PGEresponse
PGEresponse
25
26
27
28
1 Defendant Pacific Gas and Electric Company (“PG&E”) respectfully submits this
2 memorandum in response to the Court’s July 10, 2019 Request for Offender PG&E to Supply
3 Information. As required by the Request, PG&E hereby responds to each paragraph of a Wall Street
4 Journal article dated July 10, 2019, bearing the headline “PG&E Knew for Years Its Lines Could
6 PG&E has acknowledged that its transmission equipment caused the devastating November 8,
7 2018 Camp Fire that killed 85 people, destroyed the Town of Paradise, and burned over 150,000 acres.
8 And PG&E understands the magnitude of the challenges it faces in reducing wildfire risk and the
9 responsibility it owes all Californians to address those risks. The October 2017 wildfires and the
10 Camp Fire have demonstrated the new normal of significantly increased wildfire risk. PG&E
11 understands that it must do more than ever before to address this new risk profile. PG&E welcomes
12 input from the community to the ongoing dialogue on how PG&E can operate its electric system more
14 In preparing this submission, PG&E has investigated the factual basis for each statement in the
15 WSJ Article. While it has not been possible to provide exhaustive responses here given the page limit
16 for this submission, PG&E hopes that these responses will contribute to an accurate and more
17 complete understanding of the issues, including PG&E’s maintenance of its transmission lines in the
18 years before the Camp Fire and its efforts to develop enhanced, risk-based methods for inspecting and
20 PG&E takes this opportunity at the outset to address briefly three issues raised by the WSJ
21 Article. First, since the Camp Fire, PG&E has fundamentally changed its approach in light of the new
22 increased risk environment by, among other things, comprehensively inspecting its transmission,
23 distribution and substation assets in elevated and extreme fire-threat areas before the 2019 fire season.
24 As PG&E reported on June 19, 2019, by that time, PG&E had addressed every highest-priority
25 condition on transmission structures and at substations, and 97% of all such conditions on distribution
26 poles. PG&E continues to take corrective actions to address remaining conditions. These enhanced
27 inspections are but one element of PG&E’s redesigned Community Wildfire Safety Program, first
28
                                                       2
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 3 of 37
1 implemented in response to the October 2017 wildfires. That program also includes real-time, round-
2 the-clock monitoring of wildfire risks from PG&E’s Wildfire Safety Operations Center; proactively
3 de-energizing power lines when high winds and dry conditions, combined with a heightened fire risk,
4 are forecasted; enhanced vegetation management work focusing on high-risk trees that pose the most
5 wildfire risk; disabling automatic reclosing of circuit breakers and reclosers in high fire-risk areas
6 during wildfire season; and system hardening efforts that include installing stronger and more
8 Second, PG&E welcomes the growing public focus on the acute problem of aging transmission
9 infrastructure. In its filings with the Federal Energy Regulatory Commission (“FERC”), PG&E has
10 sought and continues to seek authorization to set the rates it charges for electric transmission services
11 at levels sufficient to support, among other things, replacement of aging equipment over time. When
12 PG&E files its transmission revenue requirement requests with FERC, the other participants in those
13 proceedings, including the California Public Utilities Commission (“CPUC”), PG&E’s wholesale
14 transmission customers, and FERC Trial Staff review the filings while also conducting discovery
15 related to PG&E’s requests. In the past, those participants have questioned PG&E’s proposed level of
16 spending on transmission assets. For example, in a 2017 ratemaking proceeding, the CPUC stated,
17 “While the CPUC recognizes that repair and replacement are necessary components of a utility’s
18 operation, the amount that PG&E has been spending on what appears primarily to be replacement of
19 transmission facilities is staggering and potentially unjustified.” (Ex. A, Initial Br. of the CPUC,
20 Pacific Gas and Electric Co., Dkt. No. ER16-2320-002 (Mar. 15, 2018) at 8.) The CPUC also stated
21 there was reason to believe that PG&E was “‘gold plating’ the system” and “unreasonably burden[ing]
22 ratepayers with unnecessary costs.” (Id. at 2-3.) This ratemaking process has resulted in settlements
23 at amounts less than what PG&E initially requested. Going forward, PG&E hopes to work with all
24 relevant stakeholders to re-calibrate the level of investment in transmission asset replacement that will
26 Third, PG&E strongly disagrees with the WSJ Article’s suggestion that PG&E knew of the
27 specific maintenance conditions that caused the Camp Fire and nonetheless deferred work that would
28
                                                      3
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
         Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 4 of 37
1 have addressed those conditions. The article’s implication that PG&E delayed planned maintenance
2 that could have averted the Camp Fire is based primarily on certain non-routine work PG&E was
3 planning for the Caribou-Palermo 115 kV Transmission Line in response to an October 7, 2010 North
5 Alert”). The purpose of that work was not to identify and fix worn or broken parts, such as the hook
6 on the transmission tower that failed and caused the Camp Fire to ignite. Rather, the purpose of that
7 work was to address the clearance between transmission line conductors and from transmission line
8 conductors to the ground. The NERC work on the Caribou-Palermo line was just one of hundreds of
9 projects within PG&E’s broader effort to respond to the NERC Alert. To date, PG&E has addressed
10 more than 10,000 conductor clearance issues (out of the approximately 11,500 total), at a cost of over
12 Critically, the WSJ Article fails to mention that the tower identified as the origin point of the
13 Camp Fire—Tower :27/222—was not one of the towers slated for replacement under the NERC Alert
14 program. In short, the NERC Alert work had nothing to do with the Camp Fire.
18 RESPONSE TO PARAGRAPH 1:
19 PG&E admits that it has long known that the approximately 18,000 miles of overhead high-
20 voltage power lines in its transmission system, like all energized lines, have the potential to fail and
21 ignite fires.
23 accounted for a small percentage of ignitions as compared to distribution lines. Based on ignition data
24 for the 2014-2017 period that PG&E has reported to the CPUC, equipment failure on high-voltage
25 lines operating at 115 kV or above was identified as the underlying cause of only 7 of the 1,552
26 ignitions attributed to PG&E assets (less than 1% of all ignitions reported in that period). (See PG&E
28
                                                      4
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 5 of 37
1 https://www.cpuc.ca.gov/uploadedFiles/CPUCWebsite/Content/News_Room/NewsUpdates/2019/PG
3 ignitions attributed to PG&E’s high-voltage transmission lines are varied. Such lines typically use
4 steel structures rather than wood poles, have higher conductor-to-ground clearances than distribution
5 lines, and are situated on managed rights-of-way that are cleared of trees.
6 By contrast, in the years preceding the Camp Fire, PG&E monitored data showing that a major
7 driver of ignitions caused by its equipment was vegetation contact with distribution lines. During the
8 2014-2017 period, PG&E reported 426 ignitions where vegetation came into contact with distribution
9 assets, comprising approximately 27% of all ignitions reported in that period. (Id.) Some of the most
10 devastating wildfires, including, for example, the Butte Fire, conformed to that pattern. As a result,
11 PG&E focused earlier wildfire mitigation efforts on its distribution system—and vegetation
12 management in particular.
13 PG&E denies the generalized assertion that it repeatedly failed to perform the necessary
14 upgrades to prevent failures on its transmission lines. The suggestion that PG&E has ignored
15 investment in its transmission lines is inaccurate. Across its transmission system as a whole, PG&E’s
16 actual spending on expense work related to its transmission lines, including routine maintenance,
17 ranged from $140 million to $294 million per year from 2008 to 2018, with a general upward trend
18 over that period. PG&E’s actual capital expenditures on transmission assets grew by an average of
19 7.35% each year from 2007 to 2018, trending upwards from $655 million in 2008 to approximately
20 $1.29 billion in 2018. PG&E spent the following amounts to upgrade its transmission system from
21 2006 to 2018:
27
28
                                                     5
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 6 of 37
1            •   approximately $438 million to replace transmission wood poles, steel poles, and steel
                 towers at the end of their useful lives;
2
             •   approximately $108 million on projects to maintain access to transmission line
3
                 rights-of-way; and
4
             •   approximately $290 million on emergency response work that includes replacing damaged
5                line-related equipment that has resulted in an outage or is a high priority for safety reasons.
10 RESPONSE TO PARAGRAPH 2:
11 PG&E admits reporting in its regulatory filings that parts of its transmission system had
12 reached or were reaching the end of their useful lives. PG&E’s publicly available filings also describe
13 its efforts to replace parts of its transmission system at or near the end of useful life that cannot be
14 repaired. As an example, in 2018, PG&E provided FERC with information on its “Tower
15 Replacement Program . . . established to manage the replacement of steel structures that have reached
16 the end of their useful lives . . . where repair is either less cost effective or not feasible.” (See Ex. B,
17 PGE-0003 (D. Gabbard Direct Testimony), Pacific Gas and Electric, Dkt. No. ER19-13-0000 (Oct. 1,
18 2018) at 12:1-6.)
25 transmission tower caused the Camp Fire. The component that failed was a steel suspension hook
26 known as a C-hook.
27
28
                                                       6
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 7 of 37
1 PG&E disagrees with the assertion that this failure “wasn’t an aberration.” As stated in
3 transmission lines are relatively uncommon. (See also 2018 Annual Availability Report, available at
5 (ET) wire down events typically account for between 1% and 2% of all T&D wire down events each
6 year.”).)
7 PG&E acknowledges that in connection with a FERC revenue requirement request, PG&E
8 Senior Director David Gabbard gave written and oral testimony about projected replacement
9 schedules for PG&E transmission infrastructure constructed in the early 1900s and in the years
10 following World War II. Specifically, Mr. Gabbard explained in written testimony that “[a]
11 significant part of PG&E’s transmission infrastructure was constructed in the years following World
12 War II, with some assets being even older” and that “[d]ue to an increasingly large number of these
13 assets nearing the end of their useful service lives, capital investment will shift significantly, from
14 capacity increase-related projects, to lifecycle replacement projects.” (Ex. C, Prepared Rebuttal Test.
15 of D. Gabbard, Pacific Gas and Electric Co., Dkt. No. ER16-2320-002 (Oct. 9, 2017) at 7:3-18.)
16 PG&E clarifies that it was not PG&E executives who initially likened the problem of aging
17 transmission equipment due for replacement at approximately the same time “to a ‘pig in the python.’”
18 That analogy was suggested by a CPUC attorney during cross-examination of Mr. Gabbard in a
19 January 2018 regulatory rate proceeding. The relevant portion of the hearing transcript is set forth
20 below:
21                   “Q. Yes. What years are you talking about when you say that
                     PG&E’s—a significant part of PG&E’s transmission infrastructure was
22                   constructed in the years following World War II?
23                   “A. Referencing a broad era of time in the ‘50s and ‘60s. That’s
24                   referencing a large portion of our assets, but we have a significant
                     portion of our 115 kV assets that were built as early as in the 1920s time
25                   frame and earlier.
26                   “Q. This is what I described in your deposition as the pig and the
                     python problem. There were a lot of assets built at the same time during
27                   this World War II period, in the ‘50s and ‘60s and that these assets will
28
                                                      7
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 8 of 37
9 PG&E acknowledges that, prior to November 2018, it had identified approximately 60 towers
10 for replacement on the Caribou-Palermo 115 kV Transmission Line. Tower :27/222, the tower
11 identified as the origin point of the Camp Fire, was not one of the towers slated for replacement.
12 The towers were identified for replacement in connection with PG&E’s response to the NERC
13 Alert. The industry-wide NERC Alert required PG&E and other electric utilities across the nation to
14 identify areas in their transmission system where conductors may be too close to the ground or to each
15 other, or have the potential to sag too close to the ground under extreme temperatures. In response to
16 the NERC Alert, PG&E identified thousands of towers on hundreds of lines throughout its
17 transmission system—including the Caribou-Palermo line—that required work to increase the vertical
18 clearance of conductors. To address vertical conductor clearance issues, PG&E typically installs
19 extensions on towers to make them taller or raises the height of the wires by tightening or “re-
20 tensioning” them. Tower replacements are typically done when PG&E determines that other
22 For the Caribou-Palermo towers identified for replacement, PG&E determined that those
23 towers should be replaced because the design of the towers made them unsuitable for tower extensions
24 to raise the height of the towers, as explained in greater detail in PG&E’s response to Paragraph 24.
25 Again, none of these towers slated for replacement was the tower at which the Camp Fire originated.
26
27
28
                                                     8
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 9 of 37
4    RESPONSE TO PARAGRAPH 5:
5           PG&E admits that a slide in an internal PG&E presentation titled “Electric Overhead Steel
6    Structure Strategy Overview”, dated June 2017, contains the figures referenced in the WSJ Article.
7    (See Ex. E, Electric Overhead Steel Structure Strategy Overview (June 2017) at 7.) As noted on the
8    same slide, the life expectancy and age estimates referenced in the June 2017 presentation are based
9    on a section of a May 2010 “Transmission Line Component Management Report” prepared at
10   PG&E’s request by Quanta Technology (the “Quanta Study”).
11          However, the Quanta Study notes that the life expectancy estimates in the study (on which the
12   figures in the June 2017 presentation are based) do not refer to the point at which “complete failure of
13   a structure” is anticipated. (Ex. F, Quanta Study, “Structures” Chapter, at 37.) Rather, they are
14   averages “based on the ages of failed components as found in maintenance records from 2004-2009”,
15   with “failure” referring to the point at which a component “requir[es] significant maintenance or
16   replacement”. (Id. (emphasis added).) The conditions that qualified as “failures” for the purposes of
17   the Quanta Study included slack guy wires, earth-covered anchors, cracked foundations and bent steel,
18   all of which can be addressed through maintenance work and typically do not require replacement of
19   the entire structure. Moreover, the Quanta Study specifically notes that “[t]here are many structures
20   100 years old that have not failed or, more likely, have had component replacement o[r] significant
21   maintenance prior to the period of this data set” and that “[l]attice steel structures installed in the
22   1920s in the US utility industry remain in service in many locations.” (Id. at 20, 38.)
23           The same slide referenced in the WSJ Article also notes that the life expectancy for towers
24   varies substantially depending on the surrounding environment. The slide states that the “max” life
25   expectancy for towers in “coastal” environments is 80 years, while the “max” life expectancy for
26   towers in “valley” environments is “100+ years.” (Ex. E, Electric Overhead Steel Structure Strategy
27
28
                                                       9
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 10 of 37
1 Overview (June 2017) at 7.) These variable estimates are consistent with the Quanta Study, which
2 found that the failure rates for towers in “coastal regions” are “significantly higher” than the failure
3 rates for structures “in the valley and mountain regions,” principally because coastal environments are
4 more corrosive than mountain and valley regions. (Ex. F, Quanta Study, “Structures” Chapter, at 46,
5 49.) Tower :27/222 on the Caribou-Palermo 115 kV Transmission Line is located in a mountain
6 region.
7 In the years leading up to the Camp Fire, PG&E was implementing a Tower Replacement
8 Program to replace certain towers that it determined to be at heightened risk of failure. Consistent
9 with Quanta’s recommendations, and as noted in the June 2017 presentation, towers in coastal
10 environments that were subject to corrosion (and thus at greater risk of failure) were higher priorities
11 for replacement under that program. (See Ex. E, Electric Overhead Steel Structure Strategy Overview
12 (June 2017) at 4, 15.) Specifically, PG&E focused on towers in the San Francisco Bay area due to
13 their direct exposure to saltwater from the bay. (See id.) Over the medium to long term, PG&E’s
14 Tower Replacement Program called for replacement of additional towers in valley and mountain areas
22 but acknowledges that portions of its transmission system have been in operation since the early
23 1900s. PG&E admits that many of its original steel towers and other equipment are still in service.
24
25
26
27
28
                                                     10
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 11 of 37
7 Steel Structure Strategy Overview” outlined a series of PG&E’s safety, reliability and environmental
8 objectives for overhead steel transmission lines, including “[e]nsur[ing] the environment is protected
9 from structure failure resulting [in] conductor on ground causing fire.” (Ex. E, Electric Overhead
10 Steel Structure Strategy Overview (June 2017) at 3.) PG&E admits that short-term goals listed in that
11 same internal presentation included “[d]evelop[ing] a steel structure replacement plan,” managing data
12 associated with steel structures, and “[e]valuat[ing] the effectiveness of [PG&E’s existing] design,
13 maintenance and inspection program and mak[ing] necessary recommendations for improvement.”
14 (Id. at 4.)
15 PG&E denies that it has “neglect[ed]” its transmission lines. PG&E had programs in place
16 before the Camp Fire to inspect, maintain, repair and replace transmission equipment, as well as to
17 manage vegetation in the vicinity of its transmission lines. PG&E has enhanced those programs since
19 It is true that environmental changes have fundamentally altered wildfire risk in the State of
20 California, including, in particular, PG&E’s service territory in recent years. The combined effects of
21 record drought and heat, unprecedented tree mortality, and extreme wind events have greatly
23
24
25
26
27
28
                                                     11
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 12 of 37
5    RESPONSE TO PARAGRAPH 8:
6           PG&E denies the statement that it “repeatedly delayed upgrades of some of its oldest
7    transmission lines, ranking them as low-risk projects,” as an oversimplification and misrepresentation
8    of PG&E’s process for prioritizing repair and replacement of its transmission asset base. PG&E
9    adheres to a maintenance program under which it determines repair and replacement priorities for
10   transmission assets based on a variety of factors. Among the factors that PG&E considers beyond
11   asset age are public and employee safety, system criticality, customer impact, asset health,
12   maintenance records, inspection history, and operational considerations. (Ex. G, PGE-0037, Prepared
13   Rebuttal Test. of K. Dasso, Pacific Gas and Electric Co., Dkt. No. ER16-2320-002 (Oct. 9, 2017)
14   at 13.) While PG&E—like all utilities—has to make decisions about how to prioritize work, it has
15   done so based upon a multi-factored analysis that it has disclosed to its regulators.
16   PARAGRAPH 9 OF WALL STREET JOURNAL ARTICLE:
17          Among the problems, the utility has struggled to figure out which of its lines needed
            the most attention.
18
19   RESPONSE TO PARAGRAPH 9:
20 PG&E denies the generalized assertion that it “has struggled to figure out which of its lines
21 needed the most attention.” To identify and prioritize assets for repair and replacement, PG&E uses
22 data from multiple sources, including PG&E’s Systems, Applications and Products (“SAP”) database,
23 which stores inspection and maintenance records for transmission assets; the Electric Transmission
24 Geographic Information System, which stores known information about asset location, age,
25 manufacturer, ratings, configuration and type; and PG&E’s outage information database. While
26 PG&E strives to collect and maintain comprehensive information on the condition of its transmission
27 assets, the availability and quality of such data varies for a number of reasons, including PG&E’s
28
                                                     12
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 13 of 37
1 acquisition over time of smaller utilities that did not keep reliable asset age data. Currently, PG&E is
2 evaluating how to leverage the improved asset condition information provided by its recent enhanced
3 inspections.
4 The asset condition data available to PG&E are used as inputs to PG&E’s Risk-Informed
5 Budget Allocation (“RIBA”) process. In 2014, PG&E adopted that methodology for prioritizing
7 reliability and the environment. Other prioritization considerations include any mandatory work
9 projects.
16 lines below 500 kV before the Camp Fire. Even before the Camp Fire, however, PG&E’s policies did
17 require climbing inspections on its 500 kV lines at intervals of every three years for “critical steel
18   structures” and every 12 years for “non-critical steel structures”. In addition, PG&E’s policy called
19   for conducting climbing inspections on all transmission lines, including 115 kV lines, in response to
20 specific “triggering” events such as component defects identified by inspection, component failure,
21 fire hazards and suspected vegetation clearance issues. And, in the months before the Camp Fire,
23 Palermo 115 kV Transmission Line (not including Tower :27/222) as part of an effort to assess the
25 PG&E denies that it “began detailed inspections of its transmission lines only after the Camp
26 Fire that destroyed Paradise.” Prior to the Camp Fire, PG&E policy called for detailed ground
27 inspections of overhead transmission lines between 60 and 230 kV at least every five years, as well as
28
                                                     13
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 14 of 37
1 aerial patrols of such lines every year in which a detailed inspection was not performed. In addition to
2 inspecting and patrolling every transmission line mile on a routine basis, PG&E policy called for
3 infrared (“IR”) inspections every five years for all transmission assets and as triggered by specific
4 events.
5 PG&E has significantly enhanced its inspection efforts in Tier 2 and Tier 3 High Fire-Threat
6 Districts since the Camp Fire. As PG&E has publicly disclosed, those efforts have identified
7 thousands of conditions requiring repairs on PG&E’s system that had not been previously identified.
25 PG&E disagrees with the assertion that “[f]ederal and state regulators have paid little attention
26 to the condition of PG&E’s transmission system” and “have largely left it up to the company to decide
27 what to upgrade and when.” PG&E’s transmission system is governed by federal and state regulations
28
                                                       14
                                 RESPONSE TO REQUEST FOR INFORMATION
                                        Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 15 of 37
1 and a regulatory oversight regime. For example, CPUC General Order 95 (“GO 95”) imposes
2 requirements to which utilities like PG&E must adhere in constructing and maintaining overhead
3 power lines, including transmission lines. Those requirements apply to, among other things, the
4 vertical clearance of transmission line conductors (Section III, Rule 38), vegetation management
5 around transmission lines (Section III, Rule 35), and the requisite strength of materials used on electric
6 transmission systems, including on steel transmission towers (Section IV, Rule 48).
7 The CPUC enforces compliance with the foregoing standards through regular audits of
8 PG&E’s transmission facilities. CPUC staff may review PG&E’s inspection and maintenance records
9 at any time on 30 days’ notice. See Public Utilities Code § 314(a); GO 165 § IV; GO 95, Section I,
10 Rule 18(A)(1). Since 2010, the CPUC has elected to review PG&E’s inspection and maintenance
12 PG&E’s transmission system is also subject to oversight by the California Independent System
13 Operator (“CAISO”). CAISO, which was created by California state law and approved by FERC as a
14 FERC-jurisdictional Independent System Operator, coordinates transmission activities among its state
15 utility members, including PG&E, to help ensure the safe and reliable operation of the broader electric
16 grid. Each utility with facilities under CAISO’s operational control, including PG&E, must submit
17 detailed information regarding its maintenance practices to CAISO through filing a Transmission
18 Owner Maintenance Plan (“TOMP”), and also to the Western Electric Coordinating Council
19 (“WECC”) through filing a Transmission Maintenance Inspection Plan (“TMIP”). Each such utility is
20 also required to review those plans annually and is responsible for notifying CAISO and WECC of
21 any changes to its plans. (May 21, 2007 ISO Memorandum; WECC Standard FAC 501.) Further,
22 under FERC Order Number 890, CAISO also reviews certain proposed transmission projects by each
23 Transmission Owner, such as proposed system capacity upgrades, as part of an overall transmission
24 planning process.
25 Each year, CAISO also randomly selects up to 10% of PG&E’s transmission facilities and
26 station facilities (e.g., substations and switching stations) for review. (See ISO Maintenance Review
28
                                                     15
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 16 of 37
2 subject to review by federal and state regulators through the process surrounding PG&E’s annual
3 transmission owner filings with FERC. Such filings set forth PG&E’s spending plans for its
4 transmission system and request FERC authorization of proposed rates that PG&E seeks to charge for
5 its electric transmission services. Far from “le[aving] it up to [PG&E] to decide what to upgrade and
6 when,” as the WSJ Article claims, the CPUC has intervened in those proceedings to challenge
7 PG&E’s requests for rate increases. Indeed, much of the testimony by PG&E employees cited in the
8 WSJ Article was given in rate case proceedings where the CPUC disputed PG&E’s explanation that
9 required upgrades to its infrastructure justified its proposed rate increase. (See Ex. A, Initial Br. of the
10 CPUC, Pacific Gas and Electric Co., Dkt. No. ER16-2320-002 (Mar. 15, 2018) at 2-3.)
25
26
27
28
                                                      16
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 17 of 37
23
24
25
26
27
28
                                                     17
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 18 of 37
22
23
24
25
26
27
28
                                                    18
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 19 of 37
14 PG&E is not in a position to comment on whether the WSJ Article accurately quoted
15 Ms. Malashenko or presented her quoted statement in the context of her complete remarks. PG&E
16 does not dispute that it has “a lot of work to do” to address the current, unprecedented level of risk of
17 wildfire in its service territory, including the work described extensively in PG&E’s prior filings with
18 this Court.
20          The part of PG&E’s grid that includes the Caribou-Palermo line, known as the
            Caribou-Valona system, is so old that segments were considered candidates for the
21          National Register of Historic Places at one point by federal agencies. Approximately
            800 of the original steel towers built to hold up the transmission lines are still in use,
22
            according to PG&E correspondence with federal officials, uncovered through a public-
23          records request.
25 PG&E admits that federal agencies considered parts of the Caribou-Valona system, including
26 the section of the Caribou-Palermo 115 kV Transmission Line from the Caribou Powerhouse to the
27 Big Bend Switching Station, for inclusion on the National Register of Historic Places (“NRHP”). In
28
                                                     19
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 20 of 37
1 response to PG&E’s request for authorization to perform NERC work on the Caribou-Palermo line,
2 the United States Forest Service (“USFS”) took the position that the Caribou-Big Bend section of the
3 line is historically significant and should be included on the NRHP “for its association with key
4 historical events and trends in the development of long-distance hydroelectric transmission lines in
5 California.” (Ex. H, Ltr. from J. Bird, Forest Supervisor, USFS, to J. Polanco, State Historic
6 Preservation Officer (Mar. 13, 2019) at 2.) Based on that finding and the California State Historic
7 Preservation Officer’s concurrence, PG&E understood that the National Historic Preservation Act
8 required additional measures to accommodate the line’s eligibility for historic status before PG&E
10 PG&E admits that more than 800 original towers on the historical Caribou-Valona
11 transmission network, which includes the Caribou-Palermo 115 kV Transmission Line and ten other
12 lines, are still in place. As noted above, following the Camp Fire, the Caribou-Palermo 115 kV
28
                                                    20
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 21 of 37
1 was not included within the scope of the project because the conductor clearance on that span was
3 PG&E denies that “the company needed to replace 49 steel towers” on the Caribou-Palermo
4 115 kV Transmission Line because of their age and no other reason. Age, in and of itself, was not the
5 reason PG&E decided to replace the towers. Rather, the older design of the towers made them
6 unsuitable for other methods for increasing the vertical clearance of the conductors, such as adding
7 extensions to raise the height of the towers. As the 2018 Forest Service memorandum states:
8           “Tower replacements are planned due to age and type of the existing steel lattice
            towers. The existing towers are approximately 100 years old and are directly buried
9           grillage with no concrete foundations. The towers are not considered structurally
            suited to the addition of lattice steel cage top, waist cage, or other extensions to raise
10
            the heights of the towers.” (Ex. I, Memorandum Regarding PG&E NERC Program
11          (Jan. 3, 2018) at 2 (emphasis added).)
12 Similarly, PG&E also denies that it was planning to replace conductor segments due to age and
13 integrity and no other reason. The conductor was scheduled to be replaced as a consequence of the
14 planned installation of taller replacement towers. As the 2018 Forest Service memorandum states, the
15 conductor on certain spans needed to be replaced because it did “not have adequate strength to
16 withstand the increased tension resulting from installing taller replacement structures.” (Id. at 5.)
17 PG&E is not in a position to comment on whether the Wall Street Journal obtained the
24 PG&E understands Paragraph 25 to refer to NERC Alert-related work. As stated above, the
25 purpose of that work was not to identify and fix worn or broken parts, but rather to address issues
27
28
                                                     21
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 22 of 37
1 PG&E acknowledges that the planning, timing and completion date for specific NERC Alert
2 projects has changed for a variety of reasons, including prioritization of work across the system and
3 engineering, permitting and operational reasons. Overall, PG&E has made significant progress toward
4 addressing NERC Alert work across its system, and has provided regular updates on its progress to
5 WECC. Specifically, PG&E has addressed more than 10,000 conductor clearance issues out of the
6 approximately 11,500 identified for work as part of that program (approximately 88%) along hundreds
8 PG&E has completed all NERC mitigation work on 7 of the 11 in-service transmission lines in
9 the vicinity of Plumas National Forest on which PG&E identified conductor clearance issues,
10 addressing a total of approximately 120 identified clearance issues on those lines. PG&E has some
11 outstanding NERC mitigation work on three in-service transmission lines in the vicinity of Plumas
12 National Forest. On those three lines, PG&E has thus far addressed all but approximately five of the
25
26
27
28
                                                    22
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 23 of 37
15 PG&E admits that it is not always able to determine the exact age of towers and wires on its
16 transmission lines, including lines that it has acquired from other companies over the course of more
17 than 100 years, and that PG&E commissioned Quanta Technology to assess the age and condition of
18 transmission structures (as well as other transmission components and assets) throughout its service
19 territory.
21           The firm was unable to determine the age of about 6,900 towers in the 115-kilovolt
             system. It found that nearly 30% of the remaining towers in that system, more than
22           3,500, were installed in the 1900s and 1910s. About 60% of the structures in the 230-
             kilovolt system were built between 1920 and 1950.
23
25 PG&E admits Paragraph 29 and refers to its response to Paragraph 28. PG&E further notes
26 Quanta Technology’s observation that “[l]attice steel structures installed in the 1920s in the US utility
27 industry remain in service in many locations” and that transmission tower age data from six utilities,
28
                                                    23
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 24 of 37
1 including PG&E, “demonstrate[d] that structures remain in service in the utility industry well into
2 seven or eight decades, even longer in some cases.” (Ex. F, Quanta Study, “Structures” Chapter,
3 at 20-21.)
27
28
                                                     24
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 25 of 37
5 PG&E understands that Mr. Martinez told the Wall Street Journal that he could not recall the
6 2010 Quanta Study or its recommendations, but that he felt PG&E was doing enough with regard to its
8 PG&E admits that its policies prior to the Camp Fire did not require routine climbing
9 inspections of transmission lines below 500 kV. PG&E’s policies did require, for all transmission
28
                                                     25
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 26 of 37
1 influence over PG&E’s transmission maintenance planning because the rates it authorizes will
2 ultimately determine the extent to which PG&E can recover the costs of planned capital and
3 maintenance work on its transmission lines and, thus, the proportion of that work that is economically
5 Under that regulatory framework for cost recovery, PG&E is required to provide detailed
6 information on proposed spending in its transmission revenue requirement filings. PG&E provides
7 that information because that is what FERC and federal law require. See 18 C.F.R. § 35.1 (requiring
8 utilities to file “full and complete rate schedules and tariffs . . . clearly and specifically setting forth all
9 rates and charges for any transmission or sale of electric energy subject to the jurisdiction of this
10 Commission,” as well as “the classifications, practices, rules and regulations affecting such rates”).
11 Federal regulations further require that PG&E provide significant data in support of requested rate
12 increases, including comparative information about past rates, detailed cost of service information,
13 “work papers” that provide “a comprehensive explanation of the bases for the adjustments or
15 PG&E also disagrees with the overbroad statement that “[p]rojects that involve routine
16 maintenance, such as replacing aging towers, hardware and conductors, don’t require state or federal
17 approval.” While specific types of routine maintenance such as component replacement may not
18 require such approval, projects that involve replacement of entire transmission towers, taking lines out
19 of service, or performing work on federal land may require coordination with and, in certain
20 circumstances, approval by state and federal regulators, including the CPUC, CAISO and USFS.
25 PG&E denies Paragraph 33. PG&E understands the statement that “California regulators’ . . .
26 rules for transmission are three sentences long” to be a reference to Part IV of CPUC General Order
27 165 (“GO 165”). That Part, titled “Transmission Facilities”, provides as follows:
28
                                                        26
                                 RESPONSE TO REQUEST FOR INFORMATION
                                        Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 27 of 37
1           “Each utility shall prepare and follow procedures for conducting inspections and
            maintenance activities for transmission lines. Each utility shall maintain records of
2           inspection and maintenance activities. Commission staff shall be permitted to inspect
            records and procedures consistent with Public Utilities Code Section 314 (a).”
3
4           While that specific provision in GO 165 is brief, there exist other, more detailed CPUC
5    General Orders that regulate California utilities’ transmission operations. Among those other General
6    Orders is GO 95 on Rules for Overhead Electric Line Construction, which contains detailed
7    requirements regarding the construction and maintenance of both transmission and distribution lines
8    (Section I, Rules 12.1, 12.2); minimum safety factors and loading requirements for transmission lines
9    (Section IV, Rules 43 & 44.1); material and strength requirements for towers, conductors, insulators,
10   guys and anchors (Section IV, Rules 48 & 49; Section VI, Rules 61.3 & 65); vegetation management
11   around transmission lines (Section III, Rule 35); and ground-to-conductor, conductor-to-conductor and
12   other clearance requirements for transmission lines (Section III, Rules 37-39; Section VI, Rule 64.4).
13   Other General Orders that apply to transmission lines include General Order 131-D on Planning and
14   Construction of Facilities for the Generation of Electricity and Certain Electric Transmission Facilities
15   and General Order 128 on Construction of Underground Electric Supply and Communication
16   Systems.
17   PARAGRAPH 34 OF WALL STREET JOURNAL ARTICLE:
         With no regulator keeping a close eye, the timetable for completing important upgrades
18
         slipped. PG&E told federal regulators it planned to overhaul the Caribou- Palermo line
19       in 2013, yet it still hadn’t made improvements when a piece of hardware holding a
         high-voltage line failed last November, sending sparks into the grass and igniting the
20       Camp Fire.
21   RESPONSE TO PARAGRAPH 34:
22          PG&E denies that “no regulator keep[s] a close eye” on PG&E’s transmission operations for
23   the reasons described above. PG&E regularly submits filings with FERC that contain detailed
24   information on planned upgrades to PG&E’s transmission lines, including expected timeframes for
25   completion of work. PG&E is also accountable to other regulators, including the CPUC, which has
26   intervener status in PG&E’s transmission rate cases; CAISO, which has operational control over
27
28
                                                    27
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 28 of 37
1 PG&E’s transmission facilities; and NERC and WECC, to which PG&E submits regular reports
2 regarding its progress toward bringing the vertical clearance of its transmission lines into compliance
4 PG&E acknowledges that it informed FERC in 2013 of a plan to relocate certain towers on the
5 Caribou-Palermo 115 kV Transmission Line. PG&E denies that such work constituted an “overhaul”
6 of the line. Rather, the project called for replacing and relocating 10 towers along the line, comprising
7 the approximately one-mile span from Tower :7/55 to Tower :8/64, across the river to a more easily
8 accessible area near the Caribou-Table Mountain 230 kV Transmission Line. Tower :27/222, the
9 tower identified as the ignition point of the Camp Fire, is many miles away from those towers and no
10 work was contemplated on it as part of this tower relocation project. PG&E later determined that
11 relocation of the towers was unnecessary because it could reasonably access the towers through some
12 additional roadwork, and the condition of the towers could be addressed through maintenance.
28
                                                    28
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 29 of 37
1 worn parts. Tower :27/222, which initiated the Camp Fire, was not within the scope of the project
2 because PG&E determined that the conductor clearance on that span was compliant with applicable
10 PG&E admits that in an October 18, 2017 email to USFS officials, PG&E Principal Land
11 Planner Paul Marotto wrote that “PG&E’s planned maintenance includes structure replacement,
13 modifications.” (Ex. J, Email from P. Marotto (Oct. 17, 2017).) Mr. Marotto’s email further states
14 that the purpose of the work was “to mitigate NERC discrepancies (ground to wire clearances).” (Id.)
15 As to the statement that “PG&E officials said the work was needed in part because the strength
16 of the aging towers and wires had deteriorated”, PG&E refers to its response to Paragraph 24 above.
18          Asked about the email, PG&E said it still disputes that the work was maintenance
            related, saying it was needed to adhere to 2010 industry guidelines that called on
19          companies to ensure their transmission lines met design specifications.
20   RESPONSE TO PARAGRAPH 37:
21          PG&E admits that it told the Wall Street Journal that the NERC Alert work on its transmission
22   lines was not for the purpose of identifying and fixing broken or worn parts, but rather to address
23   issues relating to the clearance of conductors. That statement was accurate.
24
25
26
27
28
                                                    29
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 30 of 37
20                  “A. It depends on the asset class, and each of those engineers are
                    familiar with the data that is available to them. They know where to
21                  find it. They also know that not all of the data is exactly perfect.
22                  “However, they know, as we’ve provided in responses to data requests,
                    the age of substation transformers, for example. That information is
23
                    available. It’s readily available. The engineers that work in that space
24                  have that information available to them, and they use that regularly in
                    their criteria or in their implementation of the replacement criteria.
25
                    “Q. A PG&E engineer, program manager who’s working on a specific
26                  asset class will simply know where to find the data to run the 1 to N
                    analysis?
27
28
                                                    30
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 31 of 37
1 “A. Yes.
5                   “Q. A listing of where all the data is available for a particular asset
                    class. It’s not identified, so if that project manager gets hit by a bus,
6                   somebody else can run the analysis? Are there no procedures in place at
                    PG&E to have this information shared and ensure that the analysis that
7                   is run looks at all the data and not just selective data?
8                   “A. In some cases, we have procedures that lay that out in some detail,
                    and in other cases we do not. We do not have in all cases the exact
9
                    cookbook instructions for how an engineer precisely does his job to
10                  produce the information necessary to create the recommendations.
27
28
                                                    31
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 32 of 37
1 $2.7 billion were assigned higher RIBA scores than NERC Alert-related work on the Caribou-Big
7 PG&E admits that it told the Wall Street Journal that it has taken a number of steps to improve
8 its records regarding the age and condition of its assets. That statement was accurate. PG&E
16 PG&E admits Paragraph 41 and notes that no structure on either of the two Ignacio-Mare
17 Island 115 kV Transmission Lines is situated in a Tier 2 or Tier 3 High Fire-Threat District. As
18 discussed in its response to Paragraph 42, much of the circuit runs through wetlands.
20          PG&E has repeatedly delayed work on the line, which has segments sagging too close
            to the ground, since first proposing it in 2014, federal regulatory filings show. The
21          $6.9 million project, which involves increasing the height of 44 towers, was initially
            expected to be completed in 2015 but now is slated to start next year, the company said.
22
25 Island 115 kV Transmission Lines. The planned NERC mitigations for PG&E transmission lines will
26 address vertical conductor clearance issues on 185 towers through a combination of tower
27 modifications and replacements and conductor replacements. PG&E admits that since work on the
28
                                                   32
                              RESPONSE TO REQUEST FOR INFORMATION
                                     Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 33 of 37
1 line was first proposed in 2014, it has been delayed due to engineering, operational and environmental
2 reasons, as well as the need to prioritize work on the hundreds of lines within the scope of PG&E’s
3 NERC Alert program. Among other issues, extensive permitting is required for this work because
4 many of the towers on the Ignacio-Mare Island 115 kV Transmission Lines run through the
5 Napa-Sonoma Marshes Wildlife Area and the San Pablo Bay National Wildlife Refuge, both sensitive
6 wetland environments with endangered species. Geological studies in these environmentally sensitive
7 areas that require permits are also required before engineering can continue. PG&E submitted its
8 application in June 2018 and received all approvals needed to proceed with those studies in May 2019.
9 This work is currently forecasted to be completed in three phases from 2020 to 2023.
10 PG&E further notes that the $6.9 million referenced in Paragraph 42 refers to the projected
11 cost for only one of these phases as of the date of the relevant regulatory filing. The total cost for all
28
                                                      33
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 34 of 37
1 each project to become operational. PG&E re-prioritizes projects for a variety of reasons, including
2 delays in obtaining necessary permits, unanticipated engineering challenges, and the need to obtain
3 clearances to perform the work, among other reasons. Shortly after the Camp Fire, PG&E suspended
4 the project in the interest of preserving potential evidence related to the Camp Fire. The entire
5 Caribou-Palermo 115 kV Transmission Line has been permanently de-energized since December
28
                                                    34
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 35 of 37
1 mitigating the identified conductor clearance issues. The current operational date of 2021 was chosen
2 based on the anticipated time required to acquire a permit from the USFS to proceed with the project.
22
23
24
25
26
27
28
                                                    35
                               RESPONSE TO REQUEST FOR INFORMATION
                                      Case No. 14-CR-00175-WHA
        Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 36 of 37
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
                                                        36
                                RESPONSE TO REQUEST FOR INFORMATION
                                       Case No. 14-CR-00175-WHA
      Case 3:14-cr-00175-WHA Document 1078 Filed 07/31/19 Page 37 of 37
1
                                                           Respectfully Submitted,
2
     Dated: July 31, 2019                                  JENNER & BLOCK LLP
3
4
                                                     By:     /s/ Reid J. Schar
5                                                           Reid J. Schar (pro hac vice)
6
                                                           CRAVATH, SWAINE & MOORE LLP
7
                                                     By:     /s/ Kevin J. Orsini
8                                                          Kevin J. Orsini (pro hac vice)
9
                                                           CLARENCE DYER & COHEN LLP
10
13
14
                                                     Attorneys for Defendant PACIFIC GAS AND
15                                                   ELECTRIC COMPANY
16
17
18
19
20
21
22
23
24
25
26
27
28
                                            37
                            RESPONSE TO REQUEST FOR INFORMATION
                                   Case No. 14-CR-00175-WHA