand % 38
Cohesion kg/sqcm 1.19 Silt % 50
Friction angle ° 06 Clay % 05
29
NATIONAL HIGHWAYS AND INFRASTRUCTURE
DEVELOPMENT CORPORATION LTD. BORE HOLE PLAN
1:500 4, Parliament Street,
New Delhi - 110001
DESCRIPTION
Consultancy Services for Preparation of Detailed Project Report and providing
MKD. DATE CHKD. APPRD.
pre-construction services in respect of 4 Laning with Paved Shoulder of
FEBRUARY, 2018 ROAD NAME:- IMPHAL TO JIRIBAM (NH-37)
REVISIONS
Imphal - Jiribam Section (length-220 Km ) on NH-37 (NH-53) for proposed bridge
over River Irang in the State of Manipur.
30
Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
4047 JRC
JIRIBAM IMPHAL
239
BH-A1(01)
R.L.=237.013 M 238
00.00 237
BH-A2 (04) Completely to highly weathered, R1 22/00
* P=0.85
R.L.=235.102 M grey to deep grey, fine grained, III 236
fractured rock. R2 25/00 *
235 00.00 02.00 235
00.50 R3 40/00 P=1.02
*
234 234
Highly to moderately R4 45/00
33/62/05 N=12 Stiff to very stiff, * IV
233 weathered, grey to deep grey, 233
brownish grey to fine grained, fractured rock. R5 42/00 *
232 1.21/7°(UU) U1
yellowish grey, silty 232
R6 46/00 * P=0.90
40/53/07 N=16 clay / clayey silt with
231 sand mixture. Observed 06.00 231
R7 68/00 *
rock fragments at lower
230 42/53/05 230
N=18 reaches.. R8 72/00 *
I CL
229 U2 R9 69/00
229
1.16/5°(UU) * P=1.10
N=21 41/56/03
228 44/50/06 228
R10 73/00 *
N=30 30/26/39/05 Moderately to slightly
227 R11 77/00
227
weathered, grey to deep grey, * V
226 09.10 N>100
N>100
21/44/40/05 fine grained, fractured rock. 226
R1 13/00 R12 62/00 *
225 N>100
* 225
P=4.25 R2 17/00 R13 64/00 * P=1.05
N>100
*
224 R14 67/00
224
P=5.10 R3 15/00 *
N>100
* Design Maxm.Scour Level=217.492 M 14.00
223 223
R4 19/00 II R15 45/00
* Maxm.Scour Level=214.840 M *
222 N>100 222
R5 16/00 R16 42/00
P=8.12 * BH-P1(02) IV
221 N>100 BH-P2(03) Loose, brownish grey, silty sand. Observed 221
14.50 R6 18/00 R.L.=219.713 M R17 45/00*
* R.L.=219.492 M
decomposed rock dust, mica & clay binders.
220 R18
220
00.00 47/00 *
00.00 00.30 N>100 S.W.L.=18.07M
219 74/26 R1 23/00 18.00 219
IA DS-01 SM *
N=10 62/37/01 R2 26/00
218 II
* 218
N>100
02.00 N>100 R3 25/00 P=6.25
217 R1 25/00
* 217
* Various coloured, different size of boulders with
R4 28/00 * P=7.40
216 R2 33/00 intermediate spaces filled with sand. 216
S.W.L.=3.90M 03.60
R5 29/00 *
215 R3 25/14 S.W.L.=5.15M
215
*
R6 26/00
214 R4 29/20 * 214
*
R7 28/00 *
213 R5 23/00 213
*
R8 29/00 *
212 P=1.25 R6 25/00 212
*
R9 25/00 *
211 R7 26/00 211
*
R10 26/00
210 R8 27/00 * 210
* P=0.97
10.50 R11 34/00 *
209 R9 24/00 209
*
R12 37/00
208 R10 28/00 Highly to moderately weathered, light * 208
* grey to grey, fine grained, fractured rock. R13 40/00 *
207 R11 30/00 207
*
R14 49/00 P=1.10
206 P=0.90 R12 29/00 * 206
* 14.00
205 R13 31/00 205
*
204 R14 33/00 204
*
203 R15 37/00 203
*
R16 35/00 *
18.00
31
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
1.6. STRATUM – V:
Underlying the above we have a highly to moderately weathered light grey/ grey, fine
grained fractured rock and that continued up to the terminating depth around all borehole
location except BH-A2 location. The core recovery of this layer ranges from 26% to 49% with
nil RQD. The average properties of this layer as revealed from the routine laboratory test are
as follows.
Bulk Density, gms/cc 2.587
Dry Density, gms/cc 2.569
Water Content, % 0.700
Specific Gravity 2.801
Porosity % 6.8020
Point Load index, kg/sqcm 1.08
32
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
33
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
Average “N” in this layer = 21, So, estimated cohesion from N value =1.00 kg/sqcm†.
From laboratory TRSH-UU test results average C = 1.19 kg/sqcm & = 6°
Considering the predominant soil condition use C = 1.00 kg/sqcm & = 0°
†
Relation between SPT “N” and Shear Strength
Widely used relationship is due to Terzagi and Peck recommending C = N/16
However, it has been seen over the years with stiffness in clay the shear strength does not increase as rapidly as proposed by Terzagi.
Our experience also shows that for clays at medium to higher depth, the above relation does not hold good.
For Static Cone Penetration Tests, the recommendations for cone factor Nk generally are
C = qc/Nk where C = Cohesion in kg/sqcm and qc = Cone resistance in Static Cone and
Nk = 17 , 21 & 27 for normally consolidated clay, partly over consolidated clay and heavily over consolidated clay respectively
[Ref. Meigh, A.C (1987) : Cone Penetration Testing Methods and Interpretation, Butterworths, London, pp-43-47]
Taveres, A.X [Penetration Testing 1988, ISOPT-1, Volume-I, J.De Ruiter Editor, pp-375-379] has shown very clearly that a better correlation can be obtained
with stiffness of the clay. From his experimental results he obtained,
Range of SPT ‘N’ K = N/C
N < 10 12.50
10 < N < 20 14.20
20 < N < 30 16.25
30 < N < 40 20.00
Over the years on the basis of the laboratory test results we have been using the following relations. However, for “N” value greater than 40, we use C = N/27
1 .4 0
1 .3 0
1 .2 0
1 .1 0
1 .0 0
0 .9 0
C (K g/sqcm )
0 .8 0
0 .7 0
0 .6 0
0 .5 0
0 .4 0
0 .3 0
0 .2 0
0 .1 0
0 .0 0
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40
N V a lu e
34
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
Now, let us consider the mvc value for the pressure range between 0.50 to 2.00 kg/sqcm
Sample No. 0.50 – 1.00kg/sqcm 1.00 – 2.00kg/sqcm
BH04 / UDS02 0.0207 0.0159
Average weighted mvc,
sqcm/kg over entire pressure 0.0175
range
Giving more weightage to the laboratory test results,
Use mvc = [2 x 0.0175+0.0095+0.0119]/4=0.0141 sqcm/kg
STRATUM – II
This is a boulder layer. Use lowest possible Young’s modulus Es = 750 kg/sqcm
[corresponding to very dense sand layer]
The above bearing capacity should be checked against settlement criteria and this is shown
below.
35
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
‡
Use of mvc value to Calculate Settlement:
In our report we have calculated the settlement of soil assuming trapezoidal distribution of stress. In case of sandy soil, we are having only immediate
settlement. Now the problem starts when the soil becomes silty clay / clayey silt.
There is no definite and particular formula to calculate settlement of this type of soil. The mv value we get from the consolidation test results includes immediate
part also. It is seen that for the present case about 20-31% of compression takes place just after application of test load. Hence, judicious use of mvc (the
consolidation part only and not the mv) should be used. Thus mv value obtained from the e-logP curves should not be used blindly.
It is seen that the settlement determined as per Clause 9.2.2.3 for computation as per IS 8009 Part-1 leads to more or less same value as calculated by us.
Moreover, for sites like the present project where we have large numbers of consolidation test results, this type of approach is very very tedious. Since, this e-
logP curve is totally undefined and can not be framed in any particular equation, it is not at all suitable for any computer programming. Thus determination of
settlement through this procedure is not feasible for a day to day work basis job.
mvc & p approach is very straight forward and the equation is similar to normal settlement calculation by theory of elasticity (mvc 1/E). We are in this field
for the last 25 years and using this approach (mvc & p) satisfactorily to calculate settlement for almost all of our Clients.
Calculation of P
Note:
1) Ei = Young's Modulus values and Gi = Geological factor
A of the ith layer / sub layer,
B 2) Pi = Stress increment at the mid depth of the layer / sub
Ei = Young's Modulus. layer due to dispersion of the load applied at the founding
Pi = Stress increment C level using trapezoidal distribution of load (1H:2V)
at mid depth 3) Hi = Thickness of each layer / sub layer.
D 4) A thick layer is sometimes divided in to several sub layers
(like A, B, C etc.) for more accurate prediction of
E settlement.
F 5) Si(immediate) = Pi x Hi / Ei
6) Si(consolidation) = Pi x Hi x mvci x Gi
G
Hi H
Geological Factor: This is nothing but the consolidation settlement reduction factor, as given in IS 8009, Part I. This is termed as geological factor by M. J.
Tomlinson as the value is dependent on geology and pore pressure history of the soil.
36
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
4.3. RECOMMENDATIONS:
Based on the above calculation, the following bearing capacity values are recommended. It
is suggested to go for foundation with scour protection.
2.00 23
37
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
Around BH-P2(03) and BH-P1(02) location deep foundation in the form of pile is
recommended. Bored cast in-situ piles are preferred due to typical geological formation,
availability of construction agencies, ease of construction and less sound pollution. Such
piles may be placed at a suitable depth below Maximum scour level / inside rock layer
depending on structural requirement/ relevant codal provisions.
While calculating the pile capacity, let us assume that
a) Assumed Grade of Concrete = M35
b) Diameter of pile used = 1200mm.
Pile capacity is determined as per the following two Approaches:
38
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
Maximum permissible stress in compression = 9 N/sqmm = 900 T/sqm for M35 grade
concrete as per [Table-21, IS 456:2000, Page 81]
Pile area = 1.131 sqm
Maximum load permissible on pile = 1018 Ton
Approach – 2
As per Clause B-8 of IS 2911 (Part 1/ Sec 2) : 2010
As per IS 2911(Part 1/Sec 2): 2010, (Annex-B, cl.B-8) the allowable load on the pile,
Qa = cu1Nc (B2/4Fs) + cu2 (BL/Fs)
Where,
Cu1 = Shear strength of rock below the base of the pile, in kN/m 2
Nc = Bearing capacity factor taken as 9
Fs = Factor of safety usually taken as 3
= 0.9 (recommended value)
Cu2 = Average shear strength of rock in the socketed length of pile, in kN/m 2
B = Minimum width of pile shaft (diameter in case of circular piles), in m
L = socket length of pile, in m
Considering socket length, L = 9.70m [Neglecting 0.30m as seating drive]
D = diameter of pile in m = 1.20m
Use design Cu1 = 400 kN/m2 = 40t/m2 and design Cu2 = 400 kN/m2 = 40t/m2
39
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
5.4. RECOMMENDATION:
With reference to the above and considering subsoil condition, the recommended pile
capacity values is presented below.
Pile Diameter = 1200mm
Approximate Recommended
Borehole Lateral Pile
Length of Pile* Vertical Pile
Location Capacity
(m) Capacity (T)
H = 40T & 40 T for
BH-P2 (03) 11.50 400 Overhang length of 0m &
2m Respectively.
Corresponding M = 2.18 &
3.21t-m/t of thrust and Lf =
BH-P1 (02) 14.50 400
6.23m and 5.68m
respectively.
Note :
a. Pile load test should be conducted to ascertain the pile capacity as per IS: 2911,Part IV.
b. *Bottom of Pile Cap is considered 2m depth below Existing ground level.
40
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
Based on the field and laboratory test results and the foregoing discussion, the following are
summarised.
1. The subsoils in general are of good quality. It is characterized by a stiff to very stiff silty
clay layer at top around BH-A2 location only. A boulder layer is encountered thereafter.
Underlying the above a weathered rock layer of is encountered and that layer continued
up to the terminating depth of all the boreholes except BH-04(A2) location where boulder
layer continues upto terminating depth.
a) We have boulder deposit from 9.10m below EGL which continues upto the borehole
terminating depth. Piling through the boulder layer is very difficult & thus avoided.
b) In A1 location weathered rock layer is encountered right from the beginning of the
borehole.
2.00 23
Note:
1) Limiting settlement inside rock is considered as 12mm irrespective of foundation type.
2) The above bearing capacity inside rock is based on limiting the settlement; it should not be
increased if the foundation is embedded further into the rock unless the rock quality improves.
3) In case any loose pocket is observed at the founding level, then the same should be excavated out
and the same shall be filled up with PCC upto the founding level..
4) Foundation will be scour protected.
41
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
Approximate Recommended
Borehole Lateral Pile
Length of Pile* Vertical Pile
Location Capacity
(m) Capacity (T)
H = 40T & 40 T for
BH-P2 (03) 11.50 400 Overhang length of 0m &
2m Respectively.
Corresponding M = 2.18 &
3.21t-m/t of thrust and Lf =
BH-P1 (02) 14.50 400
6.23m and 5.68m
respectively.
Note :
i. Pile load test should be conducted to ascertain the pile capacity as per IS: 2911,Part IV.
ii. *Bottom of Pile Cap is considered 2m depth below Existing ground level.
42
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
BH: A1 (01)
R01 (00.00-01.00)m : Moderately weathered, steel grey, fine grains are moderately compacted
and bedded, medium hard and weak Siltstone.
R03 (02.00-03.00)m : Moderately weathered, steel grey, fine grains are moderately compacted
and bedded, medium hard and weak Siltstone.
R06 (05.00-06.00)m : Slightly weathered, dark grey, very fine grains are moderately compacted
and thinly bedded, soft and weak Shale.
R09 (08.00-09.00)m : Slightly weathered, steel grey, fine grains are moderately compacted and
bedded, medium hard and weak Siltstone.
R11 (10.00-11.00)m : Slightly weathered, steel grey, fine grains are moderately compacted and
bedded, medium hard and weak Siltstone.
R13 (12.00-13.00)m : Slightly weathered, steel grey, fine grains are moderately compacted and
bedded, medium hard and weak Siltstone.
BH: A2 (04)
R02(10.00-11.00)m : Steel grey, fine grains are densely compacted, hard and strong Siltstone
boulder.
R03 (11.00-12.00)m : Steel grey, fine grains are densely compacted, hard and strong Siltstone
boulder.
R05 (13.00-14.00)m : Steel grey, fine grains are densely compacted, hard and strong Siltstone
boulder.
BH: P1 (02)
R03(02.00-03.00)m : Steel grey, fine grains are densely compacted, hard and strong Siltstone
boulder.
R04(03.00-04.00)m : Steel grey, fine grains are densely compacted, hard and strong Siltstone
boulder.
R06(05.00-06.00)m : Steel grey, fine grains are densely compacted, hard and strong Siltstone
boulder.
R10(09.00-10.00)m : Steel grey, fine grains are densely compacted, hard and strong Siltstone
boulder.
R11(10.00-11.00)m : Moderately weathered, dark grey, very fine grains are moderately
compacted and thinly bedded, soft and weak Shale.
R14(13.00-14.00)m : Moderately weathered, dark grey, very fine grains are moderately
compacted and thinly bedded, soft and weak Shale.
BH: P2 (03)
R03(04.00-05.00)m : Highly weathered, steel grey with brown patches, fine grains are
moderately compacted and bedded, medium hard and weak Siltstone.
R04 (05.00-06.00)m : Highly weathered, steel grey with brown patches, fine grains are
43
Project: Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
R06 (07.00-08.00)m : Highly weathered, steel grey with brown patches, fine grains are
moderately compacted and bedded, medium hard and weak Siltstone.
R08 (09.00-10.00)m : Highly weathered, steel grey, fine grains are moderately compacted and
bedded, medium hard and weak Siltstone.
R12 (13.00-14.00)m : Highly weathered, steel grey, fine grains are moderately compacted and
bedded, medium hard and weak Siltstone.
R16 (17.00-18.00)m : Highly weathered, steel grey, fine grains are moderately compacted and
bedded, medium hard and weak Siltstone.
44
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur. Commencement Date : 10/1/2018 Level of Ground : 219.492 M Job No : 4047
Bore Hole No. : 3 (P2) Location : E=550361.231 / N=2748453.528 Completion Date : 15/01/2018 Standing Water Level : 3.90 M Sheet No :
Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference
Void Ratio
To
Content (%)
at Laboratory
reference level
Percent RQD
From
Value
Specific Gravity
%Gravel>72mm
Natural Moisture
% Clay<0.002mm
Elevation in Metre
%Sand 2.0-0.06mm
Shrinkage Limit (%)
% Silt 0.06-0.002mm
Symbolic representation
Unconfined Compressive
Depth in Metre
Percent Core Recovery
Strength of Rock (Kg/cm2)
Angle of Shearing
Resistance in Deg.
217.4920 2.00 2.02 2.00 *SPT-03 2.00 R Various coloured, different size of boulders,
with intermediate voids filled up by sand.
219.4920 2.00 3.00 R1 25 0
45
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur. Commencement Date : 18/01/2018 Level of Ground : 237.013 M Job No : 4047
Bore Hole No. : 1 (A1) Location : E=550426.572 / N=2748403.922 Completion Date : 24/01/2018 Standing Water Level : 18.07 M Sheet No :
Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference
Void Ratio
To
Content (%)
at Laboratory
reference level
Percent RQD
From
Value
Specific Gravity
%Gravel>72mm
Natural Moisture
% Clay<0.002mm
Elevation in Metre
%Sand 2.0-0.06mm
Shrinkage Limit (%)
% Silt 0.06-0.002mm
Symbolic representation
Unconfined Compressive
Depth in Metre
Percent Core Recovery
Strength of Rock (Kg/cm2)
Angle of Shearing
Resistance in Deg.
236.0130 0.00 1.00 1.00 R1 22 0 Completely to highly weathered, grey to deep 2.385 2.722 1.07 P=0.85
grey, fine grained, fractured rock.
235.0130 1.00 2.00 2.00 R2 25 0
2.00M
234.0130 2.00 3.00 3.00 R3 40 0 2.721 2.948 0.66 P=1.02
228.0130 8.00 9.00 9.00 R9 69 0 Moderately to slightly weathered, grey to 2.491 2.665 0.66 P=1.1
deep grey, fine grained, fractured rock.
227.0130 9.00 10.00 10.00 R10 73 0
Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
* means sample could not be recovered @ 1)Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as Mg/Litr &
# means(Silt + clay) % for soil samples SO 4 content is expressed as SO 3.
46
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur. Commencement Date : 6/2/2018 Level of Ground : 219.713 M Job No : 4047
Bore Hole No. : 2 (P1) Location : E=550384.558 / N=2748416.460 Completion Date : 12/2/2018 Standing Water Level : 5.15 M Sheet No :
Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference
Void Ratio
To
Content (%)
at Laboratory
reference level
Percent RQD
From
Value
Specific Gravity
%Gravel>72mm
Natural Moisture
% Clay<0.002mm
Elevation in Metre
%Sand 2.0-0.06mm
Shrinkage Limit (%)
% Silt 0.06-0.002mm
Symbolic representation
Unconfined Compressive
Depth in Metre
Percent Core Recovery
Strength of Rock (Kg/cm2)
Angle of Shearing
Resistance in Deg.
219.5130 0.20 0.20 DS-01 Brownish grey, silty clay with sand mixture.
Observed boulders.
219.4130 0.30 0.32 0.30 *SPT-01 0.30 R
0.30M
219.7130 0.30 1.00 R1 23 0
47
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur. Commencement Date : 23/12/2017 Level of Ground : 235.102 M Job No : 4047
Bore Hole No. : 04 (A2) Location : E=550319.246 / N=2748466.027 Completion Date : 7/1/2018 Standing Water Level : Not found M Sheet No :
Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference
Void Ratio
To
Content (%)
at Laboratory
reference level
Percent RQD
From
Value
Specific Gravity
%Gravel>72mm
Natural Moisture
% Clay<0.002mm
Elevation in Metre
%Sand 2.0-0.06mm
Shrinkage Limit (%)
% Silt 0.06-0.002mm
Symbolic representation
Unconfined Compressive
Depth in Metre
Percent Core Recovery
Strength of Rock (Kg/cm2)
Angle of Shearing
Resistance in Deg.
223.1020 12.00 12.02 12.00 *SPT-10 12.00 R Various coloured, different size of boulders
with intermediate voids filled up with sand.
235.1020 12.00 13.00 R4 19 0
48
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur. Commencement Date : 23/12/2017 Level of Ground : 235.102 M Job No : 4047
Bore Hole No. : 04 (A2) Location : E=550319.246 / N=2748466.027 Completion Date : 7/1/2018 Standing Water Level : Not found M Sheet No :
Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference
Void Ratio
To
Content (%)
at Laboratory
reference level
Percent RQD
From
Value
Specific Gravity
%Gravel>72mm
Natural Moisture
% Clay<0.002mm
Elevation in Metre
%Sand 2.0-0.06mm
Shrinkage Limit (%)
% Silt 0.06-0.002mm
Symbolic representation
Unconfined Compressive
Depth in Metre
Percent Core Recovery
Strength of Rock (Kg/cm2)
Angle of Shearing
Resistance in Deg.
Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
* means sample could not be recovered @ 1)Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as Mg/Litr &
# means(Silt + clay) % for soil samples SO 4 content is expressed as SO 3.
49
Project : Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur.
Job No. 4047 Sheet No.
e-logp Curve
0.930
0.910
0.890
0.870
0.850
0.830
VOID RATIO
0.810
0.790
0.770
0.750
0.730
0.710
0.690
0.670
0.10 1.00 10.00
50
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.002
0.075
0.425
4.75
2
0.001 0.01 0.1 1 10 100
100
80
Percentage finer
60
40
20
0
0.002
0.075
0.425
4.75
2
Grain Size(mm)
Project:- Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur. Job No.
4047
51
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.002
0.075
0.425
4.75
2
0.001 0.01 0.1 1 10 100
100
80
Percentage finer
60
40
20
0
0.002
0.075
0.425
4.75
2
Grain Size(mm)
Project:- Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur. Job No.
4047
52
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.002
0.075
0.425
4.75
2
0.001 0.01 0.1 1 10 100
100
80
Percentage finer
60
40
20
0
0.002
0.075
0.425
4.75
2
Grain Size(mm)
#N/A #N/A
Project:- Geotech Inv. work for Irang Bridge at Taoban Bazar in Manipur. Job No.
4047
53
SUPER STRUCTURE DESIGN OF
IRANG BRIDGE
CH._95.500 KM
54
2. LOAD CALCULATION
Girder
c. General considerations
Hence the deck slab is designed with the following conditions
i) The slab is continuous over the long girders
ii) The action of the slab is one way
iii) The slab is to be designed for bending moment for critical position of loads
with one way bending and punching shear.
iv) For simplicity, slab is considered as 3 span continuously supported on main beam & free at ends
The load calculation for deck slab is being done for unit width.
Dead Load:
Self wt of slab = 0.225*25 = 5.63 KN/m per unit width
Surfacing:
Self wt of WC = 0.065 x 25 = 1.63 KN/m per unit width
55
SIDL ( Superimposed Dead Load)
Thickness Width L Density Total
3
(M) (M) (M) (KN/m ) (KN)
Kerb (Left) 0.225 0.5 1.00 25.00 2.81
Crash Barrier (Left) 0.392 1.00 25.00 9.80
Crash Barrier (Right) 0.392 1.00 25.00 9.80
Footpath Live load (Left) - - 1.00 - 6.00
Total = 19.60
Loading System for Deck Slab
1250 9.80
6.00 9.80
1750
500
9500
Surfacing = 1.63 KN/m
Self Wt = 5.63 KN/m
12500
Spacing of Girder= 3m
Width of web= 0.3 m
As the deck slab is continuous over support, effective span= clear span=l0= 2.7 m
Thickness of wearing course= 0.065 m
b/l0= 9.4/2.7= 3.481
α= 2.600
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1
Load Details:
Class-A Train vehicle:
Class 70R:
Tracked
Maximum Axle Load= 70 T= 700 KN
Maximum Wheel Load = 350 KN
Length along the traffic direction = 4.57 m
Tyre dimension along the traffic direction =lw= = 4.57 m
Tyre dimension across the traffic direction =bw= = 0.84 m
C/C spacing of wheels across the traffic direction = 2.06 m
Edge clearence = 1.2 m
Impact Factor= = 1.25 Ref-Cl-208, IRC-6:2010
le= Dispersion width along the span of deck= bw+2*(ts+twc)= = 1.42 m
b1=lw+2*twc = 4.7 m
56
Special Vehicle
Maximum Axle Load= 9 T= 90 KN
Maximum Wheel Load = 22.5 KN
Spacing between axles along the traffic direction = 1.5 m
Tyre dimension along the traffic direction =lw= = 0.274
Tyre dimension across the traffic direction =bw= = 0.156
le= Dispersion width along the span of deck= bw+2*(ts+twc)= = 0.736
b1=lw+2*twc = 0.404
Impact Factor = 1
156 300
1 2 3 4 5 6 7 8
225 825 525
525 225 225 225
3000
C/C spacing of wheels across the traffic direction between 1 & 2 = 0.225 m
C/C spacing of wheels across the traffic direction between 2 & 3 = 0.525 m
C/C spacing of wheels across the traffic direction between 3 & 4 = 0.225 m
C/C spacing of wheels across the traffic direction between 4 & 5 = 0.825 m
C/C spacing of wheels across the traffic direction between 5 & 6 = 0.225 m
C/C spacing of wheels across the traffic direction between 6 & 7 = 0.525 m
C/C spacing of wheels across the traffic direction between 7 & 8 = 0.225 m
Class 40R :
Boggie
410 380
1 2 3 4
Traffic
Direction
205 795 790 795
2790
Wheel Plan
57
CASE-I: Place Class A load 3 Lane load minimum clearance from inner kerb at 1st
Centre of the first wheel of 1st lane load from left edge for first span= 2900 mm
Centre of the first wheel of 2nd lane load from left edge = 6400 mm
Centre of the first wheel of 3nd lane load from left edge = 9900 mm
9900
6400
2900 1800 1700 1800 1700 1800 800
57KN 57KN 57KN 57KN 57K 57K
1 2 3 4 3 4
Ra Rb Rc Rd
For load 1
Distance from the support = a = 0.9 m
be = Dispersion width across the span of deck = α*a*[1-(a/l0)]+b1 = 1.94 m
Therefore, load on 1m span = 44.66 KN
For load 2
Distance from the support = b = 0.3 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.073 m
Therefore, load on 1m span = 80.75 KN
For load 3
Distance from the support = c = 1.4 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.133 m
Therefore, load on 3rd span = 40.62 KN
For load 4
Distance from the support= d = 0.2 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 0.861 m
Therefore, load on 3rd span = 100.63 KN
For load 5
Distance from the support = a = 1.10 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.075 m
Therefore, load on Span-4 = 41.75 KN
For load 6
Distance from the support= a = 0.70 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.728 m
Therefore, load on Span-5 = 50.14 KN
58
CASE-II: Place Class A load at the middle of second span
Centre of the first wheel of 1st lane load from left edge for first span= 3500 mm
Centre of the first wheel of 2nd lane load from left edge = 7000 mm
7000
3500 1800 1700 1800 3700
57KN 57KN 57KN 57KN
1 2 3 4
Ra Rb Rc Rd
For load 1
Distance from the support= a = 1.5 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.113 m
Therefore, load on 1m span = 41.00 KN
For load 2
Distance from the support= b= 0.3 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.073 m
Therefore, load on 1m span = 80.75 KN
For load 3
Distance from the support= c = 1m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.017 m
Therefore, load on 3rd span = 42.95 KN
For load 4
Distance from the support= c = 0.8 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.844 m
Therefore, load on 3rd span = 46.98 KN
Ra Rb Rc Rd
For load 1
Distance from the support= b = 0m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 0.38 m
Therefore, load on 1m span = 228.00 KN
For load 2
Distance from the support= c = 1.2 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.113 m
Therefore, load on 1m span = 41.00 KN
For load 3
Distance from the support= b =
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 0.50 m
Therefore, load on 1m span 1.439 m
60.21 KN
For load 4
Distance from the support= c = 0.70 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.728 m
Therefore, load on 1m span 50.14 KN
59
CASE-IV: Here Load 1 & Load 2 represents two wheels of Class 70R load. Place load 1 centrally at first span.
Centre of the first wheel of 1st lane load from left edge for first span= 4120 mm
Centre of the first wheel of 2nd lane load from left edge = 6180 mm
Ra Rb Rc Rd
For load 1
Distance from the support=b= 0.88 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 6.242 m
Therefore, load on 1m span = 70.09 KN
For load 2
Distance from the support=b= 1.18 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 6.427 m
Therefore, load on 1m span = 68.07 KN
For load 3
Distance from the support= b = 0.05 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 0.508 m
Therefore, load on 1m span 170.55 KN
For load 4
Distance from the support= c = 1.15 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.096 m
Therefore, load on 1m span 41.34 KN
CASE-V: Here Load 1 & Load 2 represents two wheels of Class 70R load. Place load 1 centrally at first span.
Centre of the first wheel of 1st lane load from left edge for first span= 5000 mm
Centre of the first wheel of 2nd lane load from left edge = 7060 mm
Ra Rb Rc Rd
60
For load 1
Distance from the support=b= 0m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 4.7 m
Therefore, load on 1m span = 93.09 KN
For load 2
Distance from the support=b= 0.94 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 6.293 m
Therefore, load on 1m span = 69.52 KN
For load 3
Distance from the support= b = 0.93 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.965 m
Therefore, load on 1m span 44.09 KN
For load 4
Distance from the support= c = 0.27 m
be= Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.012 m
Therefore, load on 1m span 85.61 KN
Here Load 1 to 4 represents four wheels of 40T Bogie load. Place load 20T axle load at minimum distance from inner kerb of
CASE-VI:
1st span.
Centre of the first wheel of 1st lane load from left edge for first span= 3905 mm
Ra Rb Rc Rd
For load 1
Distance from the support=b= 1.095 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.085 m >1.22m. Dispersion will be restricted
be= = 1.6525 m
Therefore, load on 1m span = 37.82 KN
For load 2
Distance from the support=b= 0.3 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.086 m <1.22m. Dispersion will not be
be= = 1.086 m restricted
Therefore, load on 1m span = 57.55 KN
For load 3
Distance from the support=b= 0.49 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.436 m >1.22m. Dispersion will be restricted
be= = 1.328 m
Therefore, load on 1m span = 47.06 KN
For load 4
Distance from the support=c= 1.285 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.144 m >1.22m. Dispersion will be restricted
be= = 1.682 m
Therefore, load on 1m span = 37.16 KN
61
CASE-VII: Here Load 1 to 4 represents four wheels of 40T load. Place load 40T load centrally at support.
Centre of the first wheel of 1st lane load from left edge for first span= 5000 mm
Ra Rb Rc Rd
For load 1
Distance from the support=b= 0m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 0.393 m <1.22m. Dispersion will not be
be= = 0.393 m restricted
Therefore, load on 1m span = 159.03 KN
For load 2
Distance from the support=b= 0.795 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.851 m >1.22m. Dispersion will be restricted
be= = 1.5355 m
Therefore, load on 1m span = 40.70 KN
For load 3
Distance from the support=c= 1.415 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.144 m >1.22m. Dispersion will be restricted
be= = 1.682 m
Therefore, load on 1m span = 37.16 KN
For load 4
Distance from the support=c= 0.79 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.846 m >1.22m. Dispersion will be restricted
be= = 1.533 m
Therefore, load on 1m span = 40.77 KN
CASE-VII: Here Load 1 & Load 2 represents two wheels of Special Vehicle , Placed at the centre of carriage way.
0.156 0.3
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
62
Thickness of Wearing Coat = 65 mm
α= 2.60
l 0= 2.700 m
b1= 0.40 m
le= Dispersion width along the span of deck= 0.74 m
le1= Dispersion width along the span of deck for SV 1st Load= 0.315 m
le2= Dispersion width along the span of deck for SV 2nd Load= 0.315 m
le3= Dispersion width along the span of deck for SV 3rd Load= 0.315 m
le4= Dispersion width along the span of deck for SV 4th Load= 0.315 m
le5= Dispersion width along the span of deck for SV 5th Load= 0.315 m
le6= Dispersion width along the span of deck for SV 6th Load= 0.315 m
le7= Dispersion width along the span of deck for SV 7th Load= 0.315 m
le8= Dispersion width along the span of deck for SV 8th Load= 0.315 m
For load 1
Distance from the support=a= 1.313 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.16 m
be= = 1.22 m
Therefore, load on 3rd span 18.51 KN
For load 2
Distance from the support=a= 1.162 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= = 2.12 m
be= 1.20 m
Therefore, load on 3rd span 18.76 KN
For load 3
Distance from the support=b= 0.6370 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.67 m
be= 0.97 m
Therefore, load on 3rd span 23.15 KN
For load 4
Distance from the support=b= 0.4120 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.31 m
be= 0.79 m
Therefore, load on 3rd span 28.38 KN
For load 5
Distance from the support=a= 0.4130 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.31 m
be= 0.79 m
Therefore, load on 4th span 28.35 KN
For load 6
Distance from the support=a= 0.6380 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 1.67 m
be= 0.97 m
Therefore, load on 4th span 23.14 KN
For load 7
Distance from the support=b= 1.1630 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.13 m
be= 1.20 m
Therefore, load on 4th span 18.76 KN
For load 8
Distance from the support=b= 1.3880 m
Dispersion width across the span of deck= α*a*[1-(a/l0)]+b1= 2.16 m
be= 1.22 m
Therefore, load on 4th span 18.51 KN
63
f. Analysis Output
The analysis of deck slab has been carried by SAP 2000, considering the deck slab as a beam of unit width. The output at various location has
been tabulated below.
LL Maximum
5 0.000 0.000 -25.380 35.660 6.740 7.220 61.520
Moment
g. Combination of Moments
64
f. Check for effective depth
Section-1: At Mid span
Consider the section as balanced section.
Depth of NA=Xubal= 0.46 * d Ref.: Note, Cl-38,IS-456:2000
Mu= 0.36*fck*b*Xubal*(d-0.42*xubal)= 71.1 KN-m Ref.: Annexure-G,IS-456:2000
dbal= 115 mm
Clear cover= 40 mm
Provided dia of reinforcement= 12 mm
Required overall depth=Dreqd= 161 mm
Provided overall depth=Dprovided= 225 mm Hence OK
dbal= 100 mm
Clear cover= 40 mm
Provided dia of reinforcement= 12 mm
Required overall depth=Dreqd= 146 mm
Provided overall depth=Dprovided= 225 mm Hence OK
dbal= 83 mm
Clear cover= 40 mm
Provided dia of reinforcement= 16 mm
Required overall depth=Dreqd= 131 mm
Provided overall depth=Dprovided= 225 mm Hence OK
g. Calculation of Reinforcement
Section-1: At Mid span
Calculation of main steel
Ref.: Cl-16.6.1.1.(4),
Maximum spacing allowed= 300 mm
IRC-112:2011
Provide 12 mm Tor bar @ 100 mm c/c spacing.
Astprovided= 1130 mm
2
Hence OK
Calculation of distribution steel
Distribution steel will be maximum of the followings.
Ref.: Cl-16.6.1.1.(3),
i) 20% of Astprovided= 226 mm2
IRC-112:2011
ii) 0.0013bt*deff=
2
233 mm Ref.: Cl-16.5.1.1, IRC-
iii) 0.26*fctm/fyk*bt*d= 279 mm
2 112:2011
Astreqd= 279 mm
2
Ref.: Cl-16.6.1.1.(4),
Maximum spacing allowed= 400 mm
IRC-112:2011
Provide 10 mm Tor bar @ 100 mm c/c spacing.
Astprovided= 785 mm
2
Hence OK
65
Section-2: At Mid support
Calculation of main steel
Ref.: Cl-16.6.1.1.(4),
Maximum spacing allowed= 300 mm
IRC-112:2011
Provide 12 mm Tor bar @ 100 mm c/c spacing.
2
Astprovided= 1130 mm Hence OK
Calculation of distribution steel
Distribution steel will be maximum of the followings.
Ref.: Cl-16.6.1.1.(3),
i) 20% of Astprovided= 226 mm2
IRC-112:2011
ii) 0.0013bt*deff= 233 mm2 Ref.: Cl-16.5.1.1, IRC-
iii) 0.26*fctm/fyk*bt*d= 279 mm2 112:2011
Astreqd= 233 mm
2
Ref.: Cl-16.6.1.1.(4),
Maximum spacing allowed= 400 mm
IRC-112:2011
Provide 10 mm Tor bar @ 100 mm c/c spacing.
2
Astprovided= 785 mm Hence OK
Ref.: Cl-16.6.1.1.(4),
Maximum spacing allowed= 250 mm
IRC-112:2011
Provide 16 mm Tor bar @ 100 mm c/c spacing.
Astprovided= 2010 mm
2
Hence OK
Calculation of distribution steel
Distribution steel will be maximum of the followings.
Ref.: Cl-16.6.1.1.(3),
i) 20% of Astprovided= 402 mm2
IRC-112:2011
ii) 0.0013bt*deff= 230 mm2 Ref.: Cl-16.5.1.1, IRC-
iii) 0.26*fctm/fyk*bt*d= 276 mm2 112:2011
2
Astreqd= 402 mm
Ref.: Cl-16.6.1.1.(4),
Maximum spacing allowed= 400 mm
IRC-112:2011
Provide 10 mm Tor bar @ 100 mm c/c spacing.
Astprovided= 785 mm
2
Hence OK
66
i. Calculation of Crack Width Ref.: Cl-12.3.3,IRC-112:2011
Section-1: At Mid span
3
Section modulus=Zt= Icr/Yt= 4.66E+06 mm
σsc = stress in the tension reinforcement = 266 Mpa
Maximum permissible stress in tensile steel=0.8*fyk= 400 Mpa Ref.:-Cl- 12.2.2, IRC:112-2011
Hence OK
fc = stress in the concrete = 10.3 Mpa
Maximum allowable stress in concrete = 0.48fck = 19.2 Mpa Ref.:-Cl- 12.2.1(1), IRC:112-2011
Hence OK
Calculation of crack width
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+f/2)), the maximum crack spacing,
67
Section-3: At Cantilever part
m (lomgterm)= 12.5
2
Equating the moments of areas about the centroidal axis, b*Yt =m*Astprov*(d-Yt)
2 0.5
Solving thae equation, Yt= [-(m*Astprov)±{(-m*Astprov) -4*(-m*Astprov)*deff*0.5*b} ]/(2*0.5*b)
= 72 mm
-123 (Negetive value is neglected)
Distance of CG from reinforcing steel, Ys= 105 mm
2 3
Inertia of the section, Icr=m*Atprov*Ys +b*Yt = 4.01E+08 mm
4
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+f/2)), the maximum crack spacing,
68
j. Shear Check Ref.: Cl-10.3.2,IRC-112:2011
The design shear resistance of the member without shear reinforcement, VRd.c =
0.33
=[0.12K(80ρ1.fck) +0.15σcp]bw.d Ref:-. Eq-10.1, IRC:112-2011
Where, K = 1+√(200/d)<=2.0
So, K = 2.000
ρ1 = Asl/bw.d
2
Where Asl = Area of steel provided = 2010 mm
bw = Width of section = 1000 mm
d= 177 mm
ρ1 = 0.0114
σcp = NEd/Ac < 0.2fcd, where, NEd = Axial compressive force = 0
Ac = Cross Sectional area of concrete
σcp = 0
So,VRd.c = 139.02 KN
k. Summary of Reinforcement
l. Deflection check:
69
DESIGN OF PSC T-GIRDER WITH 38.8M SPAN (C/C OF BEARING ) [INNER GIRDER]
A. GEOMETRIC PROPERTIES OF THE GIRDER
180 100
2325
300 2775
450
850
2000 3000 3000 3000 1500
C/S AT MIDDLE
500 12500
500 225 500
1500 9500
1250
42
850
2325 2775
450
850
9700
2000
1250
3000
400
300
850
300
70
B. PROPERTIES OF GIRDER SECTION
Precast Section :
1250
For end portion of girder having length 1.6 m 180
I precast = [{1.25x0.005832/12+0.225x1.68350625}+{(0.475x0.003375)/18}+{0.07125x1.34+(0.3x12.9)/12}+
{(0.275x0.008/18)+0.055x1.15}+{(0.85x0.015625/12)+0.2125x1.59}]
4
1.2 m
3 3
Ztp = 0.902 m Zbp = 0.831 m
Edge Girder
Effective flange width = 1.5+1.75 = 3.25 m
2
Area of girder = [(3.25x0.233] +1.267= 2.024 m
4
Icomposite = [(3.25x0.013/12)+(3.25x0.054)]+[1.2+1.267x(0.542^2)] = 2.278 m
3 3 3
Zts = 2.229 m Ztg = Zbs = 2.887 m Zbg = 1.147 m
71
inner Girder
Effective flange width = 1.5+1.5 = 3m
2
Area of girder = [(3x0.233] +1.267= 1.966 m
4
Icomposite = [(3x0.013/12)+(3x0.054)]+[1.2+1.267x(0.515^2)] = 2.209 m
3 3 3
Zts = 2.106 m Ztg = Zbs = 2.707 m Zbg = 1.128 m
C. DEAD LOAD
a. Precast portion
Area of each diaphragm (per girder) = 0.5 x(1.25+0.85) x2.345- 0.5 x ( 1.25+0.3) x0.15- 0.5 x (0.3+0.85) x 0.2- (0.3x1.995)
= 2.83 m2
Loading = 2.83x25x0.3 = 21.225 kN (on each girder)
b. In Situ portion
Area of each diaphragm = 0.5 x(1.75+2.15) x 2.325 = 4.534 m2
a. Precast portion
Area of each diaphragm (per girder) = (1.25x2.775) -2.443-{(1.25-0.85) x0.35} = 0.88575 m2
b. In Situ portion
Area of each diaphragm = (3-1.25)x(2.775-0.35) = = 4.24375 m2
72
3. Self weight of deck slab
Superimposed dead load will be placed on deck slab after composite action starts.
73
SHEAR AT DIFFERENT SECTIONS OF T GIRDER DUE TO DEAD LOAD:
74
ii) For inner Girder
75
3. DUE TO SUPERIMPOSED DEAD LOAD :
3.39625
76
E. LOAD TABLES
2. TABLE SHOWING MAX. SHEAR FORCE AT DIFERENT SECTION AND CORRESPONDING BM:
77
3. TABLE SHOWING MAX. BENDING MOMENTS AND STRESSES AT DIFERENT SECTION
stress at top of
- - - 28.58 30.25 198.02 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 22.07 23.54 152.89 0
MID (T/m2)
stress at top of
precast girder 705.71 387.53 387.53 70.63 70.63 152.89 0
(T/m2)
stress at bottom
of precast girder -766.00 -420.64 -420.64 -76.67 -76.67 -384.81 0.00
(T/m2)
MOMENT(T-M) 594.15 325.58 325.58 59.72 59.72 387.93 0.00
stress at top of
- - - 26.79 28.36 174.04 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 20.69 22.06 134.37 0
3/8 TH (T/m2)
stress at top of
precast girder 658.70 360.96 360.96 66.21 66.21 134.37 0
(T/m2)
stress at bottom
of precast girder -714.98 -391.80 -391.80 -71.86 -71.86 -338.21 0.00
(T/m2)
MOMENT(T-M) 477.24 261.92 261.92 47.73 47.73 340.62 0.00
stress at top of
- - - 21.42 22.67 152.81 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 16.53 17.63 117.98 0
1/4 TH (T/m2)
stress at top of
precast girder 529.09 290.38 290.38 52.92 52.92 117.98 0
(T/m2)
stress at bottom
of precast girder -574.30 -315.19 -315.19 -57.44 -57.44 -296.97 0.00
(T/m2)
MOMENT(T-M) 275.53 150.31 150.31 27.76 27.76 179.85 0.00
stress at top of
- - - 12.46 13.18 80.69 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 9.62 10.26 62.30 0
1/8 TH (T/m2)
stress at top of
precast girder 305.47 166.65 166.65 30.78 30.78 62.30 0
(T/m2)
stress at bottom
of precast girder -331.57 -180.88 -180.88 -33.41 -33.41 -156.80 0.00
(T/m2)
78
MOMENT(T-M) 129.22 70.03 70.03 13.01 13.01 152.43 0.00
stress at top of
- - - 5.84 6.18 68.38 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 4.51 4.80 52.80 0
(T/m2)
WEB. TH
stress at top of
precast girder 143.26 77.64 77.64 14.42 14.42 52.80 0
(T/m2)
stress at bottom
of precast girder -155.50 -84.28 -84.28 -15.65 -15.65 -132.89 0.00
(T/m2)
79
F. PRESTRESSING
Prestressing cables shall be 19 strand cables conforming to IS 14268-1995 class II with minimum breaking load = 18.371 Ton
for 12.7 mm dia ,7 ply strand.
80
675 200
7
350
7 6
180 350
6 5
180 350
425
5 4
180 350 2775
4 200 3
180 350
250
130 2 3 1 1 2
245 180 180
350
850 245 360 245
R(Min)= 12 m
H C/L
θv
Vc
A B C D E
Vertical Curve
C1 C2 C3 C4
Horizontal curve
θh R(Min)= 10.6 m
HS
θh
Horizontal curve
81
-1
Horrizontal splay to be given in cables 1 in 10, i.e. θH= tan 1/10= 5.71 °
LHc= 10.6X0.0997= 1.056 m
C3= 10xH s+2xLHcX0.5
Eqn-1-Eqn-2
=>C2= [{19.72 -(C3+C4)}-H/tanθv]x2 Eqn-3
Substitute the value of C2 in Eqn-1,
=>C1= 19.72 -(C3+C4+C2) Eqn-4
4. Force diagram of each cable after anchorage slip will be as shown follow:
According to IRC-112,2011,
The steel stress at jacking end= σpo=σpx.e(kx+µθ)
σpo= Applied force
σpo(x)= Force at any place in cable
µ= Friction co-efficient = 0.25 for bright metal stress
k= Wooble co-efficient = 0.0046 relieved strand
Say slip loss= 6 mm
Modulus of elasticity of material of cable= 1.95E+06 Kg/sqcm
82
For cable 1&2:
Web Thickening 1/8th section 1/4th section 3/8th section Mid-Section
3520
1410 4930 4930 4930
244.3 t
242.32 t
235.13 t 232.464 t
219.254 t
2550 211.964
209.49 t
201.62 t
203.27 t
Cable Horizontal
length distance
1771 2764
For cable 3:
Web Thickening 1/8th section 1/4th section 3/8th section Mid-Section
3520
1410 4930 4930 4930
244.3 t
242.11 t
229.10 t
216.403 t
214.100
t
200.73 t 214.10 t
202.57 t
Cable Horizontal
length distance
1975 5399
83
Area of the diagram
=0.5x(43.566+39.542)x1.975+0.5x(39.542+15)x5.399+0.5x(15+-214.1)x0= 229.304 t-m
For cable 4:
Web Thickening 1/8th section 1/4th section 3/8th section Mid-Section
3520
1410 4930 4930 4930
244.3 t
240.03 228.16 t
228.16 t
219.16 t 216.403 t
204.63 t
208.29 t Check
Cable Horizontal
length distance
3863 4413
84
For cable 5:
Web Thickening 1/8th section 1/4th section 3/8th section Mid-Section
3520
1410 4930 4930 4930
244.3 t
241.76 t
225.14 t `
220.94 214.523 t
203.52 t 205.68 t
Cable Horizontal
length distance
2299 7021
85
For cable 6:
3520
1410 4930 4930 4930
244.3 t
239.94 t
224.62 t `
223.62 t 214.523 t
205.5 t 209.29 t
Cable Horizontal
length distance
3967 5862
5. Stages of Prestressing
First Stage: 4 cables in each girder at 14 days or the
First stage prestressing will be on precast girder when the girder concrete attains a strength at least equal to 0.9
of its 28 days compressive strength or the concrete is 14 days old whichever is later. Using
grade of girder and deck concrete as M45, strength of girder concrete at the time of stressing will be at least
40.5 Mpa. Cable no. 1,2,3 & 6 will be stressed during the first stage.
Second tag: 2 cables in each girder at 28 days after casting of deck.
Second stage stressing will be done after casting of deck slab and after the deck concrete have attained its 28 days
strength. The deck will be cast after 7 days from the date of first stage prestress, i.e. when the girder concrete
is 21 days old. Hence girder concrete will be 49 days old at the time of second stage
presress and full composite action is obtained. Cable no. 4 & 5 will be stressed at this stage
Kerb, crash barrier, wearing course will be laid, when the girders are 60 days old.
86
6. PROPERTIES OF GIRDER SECTION:
PREACAST GIRDER COMPOSITE GIRDER
Section Section Section
CG from Section Section
CG from modulus modulus of modulus of
Location Area (Ap) Area (Ac) in bottom of modulus of modulus of
bottom of of top of bottom of bottom of
in m
2
m
2 girder Ybg top of girder top of slab
girder Ybp (m) girder Ztp girder Zbp 3 girder Zbgc 3
3 3 (m) Z tgc (m ) 3
Zts (m )
(m ) (m ) (m )
End Girder 1.267 1.444 0.902 0.831 2.024 1.986 2.887 1.147 2.229
Central Girder 1.267 1.444 0.902 0.831 1.966 1.959 2.707 1.128 2.106
87
8. INITIAL PRESTRESS AT DIFFERENT SECTIONS
i). END GIRDER:
a).MID SECTION: 19.72 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(869.434/1 (869.434/
0.13 0 0 219.25 0 219.254 1.314 288.100
1 .267)- 1.267)+(10
-
(1026.594/ 26.594/0.
0.13 0 0 219.25 0 219.254 1.314 288.100
2 0.902)= 831)=
1st Stage at
0.13 0 0 216.40 0 216.403 1.314 284.353
14 Days 3
88
b).3/8TH SECTION: 14.79 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(867.319/1 (867.319/
0.13 0 0 216.41 0 216.412 1.314 284.365
1 .267)- 1.267)+(10
-
(1021.392/ 21.392/0.
0.13 0 0 216.41 0 216.412 1.314 284.365
2 0.902)= 831)=
1st Stage at
0.13 0 0 215.49 0 215.487 1.314 283.150
14 Days 3
89
c).1/4TH SECTION: 9.86 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(865.204/1 (865.204/
0.13 0 0 213.57 0 213.569 1.314 280.630
1 .267)- 1.267)+(10
-
(1016.191/ 16.191/0.
0.13 0 0 213.57 0 213.569 1.314 280.630
2 0.902)= 831)=
1st Stage at
0.13 0 0 214.57 0 214.571 1.314 281.946
14 Days 3
90
d).1/8TH SECTION: 4.93 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(837.373/1 (837.373/
0.130 0.000 0 209.88 0 209.885 1.314 275.788
1 .267)- 1.267)+(96
-
(969.948/0 9.948/0.8
0.130 0.000 0 209.88 0 209.885 1.314 275.788
2 .902)= 31)=
1st Stage at
0.130 0.122 0 208.95 25.465 207.394 1.314 272.515
14 Days 3
91
e).WEB-THICKENING SECTION: 3.52 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(825.17/1. (825.17/1.
0.130 0.070 0 207.22 14.455178 206.719 1.314 271.628
1 267)- 267)+(837.
-
(837.134/0 134/0.831
0.130 0.070 0 207.22 14.455178 206.719 1.314 271.628
2 .902)= )=
1st Stage at
0.226 0.122 0 205.92 25.095 204.385 1.218 248.987
14 Days 3
92
G. ELONGATION CALCULATION
The elongation length calculated only for the cable between the midspan and end faces.
Additional length for attaching the jack may be added in consultation with the system manufacturer.
Extra elongation may be added @ 7mm/m for portion between end face and gripping point of jack.
93
H. LOSSES IN PRESTRESS
1. END GIRDER:
i). Stage-1: Between 14 days to 21 days
Elastic shortening:
Average stresses in 1st stage cables at differen sections, just after seating of anchorage will be as follows :
2
i) At mid-section= (1000x(869.434x0.977))/(4x18.772)= 11310.97 Kg/cm
2
ii) At 3/8 th section= (1000x(867.319x0.977))/(4x18.772)= 11282.80 Kg/cm
2
iii) At 1/4 th section= (1000x(865.204x0.977))/(4x18.772)= 11254.63 Kg/cm
2
iv) At 1/8 th section= (1000x(837.373x0.976))/(4x18.772)= 10883.99 Kg/cm
2
v) At web thickening section= (1000x(825.17x0.976))/(4x18.772)= 10721.47 Kg/cm
Average stress at CG of 1st stage cables at 14 days just after seating of anchorages is: [Ref: stress Tables]
=(2x(1217.387+1293.258+1173.347+1065.193)+1030.25)/9
2
1169.847 T/m = 11.698 Mpa
94
Assumed loss in different sections due to creep and shrinkage as follows:
i) At mid-section= 5.85 %
ii) At 3/8 th section= 5.86 %
iii) At 1/4 th section= 5.88 %
iv) At 1/8 th section= 6.07 %
v) At web thickening section= 6.16 %
Average stress at CG of 1st stage cables at 21 days with 1000 hour relaxation loss will be as follows:
[Ref: stress Tables]
=(2x(1116.383+1176.206+1053.513+945.113)+909.925)/9
2
1054.706 T/m = 10.547 Mpa
Average stress along CG of 1st stage cables during 14 days and 21 days will be
(0.5x(10.547+11.69847)= 11.123 Mpa
Creep strain during this period= 3.28E-04
Loss due to creep and shrinkage=
(0.0000188967241811016+0.000328)x(1950000x4x18.772)/1000= 50.849 T
Percentage loss:
i) At mid-section= (50.849X100)/(869.434)= 5.85 % Hence OK
ii) At 3/8 th section= (50.849X100)/(867.319)= 5.86 % Hence OK
iii) At 1/4 th section= (50.849X100)/(865.204)= 5.88 % Hence OK
iv) At 1/8 th section= (50.849X100)/(837.373)= 6.07 % Hence OK
v) At web thickening section= (50.849X100)/(825.17)= 6.16 % Hence OK
Average stress at CG of 1st stage cables at 14 days just after seating of anchorages is: [Ref: stress Tables]
=(2x(1057.099+1031.019+796.155+625.2)+566.459)/9
2
842.823 T/m = 8.428 Mpa
Assumed loss in different sections due to creep and shrinkage betweeen 21 days to 49 as follows:
i) At mid-section= 2.53 %
ii) At 3/8 th section= 2.54 %
iii) At 1/4 th section= 2.54 %
iv) At 1/8 th section= 2.63 %
v) At web thickening section= 2.67 %
Average stress at CG of 1st stage cables at 21 days with 1000 hour relaxation loss will be as follows:
[Ref: stress Tables]
=(2x(1020.822+989.019+753.381+582.357)+523.549)/9
2
801.634 T/m = 8.016 Mpa
Average stress along CG of 1st stage cables during 14 days and 21 days will be
(0.5x(8.016+8.42823)= 8.222 Mpa
Creep strain during this period= 1.43E-04
Loss due to creep and shrinkage=
(0.0000071338016796995+0.000143)x(1950000x4x18.772)/1000= 22.011 T
Percentage loss:
i) At mid-section= (22.011X100)/(869.434)= 2.53 % Hence OK
ii) At 3/8 th section= (22.011X100)/(867.319)= 2.54 % Hence OK
iii) At 1/4 th section= (22.011X100)/(865.204)= 2.54 % Hence OK
iv) At 1/8 th section= (22.011X100)/(837.373)= 2.63 % Hence OK
v) At web thickening section= (22.011X100)/(825.17)= 2.67 % Hence OK
95
iii). Stage-3: Between 49 days to 60 days
Additional stress at CG of 1st & 2nd stage cables due to 2nd stage prestressing are as follows:
Total depth of precast girder: 2.775 m
a) At mid section:
2
Stress at top=ftg= -23.884 T/m
2
Stress at bottom=fbg= 808.912 T/m
CG of 1st stage cables= 0.265 m
CG of 2nd stage cables= 0.400 m
2
Stress at CG of 1st stage cables= (808.912-(808.912--23.884)x0.265/2.775)= 729.384 T/m
2
Stress at CG of 2nd stage cables= (808.912-(808.912--23.884)x0.4/2.775)= 688.869 T/m
b) At 3/8 th section:
2
Stress at top=ftg= -24.058 T/m
2
Stress at bottom=fbg= 816.639 T/m
CG of 1st stage cables= 0.265 m
CG of 2nd stage cables= 0.400 m
2
Stress at CG of 1st stage cables= (816.639-(816.639--24.058)x0.265/2.775)= 736.356 T/m
2
Stress at CG of 2nd stage cables= (816.639-(816.639--24.058)x0.4/2.775)= 695.457 T/m
c) At 1/4 th section:
2
Stress at top=ftg= -24.233 T/m
2
Stress at bottom=fbg= 824.367 T/m
CG of 1st stage cables= 0.265 m
CG of 2nd stage cables= 0.400 m
2
Stress at CG of 1st stage cables= (824.367-(824.367--24.233)x0.265/2.775)= 743.33 T/m
2
Stress at CG of 2nd stage cables= (824.367-(824.367--24.233)x0.4/2.775)= 702.046 T/m
d) At 1/8 th section:
2
Stress at top=ftg= -3.027 T/m
2
Stress at bottom=fbg= 734.565 T/m
CG of 1st stage cables= 0.285 m
CG of 2nd stage cables= 0.539 m
2
Stress at CG of 1st stage cables= (734.565-(734.565--3.027)x0.285035631701054/2.775)= 658.803 T/m
2
Stress at CG of 2nd stage cables= (734.565-(734.565--3.027)x0.538929026393131/2.775)= 591.318 T/m
96
e) Web thickening section:
2
Stress at top=ftg= 15.144 T/m
2
Stress at bottom=fbg= 678.314 T/m
CG of 1st stage cables= 0.428 m
CG of 2nd stage cables= 0.666 m
2
Stress at CG of 1st stage cables= (678.314-(678.314-15.144)x0.42831826434307/2.775)= 575.954 T/m
2
Stress at CG of 2nd stage cables= (678.314-(678.314-15.144)x0.665549784066415/2.775)= 519.261 T/m
Average stresses in 1st stage cables at differen sections, just after seating of anchorage will be as follows :
2
i) At mid-section= (1000x(430.925x0.992))/(2x18.772)= 11388.65 Kg/cm
2
ii) At 3/8 th section= (1000x(435.119x0.992))/(2x18.772)= 11500.35 Kg/cm
2
iii) At 1/4 th section= (1000x(439.313x0.992))/(2x18.772)= 11612.06 Kg/cm
2
iv) At 1/8 th section= (1000x(418.35x0.992))/(2x18.772)= 11053.71 Kg/cm
2
v) At web thickening section= (1000x(412.3x0.992))/(2x18.772)= 10892.54 Kg/cm
97
Loss due to shrinkage and creep in 2nd stage cable:
Average stress at CG of all cables at 49 days , just after seating of 2nd stage anchorage will be as follows:
[Ref: stress Tables]
=(2x(1549.941+1603.754+1485.706+1314.446)+1251.119)/9
2
1462.09 T/m = 14.621 Mpa
Assumed loss in different sections at 1st stage cables after 2nd stage prestressing due to creep and shrinkage as follows:
i) At mid-section= 0.91 %
ii) At 3/8 th section= 0.91 %
iii) At 1/4 th section= 0.92 %
iv) At 1/8 th section= 0.95 %
v) At web thickening section= 0.96 %
Assumed loss in different sections at 2nd stage cables after 2nd stage prestressing due to creep and shrinkage as follows:
i) At mid-section= 0.92 %
ii) At 3/8 th section= 0.91 %
iii) At 1/4 th section= 0.90 %
iv) At 1/8 th section= 0.95 %
v) At web thickening section= 0.96 %
Average stress at CG of all cables at 60 days before completion of W.C., Railing, Crash Barrier: [Ref: stress Tables]
=(2x(1524.619+1574.758+1454.334+1283.141)+1219.881)/9
2
1432.62 T/m = 14.326 Mpa
Average stress along CG of 1st stage cables during 49 days and 60 days will be
(0.5x(14.6209+14.3262)= 14.474 Mpa
Creep strain during this period= (0.0000521601619669419X1.447355)= 0.000052
Loss due to creep and shrinkage in first stage cables=
(0.000002+0.000052)x(1950000x4x18.772)/1000= 7.930 T
Loss due to creep and shrinkage in second stage cables=
(0.000002+0.000052)x(1950000x4x18.772)/1000= 3.965 T
Percentage loss in different sections will be as follows:
a) For first stage prestress:
i) At mid-section= (7.93X100)/(869.434)= 0.91 % Hence OK
ii) At 3/8 th section= (7.93X100)/(867.319)= 0.91 % Hence OK
iii) At 1/4 th section= (7.93X100)/(865.204)= 0.92 % Hence OK
iv) At 1/8 th section= (7.93X100)/(837.373)= 0.95 % Hence OK
v) At web thickening section= (7.93X100)/(825.17)= 0.96 % Hence OK
a) For second stage prestress:
i) At mid-section= (3.965X100)/(430.925)= 0.92 % Hence OK
ii) At 3/8 th section= (3.965X100)/(435.119)= 0.91 % Hence OK
iii) At 1/4 th section= (3.965X100)/(439.313)= 0.90 % Hence OK
iv) At 1/8 th section= (3.965X100)/(418.35)= 0.95 % Hence OK
v) At web thickening section= (3.965X100)/(412.3)= 0.96 % Hence OK
98
iv). Stage-4: Between 60 days to end
Loss due to shrinkage and creep in 2nd stage cable:
Average stress at CG of all cables at 60 days , after completion of WC, Railing, Crash barrier:
[Ref: stress Tables]
=(2x(1514.465+1549.9+1409.221+1226.702)+1159.668)/9
2
1395.583 T/m = 13.956 Mpa
Assumed loss in different sections at 1st stage cables after 3rd stage casting due to creep and shrinkage as follows:
i) At mid-section= 13.36 %
ii) At 3/8 th section= 13.39 %
iii) At 1/4 th section= 13.42 %
iv) At 1/8 th section= 13.87 %
v) At web thickening section= 14.07 %
Assumed loss in different sections at 2nd stage cables after 3rd stage casting due to creep and shrinkage as follows:
i) At mid-section= 13.48 %
ii) At 3/8 th section= 13.35 %
iii) At 1/4 th section= 13.22 %
iv) At 1/8 th section= 13.88 %
v) At web thickening section= 14.08 %
Average stress at CG of all cables after final loss: [Ref: stress Tables]
=(2x(1252.36+1249.452+1092.195+933.029)+841.924)/9
2
1099.555 T/m = 10.996 Mpa
Average stress along CG of 1st stage cables during 7 days and 21 days will be
(0.5x(13.95583+10.99555)= 12.476 Mpa
Creep strain during this period= 7.80E-04
Loss due to creep and shrinkage in first stage cables=
(0.0000132+0.00078)x(1950000x4x18.772)/1000= 116.142 T
Loss due to creep and shrinkage in second stage cables=
(0.0000132+0.00078)x(1950000x2x18.772)/1000= 58.071 T
Percentage loss in different sections will be as follows:
a) For first stage prestress:
i) At mid-section= (116.142X100)/(869.434)= 13.36 % Hence OK
ii) At 3/8 th section= (116.142X100)/(867.319)= 13.39 % Hence OK
iii) At 1/4 th section= (116.142X100)/(865.204)= 13.42 % Hence OK
iv) At 1/8 th section= (116.142X100)/(837.373)= 13.87 % Hence OK
v) At web thickening section= (116.142X100)/(825.17)= 14.07 % Hence OK
a) For second stage prestress:
i) At mid-section= (58.071X100)/(430.925)= 13.48 % Hence OK
ii) At 3/8 th section= (58.071X100)/(435.119)= 13.35 % Hence OK
iii) At 1/4 th section= (58.071X100)/(439.313)= 13.22 % Hence OK
iv) At 1/8 th section= (58.071X100)/(418.35)= 13.88 % Hence OK
v) At web thickening section= (58.071X100)/(412.3)= 14.08 % Hence OK
99
v). Total percentage loss in each different section will be as follows:
20% Higher
Stages of Prestressing
section
1/4 th
2.325 3.571 5.877 2.544 1.672 0.917 13.424 30.330 5.267
section
1/8 th
2.402 3.571 6.072 2.629 1.728 0.947 13.870 31.219 5.418
section
Web thk
2.438 3.571 6.162 2.667 1.753 0.961 14.075 31.628 5.487
section
mid
0.777 3.999 0.920 13.476 19.173 3.679
section
3/8 th
0.770 3.999 0.911 13.346 19.026 3.651
2nd stage cables
section
1/4 th
0.763 3.999 0.903 13.219 18.883 3.624
section
1/8 th
0.801 3.999 0.948 13.881 19.629 3.766
section
Web thk
0.813 3.999 0.962 14.085 19.858 3.809
section
100
I. STRESS TABLES
1. END GIRDER:
Stress at top Of Stress at bottom of Stress at top of Deck Stress at bottom of Stress at
2 2 2 2
Girder (T/m ) Girder(T/m ) Slab (T/m ) Deck Slab(T/m ) Stress at C.G C.G of all
Description of load and
Due to Due to Due to Due to of 1st stage stage
prestress Cumulati Cumulati Cumulati Cumulati 2
load load load load cables (T/m ) cables
ve ve ve ve 2
described described described described (T/m )
1st stage prestress -451.916 -451.916 1921.586 1921.586
Self weight of Precast
705.709 253.793 -766.004 1155.582 1069.465
girder
Loss due to elastic
shortenings during 1st 10.456 264.249 -44.460 1111.122 1030.250
stage cables
Relaxation loss of 1st
5.380 258.869 -22.875 1088.247
stage cables
Final Relaxation loss for
16.139 -68.625
1st stage cables
Creep and shrinkage loss
between 10 days & 21 26.428 285.298 -112.375 975.872 909.925
days
Weight of Deck slab, cast-
387.533 672.830 -420.643 555.228 566.459
in-situ diaphragms
Creep & Shrinkage loss
11.441 684.271 -48.648 506.581 523.549
between 21 days & 49
2nd stagedays
prestress -23.884 648.947 808.912 1364.141 -93.784 -93.784 -23.884 -23.884
Loss due to elastic
shortenings during 1st 7.519 656.466 -31.972 1332.168
stage cables
Loss due to elastic
shortenings during 2nd 0.186 656.651 -6.288 1325.880 0.729 -93.055 0.186 -23.698 1251.119
stage cables
Relaxation loss of 2nd
0.318 656.970 -10.783 1315.097 1.250 -91.805 0.318 -24.016
stage cables
Final Relaxation loss for
0.955 -32.350 3.751 0.955
2nd stage cables
Creep and shrinkage loss
between 49 days & 60 4.342 661.311 -24.969 1290.127 0.863 -90.942 0.220 -23.797 1219.881
days
Self weight of hand rail
70.634 731.946 -76.669 1213.458 28.583 -62.359 22.069 -1.728 1159.668
and wearing course
101
ii). SECTION AT 3/8TH L
102
iii). SECTION AT 1/4TH L
103
iv). SECTION AT 1/8TH L
104
v). SECTION AT WEB THICKENING
105
I. A) STRESS TABLES (Servicibility checking with 1.1 times prestressing force) cl-7.9.5(6), IRC-112:2011
1. END GIRDER:
Stress at top Of Stress at bottom of Stress at top of Deck Stress at bottom of Stress at
2 2 2 2
Girder (T/m ) Girder(T/m ) Slab (T/m ) Deck Slab(T/m ) Stress at C.G C.G of all
Description of load and
Due to Due to Due to Due to of 1st stage stage
prestress Cumulati Cumulati Cumulati Cumulati 2
load load load load cables (T/m ) cables
ve ve ve ve 2
described described described described (T/m )
1st stage prestress -497.108 -497.108 2113.745 2113.745
Self weight of Precast
705.709 208.601 -766.004 1347.740 1238.958
girder
Loss due to elastic
shortenings during 1st 11.502 220.103 -48.905 1298.835 1195.821
stage cables
Relaxation loss of 1st
5.918 214.185 -25.163 1273.672
stage cables
Final Relaxation loss for
17.753 -75.488
1st stage cables
Creep and shrinkage loss
between 10 days & 21 29.071 243.256 -123.613 1150.059 1063.464
days
Weight of Deck slab, cast-
387.533 630.789 -420.643 729.416 719.998
in-situ diaphragms
Creep & Shrinkage loss
12.585 643.374 -53.513 675.904 672.797
between 21 days & 49
2nd stagedays
prestress -26.272 604.517 889.803 1619.219 -103.163 -103.163 -26.272 -26.272
Loss due to elastic
shortenings during 1st 8.271 612.788 -35.169 1584.050
stage cables
Loss due to elastic
shortenings during 2nd 0.204 612.992 -6.917 1577.133 0.802 -102.361 0.204 -26.068 1469.427
stage cables
Relaxation loss of 2nd
0.350 613.343 -11.862 1565.271 1.375 -100.986 0.350 -26.418
stage cables
Final Relaxation loss for
1.051 -35.585 4.126 1.051
2nd stage cables
Creep and shrinkage loss
between 49 days & 60 4.776 618.118 -27.466 1537.805 0.949 -100.036 0.242 -26.176 1435.065
days
Self weight of hand rail
70.634 688.753 -76.669 1461.136 28.583 -71.453 22.069 -4.108 1374.851
and wearing course
106
ii). SECTION AT 3/8TH L
107
iii). SECTION AT 1/4TH L
108
iv). SECTION AT 1/8TH L
109
v). SECTION AT WEB THICKENING
110
I. B) STRESS TABLES (Servicibility checking with 0.9 times prestressing force) cl-7.9.5(6), IRC-112:2011
1. END GIRDER:
Stress at top Of Stress at bottom of Stress at top of Deck Stress at bottom of Stress at
2 2 2 2
Girder (T/m ) Girder(T/m ) Slab (T/m ) Deck Slab(T/m ) Stress at C.G C.G of all
Description of load and
Due to Due to Due to Due to of 1st stage stage
prestress Cumulati Cumulati Cumulati Cumulati 2
load load load load cables (T/m ) cables
ve ve ve ve 2
described described described described (T/m )
1st stage prestress -406.724 -406.724 1729.428 1729.428
Self weight of Precast
705.709 298.985 -766.004 963.423 899.972
girder
Loss due to elastic
shortenings during 1st 9.410 308.395 -40.014 923.410 864.678
stage cables
Relaxation loss of 1st
4.842 303.553 -20.588 902.822
stage cables
Final Relaxation loss for
14.525 -61.763
1st stage cables
Creep and shrinkage loss
between 10 days & 21 23.785 327.339 -101.138 801.684 756.386
days
Weight of Deck slab, cast-
387.533 714.871 -420.643 381.041 412.920
in-situ diaphragms
Creep & Shrinkage loss
10.297 725.168 -43.783 337.258 374.302
between 21 days & 49
2nd stagedays
prestress -21.495 693.376 728.021 1109.062 -84.406 -84.406 -21.495 -21.495
Loss due to elastic
shortenings during 1st 6.767 700.143 -28.775 1080.287
stage cables
Loss due to elastic
shortenings during 2nd 0.167 700.311 -5.660 1074.627 0.656 -83.750 0.167 -21.328 1032.812
stage cables
Relaxation loss of 2nd
0.287 700.597 -9.705 1064.922 1.125 -82.625 0.287 -21.615
stage cables
Final Relaxation loss for
0.860 -29.115 3.376 0.860
2nd stage cables
Creep and shrinkage loss
between 49 days & 60 3.907 704.505 -22.473 1042.450 0.777 -81.848 0.198 -21.417 1004.697
days
Self weight of hand rail
70.634 775.139 -76.669 965.781 28.583 -53.265 22.069 0.652 944.484
and wearing course
111
ii). SECTION AT 3/8TH L
112
iii). SECTION AT 1/4TH L
113
iv). SECTION AT 1/8TH L
114
v). SECTION AT WEB THICKENING
115
J. CHECK FOR ULTIMATE STRENGTH:
2
Mult= .176*b*d *fck+(2/3)*.8*(Bf-b)*(db-t/2)*t*fck
= 3808.6 T-m
b=Width of web= 300 mm
d= Total depth= 3000 mm
fck= 45 Mpa
Bf= 1500 mm
t= 225 mm
No extra reinforcement is required.
N. DESIGN OF SHEAR :
116
Allowable shear force without shear reinforcement Cl-10.3.2(2),IRC-112:2011
VRdc= [0.12*K*(80*ρ1*fck)0.33+ 0.15*σcp]*bw*d = 1724 Shear Reinforcement is required.
Vrd.c min = (Vmin+0.15σcp )bw*d = 1513 KN
3/2 1/2
Vmin = 0.031*K fck = 0.293
K= = 1.26
ρ1 = = 0.0044
σcp = = 2.000 Mpa
117
N. DESIGN OF INTERFACE SHEAR : (Cl-10.3.4, IRC-112:2011)
Web-
Section Formula Support L/8 L/4 3L/8 Mid-Section
Thickening
VEDi=Interface Shear
stress, Mpa β*VED/z*bi 1.71 1.07 0.94 0.80 0.45 0.31
β= Conservatively 1 1 1 1 1 1
VED=in KN 3080 1921 1692 1447 805 565
z=in mm =.6d for PSC 1800 1800 1800 1800 1800 1800
bi= 1000 1000 1000 1000 1000 1000
Resistance capacity 3.36 2.66 2.02 1.87 1.49 1.34
μ*σn+ρ*fyd*[μ*sin
VRdi=in KN
α+cosα]= 3.355 2.660 2.020 1.873 1.488 1.344
0.5*v*fcd 6.03 6.03 6.03 6.03 6.03 6.03
μ= 0.6 0.6 0.6 0.6 0.6 0.6
σn= <.6*fcd 3.08 1.92 1.69 1.45 0.81 0.57
fyd=in Mpa .8*fyd 400 400 400 400 400 400
α 90 90 90 90 90 90
No. of leg 2 2 2 2 2 2
Dia 16 16 16 16 16 16
Spacing 100 100 150 150 150 150
Area of steel 4019 4019 2679 2679 2679 2679
No. of leg 2 2 2 2 2 2
Dia 12 12 12 12 12 12
Spacing 100 100 150 150 150 150
Area of steel 2261 2261 1507 1507 1507 1507
As= 6280 6280 4187 4187 4187 4187
Asmin= =.15% of Aj= 1500 1500 1500 1500 1500 1500
Check for minimum OK OK OK OK OK OK
reinforcement
ρ= As/Aj 0.0063 0.0063 0.0042 0.0042 0.0042 0.0042
v 0.6 0.6 0.6 0.6 0.6 0.6
Check for shear
OK OK OK OK OK OK
capacity
2
Steel provided= 2747.5 mm
Hence Ok 350
245 245
360
118
K. DEFLECTION CHECK:
Deflection Calculation: Long term
2 2 2
Deflection due to prestress=δps=P.L /8EI [e+Δ-4Δa /3L ]
E= 3481769.63 T/m2
Prestressi
ng force Effective Upward
% loss at
Location after prestressin a (m) Δ (in m) e (m) Deflection
service
anchorage g force (T) (in m)
slip(T)
Cable-1 219.25 30.20 153.0 4.525 0.220 1.636 6.72
Cable-2 219.25 30.20 153.0 4.525 0.220 1.636 6.72
Cable-3 216.4 30.20 151.1 7.325 0.570 1.286 6.55
Cable-4 216.4 30.20 151.1 8.22 0.740 0.936 5.85
Cable-5 214.5 19.17 173.4 9.22 0.910 0.586 5.87
Cable-6 214.5 19.17 173.4 9.72 1.080 0.236 5.04
Total upward deflection= 36.77 mm
Downward deflection:
119
DESIGN OF PSC T-GIRDER WITH 38.8M SPAN (C/C OF BEARING ) [OUTER GIRDER]
A. GEOMETRIC PROPERTIES OF THE GIRDER
180 100
2325
300 2775
450
850
2000 3000 3000 3000 1500
C/S AT MIDDLE
500 12500
500 225 500
1500 9500
1250
42
850
2325 2775
450
850
9700
2000
1250
3000
400
300
850
300
120
B. PROPERTIES OF GIRDER SECTION
Precast Section :
1250
For end portion of girder having length 1.6 m 180
I precast = [{1.25x0.005832/12+0.225x1.68350625}+{(0.475x0.003375)/18}+{0.07125x1.34+(0.3x12.9)/12}+
{(0.275x0.008/18)+0.055x1.15}+{(0.85x0.015625/12)+0.2125x1.59}]
4
1.2 m
3 3
Ztp = 0.902 m Zbp = 0.831 m
Edge Girder
Effective flange width = 1.5+1.75 = 3.25 m
2
Area of girder = [(3.25x0.233] +1.267= 2.024 m
4
Icomposite = [(3.25x0.013/12)+(3.25x0.054)]+[1.2+1.267x(0.542^2)] = 2.278 m
3 3 3
Zts = 2.229 m Ztg = Zbs = 2.887 m Zbg = 1.147 m
121
Central Girder
Effective flange width = 1.5+1.5 = 3m
2
Area of girder = [(3x0.233] +1.267= 1.966 m
4
Icomposite = [(3x0.013/12)+(3x0.054)]+[1.2+1.267x(0.515^2)] = 2.209 m
3 3 3
Zts = 2.106 m Ztg = Zbs = 2.707 m Zbg = 1.128 m
C. DEAD LOAD
a. Precast portion
Area of each diaphragm (per girder) = 0.5 x(1.25+0.85) x2.345- 0.5 x ( 1.25+0.3) x0.15- 0.5 x (0.3+0.85) x 0.2- (0.3x1.995)
= 2.83 m2
Loading = 2.83x25x0.3 = 21.225 kN (on each girder)
b. In Situ portion
Area of each diaphragm = 0.5 x(1.75+2.15) x 2.325 = 4.534 m2
a. Precast portion
Area of each diaphragm (per girder) = (1.25x2.775) -2.443-{(1.25-0.85) x0.35} = 0.88575 m2
b. In Situ portion
Area of each diaphragm = (3-1.25)x(2.775-0.35) = = 4.24375 m2
122
3. Self weight of deck slab
Superimposed dead load will be placed on deck slab after composite action starts.
123
SHEAR AT DIFFERENT SECTIONS OF T GIRDER DUE TO DEAD LOAD:
124
ii) For Central Girder
125
3. DUE TO SUPERIMPOSED DEAD LOAD :
9.0740625
126
F. CROWD LOAD:
0.000 kN/m
0 kN/m
127
E. LOAD TABLES
2. TABLE SHOWING MAX. SHEAR FORCE AT DIFERENT SECTION AND CORRESPONDING BM:
128
3. TABLE SHOWING MAX. BENDING MOMENTS AND STRESSES AT DIFERENT SECTION
stress at top of
- - - 76.37 80.83 282.50 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 58.96 62.88 218.12 0
MID (T/m2)
stress at top of
precast girder 705.71 369.25 387.53 188.72 188.72 218.12 0
(T/m2)
stress at bottom
of precast girder -766.00 -400.80 -420.64 -204.85 -204.85 -549.00 0.00
(T/m2)
MOMENT(T-M) 594.15 311.15 325.58 159.55 159.55 605.70 0.00
stress at top of
- - - 71.58 75.76 271.74 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 55.27 58.94 209.80 0
3/8 TH (T/m2)
stress at top of
precast girder 658.70 344.96 360.96 176.89 176.89 209.80 0
(T/m2)
stress at bottom
of precast girder -714.98 -374.43 -391.80 -192.00 -192.00 -528.07 0.00
(T/m2)
MOMENT(T-M) 477.24 249.55 261.92 127.54 127.54 476.68 0.00
stress at top of
- - - 57.22 60.56 213.85 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 44.18 47.11 165.11 0
1/4 TH (T/m2)
stress at top of
precast girder 529.09 276.66 290.38 141.39 141.39 165.11 0
(T/m2)
stress at bottom
of precast girder -574.30 -300.30 -315.19 -153.48 -153.48 -415.59 0.00
(T/m2)
MOMENT(T-M) 275.53 144.13 150.31 74.18 74.18 304.18 0.00
stress at top of
- - - 33.28 35.22 136.46 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 25.69 27.40 105.36 0
1/8 TH (T/m2)
stress at top of
precast girder 305.47 159.79 166.65 82.24 82.24 105.36 0
(T/m2)
stress at bottom
of precast girder -331.57 -173.44 -180.88 -89.26 -89.26 -265.20 0.00
(T/m2)
129
MOMENT(T-M) 129.22 67.33 70.03 34.75 34.75 256.85 0.00
stress at top of
- - - 15.59 16.50 115.23 0
deck slab (T/m2)
stress at bottom
of deck slab - - - 12.04 12.84 88.97 0
(T/m2)
WEB. TH
stress at top of
precast girder 143.26 74.65 77.64 38.53 38.53 88.97 0
(T/m2)
stress at bottom
of precast girder -155.50 -81.02 -84.28 -41.82 -41.82 -223.93 0.00
(T/m2)
130
F. PRESTRESSING
Prestressing cables shall be 19 strand cables conforming to IS 14268-1995 class II with minimum breaking load = 18.371 Ton
for 12.7 mm dia ,7 ply strand.
131
675 200
7
350
7 6
180 350
6 5
180 350
425
5 4
180 350 2775
4 200 3
180 350
250
130 2 3 1 1 2
245 180 180
350
850 245 360 245
R(Min)= 12 m
H C/L
θv
Vc
A B C D E
Vertical Curve
C1 C2 C3 C4
Horizontal curve
θh R(Min)= 10.6 m
HS
θh
Horizontal curve
132
-1
Horrizontal splay to be given in cables 1 in 10, i.e. θH= tan 1/10= 5.71 °
LHc= 10.6X0.0997= 1.056 m
C3= 10xH s+2xLHcX0.5
Eqn-1-Eqn-2
=>C2= [{19.72 -(C3+C4)}-H/tanθv]x2 Eqn-3
Substitute the value of C2 in Eqn-1,
=>C1= 19.72 -(C3+C4+C2) Eqn-4
4. Force diagram of each cable after anchorage slip will be as shown follow:
According to IRC-112,2011,
The steel stress at jacking end= σpo=σpx.e(kx+µθ)
σpo= Applied force
σpo(x)= Force at any place in cable
µ= Friction co-efficient = 0.25 for bright metal stress
k= Wooble co-efficient = 0.0046 relieved strand
Say slip loss= 6 mm
Modulus of elasticity of material of cable= 1.95E+06 Kg/sqcm
133
For cable 1&2:
Web Thickening 1/8th section 1/4th section 3/8th section Mid-Section
3520
1410 4930 4930 4930
244.3 t
242.32 t
235.13 t 232.464 t
219.254 t
2550 211.964
209.49 t
201.62 t
203.27 t
Cable Horizontal
length distance
1771 2764
For cable 3:
Web Thickening 1/8th section 1/4th section 3/8th section Mid-Section
3520
1410 4930 4930 4930
244.3 t
242.11 t
229.10 t
216.403 t
214.100
t
200.73 t 214.10 t
202.57 t
Cable Horizontal
length distance
1975 5399
134
Area of the diagram
=0.5x(43.566+39.542)x1.975+0.5x(39.542+15)x5.399+0.5x(15+-214.1)x0= 229.304 t-m
For cable 4:
Web Thickening 1/8th section 1/4th section 3/8th section Mid-Section
3520
1410 4930 4930 4930
244.3 t
240.03 228.16 t
228.16 t
219.16 t 216.403 t
204.63 t
208.29 t Check
Cable Horizontal
length distance
3863 4413
135
For cable 5:
Web Thickening 1/8th section 1/4th section 3/8th section Mid-Section
3520
1410 4930 4930 4930
244.3 t
241.76 t
225.14 t `
220.94 214.523 t
203.52 t 205.68 t
Cable Horizontal
length distance
2299 7021
136
For cable 6:
3520
1410 4930 4930 4930
244.3 t
239.94 t
224.62 t `
223.62 t 214.523 t
205.5 t 209.29 t
Cable Horizontal
length distance
3967 5862
5. Stages of Prestressing
First Stage: 4 cables in each girder at 14 days or the
First stage prestressing will be on precast girder when the girder concrete attains a strength at least equal to 0.9
of its 28 days compressive strength or the concrete is 14 days old whichever is later. Using
grade of girder and deck concrete as M45, strength of girder concrete at the time of stressing will be at least
40.5 Mpa. Cable no. 1,2,3 & 6 will be stressed during the first stage.
Second tag: 2 cables in each girder at 28 days after casting of deck.
Second stage stressing will be done after casting of deck slab and after the deck concrete have attained its 28 days
strength. The deck will be cast after 7 days from the date of first stage prestress, i.e. when the girder concrete
is 21 days old. Hence girder concrete will be 49 days old at the time of second stage
presress and full composite action is obtained. Cable no. 4 & 5 will be stressed at this stage
Kerb, crash barrier, wearing course will be laid, when the girders are 60 days old.
137
6. PROPERTIES OF GIRDER SECTION:
PREACAST GIRDER COMPOSITE GIRDER
Section Section Section
CG from Section Section
CG from modulus modulus of modulus of
Location Area (Ap) Area (Ac) in bottom of modulus of modulus of
bottom of of top of bottom of bottom of
in m
2
m
2 girder Ybg top of girder top of slab
girder Ybp (m) girder Ztp girder Zbp 3 girder Zbgc 3
3 3 (m) Z tgc (m ) 3
Zts (m )
(m ) (m ) (m )
End Girder 1.267 1.444 0.902 0.831 2.024 1.986 2.887 1.147 2.229
Central Girder 1.267 1.444 0.902 0.831 1.966 1.959 2.707 1.128 2.106
138
8. INITIAL PRESTRESS AT DIFFERENT SECTIONS
i). END GIRDER:
a).MID SECTION: 19.72 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(869.434/1 (869.434/
0.13 0 0 219.25 0 219.254 1.314 288.100
1 .267)- 1.267)+(10
-
(1026.594/ 26.594/0.
0.13 0 0 219.25 0 219.254 1.314 288.100
2 0.902)= 831)=
1st Stage at
0.13 0 0 216.40 0 216.403 1.314 284.353
14 Days 3
139
b).3/8TH SECTION: 14.79 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(867.319/1 (867.319/
0.13 0 0 216.41 0 216.412 1.314 284.365
1 .267)- 1.267)+(10
-
(1021.392/ 21.392/0.
0.13 0 0 216.41 0 216.412 1.314 284.365
2 0.902)= 831)=
1st Stage at
0.13 0 0 215.49 0 215.487 1.314 283.150
14 Days 3
140
c).1/4TH SECTION: 9.86 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(865.204/1 (865.204/
0.13 0 0 213.57 0 213.569 1.314 280.630
1 .267)- 1.267)+(10
-
(1016.191/ 16.191/0.
0.13 0 0 213.57 0 213.569 1.314 280.630
2 0.902)= 831)=
1st Stage at
0.13 0 0 214.57 0 214.571 1.314 281.946
14 Days 3
141
d).1/8TH SECTION: 4.93 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(837.373/1 (837.373/
0.130 0.000 0 209.88 0 209.885 1.314 275.788
1 .267)- 1.267)+(96
-
(969.948/0 9.948/0.8
0.130 0.000 0 209.88 0 209.885 1.314 275.788
2 .902)= 31)=
1st Stage at
0.130 0.122 0 208.95 25.465 207.394 1.314 272.515
14 Days 3
142
e).WEB-THICKENING SECTION: 3.52 M
Stress at Stress at
Top of Bottom of Stress at
Horizontal Eccentricity girder girder top of slab
Vertical Horizontal Pull in Vertical pull [σptg= {∑ [σpbg= {∑ [σpts= {∑
Stage of CG form soffit pull from CG of M=(P. Cosθv)
Cable No. angle angle Cable(P) ( P. Sinθv)
Prestressing of Girder (ŷ) (m) ( P. Cosθv) section xe P.Cosθv/A-∑ P.Cosθv/A+ P.Cosθv/A+
(θv)(rad) (θh)(rad) (ton) (ton)
(ton) (Yb-ŷ) (m) P.Cosθv. ∑P.Cosθv. ∑P.Cosθv.
2
e/Ztp} e/Zbp} e/Zts} (t/m )
2 2
(t/m ) (t/m )
(825.17/1. (825.17/1.
0.130 0.070 0 207.22 14.455178 206.719 1.314 271.628
1 267)- 267)+(837.
-
(837.134/0 134/0.831
0.130 0.070 0 207.22 14.455178 206.719 1.314 271.628
2 .902)= )=
1st Stage at
0.226 0.122 0 205.92 25.095 204.385 1.218 248.987
14 Days 3
143
G. ELONGATION CALCULATION
The elongation length calculated only for the cable between the midspan and end faces.
Additional length for attaching the jack may be added in consultation with the system manufacturer.
Extra elongation may be added @ 7mm/m for portion between end face and gripping point of jack.
144
H. LOSSES IN PRESTRESS
1. END GIRDER:
i). Stage-1: Between 14 days to 21 days
Elastic shortening:
Average stresses in 1st stage cables at differen sections, just after seating of anchorage will be as follows :
2
i) At mid-section= (1000x(869.434x0.977))/(4x18.772)= 11310.97 Kg/cm
2
ii) At 3/8 th section= (1000x(867.319x0.977))/(4x18.772)= 11282.80 Kg/cm
2
iii) At 1/4 th section= (1000x(865.204x0.977))/(4x18.772)= 11254.63 Kg/cm
2
iv) At 1/8 th section= (1000x(837.373x0.976))/(4x18.772)= 10883.99 Kg/cm
2
v) At web thickening section= (1000x(825.17x0.976))/(4x18.772)= 10721.47 Kg/cm
Average stress at CG of 1st stage cables at 14 days just after seating of anchorages is: [Ref: stress Tables]
=(2x(1217.387+1293.258+1173.347+1065.193)+1030.25)/9
2
1169.847 T/m = 11.698 Mpa
145
Assumed loss in different sections due to creep and shrinkage as follows:
i) At mid-section= 5.85 %
ii) At 3/8 th section= 5.86 %
iii) At 1/4 th section= 5.88 %
iv) At 1/8 th section= 6.07 %
v) At web thickening section= 6.16 %
Average stress at CG of 1st stage cables at 21 days with 1000 hour relaxation loss will be as follows:
[Ref: stress Tables]
=(2x(1116.378+1176.2+1053.508+945.109)+909.919)/9
2
1054.701 T/m = 10.547 Mpa
Average stress along CG of 1st stage cables during 14 days and 21 days will be
(0.5x(10.547+11.69847)= 11.123 Mpa
Creep strain during this period= 3.28E-04
Loss due to creep and shrinkage=
(0.0000188967241811016+0.000328)x(1950000x4x18.772)/1000= 50.849 T
Percentage loss:
i) At mid-section= (50.849X100)/(869.434)= 5.85 % Hence OK
ii) At 3/8 th section= (50.849X100)/(867.319)= 5.86 % Hence OK
iii) At 1/4 th section= (50.849X100)/(865.204)= 5.88 % Hence OK
iv) At 1/8 th section= (50.849X100)/(837.373)= 6.07 % Hence OK
v) At web thickening section= (50.849X100)/(825.17)= 6.16 % Hence OK
Average stress at CG of 1st stage cables at 14 days just after seating of anchorages is: [Ref: stress Tables]
=(2x(1059.382+1036.986+808.305+639.375)+582.658)/9
2
852.306 T/m = 8.523 Mpa
Assumed loss in different sections due to creep and shrinkage betweeen 21 days to 49 as follows:
i) At mid-section= 2.56 %
ii) At 3/8 th section= 2.57 %
iii) At 1/4 th section= 2.57 %
iv) At 1/8 th section= 2.66 %
v) At web thickening section= 2.70 %
Average stress at CG of 1st stage cables at 21 days with 1000 hour relaxation loss will be as follows:
[Ref: stress Tables]
=(2x(1022.726+994.521+765.069+596.059)+539.286)/9
2
810.671 T/m = 8.107 Mpa
Average stress along CG of 1st stage cables during 14 days and 21 days will be
(0.5x(8.107+8.52306)= 8.315 Mpa
Creep strain during this period= 1.45E-04
Loss due to creep and shrinkage=
(0.0000071338016796995+0.000145)x(1950000x4x18.772)/1000= 22.248 T
Percentage loss:
i) At mid-section= (22.248X100)/(869.434)= 2.56 % Hence OK
ii) At 3/8 th section= (22.248X100)/(867.319)= 2.57 % Hence OK
iii) At 1/4 th section= (22.248X100)/(865.204)= 2.57 % Hence OK
iv) At 1/8 th section= (22.248X100)/(837.373)= 2.66 % Hence OK
v) At web thickening section= (22.248X100)/(825.17)= 2.70 % Hence OK
146
iii). Stage-3: Between 49 days to 60 days
Additional stress at CG of 1st & 2nd stage cables due to 2nd stage prestressing are as follows:
Total depth of precast girder: 2.775 m
a) At mid section:
2
Stress at top=ftg= -23.884 T/m
2
Stress at bottom=fbg= 808.912 T/m
CG of 1st stage cables= 0.265 m
CG of 2nd stage cables= 0.400 m
2
Stress at CG of 1st stage cables= (808.912-(808.912--23.884)x0.265/2.775)= 729.384 T/m
2
Stress at CG of 2nd stage cables= (808.912-(808.912--23.884)x0.4/2.775)= 688.869 T/m
b) At 3/8 th section:
2
Stress at top=ftg= -24.058 T/m
2
Stress at bottom=fbg= 816.639 T/m
CG of 1st stage cables= 0.265 m
CG of 2nd stage cables= 0.400 m
2
Stress at CG of 1st stage cables= (816.639-(816.639--24.058)x0.265/2.775)= 736.356 T/m
2
Stress at CG of 2nd stage cables= (816.639-(816.639--24.058)x0.4/2.775)= 695.457 T/m
c) At 1/4 th section:
2
Stress at top=ftg= -24.233 T/m
2
Stress at bottom=fbg= 824.367 T/m
CG of 1st stage cables= 0.265 m
CG of 2nd stage cables= 0.400 m
2
Stress at CG of 1st stage cables= (824.367-(824.367--24.233)x0.265/2.775)= 743.33 T/m
2
Stress at CG of 2nd stage cables= (824.367-(824.367--24.233)x0.4/2.775)= 702.046 T/m
d) At 1/8 th section:
2
Stress at top=ftg= -3.027 T/m
2
Stress at bottom=fbg= 734.565 T/m
CG of 1st stage cables= 0.285 m
CG of 2nd stage cables= 0.539 m
2
Stress at CG of 1st stage cables= (734.565-(734.565--3.027)x0.285035631701054/2.775)= 658.803 T/m
2
Stress at CG of 2nd stage cables= (734.565-(734.565--3.027)x0.538929026393131/2.775)= 591.318 T/m
147
e) Web thickening section:
2
Stress at top=ftg= 15.144 T/m
2
Stress at bottom=fbg= 678.314 T/m
CG of 1st stage cables= 0.428 m
CG of 2nd stage cables= 0.666 m
2
Stress at CG of 1st stage cables= (678.314-(678.314-15.144)x0.42831826434307/2.775)= 575.954 T/m
2
Stress at CG of 2nd stage cables= (678.314-(678.314-15.144)x0.665549784066415/2.775)= 519.261 T/m
Average stresses in 1st stage cables at differen sections, just after seating of anchorage will be as follows :
2
i) At mid-section= (1000x(430.925x0.992))/(2x18.772)= 11388.65 Kg/cm
2
ii) At 3/8 th section= (1000x(435.119x0.992))/(2x18.772)= 11500.35 Kg/cm
2
iii) At 1/4 th section= (1000x(439.313x0.992))/(2x18.772)= 11612.06 Kg/cm
2
iv) At 1/8 th section= (1000x(418.35x0.992))/(2x18.772)= 11053.71 Kg/cm
2
v) At web thickening section= (1000x(412.3x0.992))/(2x18.772)= 10892.54 Kg/cm
148
Loss due to shrinkage and creep in 2nd stage cable:
Average stress at CG of all cables at 49 days , just after seating of 2nd stage anchorage will be as follows:
[Ref: stress Tables]
=(2x(1552.046+1609.286+1497.391+1328.08)+1266.7)/9
2
1471.145 T/m = 14.712 Mpa
Assumed loss in different sections at 1st stage cables after 2nd stage prestressing due to creep and shrinkage as follows:
i) At mid-section= 0.92 %
ii) At 3/8 th section= 0.92 %
iii) At 1/4 th section= 0.92 %
iv) At 1/8 th section= 0.95 %
v) At web thickening section= 0.97 %
Assumed loss in different sections at 2nd stage cables after 2nd stage prestressing due to creep and shrinkage as follows:
i) At mid-section= 0.93 %
ii) At 3/8 th section= 0.92 %
iii) At 1/4 th section= 0.91 %
iv) At 1/8 th section= 0.95 %
v) At web thickening section= 0.97 %
Average stress at CG of all cables at 60 days before completion of W.C., Railing, Crash Barrier: [Ref: stress Tables]
=(2x(1526.616+1580.165+1465.891+1296.642)+1235.329)/9
2
1441.551 T/m = 14.416 Mpa
Average stress along CG of 1st stage cables during 49 days and 60 days will be
(0.5x(14.7115+14.4155)= 14.564 Mpa
Creep strain during this period= (0.0000524843261539538X1.45635)= 0.000052
Loss due to creep and shrinkage in first stage cables=
(0.000002+0.000052)x(1950000x4x18.772)/1000= 7.978 T
Loss due to creep and shrinkage in second stage cables=
(0.000002+0.000052)x(1950000x4x18.772)/1000= 3.989 T
Percentage loss in different sections will be as follows:
a) For first stage prestress:
i) At mid-section= (7.978X100)/(869.434)= 0.92 % Hence OK
ii) At 3/8 th section= (7.978X100)/(867.319)= 0.92 % Hence OK
iii) At 1/4 th section= (7.978X100)/(865.204)= 0.92 % Hence OK
iv) At 1/8 th section= (7.978X100)/(837.373)= 0.95 % Hence OK
v) At web thickening section= (7.978X100)/(825.17)= 0.97 % Hence OK
a) For second stage prestress:
i) At mid-section= (3.989X100)/(430.925)= 0.93 % Hence OK
ii) At 3/8 th section= (3.989X100)/(435.119)= 0.92 % Hence OK
iii) At 1/4 th section= (3.989X100)/(439.313)= 0.91 % Hence OK
iv) At 1/8 th section= (3.989X100)/(418.35)= 0.95 % Hence OK
v) At web thickening section= (3.989X100)/(412.3)= 0.97 % Hence OK
149
iv). Stage-4: Between 60 days to end
Loss due to shrinkage and creep in 2nd stage cable:
Average stress at CG of all cables at 60 days , after completion of WC, Railing, Crash barrier:
[Ref: stress Tables]
=(2x(1499.488+1513.749+1345.356+1145.849)+1074.449)/9
2
1342.593 T/m = 13.426 Mpa
Assumed loss in different sections at 1st stage cables after 3rd stage casting due to creep and shrinkage as follows:
i) At mid-section= 12.84 %
ii) At 3/8 th section= 12.87 %
iii) At 1/4 th section= 12.90 %
iv) At 1/8 th section= 13.33 %
v) At web thickening section= 13.52 %
Assumed loss in different sections at 2nd stage cables after 3rd stage casting due to creep and shrinkage as follows:
i) At mid-section= 12.95 %
ii) At 3/8 th section= 12.82 %
iii) At 1/4 th section= 12.70 %
iv) At 1/8 th section= 13.34 %
v) At web thickening section= 13.53 %
Average stress at CG of all cables after final loss: [Ref: stress Tables]
=(2x(1247.627+1225.044+1040.721+844.372)+769.124)/9
2
1053.85 T/m = 10.539 Mpa
Average stress along CG of 1st stage cables during 7 days and 21 days will be
(0.5x(13.42593+10.5385)= 11.982 Mpa
Creep strain during this period= 7.49E-04
Loss due to creep and shrinkage in first stage cables=
(0.0000132+0.000749)x(1950000x4x18.772)/1000= 111.603 T
Loss due to creep and shrinkage in second stage cables=
(0.0000132+0.000749)x(1950000x2x18.772)/1000= 55.801 T
Percentage loss in different sections will be as follows:
a) For first stage prestress:
i) At mid-section= (111.603X100)/(869.434)= 12.84 % Hence OK
ii) At 3/8 th section= (111.603X100)/(867.319)= 12.87 % Hence OK
iii) At 1/4 th section= (111.603X100)/(865.204)= 12.90 % Hence OK
iv) At 1/8 th section= (111.603X100)/(837.373)= 13.33 % Hence OK
v) At web thickening section= (111.603X100)/(825.17)= 13.52 % Hence OK
a) For second stage prestress:
i) At mid-section= (55.801X100)/(430.925)= 12.95 % Hence OK
ii) At 3/8 th section= (55.801X100)/(435.119)= 12.82 % Hence OK
iii) At 1/4 th section= (55.801X100)/(439.313)= 12.70 % Hence OK
iv) At 1/8 th section= (55.801X100)/(418.35)= 13.34 % Hence OK
v) At web thickening section= (55.801X100)/(412.3)= 13.53 % Hence OK
150
v). Total percentage loss in each different section will be as follows:
20% Higher
Stages of Prestressing
section
1/4 th
2.325 3.571 5.877 2.571 1.672 0.922 12.899 29.838 5.168
section
1/8 th
2.402 3.571 6.072 2.657 1.728 0.953 13.328 30.711 5.316
section
Web thk
2.438 3.571 6.162 2.696 1.753 0.967 13.525 31.112 5.384
section
mid
0.777 3.999 0.926 12.949 18.651 3.575
section
3/8 th
0.770 3.999 0.917 12.824 18.510 3.548
2nd stage cables
section
1/4 th
0.763 3.999 0.908 12.702 18.372 3.522
section
1/8 th
0.801 3.999 0.954 13.338 19.092 3.658
section
Web thk
0.813 3.999 0.968 13.534 19.313 3.700
section
151
I. STRESS TABLES
1. END GIRDER:
Stress at top Of Stress at bottom of Stress at top of Deck Stress at bottom of Stress at
2 2 2 2
Girder (T/m ) Girder(T/m ) Slab (T/m ) Deck Slab(T/m ) Stress at C.G C.G of all
Description of load and
Due to Due to Due to Due to of 1st stage stage
prestress Cumulati Cumulati Cumulati Cumulati 2
load load load load cables (T/m ) cables
ve ve ve ve 2
described described described described (T/m )
1st stage prestress -451.916 -451.916 1921.586 1921.586
Self weight of Precast
705.709 253.793 -766.004 1155.582 1069.465
girder
Loss due to elastic
shortenings during 1st 10.456 264.249 -44.460 1111.122 1030.250
stage cables
Relaxation loss of 1st
5.380 258.869 -22.875 1088.247
stage cables
Final Relaxation loss for
16.139 -68.625
1st stage cables
Creep and shrinkage loss
between 10 days & 21 26.430 285.299 -112.382 975.865 909.919
days
Weight of Deck slab, cast-
369.248 654.548 -400.797 575.068 582.658
in-situ diaphragms
Creep & Shrinkage loss
11.564 666.112 -49.172 525.896 539.286
between 21 days & 49
2nd stagedays
prestress -23.884 630.664 808.912 1383.980 -93.784 -93.784 -23.884 -23.884
Loss due to elastic
shortenings during 1st 7.519 638.183 -31.972 1352.008
stage cables
Loss due to elastic
shortenings during 2nd 0.186 638.369 -6.288 1345.720 0.729 -93.055 0.186 -23.698 1266.700
stage cables
Relaxation loss of 2nd
0.318 638.687 -10.783 1334.936 1.250 -91.805 0.318 -24.016
stage cables
Final Relaxation loss for
0.955 -32.350 3.751 0.955
2nd stage cables
Creep and shrinkage loss
between 49 days & 60 4.368 643.056 -25.123 1309.814 0.868 -90.937 0.221 -23.795 1235.329
days
Self weight of hand rail
188.722 831.777 -204.846 1104.968 76.369 -14.568 58.963 35.168 1074.449
and wearing course
152
ii). SECTION AT 3/8TH L
153
iii). SECTION AT 1/4TH L
154
iv). SECTION AT 1/8TH L
155
v). SECTION AT WEB THICKENING
156
I. A) STRESS TABLES (Servicibility checking with 1.1 times prestressing force) cl-7.9.5(6), IRC-112:2011
1. END GIRDER:
Stress at top Of Stress at bottom of Stress at top of Deck Stress at bottom of Stress at
2 2 2 2
Girder (T/m ) Girder(T/m ) Slab (T/m ) Deck Slab(T/m ) Stress at C.G C.G of all
Description of load and
Due to Due to Due to Due to of 1st stage stage
prestress Cumulati Cumulati Cumulati Cumulati 2
load load load load cables (T/m ) cables
ve ve ve ve 2
described described described described (T/m )
1st stage prestress -497.108 -497.108 2113.745 2113.745
Self weight of Precast
705.709 208.601 -766.004 1347.740 1238.958
girder
Loss due to elastic
shortenings during 1st 11.502 220.103 -48.905 1298.835 1195.821
stage cables
Relaxation loss of 1st
5.918 214.185 -25.163 1273.672
stage cables
Final Relaxation loss for
17.753 -75.488
1st stage cables
Creep and shrinkage loss
between 10 days & 21 29.073 243.258 -123.621 1150.052 1063.457
days
Weight of Deck slab, cast-
369.248 612.507 -400.797 749.255 736.196
in-situ diaphragms
Creep & Shrinkage loss
12.721 625.227 -54.089 695.166 688.487
between 21 days & 49
2nd stagedays
prestress -26.272 586.235 889.803 1639.058 -103.163 -103.163 -26.272 -26.272
Loss due to elastic
shortenings during 1st 8.271 594.506 -35.169 1603.889
stage cables
Loss due to elastic
shortenings during 2nd 0.204 594.710 -6.917 1596.972 0.802 -102.361 0.204 -26.068 1485.007
stage cables
Relaxation loss of 2nd
0.350 595.060 -11.862 1585.110 1.375 -100.986 0.350 -26.418
stage cables
Final Relaxation loss for
1.051 -35.585 4.126 1.051
2nd stage cables
Creep and shrinkage loss
between 49 days & 60 4.805 599.865 -27.635 1557.475 0.955 -100.031 0.243 -26.175 1450.499
days
Self weight of hand rail
188.722 788.587 -204.846 1352.629 76.369 -23.662 58.963 32.788 1289.619
and wearing course
157
ii). SECTION AT 3/8TH L
158
iii). SECTION AT 1/4TH L
159
iv). SECTION AT 1/8TH L
160
v). SECTION AT WEB THICKENING
161
I. B) STRESS TABLES (Servicibility checking with 0.9 times prestressing force) cl-7.9.5(6), IRC-112:2011
1. END GIRDER:
Stress at top Of Stress at bottom of Stress at top of Deck Stress at bottom of Stress at
2 2 2 2
Girder (T/m ) Girder(T/m ) Slab (T/m ) Deck Slab(T/m ) Stress at C.G C.G of all
Description of load and
Due to Due to Due to Due to of 1st stage stage
prestress Cumulati Cumulati Cumulati Cumulati 2
load load load load cables (T/m ) cables
ve ve ve ve 2
described described described described (T/m )
1st stage prestress -406.724 -406.724 1729.428 1729.428
Self weight of Precast
705.709 298.985 -766.004 963.423 899.972
girder
Loss due to elastic
shortenings during 1st 9.410 308.395 -40.014 923.410 864.678
stage cables
Relaxation loss of 1st
4.842 303.553 -20.588 902.822
stage cables
Final Relaxation loss for
14.525 -61.763
1st stage cables
Creep and shrinkage loss
between 10 days & 21 23.787 327.340 -101.144 801.678 756.381
days
Weight of Deck slab, cast-
369.248 696.589 -400.797 400.881 429.120
in-situ diaphragms
Creep & Shrinkage loss
10.408 706.996 -44.254 356.627 390.085
between 21 days & 49
2nd stagedays
prestress -21.495 675.093 728.021 1128.902 -84.406 -84.406 -21.495 -21.495
Loss due to elastic
shortenings during 1st 6.767 681.861 -28.775 1100.127
stage cables
Loss due to elastic
shortenings during 2nd 0.167 682.028 -5.660 1094.468 0.656 -83.750 0.167 -21.328 1048.393
stage cables
Relaxation loss of 2nd
0.287 682.314 -9.705 1084.763 1.125 -82.625 0.287 -21.615
stage cables
Final Relaxation loss for
0.860 -29.115 3.376 0.860
2nd stage cables
Creep and shrinkage loss
between 49 days & 60 3.932 686.246 -22.611 1062.152 0.781 -81.843 0.199 -21.416 1020.159
days
Self weight of hand rail
188.722 874.967 -204.846 857.306 76.369 -5.474 58.963 37.548 859.279
and wearing course
162
ii). SECTION AT 3/8TH L
163
iii). SECTION AT 1/4TH L
164
iv). SECTION AT 1/8TH L
165
v). SECTION AT WEB THICKENING
166
J. CHECK FOR ULTIMATE STRENGTH:
2
Mult= .176*b*d *fck+(2/3)*.8*(Bf-b)*(db-t/2)*t*fck
= 3808.6 T-m
b=Width of web= 300 mm
d= Total depth= 3000 mm
fck= 45 Mpa
Bf= 1500 mm
t= 225 mm
No extra reinforcement is required.
N. DESIGN OF SHEAR :
167
Allowable shear force without shear reinforcement Cl-10.3.2(2),IRC-112:2011
VRdc= [0.12*K*(80*ρ1*fck)0.33+ 0.15*σcp]*bw*d = 1724 Shear Reinforcement is required.
Vrd.c min = (Vmin+0.15σcp )bw*d = 1513 KN
3/2 1/2
Vmin = 0.031*K fck = 0.293
K= = 1.26
ρ1 = = 0.0044
σcp = = 2.000 Mpa
168
N. DESIGN OF INTERFACE SHEAR : (Cl-10.3.4, IRC-112:2011)
Web-
Section Formula Support L/8 L/4 3L/8 Mid-Section
Thickening
VEDi=Interface Shear
stress, Mpa β*VED/z*bi 1.82 1.36 1.21 1.00 0.59 0.41
β= Conservatively 1 1 1 1 1 1
VED=in KN 3284 2456 2184 1795 1059 736
z=in mm =.6d for PSC 1800 1800 1800 1800 1800 1800
bi= 1000 1000 1000 1000 1000 1000
Resistance capacity 3.48 2.98 2.32 2.08 1.64 1.45
μ*σn+ρ*fyd*[μ*sin
VRdi=in KN
α+cosα]= 3.477 2.981 2.315 2.082 1.640 1.447
0.5*v*fcd 6.03 6.03 6.03 6.03 6.03 6.03
μ= 0.6 0.6 0.6 0.6 0.6 0.6
σn= <.6*fcd 3.28 2.46 2.18 1.79 1.06 0.74
fyd=in Mpa .8*fyd 400 400 400 400 400 400
α 90 90 90 90 90 90
No. of leg 2 2 2 2 2 2
Dia 16 16 16 16 16 16
Spacing 100 100 150 150 150 150
Area of steel 4019 4019 2679 2679 2679 2679
No. of leg 2 2 2 2 2 2
Dia 12 12 12 12 12 12
Spacing 100 100 150 150 150 150
Area of steel 2261 2261 1507 1507 1507 1507
As= 6280 6280 4187 4187 4187 4187
Asmin= =.15% of Aj= 1500 1500 1500 1500 1500 1500
Check for minimum OK OK OK OK OK OK
reinforcement
ρ= As/Aj 0.0063 0.0063 0.0042 0.0042 0.0042 0.0042
v 0.6 0.6 0.6 0.6 0.6 0.6
Check for shear
OK OK OK OK OK OK
capacity
2
Steel provided= 2747.5 mm
Hence Ok 350
245 245
360
169
K. DEFLECTION CHECK:
Deflection Calculation: Long term
2 2 2
Deflection due to prestress=δps=P.L /8EI [e+Δ-4Δa /3L ]
E= 3481769.63 T/m2
Prestressi
ng force Effective Upward
% loss at
Location after prestressin a (m) Δ (in m) e (m) Deflection
service
anchorage g force (T) (in m)
slip(T)
Cable-1 219.25 29.71 154.1 4.525 0.220 1.636 6.77
Cable-2 219.25 29.71 154.1 4.525 0.220 1.636 6.77
Cable-3 216.4 29.71 152.1 7.325 0.570 1.286 6.60
Cable-4 216.4 29.71 152.1 8.22 0.740 0.936 5.89
Cable-5 214.5 18.65 174.5 9.22 0.910 0.586 5.91
Cable-6 214.5 18.65 174.5 9.72 1.080 0.236 5.07
Total upward deflection= 37.02 mm
Downward deflection:
170
SUBSTRUCTURE DESIGN OF
IRANG BRIDGE
CH._95.500 KM
171
ABUTMENT DESIGN
CHAINAGE -95.500 KM
3X41.0M PSC T-GIRDER
IRANG RIVER
172
ANALYSIS OF ABUTMENT
Basic design data:-
a) Superstructure:-
Formation level = 240.000 m
R.L. of carriageway at end long girder = 239.762 m
Overall length of Bridge= 123.840 m
Span ( c/c of expansion joint) = 41.000 m
Distance between C/L of bearing to C/L of exp. joint = 1.100 m
Effective span (C/C of bearing) = 38.800 m
Clear carraige way width = 9.500 m
Depth of girder+deck slab at CL of carraigeway = 3.000 m
Thickness of Bituminus concrete Wearing Coat = 0.065 m
Thickness of cement concrete Wearing Coat = 0.075 m
b) Hydraulic and survey data :-
Lowest Bed Level, LBL 217.847 m
Max. scour level = 0.000 m ( Non seismic case)
b) Sub-structure :-
Bearing and pedestal :
Level of bearings (near to median)= 236.894 m.
Thickness of bearing = 0.300 m
Thickness of pedestal = 0.440 m
Maximum ht of bearing + pedestal = 0.740 m
c) Abutment cap :
Top of abutment Cap = 236.154 m
Bottom of Abutment cap = 235.154 m
Length of abutment Cap = 12.750 m
Thickness of abutment cap= 1 m
Width of abutment cap at top (including dirt wall part) = 2.070 m
Width of abutment cap at bottom = 2.070 m
abutment shaft :
Total length of abutment shaft = 12.50 m
Thickness of abutment wall = 1.200 m
Height of abutment wall = 1.700 m
Height of frame at abutment location = 3.440 m
Dirt wall :
Thikcness of Dirt wall = 0.400 m
Height of Dirt wall = 3.780 m
Length of dirt wall = 12.750 m
Return wall :
Width of return wall = (avg.) 0.500 m
Length of return wall = 4.500 m
Height of return wall = 4.000 m
Foundation and foundation Slab :
Thickness of foundation slab at abutment face= 1.500 m
Thickness of foundation slab at edge= 1.000 m
Length of foundation slab = 12.8 m
Width of foundation slab = 7.4 m
Bottom of foundation slab = 231.954 m
Top of foundation slab = 233.454 m
Approach Slab :
Length of approach slab = 3.500 m
Thickness of approach slab = 0.300 m (At mid-section)
Thickness of approach slab = 0.300 m (At edge)
d) Material Properties :
Grade of steel = Fe 500
Grade of Concrete = M 30
3
Unit Weight of concrete = 25 KN/m
3
Unit Weight of Cement concrete Wearing Coat = 25 KN/m
3
Unit Weight of Bituminus concrete Wearing Coat = 22 KN/m
173
e) Soil property:-
3
Density of soil = 18.00 KN/m
o
Angle of Shearing resistance of backfill soil = 30
Property of Backfill material behind Abutment and Return wall
o
= 30.00
o
= 20.00
o
= 0.00
o
= 0.00
3
= 18.00 KN/m
4.50
FRL = 240 m
1
3.780 0.55
4.00
1.0
2.07
1.2
1.700
CL of bearing
1.5
1
Bottom of foundation =231.954 m
7.40
Details of abutment
LOAD CALCULATIONS
Permanent Load :
Self Weight/Dead Load
174
= 3056 KN
Self weight of Fin wall = { 2 x 4.5m x 0.5m x 0.5 x (4 + )m x 25}= 450 KN
Line of action of load from center of abutment = -2.200 m
Line of action of load from center of foundation slab = -2.595 m
Backfill Weight
3.780
1.588
2
18.98 KN/m
2
Earth pressure at base due to backfill soil =0.279x18x3.78 = 18.98 KN/m
Total load on dirt wall = 457.37 KN
This load is located 0.42 of the height of wall above base,
Lever arm = 1.588 m…..(Clause 214.1,IRC:6-2014,page-41)
Moment at dirt wall base = 726.121 KN-m
6.48
2.722
2
32.543 KN/m
175
Calculation of moment due to earth pressure :-
2
Earth pressure at base due to backfill soil =0.279x18x6.48 = 32.543 KN/m
Horizontal force due to backfill earth = 1317.97 KN (Considering abutment bottom)
This load is located 0.42 of the height of wall above base,
Lever arm = 2.722 m…..(Clause 214.1,IRC:6-2014,page-41)
Acting at a ht of = 2.722 m ( from base of abutment )
2
Earth pressure at base due to backfill soil =0.279x18x7.98 = 40.076 KN/m
Horizontal force due to backfill earth = 1998.77 KN (Considering foundation slab bottom)
Acting at a ht of = 0.42 m of total height = 3.35 m ( from bottom of foundation slab level )
Total moment at the base of abutment due to earth pressure = 3587.00 KN-m
Total moment at the base of foundation slab due to earth pressure = 6699.0727 KN-m
So,on one abutment total surfacing load or load due to wearing coat = 393.42 KN
Vehicular Live Load
0.9 1.8
7.25 eT 5.25 m
176
Case - 2: Two Lane / One span loaded.
Minimum clearence = 1200 mm between two outer edges of vehicle.
CG of Load
1.85
0.5 0.4 1.7 2.85
1.8 -1.05
7.25 5.25
456
Maximum Reaction = 991.3 kN
And transverse eccentricity, wrt deck, eT = 1.85 m
And longitudinal eccentricity, wrt abutment, eL = -0.05 m
7.25 5.25
700
Maximum Reaction for 70R Tracked = Rb = 725.8 kN
Hence,Total Reaction Rb = 725.8 kN
177
3 Type of Loading = IRC 70 R Wheel + single lane Class A
A) One Span Loaded
Case - 1: 70 R Wheel + Class A
Span, Le = 38.8 m Minimum Clearence = 1200 mm
Lc = 1.08 m Width of ground contact = 860 mm
Expansion gap = 0.04 m Width of footpath with kerb & crash barrier = 2500 mm
Impact factor = 1.101 Width of carriageway = 9.5 m
7.25 5.25
340
max transverse eccentricity = eT = 4.16 m
4 Type of Loading = IRC Class SV Loading : Special Multi Axel Hydraulic Trailer Vehicle
(AMENDMENT TO IRC:6-2014, AMENDMENT NO.1_CLAUSE 204.5)
18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 9.5t 9.5t 6t
5.389 1.37 3.541 ####
Loading= 20 nos. of wheels each 180 KN @ c/c 1.5 m for 28.5 M Span.
so,(28.5/1.5+1)= 20
hence for, 39.88 m Sapn = 20
Left side of Ra 39.88 m Sapn = 20
178
Maximum reaction = Rb = 2299.06 kN
Hence,Total Reaction Rb = 2299.06 kN
max longitudinal eccentricity = eL = -0.050 m
0.30
Load due to
Load due to RA eL eT ML MT
CASE additional
main wheel (kN) (m) (m) (kN-m) (kN-m)
wheel
CLASS A
TWO LANE SINGLE SPAN
668 668 991.31 -0.050 1.850 -50 1833.915
70R TRACKED ONE LANE 700 0 725.817 -0.050 4.100 -36 2975.848
70R WHEELED ONE LANE &
CLASS A ONE LANE SINGLE 1000 0 986.252 -0.050 4.155 -49 4097.877
SPAN
IRC CLASS SV LOADING :
SPECIAL MULTI AXEL 3850 0 2299.057 -0.050 0.300 -115 689.717
HYDRAULIC TRAILER VEHICLE
Longitudinal Forces
Calculation of Braking Forces ……. (Ref. cl. 211 of IRC 6-2014, page-37)
179
Live load surcharge pressure is to be considered
2
Equivalent to 1.2 m height of soil = 6.03 KN/m …..(Clause 214.1,IRC:6-2010,page-37)
3.780
1.890
2
6.03 KN/m
3.241
6.03 KN/m2
180
b Wind force on live load:
as per clause 209.3.7 of IRC: 6, 2014, bridge shall not be
considered to carry any live load if the basic wind velocity exceeds 36m/sec.
c Wind force on Substructure:
Pier Cap Velocity Of Wind
i. Transverse wind force: Position Direction vert. comp. Hortz. Comp.
Exposed area = 2.07 m2 kN kN
Super
Transverse wind force = 5.7 kN structure Transverse 417.35 331.92
ii. Longitudinal Wind Force: Longitudinal 82.98
Exposed area = 12.8 m2
ACCIDENTAL ACTIONS
Seismic Hazards
181
B. Seismic on Sufacing:
Surfacing or load due to wearing coat taken by one abutment = 393.421 KN
C.G. of wearing coat from girder bottom = 3.038 m
Design Horizontal Seismic coefficient Ah = 0.18 kN
Seismic force in longitudinal direction Fh Ah x (Total Dead Load) = 70.816 KN
Seismic force in longitudinal direction taken by one support Fh = 70.816 KN ………r1
Acting at RL = 239.96 m
Lever arm for moment at bearing level = 3.038 m
Longitudinal moment at bearing level = 215.10 KN-m
Vertical pull-push effect due to Horizontal seismic force = 5.54 KN
Lever arm for moment at abutment base = 3.440 m
Longitudinal moment at abutment base = 243.61 KN-m ……..Mz
Horizontal seismic force in transeverse direction = Fh/2 = 35.408 KN ………..r2
Acting at RL = 239.96 m
Lever arm for moment at abutment base = 3.440 m
Transeverse moment at abutment base = 121.80 KN-m ……Mx
Vertical component of seismic force = 23.605 KN ……r3 (Clause 219.3, IRC:6-2014, page-47)
Combination of force components …….(Clause 219.4, IRC:6-2010, page-47)
Design force in longitudinal direction = ±r1±0.3r2±0.3r3 = 88.52 KN
Design force in transeverse direction = ±0.3r1±r2±0.3r3 = 63.73 KN
Design force in vertical direction = ±0.3r1±0.3r2±r3 = 55.47 KN
Design longitudinal moment = Mz+ 0.3Mx = 280.15 KN-m
Design transeverse moment = 0.3Mz+ Mx = 194.88 KN-m
Design longitudinal moment at bottom of foundation slab= Mz + 0.3Mx = 402.30 KN-m
Design transverse moment at bottom of foundation slab= 0.3Mz + Mx = 279.86 KN-m
182
Combination of force components …….(Clause 219.4, IRC:6-2014, page-52)
Design force in longitudinal direction = ±r1±0.3r2±0.3r3 = 178.155 KN
Design force in transeverse direction = ±0.3r1±r2±0.3r3 = 178.155 KN
Design force in vertical direction = ±0.3r1±0.3r2±r3 = 150.442 KN
Design longitudinal moment = Mz+ 0.3Mx = 339.682 KN-m
Design transeverse moment = 0.3Mz+ Mx = 339.682 KN-m
Design longitudinal moment at bottom of foundation slab= Mz + 0.3Mx = 571.284 KN-m
Design transverse moment at bottom of foundation slab= 0.3Mz + Mx = 571.284 KN-m
183
G. Seismic on carriageway live load …….(Clause 219.5.2, IRC:6-2014, page-55)
(Inertia loads due to mass of vehicular live load)
vertical
sl. No.
force
20% Reaction Ah Transverse Acting RL at Lever arm Transverse
moment at
(KN) seismic (+1.20) at Abutment Abutment
Live Load Case force base base
-1 o -1 o
= tan {Ah/(1+Av)}= 9.1302 = tan {Ah/(1-Av)} = 11.5601
2 2
cos ( - - ) = 0.8731 cos ( - - ) = 0.8999
cos( + + ) = 0.8735 cos( + + ) = 0.8521
cos( - ) = 1.0000 cos( - ) = 1.0000
cos = 0.9873 cos = 0.9797
2 2
cos = 1.0000 cos = 1.0000
sin( + ) = 0.7660 sin( + ) = 0.7660
sin( - - ) = 0.3562 sin( - - ) = 0.3163
Ca = 0.467 Ca = 0.404
Maximum of these two = 0.467 to be considered
3.780
1.588
12.76 KN/m2
Dynamic increment :
2
Earth pressure at base due to backfill = 12.76 KN/m
Horizontal force due to backfill soil = 307.48 KN
Acting at =3.78 x 0.42= 1.588 m
(Clause-8.1.1.2,IS:1893-1984,Page-47)
Bending moment increment for dynamic condition= 488.16 KNm
184
Considering Abutment Shaft
Height of the abutment=Height of abutment wall+Dirt wall= 6.471 m
Length of abutment wall = 12.50 m
Height from foundation slab bottom to deck level = 7.971 m
6.471
2.72
21.840 KN/m2
Dynamic increment
2
Earth pressure at abutment base due to backfill = 21.840 KN/m
Horizontal force increment due to backfill soil = 883.29 KN (For abutment shaft)
Acting at a ht. of = 2.72 m ( from base of abutment )
Horizontal force increment due to backfill soil = 1340.47 KN (from bottom of foundation slab)
Acting at a ht. of = 3.35 m ( from bottom of foundation slab level )
Total moment increment at the base of abutment due to Earth pressure = 2400.63 KN-m
Total moment increment at the base of foundation slab due to Earth pressure = 4487.67 KN-m
3.780
1.890
2
4.05 KN/m
Considering Abutment Shaft
Height of the abutment=Height of abutment wall+Dirt wall= 6.471 m
Length of abutment wall = 12.75 m
Height from foundation slab bottom to deck level = 7.971 m
Total horizontal force in longitudinal direction = 334.146 KN (For abutment)
Total horizontal force in longitudinal direction = 411.603 KN (For foundation slab bnase)
6.471
3.236
4.05 KN/m2
185
Load combination at abutment base:-
SL
NO LOAD DESCRIPTION V HL HT LA ML MT
A Permanent Action
i Dead load from super-structure 5425 -271.25
ii Self weight of dirt wall 481.95 -612.077
iii Self weight of abutment cap 659.81 -287.02
iv Self weight of abutment wall 637.50
v Self weight of return wall 450.0 -990.00
vi Earth Pressure due to back-Fill 1317.97 2.72 3587.00
B Variable gravity treated as Permanent
i Super Imposed Dead Load 703 -35.14
ii Surfacing 393.421 -19.67
D Variable Actions
Vehicular Live Load
i CLASS A-3 LANE 1SPAN 991.3 -49.57 1833.91
ii 70R TRACKED -1LANE+ CL-A 1L 1 SPAN 725.8 -36.29 2975.85
iii 70R WHEELED-1 LANE + CL-A 1L 1 SPAN 986.3 -49.31 4097.88
IRC Class SV Loading : Special Multi Axel Hydraulic
iv Trailer Vehicle-1 LANE 1 SPAN 2299.1 -114.95 689.72
i Longitudinal Forces (Braking)
i CLASS A-3 LANE 1SPAN 29.4 326.09 3.440 1121.75
iii 70R TRACKED -1LANE+ CL-A 1L 1 SPAN 15.4 254.52 3.440 875.56
v 70R WHEELED-1 LANE + CL-A 1L 1 SPAN 22.0 292.34 3.440 1005.64
IRC Class SV Loading : Special Multi Axel Hydraulic
iv Trailer Vehicle-1 LANE 1 SPAN 0.0 231.72 3.440 797.12
Earth Surcharge due to Live Load 488.21 3.24 1582.06
E Seismic Forces
Seismic forces for dead load
a) on superstructure 1728.02 2757.47 1985.38 8726.85 6070.85
b) Surfacing 55.47 88.52 63.73 280.15 194.88
c) on dirt wall 109.88 130.13 130.13 404.86 404.86
d) on abutment cap 150.44 178.16 178.16 339.68 339.68
e) on abutment wall 145.35 172.12 172.12 126.80 126.80
f) on return wall 102.60 121.50 121.50 544.58 544.58
vertical push-pull due to seismic at sup. 101.52
Seismic forces for Live Load
i CLASS A-3 LANE 1SPAN 21.6 32.41 7.75 251.07
iii 70R TRACKED -1LANE+ CL-A 1L 1 SPAN 15.8 23.75 7.75 184.00
v 70R WHEELED-1 LANE + CL-A 1L 1 SPAN 21.5 32.25 7.75 249.79
Wind Load
Wind Load on super-structure 417.35 82.98 331.92 3.27 271.59 1086.371
Increased Earth Pressure due to seismic 883.29 2.72 2400.63
Increased surcharge earth pressure due to
seismic 334.146 3.236 1081.13
186
Load combination at Bottom of foundation level (For open foundation) :-
SL
NO LOAD DESCRIPTION V HL HT LA ML MT
A Permanent Action
i Dead load from super-structure 5425.00 1763.125
ii Self weight of dirt wall 481.95 -479.540
iii Self weight of abutment cap 659.81 -105.57
iv Self weight of abutment wall 637.50 239.06
v Self weight of return wall 450.0 -1167.75
vi Self weight of foundation slab 3056.0
vii Back Fill weight on foundation slab 4304.5 -7317.60
viii Earth Pressure due to back-Fill 1998.77 3.35 6699.07
B Variable gravity treated as Permanent
i Super Imposed Dead Load 702.720 228.38
ii Surfacing 393.421 127.86
D Variable Actions
Vehicular Live Load
i CLASS A-3 LANE 1SPAN 900.37 292.62 1665.68
ii 70R TRACKED -1LANE+ CL-A 1L 1 SPAN 659.83 214.45 2705.32
iii 70R WHEELED-1 LANE + CL-A 1L 1 SPAN 895.78 291.13 3721.96
IRC Class SV Loading : Special Multi Axel Hydraulic
iv Trailer Vehicle-1 LANE 1 SPAN 2299.06 747.19 689.72
Longitudinal Forces (Braking)
i CLASS A-3 LANE 1SPAN 29.44 326.09 4.94 1610.88
ii 70R TRACKED -1LANE+ CL-A 1L 1 SPAN 15.43 254.52 4.94 1257.35
iii 70R WHEELED-1 LANE + CL-A 1L 1 SPAN 22.04 292.34 4.94 1444.15
IRC Class SV Loading : Special Multi Axel Hydraulic
iv Trailer Vehicle-1 LANE 1 SPAN 0.00 231.72 4.94 1144.71
Earth Surcharge due to Live Load 566.56 3.76 2130.54
E Seismic Forces
Seismic forces for dead load
a) on superstructure 2160.02 3446.84 2481.73 1.50 15665.21 10897.54
b) Surfacing 69.34 110.65 79.67 1.50 502.88 349.83
c) on dirt wall 137.35 162.66 162.66 1.50 717.53 717.53
d) on abutment cap 188.05 222.69 222.69 1.50 714.10 714.10
e) on abutment wall 181.69 215.16 215.16 1.50 438.20 438.20
f) on return wall 128.25 151.88 151.88 1.50 878.16 878.16
vertical push-pull due to seismic at sup. 126.89
Seismic forces for Live Load
i CLASS A-3 LANE 1SPAN 27.01 40.52 9.25 374.62
iii 70R TRACKED -1LANE+ CL-A 1L 1 SPAN 19.80 29.69 9.25 274.54
v 70R WHEELED-1 LANE + CL-A 1L 1 SPAN 26.87 40.31 9.25 372.71
Wind Load
Wind Load on super-structure 417.35 82.98 331.92 4.77 396.06 1584.25
Increased Earth Pressure due to seismic 1675.592 3.35 5609.58
Increased surcharge earth pressure seismic 514.503 3.99 2050.55
187
LOAD COMBINATION FOR PIER SHAFT BASE (For Ultimate Limit State)
Loads V ML MT HL HT
Dead Load 7654.26 -2160.34 0.00 0.00 0.00
SIDL 702.72 -35.14 0.00 0.00 0.00
Surfacing 393.42 -19.67 0.00 0.00 0.00
Class A(3L/1S) LL1 991.31 -49.57 1833.91 0.00 0.00
70R Tr.1L+CL-A 1L(1S) LL2 725.82 -36.29 2975.85 0.00 0.00
70R Wh.1L+CL-A 1L(1S) LL3 986.25 -49.31 4097.88 0.00 0.00
Class SV LL4 2299.06 -114.95 689.72 0.00 0.00
BrakingClass A(3L/1S) LL1 29.44 1121.75 0.00 326.09 0.00
Braking70R Tr.1L+CL-A
0.00 0.00
1L(1S) LL2 15.43 875.56 254.52
Braking70R Wh.1L+CL-A
1L(1S) LL3 22.04 1005.64 0.00 292.34 0.00
NON-SEISMIC CASE
B WIND
A DL+SIDL+Surfacing+LL+Br. LL+EP+EP LL DL+SIDL+Surfacing+LL+Br. LL+EP+EP DL+/-WL
Loads FOS Loads FOS
Dead Load 1.00 Dead Load 1.00
SIDL 1.00 SIDL 1.00
Surfacing 1.00 Surfacing 1.00
LL 1.50 LL 1.50
Braking LL 1.15 Braking LL 1.15
EP 1.50 EP 1.50
EP LL surcharge 1.20 EP LL surcharge 1.20
WL 1.50
SEISMIC CASE
A C
DL+SIDL+Surfacing+LL+Br. LL+EP+EP LL+DL S+LL S+EP S+EP LL S DL+SIDL+Surfacing+EP+DL seis+EP seis
Loads FOS Loads FOS
Dead Load 1 Dead Load 1.00
SIDL 1 SIDL 1.00
Surfacing 1 Surfacing 1.00
LL 0.2 EP 1.00
Braking LL 0.2 DL sis 1.50
EP 1 EP seis 1.50
EP LL surcharge 0.2
DL sis 1.5
LL sis 1.5
EP LL sis 1.5
EP sis 1.5
188
Vu MLu MTu HLu Htu
1 DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge 10271.22 6279.47 2750.87 2937.82 0.00
2 DL+SIDL+Surfacing+LL2+Br. LL2+EP+EP LL Surcharge 9856.87 6016.27 4463.77 2855.52 0.00
3 DL+SIDL+Surfacing+LL3+Br. LL3+EP+EP LL Surcharge 10255.12 6146.33 6146.82 2899.01 0.00
NON SEISMIC
4 DL+SIDL+Surfacing+LL4+Br. LL4+EP+EP LL Surcharge 12198.99 5808.07 1034.58 2829.30 0.00
5 DL+SIDL+Surfacing+LL4+EP+EP LL Surcharge 12198.99 4891.38 1034.58 2562.82 0.00
6 DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge+WL 10897.25 6686.86 4380.43 3062.29 497.88
7 DL+SIDL+Surfacing+LL2+Br. LL2+EP+EP LL Surcharge+WL 10482.90 6423.66 6093.33 2979.99 497.88
8 DL+SIDL+Surfacing+LL3+Br. LL3+EP+EP LL Surcharge+WL 10881.15 6553.72 7776.37 3023.47 497.88
9 DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge-WL 9645.19 5872.08 1121.31 2813.35 -497.88
10 DL+SIDL+Surfacing+LL2+Br. LL2+EP+EP LL Surcharge-WL 9230.84 5608.89 2834.22 2731.05 -497.88
11 DL+SIDL+Surfacing+LL3+Br. LL3+EP+EP LL Surcharge-WL 9629.09 5738.94 4517.26 2774.54 -497.88
DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge+DL S+LL1 S+EP
12 S+EP LL Surcharge 12544.47 22759.71 366.78 8478.84 0.00
SEISMIC
189
LOAD COMBINATION FOR ABUTMENT SHAFT BASE (For Servicibility Limit State)
Loads V ML MT HL HT
Dead Load 7654.26 -2160.34 0.00 0.00 0.00
SIDL 702.72 -35.14 0.00 0.00 0.00
Surfacing 393.42 -19.67 0.00 0.00 0.00
Class A(3L/1S) LL1 991.31 -49.57 1833.91 0.00 0.00
725.82 -36.29 2975.85 0.00 0.00
70R Tr.1L+CL-A 1L(1S) LL2
70R Wh.1L+CL-A 1L(1S) 986.25 -49.31 4097.88 0.00 0.00
LL3
Class SV LL4 2299.06 -114.95 689.72 0.00 0.00
BrakingClass A(3L/1S) LL1 29.44 1121.75 0.00 326.09 0.00
Braking70R Tr.1L+CL-A
15.43 875.56 0.00 254.52 0.00
1L(1S) LL2
Braking70R Wh.1L+CL-A
22.04 1005.64 0.00 292.34 0.00
1L(1S) LL3
0.00 797.12 0.00 231.72 0.00
Friction Class SV LL4
Earth Pressure 0.00 3587.00 0.00 1317.97 0.00
LL surcharge on Earth Pr. 0.00 1582.06 0.00 488.21 0.00
Dead Load Seismic 2393.28 10422.92 7681.66 3447.90 2651.02
Seismic Class A(3L/1S) LL1 21.61 0.00 251.07 0.00 32.41
NON-SEISMIC CASE
B WIND
A DL+SIDL+Surfacing+LL+Br. LL+EP+EP LL DL+SIDL+Surfacing+LL+Br. LL+EP+EP DL+/-WL
Loads FOS Loads FOS
Dead Load 1.00 Dead Load 1.00
SIDL 1.00 SIDL 1.00
Surfacing 1.00 Surfacing 1.00
LL 1.00 LL 1.00
Braking LL 1.00 Braking LL 1.00
EP 1.00 EP 1.00
EP LL surcharge 0.80 EP LL surcharge 0.80
WL 1.00
190
ABUTMENT SHAFT DESIGN
Grade of concrete : M 30
Grade of steel = Fe 500
Ecm of concrete = 31000 N/mm2 (From table 6.5, IRC:112-2011, page no. 38)
Es of steel = 200000 N/mm2 (From clause6.3.5, IRC:112-2011, page no. 32)
Checking as wall:
Ref. Cl-7.6.4.1, IRC-112:2011
0.1.fcd.Ac= 20100 kN
Maximum Design verical Load= 12544.47 kN
The section is to be designed for pure bending element also.
Checking for pure Bending:
Design moment = 22759.71 KN-m
Width of section = 12.50 m
Depth of section = 1.2 m
Concrete failure strain = εcu1 = 0.0035 (Table 6.5, IRC:112-2011, page-38)
Concrete limiting strain = εc2 = 0.002 (Table 6.5, IRC:112-2011, page-38)
Yield strain of steel = 0.87fy/Es = 0.00218
Limiting strain of steel = (0.87fy/Es+0.002) = 0.00418
191
Slenderness criteria check:
Clear height of Abutment shaft = 1.700 m (upto abutment cap top)
Effective length, l e = 1.3l 0 = 2.21 m (Table 11.1, case-4, IRC:112-2011, page-114)
As the ratio does not exceed 12, it is short and no secondary effect to be considered
(clause 7.6.4, IRC:112-2011, page-57)
192
Interaction check
Grade of concrete = M 30
Grade of steel = Fe 500
Width of section considered = 1m
193
Total reinforcement provided = 3291 mm2
Effective depth "d" = 1137.5 mm
Netral axis depth = x = 132.54 mm
CG of compressive force = 55.140 mm from most compressed surface
Moment , Mu =σst*Ast*(d-0.416*xu) = 1549.3333 OK
Now,
(Eq. 12.6, IRC:112-2011, page-125)
Where, sc = stress in the tension reinforcement = 89.42 Mpa
e = Es/Ecm = 6.4516
fct.eff = mean value of tensile strength of concrete = 2.5 Mpa
.eff = As/Ac.eff Where, Ac.eff = Effective area of concrete in tension, surrounding
the reinforcement of depth h c.eff
Where, hc.eff = lesser of the followings
2.5(h-d);(h-x/3);or h/2
Where, A = level of steel centroid
B = Effective tension area, Ac.eff
x
1,2 = greater and lesser tensile strain
h
d
hc.eff
B
So, hc.eff = 156.25 mm
2
Ac.eff = 156250 mm
Now. eff = As/Ac.eff = 0.0210602
kt = factor dependant on duration of the load may be taken as 0.5
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+ /2)), the maximum crack spacing,
194
p
D. LOAD COMBINATION FOR ABUTMENT FOUNDATION BASE (Ultimate Limit State)
Loads V ML MT HL HT
Dead Load 10710.26 -7068.27 0.00 0.00 0.00
Backfill weight 4304.47 0.00 0.00 0.00 0.00
SIDL 702.72 228.38 0.00 0.00 0.00
Surfacing 393.4208 127.86 0.00 0.00 0.00
Class A(3L/1S) LL1 900.37 292.62 1665.68 0.00 0.00
NON-SEISMIC CASE
195
N COMB V ML MT HL HT
O 1 DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge 23937.13 5886.60 2498.52 4053.02 0.00
N 2 DL+SIDL+Surfacing+LL2+Br. LL2+EP+EP LL Surcharge 23560.21 5362.78 4057.98 3970.72 0.00
3 DL+SIDL+Surfacing+LL3+Br. LL3+EP+EP LL Surcharge 23921.73 5692.62 5582.94 4014.21 0.00
S 4 DL+SIDL+Surfacing+LL4+EP+EP LL Surcharge 26001.30 4715.95 1034.58 3678.02 0.00
E 5 DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge+WL 24563.16 6480.70 4874.90 4177.49 497.88
I 6 DL+SIDL+Surfacing+LL2+Br. LL2+EP+EP LL Surcharge+WL 24186.24 5956.88 6434.35 4095.19 497.88
S 7 DL+SIDL+Surfacing+LL3+Br. LL3+EP+EP LL Surcharge+WL 24547.76 6286.72 7959.31 4138.68 497.88
M 8 DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge-WL 23311.10 5292.51 122.15 3928.55 -497.88
I 9 DL+SIDL+Surfacing+LL2+Br. LL2+EP+EP LL Surcharge-WL 22934.18 4768.69 1681.60 3846.25 -497.88
C 10 DL+SIDL+Surfacing+LL3+Br. LL3+EP+EP LL Surcharge-WL 23295.70 5098.53 3206.56 3889.74 -497.88
DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge+DL S+LL1 S+EP
S 11 S+EP LL Surcharge 19123.60 26667.20 0.00 8546.8309 0.00
E
I
DL+SIDL+Surfacing+LL2+Br. LL2+EP+EP LL Surcharge+DL S+LL2 S+EP
S 12 S+EP LL Surcharge 19119.18 26737.90 0.00 8561.14 0.00
M DL+SIDL+Surfacing+LL3+Br. LL3+EP+EP LL Surcharge+DL S+LL3 S+EP
I
C
13 S+EP LL Surcharge 19124.94 26701 0.00 8553.58 0.00
14 DL+SIDL+Surfacing+EP+DL seis+EP seis 19102.47 24512.71 0.00 7984.23 0.00
196
H. LOAD COMBINATION FOR ABUTMENT FOUNDATION BASE (Servicebility Limit State)
Loads V ML MT HL HT
Dead Load 10710.26 -7068.27 0.00 0.00 0.00
Backfill weight 4304.47 0.00 0.00 0.00 0.00
SIDL 702.72 228.38 0.00 0.00 0.00
Surfacing 393.42 127.86 0.00 0.00 0.00
Class A(3L/1S) LL1 900.37 292.62 1665.68 0.00 0.00
70R Tr.1L+CL-A 1L(1S) LL2 659.83 214.45 2705.32 0.00 0.00
NON-SEISMIC CASE
COMB V ML MT HL HT
1 DL+SIDL+Surfacing+LL1+Br. LL1+EP+EP LL Surcharge 17033.32 3618.36 1665.68 2809.89 0.00
2 DL+SIDL+Surfacing+LL2+Br. LL2+EP+EP LL Surcharge 16782.28 3275.04 2705.32 2756.22 0.00
3 DL+SIDL+Surfacing+LL3+Br. LL3+EP+EP LL Surcharge 17023.18 3491.82 3721.96 2784.58 0.00
NON SEISMIC
197
CHECK FOR STABILITY
1.2
1.5
1
A B
3.4 1.2 2.8
OVERTURNING CHECK
Non-Seismic
Overturning Restoring
Loads V ML LA
moment moment
Dead Load 10710.26 -7068.27 0.00 3.4 36414.893
Earth weight 4304.47 0.00 0.00 5.7 24535.485
SIDL 702.72 228.38 0.00 3.4 2389.248
Surfacing 393.42 127.86 0.00 3.4 1337.631
Class A(3L/1S) LL1 900.37 292.62 0.00 3.4 3061.251
Braking Class A(3L/1S) LL1 29.44 1610.88 1610.88
3.4 100.097
Earth pressure 0.00 6699.07 6699.07 0 0.000
Earth pressure LL Surcharge 0.00 2130.54 2130.54 0 0.000
Total 10440.49 67838.60
Overturning Restoring
Loads V ML LA
moment moment
Dead Load 10710.26 -7068.27 0.00 3.4 36414.89
Earth weight 4304.47 0.00 0.00 5.7 24535.48
SIDL 702.72 228.38 0.00 3.4 2389.25
Surfacing 393.42 127.86 0.00 3.4 1337.63
Class A(3L/1S) LL1 180.07 292.62 292.62 3.4 612.25
5.89 322.18 322.18
Braking Class A(3L/1S) LL1 3.4 20.02
Earth Pressure 0.00 6699.07 6699.07 0 0.00
LL Surcharge earth pressure 0.00 2130.54 2130.54 0 0.00
Dead Load Seismic 2991.60 18916.09 18916.09 3.4 10171.44
Increased earth due to seismic 0.00 7660.13 7660.13 0 0.00
Total 36020.63 75480.965
198
SLIDING CHECK
Considering frictional co-efficient; m = 0.70
Non-Seismic
Restoring
Loads V HL Sliding force
force
Dead Load 10710.26 0.00 0.000 7497.184
Earth weight 4304.47 0.00 0.000 3013.130
SIDL 702.72 0.00 0.000 491.904
Surfacing 393.42 0.00 0.000 275.395
Class A(3L/1S) LL1 900.37 0.00 0.000 630.258
29.44 326.09
Braking Class A(3L/1S) LL1 326.089 20.608
Earth pressure 0.00 1998.77 1998.769 0.000
Earth pressure LL Surcharge 0.00 566.56 566.557 0.000
Total 2891.415 11928.478
Seismic
Restoring
Loads V HL Sliding force
force
Dead Load 10710.26 0.00 0.00 7497.184
Earth weight 4304.47 0.00 0.00 3013.130
SIDL 702.72 0.00 0.00 491.904
Surfacing 393.42 0.00 0.00 275.395
Class A(3L/1S) LL1 180.07 0.00 0.00 126.052
5.89 65.22 65.22
Braking Class A(3L/1S) LL1 4.122
Earth pressure 0.00 1998.77 1998.77 0.000
Earth pressure LL Surcharge 0.00 566.56 566.56 0.000
Dead Load Seismic 2991.60 4309.87 4309.87 2094.120
Increased earth due to seismic 0.00 2190.10 2190.10 0.000
Total 9130.512 13501.905
199
CHECK FOR BASE PRESSURE
D L A
12.8 T
C 7.4 B
200
Base pressure calculation
Base
Base pressure Base Base
Load V Net ML MT
pressure (Corner pressure pressure Remarks
Case
(Corner A) B) (Corner C) (Corner D)
2 2 2 2
KN KN-m KN-m KN/m KN/m KN/m KN/m
MLmax 1 17458.04 65175.985 3249.93 195.420 163.253 173.204 205.371
Considering Wind
Vmax 2 18827.28 69774.568 2273.97 209.049 186.542 188.487 210.994
MLmax 3 17040.68 64173.911 1665.68 178.533 162.046 181.279 197.765
Normal Case
Vmax 4 18409.93 67627.790 689.72 201.960 195.134 186.763 193.589
Unloaded (Non-
MLmax 5 16110.87 62962.554 0.000 141.393 141.393 198.786 198.786
seismic)
2
Maximum base pressure = 210.994 KN/m
Allowable base pressure = 230 KN/m2 OK
Minimum base pressure = 141.393 KN/m2 OK, No tension developed
201
G. DESIGN OF FOUNDATION BY BENDING ANALOGY (ULS)
ML
C 2.80 D
1.988 1.413 1.388
B
A
MT
12.8
A B
C D
7.4
1.5 1
A B
3.40 1.2
Resistive Resultant
Overturning
Moment Net Moment reaction Eccentricity
COMB V Moment ML
WRT point B (MR-MO) from B; x = (e ) = b/2-x Base Base
(MO) pressure pressure
(MR) (MR-MO)/V
(Toe side) (Heel side)
KN KN-m KN-m KN-m m m KN/m2 KN/m2
12 19119.18 81093.331 26737.90 54355.430 2.843 0.857 342.111 61.588
4 26001.30 104492.540 4715.951 99776.589 3.837 -0.137 243.932 305.082
14 19102.47 81036.517 24512.712 56523.806 2.959 0.741 322.844 80.502
202
61.588 190.477 235.967 342.111
Grade of concrete = M 30
Grade of steel = Fe 500
Width of section considered = 1m
203
CHECK FOR SHEAR IN FOUNDATION TOE SIDE (Clause 10.3.2, IRC:112-2011, page-88)
2.8
1.5
1.3875
The design shear resistance of the member without shear reinforcement, VRd.c =
=[0.12K(80 1.fck)0.33+0.15 cp]bw.d
Where, K = 1+√(200/d)<=2.0
So, K = 1.376
1 = Asl/bw.d
2
Where Asl = Area of steel provided = 4416 mm
bw = Width of section = 1000 mm
d= 1160 mm
1= 0.0038
cp = NEd/Ac < 0.2fcd, where, NEd = Axial compressive force = 0
Ac = Cross Sectional area of concrete
cp = 0
So,VRd.c = 397.55 KN
204
Calculation of shear reinforcement:
αcw= 1 for σ cp =0, Ref: Eq-10.9, 1.00
b(mm)= IRC-112:2011 1000
z(mm)= 0.9*d for RCC 900.00
v1= for fck<80MPa 0.60
fcd= Design value of concrete 0.67*fck/γm 13.40
Value of θ° = 45.0
tanθ= 1.00
cotθ= 1.00
Vrd.min= 3618.00
205
CHECK FOR SHEAR IN FOUNDATION HEEL SIDE (Clause 10.3.2, IRC:112-2011, page-88)
3.4
1.4125
206
Where, K = 1+√(200/d)<=2.0
So, K = 1.407
1 = A /b
sl w .d
2
Where Asl = Area of steel provided = 3925 mm
bw = Width of section = 1000 mm
d= 1204.5 mm
1= 0.0033
cp = NEd/Ac < 0.2fcd, where, NEd = Axial compressive force = 0
Ac = Cross Sectional area of concrete
cp = 0
So,VRd.c = 401.05 KN
As the basic control perimeter is exceeding the foundation dimension, we will check the
punching shear at reduced control perimeter.
b
207
a= 12.8 m
b= 6.85 m OK, Shear check at basic control perimeter
Now, = 1+1.8√((el/a)2+(et/b)2) ( = Factors accounting for effects of bending
= 1.255 moment and axial load acting on loaded area)
Now, reduced control perimeter, u = 48.2 m
So, total load for punching shear = Load from abutment shaft+ Wt. within reduced control perimeter
VEd = 15284.4723 KN
Shear stress, ƬEd = VEd/ud = 0.343 Mpa
a= 12.80 m
b= 1.2 m
Now, = 1+1.8√((el/a)2+(et/b)2) ( = Factors accounting for effects of bending
= 1.259 moment and axial load acting on loaded area)
Now, reduced control perimeter, u = 28.000 m
So, total load for punching shear = Load from abutment shaft
VEd = 12544.47 KN
Shear stress,ƬEd = VEd/ud = 0.486 Mpa
208
I. DESIGN OF FOUNDATION (SLS)
COMB LOAD CASE Vu (KN) MLu (KN-m) MTu (KN-m) HLu (KN) HTu(KN)
ML D
1.9875 C A B 1.4125 1.3875
12.800
MT
A B
C D
7.4
3.40 1.2 2.80
1.5
1
209
Resistive Resultant
Overturnin Base Base
Moment Net Moment reaction Eccentricity
COMB V g Moment pressure pressure
WRT point B (MR-MO) from B; x = (e ) = b/2-x
ML (MO) (Toe side) (Heel side)
(MR) (MR-MO)/V
Grade of concrete = M 30
Grade of steel = Fe 500
Width of section considered = 1m
210
Maximum allowable stress in concrete = 0.48fck = 14.4 Mpa
(Clause 12.2.1(1), IRC:112-2011, page-120)
Maximum allowable stress in steel = 0.8fyk = 400 Mpa
(Clause 12.2.2, IRC:112-2011, page-120)
2
Total reinforcement provided = 4416 mm
Effective depth "d" = 1412.5 mm
Netral axis depth = x = 302.48
CG of compressive force = 100.826 mm from most compressed surface
Now moment, M = (Stress in steel)x(area of steel)x(d-CG of compressive force) =
Now,
hc.eff
1
B
211
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+ /2)), the maximum crack spacing,
2
Total reinforcement provided = 3925 mm
Effective depth "d" = 1412.5 mm
Netral axis depth = x = 287.14 mm
CG of compressive force = 95.714 mm from most compressed surface
Now moment, M = (Stress in steel)x(area of steel)x(d-CG of compressive force) =
212
Crack width check:
Now,
hc.eff
1 B
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+ /2)), the maximum crack spacing,
213
.
214
215
216
mm
217
mm
218
Design of dirt wall
Grade of concrete = M 30
Grade of steel = Fe 500
Width of section considered = 1m
Where, K = 1+√(200/d)<=2.0
So, K = 1.767
r1 = Asl/bw.d
219
2
Where Asl = Area of steel provided = 2512 mm
bw = Width of section = 1000 mm
d= 340 mm
r1 = 0.0074
scp = NEd/Ac < 0.2fcd, where, NEd = Axial compressive force = 0
Ac = Cross Sectional area of concrete
scp = 0
So,VRd.c = 186.20 KN
2
Total reinforcement provided = 2512 mm
Effective depth "d" = 340 mm
Netral axis depth = x = 104.98 mm
CG of compressive force = 34.993 mm from most compressed surface
Now moment, M = (Stress in steel)x(area of steel)x(d-CG of compressive force) =
Now,
220
rr.eff = As/Ac.eff Where, Ac.eff = Effective area of concrete in tension, surrounding
the reinforcement of depth h c.eff
Where, hc.eff = lesser of the followings
2.5(h-d);(h-x/3);or h/2
hc.eff
1 B
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+φ/2)), the maximum crack spacing,
221
DESIGN OF FINN
Moment Calculation of Fly wing wall taking 1m strip 2m below the top
Earth pressure at 1 m below the wall from top = 5.022 KN/m2
Surcharge earth pressure equivalent to earth pressure of 1.2 m height = 6.026 KN/m2
Bending moment at wall junction due to earth pressure, M1 = 50.848 KN-m
Bending moment at wall junction due to surcharge earth pressure, M 2 = 61.017 KN-m
Design moment at junction, Mu = 1.5M1+1.2M2 = 149.492 KN-m
Design shear force at junction, Fu = 1.5F1+1.2F2 = 66.441 KN
Design of Finn in flexure
4.5
1.0
4.5 m
4.0
Slope 1 : 1.5
0.5 m
Grade of concrete = M 30
Grade of steel = Fe 500
Width of section considered = 1m
222
Section is checked for ULS
Design moment = 369.833 KN-m (for 1m width)
Width of section = 1 m
Depth of section = 0.5 m
"E" value of steel = 200000 Mpa
"E" value of concrete = 32000 Mpa
Design compressive strength of concrete =
fcd= fck/ m = 13.40 Mpa Where, = 0.67
m = 1.5
Design peak strength of steel = fy/ s = 434.783 Mpa Where, s = 1.15
Concrete failure strain = cu1 = 0.0035 (Table 6.5, IRC:112-2011, page-38)
Concrete limiting strain = c2 = 0.002 (Table 6.5, IRC:112-2011, page-38)
Yield strain of steel = 0.87fy/Es = 0.00218
Limiting strain of steel = (0.87fy/Es+0.002) = 0.00418
223
CHECK FOR SHEAR IN FINN (Clause 10.3.2, IRC:112-2011, page-88)
The design shear resistance of the member without shear reinforcement, V Rd.c =
=[0.12K(80 1.fck)0.33+0.15 cp]bw.d
Where, K = 1+√(200/d)<=2.0
So, K = 1.674
1 = A /b
sl w .d
2
Where Asl = Area of steel provided = 2826 mm
bw = Width of section = 1000 mm
d= 440 mm
1= 0.0064
cp = NEd/Ac < 0.2fcd, where, NEd = Axial compressive force = 0
Ac = Cross Sectional area of concrete
cp = 0
So,VRd.c = 218.00 KN
224
Total reinforcement provided = 2826 mm2
Effective depth "d" = 440 mm
Netral axis depth = x = 128.24 mm
CG of compressive force = 42.747 mm from most compressed surface
Now moment, M = (Stress in steel)x(area of steel)x(d-CG of compressive force) =
Now,
2=0 x
Where, A = level of steel centroid
B = Effective tension area, Ac.eff
h
1,2 = greater and lesser tensile strain
d
A
hc.eff
1
B
225
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+ /2)), the maximum crack spacing,
226
Summarized Reinforcement Detailing
(According to chapter 16, IRC:112-2011, page-171)
ABUTMENT SHAFT
2
Total vertical reinforcement provided = 7301 mm
2
Concrete area, Ac = 1200000 mm
2
Now, 0.0024Ac = 2880 mm < steel provided, OK
2
and 0.04Ac = 48000 mm >steel provided, OK
227
FOUNDATION SLAB
Reinforcement of toe slab
Main reinforcement provided 25 mm dia. 125 mm c/c
2
Steel in 1m strip = 3925 mm
2
As.min =( 0.26fctm/fyk)btd= 1836.25 mm OK
2
or, 0.0013btd = 1836.25 mm OK
Reinforcement of heel slab
Main reinforcement provided 25 mm dia. 125 mm c/c
2
Steel in 1m strip = 3925 mm
2
As.min =( 0.26fctm/fyk)btd= 1836.25 mm OK
2
or, 0.0013btd = 1836.25 mm OK
Calculation of distrubution reinforcement
Top bar at toe slab 16 mm dia. 150 mm c/c
2
Steel in 1m strip = 1339.73333 mm OK
25% of main steel = 981.25
Bottom bar at heel slab 16 mm dia. 150 mm c/c
2
Steel in 1m strip = 1339.73333 mm OK
25% of main steel = 981.25
Transverse reinforcement provided at bottom and at top
16 mm dia. 150 mm c/c
2
Steel in 1m strip = 1339.73333 mm
OK
Provide surface reinforcement 16 mm dia. 4 Nos. each face
FINN WALL
Main reinforcement provided 20 mm dia. 125 mm c/c
Distributor reinforcement 12 mm dia. 125 mm c/c
OK
DIRT WALL
Provide main reinforcement 20 mm dia. 125 mm c/c
Distributor reinforcement 12 mm dia. 125 mm c/c
OK
228
PIER DESIGN
CHAINAGE -95.500 KM
3X41.0 PSC T-GIRDER
IRANG RIVER
229
ANALYSIS OF PIER
a) Superstructure:- FRL=240 m
At the proposed Bridge Site, the following data are available;
a) High Flood Level, HFL = 223.358 m
b) Lowest Bed Level, LBL = 218.500 m
At Pier Locations
Max. Scour Level = 207.948 m
Formation level = = 240.000 m
R.L. of carriageway at end of carriageway = 239.763 m
Depth of girder+deck slab at CL of carraigeway = 3.016 m
Thickness of cement concrete Wearing Coat = 0.065 m
b) Substructure:-
Pier
Level of bearings (near to median)= = 236.894 m
Height fo bearing= = 0.300 m
Height of pedestal= = 0.440 m
Top of Pier cap level = 236.154 m
Hence, 236.894 - 217.904 = 18.990 m
Height of frame at Pier locations = 18.990 m
Height of Pier with cap = 18.250 m Pile cap
Height of Pier shaft = 16.250 m
c) Foundation:-
E.G.L. at Pier = 220.298 m
The lowest E.G.L. at Pier = 220.298 m
Bottom pile cap at = 215.904 m
Height of pile cap = 2.000 m
Top of pile cap level = 217.904 m
LOAD CALCULATIONS
PERMANENT ACTIONS
Self Weight/Dead Load
Wt. of deck with girder = 10806.525 kN Weight of pier cap = = 1761.50 kN
Dead Load from super-structure = 10806.525 kN Weight of pier (Circular part) = = 1544.29 kN
Weight of pier (Straight part) = = 7150.00 kN
Total weight of pier = 8694.29 kN
Total weight of pile cap = = 10269.00 kN
VARIABLE ACTIONS
Vehicular Live Load
230
1 Type of Loading = Class A train of vehicle.
A) One Span Loaded
Span, Le = 38.80 m Case - 1: One Lane / one span loaded.
Lc = 1.08 m Minimum Clearence = 150 mm
Expansion gap = 0.04 m Width of ground contact (In transverse direction) = 500 mm
Impact Factor = 1.101 Width of Footpath with crush barrier & kerb = 2500 mm
Width of carriageway = 9.50 m
Width of Footpath(only) = 500 mm
114 114 68 68 68 68 27 27 114
1.2 4.3 3 3 3 20 1.08
1.1 3.2
7.25 eT 5.25
7.25 5.25
456
Maximum Reaction = 991.3 kN
And transverse eccentricity, wrt deck, eT = 1.70 m
And longitudinal eccentricity, wrt abutment, eL = 1.1 m
CG of load = 40.71 m
68 68 27
68 68 27 114 114 68 68 68 68 27 27 114 114 68
2.2 3.0 3.0 20 1.1 3.2 2.10 3.0 3.0 3.0 20 1.1 3.2 1.2
3.0 1.2 4.3 0.0
1176
CG calculation of load:
Taking moment with respect to the left most load, CG of load = 40.71 m
With above consideration, x = 6.21 m
Similarly, we have y = 1.91 m
In order to get the maximum pier reaction, we have place the loads in such a manner so that
the CG of the load passes through the centre line of the pier.
231
68 68 27 68 68 68
68 27 114 114 1.09 68 27 27 114 114 68 68
2.2 3.0 20 3.2 0.81 3.0 3.0 20 1.1 3.2 1.2 4.3 3.01 -0.006
3.0 1.1 1.2 4.3 1.91
1.10
7.25 5.25
700
Maximum Reaction for 70R Tracked = Rb = 725.8 kN
Hence,Total Reaction Rb = 725.8 kN
232
153.17 kN/m
4.57
7.25 5.25
340
max transverse eccentricity = eT = 2.155 m
2000
CG calculation of load: 2.7
Taking moment with respect to the left most load, CG of load = 29.98 m
With above consideration, x = 2.68 m
Similarly, we have y = 0.48 m
233
29.98 170
80 120 120 170 170 170 80 120 120 170 170 170 170
9.92 3.96 2.13 1.37 3.05 1.37 16.58 13.42 3.96 2.13 1.37 3.05 1.37
1.52 15.48 12.32 1.52
4 Type of Loading = IRC Class SV Loading : Special Multi Axel Hydraulic Trailer Vehicle
(AMENDMENT TO IRC:6-2014, AMENDMENT NO.1_CLAUSE 204.5)
18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 9.5t 9.5t 6t
5.389 1.37 3.541 -0.341
Loading= 20 nos. of wheels each 180 KN @ c/c 1.5 m for 28.5 M Span.
so,(28.5/1.5+1)= 20
hence for, 40.96 m Sapn = 20 no. of wheels
18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 18t 9.5t 9.5t 6t
5.389 1.37 3.2 15.341
1.080
38.8 2.20 38.8 1.08
Rb Ra Rc Rd
Loading= 20 nos. of wheels each 180 KN @ c/c 1.5 m for 28.5 M Span.
so,(28.5/1.5+1)= 20
Total loading = 3600 KN
Spacing of loads= 1.5 m centre to centre
No. of wheels per span = 10 ( for maximum reaction)
Maximum reaction = Rc = 1604.7 kN
Ra = 280.7 kN
Total = 1885.4 kN
Hence,Total Reaction Rb = 1885.4 kN
max longitudinal eccentricity = eL = 0.77 m
0.3
0.403
0.244 0.506 0.244
7.25 5.25
234
CWLL Load on Pier
1 2 3 4 5 6 7 8 9 10
(col 4 x col 6) (col 4 x col 8) +
Class A 70R SV Class A 70R SV + (col 5 x col (col 5 x col 8)
For Class-A 7)
1 One lane / one span loaded 668 0 495.65 1.10 3.450 545.22 1710.00
2 Two lane / one span loaded 1336 0 991.31 1.10 1.700 1090.44 1685.22
3 One lane / Both span loaded 1176 0 644.55 0.13 3.450 86.39 2223.70
4 Two lane / Both span loaded 2352 0 1289.10 0.13 1.700 172.78 2191.47
For IRC class 70R Tracked
5 One span loaded 700 0 725.82 1.100 2.100 798.40 1524.22
6 Both span loaded 700 0 769.16 0.000 2.100 0.00 1615.23
For IRC class 70R Wheeled
7 One span loaded 1000 0 986.25 1.100 2.155 1084.88 2125.37
8 Both span loaded 1000 0 1101.00 0.068 2.155 74.91 2372.66
For IRC SV
9 One lane / one span loaded 3850 0 2299.06 1.10 0.300 2528.96 689.72
10 One lane / Both span loaded 3850 0 1885.40 0.77 0.300 1456.46 565.62
Longitudinal forces
1 Calculation of Braking Forces
Caused by braking of vehicles ……. (Ref. cl. 211 of IRC 6-2014, page-37)
Case - I Case - II Case - III Case - IV Case - V Case - VI Case - VII Case - VIII
Braking force line of action
70R Wh. 70R Wh.
Class A - 70R Tr. - 70R Tr.- Load - - Two SV One
Class A - two SV One
Two lane / Two Lane , two lane / Two lane / lane /
1.2m Lane both lane / Both
one span one span Both span Lane , Both one span
span loaded span loaded
loaded loaded loaded one span span loaded
loaded loaded
a Total Load kN = 1336 2352 700 700 1000 1000 3850 3850
b Braking force Fh kN = 267.2 470.4 140.0 140.0 200.0 200.0 0 0
c Each side Fh kN = 267.2 470.4 140.0 140.0 200.0 200.0 0.0 0.0
d Bearing forces at bearing level μ(Rg + Rq) = kN = 353.9 362.9 324.2 324.2 324.2 324.2 393.2 380.8
e ThickNess of wearing coat m = 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065
f Ht. of Braking force act above bearing m = 4.490 4.490 4.490 4.490 4.490 4.490 4.490 4.490
g Moment at bearing level kN-m = 1199.73 2112.10 628.60 628.60 898.00 898.00 0.00 0.00
h Reaction as push/pull (+/-) kN = 30.92 54.44 16.20 16.20 23.14 23.14 0.00 0.00
i For moment at pier base, lever arm m = 18.990 18.990 18.990 18.990 18.990 18.990 18.990 18.990
j Longitudinal moment at pier base kN-m = 6721.22 6890.88 6156.48 6156.48 6156.48 6156.48 7466.25 7230.59
235
236
237
Calculation of WIND LOAD
a Wind Force on superstructure:
i. Transverse wind force (FT) :
Solid area (A1) = Exposed area in Transverse direction = 169.125 m2
FT = Area x Pz x G x CD = 517 kN
ii. Longitudinal wind force (FL) :
FL = 25% of transverse wind force = 129.27 kN
iii. Vertical wind load (FV) :
Plan area (A3) = 512.5 m2
Lift Coefficient (CL) = 0.75
FV = Area x pz x G x CL = 603 kN
b Wind force on live load:
as per clause 209.3.7 of IRC: 6, 2014, bridge shall not be considered to carry any live load if the basic wind velocity exceeds 36m/sec
ACCIDENTAL ACTIONS
Seismic Hazards
Seismic Zone of bridge location = V
Zone factor, Z = 0.36 (Table 6, IRC:6-2014, page-51)
Seismic importance factor of the structure I = 1.20 (Table 8, IRC:6-2014, page-56)
Average response acceleration co-efficient (Sa/g) = 2.50 (Clause 219.5.1, IRC:6-2014, page-55)
Where R is response reduction factor to be
Horizontal seismic co-efficient Ah (Z/2)X (I)X(Sa/g)/R = 0.54 /R
considered
Is ductile detailing to be done ? Yes
Value of R for sub-structure = 3
Hence horizontal seismic co-efficient (Ah) for sub-structure = 0.180
Horizontal seismic force, Feq = Ah.(Dead Load+Appropriate Live Load)
A. Seismic on Superstructure:
Dead Load from super-structure and SIDL without surfacing = = 12327.53 KN
C.G. of Deck from girder bottom = 1.688 m
Design Horizontal Seismic coefficient Ah = 0.180
Seismic force in longitudinal direction Fh= Ah x (Total Dead Load)= 2218.95 KN
Seismic force in longitudinal direction taken by one support Fh = 2218.95 KN ………r1
Acting at RL = 238.58 m
Lever arm for moment at bearing level = 1.688 m
Longitudinal moment at bearing level = 3745.60 KN-m
Vertical pull-push effect due to Horizontal seismic force = 48.27 KN
Lever arm for moment at pier base = 18.990 m
Longitudinal moment at pier base = 42137.95 KN-m ……..Mz
238
239
Horizontal seismic force in transeverse direction = Fh = 2218.955 KN ………..r2
Acting at RL = 238.582 m
Lever arm for moment at pier base = 18.990 m
Transeverse moment at pier base = 42137.946 KN-m ……Mx
Vertical component of seismic force = 1479.303 KN ………r3 (Clause 219.3, IRC:6-2014, page-51)
Combination of force components …….(Clause 219.4, IRC:6-2014, page-51)
Design force in longitudinal direction = r1 + 0.3r2 + 0.3r3 = 3328.432 KN
Design force in transeverse direction = 0.3r1 + r2 + 0.3r3 = 3328.432 KN
Design force in vertical direction = 0.3r1 + 0.3r2 + r3 = 2810.676 KN
Design longitudinal moment at Pier-base = Mz + 0.3Mx = 54779.330 KN-m
Design transeverse moment at Pier-base = 0.3Mz + Mx = 54779.330 KN-m
B. Seismic on Sufacing:
Surfacing or load due to wearing coat = 786.842 KN
C.G. of wearing coat from girder bottom = 3.258 m
Design Horizontal Seismic coefficient Ah = 0.180
Seismic force in longitudinal direction Fh= Ah x (Total Dead Load) = 141.631 KN
Seismic force in longitudinal direction taken by one support Fh = 141.631 KN ………r1
Acting at RL = 240.152 m
Lever arm for moment at bearing level = 3.258 m
Longitudinal moment at bearing level = 461.360 KN-m
Vertical pull-push effect due to Horizontal seismic force = 5.946 KN
Lever arm for moment at pier base = 18.990 m
Longitudinal moment at pier base = 2689.582 KN-m ……..Mz
Horizontal seismic force in transeverse direction = Fh = 141.631 KN ………..r2
Acting at RL = 240.152 m
Lever arm for moment at pier base = 18.990 m
Transeverse moment at pier base = 2689.582 KN-m ……Mx
Vertical component of seismic force = 94.421 KN ………r3 (Clause 219.3, IRC:6-2014, page-51)
Combination of force components …….(Clause 219.4, IRC:6-2014, page-51)
Design force in longitudinal direction = r1 + 0.3r2 + 0.3r3 = 212.447 KN
Design force in transeverse direction = 0.3r1 + r2 + 0.3r3 = 212.447 KN
Design force in vertical direction = 0.3r1 + 0.3r2 + r3 = 179.400 KN
Design longitudinal moment = Mz + 0.3Mx = 3496.457 KN-m
Design transeverse moment = 0.3Mz + Mx = 3496.457 KN-m
240
D. Seismic on Pier :
CG of the pier from top of pile cap = 8.125 m
Longitudinal seismic force = A_h x W_Pier = 1564.970 KN ……….r1
Acting at RL = 226.029 m RL
Longitudinal moment = 12715.381 KN-m ……..Mz
Transverse seismic = A_h x W_Pier = 1564.970 KN ……….r2
Acting at RL = 226.029 m RL
Transeverse moment = 12715.381 KN-m ……..Mx
Vertical component of seismic force = 1043.313 KN ………r3 (Clause 219.3, IRC:6-2014, page-51)
Combination of force components …….(Clause 219.4, IRC:6-2010, page-51)
Design force in longitudinal direction = r1 + 0.3r2 + 0.3r3 = 2347.455 KN
Design force in transeverse direction = 0.3r1 + r2 + 0.3r3 = 2347.455 KN
Design force in vertical direction = 0.3r1 + 0.3r2 + r3 = 1982.295 KN
Design longitudinal moment = Mz + 0.3Mx = 16529.996 KN-m
Design transeverse moment = 0.3Mz + Mx = 16529.996 KN-m
241
All the actions at pier base analised above are summarised bellow, loads are in KN
Sl.NO LOAD DESCRIPITION V HL HT LA ML MT
A PERMANENT LOADS
i Dead Load from super-structure 10806.53
ii Self weight of Pier Cap 1761.50
iii Self weight of pier 8694.29
VARIABLE GRAVITY TREATED AS PERMANENT
i SIDL except surfacing 1521.00
ii Surfacing 786.84
B VARIABLE LOAD
Carriageway Live Load
a For Class-A
i One lane / one span loaded 495.65 545.22 1710.00
ii Two lane / one span loaded 991.31 1090.44 1685.22
iii One lane / Both span loaded 644.55 86.39 2223.70
iv Two lane / Both span loaded 1289.10 172.78 2191.47
b For IRC class 70R Tracked
i One span loaded 725.82 798.40 1524.22
ii Both span loaded 769.16 0.00 1615.23
c For IRC class 70R Wheeled
i One span loaded 986.25 1084.88 2125.37
ii Both span loaded 1101.00 74.91 2372.66
d For IRC SV
i One lane / one span loaded 2299.06 2528.96 689.72
ii One lane / Both span loaded 1885.40 1456.46 565.62
Braking /Friction Force
a For Class-A
i One lane / one span loaded 30.92 357.60 18.990 6790.74
ii Two lane / one span loaded 54.44 487.53 18.990 9258.29
iii One lane / Both span loaded 30.92 383.00 18.990 7273.09
iv Two lane / Both span loaded 54.44 598.07 18.990 11357.33
b For IRC class 70R Tracked
i One span loaded 16.20 394.20 18.990 7485.78
ii Both span loaded 16.20 394.20 18.990 7485.78
c For IRC class 70R Wheeled
i One span loaded 23.14 424.20 18.990 8055.48
ii Both span loaded 23.14 424.20 18.990 8055.48
d For IRC SV
i One lane / one span loaded 0.00 393.17 18.990 7466.25
ii One lane / Both span loaded 0.00 380.76 18.990 7230.59
WIND LOAD
Wind load from super-structure 602.67 129.27 517.09 20.17 2607.83 10431.32
Wind load from sub-structure 0.00 30.79 85.34 9.13 280.98 778.77
SEISMIC EFFECTS
on superstructure except surfacing 2810.68 3328.43 3328.43 54779.33 54779.33
on pier cap 401.62 475.61 475.61 7114.42 7114.42
on pier 1982.30 2347.46 2347.46 16530.00 16530.00
On surfacing/ wearing coat 179.40 212.45 212.45 3496.46 3496.46
Vertical push-pull 54.21
for Live load
For Class-A
One lane / one span loaded 251.70 16.21 23.30 377.55
Three lane / one span loaded 503.40 32.41 23.30 755.10
One lane / Both span loaded 327.31 21.08 23.30 490.97
Three lane / Both span loaded 654.62 42.15 23.30 981.94
For IRC class 70R Tracked
One span loaded 368.92 23.75 23.30 553.37
Both span loaded 390.94 25.17 23.30 586.42
For IRC class 70R Wheeled
One span loaded 500.83 32.25 23.30 751.25
Both span loaded 559.10 36.00 23.30 838.66
HYDRAULIC LOAD
Water current force on shaft 0.00 40.87 0.00 0.00
Buoyant force on shaft 1693.04
242
Load combination at bottom of pile cap level
Sl.NO LOAD DESCRIPITION V HL HT LA ML MT
A PERMANENT LOADS
i Dead Load from super-structure 10806.53
ii Self weight of Pier Cap 1761.50
iii Self weight of pier 8694.29
iv Self weight of pile cap 10269.00
VARIABLE GRAVITY TREATED AS PERMANENT
i SIDL except surfacing 1521.00
ii Surfacing 786.84
B VARIABLE LOAD
Carriageway Live Load
a Class-A
i One lane / one span loaded 450.18 495.20 1553.13
ii Two lane / one span loaded 900.37 990.40 1530.63
iii One lane / Both span loaded 585.42 78.46 2019.71
iv Two lane / Both span loaded 1170.84 156.93 1990.44
b For IRC class 70R Tracked
i One span loaded 659.83 725.82 1385.65
ii Both span loaded 699.23 0.00 1468.39
c For IRC class 70R Wheeled
i One span loaded 895.78 985.36 1930.40
ii Both span loaded 1000.00 68.04 2155.00
d For IRC SV
i One lane / one span loaded 2299.06 2528.96 689.72
ii One lane / Both span loaded 1885.40 1456.46 565.62
Braking / Friction Force
a Class-A
i One lane / one span loaded 30.92 357.60 20.99 7505.93
ii Two lane / one span loaded 54.44 487.53 20.99 10233.36
iii One lane / Both span loaded 30.92 383.00 20.99 8039.08
iv Two lane / Both span loaded 54.44 598.07 20.99 12553.46
b For IRC class 70R Tracked
i One span loaded 16.20 394.20 20.99 8274.17
ii Both span loaded 16.20 394.20 20.99 8274.17
c For IRC class 70R Wheeled
i One span loaded 23.14 424.20 20.99 8903.87
ii Both span loaded 23.14 424.20 20.99 8903.87
d For IRC SV
i One lane / one span loaded 0.00 393.17 20.99 8252.58
ii One lane / Both span loaded 0.00 380.76 20.99 7992.10
THERMAL LOAD
i Temperature variation effect 0.00 2.00 0.00
WIND LOAD
Wind load from super-structure 602.67 129.27 517.09 22.17 2866.38 11465.51
Wind load from sub-structure 30.79 85.34 11.13 342.57 949.45
SEISMIC EFFECTS
on superstructure except surfacing 3513.34 4160.54 4160.54 75685.76 75685.76
on pier cap 502.03 594.51 594.51 9923.50 9923.50
on pier 2477.87 2934.32 2934.32 25748.65 25748.65
On surfacing/ wearing coat 224.25 265.56 265.56 4830.87 4830.87
on pile cap 2926.67 3465.79 3465.79 3003.68 3003.68
Vertical Push-Pull 67.77
for Live load
For Class-A
One lane / one span loaded 314.62 20.26 25.30 512.45
Three lane / one span loaded 629.25 40.52 25.30 1024.91
One lane / Both span loaded 409.14 26.34 25.30 666.40
Three lane / Both span loaded 818.28 52.69 25.30 1332.80
For IRC class 70R Tracked
One span loaded 461.14 29.69 25.30 751.10
Both span loaded 488.68 31.47 25.30 795.95
For IRC class 70R Wheeled
One span loaded 626.04 40.31 25.30 1019.68
Both span loaded 698.88 45.00 25.30 1138.32
HYDRAULIC LOAD
Water current force on shaft 0.00 40.87 4.73 0.00 193.20
Buoyant force on pile cap 4107.60
243
LOAD COMBINATION FOR PIER SHAFT BASE (For Ultimate Limit State)
Loads V ML MT HL HT
Dead Load 21262.31 0.00 0.00 0.00 0.00
SIDL 1521.00 0.00 0.00 0.00 0.00
Surfacing 786.84 0.00 0.00 0.00 0.00
Class A(3L/1S) LL1 991.31 1090.44 1685.22 0.00 0.00
Class A(3L/BS) LL2 1289.10 172.78 2191.47 0.00 0.00
70R Tr.1L+CL-A 1L(1S) LL3 725.82 798.40 1524.22 0.00 0.00
70R Tr.1L+CL-A 1L(BS). LL4 769.16 0.00 1615.23 0.00 0.00
70R Wh.1L+CL-A 1L(1S) LL5 986.25 1084.88 2125.37 0.00 0.00
70R Wh.1L+CL-A 1L(BS) LL6 1101.00 74.91 2372.66 0.00 0.00
Class SV(1S) LL7 2299.06 2528.96 689.72 0.00 0.00
Class SV(BS) LL8 1885.40 1456.46 565.62 0.00 0.00
BrakingClass A(3L/1S) LL1 54.44 9258.29 0.00 487.53 0.00
BrakingClass A(3L/BS) LL2 54.44 11357.33 0.00 598.07 0.00
Braking70R Tr.1L+CL-A 1L(1S) LL3 16.20 7485.78 0.00 394.20 0.00
Braking70R Tr.1L+CL-A 1L(BS). LL4 16.20 7485.78 0.00 394.20 0.00
Braking70R Wh.1L+CL-A 1L(1S) LL5 23.14 8055.48 0.00 424.20 0.00
Braking70R Wh.1L+CL-A 1L(BS) LL6 23.14 8055.48 0.00 424.20 0.00
Friction Class SV(1S) LL7 0.00 7466.25 0.00 393.17 0.00
Friction Class SV(BS) LL8 0.00 7230.59 0.00 380.76 0.00
Dead Load Seismic 5428.21 81920.20 0.00 6363.94 0.00
Seismic Class A(3L/1S) LL1 503.40 0.00 755.10 0.00 32.41
Seismic Class A(3L/BS) LL2 654.62 0.00 981.94 0.00 42.15
Seismic 70R Tr.1L+CL-A 1L(1S) LL3 368.92 0.00 553.37 0.00 23.75
Seismic 70R Tr.1L+CL-A 1L(BS). LL4 390.94 0.00 586.42 0.00 25.17
Seismic 70R Wh.1L+CL-A 1L(1S) LL5 500.83 0.00 751.25 0.00 32.25
Seismic 70R Wh.1L+CL-A 1L(BS) LL6 559.10 0.00 838.66 0.00 36.00
Wind load 602.67 2888.82 11210.09 160.07 602.44
Water Current force -1693.04 0.00 0.00 0.00 40.87
NON-SEISMIC CASE
A HFL / DRY CONDITION B HFL / DRY CONDITION WIND C ONE SPAN DISLODGED CASE
DL+SIDL+Surfacing+/-WL+WCF DL+SIDL+Surfacing+WCF
DL+SIDL+Surfacing+LL+Br. LL+WCF
Loads FOS Loads FOS Loads FOS
Dead Load 1.35 Dead Load 1.35 Dead Load 1.35
SIDL 1.35 SIDL 1.35 SIDL 1.35
Surfacing 1.75 Surfacing 1.75 Surfacing 1.75
LL 1.50 LL 1.50 Water Current force 1
Braking LL 1.15 Wind load 1.50
Water Current force 1.00 Water Current force 1.00
Special vehicle 1.0 Special vehicle 1.0
SEISMIC CASE
244
Vu MLu MTu HLu Htu
1 DL+SIDL+Surfacing+LL1+Braking LL1+WCF 31990.96 12282.68 2527.83 560.67 40.87
2 DL+SIDL+Surfacing+LL2+Braking LL2+WCF 32437.65 13320.09 3287.20 687.78 40.87
3 DL+SIDL+Surfacing+LL3+Braking LL3+WCF 31548.76 9806.24 2286.32 453.33 40.87
4 DL+SIDL+Surfacing+LL4+Braking LL4+WCF 31613.77 8608.64 2422.84 453.33 40.87
HFL Condition 5 DL+SIDL+Surfacing+LL5+Braking LL5+WCF 31947.40 10891.11 3188.06 487.83 40.87
Non Seismic 6 DL+SIDL+Surfacing+LL6+Braking LL6+WCF 32119.52 9376.17 3558.98 487.83 40.87
7 DL+SIDL+Surfacing+LL7+Braking LL7+WCF 32740.46 2528.96 689.72 0.00 40.87
8 DL+SIDL+Surfacing+LL8+Braking LL8+WCF 32326.80 1456.46 565.62 0.00 40.87
9 DL+SIDL+Surfacing+LL1+Braking LL1+WCF+WL(UP) 31086.95 16615.91 19342.96 800.76 944.53
10 DL+SIDL+Surfacing+LL2+Braking LL2+WCF+WL(UP) 31533.65 17653.31 20102.33 927.88 944.53
11 DL+SIDL+Surfacing+LL3+Braking LL3+WCF+WL(UP) 30644.75 14139.46 19101.45 693.42 944.53
12 DL+SIDL+Surfacing+LL4+Braking LL4+WCF+WL(UP) 30709.76 12941.87 19237.97 693.42 944.53
13 DL+SIDL+Surfacing+LL5+Braking LL5+WCF+WL(UP) 31043.39 15224.34 20003.19 727.92 944.53
14 DL+SIDL+Surfacing+LL6+Braking LL6+WCF+WL(UP) 31215.51 13709.39 20374.11 727.92 944.53
15 DL+SIDL+Surfacing+LL1+Braking LL1 33684.01 12282.68 2527.83 560.67 0.00
16 DL+SIDL+Surfacing+LL2+Braking LL2 34130.70 13320.09 3287.20 687.78 0.00
17 DL+SIDL+Surfacing+LL3+Braking LL3 33241.80 9806.24 2286.32 453.33 0.00
18 DL+SIDL+Surfacing+LL4+Braking LL4 33306.81 8608.64 2422.84 453.33 0.00
19 DL+SIDL+Surfacing+LL5+Braking LL5 33640.44 10891.11 3188.06 487.83 0.00
DRY Condition
Non Seismic
DL+SIDL+Surfacing+DL SEISMIC
dislodged LL
245
LOAD COMBINATION FOR PIER SHAFT BASE (For Serviceability Limit State)
Loads V ML MT HL HT
Dead Load 21262.31 0.00 0.00 0.00 0.00
SIDL 1521.00 0.00 0.00 0.00 0.00
Surfacing 786.84 0.00 0.00 0.00 0.00
Class A(3L/1S) LL1 991.31 1090.44 1685.22 0.00 0.00
Class A(3L/BS) LL2 1289.10 172.78 2191.47 0.00 0.00
70R Tr.1L+CL-A 1L(1S) LL3 725.82 798.40 1524.22 0.00 0.00
70R Tr.1L+CL-A 1L(BS). LL4 769.16 0.00 1615.23 0.00 0.00
70R Wh.1L+CL-A 1L(1S) LL5 986.25 1084.88 2125.37 0.00 0.00
70R Wh.1L+CL-A 1L(BS) LL6 1101.00 74.91 2372.66 0.00 0.00
Class SV(1S) LL7 2299.06 2528.96 689.72 0.00 0.00
Class SV(BS) LL8 1885.40 1456.46 565.62 0.00 0.00
BrakingClass A(3L/1S) LL1 54.44 9258.29 0.00 487.53 0.00
BrakingClass A(3L/BS) LL2 54.44 11357.33 0.00 598.07 0.00
Braking70R Tr.1L+CL-A 1L(1S) LL3 16.20 7485.78 0.00 394.20 0.00
Braking70R Tr.1L+CL-A 1L(BS). LL4 16.20 7485.78 0.00 394.20 0.00
Braking70R Wh.1L+CL-A 1L(1S) LL5 23.14 8055.48 0.00 424.20 0.00
Braking70R Wh.1L+CL-A 1L(BS) LL6 23.14 8055.48 0.00 424.20 0.00
Dead Load Seismic 5428.21 81920.20 0.00 6363.94 0.00
Seismic Class A(3L/1S) LL1 503.40 0.00 755.10 0.00 32.41
Seismic Class A(3L/BS) LL2 654.62 0.00 981.94 0.00 42.15
Seismic 70R Tr.1L+CL-A 1L(1S) LL3 368.92 0.00 553.37 0.00 23.75
Seismic 70R Tr.1L+CL-A 1L(BS). LL4 390.94 0.00 586.42 0.00 25.17
Seismic 70R Wh.1L+CL-A 1L(1S) LL5 500.83 0.00 751.25 0.00 32.25
Seismic 70R Wh.1L+CL-A 1L(BS) LL6 559.10 0.00 838.66 0.00 36.00
Wind load 602.67 2888.82 11210.09 160.07 602.44
Water Current force -1693.04 0.00 0.00 0.00 40.87
NON-SEISMIC CASE
HFL / DRY CONDITION HFL / DRY CONDITION ONE SPAN DISLODGED CASE
A B C
246
Vu MLu MTu HLu Htu
1 DL+SIDL+Surfacing+LL1+Braking LL1+WCF 22909.25 8034.15 1685.22 365.65 40.87
2 DL+SIDL+Surfacing+LL2+Braking LL2+WCF 23207.04 8690.77 2191.47 448.55 40.87
3 DL+SIDL+Surfacing+LL3+Braking LL3+WCF 22615.08 6412.73 1524.22 295.65 40.87
4 DL+SIDL+Surfacing+LL4+Braking LL4+WCF 22658.42 5614.33 1615.23 295.65 40.87
5 DL+SIDL+Surfacing+LL5+Braking LL5+WCF 22880.72 7126.49 2125.37 318.15 40.87
HFL Condition
Non Seismic
6 DL+SIDL+Surfacing+LL6+Braking LL6+WCF 22995.47 6116.52 2372.66 318.15 40.87
7 DL+SIDL+Surfacing+LL7+WCF 24176.17 2528.96 689.72 0.00 40.87
8 DL+SIDL+Surfacing+LL8+WCF 23762.51 1456.46 565.62 0.00 40.87
9 DL+SIDL+Surfacing+LL1+Braking LL1+WCF+WL(UP) 22306.57 10922.97 12895.31 525.72 643.31
10 DL+SIDL+Surfacing+LL2+Braking LL2+WCF+WL(UP) 22604.37 11579.58 13401.56 608.62 643.31
11 DL+SIDL+Surfacing+LL3+Braking LL3+WCF+WL(UP) 22012.41 9301.55 12734.30 455.71 643.31
12 DL+SIDL+Surfacing+LL4+Braking LL4+WCF+WL(UP) 22055.75 8503.15 12825.32 455.71 643.31
13 DL+SIDL+Surfacing+LL5+Braking LL5+WCF+WL(UP) 22278.05 10015.30 13335.46 478.21 643.31
14 DL+SIDL+Surfacing+LL6+Braking LL6+WCF+WL(UP) 22392.80 9005.34 13582.74 478.21 643.31
15 DL+SIDL+Surfacing+LL1+Braking LL1 24602.29 8034.15 1685.22 365.65 0.00
16 DL+SIDL+Surfacing+LL2+Braking LL2 24900.08 8690.77 2191.47 448.55 0.00
17 DL+SIDL+Surfacing+LL3+Braking LL3 24308.12 6412.73 1524.22 295.65 0.00
18 DL+SIDL+Surfacing+LL4+Braking LL4 24351.46 5614.33 1615.23 295.65 0.00
19 DL+SIDL+Surfacing+LL5+Braking LL5 24573.77 7126.49 2125.37 318.15 0.00
DRY Condition
Non Seismic
247
PIER SHAFT DESIGN(ULS)
Grade of concrete : M 30
Grade of steel = Fe 500
Ecm of concrete = 31000 N/mm2 (From table 6.5, IRC:112-2011, page no. 38)
Es of steel = 200000 N/mm2 (From clause6.3.5, IRC:112-2011, page no. 32)
Design compressive strength of concrete = sc = fcd = afck/gm = 13.400 N/mm2
(From clause6.3.5, IRC:112-2011, page no. 32)
Design peak strength of steel = fy/gs = 434.783 N/mm2
As the ratio does not exceed 12, it is short and no secondary effect to be considered
(clause 7.6.4, IRC:112-2011, page-57)
Effective cover = 101 mm
d'
248
Interaction check
Grade of concrete = M 30
Grade of steel = Fe 500
Width of section considered = 1m
249
Crack width check:
Now,
(Eq. 12.6, IRC:112-2011, page-125)
Where, ssc = stress in the tension reinforcement = 96.73 Mpa
ae = Es/Ecm = 6.45
fct.eff = mean value of tensile strength of concrete = 2.9 Mpa
rr.eff = As/Ac.eff Where, Ac.eff = Effective area of concrete in tension, surrounding
the reinforcement of depth h c.eff
Where, hc.eff = lesser of the followings
2.5(h-d);(h-x/3);or h/2
Where, A = level of steel centroid
B = Effective tension area, Ac.eff
Ô1,Ô2 = greater and lesser tensile strain
So, hc.eff = 253 mm
2
Ac.eff = 252500 mm
Now. rr.eff = As/Ac.eff = 0.1687268
kt = factor dependant on duration of the load may be taken as 0.5
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+f/2)), the maximum crack spacing,
2=0 x
250
Design of Pier Cap
No. of Bearing = 8
3 3 3
P1 P2 P4 P5
9.40 1.55
3 0.2
2.2
251
Checking for transverse direction :
ac = 0.200 m
h = 2.00 m
ac / h = 0.1 < 1 Hence pier cap is to be designed as corbel
CORBEL DESIGN:
Distance of central line of beraing from face of pier shaft = 0.400 m
Pier Cap thickness at face of pier shaft= 2m
Which is less than the pier cap thickness at face of pier shaft .
hence the pier cap will be designed as a corbel.
252
Vertical reaction :
2
i) Af + At = 2292.521 mm
2
ii)(2/3)Avf + At = 4064.2279 mm
2
iii)(0.04xfc'/fsy)x(bxd') = 12644.736 mm
2
Ast provided (As)= 13836 mm OK
2
Step VII Ah = 1056.603 mm
2
Avf /3 = 1942.456 mm
253
Design for seismic case :
Vu = 381.541 KN
Hu = 11.601 KN
2
Step III Avf = 641.245 mm
2
Step IV At = 27.296 mm
2
Step V Af = 2113.206 mm
2
i) Af + At = 2140.502 mm
2
ii) (2/3)Avf + At = 454.79261 mm
2
iii) (0.04xfc'/fsu)x(bxd') 12644.736 mm
2
Ast provided = 13345.000 mm OK
2
Step VII Ah = 1056.603 mm
2
Avf /3 = 213.748 mm
254
D. LOAD COMBINATION FOR ABUTMENT FOUNDATION BASE (Ultimate Limit State)
Loads V ML MT HL HT
Dead Load 31531.31 0.00 0.00 0.00 0.00
SIDL 1521.00 0.00 0.00 0.00 0.00
Surfacing 786.84 0.00 0.00 0.00 0.00
Class A(3L/1S) LL1 900.37 990.40 1530.63 0.00 0.00
Class A(3L/BS) LL2 1170.84 156.93 1990.44 0.00 0.00
70R Tr.1L+CL-A 1L(1S) LL3 659.83 725.82 1385.65 0.00 0.00
70R Tr.1L+CL-A 1L(BS). LL4 769.16 0.00 1615.23 0.00 0.00
70R Wh.1L+CL-A 1L(1S) LL5 986.25 1084.88 2125.37 0.00 0.00
70R Wh.1L+CL-A 1L(BS) LL6 1101.00 74.91 2372.66 0.00 0.00
Class SV(1S) LL7 2299.06 2528.96 689.72 0.00 0.00
Class SV(BS) LL8 1885.40 1456.46 565.62 0.00 0.00
BrakingClass A(3L/1S) LL1 54.44 10233.36 0.00 487.53 0.00
BrakingClass A(2L/BS) LL2 54.44 12553.46 0.00 598.07 0.00
Braking70R Tr.1L+CL-A 1L(1S) LL3 16.20 8274.17 0.00 394.20 0.00
Braking70R Tr.1L+CL-A 1L(BS). LL4 16.20 8274.17 0.00 394.20 0.00
Braking70R Wh.1L+CL-A 1L(1S) LL5 23.14 8903.87 0.00 424.20 0.00
Braking70R Wh.1L+CL-A 1L(BS) LL6 23.14 8903.87 0.00 424.20 0.00
Friction Class SV(1S) LL7 0.00 8252.58 0.00 393.17 0.00
Friction Class SV(BS) LL8 0.00 7992.10 0.00 380.76 0.00
Dead Load Seismic 9711.92 119192.47 0.00 11420.71 0.00
Seismic Class A(2L/1S) LL1 629.25 0.00 1024.91 0.00 40.52
Seismic Class A(2L/BS) LL2 818.28 0.00 1332.80 0.00 52.69
Seismic 70R T(2L/1S) LL3 461.14 0.00 751.10 0.00 29.69
Seismic 70R T(2L/BS) LL4 488.68 0.00 795.95 0.00 31.47
Seismic 70R W(2L/1S) LL5 626.04 0.00 1019.68 0.00 40.31
Seismic 70R W(2L/BS) LL6 698.88 0.00 1138.32 0.00 45.00
Wind load 602.67 3208.95 12414.96 160.07 602.44
Water Current force 4107.60 0.00 193.20 0.00 40.87
NON-SEISMIC CASE
A HFL / DRY CONDITION B HFL / DRY CONDITION C ONE SPAN DISLODGED CASE
DL+SIDL+Surfacing+LL+Br. LL+WCF DL+SIDL+Surfacing+/-WL+WCF DL+SIDL+Surfacing+WCF
Loads FOS Loads FOS Loads FOS
Dead Load 1.35 Dead Load 1.35 Dead Load 1.35
SIDL 1.35 SIDL 1.35 SIDL 1.35
Surfacing 1.75 Surfacing 1.75 Surfacing 1.75
LL 1.50 LL 1.50 Water Current force 1
Braking LL 1.15 Wind load 1.50 Special vehicle 1.0
Water Current force 1.00 Water Current force 1.00
Special vehicle 1.0 Special vehicle 1.0
SEISMIC CASE
255
COMB V ML MT HL HT
1 DL+SIDL+Surfacing+LL1+Braking LL1+WCF 51518.35 13253.97 2489.14 560.67 40.87
2 DL+SIDL+Surfacing+LL2+Braking LL2+WCF 51924.06 14671.87 3178.85 687.78 40.87
3 DL+SIDL+Surfacing+LL3+Braking LL3+WCF 51113.58 10604.02 2271.67 453.33 40.87
4 DL+SIDL+Surfacing+LL4+Braking LL4+WCF 51277.56 9515.29 2616.04 453.33 40.87
5 DL+SIDL+Surfacing+LL5+Braking LL5+WCF 51611.19 11866.76 3381.26 487.83 40.87
HFL Condition
Non Seismic
256
H. LOAD COMBINATION FOR ABUTMENT FOUNDATION BASE (Servicebility Limit State)
Loads V ML MT HL HT
Dead Load 31531.31 0.00 0.00 0.00 0.00
SIDL 1521.00 0.00 0.00 0.00 0.00
Surfacing 786.84 0.00 0.00 0.00 0.00
Class A(3L/1S) LL1 900.37 990.40 1530.63 0.00 0.00
Class A(3L/BS) LL2 1170.84 156.93 1990.44 0.00 0.00
70R Tr.1L+CL-A 1L(1S) LL3 659.83 725.82 1385.65 0.00 0.00
70R Tr.1L+CL-A 1L(BS). LL4 769.16 0.00 1615.23 0.00 0.00
70R Wh.1L+CL-A 1L(1S) LL5 986.25 1084.88 2125.37 0.00 0.00
70R Wh.1L+CL-A 1L(BS) LL6 1101.00 74.91 2372.66 0.00 0.00
Class SV(1S) LL7 2299.06 2528.96 689.72 0.00 0.00
Class SV(BS) LL8 1885.40 1456.46 565.62 0.00 0.00
BrakingClass A(3L/1S) LL1 54.44 10233.36 0.00 487.53 0.00
BrakingClass A(3L/BS) LL2 54.44 12553.46 0.00 598.07 0.00
Braking70R Tr.1L+CL-A 1L(1S) LL3 16.20 8274.17 0.00 394.20 0.00
Braking70R Tr.1L+CL-A 1L(BS). LL4 16.20 8274.17 0.00 394.20 0.00
Braking70R Wh.1L+CL-A 1L(1S) LL5 23.14 8903.87 0.00 424.20 0.00
Braking70R Wh.1L+CL-A 1L(BS) LL6 23.14 8903.87 0.00 424.20 0.00
Dead Load Seismic 9711.92 119192.47 0.00 11420.71 0.00
Seismic Class A(3L/1S) LL1 629.25 0.00 1024.91 0.00 40.52
Seismic Class A(3L/BS) LL2 818.28 0.00 1332.80 0.00 52.69
Seismic 70R Tr.1L+CL-A 1L(1S) LL3 461.14 0.00 751.10 0.00 29.69
Seismic 70R Tr.1L+CL-A 1L(BS). LL4 488.68 0.00 795.95 0.00 31.47
Seismic 70R Wh.1L+CL-A 1L(1S) LL5 626.04 0.00 1019.68 0.00 40.31
Seismic 70R Wh.1L+CL-A 1L(BS) LL6 698.88 0.00 1138.32 0.00 45.00
Wind load 602.67 3208.95 12414.96 160.07 602.44
Water Current force 4107.60 0.00 193.20 0.00 40.87
NON-SEISMIC CASE
A HFL / DRY CONDITION B HFL / DRY CONDITION C ONE SPAN DISLODGED CASE
257
COMB V ML MT HL HT
1 DL+SIDL+Surfacing+LL1+Braking LL1+WCF 38887.95 8665.42 1723.82 365.65 40.87
2 DL+SIDL+Surfacing+LL2+Braking LL2+WCF 39158.43 9572.02 2183.63 448.55 40.87
HFL Condition
Non Seismic 3 DL+SIDL+Surfacing+LL3+Braking LL3+WCF 38618.74 6931.44 1578.85 295.65 40.87
4 DL+SIDL+Surfacing+LL4+Braking LL4+WCF 38728.06 6205.63 1808.43 295.65 40.87
5 DL+SIDL+Surfacing+LL5+Braking LL5+WCF 38950.37 7762.78 2318.57 318.15 40.87
6 DL+SIDL+Surfacing+LL6+Braking LL6+WCF 39065.11 6752.81 2565.85 318.15 40.87
7 DL+SIDL+Surfacing+LL7+WCF 40245.81 2528.96 882.92 0.00 40.87
8 DL+SIDL+Surfacing+LL8+WCF 39832.15 1456.46 758.82 0.00 40.87
9 DL+SIDL+Surfacing+LL1+Braking LL1+WCF+WL 39490.62 11874.37 14138.79 525.72 643.31
10 DL+SIDL+Surfacing+LL2+Braking LL2+WCF+WL 39761.10 12780.97 14598.59 608.62 643.31
11 DL+SIDL+Surfacing+LL3+Braking LL3+WCF+WL 39221.41 10140.39 13993.81 455.71 643.31
12 DL+SIDL+Surfacing+LL4+Braking LL4+WCF+WL 39330.74 9414.57 14223.39 455.71 643.31
13 DL+SIDL+Surfacing+LL5+Braking LL5+WCF+WL 39553.04 10971.73 14733.53 478.21 643.31
14 DL+SIDL+Surfacing+LL6+Braking LL6+WCF+WL 39667.79 9961.76 14980.81 478.21 643.31
15 DL+SIDL+Surfacing+LL1+Braking LL1 34780.35 8665.42 1530.63 365.65 0.00
16 DL+SIDL+Surfacing+LL2+Braking LL2 35050.83 9572.02 1990.44 448.55 0.00
17 DL+SIDL+Surfacing+LL3+Braking LL3 34511.14 6931.44 1385.65 295.65 0.00
18 DL+SIDL+Surfacing+LL4+Braking LL4 34620.46 6205.63 1615.23 295.65 0.00
19 DL+SIDL+Surfacing+LL5+Braking LL5 34842.77 7762.78 2125.37 318.15 0.00
DRY Condition
Non Seismic
258
CHECK FOR PILE CAPACITY
3.7
Diameter of pile = 1.2 m
C/C of pile along longitudinal direction = 3.7 m
C/C of pile along transeverse direction = 3.7 m
No. of piles along longitudinal direction = 4 nos.
No. of piles along transeverse direction = 5 nos.
Edge Clearance = 0.15 m 3.7
Pile cap dimension in longitudinal direction = 12.6 m
Pile cap dimension in transeverse direction = 16.3 m
Pier dimension in longitudinal direction = 3 m
Pier dimension in transeverse direction = 8 m
Depth of pile cap = 2 m
Height of earth above pile cap = 3.555 m
Clear cover = 0.075 m
Effective depth of pile cap = 1.909 m
Load Case V ML MT HL HT
MLmax 1 36740.89 13990.49 13104.68 553.23 602.44
Considering Wind
Vmax 2 36740.89 13990.49 13104.68 553.23 602.44
MLmax 3 45312.443 127033.50 13691.22 11777.4 647.44 Considering
Vmax 4 45312.443 127033.50 13691.22 11777.4 647.437 Seismic
MLmax 5 40245.812 10781.547 882.915 393.167 40.871
Normal Case
Vmax 6 40245.812 10781.547 882.915 393.167 40.871
1 span dislodged
MLmax 7 21027.178 0.000 193.198 0.000 40.871
(Seismic)
259
Moment per unit load on pile at provided pile cap position = 3.97 KN-m/KN
Moment in pile
Load
V/N ML/ZL1 ML/ZL2 MT/ZT1 MT/ZT2 H/N due to horizontal
Case
force
1 1837.04 189.06 94.530 212.51 70.84 40.90 162.153
2 1837.04 189.06 94.530 212.51 70.84 40.90 162.153
3 2265.62 1716.67 858.334 222.02 74.01 589.76 2338.387
4 2265.62 1716.67 858.334 222.02 74.01 589.76 2338.387
5 2012.29 145.70 72.848 14.32 4.77 19.76 78.365
6 2012.29 145.70 72.848 14.32 4.77 19.76 78.365
7 1051.36 0.00 0.000 3.13 1.04 2.04 8.103
NORMAL CASE
Vmax = 2172.305 KN
Load Case = 5
Coresponding moment = 5.000 KN-M
Mmax = 78.365 KN-M
Load Case = 5
Coresponding min. vertical load = 1852.2765 KN
260
DESIGN OF PILE CAP BY BENDING ANALOGY (ULS)
load
comb sl LOAD CASE Vu MLu MTu HLu HTu
30 MLmax 47903.73 121734.54 591.3 11540.32 40.87
10 Vmax 52828.07 19485.292 21801.29 927.878 944.527
41 Vmin 43551.08 119192.47 0.00 0.00 0.00
43 1 span dislodged 34390.34 122705.36 193.20 0.00 40.87
No. of piles = 20
B' D
B 2.2 ML 1.909
0.75 5.9 0.891 4.741
0.75
17 16 9 8 1
3.7
18 15 10 7 2
MT
12.6
19 14 11 6
3
20 13 12 5 4
B B' 16.3 D
6.65
4.741
1.2
Load
V/N ML/ZL1 ML/ZL2 MT/ZT1 MT/ZT2
Case
30 2395.19 1645.06 822.5307 9.588 3.196
10 2641.40 263.31 131.6574 353.534 117.845
41 2177.55 1610.71 805.3545 0.000 0.000
43 1719.52 1658.18 829.0903 3.133 1.044
Loads on piles
Moment
Load
Pile 1 Pile 2 Pile 3 Pile 4 Pile 5 Pile 6 Pile 7 Pile 8 in each
Case
pile
30 4049.84 4043.44 4037.052 4030.660 3208.1290 3214.52 3220.91 3227.31 2287.88
10 3258.25 3022.56 2786.874 2551.184 2419.5266 2655.22 2890.91 3126.60 262.49
41 3788.26 3788.26 3788.263 3788.263 2982.9084 2982.91 2982.91 2982.91 0.00
43 3380.83 3378.74 3376.653 3374.565 2545.4744 2547.56 2549.65 2551.74 8.10
261
Considering case 30
Bending Moment at section B-B & B'-B' (in KN-m)
Moment
Sl. No. Force due to Force Moment
arm
1 Pile 1 4049.837 5.9 23894.036
2 Pile 2 4043.444 5.9 23856.321
3 Pile 3 4037.052 5.9 23818.607
4 Pile 4 4030.660 5.9 23780.892
5 Pile 5 3208.129 2.2 7057.884
6 Pile 6 3214.521 2.2 7071.947
7 Pile 7 3220.914 2.2 7086.010
8 Pile 8 3227.306 2.2 7100.073
9 Self Wt. -4189.500 3.325 -13930.09
10 Earth Wt. -595.747 3.325 -1980.86
Total 107754.82
Design moment positive means tension at bottom of pile
Shear force at section D-D ("d" distance away from B-B) in KN
Total For Shear
Sl. No. Force due to
Force at D-D
1 Pile 1 4049.837 4049.837
2 Pile 2 4043.444 4043.444
3 Pile 3 4037.052 4037.052
4 Pile 4 4030.660 4030.660
5 Pile 5 3208.129 2382.036
6 Pile 6 3214.521 2386.782
7 Pile 7 3220.914 2391.528
8 Pile 8 3227.306 2396.275
9 Self Wt. -4189.500 -2986.83
10 Earth Wt. -595.747 -424.73
Total 22306.056
Design of pile cap in flexure
Grade of concrete = M 30
Grade of steel = Fe 500
Width of section considered = 1m
262
CHECK FOR SHEAR IN PILE CAP (Clause 10.3.2, IRC:112-2011, page-88)
Design Shear Force = 1770.322 KN
The design shear resistance of the member without shear reinforcement, VRd.c =
=[0.12K(80r1.fck)0.33+0.15scp]bw.d
Where, K = 1+√(200/d)<=2.0
So, K = 1.324
r1 = Asl/bw.d
2
Where Asl = Area of steel provided = 12861 mm
bw = Width of section = 1000 mm
d= 1909 mm
r1 = 0.0067
scp = NEd/Ac < 0.2fcd, where, NEd = Axial compressive force = 0
Ac = Cross Sectional area of concrete
scp = 0 So,VRd.c = 759.69 KN
Now, VRd.c minimum = (nmin+0.15scp)bw.d
where nmin = 0.031K3/2fck1/2 = 0.25858
So, VRd.c minimum = 493.630 KN
So, governing shear resistance = 759.69 KN Shear reinforcement required
b a b
263
264
265
266
SERVICEABILITY LIMIT STATE CHECK
SL NO. LOAD CASE Vu MLu MTu HLu HTu
10 MLmax 39761.10 12780.97 14598.59 608.618 643.309
7 Vmax 40245.81 2528.96 882.92 0.00 40.87
17 Vmin 34511.140 6931.44 1385.65 295.647 40.871
29 1 span dislodged 37946.76 0.00 193.20 0.00 40.87
No. of piles = 20
B'
B 2.2 ML 0.891
0.75 5.9 1.909 4.741
0.75
17 16 99 8 1
3.7
18 15 10 7 2
MT
3 2 12.6
19 14 11 6 3
20 13 12 5 4
16.3
B B'
6.65
1.2
Load
Case V/N ML/ZL1 ML/ZL2 MT/ZT1 MT/ZT2
10 1988.05 172.72 86.357907 236.734 78.911
7 2012.29 34.18 17.087584 14.318 4.773
17 1725.56 93.67 46.834076 22.470 7.490
29 1897.34 0.00 0 3.133 1.044
267
Vertical Loads on piles
Load
Pile 1 Pile 2 Pile 3 Pile 4 Pile 5 Pile 6 Pile 7 Pile 8
Case
10 2397.50 2239.68 2081.86 1924.04 1837.68 1995.50 2153.32 2311.15
7 2060.78 2051.24 2041.69 2032.15 2015.06 2024.61 2034.15 2043.70
17 1841.70 1826.72 1811.74 1796.76 1749.92 1764.90 1779.88 1794.86
29 1900.47 1898.38 1896.29 1894.20 1894.20 1896.29 1898.38 1900.47
Considering case 10
Bending Moment at section B-B (in KN-m)
Moment
Sl. No. Force due to Force Moment
arm
1 Pile 1 2397.505 5.9 14145.28
2 Pile 2 2239.682 5.9 13214.12
3 Pile 3 2081.859 5.9 12282.97
4 Pile 4 2032.148 5.9 11989.67
5 Pile 5 2015.061 2.2 4433.13
6 Pile 6 2024.606 2.2 4454.13
7 Pile 7 2153.324 2.2 4737.31
8 Pile 8 2311.147 2.2 5084.52
4 Self Wt. -4189.500 3.325 -13930.09
5 Earth Wt. -595.747 3.325 -1980.86
Total 54430.20
268
Stress level check:
Grade of concrete = M 30
Grade of steel = Fe 500
Width of section considered = 1.0 m
2
Total reinforcement provided = 12861 mm
Effective depth "d" = 1909 mm
Neutral axis depth = x = 567.51
CG of compressive force = 189.169 mm from most compressed surface
Now moment, M = (Stress in steel)x(area of steel)x(d-CG of compressive force) =
Now,
hc.eff
1 B
269
So, hc.eff = 227.5 mm
2
Ac.eff = 227500 mm
Now. rr.eff = As/Ac.eff = 0.0565338
kt = factor dependant on duration of the load may be taken as 0.5
Now in situations where spacing of bonded reinforcement within the tension zone is reasonably
close (i.e <=5(c+f/2)), the maximum crack spacing,
270
DESIGN OF PILES
d'
Diameter of bars provided = 32 mm
No. of bars provided = 48 Nos. in 2 layers
Percentage of stee, p = 3.413
So, p/fck = 0.098
d'/D = 0.076
Now for case 30, Pile No. 1
Pu = 4049.84 KN
2
Pu/fck.D = 0.0804
271
Summarised Reinforcement Detailing
(According to chapter 16, IRC:112-2011, page-171)
PIER SHAFT
2
Total vertical reinforcement provided = 10669.1 mm
2
Concrete area, Ac = 3883573 mm
2
Now, 0.0024Ac = 9320.575 mm < Steel provided, OK
2
and 0.04Ac = 155342.9 mm > Steel provided, OK
2
Total horizontal reinforcement provided = 1608 mm
2
Now 25% of vertical steel = 1340 mm < Steel provided, OK
2
and 0.001Ac = 239 mm < Steel provided, OK
272
PILE CAP
Main reinforcement provided 32 mm dia. 125 mm c/c
in 2 layers
2
Steel in 1m strip = 12861.44 mm
2
As.min = 0.26fctm/fykbtd= 2878.77 mm OK
2
or, 0.0013btd = 2481.7 mm OK
Distribution reinforcement provided at bottom and both direction at top
25 mm dia. 150 mm c/c
OK
Provide surface reinforcement 16 mm dia. 6 Nos. each face
Provide shear reinforcement 25 mm dia 4 legged stirrup @
175 mm spacing at toe side
PIER CAP
PILE
Main reinforcement provided 32 mm dia. 48 Nos. in 2 layers
Continue all bars upto end of pile
Distribution reinforcement provided 10 mm dia. 150 mm c/c
273
ESTIMATE OF IRANG BRIDGE
CH._95.500 KM
274
COST ABSTRACT
275
ABSTRACT
Sr No Description of Bill Items Amount (INR Crore)
A Road Portion (Approach road)
I Cutting , Earthfilling & Disposal 1.65
II Sub base 0.24
III Non-Bituminous Base Course 0.47
IV Bituminous Base Course 0.25
V Wearing Coat 0.14
Sub Total A 2.75
B Culvert (Sub Total B) 0.38
C Bridge
I Foundation 9.10
II Substructure 5.52
III Superstructure 10.28
IV Protection work 0.17
V Miscellaneous 0.03
Sub Total C 25.1
D Grand Total (A+B+C) (As per SOR 2016) 28.23
E Inflation @ 2.93% 0.83
F Add GST @ 6% 1.69
G Civil work without Maintenance (D+E+F) 30.75
COST ESTIMATION
277
Summary Sheet of Major Bridge (Quantities & Amount)
CHAINAGE 3X41M
95.500 KM Twin Bridge
Rate Amount
of
Span(m) x (Rs.) (Rs.)
CW=9.5
Height(m)=
BW=12.5
ITEM NO. Description Unit
A. Foundation
Item no 1(a) Excavation (upto 3 m depth) cum 4191.910 423.50 17,75,274.00
Item no 1(b) Excavation (3 m to 6 m depth) in rock cum 2519.090 1,736.73 43,74,979.00
Item no 2 R.C.C M30 (Foundation) cum 2132.000 11,269.97 2,40,27,572.00
Item no 3 P.C.C (M-15) cum 209.510 8,873.64 18,59,116.00
Item no 4 Bored cast-in-situ M35 grade R.C.C. Piles m 1200.000 19,561.41 2,34,73,692.00
Item no 5 Steel liner 6mm thick (1.2m DIA PILE) ton 1.240 100,426.17 1,24,528.00
Item no 6 Steel (Foundation) ton 469.160 75,930.20 3,56,23,412.00
B. SubStructure
Item no 1(a) R.C.C M30 (Substructure) upto 5m cum 784.810 10,581.08 83,04,136.00
Item no 1(b) R.C.C M30 (Substructure) from 5m to 10m cum 497.600 10,721.42 53,34,978.00
Item no 1(C) R.C.C M30 (Substructure) above 10m cum 637.90 10,861.77 69,28,722.00
Item no 2 R.C.C M35 (Substructure) upto 5m cum 66.040 11,381.14 7,51,610.00
Item no 3 Steel (Substructure) ton 289.812 75,930.20 2,20,05,483.00
Item no 4 Weep Holes each 338.000 482.27 1,63,007.00
Item no 5 Backfilling - Granular Material cum 667.860 2,152.78 14,37,756.00
Item no 6 Backfilling - Sandy Material cum 1288.740 2,254.65 29,05,658.00
Item no 7 Filter Media cum 339.280 2,168.88 7,35,858.00
Item no 8 Elastomeric Bearing cc 1145609 3.19 36,54,493.00
Item no 9 Brick Masonary Wall at Median cum 8.750 9,667.37 84,589.00
Item no 10 Pot & Pot cum PTFE ton capacity 9600.000 504.74 48,45,504.00
C. Super Structure
Item no 1(a) P.S.C M45 (Superstructure) upto 5m cum 1553.840 18,764.75 2,91,57,419.00
Item no 1(b) R.C.C M45 (Superstructure) upto 5m cum 699.800 13,858.18 96,97,955.00
Item no 1(c) RCC M30 Kerb cum 52.210 12,774.37 6,66,950.00
Item no 2(a) Steel (PSC) ton 131.010 134,692.76 1,76,46,098.00
Item no 2(b) Steel (Superstructure) ton 458.320 76,311.35 3,49,75,017.00
Item no 3(a) Bituminous Concrete Wearing Coat(40mm) cum 101.040 14,039.14 14,18,514.00
Item no 3(b) Mastic Asphalt (25mm) sqm 2525.920 553.17 13,97,273.00
Item no 3(c) Tack Coat sqm 2525.920 15.63 39,470.00
Item no 3(d) Cement concrete wearing course(75 mm) cum 29.410 16,790.82 4,93,818.00
Item no 4 Railing metre 261.440 2,361.87 6,17,486.00
Item no 5 Crash Barrier metre 530.560 6,919.68 36,71,305.00
Item no 6 Drainage Spout each 46.00 1,919.84 88,313.00
Item no 7 PCC below approach slab cum 24.260 8,739.16 2,12,012.00
Item no 8 R.C.C. Approach Slab with steel cum 50.400 16,567.57 8,35,005.00
Item no 9 Strip Seal Expansion Joint metre 50.000 41863.77 20,93,189.00
Item no 10 Filler Joint
(i) copper plate metre 50.000 6,379.01 3,18,950.00
(ii) fibar board metre 50.000 504.68 25,234.00
(iii) 20mm thick premoulded joint filler metre 50.000 602.12 30,106.00
(iv) joint sealing compound metre 50.000 32.00 1,600.00
D. Protection Work
Item no 1a Boulder Pitching cum 202.420 4,092.80 8,28,465.00
Item no 1b Filter Blanket cum 101.210 3,649.89 3,69,405.00
Item no 2 PCC(M15) Toe Wall cum 48.440 9,950.67 4,82,011.00
Item no 5 750 mm thick Flexible appron cum 46.238 2,971.45 1,37,394.00
Item no 6 Below Curtain Wall- PCC (M-15) cum 10.105 9,950.67 1,00,552.00
Item no 7 Excavation cum 318.444 423.50 1,34,861.00
Item no 9 PCC M20 curtain wall cum 68.321 8926.714 6,09,882.00
MISCELLANEOUS
Item no 1a Painting sqm 2081.110 127.320 2,64,967.00
Item no 1b Citizen information Board NH Project no 2.000 25000.000 50,000.00
ROAD PART
Item no 1 Earth cutting for Approach Road cum 15900.000 174.210 27,69,939.00
Earth Filling under road
Item no 1a Granular Material cum 2498.760 2152.780 53,79,280.00
Item no 1b Sandy Material cum 2498.760 2254.650 56,33,829.00
Item no 1b Disposal For Excavated Earth cum 10902.480 252.040 27,47,861.06
Pavement Composition
Item no 1a BC cum 99.000 14039.135 13,89,874.00
Item no 1b DBM cum 198.000 12478.705 24,70,784.00
Item no 1c WBM cum 990.000 4815.815 47,67,657.00
Item no 1d GSB cum 594.000 4013.178 23,83,828.00
TOTAL = 28,23,16,670.06
278
LEAD DETAILS
279
Leads for Various Materials
Name of Name of
Sl. No. Distance from Source to BridgeLocation Total Lead
Material Source
1 Sand (Fine) Noney 58 km by road to Irang Bridge Location 60 Km
2 Filling Material Local - 10km
3 Stone Metal Barak 69 km by road to Irang Bridge Location 71 km
4 Stone Boulder Barak 69 km by road to Irang Bridge Location 71 km
5 Stone Chips, Noney 58 km by road to Irang Bridge Location 60 Km
Aggregate
6 Coarse Sand Noney 58 km by road to Irang Bridge Location 60 Km
7 Cement Imphal 105.5 km by road to Irang Bridge Location 107.5 Km
8 Steel Imphal 105.5 km by road to Irang Bridge Location 107.5 Km
Numaligarh
9 Bitumen Refinery, 415 km by road to Irang Bridge Location 417 Km
Assam
10 Structural Steel Imphal 105.5 km by road to Irang Bridge Location 107.5 Km
280
Carriage Cost of Material (Including loading & unloading )
Rubbish
Name of Quarries Local
Lead Upto Site (KM)= 10
Cost of
Lead Carriage Rate Carriage
Sl.No. Kilometer Unit
(km) (Km) (Rs) (In Rs)
281
Sand
Name of Quarries Noney
Lead Upto Bridge Locationl (KM)= 58
Lead on Quarry (KM)= 2.00
Total Lead (KM)= 60
Cost of
Carriage Rate
Sl.No. Lead in km Kilometer Unit Carriage
(Km) (Rs)
(In Rs)
Upto 1 per m3 149.05
3
Upto 2 per m 173.04
3
Upto 3 per m 196.57
3
Upto 4 per m 219.13
3
Upto 5 per m 5 240.80 240.80
3 60.17
for Every km beyond 5 km
per m3 117.45
up to 10 km 5 23.49
for Every km beyond10 km
per m3 187.90
up to 20 km 10 18.79
282
Cement, Steel
Name of Quarries Imphal
Lead Upto Bridge Location (KM)= 105.50
Lead upto Quarry (KM)= 2.00
Total Lead (KM)= 107.50 Cost of
Carriage
Rate
Sl.No. Lead in km Kilometer Unit Carriage (In Rs)
(Rs)
283
QUANTITY ESTIMATE OF
BRIDGE & ROAD
284
DETAIL QUANTITY CALCULATION OF BRIDGE AT IRANG BRIDGE
FOUNDATION
1.1 Excavation upto 3m depth
Abutment-1 cum 2 13.80 8.40 3.00 695.52
Pier-1 cum 2 13.60 17.30 3.00 1411.68
Pier-2 cum 2 13.60 17.30 3.00 1411.68
Abutment-2 cum 2 13.80 8.40 2.20 510.05
Total 4028.93
6 HYSD Bars
130kg/cum for pile cap & @
T Total= 469.160
160kg/m for pile
SUBSTRUCTURE
7 RCC M-30 upto 5.0m height
Abutment wall (A1) cum 2 12.50 1.200 1.700 51.00
Abutment wall (A2) cum 2 12.50 1.200 1.700 51.00
Abutment cap cum 4 12.75 2.070 1.000 105.57
Pier shaft (P1) cum 2 21.24 5.000 212.40
Pier shaft (P2) cum 2 21.24 5.000 212.40
Dirt Wall cum 4 12.50 0.400 2.300 46.00
RCC Wall at median cum 2 3.00 0.300 2.600 4.68
Total= 683.05
285
DETAIL QUANTITY CALCULATION OF BRIDGE AT IRANG BRIDGE
11 RCC M-35 for Pedestal & Seismic Arrestor Blocks height upto 5.0m
cum 2 0.80 0.800 0.243 0.31
cum 2 0.80 0.800 0.290 0.37
Pedestal at Abutment Pot bearing
cum 2 0.80 0.800 0.365 0.47
cum 2 0.80 0.800 0.440 0.56
cum 2 0.80 0.800 0.243 0.31
Pedestal at Abutment Pot cum PTFE cum 2 0.80 0.800 0.290 0.37
bearing cum 2 0.80 0.800 0.365 0.47
cum 2 0.80 0.800 0.440 0.56
cum 4 0.80 0.800 0.243 0.62
cum 4 0.80 0.800 0.290 0.74
Pedestal at Pier for Pot bearing
cum 4 0.80 0.800 0.365 0.93
cum 4 0.80 0.800 0.440 1.13
cum 4 0.80 0.800 0.243 0.62
Pedestal at Pier for Pot cum PTFE cum 4 0.80 0.800 0.290 0.74
bearing cum 4 0.80 0.800 0.365 0.93
cum 4 0.80 0.800 0.440 1.13
Block RB2 cum 16 1.000 0.550 1.425 12.54
Block RB1 cum 24 0.800 1.321 25.36
Block RB3 cum 16 1.060 0.740 1.425 17.88
Total= 66.04
11 HYSD Bars
@ 150 kg/cum T 282.689
Total= 282.689
286
DETAIL QUANTITY CALCULATION OF BRIDGE AT IRANG BRIDGE
14 Filter media
Behind Abutment cum 4 12.000 0.60 6.390 184.03
Behind Fin wall cum 4 4.500 0.60 4.000 43.20
Behind RCC wall at median cum 2 3.000 0.60 7.440 26.78
Total 254.01
16 Elastomeric Bearing
Bearing B1 cucm 24 37.00 54.50 9.80 474281
Bearing B2 cucm 16 27.00 42.00 13.00 235872
Bearing B3 cucm 32 27.00 42.00 12.00 435456
Total 1145609
287
DETAIL QUANTITY CALCULATION OF BRIDGE AT IRANG BRIDGE
19 PSC Steel
@550kg/m length of PSC girder TON 131.01 131.01
Total 131.01
21 Railing
m 2 130.72 261.44
Total= 261.44
25 Approach Slab(M30)
Approach Slab cum 4 3.500 12.000 0.300 50.40
Total 50.40
288
DETAIL QUANTITY CALCULATION OF BRIDGE AT IRANG BRIDGE
28 Tack coat
sqm 2 130.72 9.50 2483.68
Total= 2483.68
30 Filler joint
Providing & fixing 2 mm thick
corrugated copper plate in expansion m 4 12.50 50.00
joint
Providing & fixing 20 mm thick
compressible fibre board in m 4 12.50 50.00
expansion joint
Providing and fixing in position 20
m 4 12.50 50.00
mm thick premoulded joint filler
Providing and filling joint sealing
m 4 12.50 50.00
compound
PROTECTION WORK
33 Toe Wall
In A1 side cum 2 26.992 0.353 19.056
In A2 side cum 2 41.616 0.353 29.381
Total 48.44
MISCELLANNEOUS
35 Painting
Railing(Post) sqm 144 1.05 1.10 166.32
Railing(Beam) sqm 6 0.69 130.72 541.18
Crash Barrier sqm 4 2.627 130.72 1373.61
Total 2081.110
289
ESTIMATE OF QUANTITY OF BOX CULVERT
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity
A. FOUNDATION
1 Excavation(up to 3m)
Box Bridge cum 1 6.640 13.000 0.870 75.098
Shear Key cum 2 6.640 1.680 0.780 17.402
Return Wall-II cum 4 4.710 4.300 0.870 70.480
` Total 162.980
2 PCC-M15
Box Bridge cum 1 5.640 9.940 0.150 8.409
Shear Key cum 2 5.940 1.503 0.150 2.678
Return Wall-II cum 4 4.360 3.600 0.150 9.418
Total 20.505
B. SUBSTRUCTURE
5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment =11.4/2+1 = 7
No of weep holes in vertical direction per abutment =2.8/1+1 = 4
No of weep holes in horizontal direction per return wall =5.11/2+1 = 4
No of weep holes in vertical direction per return wall =3.54/1 +1= 5
Total no of Weep holes per abutment = 7 x 4 28
Total no of Weep holes per return wall = 4 x 5 16
Total no of weep holes = 28 x 2 + 16 x 4 136
290
7 Filter media
Behind Abutment cum 2 11.400 0.600 3.420 46.786
Behind Return Wall cum 4 4.530 0.600 3.540 38.487
Total 85.273
C. SUPERSTRUCTURE
8 RCC-M30(up to 5m)
Box Bridge cum 1 3.840 12.000 0.489 22.533
(+)Haunch cum 2 12.000 0.011 0.264
Total 22.797
11 Mastic Asphalt
sqm 1 3.840 11.000 42.240
Total 42.240
12 Tack Coat
sqm 1 3.840 11.000 42.240
Total 42.240
D. PROTECTION WORK
17 Excavation in Soil
Curtain Wall (downstream) cum 1 22.900 2.850 2.650 172.952
Curtain Wall (upstream) cum 1 18.900 2.500 2.150 101.588
Flexible appron(downstream) cum 1 12.700 0.175 0.750 1.667
Flexible appron(upstream) cum 1 12.700 1.850 0.750 17.621
Rigid appron(downstream) cum 1 13.600 1.175 0.400 6.392
Rigid appron(upstream) cum 1 13.600 3.350 0.400 18.224
Total 318.444
18 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 21.900 1.850 0.150 6.077
Upstream side cum 1 17.900 1.500 0.150 4.028
Total 10.105
291
DETAIL QUANTITY CALCULATION OF ROAD PART
40 Pavement Composition
2.1 BC cum 2 120 16.5 0.025 99.000
2.2 DBM cum 2 120 16.5 0.05 198.000
2.3 WBM cum 2 120 16.5 0.25 990.000
2.4 GSB cum 2 120 16.5 0.15 594.000
292
RESETTLEMENT
REHABILITATION & SOCIAL
IMPACT ASSESSMENT
293
Consultancy Services for preparation of Detailed Project Report
and providing pre-construction services in respect of 4 laning with paved
shoulder of Imphal-Jiribam road section on NH-37(NH-53)
for proposed bridge over River Irang in the State of Manipur.
294
Consultancy Services for preparation of Detailed Project Report
and providing pre-construction services in respect of 4 laning with paved
shoulder of Imphal-Jiribam road section on NH-37(NH-53)
for proposed bridge over River Irang in the State of Manipur.
5.6m. The existing bridge condition along the road is poor. 3 x 41m PSC T- Girder 4-lane
bridge is proposed just on the upstream side of the existing bridge.
Figure 1: Photograph of Existing Irang Bridge
Adequate attention has been given during the feasibility phases of the project preparation to
minimize the adverse impacts on land acquisition and resettlement impacts. However,
technical and engineering constraints were one of the major concerns during exploration of
various alternative alignment option. With the available options proposed bridge alignment
has been has finalised with best engineering solution as well as avoiding large scale land
acquisition and involuntary resettlement impacts.
295
Consultancy Services for preparation of Detailed Project Report
and providing pre-construction services in respect of 4 laning with paved
shoulder of Imphal-Jiribam road section on NH-37(NH-53)
for proposed bridge over River Irang in the State of Manipur.
Government of India and National Highway’s guidelines. Prior to the preparation of the
Resettlement Plan, a detailed analysis of the proposed national and state policies was
undertaken and an entitlement matrix has been prepared for the entire program. The section
below provides details of the various national and state level legislations studied and their
applicability within this framework. This resettlement plan (RP) is prepared based on the
review and analysis of all applicable legal and policy frameworks of the country and State
policy requirements. Land acquisition for the project would be done as per State provisions
in accordance with RTFCLARR 2013 and/or other prevailing acts and rules of Govt.
Manipur.
All common property resources (CPR) lost due to the project will be replaced or
compensated by the project.
The project will recognize two types of displaced persons like (i) persons with formal legal
rights to land lost in its entirety or in part and (ii) persons who lost the land they occupy in its
entirety or in part who have no formal legal rights to such land, but who have claims to such
lands that are recognized or recognizable under national/state laws. The involuntary
resettlement requirements apply to all types of displaced persons.
296
Consultancy Services for preparation of Detailed Project Report
and providing pre-construction services in respect of 4 laning with paved
shoulder of Imphal-Jiribam road section on NH-37(NH-53)
for proposed bridge over River Irang in the State of Manipur.
R&R Budget
Road Name : IMPHAL TO JIRIBAM (NH-37) Location : Irang Bridge
297
Consultancy Services for preparation of Detailed Project Report
and providing pre-construction services in respect of 4 laning with paved
shoulder of Imphal-Jiribam road section on NH-37(NH-53)
for proposed bridge over River Irang in the State of Manipur.
298
Consultancy Services for preparation of Detailed Project Report
and providing pre-construction services in respect of 4 laning with paved
shoulder of Imphal-Jiribam road section on NH-37(NH-53)
for proposed bridge over River Irang in the State of Manipur.
Total(O) = (A to M) 35,649,714.71
299
Consultancy Services for preparation of Detailed Project Report
and providing pre-construction services in respect of 4 laning with paved
shoulder of Imphal-Jiribam road section on NH-37(NH-53)
for proposed bridge over River Irang in the State of Manipur.
---------------------
300
LAND ACQUISITION PLAN
301
95+650
R
LA
PIL
600
95+
95
+8
00 123
.00
00
95
R
LA
PIL
+9
00
SSB
B SSBB
R
LA
PIL
Proposed Road Centre Line :
0+200
A
:
Proposed Chainage
:
Proposed ROW
:
Existing ROW +5
95
00
:
Proposed Land Acquisition
R
LA
Existing Carriageway
PIL
:
Proposed Road :
Toe Line :
400
95+
95+283
302
NATIONAL HIGHWAYS AND INFRASTRUCTURE
AS DEVELOPMENT CORPORATION LTD.
SHOWN 4, Parliament Street, LAND ACQUISITION OF APPROACH ROAD
New Delhi - 110001
CONSULTANCY SERVICES FOR PREPARATION OF DETAILED PROJECT REPORT AND
MKD. DATE DESCRIPTION CHKD. APPRD.
PRE-CONSTRUCTION SERVICES IN RESPECT OF 4 LANING WITH PAVED SHOULDER OF
BRIDGE & APPROACH ROAD OVER IRANG RIVER
APRIL, 2018 IMPHAL - JIRIBAM ROAD SECTION (LENGTH- 220KM ) ON NH-37 (NH-53)
REVISIONS ROAD NAME:- IMPHAL - JIRIBAM ( NH-53 )
FOR PROPOSED BRIDGE OVER RIVER IRANG IN THE STATE OF MANIPUR.
LAND ACQUISITION AREA
303
RATE ANALYSIS FOR BRIDGE
WORKS
304
HAULAGE CALCULATION SHEET FOR BRIDGE WORKS
305
HAULAGE CALCULATION SHEET FOR BRIDGE WORKS
306
HAULAGE CALCULATION SHEET FOR BRIDGE WORKS
SUB-STRUCTURE
Brick masonry work in cement mortar
1:3 in Sub-structure complete
15.1 excluding pointing and plastering, as Cum 9667.37 9667.37
per drawing and technical
specifications
Stone masonry work in cement
mortar 1:3 in Sub-structure complete
15.2
as drawing and Technical
Specification
Stone Cum 1.100 1465.86 1612.45
(a) Coursed rubble masonry( first sort ) Cum 6377.48 Sand Cum 0.315 1150.63 362.45
Cement Tonne 0.153 1336.78 204.53 8556.90
Stone Cum 1.0000 1465.86 1465.86
Random Rubble Masonry
(b) Cum 5658.74 Sand Cum 0.3470 1150.63 399.27
(coursed/uncoursed )
Cement Tonne 0.1680 1336.78 224.58 7748.45
307
HAULAGE CALCULATION SHEET FOR BRIDGE WORKS
308
HAULAGE CALCULATION SHEET FOR BRIDGE WORKS
309
HAULAGE CALCULATION SHEET FOR BRIDGE WORKS
310
HAULAGE CALCULATION SHEET FOR BRIDGE WORKS
(a) Boulder Cum 2053.98 Stone Boulder Cum 1.2000 1465.86 1759.03 3813.01
(b) Boulder in wire crates. Cum 2014.46 Stone Boulder Cum 1.2007 1465.86 1760.06 3774.52
Aggregate/Stone Chips Cum 0.275 1150.63 316.81
(c) Cement concrete block (M-15grade) Cum 7912.98 Sand Cum 0.450 1150.63 517.78
Cement Tonne 0.900 1336.78 1203.10 9950.67
Filter material underneath pitching in
17.2 slopes complete as per drawing and Cum 2269.13 Stone Aggregate Cum 1.200 1150.63 1380.76 3649.89
Technical specification
17.3 Pitching on slopes
(a) Stone Cum 2333.77 Stone Boulder Cum 1.200 1465.86 1759.03 4092.80
Aggregate/Stone Chips Cum 0.275 1150.63 316.81
(b) Cement concrete block (M-15grade) Cum 7912.98 Sand Cum 0.450 1150.63 517.78
Cement Tonne 0.900 1336.78 1203.10 9950.67
311
RATE ANALYSIS FOR ROAD
WORKS
312
HAULAGE CALCULATION SHEET FOR ROAD WORKS
Cost for
Final Rates
Code No. Item Unit SOR rate Materials Required Unit Quantity Rate haulage
( Rs.)
(Rs)
313
Cost for
Final Rates
Code No. Item Unit SOR rate Materials Required Unit Quantity Rate haulage
( Rs.)
(Rs)
314
Cost for
Final Rates
Code No. Item Unit SOR rate Materials Required Unit Quantity Rate haulage
( Rs.)
(Rs)
A) On WBM/ WMM Surface @ 0.70-1.00 kg/sqm Sqm 56.41 Bitumen Emulsion Tonne 0.0008 4679.38 3.74 60.15
315
Cost for
Final Rates
Code No. Item Unit SOR rate Materials Required Unit Quantity Rate haulage
( Rs.)
(Rs)
316
Cost for
Final Rates
Code No. Item Unit SOR rate Materials Required Unit Quantity Rate haulage
( Rs.)
(Rs)
Road Delineators
8.15 Piece 1061.01 1061.01
120x120 -Road Delineator
8.17 RCC Crash Barrier m 4613.12 6919.68
8.18 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier
(a) For post Height of 1.2 m Rm 2639.41 2639.41
(b) For post Height of 1.5 m Rm 2571.65 2571.65
(c) For post Height of 1.8 m Rm 2680.55 2680.55
Road Markers/Road stud with lense reflector
8.20
317