         GOVERNMENT OF INDIA
          MINISTRY OF POWER
               फ़रिरी – २०१९
              February – 2019
                     1
2
Sl. No.                                          Contents                                         Page
                                                                                                   No
                                      SUMMARY
 1.0      12th Plan Capacity Addition Programme                                                    01
 1.A      Total Capacity Addition (MW) During 12th Plan                                            01
 1.B      Year wise Sector wise Thermal capacity Addition Target / Achievement during 12th Plan    01
 1C       Sector-wise break up of under construction Thermal Power Projects                        01
 1D       Thermal capacity added during the year 2018-19                                           01
 2.0      Thermal Capacity Addition Target/ Achievement for the year 2012-13                      02-03
 2.1      Thermal Capacity Addition Target/ Achievement for the year 2013-14                      04-05
 2.2      Thermal Capacity Addition Target/ Achievement for the Year 2014-15                      06-07
 2.3      Thermal Capacity Addition Target/ Achievement for the Year 2015-16                      08-09
 2.4      Thermal Capacity Addition Target/ Achievement for the Year 2016-17                       10
 2.5      Thermal Capacity Addition Target/ Achievement for the Year 2017-18                       11
 2.6      Thermal Capacity Addition Programme (RFD) for the year 2018-19                           12
 3.0      Target/Achievement of Thermal Cap. Addition During 12th Plan                            13-19
 4.0      Thermal Projects Slipped from 12th Plan Target with reason for slippage                 20-21
 5.0      Thermal Power Projects under construction in the country                                22-25
                                       CENTRAL SECTOR PROJECTS
  1.      NATIONAL THERMAL POWER CORPORATION LTD.                                                 27-41
          Bongaigaon TPS, Distt: Kokrajhar, Assam                                                  27
          Barh STPP St-I, Dist: Patna, Bihar                                                       28
          Nabinagar TPP, Dist: Aurangabad, Bihar                                                   29
          New Nabinagar STPP, Dist.: Aurangabad, Bihar                                             30
          Lara STPP, Dist:Raigarh, Chhattisgarh                                                    31
          North Karanpura STPP, Dist.Chatra, Jharkhand                                             32
          Kudgi STPP St-I, Dist: Bijapur, Karnataka                                                33
          Solapur STPP, Dist: Solapur, Maharashtra                                                 34
          Gadarwara STPP, St–I, Dist: Narsinghpur, Madhya Pradesh                                  35
          Khargone STPP, Dist.Khargone, M.P                                                        36
          Darlipalli STPPSt-I, Dist. Sundergarh, Odisha                                            37
          Telangana TPP (Ph-I), Dist. Karim Nagar Telangana                                        38
          Meja STPP, Dist:Allahabad, U.P                                                           39
          Tanda-II STPP, Dist. Ambedkar Nagar, U.P.                                                40
          Patratu TPS, Dist:, Jharkhand. (JV of NTPC & Govt. of Jharkhand)]                        41
          Rourkela PP-II Expension, Odisha                                                         42
  2.      NLC                                                                                     43-46
          Neyveli New TPP,M/s Neyveli Lignite Corporation Ltd. at Neyveli in Tamil Nadu            43
          Ghatampur TPP,JV of NLC & UPRVUNL,Lahurimau village,Ghatampur,Kanpur                     44
          Barsingsar TPP ext, (Distt. Bikaner ), Rajastan                                          45
          Bithnok TPP, (Distt. Bikaner ), Rajastan                                                 46
                                  STATE & PRIVATE SECTOR PROJECTS
                                                Northern Region
  3.      Rajasthan                                                                               49-50
          Chhabra SCTPP, Chhabra RRVUNL, (Distt. Baran )                                           49
          Suratgarh Super Critical TPP, RRVUNL, Suratgarh                                          50
  4.      Uttar Pradesh                                                                           51-56
          Prayagraj TPP, Distt. Bara, Allahabad, M/s Prayagraj Power Generation Co. Ltd.           51
          Harduaganj Expn.,-II, UPRVUNL, Distt.; Aligarh                                          52-53
          Obra-C TPP, UPRVUNL, Obra, Dist. Sonebhadra                                              54
          Jawaharpur STPP, JVUNL( A 100% subsidiary of UPRVUNL), Dist. Etah                        55
          Panki TPS Ext, Distt. Kanpur, U.P. (UPRVUNL)  3                                          56
  5.      Uttarakhand                                                                             57-58
          Kashipur Gas Based CCPP, Ph-II, Udhamsingh Nagar (M/s Sravanthi Energy Pvt. Ltd.)        57
      BETA CCPP, Module-I, at Kashipur Udhamsingh Nagar                                  58
      (M/s Beta Infratech Pvt. Ltd.)
                                         Western Region
6.     Chhattisgarh                                                                     60-67
       Akaltara(Nariyara) TPP, Distt: jangir-Champa                                      60
        M/s KSK Mahanadi Power Company Ltd
       Uchpinda TPP Ph-I, R.K.M Power, Janjgir Champa District, Chhattisgarh             61
       Lanco Amarkantak Mega TPS Phase-II (Pathadi ),                                    62
       (Distt. Korba ) M/s LAP Pvt. Ltd.
      Salora TPP , Katghora Tal; Distt. Korba, M/s Vandana Vidyut Ltd                    63
      Deveri TPP Raigarh TPP (Visa) (VISA Raigarh STPP, Ph-I,) (Distt: Jangir Champa)    64
       M/s VISA Power Ltd.
       Singhitarai TPP ( DumatpalliTPP), Janjgir (Vill), Champa Distt.                   65
      (M/s Athena Chhattisgarh Power Ltd)
       Binjkote TPP, Vill-Binjkote, Distt.: Raigarh,                                     66
       SKS power Gen. (Chhattisgarh.) Ltd
       Nawapara TPP (TRN TPP), Distt: Raigarh, M/s TRN Energy Pvt Ltd                    67
 7.    Gujarat                                                                          68-68
       Wanakbori TPS Extn., GSECL, Dist: Kheda                                           68
8.     Madhya Pradesh                                                                   69-72
       Shree Singaji TPP, Stage –II, (At Dongalia Distt. Khandwa), MPPGCL                69
       Mahan TPP, Dist. Singrauli, Essar Power MP Ltd.                                   70
       Gorgi TPP , Dist. Singrauli, DB Power (MP) Ltd.                                   71
       Niwari TPP , Dist. Narsinghpur, BLA Power Ltd.                                    72
9.     Maharashtra                                                                      73-79
       Amravati TPP , Ph-II, (Distt: Amravati)                                           73
       M/s RattanIndia Power Ltd.(Formermerly known as Indiabulls Power Ltd.)
       Nasik TPP, Ph-I, Distt: Nasik                                                     74
       M/s RattanIndia Nasik Power Ltd.(Formerly known as Indiabulls Realtech Ltd.)
       Nasik TPP, Ph-II, Distt: Nasik                                                    75
       M/s RattanIndia Nasik Power Ltd.(Formerly known as Indiabulls Realtech Ltd.)
       Lanco Vidarbha TPP, Distt: Wardha,                                                76
       M/s Lanco vidarbha Thermal Power Ltd.
       Bijora Ghanmukh TPP, Distt: Yavatmal                                              77
       M/s Jinbhuvish Power Generations Pvt. Ltd. (JPGPL)
       Shirpur Power Private Ltd. Distt. Dhule, Maharashtra                              78
       Bhusawal TPP, Distt. Jalgaon, Maharashtra                                         79
                                              Southern Region
10.    Andhra Pradesh                                                                   81-85
        Rayalaseema TPP St-IV, (M/s. APGENCO), Distt.Cuddapah                            81
       Sri Damodaram Sanjeevaiah TPP St-II (Krishnapatnam), (APPDCL) Distt.Nellore       82
       Dr. Narla Tata Rao TPP, Distt. Vijayawada, AP (APGENCO)                           83
       Thamminapatnam TPP Ph-II, Thamminapatnam, Distt.: SPSR Nellore, AP                84
       (M/s Meenakshi Energy Pvt.Ltd.),
        Bhavanapadu TPP Ph-I, Distt.: Srikakulam, (M/s East Coast Energy Pvt. Ltd.)      85
11.    Telangana                                                                        86-88
       Kothagudem TPS –VII (TSGENCO) Distt. Kammam                                       86
       Bhadradri TPP (TSGENCO), Distt. Khammam                                           87
       Yadadri TPP (TSGENCO), Distt. Nalgonda, Telangana                                 88
12.    Karnataka                                                                        89-89
       Yelahanka Combined Cycle Power plant.                                             89
13.    Tamil Nadu                                                                       90-96
       Ennore SEZ SCTPP, Distt. Thiruvallur, TANGEDCO                                    90
       Uppur SCTPP, Distt. Ramnad, T.N, TANGEDCO                                         91
       North Chennai TPP St-III, Distt. Thiruvallur, TANGEDCO                            92
       Ennore SCTPP, Distt. Thiruvallur TANGEDCO                                         93
       TuiticorinTPP St-IV, Distt. Tuticorin, Tamil Nadu,                                94
                                                  4
      M/s SEPC Power Pvt. Ltd.
      Tuticorin TPP, Tamil Nadu (Ind. Barath Power Limited)                                  95
      Udangudi STPP, TANGEDCO (Distt. Thoothukudi) Tamil Nadu                                96
                                             Eastern Region
14.   Bihar                                                                                 98-99
      Barauni Extn TPS, P.O.: Barauni, Dist: Begusarai Bihar -742237 (BSPGCL)                 98
      Siriya TPP, (JAS INFRA), Village.: Siriya, Dist.: Banka Bihar                           99
15.   Jhakhand                                                                             100-101
      Matri Shri UshaTPP, Distt. Latehar, Jharkhand                                          100
       M/s Corporate Power Ltd.
      Tori TPP Essar Power (Jharkhand) Ltd. Distt. Angarha Latehar Jharkhand                 101
16.   Odisha                                                                               102-106
      Ib Valley TPP, Village: Banaharpalli, Dist: Jharsaguda                                 102
      (OPGC)
      Ind Barath TPP, Distt-Jharsuguda                                                      103
      M/s Ind-Barath Energy (Utkal) Ltd.
      Lanco Babandh TPP, Distt-Dhenkanal                                                    104
       (M/s Lanco Babandh Power Ltd.)
      Malibrahmani TPP, Distt-Angul, M/s Monnet Ispat                                       105
      KVK Nilachal TPP, Ph-I Kandarei, Distt-Dhenkanal, Odisha                              106
      M/s KVK Nilanchal Ltd
17.   West Bengal                                                                          107-107
      Hiranmaye Energy Limited, PO-Shibramnagar, Haldia, Dist.- Purba Medinipur- 721635,     107
      West Bengal, India Power Corporation (Haldia) Ltd.,
                                        North-Eastern Region
18.   Assam                                                                                109-109
      Namrup Replacement Power Project, Distt: Dibrugarh, Assam APGCL                        109
      Lakwa Replacement Power Project, Distt: Shivsagar, Assam APGCL                         110
19    List of Abbreviations                                                                  111
                                                5
 1.0 12th Plan Capacity Addition:
1.A. Targeted Capacity Addition (MW) during 12th Plan
1.B. Year wise Sector wise Thermal capacity Addition Achievement against Revised Target during
     12th Plan:
                                                                                                       ( in MW)
         Year                    Thermal capacity addition during 12th Plan (MW)            Revised        %
                                                                                            Target    Achievement
                           Central        State                Private            Total
         2012-13           5023.3         3911                 11187.5           20121.8    15154.3    132.78%
         2013-14            1660          3322                 11785              16767     15234.3    110.06%
         2014-15           2659.2        4886.1                13285             20830.3    14988.3    138.98%
         2015-16           3295.6         6460                 12705             22460.6    17346.1    129.49%
         2016-17           3230.5       3622.25                 4698            11550.75    13440.5     85.94%
         Total            13463.6       21151.35               53660.5          91730.45    76163.5    126.81%
                                  SECTOR                   CAPACITY
                                                             (MW)
                                 CENTRAL                       22380
                                  STATE                       22166.15
                                 PRIVATE                       24135
                                  TOTAL                       68681.15
   State                   Project Name                  Impl Agency           Unit No       LOA Date           BTG       Targeted   Actual Cap.            Comm. Date                 COD
                                                                                                               Supplier     Cap.       comm.       Envisaged at the   Ant. /Act(A)
                                                                                                                           (MW)        (MW)         beginning of
                                                                                                                                                        year
CENTRAL SECTOR
Chhattisgarh Sipat -I                            NTPC                          U-3          Apr-04              Others       660         660            06/12         02.06.12(A)    01.08.2012
Haryana      Indira Gandhi TPP                   APCPL                         U-3          Jul-07              BHEL         500        500             12/12         07.11.12(A)    26.04.2013
Jharkhand    Kodarma TPP                         DVC                           U-2          Jun-07              BHEL         500        500              12/12        15.02.13(A)    14.06.2014
Maharashtra  Mouda TPP                           NTPC                          U-1          Nov-08              BHEL         500         500            07/12         19.04.12(A)    13.03.2013
Maharashtra  Mouda TPP                           NTPC                          U-2          Nov-08              BHEL                     500                          29.03.13(A)     March 14
MP           Vindhyachal TPP-IV                  NTPC                          U-11         Jan-09              BHEL         500         500            07/12         14.06.12(A)    01.03.2013
MP           Vindhyachal TPP-IV                  NTPC                          U-12         Jan-09              BHEL                     500                          22.03.13(A)     March 14
TN           Vallur TPP Ph-I                     NTECL                         U-2          Aug-07              BHEL        500          500            02/13         28.02.13(A)    25.08.2013
Tripura      Tripura Gas                         ONGC                         Module-1      Jun-08              BHEL       363.3        363.3           11/12         03.01.13 (A)   04.01.2014
UP           Rihand TPP-III                      NTPC                          U-5          Feb-09              BHEL        500          500            06/12         25.05.12(A)    19.11.2012
                                                                                         Total Central Sector              4023.3      5023.3
STATE SECTOR
Chhattisgarh Korba West Extn.St.III TPP          CSEB                          U-5                               BEHL                   500                           22.03.13(A)    05.09.2013
Chhattisgarh Marwa TPP                           CSEB                          U-1              Apr-08           BHEL       500                         02/13           Slipped
    Delhi    Pragati CCGT - III                  PPCL                          GT-3             May-08          BHEL        250         250              08/12        27.06.12(A)    28.10.2013
             Pipavav CCPP                        GSECL                         Block-2          Dec-07          BHEL        351         351             01/13         27.03.13(A)    27.03.2013
   Gujarat
             Ukai TPP Extn                       GSECL                         U-6              Sep-07          BHEL        490          490            12/12         05.03.13(A)    08.06.2013
             Ramgarh CCGT                        RRVUNL                        GT               Aug-09          BHEL        110          110            01/13         20.03.13(A)    06.12.2013
  Rajasthan
             Ramgarh CCGT                        RRVUNL                        ST-1                             BHEL         50                          02/13          Slipped
     MP      Satpura TPP Extn.                   MPPGCL                        U-10             Mar-08          BHEL        250         250              02/13        22.03.13(A)    18.08.2013
             Mettur TPP Ext                      TNEB                          U-1              Aug-08          Chinese     600          600             06/12        11.10.12(A)    12.10.2013
     TN
             North Chennai Extn.                 TNEB                          U-2              Aug-08          BHEL        600         600              03/13        09.03.13(A)    08.05.2014
             Harduaganj Ext                      UPRVUNL                       U-9              Jun-06          BHEL        250          250            05/12         25.05.12(A)    10.10.2013
     UP      Parichha Extn                       UPRVUNL                       U-5              Jun-06          BHEL        250          250            06/12         24.05.12(A)    17.07.2012
             Parichha Extn                       UPRVUNL                       U-6                                          250         250              09/12        11.03.13(A)    18.04.2013
                                                                                         Total -State Sector                3951        3911
PRIVATE SECTOR
              Simhapuri TPP Ph-1                 Madhucon Projects Ltd.        U-2              Jan-09          Chinese      150        150             09/12         02.07.12(A)    15.07.2012
     AP       Thamminapatnam TPP-I               Meenakshi Energy Pvt. Ltd.    U-1                              Chinese      150        150              08/12        09.09.12(A)    07.10.2012
                                                                                                Aug-09
              Thamminapatnam TPP-I               Meenakshi Energy Pvt. Ltd.    U-2                                           150                         11/12          Slipped
              Kasaipalli TPP                     M/s ACB (India)               U-2              Nov-08      Chinese          135        135             06/12         21.06.12(A)    21.06.2012
              Salora TPP                         M/s Vandna Vidyut             U-1              Nov-08      Chinese          135                         12/12          Slipped
 Chhattisgarh
              Swastik Korba TPS                  ACB                           U-1                          Others            25                         06/12          Slipped
              Ratija TPP                         SCPL                          U-1                          Chinese                      50                           04.02.13(A)    27.02.2013
              Mundra Ultra Mega TPP              Tata Power Co.                U-2              May-07      Others           800        800             12/12         25.07.12(A)    28.07.2012
              Mundra Ultra Mega TPP              Tata Power Co.                U-3              May-07      Others                      800                           16.10.12(A)    27.10.2012
              Mundra Ultra Mega TPP              Tata Power Co.                U-4              May-07      Others                       800                          16.01.13(A)    21.01.2013
   Gujarat
              Mundra Ultra Mega TPP              Tata Power Co.                U-5              Jun-07      Others                       800                          18.03.13(A)    22.03.2013
              UNO-SUGEN CCPP                     Torrent Power Ltd.            Mod-1                        Others                      382.5                         20.01.13(A)    04.04.2013
              Salaya TPP                         ESSAR                         U-2              Nov-07      Chinese          600         600            08/12         13.06.12(A)    15.06.2012
   Haryana    Jhajjar TPP (Mahatma Gandhi TPP)   CLP Power India Pvt. Ltd.     U-2              Jan-09      Chinese          660         660            04/12         11.04.12(A)    19.07.2012
              Adhunik Power TPP                  Adhunik Power Co. Ltd.        U-1              May-09       BHEL            270        270             09/12         19.11.12(A)    21.01.2013
  Jharkhand
              Adhunik Power TPP                  Adhunik Power Co. Ltd.        U-2              May-09       BHEL                       270                           29.03.13(A)    19.05.2013
                                                                                            2
   State                   Project Name                     Impl Agency               Unit No      LOA Date         BTG        Targeted   Actual Cap.            Comm. Date                 COD
                                                                                                                   Supplier      Cap.       comm.       Envisaged at the   Ant. /Act(A)
                                                                                                                                (MW)        (MW)         beginning of
                                                                                                                                                              year
              Corporate Power Ltd Ph-I (Maitrishi                                    U-1              Dec-09        BHEL          270                        12/12            Slipped
                                                    M/s Corporate Power Ltd.
              Usha)
              Bela TTP-I                            IEPL                             U-1              Dec-08      BHEL            270        270              09/12         20.03.13(A)   18.07.2013
              Butibori TPP                          Vidarbha Industries Power Ltd    U-2              Dec-09      Chinese         300         300            08/12         17.08.12 (A)   04.04.2013
              EMCO Warora TPP                       EMCO Energy Ltd. (GMR)           U-1              Sep-09      Chinese         300        300             11/12          07.02.13(A)   19.032013
              Tirora TPP Ph-I                       Adani Power Ltd                  U-1                          Chinese         660        660             08/12          11.09.12(A)   23.09.2012
Maharashtra   Tirora TPP Ph-I                       Adani Power Ltd                  U-2              Feb-08                      660        660              11/12         25.03.13(A)   30.03.2013
              Tirora TPP Ph-II                      Adani Power Ltd                  U-1                                          660                         02/13           Slipped
              GEPL TPP                              GEPL Pvt. Ltd.                   U-2              Mar-09       Chinese                   60                             28.04.12(A)
              GEPL TPP                              GEPL Pvt. Ltd.                   U-1                           Chinese                   60                             08.09.12(A)   09.05.2012
              Amaravathi TPP Ph-I                   Indiabulls                       U-1                           BHEL                      270                            25.03.13(A)   03.06.2013
              Bina TPP                              Bina Power Ltd.                  U-1              Sep-08         BHEL         250       250              09/12         12.08.12(A)    30.08.2012
   MP         Bina TPP                              Bina Power Ltd.                  U-2              Sep-08         BHEL                   250                            31.03.13(A)    07.04.2013
              Mahan                                 Essar Power Ltd.                 U-1                             Chinese                 600                           24.02.13(A)    29.04.2013
              Sterlite TPP                          Sterlite Energy Ltd.             U-4              Sep-08         Chinese      600        600             06/12          25.04.12(A)   26.04.2012
  Orissa
              Kamalanga TPP                                                          U-1                             Chinese                 350                            29.03.13(A)   25.03.2014
              Jallipa- Kapurdi TPP                                                   U-5              Mar-07         Chinese      135        135             03/13          05.02.13(A)   05.02.2013
                                                                                     U-6              Apr-07         Chinese                 135                            03.03.13(A)   03.03.2013
 Rajasthan                                           Raj west power Ltd (JSW)
                                                                                     U-7              Jun-07         Chinese                 135                            16.03.13(A)   16.03.2013
                                                                                     U-8             May-07          Chinese                 135                            28.02.13(A)   28.02.2013
    TN        Tuticorin TPP                         Ind Barath                       U-1                             Chinese                 150                            10.03.13(A)   07.02.2013
                                                                                               Total -Private Sector             7180      11187.5
                                                                           Total for the year 2012-13                          15154.3     20121.8
                                                                                                  3
  2.1 Thermal Capacity Addition Target/ Achievement for the Year 2013-14
State           Project Name                                   Impl Agency                 Unit No   LOA Date         BTG Supplier     Targeted   Actual Cap.    Actual          At the          COD
                                                                                                                                      Cap. (MW)     comm.        Comm.        beginning of
                                                                                                                                                     (MW)         Date          the year
CENTRAL SECTOR
                                                                                                       03/08&                                                                12/13           15.11.2014
Bihar           Barh STPP St-II                                    NTPC                       4                             BHEL         660         660         30/11/13
                                                                                                        10/08
TN              Vallur TPP Ph-I                         NTPC/ NTECL/ TNEB-JV                   3        07/09               BHEL        500          500        28.02.2014   03/14           26.02.2015
TN              Tuticorin TPP                              NLC/ TNEB-JV                        1        01/09               BHEL        500                      Slipped     03/14
Tripura         Tripura CCGT                                  ONGC JV                     Blk-2         06/08               BHEL       363.3                     Slipped     09/13
UP              Rihand STPP St-III                              NTPC                           6        02/09               BHEL        500          500        7/10/2013    12/13           March 2014
WB              Raghunathpur TPP                                DVC                            1        12/07               CHINA       600                       Slipped    03/14
                                                                                                     Total Central Sector              3123.3        1660
STATE SECTOR
Chhattisgarh Marwa TPP                                             CSEB                       1         04/08               BHEL         500         500        30.03.2014   09/13
Delhi           Pragati St-III CCGT                                PPCL                      GT-4       05/08               BHEL         250         250         7/5/2013    06/13           27.02.2014
Delhi           Pragati St-III CCGT                              PPCL                       ST-2       05/08              BHEL          250          250        26.02.2014   09/13           27.03.2014
Gujarat         Pipavav JV CCGT                                 GSECL                      Block-1     12/07              BHEL          351          351        05/02/2013   09/13
MP              Shree Singaji TPP(Malwa TPP)                   MPPGCL                         1        12/08              BHEL          600          600        18/11/2013   06/13           February 2014
MP              Satpura TPS Extn.                              MPPGCL                        11        03/08              BHEL          250          250        25/12/2013   10/13           16.03.2014
Maha-rashtra    Chandrapur TPS Extn.                          MAHAGENCO                       8        07/08              BHEL          500                       Slipped    12/13
Rajasthan       Kalisindh TPP                                  RRVUNL                         1        07/08          SEPCO, CHINA      600                       Slipped    12/13
Rajasthan       Chhabra TPS Extn.                              RRVUNL                         3        08/08              BHEL          250          250         14/09/13    06/13           19.12.2013
Rajasthan       Chhabra TPS Extn.                              RRVUNL                         4        08/08              BHEL          250                       Slipped    01/14
Rajasthan       Ramgarh CCPP                                   RRVUNL                        ST        08/09              BHEL           50                       Slipped    12/13
TN              North Chennai TPS Extn.                         TNEB                          1        08/08              BHEL          600           600        13/09/13    09/13           20.03.2014
                                                                                                     Total -State Sector                4451         3051
PRIVATE SECTOR
AP           Vizag TPP                                          Hinduja                       1         03/10               BHEL         520                                 03/14
AP           Thammina-patnam TPP                            Meena-kshi Energy                 2         08/09               Chinese      150         150         17/04/13    09/13           30.04.2013
Chhattis-garh   Tamnar TPP                                     Jindal Power                   1         12/08            BHEL            600         600        10.03.2014   03/14           14.03.2014
                                                                                                                    BOILER: CETHAR                                           06/13
                                                                                                                     VESSELS LTD
Chhattis-garh   Vandana Vidyut TPP                         Vandana Vidyut TPP                 1         05/08                            135                      Slipped
                                                                                                                      TG: CNAIC,
                                                                                                                        CHINA
Chhattis-garh   DB Power TPP                                   DB Power Ltd                   1         05/10            BHEL            600         600        23.02.2014   12/13           03.11.2014
                                                                                                                      BOILER: IJT;                                           12/13
Chhattis-garh   Swastik Korba TPP                                  ACB                        1         02/10          TURBINE:          25                      Slipped
                                                                                                                       SIEMENS
Chhattis-garh   Akaltara TPP                                  KSK Mahanadi                    1         04/09         SEC,CHIINA         600         600         13/08/13    09/13           14.08.2013
MP                         Sasan UMPP                         Reliance Power                  3         06/08         SEC, CHINA         660         660          30/5/13         05/13
MP              Sasan UMPP                                   Reliance Power                   2         06/08        SEC, CHINA          660         660         18/12/13    09/13
Maha-rashtra    Nasik TPP Ph-I                                  India Bulls                   1         11/09             BHEL           270         270        25.02.2014   09/13           29.03.2014
Maha-rashtra    Dhariwal Infrastructure (P) Ltd.TPP   Dhariwal Infra-structure (P) Ltd.       1         04/10         SEC, CHINA         300         300         3/11/2013   06/13           13.02.2014
Maha-rashtra    Dhariwal Infrastructure (P) Ltd.TPP   Dhariwal Infra-structure (P) Ltd.       2         04/10         SEC, CHINA         300                      Slipped    12/13
Maha-rashtra    EMCO Warora TPP                         GMR EMCO Energy Ltd.                  2         09/09         SEC, CHINA         300         300        27/08/2013   06/13           01.09.2013
Maha-rashtra    Tirora TPP Ph-II                               Adani Power                    1         02/08        SCMEC, CHINA        660         660         10/6/2013   06/13           14.06.2013
                                                                                                         4
State           Project Name                  Impl Agency                   Unit No       LOA Date     BTG Supplier         Targeted   Actual Cap.     Actual         At the          COD
                                                                                                                           Cap. (MW)     comm.        Comm.        beginning of
                                                                                                                                          (MW)          Date         the year
Orissa          Derang TPP             Jindal India Thermal Power              1            07/09              BHEL           600                      Slipped    12/13
Orissa          Kamalang TPP                   GMR Energy                      2            08/08        SEPCO III, CHNA      350         350         28/09/13    09/13           12.11.2013
Punjab          Goindwal Sahib TPP           GVK Industries                    1            02/09              BHEL           270                      Slipped    06/13
Punjab          Talwandi Sahib TPP                Sterlite                     1            07/09         SEPCO I, CHINA      660                      Slipped    01/14
                                                                                         Total -Private Sector               7660         5150
                                                                Total for during the year 2013-14                           15234.3       9861
Maha-rashtra    Tirora TPP Ph-II              Adani Power                      2            02/08     SCMEC, CHINA                        660        23/3/2014                    31.03.2014
MP              Sasan UMPP                   Reliance Power                    4            06/08     SEC, CHINA                          660         25/03/14                    12.04.2014
Chhattis-garh   Tamnar TPP                    Jindal Power                     2            12/08          BHEL                           600        30.03.2014                   31.03.2014
Chhattis-garh   Chakabura TPP                    ACBIL                         1                          Chinese                         30         28.03.2014                   30.03.2014
West Bengal     Durgapur TPS Extn                 DPL                          8                           BHEL                           250        31.03.2014
Chhattis-garh   Avantha Bhandar TPP             KWPCL                          1                           BHEL                           600        31.03.2014                   01.04.2014
Maharashtra     Butibori TPP          Vidarbha Industries Power Ltd              1                         Chinese                        300        31.03.2014                   28.03.2014
                                                                        Total Addl.Capacity                                               6906
                                                                     Total for the Year 2013-14                                          16767
                                                                                              5
2.2 Thermal Capacity Addition Target/ Achievement for the Year 2014-15
State              Project Name         Impl Agency                    Equip. Supplier   Fuel       Unit No       LOA date          Targeted   Actual Cap     Actual        At the        COD
                                                                                                                                   Cap. (MW)    .comm.      Comm. Date   beginning of
                                                                                                                                                 (MW)                      the year
CENTRAL SECTOR
            Barh STPP-II                NTPC                                BHEL                      U-5        SG:03/2008           660         660       04.03.2015     Feb-15       18.02.2016
                                                                                          Coal
Bihar                                                                                                            TG:10/2008
            Muzaffarpur TPS Exp         KBUNL (JV of NTPC & BSEB)           BHEL          Coal       U-3          03/2010             195         195       31.03.2015     Mar-15       18.03.2017
            Tuticorin TPP               NTPL( JV of NLC &                   BHEL          Coal       U-1                              500         500       10.03.2015     Oct-14       18.06.2015
TN                                                                                                                 28.01.09
                                        TANGEDCO)                           BHEL          Coal       U-2                              500                                  Feb-15
Tripura        Palatana CCPP            OTPC (JV of ILFS, ONGC &            BHEL                    BLK-2          23.06.08          363.3       363.3      16.11.2014     Aug-14
                                                                                          Gas
                                        Tripura Govt)
WB             Raghunathpur TPP, Ph-I   DVC                                Chinese        Coal        U-1         14.12.2007          600         600       24.08.2014     Aug-14       31.03.2016
                                                                                                            Total Central Sector     2818.3      2318.3
STATE SECTOR
             Damodaram                                                    Blr- BHEL                   U-1        SG:08/2008           800         800       28.08.2014     Jun-14       05.02.2015
    AP                                  APPDCL                                            Coal
             Sanjeevaiah TPP                                               TG- L&T                    U-2        TG:09/2008           800         800       17.03.2015     Jan-15       24.08.2015
Chhattisgarh Marwa TPP                  CSPGCL                              BHEL          Coal        U-2         11.04.08            500                    Slipped       Dec-14
             Chandrapur TPS             MSPGCL                              BHEL          Coal        U-8         25.07.08            500         500       29.03.2015     Oct-14       04.06.2016
             Koradi TPS Expn.           MSPGCL                               L&T          Coal        U-8         23.09.09            660         660       30.03.2015     Oct-14       16.12.2015
Maharashtra
             Koradi TPS Expn.           MSPGCL                               L&T          Coal        U-9                             660                    Slipped       Jan-15
             Parli TPS Expn.            MSPGCL                              BHEL          Coal        U-8          21.01.09           250                     Slipped      Nov-14
MP           Malwa TPP                  MPPGCL                              BHEL                      U-2          12.12.08           600         600       15.10.2014     Sep-14       01.01.2015
                                                                                          Coal
             (Shree Singaji)
Rajasthan    Kalisindh TPP                                                 Chinese        Coal       U-1                              600         600       02.05.2014     Jun-14       01.06.2014
                                                                                                                   09.07.08
             Kalisindh TPP                                                 Chinese        Coal       U-2                              600                     Slipped      Jan-15
                                        RRVUNL
             Ramgarh CCPP                                                  BHEL           Gas        ST            18.08.09           50          50        01.05.2014     Jul-14
             Chhabra TPP                                                   BHEL           Coal       U-4           20.08.08           250         250       30.06.2014     Jun-14       30.12.2014
UP           Anpara-D TPS               UPRVUNL                            BHEL           Coal       U- 6          27.10.07           500                     Slipped      Mar-15
                                                                                                              Total State Sector      6770        4260
PRIVATE SECTOR
            Painampuram TPP             Thermal Power Tech Corp.Ltd        Chinese        Coal        U-1          09/2010            660         660       07.02.2015     Dec-14       02.03.2015
AP          Vizag TPP                   Hinduja National Power             BHEL                       U-1          03/2010            520                     Slipped      Oct-14
                                                                                          Coal
                                        Corp.Ltd
               Swastic Korba TPP        ACB India Ltd.                Blr:ISGEC India                 U-1          29.03.10           25          25        31.03.2015     Nov-14
                                                                                          Coal
                                                                      TG:Siemens
Chhattisgarh
               Salora TPP               Vandana Vidyut Ltd                  Chinese       Coal        U-1          11/2008            135         135       10.04.2014     Sep-14       01.05.2014
               Bandakhar TPP            Maruti Clean coal                   Chinese       Coal        U-1                             300                    Slipped       Jan-15
Maharashtra    Amravati TPP Ph-I        India Bulls Power Ltd               BHEL          Coal        U-3          30.11.09           270         270       29.01.2015     Oct-14       03.02.2015
Maharashtra    Nasik TPP Ph-I           India Bulls Realtech                BHEL          Coal        U-2          24.11.09           270                    Slipped       Jul-14
Maharashtra    Dhariwal TPP              Dhariwal Infrastucture Ltd         Chinese       Coal        U-2          28.04.10           300         300       28.05.2014     Jun-14       02.08.2014
Orissa         Derang TPP               JIPL                                BHEL          Coal        U-1          26.07.09           600         600       10.05.2014     Jun-14       06.06.2014
Punjab         Rajpura TPP (Nabha)      Nabha Power Ltd                      L&T          Coal        U-2          16.07.10           700         700       06.07.2014     Jul-14       01.08.2014
Punjab         Talwandi Sabo TPP        M/s Sterlite                        Chinese       Coal        U-1          18.07.09           660         660       17.06.2014     May-14       01.08.2014
Punjab         Talwandi Sabo TPP        M/s Sterlite                        Chinese       Coal        U-2          18.07.09           660                    Slipped       Sep-14
WB             Haldia TPP               M/s Haldia Energy Ltd.              Chinese       Coal        U-1          14.09.11           300         300       14.01.2015     Dec-14       28.01.2015
                                                                                                            Total Private Sector      5400        3650
                                                                                                    Total target during 2014-15      14988.3     10228.3
                                                                                                6
Additional Capacity Commissioned
State                    Project Name      Impl Agency                  Equip.    Fuel    Unit No    LOA date     Actual Cap     Actual        At the          COD
                                                                       Supplier                                    .comm.      Comm. Date   beginning of
                                                                                                                    (MW)                     the year
Gujarat            D gen CCPP              Torrent Power            Siemens
                                                                                    gas   Block-II   02.07.2010      400       23.04.2014
                                                                    Germany
Gujarat            Dhuvaran CCPP           GSECL                    Siemens
                                                                                    gas   Uniit 1                   376.1      21.05.2014
                                                                    Germany
MP                 Sasan UMPP              SPL                      Chinese               4th Unit                                                         27.05.2014
                                                                                   Coal                              660       21.05.2014
                                                                                          (Unit-1)
MP                 Sasan UMPP              SPL                      Chinese        Coal    Unit-5                    660       24.08.2014                  26.12.2014
Chhattisgarh       Akaltara TPP            KSK                      Chinese        Coal    Unit-2                    600       22.08.2014                  26.08.2014
MP                 Nigrie TPP              JPVL                     L&T            Coal    Unit-1                    660       29.08.2014                  03.09.2014
Maharashtra        Tirora TPP Ph-II        Adani Power              Chinese                                                                                11.10.2014
                                                                                   Coal   Unit-3     05.11.2009      660       25.09.2014
                                           Maharashtra Pvt Ltd
TN                 Mutiara TPP             Coastal Energen          Chinese        Coal   Unit-1     25.02.2009      600       02.12.2014                  23.12.2014
Chhattisgarh       Tamnar TPP (Raigarh)    Jindal Power             BHEL           Coal   Unit-3                     600       07.01.2015                  15.01.2015
Orissa             Derang TPP              JIPL                     BHEL           Coal    U-2                       600       24.01.2015                  12.02.2015
TN                 Neyveli TPS Ph-II Exp   NLC                      BHEL           Coal       U-2                    250       24.01.2015                  22.04.2015
WB                 Haldia TPP              M/s Haldia Energy Ltd.   Chinese        Coal       U-2                    300       16.02.2015                  21.02.2015
MP                 Nigrie TPP              JP Ventures Ltd          Non-BHEL       Coal       U-2                    660       17.02.2015                  21.02.2015
Chhattisgarh       Raikhera TPP            GMR                      Chinese        Coal       U-1                    685       27.02.2015                  01.06.2015
Maharashtra        Amravati TPP Ph-I       India Bulls Power Ltd    BHEL           Coal       U-4     30.11.09       270       04.03.2015                  08.03.2015
AP                 Simhapuri               Simhapuri Energy Pvt     Chinese        Coal       U-4                    150       07.03.2015                  31.03.2015
                                           Ltd
Maharashtra        Amravati TPP Ph-I       India Bulls Power Ltd    BHEL           Coal    U-5        30.11.09       270       12.03.2015                  13.03.2015
MP                 Sasan UMPP              SPL                      Chinese        Coal   Unit-6                     660       19.03.2015                  27.03.2015
Tripura            Agartala CCPP           NEEPCO                   Thermax        gas    ST-2                       25.5      22.03.2015
Chhattisgarh       DB Power TPP            DB Power Ltd             BHEL           Coal   Unit-2                     600       24.03.2015
Chhattisgarh       Tamnar TPP (Raigarh)    Jindal Power             BHEL           Coal   Unit-4                     600       26.03.2015
Gujarat            Sikka TPP Extn          GSECL                    BHEL           Coal       U-3                    250       28.03.2015                  14.09.2015
Tripura            Monarchak gas power     NEEPCO                   BHEL            Gas                              65.4      30.03.2015
                                                                                              GT
                   project
                                                                                                                    10602
                                                                                                                   20830.3
                                                                                          7
  2.3 Thermal Capacity Addition Target/ Achievement for the Year 2015-16
   State                 Project Name                           Impl Agency                 Unit No       BTG Supplier    Cap. (MW)    Anti. Comm.     Now Anti.   Cap. Add   Actual Date     COD
                                                                                                                                      ( beginning of    Comm.       (MW)       of Comm.
                                                                                                                                         the year)
CENTRAL SECTOR
Assam       Bongaigaon TPP                         NTPC                                      U-1            BHEL             250        06/2015                      250      22.06.15(A)   01.04.2016
Bihar       Muzafferpur                            NTPC                                      U-4            BHEL             195        02/2016        03/2016
Bihar       Nabi Nagar TPP                         NTPC                                      U-1            BHEL                                                     250      20.03.16(A)   15.01.2017
Jharkhand   Bokaro TPS "Ä" Exp.                    DVC                                       U-1            BHEL                                                     500      22.03.16(A)   23.02.2017
Maharashtra Mouda STPP-II                          NTPC                                      U-3            BHEL                                                     660      28.03.16(A)   01.02.2017
MP          Vindhyachal TPP-V                      NTPC                                      U-13           BHEL            500         12/2015                      500      06.08.15(A)   30.10.2015
Tripura     Agratala STG                           NEEPCO                                    ST-2          Thermax          25.5        05/2015        01/2016
Tripura     Monarchak CCPP                         NEEPCO                                     ST            BHEL            35.6        08/2015                      35.6     14.01.16(A)
TN          Tuticorin TPP                          NLC                                       U-2            BHEL            500         07/2015                      500      09.07.15(A)   29.08.2015
WB          Raghunathpur TPP,Ph-I                  DVC                                       U-2           Chinese          600         01/2016                      600      18.01.16(A)   31.03.2016
                                                   Total Central Sector                                                    2106.1                                   3295.6
STATE SECTOR
Chhattisgarh Marwa TPP                             CSPGCL                                    U-2           BHEL              500        09/2015        02/2016
Gujarat      Sikka TPS                             GSECL                                     U-4           BHEL              250        12/2015                      250      25.09.15(A)   28.12.2015
Karnataka    Bellary TPS St-III                    KPCL                                      U-3           BHEL              700        12/2015        01/2016       700      01.03.16(A)   16.09.2017
Karnataka    Yermarus TPP                          KPCL                                      U-1           BHEL              800        01/2016        02/2016       800      29.03.16(A)   07.03.2017
Maharashtra  Chandrapur TPS                        MSPGCL                                    U-9           BHEL              500        10/2015        02/2016       500      21.03.16(A)   24.11.2016
Maharashtra  Koradi TPS Expn.                      MSPGCL                                    U-9            L&T              660        09/2015        02/2016       660      15.03.16(A)   22.11.2016
Maharashtra  Koradi TPS Expn.                      MSPGCL                                    U-10           L&T              660        02/2016        05/2016
Maharashtra  Parli TPS                             MSPGCL                                    U-8           BHEL              250        01/2016        03/2016       250      30.03.16(A)   30.11.2016
Rajasthan    Kalisindh TPP                         RVUNL                                     U-2           Chinese           600        05/2015                      600      06.06.15(A)   25.07.2015
Telangana    Singareni TPP                         Singareni Collieries Co Ltd               U-1           BHEL              600        01/2016        03/2016       600      13.03.16(A)   25.09.2016
Telangana    Kakatiya TPS Extn.                    T GENCO                                   U-1           BHEL              600        12/2015        12/2015       600      31.12.15(A)   24.03.2016
UP           Anpara-D TPS                          UPRVUNL                                   U- 6          BHEL              500        06/2015                      500      06.06.15(A)   08.05.2016
UP           Anpara-D TPS                          UPRVUNL                                   U- 7          BHEL              500        12/2015        02/2016       500      06.03.16(A)   18.10.2016
WB           Sagardighi TPS-Extn                   West Bengal                               U-3           BHEL              500        09/2015        12/2015       500      14.12.15(A)
WB           Sagardighi TPS-Extn                   West Bengal                               U-4           BHEL              500        01/2016        06/2016
                                                   Total State Sector                                                       8120                                    6460
PRIVATE SECTOR
AP           Painampuram TPP                       Thermal Power Tech Corporation Ltd         U-2          Chinese           660        08/2015                      660      03.09.15(A)   15.09.2015
AP           Vizag TPP                             Hinduja National Power Corp. Ltd           U-1           BHEL             520        10/2015        02/2015       520      27.12.15(A)   11.01.2016
AP           Lanco Kondapalli Extn. Ph-III ( PS)   Lanco Kondapalli Power Co.Ltd          Block-I           Others                                                   371      07.08.15(A)
AP           Lanco Kondapalli Extn. Ph-III (PS)    Lanco Kondapalli Power Co.Ltd          Block-II          Others                                                   371      05.09.15(A)
AP           Vemagiri CCPP-II (PS)                 GMR Rajahmundry Energy Ltd.            Block-I           Others                                                   384      12.09.15(A)
AP           Vemagiri CCPP-II (PS)                 GMR Rajahmundry Energy Ltd.            Block-II          Others                                                   384      05.10.15(A)
AP           Vizag TPP                             Hinduja National Power Corp. Ltd           U-2           BHEL                                                     520      30.03.16(A)   03.07.2016
Chhattisgarh Bandakhar TPP                         M/s Maruti Clean (Chhattisgarh) Ltd.       U-1          Chinese           300        06/2015                      300      19.06.15(A)
Chhattisgarh Uchpinda TPP                          RKM Powergen Pvt. Ltd                      U-1          Chinese           360        06/2015                      360      28.10.15(A)   27.11.2015
Chhattisgarh Uchpinda TPP                          RKM Powergen Pvt. Ltd                      U-2          Chinese                                                   360      28.01.16(A)   12.02.2016
Chhattisgarh BALCO TPP                             BALCO Pvt Ltd                              U-1          Chinese           300        06/2015                      300      05.06.15(A)   11.07.2015
Chhattisgarh BALCO TPP                             BALCO Pvt Ltd                              U-2          Chinese           300        09/2015        02/2016       300      24.03.16(A)   30.03.2016
Chhattisgarh Raikheda TPP                          GMR                                        U-2     Doosan (Non-BHEL)      685        12/2015        02/2016       685      28.03.16(A)
Chhattisgarh Salora                                Vandana Vidyut                             U-2          Chinese           135        09/2015        2016-17
Maharashtra  Nasik TPP Ph-I                        Ratan India (Nasik) Power Ltd              U-2           BHEL             270        01/2016        03/2016
MP           Anuppur TPP Ph-I                      MB Power(MP)                               U-1          Chinese           600        06/2015                      600      20.04.15(A)   20.05.2015
M.P          Seioni TPP Ph-I                       Jhabua Power Ltd                           U-1           BHEL                                                     600      22.03.16(A)   03.05.2016
                                                                                                      8
     State             Project Name                  Impl Agency           Unit No       BTG Supplier   Cap. (MW)    Anti. Comm.     Now Anti.   Cap. Add   Actual Date     COD
                                                                                                                    ( beginning of    Comm.       (MW)       of Comm.
                                                                                                                       the year)
MP           Anuppur TPP Ph-I          MB Power(MP)                         U-2           Chinese                                                  600      30.03.16(A)   07.04.2016
Orissa       Ind Bharat TPP (Orissa)   Ind Barath                           U-1           Chinese          350        10/2015        01/2016       350      25.02.16(A)   20.07.2016
Punjab       Talwandi Sabo TPP         Talwandi Sabo Power Ltd              U-2           Chinese          660        06/2015                      660      30.10.15(A)   25.11.2015
Punjab       Talwandi Sabo TPP         Talwandi Sabo Power Ltd              U-3           Chinese          660        12/2015        03/2016       660      29.03.16(A)   25.08.2016
Punjab       Goindwal Sahib TPP        GVK Power                            U-1            BHEL                                                    270      14.02.16(A)   06.04.2016
Punjab       Goindwal Sahib TPP        GVK Power                            U-2            BHEL                                                    270      15.03.16(A)   16.04.2016
TN           ITPCL TPP                 IL&FS TN PC.Ltd                      U-1      Chinese                                                       600      19.09.2015    29.09.2015
TN           Melamaruthur (Mutiara)    Coastal Energen                      U-2      Chinese                                                       600      02.01.16(A)   15.01.2016
UP           Lalitpur TPP              Lalitpur power Generation Co. Ltd    U-1            BHEL            660                                     660      26.03.16(A)   01.10.2015
UP           Lalitpur TPP              Lalitpur power Generation Co. Ltd    U-2            BHEL                       09/2015                      660      08.01.16(A)   14.10.2016
UP           Prayagraj (Bara ) TPP     Prayagraj power Gen. Co. Ltd(        U-1            BHEL            660        10/2015                      660      25.12.15(A)   29.02.2016
                                       J.P.Power Ventures)
                                       Total Private Sector                                               7120                                    12705
                                       Grand Total                                                       17346.1                                 22460.6
                                                                                     9
2.4 Thermal Capacity Addition Target/ Achievement for the Year 2016-17
         State                         Project                  Unit                    Imp Agency          BTG Supplier   Capacity       Anticipated       Actual      Capacity     COD
                                                                                                                            (MW)        Commng. Schedule    date of     Achieved
                                                                                                                                                            comm.
                   CENTRAL SECTOR
  Bihar            Nabinagar TPP                                U-2             NTPC                       BHEL              250            12-2016
  Bihar            Kanti TPS St-II                              U-4             NTPC                       BHEL              195            09-2016        24.03.2017    195.0     01.07.2017
  Chhattisgarh     Lara STPP                                    U-1             NTPC                       NON BHEL          800            01-2017
  Karnataka        Kudgi TPP                                    U-1             NTPC                       NON BHEL          800            11-2016        25.12.2016    800.0     31.07.2017
  Maharashtra      Mauda STPP-II                                U-4             NTPC                       BHEL              660            12-2016        18.03.2017    660.0     18.09.2017
  Tripura          Agartala Gas Based Power Project             ST-1            NEEPCO                     NON BHEL          25.5           06-2016        23.08.2016     25.5
                                                                           Total Central                                    2730.5                                       1680.5
                   STATE SECTOR
  Assam            Namrup CCGT                                   GT             APGCL                      BHEL              70             09-2016        11.01.2017    62.25
  Assam            Namrup CCGT                                   ST             APGCL                      BHEL              30             09-2016
  Bihar            Barauni TPP,                                 U-8             BSEB                       BHEL             250             12-2016
  Chhattisgarh     Marwa TPS                                    U-2             CSPGCL                     BHEL             500             06-2016        15.07.2016    500.0     31.07.2016
  Gujarat          Bhavnagar TPP                                U-1             BECL                       BHEL             250             06-2016        16.05.2016    250.0
  Gujarat          Bhavnagar TPP                                U-2             BECL                       BHEL             250             08-2016        27.03.2017    250.0
  Karnataka        Yermarus TPP                                 U-2             KPCL                       BHEL             800             07-2016        29.03.2017    800.0     06.04.2017
  Maharashtra      Koradi TPP                                   U-10            MSPGCL                     NON BHEL         660             08-2016        28.12.2016    660.0     17.01.2017
  Telangana        Singreni TPP                                 U-2             SCCL                       BHEL             600             06-2016        25.11.2016    600.0     02.12.2016
  West Bengal      Sagardighi TPS-II                            U-4             WBPDCL                     BHEL             500             09-2016        15.12.2016    500.0
                                                                            Total State                                     3910                                        3622.25
                   PRIVATE SECTOR
  Andhra pradesh   Sembcorp Gayatri Pvt.ltd.(NCC TPP)           U-1         SGPL                     NON BHEL                660            09-2016        12.11.2016    660.0     17.11.2016
  Andhra pradesh   Sembcorp Gayatri Pvt.ltd.(NCC TPP)           U-2         SGPL                     NON BHEL                660            12-2016        15.02.2017    660.0     21.02.2017
  Chhattisgarh     Nawapara TPP                                 U-1         TRN                      CHINESE                 300            05-2016        14.08.2016    300.0     19.08.2016
  Chhattisgarh     Nawapara TPP                                 U-2         TRN                      CHINESE                 300            11-2016
  Chhattisgarh     Ucchpinda TPP                                U-3         RKM                      CHINESE                 360            07-2016
  Chhattisgarh     Binjkote TPP                                 U-1         SKS                      NON BHEL                300            11-2016
  Chhattisgarh     Athena Singhitarai TPP                       U-1         Athena Chhattisgarh      NON BHEL                600            10-2016
  Maharashtra      Nashik TPP, Ph-I                             U-2         Rattan Power             BHEL                    270            06-2016        15.02.2017    270.0
  Maharashtra      Nashik TPP, Ph-I                             U-3         Rattan Power             BHEL                    270            12-2016
  Orissa           Utkal TPP                                    U-2         Ind Barath               NON BHEL                350            07-2016
  Orissa           Lanco Babandh TPP                            U-1         Lanco Babandh            NON BHEL                660            02-2017
  Tamilnadu        ITPCL TPP                                    U-2         ILFS                     NON BHEL                600            05-2016        18.04.2016    600.0     30.04.2016
  Uttar pradesh    Bara TPP                                     U-2         Jaypee                   BHEL                    660            07-2016        06.09.2016    660.0     10.09.2016
  Uttar pradesh    Lalitpur TPP                                 U-3         LPGCL                    BHEL                    660            04-2016        01.04.2016    660.0     23.12.2016
  West Bengal      Hiranmaye Energy TPP                         U-1         Hiranmaye Energy Limited BHEL                    150            07-2016
                                                                       Total Private                                        6800                                         3810.0
                                                                      Total Thermal                                        13440.5                                      9112.75
                                                            ADDITIONAL PROJECTS COMMISSIONED IN RFD 2016-17
                   CENTRAL SECTOR
  Assam            Bongaigaon TPP                               U-2             NTPC                       BHEL                                            22.03.2017    250.0     01.11.2017
  Karnataka        Kudgi TPP                                    U-2             NTPC                       NON BHEL                                        23.03.2017    800.0     31.12.2017
  Uttar Pradesh    Unchahar TPS ST-IV                           U-6             NTPC                       BHEL                                            31.03.2017    500.0
                   PRIVATE SECTOR
  Chhattisgarh     Ratija TPP -II                                U-2            Spectrum Coal&Power Ltd    Non-BHEL                                        10.11.2016     50.0
  Uttrakhand       GAMA CCPP                            Module-1 (GT1&2+ST)     M/s GAMA Infraprop Ltd.    Others                                          25.04.2016    225.0
  Uttrakhand       Kashipur CCPP                                Blk-I           Srawanthi Energy Pvt.Ltd   Others                                          20.11.2016    225.0
  Maharashtra      Mangaon CCPP                                Block-I          M/s PGPL                   Others                                          14.07.2016    388.0
                                                                         Total Additional                                                                                2438.0
                                                        Total Grand Thermal Capacity                                          13440.5                                   11550.75
                                                                                            10
2.5 Thermal Capacity Addition Target/ Achievement for the Year 2017-18
  State                Project Name           Impl Agency                                   Equipment   Unit   Targeted     Anti.       Anti.    Actual Date   Capacity     COD
                                                                                             Supplier   No.      Cap.      Comm        Comm       of Comm      Achieved
                                                                                                                 (MW)      Date at    Date (At                   (MW)
                                                                                                                          beginning   present)
                                                                                                                           of year
  CENTRAL SECTOR
  Assam        Bongaigaon TPP                 NTPC                                       BHEL            3      250        Dec-17     Apr-18
  Bihar        Nabi Nagar TPP                 JV of NTPC &Rly                            BHEL            2      250        Apr-17       -        03.04.2017     250.00    10.09.2017
  Bihar        New Nabi Nagar TPP              JV of NTPC & BSPGCL                       NON BHEL        1      660        Aug-17     Mar-18
  Chhattisgarh Lara TPP                       NTPC                                       NON BHEL        1      800        Oct-17       -        23.03.2018     800.00
  Karnataka    Kudgi STPP Ph-I                NTPC                                       NON BHEL        3      800        Aug-17       -        12.03.2018     800.00
  MP           Gadarwara STPP,St-I            NTPC                                       BHEL            1      800        Jan-18     Mar-18
  Maharashtra  Solapur STPP                   NTPC                                       NON BHEL        1      660        Apr-17       -        07.04.2017     660.00    25.09.2017
  UP           Meja STPP                      JV of NTPC & UPRVUNL                       NON BHEL        1      660        Oct-17       -        31.03.2018     660.00
                                        TOTAL CENTRAL SECTOR                                                    4880                                           3170.00
  STATE SECTOR
  AP         Rayal seema TPP                 APGENCO                                     BHEL            6       600       Aug-17        -       12.03.2018     600.00    29.03.2018
  Assam      Namrup                          APGCL                                       BHEL           ST      36.15      Feb-18     Mar-18
  MP         Shree Singaji TPP, St-II        MPPGCL                                      NON BHEL        3       660       Dec-17     Jun-18
  Rajasthan  Suratgarh TPS                   RRVUNL                                      BHEL            7       660       Nov-17     Feb-18
  Rajasthan  Chhabra SCTPP                   RRVUNL                                      L&T & MHI       5       660       Apr-17        -       04.04.2017     660.00
  Rajasthan  Chhabra SCTPP                   RRVUNL                                      L&T & MHI       6       660       Jan-18     Feb-18
  Telangana  Bhadradri TPP                   TGENCO                                      BHEL            1       270       Mar-18     May-19
                                         TOTAL STATE SECTOR                                                    3546.15                                         1260.00
  PRIVATE SECTOR
  Chhattisgarh Akaltara (Naiyara) TPP         KSK Mahandi Power Company Ltd              CHINESE         3       600       Nov-17       -        18.01.2018     600.00    28.02.2018
  Chhattisgarh Binjkote TPP                   SKS Power Generation ( Chhattisgarh) Ltd   CHINESE         1       300       May-17       -        25.04.2017     300.00
  Chhattisgarh Nawapara TPP                   TRN Energy                                 CHINESE         2       300       May-17       -        18.04.2017     300.00    01.05.2017
  Chhattisgarh Lanco Amarkantak TPS-II        LAP Pvt. Ltd.                              CHINESE         3       660       Nov-17     Mar-18
  Maharashtra  Nasik TPP Ph-I                 RattanIndia Nasik Power Ltd                BHEL            3       270       May-17       -        14.04.2017     270.00
  UP           Bara TPP                       Prayagraj Power Generation Co.Ltd.         BHEL            3       660       Aug-17       -        22.05.2017     660.00    26.05.2017
  WB            Hiranmaye Energy TPP       Hiranmaye Energy Limited                      BHEL            1      150        Apr-17        -       07.06.2017     150.00    13.08.2017
                                     TOTAL PRIVATE SECTOR                                                       2940                                           2280.00
  ADDITIONAL PROJECTS COMMISSIONED
  PRIVATE SECTOR
  Maharashtra  Nasik TPP Ph-I              RattanIndia Nasik Power Ltd                   BHEL            4                                       19.05.2017     270.00
  Maharashtra  Nasik TPP Ph-I              RattanIndia Nasik Power Ltd                   BHEL            5                                       30.05.2017     270.00
  Chhattisgarh Uchpinda TPP                RKM Powergen Pvt.Ltd.                         Chinese         3                                       12.09.2017     360.00
  Maharashtra  Shirpur TPP                 Shirpur Power Pvt. Ltd.                       BHEL            1                                       28.09.2017     150.00
  WB           Hiranmaye Energy TPP        Hiranmaye Energy Limited                      BHEL            2                                       31.12.2017     150.00    31.12.2017
  Bihar        Barauni Ext.                BSEB                                          BHEL            8                                       11.01.2018     250.00
  Chhattisgarh Binjkote TPP                SKS Power Generation ( Chhattisgarh) Ltd      CHINESE         2                                       28.03.2018     300.00
  Bihar        Barauni Ext.                BSEB                                          BHEL            9                                       31.03.2018     250.00
                               TOTAL ADDITIONAL PRIVATE SECTOR                                                                                                 2000.00
                                    TOTAL THERMAL CAPACITY                                                     11366.15                                        8710.00
                                                                                            11
                  2.6 Thermal Capacity Addition Programme (RFD) for the year 2018-19
                                                                                                                    Expected
                                                         Targeted Ach.      Org.      Ant.
S.                Project Name / Impl.   LOA      Unit                                          Ant.      Actual     COD
        State                                               Cap.  Cap.     Comm.     Comm.
No.               Agency/ EPC or BTG     Date     No                                            COD       COD       Quarter-
                                                           (MW) (MW)       Sched.    Sched.
                                                                                                                      wise
                 CENTRAL SECTOR
 1     Assam     Bongaigaon TPP          Feb-08  U-3     250               Sep-11      Q1      Oct-18                 Q4
 2     Bihar     Nabi Nagar TPP          Jan-08  U-3     250               Aug-13      Q2      Mar-19                 Q4
 3     Bihar     New Nabi Nagar TPP      Jan-13  U-1     660               Jan-17      Q2       Jan-19                Q4
 4      MP       Gadarwara TPP           Mar-13  U-1     800               Mar-17      Q2      Nov-18                 Q4
 5     Odisha    Darlipalli STPP         Feb-14  U-1     800               Feb-18      Q4      Mar-19                 Q4
                 Total Central Sector                   2760
                 STATE SECTOR
 1     Assam     Namrup CCGT             Feb-09  ST     36.15              Jan-12      Q3      Feb-19                 Q4
 2       MP      Shri Singhaji TPP St-   Sep-14  U-3     660     660       May-18      Q1      Oct-18    18.11.18     Q3
                 II
 3       MP      Shri Singhaji TPP St-   Sep-14  U-4     660               Jul-18      Q3      Feb-19                 Q4
                 II
 4     Odisha    Ib valley TPP           Mar-14  U-4     660               Sep-17      Q4      Mar-19                 Q4
 5    Rajasthan Chhabra TPP Extn         Mar-13  U-6     660               Jun-18      Q2      Dec-18                 Q4
 6    Rajasthan Suratgarh SCTPP          May-13  U-7     660               Sep-16      Q2      Dec-18                 Q4
 7    Karnataka Yelahanka CCPP BY        Nov-15 GT+      370               Mar-18      Q2      Oct-18                 Q4
                 KPCL                            ST
 8    Telangana Kothagudem TPS St-       Jan-15  U-1     800     800       Nov-17      Q2      Dec-18    26.12.18     Q3
                 VII
                 Total State Sector                    4506.15   1460
                 PRIVATE SECTOR                         NIL
              TOTAL THERMAL CAPACITY ADDITION                    1460
          ADDITIONAL PROJECTS
                 STATE SECTOR
 1     Assam     Lakwa Replacement       Dec-15  U-             69.755                                   26.04.18
                 Power Project./                1,2,3,
                 APGCL/ Wartsila                4,5,6
                 India Pvt Ltd                   &7
                 Total State Sector                             69.755
                 PRIVATE SECTOR
 1       MP      Mahan TPP /Essar        Aug-07  U-2             600       Dec-11                        07.10.18
                 Power MP Ltd./
                 Chinese
                 Total Private Sector                            600
                 Total Additional Capacity                     669.755
                                                                12
3.0 Target/ Achievement of Thermal Capacity addition during 12th Plan
State         Project Name        Impl          Main Plant   Unit          12th Plan    Cap. Ach.   Add.       Total    Actual     Slipped
                                  Agency        Equipment    No            Tar. Cap.   From         Cap.    cap. Ach.   Comm.
                                                 Supplier                              Target       Ach       (MW)      Date
                                                                                       (MW)         (MW)
              CENTRAL SECTOR
Assam         Bongaigaon TPP      NTPC            BHEL        U-1             250          250                250       22.06.15
Assam         Bongaigaon TPP      NTPC            BHEL        U-2             250          250                250       22.03.17
Assam         Bongaigaon TPP      NTPC            BHEL        U-3             250                                                    250
Bihar         Barh STPP-II        NTPC            BHEL        U-4             660          660                660       30.11.13
Bihar         Barh STPP-II        NTPC            BHEL        U-5             660          660                660       04.03.15
Bihar         Muzaffarpur TPP     KBUNL           BHEL        U-3             195          195                195       31.03.15
              Extn                (JV of
                                  NTPC and
                                  BSEB)
Bihar         Muzaffarpur TPP     KBUNL           BHEL        U-4             195          195                195       24.03.17
              Extn                (JV of
                                  NTPC and
                                  BSEB)
Bihar         Nabi Nagar TPP      NTPC            BHEL        U-1             250          250                250       20.03.16
Bihar         Nabi Nagar TPP      NTPC            BHEL        U-2             250                                                    250
Bihar         Nabi Nagar TPP      NTPC            BHEL        U-3             250                                                    250
Bihar         Nabi Nagar TPP      NTPC            BHEL        U-4             250                                                    250
Bihar         Barh STPP-I         NTPC            Others      U-1             660                                                    660
Bihar         Barh STPP-I         NTPC            Others      U-2             660                                                    660
Bihar         Barh STPP-I         NTPC            Others      U-3             660                                                    660
Chhattisgar   Sipat-I             NTPC            Others      U-3             660          660                660       02.06.12
h
Haryana       Indira Gandhi TPP   APCPL           BHEL        U-3             500          500                500       07.11.12
Jharkhand     Koderma TPP         DVC             BHEL        U-2             500          500                500       15.02.13
Jharkhand     Bokaro TPS "A"      DVC             BHEL        U-1             500          500                500       22.03.16
              Exp.
Karnataka     Kudgi STPP Ph-I     NTPC          Non-BHEL     U-1 #                                   800      800       25.12.16
Karnataka     Kudgi STPP Ph-I     NTPC          Non-BHEL     U-2 #                                   800      800       23.03.17
Maharashtra   Mouda TPP           NTPC            BHEL        U-1             500          500                500       19.04.12
Maharashtra   Mouda TPP           NTPC            BHEL        U-2             500          500                500       29.03.13
Maharashtra   Mouda STPP Ph-II    NTPC            BHEL       U-3 #                                   660      660       28.03.16
Maharashtra   Mouda STPP Ph-II    NTPC            BHEL       U-4 #                                   660      660       18.03.17
MP            Vindhyachal TPP-V   NTPC            BHEL       U-13                                    500      500       06.08.15
                                                               #
MP            Vindhyachal STPS-   NTPC            BHEL       U-11             500          500                500       14.06.12
              IV
MP            Vindhyachal STPS-   NTPC            BHEL        U-12            500          500                500       25.03.13
              IV
TN            Vallur TPP Ph I     NTECL           BHEL        U-2             500          500                500       28.02.13
TN            Vallur TPP-II       NTECL           BHEL        U-3             500          500                500       28.02.14
TN            Neyveli TPS-II      NLC             BHEL        U-2             250          250                250       24.01.15
              EXP
TN            Tuticorin TPP       NTPL (JV        BHEL        U-1             500          500                500       10.03.15
                                  NLC &
                                  TANGEDC
                                  O)
TN            Tuticorin TPP       NTPL (JV        BHEL        U-2             500          500                500       09.07.15
                                  NLC &
                                  TANGEDC
                                  O)
Tripura       Tripura Gas         ONGC            BHEL       Module          363.3        363.3               363.3     03.01.13
                                                              -1
Tripura       Tripura Gas         OTPS            BHEL       Module          363.3        363.3               363.3     16.11.14
                                                              -2
Tripura       Monarchak Gas       NEEPCO          BHEL        GT             65.4          65.4               65.4      30.03.15
              Power Project
Tripura       Monarchak CCPP      NEEPCO          BHEL        ST             35.6          35.6               35.6      14.01.16
Tripura       Agartala CCPP       NEEPCO         Thermax     ST-2 #                                  25.5     25.5      22.03.15
Tripura       Agartala CCPP       NEEPCO         Thermax     ST-I #                                  25.5     25.5      23.08.16
UP            Rihand STPS- III    NTPC            BHEL        U-6             500          500                500       07.10.13
UP            Rihand STPS- III    NTPC            BHEL        U-5             500          500                500       25.05.12
UP            Unchahar - IV       NTPC            BHEL       U-6 #                                   500      500       31.03.17
WB            Raghunathpur TPP    DVC            Chinese      U-1             600          600                600       24.08.14
              Ph-I
WB            Raghunathpur        DVC             Chinese     U-2             600          600                600       18.01.16
              TPP,Ph-I
                                  Total Central Sector                      14877.6      11897.6     3971    15868.6                2980
              STATE SECTOR
AP            Damodaram           APPDL         BHEL/MHI      U-1             800          800                800       28.08.14
              Sanjeevaiah TPS
AP            Damodaram           APPDL         BHEL/MHI      U-2             800          800                800       17.03.15
              Sanjeevaiah TPS
                                                                      13
State          Project Name          Impl          Main Plant   Unit          12th Plan    Cap. Ach.   Add.        Total    Actual     Slipped
                                     Agency        Equipment    No            Tar. Cap.   From         Cap.     cap. Ach.   Comm.
                                                    Supplier                              Target       Ach        (MW)      Date
                                                                                          (MW)         (MW)
AP             Rayalaseema St-IV     AP Genco        BHEL        U-6             600                                                     600
Assam          Namrup CCGT           APGCL           BHEL        GT             63.85        62.25                62.25     11.01.17
Assam          Namrup CCGT           APGCL           BHEL        ST             36.15                                                   36.15
Chhattisgar    Korba West -St -III   CSPGCL          BHEL        U-5             500          500                 500       22.03.13
h
Chhattisgarh   Marwa TPP             CSPGCL          BHEL        U-1         500              500                 500       30.03.14
Chhattisgarh   Marwa TPP             CSPGCL          BHEL        U-2         500              500                 500       15.07.16
Delhi          Pragati CCGT - III    PPCL            BHEL       GT-3         250              250                 250       27.06.12
Delhi          Pragati CCGT - III    PPCL            BHEL       GT-4         250              250                 250       07.05.13
Delhi          Pragati CCGT - III    PPCL            BHEL        ST-2        250              250                 250       26.02.14
Gujarat        Pipavav CCPP          GSECL           BHEL       Block-       351              351                 351       27.03.13
                                                                  2
Gujarat        Pipavav CCPP          GSECL           BHEL       Block-       351              351                 351       05.02.14
                                                                  1
Gujarat        Ukai TPP Extn.        GSECL           BHEL        U-6         500              500                  500      05.03.13
Gujarat        Dhuvaran CCPP-III     GSECL           Others          Block-1 #                          376.1     376.1     21.05.14
Gujarat        Sikka TPS Extn        GSECL           BHEL        U-3         250              250                  250      28.03.15
Gujarat        Sikka TPS             GSECL           BHEL       U-4 #                                   250        250      25.09.15
Gujarat        Bhavnagar CFBC        Bhavnagar       BHEL       U-1 #                                   250        250      16.05.16
               TPP                   Energy
Gujarat        Bhavnagar CFBC        Bhavnagar       BHEL       U-2 #                                   250       250       27.03.17
               TPP                   Energy
Karnataka      Bellary TPS St-III    KPCL            BHEL       U-3 #                                   700       700       01.03.16
Karnataka      Yermarus TPP          KPCL            BHEL       U-1 #                                   800       800       29.03.16
Karnataka      Yermarus TPP          KPCL            BHEL       U-2 #                                   800       800       29.03.17
Maharashtra    Chandrapur TPS        MSPGCL          BHEL        U-8             500          500                 500       29.03.15
Maharashtra    Koradi TPS Extn       MSPGCL          L&T         U-8             660          660                 660       30.03.15
Maharashtra    Koradi TPS Expn.      MSPGCL          L&T        U-9 #                                   660       660       15.03.16
Maharashtra    Koradi TPS Expn.      MSPGCL          L&T        10 #                                    660       660       28.12.16
Maharashtra    Chandrapur TPS        MSPGCL          BHEL       U-9 #                                   500       500       21.03.16
Maharashtra    Parli TPS             MSPGCL          BHEL        U-8             250          250                 250       30.03.16
MP             Malwa TPP ( Shree     MPGENC          BHEL        U-2             600          600                 600       15.10.14
               Singaji TPP)          O
MP             Malwa TPP ( Shree     MPGENC          BHEL        U-1             600          600                 600       18.11.13
               Singa ji TPP)         O
MP             Satpura TPS Extn      MPPGCL          BHEL        U-10            250          250                 250       22.03.13
MP             Satpura TPS Extn      MPPGCL          BHEL        U-11            250          250                 250       25.12.13
Rajasthan      Ramgarh               RRVUNL          BHEL        GT              110          110                 110       20.03.13
Rajasthan      Ramgarh CCPP          RRVUNL          BHEL         ST              50          50                   50       01.05.14
               Extn. -III
Rajasthan      Chhabra TPS Extn.     RRVUNL         BHEL         U-3             250          250                 250       14.09.13
Rajasthan      Chhabra TPS Extn.     RRVUNL         BHEL         U-4             250          250                 250       30.06.14
Rajasthan      Kalisindh TPP         RRVUNL         Chinese      U-1             600          600                 600       02.05.14
Rajasthan      Kalisindh TPP         RVUNL          Chinese     U-2 #                                   600       600       06.06.15
TN             North Chennai Extn    TNEB           BHEL         U-2             600          600                 600       09.03.13
TN             North Chennai TPS     TNEB           BHEL         U-1             600          600                 600       13.09.13
               Extn, U-1
TN             Mettur TPS Ext        TNEB           Chinese      U-1             600          600                 600       11.10.12
Telangana      Singareni TPP         Singareni      BHEL        U-1 #                                   600       600       13.03.16
                                     Collieries
                                     Co Ltd
Telangana      Singareni TPP         Singareni       BHEL       U-2 #                                   600       600       25.11.16
                                     Collieries
                                     Co Ltd
Telangana      Kakatiya TPS Extn.    T GENCO         BHEL       U-1 #                                   600       600       31.12.15
Tripura        Rokhia CCPP           Govt.of                    GT-9 #                                   21        21       31.08.13
                                     Ttipura
UP             Parichha Extn         UPRVUNL         BHEL        U-5             250          250                 250       24.05.12
UP             Parichha Extn         UPRVUNL         BHEL        U-6             250          250                 250       11.03.13
UP             Harduaganj Ext        UPRVUNL         BHEL        U-9             250          250                 250       25.05.12
UP             Anpara-D TPS          UPRVUNL         BHEL       U- 6             500          500                 500       06.06.15
UP             Anpara-D TPS          UPRVUNL         BHEL       U- 7             500          500                 500       06.03.16
WB             Durgapur TPS Extn     DPL             BHEL       U-8 #                                   250       250       31.03.14
               U-8
WB             Sagardighi TPS-       West             BHEL      U-3 #                                   500       500       14.12.15
               Extn                  Bengal
WB             Sagardighi TPS-       West             BHEL      U-4 #                                   500       500       15.12.16
               Extn                  Bengal
                                     Total State Sector                         13922      13284.25    8917.1    22201.4       0       636.15
               PRIVATE SECTOR
AP             Simhapuri TPP Ph-I    Madhucon       Chinese      U-2             150          150                 150       02.07.12
AP             Thamminapatnam        Meenakshi      Chinese      U-1             150          150                 150       09.09.12
               TPP-I
AP             Thamminapatnam        Meenakshi      Chinese      U-2             150          150                 150       17.04.13
               TPP-I                 Energy Pvt.
                                     Ltd
                                                                         14
State          Project Name          Impl           Main Plant   Unit           12th Plan    Cap. Ach.   Add.      Total    Actual     Slipped
                                     Agency         Equipment    No             Tar. Cap.   From         Cap.   cap. Ach.   Comm.
                                                     Supplier                               Target       Ach      (MW)      Date
                                                                                            (MW)         (MW)
AP             Thamminapatnam        Meenakshi        Chinese     U-3              350                                                   350
               TPP-II                Energy Pvt.
                                     Ltd
AP             Thamminapatnam        Meenakshi        Chinese     U-4              350                                                   350
               TPP-II                Energy Pvt.
                                     Ltd
AP             Simhapuri Energy      Madhucon         Chinese    U-3 #                                    150     150       21.02.14
               Pvt Ltd Ph-II         Projects
                                     Ltd.
AP             Simhapuri Ph-II       Simhapuri        Chinese    U-4 #                                    150     150       06.03.15
                                     Energy
                                     Ltd.,
AP             Bhavanapadu TPP        East Coast    Chinese       U-1              660                                                   660
               Ph-I                  Energy Ltd.
AP             Bhavanapadu TPP        East Coast    Chinese       U-2              660                                                   660
               Ph-I                  Energy Ltd.
AP             NCC TPP                NCC           Chinese       U-1              660          660               660       12.11.16
                                     Power
                                     Project Ltd.
AP             NCC TPP                NCC           Chinese       U-2              660          660               660       15.02.17
                                     Power
                                     Project Ltd.
AP             Painnampuram TPP      Thermal          Chinese     U-1              660          660               660       07.02.15
                                     Power Tech
                                     Corp.Ltd.
AP             Painampuram TPP       Thermal          Chinese     U-2              660          660               660       03.09.15
                                     Power Tech
                                     Corporation
                                     Ltd
AP             Vizag TPP             Hinduja          BHEL        U-1              525          520               520       27.12.15
                                     National
                                     Power
                                     Corp. Ltd
AP             Vizag TPP             Hinduja          BHEL        U-2              525          520               520       30.03.16
                                     National
                                     Power
                                     Corp. Ltd
AP             Lanco Kondapalli      Lanco            Others     Block-I                                  371     371       07.08.15
               Extn. Ph-III ( PS)    Kondapalli                     #
                                     Power
                                     Co.Ltd
AP             Lanco Kondapalli      Lanco            Others     Block-                                   371     371       05.09.15
               Extn. Ph-III (PS)     Kondapalli                   II #
                                     Power
                                     Co.Ltd
AP             Vemagiri CCPP-II      GMR              Others     Block-I                                  384     384       12.09.15
               (PS)                  Rajahmund                      #
                                     ry Energy
                                     Ltd.
AP             Vemagiri CCPP-II      GMR              Others     Block-                                   384     384       05.10.15
               (PS)                  Rajahmund                    II #
                                     ry Energy
                                     Ltd.
Chattisgarh    Kasaipalli TPP         ACB             Chinese     U-2              135          135               135       21.06.12
Chattisgarh    Nawapara TPP          TRN              Chinese     U-1              300          300               300       14.08.16
                                     energy
                                     Pvt.Ltd..
Chattisgarh    Nawapara TPP          TRN              Chinese     U-2              300                                                   300
                                     energy
                                     Pvt.Ltd..
Chhattisgarh   Ratija TPP            Spectrum         Chinese     U-1              50           50                 50       03.02.13
                                     Coal &
                                     Power Ltd
Chhattisgarh   Ratija TPP -II        Spectrum       Non-BHEL     U-2 #                                     50      50       10.11.16
                                     Coal &
                                     Power Ltd
Chhattisgarh   Akaltara (Nariyara)   Wardha           Chinese     U-1              600          600               600       13.08.13
               TPP                   PCL (KSK)
Chhattisgarh   Akaltara (Naiyara)    KSK              Chinese      U-2             600          600               600       22.08.14
               TPP                   Mahandi                      (4th)
                                     Power Co.
                                     Ltd
Chhattisgarh   Akaltara (Naiyara)    KSK              Chinese     U-3              600                                                   600
               TPP                   Mahandi
                                     Power Co.
                                     Ltd
                                                                           15
State          Project Name         Impl          Main Plant   Unit          12th Plan    Cap. Ach.   Add.        Total    Actual     Slipped
                                    Agency        Equipment    No            Tar. Cap.   From         Cap.     cap. Ach.   Comm.
                                                   Supplier                              Target       Ach        (MW)      Date
                                                                                         (MW)         (MW)
Chhattisgarh   Avantha Bhandar      Korba West      BHEL        U-1             600          600                 600       31.03.14
               TPP, U-1             Power Co.
                                    Ltd.
Chhattisgarh   Baradarha TPP        D.B. Power      BHEL        U-1             600          600                 600       23.02.14
                                    Ltd
Chhattisgarh   Baradarha TPP        D.B. Power      BHEL        U-2             600          600                 600       24.03.15
                                    Ltd
Chhattisgarh   Chakabura TPP        ACB India     Non-BHEL      U-1#                                    30        30       28.03.14
Chhattisgarh   Tamnar TPP (         O.P.Jindal      BHEL        U-1             600          600                 600       10.03.14
               Raigarh)
Chhattisgarh   Tamnar TPP (         O.P.Jindal      BHEL        U-2             600          600                 600       30.03.14
               Raigarh)
Chhattisgarh   Tamnar (Raigarh)     Jindal          BHEL       U-3 #                                   600       600       07.01.15
               TPP                  Power
Chhattisgarh   Tamnar (Raigarh)     Jindal          BHEL       U-4 #                                   600       600       26.03.15
               TPP                  Power
Chhattisgarh   Salora TPP           M/s            Chinese      U-1             135          135                 135       10.04.14
                                    Vandana
                                    Vidyut
Chhattisgarh   Salora TPP           M/s            Chinese      U-2             135                                                     135
                                    Vandana
                                    Vidyut
Chhattisgarh   Raikheda TPP         GMR            Chinese     U-1 #                                   685       685       27.02.15
                                    Chhattisgar
                                    h Power
                                    Ltd.
Chhattisgarh   Raikheda TPP         GMR             Doosan     U-2 #                                   685       685       28.03.16
                                                  (Non-BHEL)
Chhattisgarh   Swastic TPP          ACB India        Others     U-1              25          25                   25       31.03.15
Chhattisgarh   Bandakhar TPP        M/s Maruti      Chinese     U-1             300          300                 300       19.06.15
                                    Clean
                                    (Chhattisga
                                    rh) Ltd.
Chhattisgarh   Uchpinda TPP         RKM            Chinese      U-1             360          360                 360       28.10.15
                                    Powergen
                                    Pvt. Ltd
Chhattisgarh   Uchpinda TPP         RKM            Chinese      U-2             360          360                 360       28.01.16
                                    Powergen
                                    Pvt. Ltd
Chhattisgarh   Uchpinda TPP         RKM            Chinese      U-3             360           0                                         360
                                    Powergen
                                    Pvt. Ltd
Chhattisgarh   Athena Singhitarai   Athena         Chinese      U-1             600                                                     600
               TPP
Chhattisgarh   Binjkote TPP         SKS Power      Chinese      U-1             300                                                     300
                                    Gen
Chhattisgarh   Binjkote TPP         SKS Power      Chinese      U-2             300                                                     300
                                    Gen
Chhattisgarh   Binjkote TPP         SKS Power      Chinese      U-3             300                                                     300
                                    Gen
Chhattisgarh   Lanco Amarkantak     LAP Pvt.       Chinese      U-3             660                                                     660
               TPP-II               Ltd.
Chhattisgarh   Lanco Amarkantak     LAP Pvt.       Chinese      U-4             660                                                     660
               TPP-II               Ltd.
Chhattisgarh   BALCO TPP            BALCO          Chinese      U-1             300          300                 300       05.06.15
                                    Pvt Ltd
Chhattisgarh   BALCO TPP            BALCO          Chinese      U-2             300          300                 300       24.03.16
                                    Pvt Ltd
Gujarat        Mundra UMTPP         Tata Power     Others       U-2        800               800                  800      25.07.12
Gujarat        Mundra UMTPP         Tata Power     Others      U-3 #                                   800        800      16.10.12
Gujarat        Mundra UMTPP         Tata Power     Others      U-4 #                                   800        800      16.01.13
Gujarat        Mundra UMTPP         Tata Power     Others      U-5 #                                   800        800      18.03.13
Gujarat        Salaya TPP           EssarPower     Chinese      U-2        600               600                  600      13.06.12
Gujarat        Uno sugen Mega       Torrent        Others      Mod.I                                   382.5     382.5     20.01.13
               CCPP                 Energy Ltd                   #
Gujarat        DGEN Mega CCPP       Torrent         Others         Module-1 #                          400       400       12.01.14
                                    Energy Ltd
Gujarat        DGEN Mega CCPP       Torrent         Others            Module-3 #                       400       400       09.03.14
                                    Energy Ltd
Gujarat        DGEN Mega CCPP       Torrent         Others            Module-2 #                       400       400       23.04.14
                                    Energy Ltd
Haryana        Jajjar TPS (         CLP Power      Chinese      U-2             660          660                 660       11.04.12
               Mahatama Gandhi
               TPP)
Jharkhand      Adhunik Power        Adhunik         BHEL        U-1             270          270                 270       19.11.12
               TPP                  Power
                                                                        16
State         Project Name          Impl          Main Plant   Unit          12th Plan    Cap. Ach.   Add.      Total    Actual     Slipped
                                    Agency        Equipment    No            Tar. Cap.   From         Cap.   cap. Ach.   Comm.
                                                   Supplier                              Target       Ach      (MW)      Date
                                                                                         (MW)         (MW)
Jharkhand     Adhunik Power         Adhunik         BHEL         U-2            270          270               270       29.03.13
              TPP                   Power
Jharkhand     Matrishri Usha TPP    Corporate       BHEL         U-1            270                                                   270
              Ph-I                  Power Ltd.
Jharkhand     Matrishri Usha TPP    Corporate       BHEL         U-2            270                                                   270
              Ph-I                  Power Ltd.
Maharashtra   Butibori TPP          VIPL           Chinese       U-1            300          300               300       17.08.12
Maharashtra   Butibori TPP          VIPL           Chinese      U-2 #                                  300     300       31.03.14
Maharashtra   Bela TPP-I,           IEPL           BHEL          U-1            270          270               270       20.03.13
Maharashtra   EMCO Warora           EMCO           Chinese       U-1            300          300               300       07.02.13
              TPP,                  GMR
Maharashtra   EMCO Warora           EMCO           Chinese       U-2            300          300               300       27.08.13
              TPP,                  GMR
Maharashtra   Tirora TPP Ph-I,      Adani          Chinese       U-1            660          660               660       11.09.12
                                    Power Ltd
Maharashtra   Tirora TPP Ph-I,      Adani          Chinese       U-2            660          660               660       25.03.13
                                    Power Ltd
Maharashtra   Gupta Energy          Gupta          Chinese       U-2            60           60                 60       28.04.12
              Power Ltd             Energy
                                    Power Ltd
Maharashtra   Gupta Energy          Gupta          Chinese       U-1            60           60                 60       08.09.12
              Power Ltd             Energy
                                    Power Ltd
Maharashtra   Amaravati TPP Ph-     Indiabulls      BHEL         U-1            270          270               270       25.03.13
              I
Maharashtra   Amravati TPP Ph-I     India Bulls    BHEL          U-2            270          270               270       17.02.14
Maharashtra   Amravati TPP Ph-I     India Bulls    BHEL          U-3            270          270               270       29.01.15
Maharashtra   Amravati TPP Ph-I     India Bulls    BHEL          U-4            270          270               270       04.03.15
Maharashtra   Amravati TPP Ph-I     India Bulls    BHEL          U-5            270          270               270       12.03.15
Maharashtra   Dhariwal Infracture   Dhariwal       Chinese       U-1            300          300               300       03.11.13
              TPP                   Infracture
                                    (P) Ltd
Maharashtra   Dhariwal Infracture   Dhariwal       Chinese       U-2            300          300               300       28.05.14
              TPP                   Infracture
                                    (P) Ltd
Maharashtra   Nasik TPP Ph-I        Ratan India     BHEL         U-1            270          270               270       25.02.14
                                    Nasik
                                    Power Ltd.
Maharashtra   Nasik TPP Ph-I        Ratan India     BHEL         U-2            270          270               270       15.02.17
                                    Nasik
                                    Power Ltd.
Maharashtra   Nasik TPP Ph-I        Ratan India     BHEL         U-3            270                                                   270
                                    Nasik
                                    Power Ltd.
Maharashtra   Nasik TPP Ph-I        Ratan India     BHEL         U-4            270                                                   270
                                    Nasik
                                    Power Ltd.
Maharashtra   Nasik TPP Ph-I        Ratan India     BHEL         U-5            270                                                   270
                                    Nasik
                                    Power Ltd.
Maharashtra   Tirora TPP Ph-II      Adani          Chinese       U-1            660          660               660       10.06.13
                                    Power Ltd
Maharashtra   Tirora TPP Ph-II      Adani          Chinese      U-2 #                                  660     660       23.03.14
                                    Power Ltd
Maharashtra   Tirora TPP Ph-II      Adani          Chinese      U-3 #                                  660     660       25.09.14
                                    Power Ltd
Maharashtra   Lanco Vidarbha        Lanco          Chinese       U-1            660                                                   660
              TPP                   Vidarbha
Maharashtra   Lanco Vidarbha        Lanco          Chinese       U-2            660                                                   660
              TPP                   Vidarbha
Maharashtra   Mangaon CCPP          PGPL           Others      Block-1#                                388     388       14.07.16
MP            Nigri TPP             Jaiprakash    L&T/MHI       U-1 #                                  660     660       29.08.14
                                    Power
                                    Ventures
                                    Ltd
MP            Nigri TPP             Jaiprakash    L&T/MHI       U-2 #                                  660     660       17.02.15
                                    Power
                                    Ventures
                                    Ltd
MP            Sasan UMPP            Reliance       Chinese      U-1 #                                  660     660       21.05.14
                                    Power Ltd.
MP            Sasan UMPP            Reliance       Chinese      U-4 #                                  660     660       25.03.14
                                    Power Ltd.
MP            Sasan UMPP            Reliance       Chinese      U-5 #                                  660     660       24.08.14
                                    Power Ltd.
                                                                        17
State       Project Name          Impl           Main Plant   Unit         12th Plan    Cap. Ach.   Add.       Total    Actual     Slipped
                                  Agency         Equipment    No           Tar. Cap.   From         Cap.    cap. Ach.   Comm.
                                                  Supplier                             Target       Ach       (MW)      Date
                                                                                       (MW)         (MW)
MP          Sasan UMPP            Reliance        Chinese     U-6 #                                   660     660       19.03.15
                                  Power Ltd.
MP          Sasan UMPP            Reliance        Chinese      U-2            660          660                660       18.12.13
                                  Power Ltd.
MP          Sasan UMPP            Reliance        Chinese      U-3            660          660                660       30.05.13
                                  Power Ltd.
MP          Niwari TPP            BLA Power      Non-BHEL     U-1 #                                   45       45       01.12.13
                                  Ltd
MP          Bina TPP,             Bina Power      BHEL         U-1            250          250                250       12.08.12
MP          Bina TPP,             Bina Power      BHEL         U-2            250          250                250       31.03.13
M.P.        Mahan TPP             Essar           Chinese     U-1 #                                   600     600       24.02.13
                                  Power
                                  MP Ltd
MP          Anuppur TPP Ph-I      MB              Chinese      U-1            600          600                600       20.04.15
                                  Power(MP)
MP          Anuppur TPP Ph-I      MB              Chinese      U-2            600          600                600       30.03.16
                                  Power(MP)
MP          Seioni TPP Ph-I       Jhabua           BHEL        U-1            600          600                600       22.03.16
                                  Power Ltd
MP          Gorgi TPP ( D B       DB Power         BHEL        U-1            660                                                    660
            Power)                Ltd
Orissa      Sterlite TPP,         Sterlite        Chinese      U-4            600          600                600       25.04.12
Orissa      Lanco Babandh         Lanco           Chinese      U-1            660                                                    660
            TPP                   babandh
                                  Power Ltd.
Orissa      Kamalanga TPP         GMR             Chinese      U-1            350          350                350       28.03.13
Orissa      Kamalanga TPP         GMR             Chinese      U-2            350          350                350       28.09.13
Orissa      Kamalanga TPP         GMR             Chinese      U-3            350          350                350       21.03.14
Orissa      Derang TPP            JITPL           BHEL         U-1            600          600                600       10.05.14
Orissa      Derang TPP            JITPL           BHEL        U-2 #                                   600     600       24.01.15
Orissa      Ind Bharat TPP        Ind Barath      Chinese      U-1            350          350                350       25.02.16
            (Orissa)
Orissa      Ind Bharat TPP        Ind Barath      Chinese      U-2            350                                                    350
            (Orissa)
Orissa      KVK Neelanchal        KVK             Chinese      U-1            350                                                    350
            TPP                   Neelanchal
Punjab      Talwandi Sabo TPP     M/s Sterlite    Chinese      U-1            660          660                660       17.06.14
Punjab      Talwandi Sabo TPP     Talwandi        Chinese      U-2            660          660                660       30.10.15
                                  Sabo Power
                                  Ltd
Punjab      Talwandi Sabo TPP     Talwandi        Chinese      U-3            660          660                660       29.03.16
                                  Sabo Power
                                  Ltd
Punjab      Rajpura TPP (         Nabha            L&T         U-2            700          700                700       06.07.14
            Nabha)                Power Ltd
Punjab      Rajpura TPP (         Nabha          BTG- L&T      U-1            700          700                700       24.01.14
            Nabha)                Power Ltd
Punjab      Goindwal Sahib        GVK              BHEL        U-1            270          270                270       14.02.16
            TPP                   Power
Punjab      Goindwal Sahib        GVK              BHEL        U-2            270          270                270       15.03.16
            TPP                   Power
Rajasthan   Jallipa-Kapurdi       Raj West        Chinese      U-5            135          135                135       05.02.13
            TPP,
Rajasthan   Jallipa-Kapurdi TPP   Raj West        Chinese      U-6            135          135                135       03.03.13
Rajasthan   Jallipa-Kapurdi TPP   Raj West        Chinese     U-8 #                                   135     135       28.02.13
Rajasthan   Jallipa-Kapurdi TPP   Raj West        Chinese     U-7 #                                   135     135       16.03.13
Rajasthan   Kawai TPP             Adani           Chinese     U-1 #                                   660     660       28.05.13
                                  Power Ltd.
Rajasthan   Kawai TPP             Adani           Chinese     U-2 #                                   660     660       24.12.13
                                  Power Ltd.
TN          Tutucorin TPP -       Ind Barath      Chinese     U-1 #                                   150     150       10.03.13
            2(Ind Barath)
TN          Tuticorin TPP(Ind     Ind Barath      Chinese     U-2 #                                   150     150       30.12.13
            barath)
TN          Tuticorin TPP-        IBPIL           Chinese      U-1            660                                                    660
            II(Ind barath)
TN          Melamaruthur TPP      Coastal         Chinese     U-1 #                                   600     600       02.12.14
                                  Energen
TN          Melamaruthur          Coastal         Chinese     U-2 #                                   600     600       02.01.16
            (Mutiara)             Energen
TN          ITPCL TPP             IL&FS TN        Chinese     U-1 #                                   600     600       19.09.15
                                  PC.Ltd
TN          ITPCL TPP             IL&FS TN        Chinese     U-2 #                                   600     600       18.04.16
                                  PC.Ltd
                                                                      18
State         Project Name          Impl           Main Plant     Unit        12th Plan    Cap. Ach.   Add.         Total    Actual     Slipped
                                    Agency         Equipment      No          Tar. Cap.   From         Cap.      cap. Ach.   Comm.
                                                    Supplier                              Target       Ach         (MW)      Date
                                                                                          (MW)         (MW)
Uttrakhand    GAMA CCPP           M/s               Others           Module-1#                           225       225       25.04.16
                                  GAMA
                                  Infraprop
                                  Ltd.
Uttrakhand    Kashipur CCPP       M/a               Others           Module-1#                           225       225       20.11.16
              Ph-I                Sravanthi
                                  Energy
                                  Pvt.Ltd
UP            Lalitpur TPP        Lalitpur          BHEL        U-2 #                                    660       660       08.01.16
                                  power
                                  Generation
                                  Co. Ltd
UP            Lalitpur TPP        Lalitpur          BHEL        U-1 #                                    660       660       26.03.16
                                  power
                                  Generation
                                  Co. Ltd
UP            Lalitpur TPP        Lalitpur          BHEL         U-3#                                    660       660       01.04.16
                                  power
                                  Generation
                                  Co. Ltd
UP            Prayagraj (Bara )   Prayagraj         BHEL         U-1         660                 660               660       25.12.15
              TPP                 power Gen.
                                  Co. Ltd(
                                  J.P.Power
                                  Ventures)
UP            Prayagraj (Bara )   Prayagraj         BHEL         U-2         660                 660               660           06.09.2016
              TPP                 power Gen.
                                  Co. Ltd(
                                  J.P.Power
                                  Ventures)
UP            Prayagraj (Bara )   Prayagraj         BHEL         U-3         660                                                          660
              TPP                 power Gen.
                                  Co. Ltd(
                                  J.P.Power
                                  Ventures)
WB            Haldia TPP-I        Haldia           Chinese       U-1         300                 300               300       14.01.15
                                  Energy Ltd
              Haldia TPP-I        Haldia           Chinese       U-2         300                 300               300       16.02.15
                                  Energy Ltd
                                  Total Private Sector                     43540            31285      22375.5    53660.5                12245
                  Total Commissioned during 12th Plan up to 31.03.17      72339.6          56466.85    35263.6   91730.45               15861.15
Note: # indicates the additional units commissioned which are not included in 12th Plan Target
              Difference of 11.60 MW is 10 MW in Vizag TPP (PS) and 1.6 MW in Namrup CCGT
                                                                         19
4.0 Thermal power projects Slipped from the 12th Plan Target with reasons for Slippage
State          Project Name         Impl Agency     Main       Unit      12th Plan       Reasons for Slippage
                                                    Plant      No        Slipped
                                                  Equipment              Cap.
                                                   Supplier              (MW)
CENTRAL SECTOR
Assam     Bongaigaon TPP            NTPC            BHEL         U-3        250          Frequent bandhs, Heavy monsoon and slow civil
                                                                                         works. Delay in supply of material by BHEL.
                                                                                         Work came to halt due to violence and mass
                                                                                         exodus of labour from site in 2011-12. Civil
                                                                                         works got affected due to poor performance by
                                                                                         civil contractors resulting in to their contract
                                                                                         cancellation. Balance civil and structural works
                                                                                         awarded to NBCC on 29.09.14 .
Bihar          Nabi Nagar TPP       NTPC            BHEL         U-2        250          Delay in acquisition of Land. Slow progress of
                                                                                         works by main plant civil agency M/s ERA
Bihar          Nabi Nagar TPP       NTPC            BHEL         U-3        250          resulting in delay in handing over civil fronts to
                                                                                         erection agencies. Delay in Supply of equipment
                                                                                         by BHEL. Agitation by villagers. Patches of land
                                                                                         could not be acquired because of unwillingness of
Bihar          Nabi Nagar TPP       NTPC            BHEL         U-4        250          people to accept compensation. Financial crunch
                                                                                         faced by CHP vendor(Techpro).
Bihar          Barh STPP-I          NTPC            Others       U-1        660          Delay due to contractual dispute of NTPC with
                                                                                         Power machine & Technopromexport, Russia.
                                                                                         *Orig. Sch. was in 2009-10 & 2010-11. Delay in
                                                                                         supply of boiler material and ordering of Bought
Bihar          Barh STPP-I          NTPC            Others       U-2        660          out Items(BOIs)by M/s TPE due to financial
                                                                                         constrant. M/s. TPE stopped work from 10/13.
                                                                                         M/s TPE contract was terminated on 14.01.2015
                                                                                         by NTPC. Delay in supply of material and slow
Bihar          Barh STPP-I          NTPC            Others       U-3        660          progress by M/s. Power Machine.
Assam          Namrup CCGT          APGCL           BHEL         ST        36.15         Delay in start and slow progress of of civil works,
                                                                                         Termination of civil contractor. Poor soil
                                                                                         conditions and heavy monsoon. Delay in supply
                                                                                         of material by BHEL & shortage of skilled
                                                                                         manpower. Termination of NBPL order. Delay in
                                                                                         award of civil and Electrical, Mechanical &
                                                                                         Instrumentation agency.
           Total State Sector                                              636.15
PRIVATE SECTOR
AP         Thamminapatnam           Meenakshi       Chinese      U-3        350          Slow progress of Civil works. Due to financial
           TPP-II                   Energy Pvt.                                          problem, work at site remained closed for a long
                                    Ltd                                                  time.
AP             Thamminapatnam       Meenakshi       Chinese      U-4        350
               TPP-II               Energy Pvt.
                                    Ltd
AP             BhavanapaduTPP       East Coast    Chinese        U-1        660          Work remained under suspension due to MoE&F
               Ph-I                 Energy Ltd.                                          order for a long time. After restart works
                                                                                         hampered due to two cyclones . Agitation against
AP             BhavanapaduTPP       East Coast    Chinese        U-2        660          State bifurcation. Slow progress of work at site
               Ph-I                 Energy Ltd.                                          due to financial problems.
Chattisgarh    Nawapara TPP         TRN energy      Chinese      U-2        300          Delay in start of civil works. Slow progress in
                                    Pvt.Ltd..                                            erection works of boiler and T.G. Manpower
                                                                                         shortage.
Chhattisgarh   Akaltara (Naiyara)   KSK             Chinese      U-3        600          Shortage of manpower, Agitation by Villagers.
               TPP                  Mahandi                                              Delay in supply of material due to fund contraints.
                                    Power Co.
                                    Ltd
                                                               20
State          Project Name         Impl Agency        Main      Unit   12th Plan   Reasons for Slippage
                                                       Plant     No     Slipped
                                                     Equipment          Cap.
                                                      Supplier          (MW)
Chhattisgarh   Salora TPP           M/s Vandana       Chinese     U-2      135      Delay in commissioning of unit-1. Agitation by
                                    Vidyut                                          vllagers at site. Delay in supply of BTG and CHP
                                                                                    material. Non cooperation of BTG supplier in
                                                                                    commissioning activities. Acquistion for railway
                                                                                    siding and ash pond.
Chhattisgarh   Uchpinda TPP         RKM               Chinese     U-3      360      Work suffered due to agitation by villagers. Slow
                                    Powergen                                        progress of work at site. Delay in readiness of
                                    Pvt. Ltd                                        BOPs.Delay in readiness of start up power. Delay
                                                                                    due to financial problem. Balance land acquistion
                                                                                    for ash pond and Railway line siding. Consent to
                                                                                    operate for U- 3 &4.
Chhattisgarh   Athena Singhitarai   Athena            Chinese     U-1      600      Delay in land acquisition. Slow progress of Boiler
               TPP                                                                  & TG erection. Delay due to financial problems.
Chhattisgarh   Binjkote TPP         SKS Power         Chinese     U-1      300      Delay in start of civil works. Slow progress of
                                    Gen                                             pressure parts erection. Balance land acquisition
Chhattisgarh   Binjkote TPP         SKS Power         Chinese     U-2      300      for ash dyke. Delay due to financial problems.
                                    Gen
Chhattisgarh   Binjkote TPP         SKS Power         Chinese     U-3      300
                                    Gen
Chhattisgarh   Lanco Amarkantak     LAP Pvt.          Chinese     U-3      660      Delay in acquisition of land for water system.
               TPP-II               Ltd.                                            Presently work is going slow at site due to
Chhattisgarh   Lanco Amarkantak     LAP Pvt.          Chinese     U-4      660      financial problems.
               TPP-II               Ltd.
Jharkhand      Matrishri Usha TPP   Corporate          BHEL       U-1      270      Law and order problem. Delay in supply of BTG
               Ph-I                 Power Ltd.                                      equipment. Delay in readiness of transmission line
                                                                                    due to forest clearance. Work held up due to
Jharkhand      Matrishri Usha TPP   Corporate          BHEL       U-2      270      financial problems since Nov, 12.
               Ph-I                 Power Ltd.
Maharashtra    Nasik TPP Ph-I       Ratan India        BHEL       U-3      270      Non-Acceptanceof BTG material by Project
                                    Nasik Power                                     Authorities. Work is going slow at site due to
                                    Ltd.                                            financial problems.
Maharashtra    Nasik TPP Ph-I       Ratan India        BHEL       U-4      270
                                    Nasik Power
                                    Ltd.
Maharashtra    Nasik TPP Ph-I       Ratan India        BHEL       U-5      270
                                    Nasik Power
                                    Ltd.
Maharashtra    Lanco Vidarbha       Lanco             Chinese     U-1      660       Work is going slow at site due to financial
               TPP                  Vidarbha                                        problems
Maharashtra    Lanco Vidarbha       Lanco             Chinese     U-2      660
               TPP                  Vidarbha
MP             Gorgi TPP ( D B      DB Power           BHEL       U-1      660      Order for main plant equipment has been placed.
               Power)               Ltd                                             Work is on hold. Commissioning schedule would
                                                                                    be assessed after re-start of work.
Orissa         Lanco Babandh        Lanco             Chinese     U-1      660      Delay in land acquisition. Work is going slow at
               TPP                  babandh                                         site due to financial problem.
                                    Power Ltd.
Orissa         Ind Bharat TPP       Ind Barath        Chinese     U-2      350      Delay due to heavy rains. Delay in readiness of
               (Orissa)                                                             transimission line for start up power.
Orissa         KVK Neelanchal       KVK               Chinese     U-1      350      Commissioning problems such as change of firing
               TPP                  Neelanchal                                      guns of boiler and change in bypass valve.
TN             Tuticorin TPP-       IBPIL             Chinese     U-1      660      Late start and slow progress of civil works and
               II(Ind barath)                                                       delay in supply of boiler structural material at
                                                                                    site.
UP             Prayagraj (Bara )    Prayagraj          BHEL       U-3      660      Delay in BTG supply, Raw water pipe line
               TPP                  power Gen. Co.                                  readiness and transmission line readiness for start
                                    Ltd( J.P.Power                                  up power. Progress of work at site delayed due to
                                    Ventures)
                                                                                    financial problems. Delay in Land Acqisition for
                                                                                    railway siding and power evacuation.
                                    Total Private Sector                  12245
                  Total Slippage from 12th Plan Target as on 31.03.17    15861.15
                                                                 21
5.0 THERMAL POWER PROJECTS UNDER CONSTRUCTION IN THE COUNTRY
S.No      State       Project Name /      LOA      Unit        Cap.    Org.      Ant.         Original /     Exp. In
  .                   Impl. Agency/       Date/    No          (MW)   Comm.     Comm.        Latest cost    Rs.crores.
                       EPC or BTG                                     Sched.    Sched.     (in Rs.Crores)
CENTRAL SECTOR
1.       Assam       Bongaigaon TPP/      Feb-08   U-3         250    Sep-11    Feb-19       4375.35/        7220.84
                     NTPC/ BHEL                                                              6749.18         (Dec-18)
2.        Bihar      Barh STPP-I          Mar-05   U-1         660    May-17    April-20       8693/        15278.98
                     /NTPC/Others                  U-2         660    Nov-17    Oct-20       15095.67       (Dec-18)
                                                   U-3         660    May-18    April-21
3.        Bihar      Nabi Nagar TPP /     Jan-08   U-3         250    Aug-13    Jan-19       5352.51/        7567.35
                     JV of NTPC &                                                              7998          (Dec-18)
                                                   U-4         250    Nov-13    Aug-19
                     Rlys/BHEL
4.        Bihar      New Nabi Nagar       Jan-13   U-1         660    Jan-17    Mar-19      13624.02 /      12594.35
                     TPP /JV of NTPC &                                                       15131.67       (Dec-18)
                     BSPGCL                        U-2         660    Jul-17       -
                     TG-Alstom &
                     Bharat Forge, SG-             U-3         660    Jan-18       -
                     BHEL
5.     Chhatisgarh   Lara TPP/NTPC /      Dec-12   U-2         800    Jun-17    Jun-19     11846/ 11846     10831.46
                     SG-Dooson TG-                                                                          (Dec-18)
                     BGR Hitachi
6.      Jharkhand    North Karanpura      Feb-14   U-1         660    Feb-18    Oct-19     14367/ 14367      7916.41
                     TPP/ NTPC / BHEL              U-2         660    Aug-18    April-20                     (Dec-18)
                                                   U-3         660    Feb-19    Oct-20
7.     Jharkhand     Patratu              Mar-18   U-1         800    Dec-21    Jan-22     18668/18668       1477.29
                     STPP/NTPC/BHEL                U-2         800    Jan-22    Jun-22                       (Nov-18)
                                                   U-3         800    Jul-22    Dec-22
8.     Maharashtra   Solapur STPP/        Apr-12   U-2         660    Nov-16    Mar-19       9395.18/        9026.43
                     NTPC/ SG-BGR &                                                          9395.18         (Dec-18)
                     Hitachi, TG-Alstom
                     & Bharat Forge
9.         MP        Gadarwara TPP/       Mar-13   U-1         800    Mar-17    Oct-18       11638.55/      10375.32
                     NTPC /BTG-BHEL                U-2         800    Sep-17    Jun-19       11638.55       (Dec-18)
10.        MP        Khargone TPP/        Mar-15   U-1         660    Mar-19    Mar-19       9870.51/        6693.90
                     NTPC/ EPC - L&T               U-2         660    Sep-19    Sep-19       11148.86        (Dec-18)
11.      Odisha      Darlipalli STPP/     Feb-14   U-1         800    Feb-18    May-19       12532.44/       8441.41
                     NTPC / SG- BHEL                                                         12532.44        (Dec-18)
                                                   U-2         800    Jun-18    Nov-19
                     TG-JSW & Toshiba
12.    Odisha        Rourkela PP-II,      May-16   U-1         250    Sept-18   Sept-19      1885.13/        1081.38
                     Expansion/ NTPC-                                                        1885.13         (Jan-19)
                     SAIL Power Co.
                     Ltd.
13.     Rajasthan    Barsingsar TPP       Nov-16   U-1         250    May-20    Aug-20                        158.18
                     ext/ NLC/ EPC-                                                           2112.59        (Feb-19)
                     Reliance Infra.
14.     Rajasthan    Bithnok TPP/ NLC/    Nov-16   U-1         250    May-20    Aug-20                        173.23
                     EPC- Reliance                                                            2196.30        (Feb-19)
                     Infra.
15.     Telangana    Telangana Ph- I /    Feb-16   U-1         800    Jan-20    April-20   10599/ 10599      3272.35
                     NTPC/SG- BHEL                                                                           (Dec-18)
                     TG- Alstom &
                                                   U-2         800    Jul-20    Oct-20
                     Bharatforge
16.        TN        Neyveli New TPP/     Dec-13   U-1         500    Sept-17   Mar-19       5907.11/        5461.30
                     NLC/BHEL                                                                5907.11         (Feb-19)
                                                   U-2         500    Mar-18    Apr-19
17.        UP        Meja STPP/ JV of     Apr-12   U-2         660    Dec-16    Aug-19        10821/           8464
                     NTPC &                                                                   10821          (Aug-18)
                     UPRVUNL/ SG-
                     BGR, G-Toshiba
18.        UP        Ghatampur TPP/       Aug-16   U-1         660    Nov-20    Sept-20      17237.80/       4256.66
                     JV of NLC &                   U-2         660    May-21    Mar-21       17237.80        (Feb-19)
                     UPRVUNL/ MHPS                 U-3         660    Nov-21    Sept-21
                     Boiler Pvt. Ltd.
19.        UP        Tanda TPP/ NTPC/     Sep-14   U-1         660    Sep-18    Mar-19       9188.98/        5433.65
                     SG: L&T/ TG:                                                            9188.98         (Dec-18)
                     Alstom                        U-2         660    Mar-19    Sept-19
                                                          22
S.No          State     Project Name /        LOA      Unit        Cap.     Org.      Ant.          Original /     Exp. In
  .                     Impl. Agency/         Date/    No          (MW)    Comm.     Comm.         Latest cost    Rs.crores.
                         EPC or BTG                                        Sched.    Sched.      (in Rs.Crores)
STATE SECTOR
1.             A.P     Dr.Narla Tata Rao     Oct-15    U-1         800     Jun-19     Jun-19       5286.54 /       3932.12
                       TPS St-V /                                                                    5515          (Jan-19)
                       APGENCO /
                       BTG- BHEL
2.             A.P     Sri Damodaran         Nov-15    U-1         800     Mar-19     Aug-19       4276.04 /         4186
                       Sanjeevaiah TPP                                                              4276.04        (Feb-19)
                       St-II / APGENCO
                       /BTG- BHEL
3.            Assam    Namrup      CCGT /    Feb-09    ST          36.15   Jan-12     Oct-19      411 / 693.73      581.48
                       APGCL / BHEL                                                                                (Jun-18)
4.         Gujarat     Wanakbori TPS         Oct-14    U-8         800     Oct-18     Mar-19       3536.51 /       3639.04
                       Extn. / GSECL                                                                3536.51        (Jan-19)
                       SG-Alstom
                       TG-Siemens
5.        Karnataka    Yelahanka CCPP        Nov-15    GT+         370     Mar-18     Mar-19       1571.18 /       1262.23
                       BY KPCL                         ST                                           1571.18        (Feb-19)
6.             MP      Shri Singhaji TPP     Sep-14    U-4         660     Jul-18     Mar-19      6500 / 7738      5862.59
                       St-II / MPGENCO                                                                             (Jan-19)
                       EPC-L&T
7.            Odisha   Ib valley TPP /       Mar-14    U-3         660     Sept-17    Feb-19     11965 / 11965     5068.83
                       OPGCL BTG-                                                                                  (Jun-17)
                                                       U-4         660     Jan-18     Jan-19
                       BHEL
8.       Rajasthan     Chhabra TPP            Mar-13   U-6         660     Jun-18     Feb-19      7920/ 7920       8929.39
                       Extn./RRVUNL /                                                                              (Jan-19)
                       L&T-MHPS
9.        Rajasthan    Suratgarh SCTPP/      May-13    U-7         660     Sep-16     Feb-19      7920 / 7920      8285.10
                       RRVUNL / BHEL                   U-8         660     Dec-16     Jun-19                       (Feb-19)
10.       Telangana    Bhadradri TPP /       Mar-15    U-1         270     Mar-17     Apr-19      5044 / 5044      4505.49
                       TSGENCO/ BHEL                   U-2         270     May-17     Jun-19                       (Feb-19)
                                                       U-3         270     Jul-17     Aug-19
                                                       U-4         270     Sept-17    Oct-19
11.       Telangana    Yadradri TPP/         Oct-17    U-1         800     Oct-20    2020-21       25099.42        3098.14
                       TSGENCO/ BHEL                   U-2         800     Oct-20    2020-21                       (Feb-19)
                                                       U-3         800     Oct-21    2021-22
                                                       U-4         800     Oct-21    2021-22
                                                       U-5         800     Oct-21    2021-22
12.            TN      Ennore exp.           May-14    U-1         660     Jan-18     Jun-19       5421.38 /        791.4
                       SCTPP (Lanco) /                                                              5421.38        (Dec-17)
                       TANGEDCO
                       BTG-LANCO
13.            TN      Ennore SEZ SCTPP/     Sep-14    U-1         660     Jan-18     Jul-20      9800 / 9800      3102.96
                       TANGEDCO/ BHEL                  U-2         660     Mar-18     Oct-20                       (Jan-19)
14.            TN      North Chennai TPP     Jan-16    U-1         800     Mar-19     Dec-19      6376 / 6376      3199.32
                       St-III TANGEDCO /                                                                           (Feb-19)
                       BHEL
15.            TN      Uppur Super           Feb-16    U-1         800     Mar-19     Apr-20     12778 / 12778      720.27
                       Critical TPP                    U-2         800     Oct-19     Oct-20                       (Feb-19)
                       TANGEDCO
                       /BHEL
16.            TN       Udangudi STPP St-I   Dec-17    U-1         660     Feb-21     Feb-21       13076.71/        332.85
                       / TANGEDCO/ BHEL                                                            13076.71        (Feb-19)
                                                       U-2         660     Feb-21    April-21
17.            UP      Harduaganj TPS        Sep-15    U-1         660     Jun-19    Jan-20        4826.49 /       1996.03
                       Exp-II/UPRVUNL                                                               5500.98        (Feb-19)
                       /Toshiba JSW
18.            UP      Jawaharpur STPP/      Dec-16    U-1         660     Sept-20    Mar-21       10556.27/         1021
                       UPRVUNL/                        U-2         660     Jan-21     July-21      10556.27        (Jan-19)
                       Doosan
19.            UP      Obra-C STPP/          Dec-16    U-1         660     Sept-20    Apr-21     10416 / 10416     1502.48
                       UPRVUNL/                                                                                    (Feb-19)
                       Doosan                          U-2         660     Dec-20    July-21
                       Panki TPS                       U-1         660      NA       Sept-21                          16
21.      UP                                  Mar-18                                                   NA
                       Extn./UPRVUNL                                                                               (Apr-18)
                       Bhusawal TPS/                   U-6         660       NA         NA
22.      Maharashtra                         Jan-18                                                  5097            NA
                       MAHAGENCO
                       Total State Sector                      22166.15
PRIVATE SECTOR
     1         AP      Bhavanapadu TPP       Sep-09    U-1         660     Oct-13    Uncertain     6571.94 /        3785.6
                       Ph-I / East Coast               U-2         660     Mar-14    Uncertain      9343.15        (Jan-16)
                       Energy Ltd.
                       BTG-Chinese
                                                              23
S.No      State         Project Name /      LOA      Unit        Cap.    Org.     Ant.          Original /     Exp. In
  .                     Impl. Agency/       Date/    No          (MW)   Comm.    Comm.         Latest cost    Rs.crores.
                         EPC or BTG                                     Sched.   Sched.      (in Rs.Crores)
                                                            24
S.No       State        Project Name /        LOA      Unit        Cap.     Org.     Ant.          Original /     Exp. In
  .                     Impl. Agency/         Date/    No          (MW)    Comm.    Comm.         Latest cost    Rs.crores.
                         EPC or BTG                                        Sched.   Sched.      (in Rs.Crores)
 19     Maharashtra   Shirpur TPP             Nov-11   U-2         150     Apr-15       *        2413 / 2413      2383.85
                      ,Shirpur Power Pvt.                                                                         (Nov-17)
                      Ltd.-BHEL
 20         MP        Gorgi TPP / D.B.        Mar-11   U-1         660     Jun-13   Uncertain    3941 / 3941       475.79
                      Power (MP) Ltd.                                                                             (Sep-15)
                      BTG-BHEL
 21         MP        Niwari TPP / BLA        Apr-11   U-2          45     May-14   Uncertain     232.49 /         290.01
                      Power Ltd./ BHEL -                                                           250.49         (Mar-15)
                      Siemens
 22       Odisha      Ind Barath TPP          May-09   U-2         350     Dec-11   Stressed     3150 / 4001        4254
                      (Odisha) / Ind                                                                              (Apr-17)
                      Barath /BTG-
                      Cethar Vessels
 23       Odisha      KVK Nilanchal           Nov-09   U-1         350     Dec-11   Uncertain    4990 / 6000      1708.36
                      TPP/        KVK                  U-2         350     Feb-12   Uncertain                     (Mar-15)
                      Nilanchal /
                      BTG-Harbin China                 U-3         350     Feb-12   Uncertain
 24       Odisha      Lanco Babandh           Nov-09   U-1         660     Apr-13   Stressed    6930 / 10430        7615
                      TPP / LBP Ltd./                                                                             (Mar-17)
                      BTG-Chinese
                                                       U-2         660     Aug-13   Stressed
 25       Odisha      Malibrahmani TPP        Jun-10   U-1         525     Dec-12   Uncertain    5093 / 6330      5329.75
                      / MPCL/ BTG-                                                                                (Dec-14)
                                                       U-2         525     Feb-13   Uncertain
                      BHEL
 26         TN        Tuticorin TPP (Ind-     May-10   U-1         660     May-12    19-20       3595 / 3595       2000
                      Barath) / IBPIL /                                                                          (May-15)
                      BTG-Chinese
 27         TN        Tuticorin TPP St-       Jan-14   U-1         525     Sep-18    Dec-19      3514 / 3514      1905.65
                      IV / SEPC/ EPC-                                                                             (Feb-19)
                      MEIL (BTG-BHEL)
 28        WB         Hiranmaye Energy        Sep-10   U-3         150     May-16       *        2656 / 3307      3263.05
                      TPP/ BTG-BHEL.                                                                              (Oct-17)
                                                              25
CENTRAL
 SECTOR
   26
      BROAD STATUS OF UNDER CONSTRUCTION CENTRAL SECTOR THERMAL POWER PROJECTS
                                 (NTPC Limited)
Sl.                            Cap.                Commissioning Schedule
No.       Project Details     (MW)           Original       Actual(A)      /   As   now                          Broad Status
                                                            Expected
                                           Syn.         COD    Syn.             COD
                                           Com                 Com
       Central Sector
1.     Bongaigaon TPS,            750                                                     Unit-1:
       Distt: Kokrajhar,                                                                  COD achieved on 01/04/2016. Commissioned on
       Assam NTPC Ltd                                                                     22/06/15(A).
                                                                                          Boiler: Boiler Erection started on 27/02/2009.Drum
                        U-1   250         11/10        -      06/15(A) 01/04/16(A)        lifted on 25/01/2010.Hydro test done on 01/2011. BLU
                                          01/11            22/06/15(A                     done on 29/11/14 & steam blowing completed on
                         U-2 250          03/11        -      02/17(A) 01/11/17(A)        01/04/15.
                                          05/11             22/03/17(A                    TG: Condenser erection started in 2/10. TG erection
                         U-3 250          07/11        - 02.01.19(A)    02/19             started in 03/11& boxed up in 04/15.
                                          09/11                02/19                      Unit-2:
           Original / Latest cost : Rs. 437535 Lakhs/ Rs. 674918 Lakhs                    COD achieved on 01/11/2017. Unit commissioned on
                                                                                          22/03/2017.
          Exp. During 2007-08       : Rs. 23831 Lakhs                                     Boiler: Boiler Erection started on 3/10 & Drum lifted in
                      2008-09       : Rs. 16046 lakhs                                     10/10.Hydro test done in 04/12. BLU done on 27.03.16.
                      2009-10       : Rs 70913 lakhs                                      Steam blowing completed in 11/16.
                      2010-11       : Rs 56300 lakhs                                      TG: TG erection started in 01/16. TG Box up completed
                      2011-12       : Rs 137610 Lakhs                                     in 11/16.TG oil flushing completed in 12/16.
                      2012-13       : Rs. 74900 Lakhs                                     Synchronization achieved in 02/17.
                      2013-14         Rs. 68500 Lakhs                                     Unit-3:
                      2014-15       : Rs. 65700 Lakhs                                     Unit synchronized on 02.01.19.
                      2015-16       : Rs. 78700 Lakhs                                       Boiler: Boiler Erection started in 4/12. Boiler drum
                      2016-17       : Rs. 59100 Lakhs                                       lifted on 25/02/13 & HT done on 21/03/14. BLU done
                      2017-18       : Rs. 50600 Lakhs                                       in 07/2017. Steam Blowing is completed in 09/18.Coal
                      2018-19       : Rs. 22088 Lakhs (12/18)                               firing done in 12/18.
         Cumulative Exp.            : Rs. 722084 lakhs(12/18)
                                                                                           TG: TG deck casting done in 03/16. TG erection started
           Investment Approval      : 30/01/2008                                           in 10/16. HP, IP module placed. TG boxed up in
                    Type of fuel : Coal                                                    03/18.TG put on barring gear.
           Investment Approval : 30/01/2008
                                                                                           Balance of Plant:
       Date of Main Plant Order       : 05/02/08,M/s BHEL
                                                                                           Chimney: Completed.
             Power Evacuation:       1. 400KV BTPS(NTPC)-                                  CHP: Order placed on M/s McNally Bharat in Jan’10.
                                     Bongaigaon (PG) D/C Line                              Both Trippers are ready and coal bunking conveyors
                                     2. 220 KV BTPS(NTPC)-                                 commissioned.
                                     Bongaigaon (Assam ) D/C Line                          AHP: Order placed on M/s McNelly Bharat in Jun’09.
       Coal Source and Transportation :                                                    Unit#3 Bottom Ash trench completed. Fly Ash trench
       2/3 of required Coal will be transported from Margarita- Makuma mines of NECL       completed. Dry Ash extraction system Silo-1&II
       (Upper Assam).Rest 1/3 will be supplied by ECL mines in Raniganj area of West       commissioned.Ash dyke is ready. Dry ash system
       Bengal. Coal will be transported using Railway wagons by BOBR.                      resdiness by Feb’19.
                                                                                           CW: CW pumps commissioned.
                                                                                           DM plant: DM system is in serivce.DM control rrom
                                                                                           building civil work is in progress.
                                                                                           FGD: Awarded with SG Package to BHEL.Resolution
                                                                                           of Commercial issues between M/s BHEL and OEM of
                                                                                           FGD M/s Ducon is awaited.
                                                                          27
Sl.                                   Cap              Commissioning Schedule
No.    PROJECT DETAILS               (MW)                                                                           Broad Status
                                                     Original          Actual(A) / As
                                                                       now Expected
                                                  Syn.       COD        Syn.    COD
                                                  com.                  com.
      Central Sector
2.    Barh STPP St-I,                 1980                                                  Unit-1:
      Dist: Patna, Bihar                                                                    Main Plant
      (NTPC Ltd.)                                                                           Boiler: Boiler erection started in 03/11. Boiler Hydro Test
                            U-1        660        03/09      06/17     04/20      8/20      completed on 28.02.13. Boiler light up expected by 12/19.
                                                  08/09                04/20                Multiple tube leakage observed from super heater and re-
                                                 05/17*                                     heater action has been taken for replacement of material.
                                                 05/17*                                     TG: TG erection started in 08/11. TG Box up completed on
                            U-2        660        01/10      12/17     10/20     02/21      28/12/13. 1st stage of TG oil flushing completed and other
                                                  06/10                10/20                works are in progress.
                                                 11/17*                                     Unit-2:
                                                 11/17*                                     Boiler: Boiler erection started in 07/11. Boiler Hydro Test
                           U-3          660       11/10                                     expected by 01/20.
                                                  04/11     06/18       4/21      8/21      TG: TG erection started in 09/11.TG Box up completed in
                                                 05/18*                 4/21                01/15. TG oil-flushing completion expected by 05/20.
                                                 05/18*                                     Unit-3:
                                       (*Revised as per award of balance works of SG        Boiler: Boiler erection started in 01/12. Boiler Hydro Test
                                                  package dated 30.01.16)                   expected by 07/20.
            Original/Latest Cost    : Rs869300/1509567 lakhs                                TG: TG erection started in 03/12.TG box-up expected by
                                                                                            09/20.
            Cum Exp.upto 2009      : Rs 396710 lakhs
                       2009-10     : Rs 69539 lakhs                                         Balance of Plant (BoP):
                       2010-11     : Rs 92200 lakhs                                         Chimney: Ready
                       2011-12     : Rs 127200 lakhs                                        CHP: Erection up to TP-4 completed. Beyond TP-4 erection
                       2012-13     : Rs 143300 lakhs                                        is in progress. Track hopper & MT system stream
                       2013-14     : Rs 160100 lakhs                                        commissioned.
                       2014-15     : Rs 81100 lakhs                                         AHP: Erection of ash water pumps, vacuum pumps, 3 Nos.
                       2015-16     : Rs 116700 lakhs                                        FAE tower structures completed. Trench work, Ash slurry
                       2016-17     : Rs 147400 lakhs                                        sump, BA line pedestal work in progress.
                       2017-18     : Rs. 139500 Lakhs                                       Ash dyke: All works in Ash Dyke completed.
                       2018-19     : Rs. 717642 Lakhs (12/18)                               Cooling Tower: Erection completed. Water charging done
               Cumulative Exp      : Rs 1527898 lakhs (up to 12/18)                         once, repair/replacement required.
           Investment Approval     : Feb’05                                                 PT Plant: 2 clarifiers Ready
          Sanctioning Authority : NTPC Board                                                DM Plant: Ready
                                                                                            CW System: Erection nearly completed. 2nos Raw water
                   Type of fuel : Coal
                                                                                            pumps & SACW pumps commissioned.2nos CW pupmps
       Date of Main Plant Order SG :03/2005 on M/s Technopromexport, Russia.                trial taken.
                         (BTG) (Terminated on 14.01.2015) #                                 Switchyard: Ready
                                  TG : 03/2005 on M/s Power Machines Russia
                       Zero Date    14/03/2005                                              FGD: FGD is awarded to BHEL on 18.09.18.Yet to
                                                                                            mobilize. Basic Engg ordering in progress.
              Power Evacuation
                  Critical Areas    Multiple failures of Boiler#1 Super heater and Re-heater tubes (DI 59 materials) for which action plan is under
                                    finalization for expeditious supply of new materials and restoration of Boiler to move forward. Readiness of railway
                                    line 250 km (Hazaribagh-Koderma-Tillaiya Rajaji-Bhaktiyarpur) is critical for transportation of coal. Project would
                                    face major coal supply constraints till this line is made operational. Following activities are critical for completion
                                    of the coal transportation route. NTPC funded Rs. 664 Crores to Railways for development of following works in
                                    envisaged coal transportation route. Construction of Karnauti-Bakhtiyarpur flyover with 3rd line and surface
                                    triangle. ROR portion work is suffering due to encroachment from villagers. Construction of ManpurFlyover
                                    (ROR)- Work is suffering in want of land acquisition (apprx 32 Hectares) from State Government. Electrification of
                                    Manpur-Tillaiya-Bakhtiyarpur section. Work progress is slow due to land issues faced by Railways. Out of this 250
                                    Km route Koderma-Tillaiya stretch (65 km) is being constructed in three phases,Phase-II (25.2 Km to 49.5 Km from
                                    Tillaiya side) work has not yet started as it involves 330 Acres of Forest land in Bihar State and forest clearance for
                                    the same is pending. It is required for construction of New Broad Gauge Line from Koderma to Tillaiya.
                                    USA has imposed sanction on Power Machines,Russia on 26 th Jan’18 which is a major issue for balance
                                    supply,erection & commissioning of TG & Aux package.
             Reasons for Delay      Non-Performance by TPE (SG contract) & M/s PM.
                                                                            28
Sl.                                   Capacity            Commissioning Schedule
No.    PROJECT DETAILS                 (MW)                                                                          Broad Status
                                                      Original        Actual(A) / As now
                                                                      Expected
                                                   Syn.      COD        Syn.       COD
                                                   com.                 com
      Central Sector
3.    Nabinagar TPP, Dist:              1000                                               Unit-1:
      Aurangabad, Bihar                                                                    COD achieved on 15/01/17. Commissioned on
      [BRBCL-Bhartiya Rail                                                                 20.03.2016.
      Bijlee Co. Ltd. (JV of                                                               Boiler: Boiler erection started in 05/11. Boiler drum lifted
      NTPC & Indian                                                                        on 20/10/12. Boiler HT completed on 11.04.2014. BLU
      Railways)]                                                                           done in Mar’15. Chemical cleaning completed on 11.10.15.
                                                                                           SBO completed in 01/16.
                              U-1         250      08/10*     06/13    03/16(A) 15/01/17( TG: Condenser erection started on 26.2.13. TG erection
                                                   10/10*             20/03/16(A)   A)
                                                                                           started in 01/14. TG Box-up done in 12/15. TG oil flushing
                                                   12/12**                                 completed in 12/15.
                                                   02/13**                                 Unit-2:
                              U-2         250      02/11*     10/13    03/17(A) 10/09/17   COD achieved on 10/09/17. Unit commissioned on
                                                   04/11*             30/04/17(A) (A)      03.04.2017(A).
                                                   03/13**                                 Boiler: Boiler erection started in Dec’11. Boiler drum lifting
                                                   05/13**                                 completed on 21st Mar’13. Boiler HT completed in 02/15.
                              U-3         250      08/11*     02/14 31/12/18(A) 03/19      BLU done in 10/16.
                                                   10/11*             23/01/19(A)          TG: TG deck casting completed in 04/15. Condenser
                                                   06/13**                                 erection started in 05/15. TG erection started in 10/15. TG
                                                   08/13**                                 box-up done in 02/17.
                           U-4           250       02/12*                07/19      10/19  Unit-3:
                                                   04/12*     06/14      08/19             Commissioned on 23.01.19. Unit Syn on 31.12.18
                                                   09/13**                                 Boiler: Boiler erection started in 11/11. Boiler drum lifting
                                                   11/13**                                 completed on 10.06.13. Boiler hydro test done on 30.11.16.
                                                   (* Org /                                Trial run completed on 10.02.19.
                                                   ** Rev)                                 TG: TG erection started in 06/16. TG box-up done in 3/18.
          Original/Latest. Cost      : Rs 535251 /799800 lakhs                             TG Deck floating work started on 28/08/18
      Exp. During    2007-08           : Rs 26319 lakhs                                    Unit-4:
                       2008-09         : Rs 6837 lakhs                                     Boiler: Boiler erection started in 12/12. Boiler drum lifting
                       2009-10         : Rs 19617 lakhs                                    completed on 16.09.13.
                       2010-11         : Rs 22680 lakhs                                    TG: TG columns work in progress. TG erection start
                       2011-12         : Rs 48713 lakhs                                    expected by 03/19.
                       2012-13         : Rs109668 lakhs                                   Balance of Plant:
                       2013-14         : Rs130068 lakhs                                     Chimney: Chimney-1(for U-1&2) ready. Chimney #2
                       2014-15         : Rs 90604 lakhs                                       (for U-3&4) shell casting completed. Flue can erection
                       2015-16         : Rs 92777 lakhs                                       completed for U-3.
                       2016-17         : Rs 92409 lakhs                                     CHP: Coal feeding in progress at both 2A & 2B Side.
                       2017-18         : Rs 70571 lakhs                                       WT1 – Commissioned on 25.12.18. SR-2 Bal foundation
                       2018-19         : Rs 43869 lakhs (12/18)                               civil work i/p.
             Total Expenditure       : Rs 756735 lakhs (12/18)                              AHP (Indure): AWPH, Ash slurry Trench has been
      Investment Approval            : January’2008.                                          completed, Compressor house comm. U-3 BAH
                                                                                              completed.Clinker grinder work is u/p.
      Sanctioning Authority          : BRBCL board accorded investment approval
                                                                                            CW Pump house: Forebay raft completed. Pumps (11
                     Type of fuel    : Coal ( Pachra and South Pachra blocks of North         Nos) erection completed. CW Pump 5 & 6 trial run taken
                                     Karanpura Coalfields)                                    on 24/08/18
                     Fuel linkage     : 5 MTPA (FSA signed on 29.08.13)                     IDCTs: Order placed in Sep’13. IDCT is FRP type. There
       Date of Main Plant Order      : 23.01.2008 on M/s BHEL(BTG)                            are 20 cells in each IDCT. IDCT-1&2 ready. IDCT-3 cells
                                                                                              completedand fan trail taken.. IDCT-4 cells (08/20) in
                       Zero Date       : 01/01/2008                                           progress.
                                                                                            PT palnt: Completed in all respect.
                                                                                            DM plant: DM plamnt comm. DM lab building civil
              Power Evacuation         : ATS work completed and is in charged condition.
                                                                                              work is i/p. CW treatment is i/p.
                                                                                            FOHS: LDO tanks commissioned. HFO tank work isi/p.
                    Critical AreasUnit-2:SG Supplies, Poor mobilization by M/s ERA (main plant civil agency); Unit-3:Boiler erection, Land availability
                                  for ESP;Unit-4:Structural material to be expedited, Land availability for ESP;
                                Land acquisition issues :out of 1526.873 acres, 1392.628 acres is in physical possession) for makeup water corridor,
                                railway siding & critical patches inside plant and ash dyke due to unwillingness of people to accept compensation;
                                Frequent bandhs/Local agitation by villagers.
              Reasons for Delay Delay in land acquisition, Civil Works, SG Supplies, Frequent bandhs/Local agitation by villagers
                                                                             29
Sl. No.                                 Capacity               Commissioning Schedule
            PROJECT DETAILS              (MW)                                                                                  Broad Status
                                                            Original                  Actual(A) /
                                                                                     Anticiciapted
                                                        Syn.           COD           Syn.      COD
                                                        com.                         com
          Central Sector
 4.       New Nabinagar STPP,             1980                                                            Unit-1:
          Dist.: Aurangabad, Bihar                                                                        Unit synchronized on 14.01.19.
          [NPGCPL- Nabinagar                                                                              Boiler: Boiler erection started on 15th Jun’14 (delay:
          Power Generating Co.                                                                            05 months). Hydro test done in 12/16. BLU done in
          Pvt. Ltd. (JV of NTPC &                                                                         07/17. Steam blowing completed on 27.12.17.
          BSPGCL)]                                                                                        TG: Condenser erection started in 09/15. TG erection
                                U-1        660     11/16               05/17   14/01/19(A)     03/19      started in 01/16. TG Box-up achieved in 12/16. TG oil
                                                   01/17                           03/19                  flushing completed in 06/17.TG on barring gear on
                                                                                                          14.09.17 .
                                  U-2      660  05/17           11/17            -             09/19
                                                07/17                                                     Unit-2:
                                U-3 660         11/17           05/18            -             08/20      Boiler: Boiler erection started on 29.11.14. Hydro test
                                                01/18                                                     completed. Boiler light up expected in 02/19.
          Orig.Cost/Latest Cost     : Rs 13624.02 Cr/15131.67 Crores                                      TG:TG raft casting completed.TG erection started in
                                                                                                          12/16.TG boxed-up in 06/17.
                Exp. During 2008-09     :Rs     10 lakhs
                            2009-10     :Rs 22290 lakhs                                                   Unit-3: Boiler erection started on 29.04.2015. Hydro
                            2010-11     :Rs 8300 lakhs                                                    test expected in 2/19.
                            2011-12     :Rs 38392 lakhs                                                   TG:TG erection started on 31.07.17. TG boxup
                            2012-13     :Rs 71117 lakhs                                                   completed in 06/18.
                            2013-14     :Rs 36991 lakhs                                                   BOPs:
                            2014-15     :Rs 153432 lakhs
                                                                                                           Chimney: Chimney-1(Unit-1) & Chimney-2 (Unit-
                            2015-16     :Rs 269712 lakhs
                                                                                                            2&3) shell casting completed. Flue can erection
                            2016-17     :Rs 307000 lakhs
                                                                                                            completed for U-1, 2 & 3.
                            2017-18     :Rs 226500 lakhs
                                                                                                           CHP: Order has been placed on M/s TRF Ltd in
                            2018-19      Rs 125691 lakhs
                                                                                                            March’13. Coal Transportation- 2nos NPGC Loco
               Cum. Exp up to 03/18       Rs 1259435 lakhs (12/18)
                                                                                                            Trial Run from Warf Wall to R&D and R&D yard to
          Investment Approval           : 31.01.2013(Jan’13)                                                Inside plant completed on 25.05.18
          Sanctioning Authority         : NTPC Board                                                        Rail laying 6.5 km completed.
                                                                                                            Crusher house, Stacker cum reclaimer, Crusher
                    Type of fuel/FSA     : Coal. Coal linkage from CCL for 7.03Million Ton Per              house work has been completed. Wagon tippler
                                         Annum. For commissioning coal 2 Lakh MT MOU has                    work is u/p.
                                         been signed. FSA will be signed after unit commissioning           AHP: Fly Ash water pump house work
                                         as per guideline.                                                    completed.BASPH motors no load trail run
                          Zero Date      : 31.01.2013                                                         completed. Bottom ash hopper U#2 column work
             Date of Main Plant Order    TG –M/s ALSTOM-Bharat Forge on 31.03.2013.                           in progress.HCSD silo and other work is u/p.
                                         SG-Awarded to M/s BHEL on 31.01.2013.                              DM plant: Order placed on M/s Thermax in
                                                                                                              Jan’14. All the three streams charged manually.
                    Financial Closure  loan from REC. Debt, equity ratio is 70:30. NOC from                   Work for two streams completed for auto mpde.
                                       BSPCB received on 08.04.2011                                         CW pump house: CW pump 1,2,3&4 load trail
                   Main plant order Boiler erection agency: U-1&3 – Powermech and U-2 is                      done.RWPH2/3PT pump comm.CWPh 2/2 mototrs
                                       Indwell.                                                               trail done.
          MOEF clearance received in Dec 2010. Mega status received in Apr’09.                              IDCTs: Order placed on M/s Fans. CT # 1A:-
                                                                                                              Motor trial run in progress CT # 1B:-
          Power Purchase Agreement :- ( Bihar/BSEB:-1552.5 MW signed on21.01.10, Jharkhand:-                  commissioned. CT # 2A:- Piping work completed.
          60 MWsigned on 01.12.10, Sikkim :-10 MW signed on 28.09.10,UP:-209 MWsigned on                      Equp erection is i/p.CT # 2B:- Civil work
          07.04.18, Un-Allocated - 148.5MW)                                                                   completed.. CT # 3A:-16 /16 Deck Slab completed.
          Power Evacuation System: Being Executed by PGCIL. 400 kV One line from NPGC to                      CT # 3B:-Column up to lev – 1,12 cells completed.
          GAYA is charged. Second line 400 kV NPGC to Patna - work under progress                             CT # AUX: - Commissioning completed MCC-
                                                                                                              1/CR: Panel charged on 23.09.17 MCC-2&3:- u/p.
          Coal Transportation- 2nos NPGC Loco Trial Run from Warf                                           Switchyard:       132kV     line    charged.400kV
          Wall to R&D and R&D yard to Inside plant completed on                                               switchyard charged..Power evacuation line(400kV)
          25.05.18                                                                                            nabinagar-Gaya line charged
          Rail laying 6.5 km completed.                                                                     FGD: Under bulk tendering process by NTPC ltd.
          CHP:-                                                                                               BOD in June 2018.
          Crusher House:-04/04 crushers alignment, Floor casting Civil work &
          Structure Erection completed.
          Conveyor Galley- 2A/B,3A/B,4A/B, 5A/B, 6A/B,7A/B structure
          erection completed.
          Wagon Tippler:
          WT3- Civil work completed. Mechanical erection in progress.Side arm
          charger erection completed.
          WT 1-2- Apron feeder raft and slab (-10.5m) completed
          TP-1 0Mtr floor Casting completed on 22.04.18
          Track Hopper: - 0.0m slab for seg-9, 8, 7, 6, 5, 4&3 completed.
          Hopper for Seg-8 & 9 completed
                        Critical Areas Land acquisition for MUW corridor ( 9.78 Acres), outfall drainage corridor (19.44 Acres) total 29.22 acres
                   Reasons for Delay     Acquisition of balance land and relocation of homestead owners still living inside the project area.
                                                                                      30
Sl.                            Capacity         Commissioning Schedule
No.   PROJECT DETAILS           (MW)                                                                         Broad Status
                                              Original       Actual(A) / As
                                                             now Expected
                                           Syn.     COD        Syn.     COD
                                           com.                com
      Central Sector
5.    Lara STPP,                 1600                                               Unit-1:
      Dist: Raigarh,                                                                Unit commissioned on 22/03/18. Synchronized on oil on
      Chhattisgarh (NTPC                                                            09/09/17.
      Ltd.)                                                                         Boiler: Boiler erection started on 23/12/13. Boiler Hydro test
                      U-1         800     09/16     03/17 09/09/17(A) -             done on 12/15.BLU done in 01/17.SBO completion done in
                                          11/16           22/03/18(A)               05/17.
                                                           05/19      09/19         TG: Condenser erection started on 29.05.2015 and TG
                        U-2       800   03/17       09/17 6/19                      erection started in 08/15.TG box-up done in 02/17. TG oil
                                        05/17                                       flushing completed in 07/17.
        Investment Approval : 07.11.2012                                            ESP: 05 out of 06 passes of ESP erection completed.
       Sanctioning Authority : NTPC Board
                                                                                    Unit-2:
              Orig.Est. cost : Rs 1184600 lakhs                                     Boiler: Boiler erection started in 04/14. Boiler Hydro test
             Latest.Est. Cost : Rs 1184600 lakhs                                    done on 26/04/16. BLU completed on 24.12.18.
         Exp.During 2011-12     : Rs 28000 Lakhs                                    ESP: ESP structural erection completed. ESP hoppers erection
                    2012-13     : Rs 77300 Lakhs                                    completed in 3rd pass and hopper erection works are in
                    2013-14     : Rs 53500 Lakhs.                                   progress in 4th pass.
                    2014-15     : Rs 214700 Lakhs.                                  TG: Condenser erection started in 01/16. TG deck casting
                    2015-16     : Rs 238300 Lakhs                                   started on 26.05.16. TG erection started in 02/17. TG Box-up
                    2016-17    : Rs 190000 Lakhs                                    expected in 02/19.
                    2017-18     : Rs. 151200Lakhs                                   BOPs:
                    2018-19    : Rs 105228 Lakhs ( 12/18)                           Chimney: U#1& U#2 flue can erection completed
                  Cum Exp       : Rs 1083146 lakhs (up to 12/18)                    CHP: Both streams commissioned from TH to Bunker for
               Type of fuel    : Coal                                               U#1. Work for U#2 affected due to pending civil works in
                                                                                    ERA. Stacker reclaimer work in progress.
                Fuel linkage                                                        AHP: Unit-1 system commissioned and ash discharged up to
          Date of Main Plant    SG- M/s Doosan, in Dec’12                           ash dyke. Erection of U#2 BAH, HCSD silo(balance 2 nos.),
                Order (BTG)     TG - M/s BGR Hitachi in Dec’12                      HCSD PH equipment, ASPH(3rd stream)erection is in
                                13.12.2012                                          progress. However, due to financial condition of agency,
                  Zero Date
                                                                                    balance supplies for U#2 are critically delayed. Frequent
           Power Evacuation     There are two nos. of D/c evacuation lines from
                                                                                    stoppage of work by workers due to non payment of wages is
                                Lara switchyard, each line is capable of
                                                                                    affecting progress.
                                evacuating around 1000 MW. One line is going
                                                                                    Ash dyke: Order placed on M/s K N International in Dec’13.
                                to Champa and the other going to Kotra. Tower
                                                                                    Ash dyke is located around 06 km from the plant. Ash slurry
                                erection, stringing of one line near to the plant
                                                                                    lines works from ash slurry pump house to ash dyke to be
                                is completed and for the other line stringing is
                                                                                    completed. Presently ash slurry lines pedestals work started.
                                to be done.
                                                                                    Excavation and bund raising works are in progress.
                                                                                    PT Plant: Both streams are commissioned.
                                                                                    DM Plant: Both streams for DM water generation are ready.
                                                                                    CWPs: CW pump house is of open type in this project. U-1:
                                                                                    Stream Commissioned, U-2: equipment erection is u/p.
                                                                                    IDCT: For each unit there are 02 blocks of IDCTs. Each
                                                                                    IDCT is having 09 nos. of cells. Unit-1 circuit is
                                                                                    commissioned & unit-2 comm is in progress.
                                                                                    Switchyard: ST charged.
              Critical Areas    Delay in completion of site priority infrastructures i.e. road & drain etc. and balance earthwork at water reservoir
                                #2, in plant MGR area etc. State Govt. help (GoCG commitment given during PRAGATI Meeting held in Feb’16
                                for LA is May’2016: Not attained) solicited in acquisition of Land for MGR route, balance left out land in
                                Plant/Township area, MuW pipe corridor & pump house, Permanent approach road, Dolamite mining area in
                                reservoir-II/ Ash Dyke etc. Balance payment to be disbursed where Sec-23 (award) is done and also award of
                                balance 3 villages to be expedited. Tree cutting in Villages where approval received needs to be expedited.
          Reasons for Delay     Slow progress of TG side civil works, Delay in supplies of Generator Transformer, supply of BFP discharge
                                piping, Delay in land acquisition. Delay in TDBFP readiness for U-1, Delay in Boiler auxiliaries for U-2 BLU
                                                                         31
Sl.                             Capacity       Commissioning Schedule
No.        PROJECT               (MW)                                                                       Broad Status
                                              Original         Actual(A) / As
           DETAILS
                                                               now Expected
                                           Syn.      COD        Syn.    COD
                                           com.                 com
      Central Sector
6.    North   Karanpura          1980                                               Unit-1:
      STPP, Dist.Chatra,                                                            Boiler: Boiler erection started in 04/16. Hydro test completed
      Jharkhand NTPC ltd                                                            in 1/19.
                       Unit-1     660      12/17    04/19      09/19      4/20
                                           02/18               10/19                TG: TG erection started in 11/17. TG Boxup expected in
                                          02/19*                                    03/19.
                                          02/19*
                       Unit-2     660      06/18    10/19      02/20      10/20
                                           08/18               04/20
                                          08/19*                                    Unit-2:
                                          08/19*                                    Boiler: Boiler erection started in 07/16. Hydro test expected in
                       Unit-3     660      12/18    04/20      08/20      04/21     02/19.
                                          02/19                10/20
                                          02/20*                                    TG: TG erection started in 01/18. Boxup expected in 08/19
                                          02/20*
                                * Revised Schedule.                                 Unit-3:
                                                                                    Boiler: Boiler erection started in 06/17.
       Original /Latest Cost    : Rs 1436658 Lakhs
      Exped. during2013-14      : Rs. 153000 lakhs                                  TG: TG civil work started in 06/16. TG erection start expected
                   2014-15      : Rs. 52500 lakhs                                   in 02/19.
                   2015-16      : Rs 57300 lakhs
                   2016-17      : Rs 220800 lakhs
                   2017-18      : Rs 204200 Lakhs                                   BOP:
                   2018-19      : Rs. 99807 Lakhs ( 12/18)                          Chimney: U-1 flue can erection in progress.
          Cumulative Exp        : Rs. 791641 lakhs (up to 12/18)                    U-2 beam erection in progress. U-3 chimney shell 253 mtr.
                Type of fuel    : Coal                                              CHP: Civil & Structural works under progress
                                                                                    AHP: Civil & Structural works under progress
       Investment. approval     Feb 2014
                                                                                    PT/DM Plant: Civil works on clarifier in progress. Tank
         Date of Main Plant      EPC placed on BHEL (except external CHP,          foundations completed.
                     Order       MUW system and Ash dyke) in Feb'14. Main           Cooling Towers: Supplies under progress.
                                 plant civil works awarded on BHEL/Sunil
                                 Hitech.                                            FGD: Awarded to BHEL on31.07.18
             Critical Areas     Balance land acquisition (53.03 Acres), Lease transfer of 704 Acres of Govt. land, water system package,
                                Switchyard transmission system by BHEL, ATS/Start up power, No objection certificate from MoC is required
                                for start of transmission line works for startup power readiness by Dec 2018.
         Reasons for Delay      Delay in start of Civil works due to land acquisition issues. Delay in BHEL supplies related to boiler foundation.
                                Delay in land handover by NTPC to BHEL due to change in main plant area location change in plot plan. Delay in
                                award of ACC package by BHEL.
                                                                          32
Sl. No.                          Capacit          Commissioning Schedule
              PROJECT              y                                                                             Broad Status
                                              Original        Actual(A) / As now
              DETAILS            (MW)
                                                              Expected
                                           Syn.      COD        Syn.       COD
                                           com.                 com
          Central Sector
 7.       Kudgi STPP ST-I,        2400                                                 Unit-1:
          Dist: Bijapur,                                                               COD achieved on 31/07/17. Commissioned on 25/12/16.
          Karnataka, NTPC                                                              Boiler: Boiler erection started on 04.05.13. Boiler hydro test done
          Ltd.                                                                         in 01/15. BLU done in 12/15. SBO completed on 12.06.16.
                         U-1       800  09/15     04/16         12/16 31/07/17(A)
                                        12/15                25/12/16(A)               TG: Condenser erection started in 02/14. TG erection started in
                           U-2    800   03/16     10/16         03/17    31.12.17(A)   Jun’14. TG box-up done on 24.04.2015. TG oil flushing started in
                                        06/16                22/03/17(A)               Jun’15 and completed in 11/15. TG put on barring gear in 12/15.
                                 800    09/16     04/17       08/17(A) -               Full Load achieved on 25.12.2016.
                           U-3          12/16                12/03/18(A)
          Orig.Est. cost       : Rs 1516619 lakhs                                      Unit-2:
                               : Rs 1516619 lakhs                                      COD achieved on 31/12/17. Commissioned on 22/03/17.
          Latest.Est. Cost
                                                                                       Boiler: Boiler erection commenced on 20.08.13. Boiler hydro test
                                                                                       done in 08/15. BLU done in 10/16.SBO completion achieved in
           Exp.During 2011-12      : Rs 19200 lakhs                                    01/17.
                       2012-13     : Rs 130400 lakhs                                   TG: Condenser erection started on 14.11.14.TG erection started in
                       2013-14    : Rs 227700 Lakhs.                                   03/15. TG box-up done in 01/16. TG oil flushing done in 11/16
                       2014-15    : Rs 404700 Lakhs.
                       2015-16    : Rs 280000 Lakhs                                    Unit-3:
                       2016-17   : Rs 256000 Lakhs                                     Commissioned on 12/03/18.
                       2017-18   : Rs. 209800 Lakhs (2/18)                             Boiler: Boiler erection started in 09/13. Boiler Hydro test done in
                     Cum Exp       :Rs 1508600 lakhs(up to 2/18)                       03/16. BLU done in 04/17. SBO completed in 06/17. Unit
          Invest. Approval       :Dec’2011.                                            synnchronised on oil on 22.08.17. Full load achieved on 12th
          Sanctioning            : NTPC Board                                          March 18.
          Authority                                                                    TG: Condenser & TG erection started in 09/15. TG box-up done in
                                                                                       01/17.TG oil Flushing done in 01/17.Turbine rolled.
                  Type of fuel    : Coal                                               BOPs:
                    Coal block    Bhalumuda Captive coal block                         Chimney: Chimney-1 (for unit-1) & Chimney-2 (for unit-2&3)
                     Zero Date    25.01.2012                                           Shell casting works completed.
            Date of Main Plant    SG: Feb’12, M/s Doosan Heavy Ind., Korea
                         Order    TG: Feb’12 on M/s Toshiba                            CHP: The progress of CHP is slow. Only structural work of
                                                                                       transfer points, conveyor galleries and crusher house etc. are in
                                                                                       progress. Civil works have been started in WT4 & WT5. Erection
                                                                                       of mechanical equipment are yet to be started. Requirement for U#1
                                                                                       & U#2 services completed and U#3 portion works in progress. M/s.
                                                                                       Energo contract terminated in Oct 17.
               Critical Areas     Land acquisition for Railway siding, ash pipe corridor, raw water reservoir. Poor progress of main plant civil works
                                  Readiness of railway siding.
           Reasons for Delay      Stoppage of work on account of NGT order–work stopped from 17.03.2014 to 01.04.2014. Work stoppage due to
                                  agitation against the project (05.07.2014 to 22.07.2014). Delay in award of SG civil works. Delay in TG erection start.
                                  Unrest and violent agitation in 07/14 with exodus of manpower. Delay in supply of generator stator of Unit #2 &3 by M/s
                                  Toshiba. Supply of material against CHP-Energo, AHP- MBECL, ESP-L&T and FDPS & slow progress.
                                                                             33
Sl. No.                                Capacity               Commissioning Schedule
           PROJECT DETAILS              (MW)                                                                        Broad Status
                                                            Original       Actual(A) / As
                                                                           now Expected
                                                      Syn.         COD       Syn.     COD
                                                      com.                   com
          Central Sector
 8.       Solapur STPP,                  1320                                                Unit-1:
          Dist: Solapur,                                                                     COD achieved on 25/9/17. Commissioned on
          Maharashtra, NTPC Ltd.                                                             07/04/17.
                             U-1         660        03/16         07/16 03/17(A) 25/09/17(A) Boiler: Boiler erection started on 07th May’13.
                                                    05/16               007/04/17(A)         Boiler hydro test done in 12/15. BLU done on
                               U-2       660        09/16         01/17    02/19     03/19   21.08.16. SBO completed in 03/17.
                                                    11/16                  03/19             TG: TG erection started on 04.07.14. TG box-up
               Investment Approval : March’12                                                completed in 07/15. TG oil flushing completed in
                                                                                             11/15.
              Sanctioning Authority : NTPC Board                                             Unit-2:
                    Orig.Est. cost      : Rs939518 lakhs                                     Boiler: Boiler erection started on 29/09/13.Boiler
                   Latest.Est. Cost     : Rs 939518 lakhs                                    hydro test completed in 09/18. BLU done in
               Exp.During 2011-12      : Rs 9500 lakhs                                       11/18.Steam blowing completed in 01/19.
                          2012-13      : Rs 114200 Lakhs                                     TG: TG erection started on 15th May’15. TG
                          2013-14      : Rs 98300 Lakhs                                      Boxed-up in 08/16.TG oil flushing completed in
                          2014-15      : Rs 212800 Lakhs                                     05/17. TG on barring gear since 05/17.
                          2015-16      : Rs 166800 Lakhs
                          2016-17      : Rs 132600 Lakhs                                          BOPs:
                          2017-18     : Rs. 92500Lakhs                                            Chimney: Chimney shell casting completed. Flue
                          2018-19     : Rs. 40991 Lakhs ( 12/18)                                  can have erected for both the units.
                        Cum Exp         :Rs 902643 Lakhs (upto 12/18)                             CHP: Priority area completed. Balance works in
                      Type of fuel    : Coal                                                      progress.
                                                                                                  AHP:Ash dyke Priority area completed. Balance
           Date of Main Plant Order    SG : 06.04.12 on M/s BGR Energy Systems Ltd –
                                                                                                  work in progress. U-2 erection work i/p.
                             (BTG)     Hitachi
                                                                                                  PT Plant: Order placed on Ion Exchange in
                                       TG : 23.04.12 on M/s Alstom-Bharat Forge
                                                                                                  Apr’12. Priority area completed.
                                                                                                  DM Plant: Order placed on Ion Exchange in
                          Zero date    19.03.2012
                                                                                                  Mar’12. Work completed.
                                                                                                  CW System: Work completed.
                                                                                                  IDCTs: Each unit is provided with 2 IDCTs.
                                                                                                  Unit#1: Completed.Unit#2: Civil works under
                                                                                                  progress in both the IDCTs. Partly completed.
                                                                                                  Switchyard: 400& 132kV line charged.
                                                                                                  FGD: FGD is awarded to GE on 31.07.18.
                                                                                                  Geotech investigaton is completed. Civil drag
                                                                                                  submission i/p.
                     Critical Areas    Delay in Laying of Make Up Water Pipe line due to No Right of Use Act in Maharashtra. Delay in SG supplies
                                       by BGR-Hitachi and resource augmentation. Resources augmentation by M/s Indure, for CHP & AHP
                                       packages. Major damage in Pressure parts and support structure (9nos hdrs, buckstays, springs, etc) and delay
                                       in rectification and replacement by BGR. Rectification work started in May -17 but work progress is very slow.
                                       Expediting Supply of U#2 Boiler components & BOIs by BGR Energy- Systems Ltd. & Hitachi Power Europe,
                                       Supply of Structures & BOIs/SMIs by M/s. Indure for AHP and CHP Packages. Supply of FDA and inert gas
                                       nozzles & detectors by M/s Sureland for FDPS Package. Due to resistance from farmers, seeking higher
                                       compensation than as recommended by state revenue/agriculture deptt., the Completion of MUWPH 132 KV
                                       line is getting delayed.
                 Reasons for Delay     Delay in steam generator Engineering & supply by BGR due to non-settlement of QSGM between BGR and
                                       Hitachi.Delay in repair & replacement of damaged pressure parts due to accident.
                                                                             34
Sl. No.                              Capacity              Commissioning Schedule
           PROJECT DETAILS            (MW)                                                                         Broad Status
                                                     Original         Actual(A) / As
                                                                      now Expected
                                                  Syn.        COD       Syn.     COD
                                                  com.                  com
          Central Sector
 9.       Gadarwara STPP, St–I,         1600                                                Unit-1:
          Dist: Narsinghpur                                                                 Full load is achieved on 13.10.18. Synchronisation is
          M.P NTPC Ltd.tanda                                                                achieved on 30.08.18
                            U-1         800      12/16       07/17   30/08/18(A) 03/19      Boiler: Boiler erection started in 06/14. HT done in 12/16.
                                                 03/17               13/10/18(A)            BLU achieved in 04/17. SBO completed in July‘17.
                              U-2       800      06/17       01/18    05/19      09/19      ESP: All six pass erection completed and emitter’s erection
                                                 09/17                06/19                 is in progress. Hopper erection completed.
              Investment Approval : 22.02.2013                                              TG: Condenser erection started in 12/15. TG erection
                                                                                            started in 04/16. TG box-up completed in 08/17.TG oil
             Sanctioning Authority : NTPC Board                                             flushing completed in 09/17.
                   Orig.Est. cost    : Rs 1163855 lakhs
                                     : Rs 1163855 lakhs.                                    Unit-2:
                  Latest.Est. Cost
                                                                                            Boiler: Boiler erection started in 30th Nov’14. Pressure part
              Exp.During 2012-13     : Rs 65500 Lakhs
                                                                                            erection in progress. HT completed in 11/17. BLU
                         2013-14     : Rs 46300 Lakhs
                                                                                            completed on 31.12.18
                         2014-15     : Rs 161400 Lakhs
                                                                                            ESP: Pass A, B & C erection completed and foundation
                         2015-16     : Rs 274900 Lakhs
                                                                                            work of D, E & F passes completed.
                         2016-17     : Rs 198800 Lakhs
                                                                                            TG: TG erection started in 06/17. TG Box-up completed in
                         2017-18     : Rs 155600 Lakhs
                                                                                            11/18.
                         2018-19     : Rs 131450 Lakhs (12/18)
               Cumulative Exp         : Rs 1037532 Lakhs( upto 12 /18)                      BOPs:
                      Type of fuel : Coal
                                                                                            Chimney: Unit-1 work done. U-2 Mini shell work in
                      Fuel linkage
                                                                                            progress. Unit-2 flue can erection done.
          Date of Main Plant Order    in 03/2013 M/s BHEL, Main plant & offsite             CHP:.Both stream from WT-3 upto U1 tipper floor
                            (BTG)     civil works order placed in 08/13.                    comm.One stacker reclaimer comm.
                        Zero Date     22.03.13                                              AHP: Silos piling work completed. HCSD pump
                                                                                            foundation completed. U-1 Bottom ash evacuation with
                                                                                            2nos ash slurry series completed uoto ash yke. Flyash
                                                                                            evacuation for all passes completed upto HCSD silo
                                                                                            PT Plant: All three CW streams commissioned.
                                                                                            DM Plant: Both stream of DM water commissioned.
                    Critical Areas    Slow progress of Civil Agencyh (B&R) has delay release of fronts to Main Plant SG & TG erection, BoP Packages
                                      and completion of Site priority infrastructures, i.e. road & drain, Boundary wall etc. State Government’s help is
                                      solicited in acquisition of balance Land for Railway line corridor and obtaining RoU for Make-up Water Pipe
                                      laying. Allocation of dedicated Coal block & supply of coal, Chandrabila coal block (Odisha) linked to Gadarwara
                                      Project was deallocated and new coal block allocation/coal linkage yet to be firmed by MoC.
                Reasons for Delay     Work stopped for 56 daysin 2014 due to agitation by villagers demanding additional compensation for already
                                      acquired land.
                                      Land acquisition for railway line corridor, RoU for MuW pipeline laying.,
                                                                            35
Sl. No.                            Capacity          Commissioning Schedule
          PROJECT DETAILS           (MW)                                                                  Broad Status
                                                   Original         Actual(A) / As
                                                                    now Expected
                                                Syn.       COD       Syn.    COD
                                               (com.)               (com)
          Central Sector
 10.      Khargone STPP,             1320                                               Unit-1:
          Dist.Khargone, M.P.                                                           Boiler: Boiler erection started in 04/16. Boiler
          (NTPC Ltd.)                                                                   Hydro test done on 24.6.18.BLU completed on
                         Unit-1      660        01/19     07/19      03/19    07/19     29.12.18
                                                03/19                03/19              TG: TG erection started in 06/17. TG Box-up
                          Unit-2       660      07/19     01/20      07/19    11/19     done on 29.05.18. TG oil flushing comleted on
                                                09/19                09/19              27.01.19.
             Original/Latest Cost : Rs 987051/987051 lakhs
                                                                                        Unit-2:
           Exp. During 2014-15     : Rs. 63400 lakhs                                    Boiler: Boiler erection to started in 09/16.Pressure
                       2015-16     : Rs. 90200 lakhs                                    part erection in progress. Boiler Hydro test
                       2016-17     : Rs. 112400 lakhs                                   completed on 30/ 09/18.
                       2017-18     : Rs. 243900 Lakhs
                       2018-19     : Rs 161107 Lakhs (12/18)                            TG: TG erection started in 12/17. TG Box-up
           Cumulative Exp          : Rs 669390 lakhs(up to 12/18)                       done on27.11.18.
                                                                                        ESP: pass E air leak test successfully completed
                    Type of fuel : Coal                                                 on 16.08.18. pass F air leak test successfully
                       Zero date 31.03.2015                                             completed on 12.09.18.
          Date of Main Plant Order EPC On L&T on 31.03.2015
BOPs:
                  Critical Areas   Broad gauge work from Khandwa to Nimarkheri (Take off point for Railway siding) by Western railways.
                                   Disbursement of compensation amount to balance beneficiaries of RoW who are not accepting the
                                   compensation amount, for laying of 66KV transmission line from plant to make up water pump house
                                   location.
              Reasons for Delay    ---
                                                                      36
Sl.                               Capacity         Commissioning Schedule
No.    PROJECT DETAILS             (MW)                                                                         Broad Status
                                                  Original         Actual(A) / As
                                                                   now Expected
                                               Syn.       COD       Syn.    COD
                                              (com.)               (com)
      Central Sector
11.   Darlipalli STPP ST-I,         1600                                                  Unit-1:
      Dist.       Sundergarh,                                                             Boiler: Boiler erection started in 04/15. HT completed in
      Odisha (NTPC Ltd.)                                                                  8/17. BLU completed in 11/18. Steam blowing comleted in
                          U-1       800       12/17       04/18      03/19        05/19   02/19.
                                              02/18                  05/19
                          U-2       800       04/18       08/18      10/19        11/19   TG: Condenser erection started in 12/15. TG erection
                                              06/18                  11/19                started in 05/16.TG box-up done in 11/17.TG oil flushing
          Investment. approval                                                            done in 11/18.
                 Orig.Est. cost : Rs 1253244 lakhs                                        ESP: All passes completed.
              Latest. Est. Cost : Rs 1253244 lakhs.                                       Unit-2:
                                                                                          Boiler: Boiler erection started in 07/15. HT done in 03/18.
          Exp. During 2013-14     :Rs.95100 lakhs
                      2014-15     :Rs145700 lakhs                                         TG: Condenser erection started in 09/16. TG erection
                      2015-16     :Rs141700 lakhs                                         started in 03/17. TG Box-up expected in 02/19.
                      2016-17     :Rs 238400 lakhs                                        ESP: 5 passes are completed. Internal erection is in
                      2017-18     :Rs 210000 lakhs                                        progress
                      2018-19     :Rs 93774 lakhs (12/18)
              Cumulative Exp       :Rs. 844141 lakhs (up to 12/18)                        BOPs:
              MOEF clearance
                   Type of fuel    : Coal                                                 Chimney: raft completed.
      Date of Main Plant Order      SG. awarded in 02/14 on M/s BHEL.
                                    TG awarded in 02/14 on M/s Toshiba                    CHP: Order placed on Tata projects in Feb’15. Civil work
                                                                                          in Track hopper, Wagon tippler ,erection work in TPs,
                                                                                          Crusher house stacker reclaimer in progress
               Critical Areas      RoU for maker up water line & 132 KV transmission line corridor, balance land registration (132.45 Acres out
                                   of 2002.46 Acres) for Railway siding & outfall drain.
            Reasons for Delay      ---
                                                                             37
Sl. No.                             Capacity              Commissioning Schedule
           PROJECT DETAILS           (MW)                                                                     Broad Status
                                                      Original         Actual(A) / As now
                                                                       Expected
                                                   Syn.       COD       Syn.       COD
                                                   com.                 com
          Central Sector
  12.     Telangana TPP (Ph-I),       1600                                                    Unit-1:
          Dist. Karim Nagar
          Telangana NTPC Ltd.                                                                 Boiler: Boiler erection started in 12/17.8th Tier
                          Unit-1      800           10/19     05/20   03/20         08/20     erection in progress.
                                                    01/20             04/20
                            Unit-2       800        05/20     11/20   09/20         01/21     TG: Condenser erection started in 07/18. TG
                                                    07/20             10/20                   erection started in 08/18.
                     Orig.Est. cost : Rs 1059900 lakhs                                        ESP: erection in 6 passes in progress.
                   Latest.Est. Cost : Rs 1059900 lakhs
                                                                                              Unit-2:
          Exp. During     2015-16 : Rs. 600 lakhs
                                                                                              Boiler: Boiler erection started in 12/17.4th
                          2016-17 : Rs 80700 lakhs
                                                                                              Tier erection in progress
                          2017-18 : Rs. 103500 lakhs
                          2018-19 : Rs. 140515 lakhs      (12/18)
                                                                                              TG: Condenser erection start expected in
                 Cumulative Exp : Rs. 327235 lakhs(up to 12/18)                               02/19. TG erection start expected in 03/19
                      Type of fuel Coal                                                       ESP: erection in 6 passes in progress.
               Date of Main Plant: SG on BHEL
                            Order: TG on Alstom-Bharatforge on 05.02.16.
                         Zero date     31.03.2015                                             BOPs:
                MOEF clearance                                                                CHP: TPs and Coveyor foundation in
                                                                                              progress
                                                                                              Chimney: shell completed upto 45 mtr.
                   Critical Areas   During last CRM held with BHEL on 28/9/17, BHEL confirmed primary structure dispatch commences
                                    only from Dec 17.
Reasons for Delay Change in boiler design w.r.t. new environmental norms, Delay in BHEL supplies.
                                                                         38
Sl.                                 Capacity             Commissioning Schedule
No.    PROJECT DETAILS               (MW)                                                                         Broad Status
                                                     Original        Actual(A) / As now
                                                                     Expected
                                                  Syn.      COD        Syn.       COD
                                                  com.                 com
      Central Sector
13.   Meja STPP,                       1320                                                 Unit-1:
      Dist:Allahabad,                                                                       Commissione on 31/03/18. Synchronised on 23/08/17.
      U.P.[MUNPL- Meja Urja                                                                 Boiler: Boiler erection started on 11th Jun’13. Boiler
      Nigam Pvt. Ltd. (JV of                                                                hydro test done on 27.05.16. BLU achieved in 03/17.
      NTPC & UPRVUNL)]                                                                      SBO completed in 07/17.
                         U-1           660       04/16     08/16    23/08/17(A)     -       TG: TG erection started in 09/14. TG box-up done in
                                                 06/16              31/3/18(A)              09/15. TG oil flushing completion done in 11/16.
                                                                                            Unit-2:
                            U-2        660   10/16    02/17            06/19      08/19     Boiler: Boiler erection started on 20.06.14 (Delay 06
                                             12/16                     08/19                months). All mill and bunker foundations completed.
          Original/Latest Cost : Rs 1082100 /1082100 lakhs                                  TG: TG Deck casting completed. Condenser erection
                                                                                            started in 11/15. TG erection started on 30/01/18.
           Exp.During 2008-09      :Rs 5401 lakhs
                                                                                            ESP: U #1-All Pass ATT & purge system piping done.
                      2009-10      :Rs 4151 lakhs
                                                                                            Insulation & cladding works for A,B & C pass completed.
                      2010-11      :Rs 6143 lakhs
                                                                                            62/96 rectifier transformer filtration done. A,B pass field
                      2011-12      :Rs 6542 lakhs
                                                                                            test charged. U#2- Erection commenced on 19.02.15
                      2012-13      :Rs 86287 lakhs
                      2013-14      :Rs 56590 lakhs
                      2014-15      :Rs 162420 lakhs
                      2015-16      :Rs 180386 lakhs                                         BOPs:
                      2016-17      :Rs 71583 lakhs                                          Chimney: Chimney shell concreting completed. Flue can
                      2017-18      :Rs 200597 lakhs                                         erection & Mini cell done completed, Outer platform
                      2018-19       Rs 555.15 lakhs                                         RCC done. Painting works done. Wind stack fixing -6/39
                                                                                            done, Lift erected.
              Cumulative Exp.       :Rs 846400 lakhs (Up to 8/18)
                                                                                            CHP: Order placed on BHEL-ISG in Apr’12. Structure
                  Type of fuel     : Coal
                                                                                            erection of TP-1,2,3,4,5,11 &12 completed and
                       Zero Date    30.04.2012                                              CRUSHER house in progress. WT-B: Flushing
                                                                                            completed of WT-2
          Sanctioning Authority : NTPC Board                                                WT-A: Oil flushing -Piping work i/p.
                                                                                            AHP: Order placed on Techpro in 07/12. Ash Water P/H.
       Date of Main Plant Order     SG: 30.04.12 on M/s BGR Energy Systems, Chennai.        Pumps foundations completed. Ash Slurry P/H- -RCC &
                         (BTG)      TG: 01.05.12 on M/s Toshiba Corporation, Japan.         Bricks works completed. Pumps foundations completed.
                                                                                            Pump erection started. Ash disposal pipe laying in side
      MOE&F clearance available on 10.01.11. Environment Clearance for Project              plant- -Pipe Laying started in May’16 inside plant. 25 Km
      extended up to 31.03.2019 by MOEF on 30.08.2018                                       pipe supplied. Inside pipe laying done
                                                                                            CWPs: Order placed on Flowmore in 12/14. Gantry
                                                                                            commissioned. Two nos pump commissioned. 3rd
                                                                                            Erection in progress.
                                                                                            IDCTs: Order placed on Fans A S in May’12. Aux CT-
                                                                                            2/3 Fans commissioned. Balance One fan ready for
                                                                                            commissioning. CT 1A: All 16 fans commissioned. CT
                                                                                            1B: 6/16 nos fan commissioned, Balance cabling works in
                                                                                            progress. Civil works completed, fill erection done, motor
                                                                                            & gear box placed on fdns. Painting & drift eliminators
                                                                                            works compld. CT 2B: Civil works completed, Hot water
                                                                                            pipe risers erection in progress. CT 2A: Civil works- All
                                                                                            fan deck slab done & 14/16 fan stack rcc completed.
                                                                                            Railway siding: Order placed on M/s RITES. This work is
                                                                                            split in to 07 no of packages and all packages are
                                                                                            awarded. Further, works are in progress.
                                                                                            Switchyard: Completed. Start up Power charged by
                                                                                            Allahabad line-1 on 12.11.16
                                    Balance land for railway siding-Village Lehdi 22.12 acres for laying 1.8 km track & Other 0.75 KM in assorted
                 Critical Areas     patches in different villages. Various Clearances from Indian Railway and DFCIL to be taken by Rites at the
                                    earliest: ·Clearance from Railways for Connection of Meja Siding with IR Tracks at Meja and Unchdih. Approval of
                                    Girder Launching Scheme for ROR & Block for launching from Railways. Approval of General Arrangement
                                    Drawing (GAD) of Rail Over Rail Bridge (ROR) and ViaDuct from Railways. ·Approval of Girder Launching
                                    Scheme for ROR & Block for launching from Railways. Shifting of UPTCL and Power Grid Transmission lines 4
                                    nos each 132/400 KV.
             Reasons for Delay      Delay in supply of boiler material by M/s BGR due to non-settlement of QSGM between BGR and Hitachi. Slow
                                    progress of main plant civil works.
                                                                        39
Sl. No.                              Capaci          Commissioning Schedule
           PROJECT DETAILS             ty                                                                    Broad Status
                                                 Original        Actual(A) / As
                                     (MW)
                                                                 now Expected
                                              Syn.      COD        Syn.     COD
                                              com.                 com
          Central Sector
  14      Tanda-II STPP,             1320                                               Unit-5:
          Dist. Ambedkar Nagar,                                                         Boiler: Boiler erection started in 12/15. Hydro test done
          U.P. NTPC Ltd.                                                                on 20/04/18.BLU completed on 31.12.18
                            U-5       660    07/18    01/19    03/19      07/19
                                             09/18             03/19                    TG: Condenser erection started in 03/17. TG erection
                              U-6    660     01/19    07/19    09/19      11/19         started in 07/17. TG Boxed up in 03/18.TG Oil flushing
                                             03/19             09/19                    is completed in 09/18.
               Original/Latest Cost : Rs 918898 /918898 lakhs.                          ESP: ESP is having 6 Passes; work is in progress for all
             Exp. During 2013-14 : Rs 28000 lakhs                                       passes
                          2014-15 : Rs.29800 lakhs
                          2015-16 : Rs 64900 lakhs                                      Unit-6
                          2016-17 : Rs 141300 lakhs                                     Boiler: Boiler erection started in 10/16. Hydro test
                          2017-18 : Rs 167112 Lakhs                                     completed on 18/01/19.
                          2018-19 : Rs 102543 Lakhs (12/18)
                 Cumulative Exp : Rs 543365 lakhs (up to 12/18)                         TG: TG erection started in 12/18.Condenser erection
                                                                                        started in 10/18.
                     Type of fuel : Coal
                                                                                        ESP: ESP is having 6 Passes; work is in progress for all
             Investment. approval Sep 2014
                                                                                        passes
           Date of Main Plant Order Boiler: L&T, TG: Alstom in Sep’14. MP civil
                                     works awarded to M/s GDCL in Feb’15.
                                                                                        BOPs:
                    Critical Areas   Tapering coal linkage, physical possession of balance abadi land in main plant & Ash dyke area.
                Reasons for Delay    Poor mobilization by civil agency, Delay in Engg. & Supply.
                                                                          40
Sl.                                Capacity              Commissioning Schedule
No.    PROJECT DETAILS              (MW)                                                                          Broad Status
                                                    Original         Actual(A) / As now
                                                                     Expected
                                                 Syn.       COD       Syn.       COD
                                                 com.                 com
      Central Sector
15.   PatratuTPS,                    2400                                                   Unit-1:
      Imp.Agency-PVUNL                                                                      Boiler: Work yet ot be Start.
      Dist: Jharkhand. (JV of                                                               TG:
      NTPC & Govt. of                                                                       Unit-2:
      Jharkhand)]                                                                           Boiler: Work yet ot be Start.
                          U-1         800        11/21      03/22        -     -            TG:.
                                                 01/22
                                   Shifting of Transmission line from Project Area, Acquisition of Balance land of 35Acre for ash dyke-2 and lease of
                 Critical Areas    14.09acres of land
                                   Early accordance of permanent township environment clearance y SEIAA
                                   GR from JUSNL
             Reasons for Delay
                                                                         41
Sl. No.                              Capacity           Commissioning Schedule
           PROJECT DETAILS            (MW)                                                                        Broad Status
                                                     Original        Actual(A) / As
                                                                     now Expected
                                                  Syn.      COD       Syn.    COD
                                                  com.                com
          Central Sector
 9.       Rourkela PP-II                250                                                 Unit-1:
          Expension,Odisha                                                                  Boiler: Boiler erection started on 30.03.17. Boiler drum
                                                                                            lifted on 04.11.17. Hydro Test (drainable) done on
                              U-1       250        -        12/18        -          11/19   08.09.18.
                                                 09/18                 09/19                ESP: 2352/4000MT erection done. Pass A Hopper erection
              Investment Approval : 14.09.15                                                u/p.Pass B shock bar hawk bolting completed. Pass C
                     Orig.Est. cost : Rs 188513 lakhs                                       suspension hangers for electrodes erection inprogress. Pass
                                    : Rs 188513 lakhs                                       D erection is u/p.
                  Latest.Est. Cost                                                          TG: TG civil work started on 02.03.17. Condenser erection
                      Exp.During     :                                                      started on 28.12.17. TG erection started on 27.11. 18.
                         2016-17     : Rs 23751 Lakhs
                         2017-18     : Rs 51581 Lakhs                                       BOPs:
                         2018-19     : Rs 32806 Lakhs (01/19)
                Cumulative Exp        : Rs 108138 Lakhs( upto 01/19)                        Chimney: shell casting completed on 30.03.18. Beam
                      Type of fuel : Coal                                                   erection Is u/p.
                                                                                            CHP: ERH-1 lift wall cast done and penthouse roof slab
                      Fuel linkage Applied on 14.05.18 under Shakti Scheme                  casted. Final lift wall cast hopper beam shuttering in
          Date of Main Plant Order    BTG and EPC contracted to M/s                         progress.ERH-2 wall along with hopper casting completed.
                            (BTG)     BHELincluding offsite civil works, order              and penthouse roof slab casted. Crusher house erection is
                                      placed on 11.05.16                                    u/p.
                                                                                            AHP: AHP control room, compressor house cum AWPH
                                                                                            roof slab cast on 29.12.18
                                                                                            PT Plant: Prepatory work for starting civil work being
                                                                                            done. Clarified water storage tank raft cst done.
                                                                                            DM Plant: Main Foundation completed, erection of DM
                                                                                            tank to start shortly.
                                                                                            CWPs: CWPH feed pool wall final lift, Intermediate drop
                                                                                            wall& tie beam cast.
                                                                               42
                                                                        Commissioning Schedule
 Sl. No.              Project Details            Capacity                                                                      Broad Status
                                                  (MW)             Original          Actual(A)/ As
                                                                                         Expected
                                                                Syn.          COD       Syn.     COD
                                                               Comm                    Comm
Central Sector
1         Neyveli New TPP                          1000                                                     Boiler (M/s BHEL) U-1 Erection commenced on
           M/s Neyveli Lignite                                                                                07/03/16. HT done in 08/18. ESP, Duct and ID
           Corporation Ltd. at Neyveli                                                                        fans erection work in progress.
           in Tamil Nadu                                                                                    TG & Condenser: TG erection started on
                                          U-1       500         07/17        10/17      02/19      03/19      24/03/16 & Condenser pre assembly started on
                                                                09/17                   03/19                 22/02/16. Generator stator received at site on
                                                                                                              25/06/16. BFP (MD) erection completed. Turbine
                                          U-2       500        01/18      04/18         03/19      04/19      box-up completed on 31.03.17. Synchronisation
                                                               03/18                    04/19                 on Oil is expected in 03/19.
                                                                                                            Boiler U-2 Erection commenced on 28/03/16. HT
                        Original Estd. Cost     : Rs. 590711 Lakh
                                                                                                              done in 11/18 ESP, Duct and ID fans erection
                            Latest Est. Cost    : Rs. 708041 Lakh                                             work in progress.
                Expenditure during 2011-12      : Rs. 1447.15 Lakh                                          TG & Condenser: TG erection started on
                                   2012-13      : Rs. 1353.19 Lakh                                            24.03.16. TG Box-up completed on 30.06.17
                                   2013-14      : Rs. 31114.26 Lakh                                        BOPs
                                   2014-15      : Rs. 44560.23 Lakh
                                                                                                            Chimney: Shell concreting up to 269.5 mtrs
                                   2015-16      : Rs. 102862.06 Lakh
                                                                                                              completed. Flue can erection work completed for
                                   2016-17      : Rs. 193335.14 Lakh
                                                                                                              U-I and II. Borosilicate lining liner works are in
                                   2017-18      : Rs. 109936.54 Lakh
                                                                                                              Progress. External painting completed.
                                   2018-19      : Rs. 61521.96 Lakh ( 2/19)]
                                                                                                            LHP: Stream-B Commissionint checks and Trial
                       Total Expenditure        : Rs. 546130.53 Lakh (up to 2/19)
                                                                                                              run is in progress. Stream-A conveyor system
                           Approval date:                                                                     Erection & Equipment alignment work pro8ress in
                                Zero date:      : 09/06/11                                                    BCN 9A,10A,11A,108,12A, SFD 3A, RFSD 381,
                            Financial closure                                                                 RFSD 3A2/382, JNT-01,02,03,04 & Crusher
                           Main Plant Order     : Main Plant Order (EPC) issued to M/s BHEL on for            House. Hydraulic test and chemicalcleaning ofoil
                                                SG & Auxiliaries on 31/10/13 and TG & Auxiliaries on          lines of hydraulic power packs are in progress.
                                                23/12/13.                                                   AHP: All the equipments in AHS is
                               BOP Package      : Awarded to M/s EPIL on 30/04/2014.                          commissioned. Except ISH-1E mobile belt
                                                                                                              conveyor erection.
                                Type of fuel    : Lignite from NLC mine 1 & 1A
                                                                                                            RO/DM plant: Awarded to M/s EPIL on
                                       PPA      :PPA signed for 25 years with AP- 52.46 MW,                   30/04/14. Initial operation completed and plant in
                                                Telangana – 61.31 MW, Karnataka 70.54 MW, Kerala              service.
                                                32.38 MW, Tamil Nadu 653.07 MW, Puducherry 4.24             CW System: Awarded to M/s EPIL on 30/04/14
                                                MW, NLC – 66.00MW and Un allocated power –                    and further to M/s KBL on 20/01/15. All4 pumps
                                                60.00MW.                                                      lnitial Operation completed and Pump in service.
                    Power Evacuation system     For power evacuation and drawing of start-up                Cooling Tower: Mechanical erection completed
                                                power,400kVand 220kV switchyard would be                      and commissioned.Paving and drain works are in
                                                provided. Each of the 500 MW units would be                   progress.
                                                connected to the 400kV switchyard. The power                FO System: Awarded to M/s BHEL on 31/10/13,
                                                generated at the plant would be evacuated through a           civil work completed. Erecting HFO tank 1 & 2
                                                400kV system. Start-up power would be drawn from              are nearing completion and LDO tank 1 & 2
                                                the 220kV switchyard.                                         erection completed. Supply & erection of LDO &
                                                The generator transformers of 500MW units would step          HFO pumps completed.
                                                up generator voltages to the switchyard voltage of          Switchyard: Awarded to M/s EPIL on 30/04/14.
                                                400Kv.One and Half Breaker scheme is proposed for             Civil works are in progress both in 200 Kv GIS
                                                400kV and 220kV switchyard. These schemes are                 and 400 Kv GIS halls. 220 kV outdoor yard
                                                reliable and provide flexibility in operation.                equipment structural erection work completed.230
                                                                                                              kV LILO work is in progress by TANTRANSCO.
            Coal Linkage/FSA: Lignite from the NLC Mine 1 & 1A.
            Land possession: 160 Hectares Owned by NLC                                                      FGD : First cover open on 26.02.2019. QR short
            Water allocation: Existing TS 1 lake and erstwhile Fertilizer lake of NLC Ltd.,                  listing under progress.
            MOE&F: Clearances obtained on 21/10/2010 and extended up to 20/10/2017, clearance
             further extended upto 20.10.19.
            CPCB: Clearances obtained and valid up to 31/03/2018.
            Civil Aviation: clearance obtained on 25/11/09
Critical issues
Reasons for Delay               Delayed due to change in design of foundations(depth) of main plant area and finalisation of civil contractors. Initial delay in
                                supply of Boiler Material and inadequate resource mobilization and new technology(Boiler) being used first time in India
                                                                                43
Sl. No. PROJECT DETAILS                  Capacity            Commissioning Schedule
                                          (MW)             Original      Actual (A) / As                                  Broad Status
                                                                         now Anticipated.
                                                        Syn.      COD      Syn.      COD
                                                       Comm               Comm
 2     Ghatampur TPP                       1980                                                    Unit-I:
       JV of NLC & UPRVUNL                                                                         Boiler: Boiler & Auxiliaries- Civil & structural work
       (Lahurimau village,                                                                         1. Unit -1: 15265 MT erection completed. Coal Silo hopper
       Ghatampur, Kanpur), U.P.                                                                    fabrication & welding work under progress. SS liner fit-up
                            U-1             660         03/20      11/20           08/20   11/20   & plug welding completed in Part-I of Bunker Hopper A,
                                                        04\20                      9/20            B,C,D,E,F,G & H.
                                                                                                   2. Boiler #1 – Roof Structure erection under progress &
                                  U-2       660          09/20    05/21        02/21       05/21   06/13 nos Silencer erection completed..
                                                         10/20                 03/21               3.ESP-1 Structural erection in progress. 1265 MT erection
                               U-3           660       03/21      11/21        08/21       12/21   completed.
                                                       04/21                   09/21               4. ESP # 1 Control building Lintel beam completed. First
        Original/Latest Est. Cost        : Rs.1723780 lakhs                                        floor slab completed.
                 Exp. During 2012-13     :Rs.13838 Lakhs                                           5. Air duct, backend duct & flue gas duct fabrication work
                               2013-14   :Rs.580 Lakhs                                             under progress.
                               2014-15   :Rs.3978.08 Lakhs                                         6. 21921 nos. Pressure parts joints welding works
                               2015-16   :Rs.(-)528.76 Lakhs                                       completed.
                               2016-17   :Rs.73580.84 Lakhs                                        7. Unit-2: Boiler erection is in progress 7928 MT erected.
                               2017-18   :Rs. 90950.32 Lakhs                                          316 nos Pressure Parts joints welding works completed.
                                                                                                   8. ESP-2 Structure erection works in progress. 304 MT
               Cumulative Exp            : Rs. 425666.94 Lakhs(up to 02/19)                           erected.
       Type of fuel                      : Coal                                                    9. Unit-3: Boiler- Mechanical Erection under progress.
       Date of Financial Closure         : Declared on 31.12.2017                                     3135 MT erection completed.
       Date of clearance by the board    : 15.10.2016                                              TG& Auxiliaries Civil & Structural Work
       of NUPPL                                                                                     1. Unit#1,2 &3 TG: All rafts completed. TG Deck#1
       Date of Main Plant Order/BoPs  : Order for Gen. Auxiliaries (1) placed on MHPS Boilers       Casting completed. TG # 2 -3rd lift pedestal under
                                      Pvt. Ltd. on 02.08.16                                         progress.
                                      Order for Gen. Auxiliaries (2) placed on M/s. Alstom          2. Unit#1: Main Power House structural erection in
                                      Bharat Forge Power Ltd. on 02.08.16                           progress. 3986 MT erected.
       Zero date                      : 02.08.2016                                                  3. Unit#2 Main Power House Structure erection work
       PPA                              : Signed with UP Govt. on 31.12..2010                       under progress. 482 MT erected.
                                                                                                    4. CW Pipe Erection 1192/2308 metere Completed
        Fuel Linkage                  : Govt. of India allocated Pachwara South Coal Block,
                                                                                                    5. TG Auxiliary columns erection works under progress.
                                      Jharkhand to NUPPL for fuel. But due to Law & Order
                                                                                                    6. 665 MT CCR building structural erection completed.
                                      problem, MoU signed with MSTC for imported Coal on
                                                                                                    Service building Civil works under progress.
                                      04.02.2015.
                                                                                                    7.Transformer Yard #1 –ST, GT & UT foundation
      Power Evacuation System         CEA in its 36th Standing Committee meeting held on
                                                                                                    completed. and fire wall works under progress.
                                      13.07.2015 at New Delhi, has agreed for power evatuation
                                                                                                    8. Transformer Yard #2 –GT RYB raft completed and wall
                                      system of Ghatampur Thremal Power Station proposed by
                                                                                                    works under progress.
                                      UPPTCL
                                                                                                    9. Unit#1 Station transformer & 03 nos Generator
       MoEF: MoEF issued Environmental clearance to NUPPL on 17.06.2015                             Transformer erected.
       Land: Entire Land of 828 Hectares has been acquired and taken physical possession on
                                                                                                    7. TG Hall 1 no. 200 MT EOT Crane (capacity-200 MT)
       27.11.2016
                                                                                                    commissioned . 2nd no. EOT crane erection completed &
                                                                                                    Commissioning work in progress.
                                                                                                   BOP (GA3 Package)
                                                                                                   Chimney:
                                                                                                    26.8 m out of 275m height completed.
                                                                                                   Coal handling Plant:
                                                                                                   Wagon Tippler, Track Hopper, Crusher House, Stacker
                                                                                                   reclaimer, JT 1 to 12 & Emergency Reclaimer works are in
                                                                                                   progress.
                                                                                                   Ash handling Plant:
                                                                                                   Ash Silo and Ash dyke civil works are in progress.
                                                                                                   CW System:
                                                                                                   CW Pump House (CWPH) and CW channel RCC works in
                                                                                                   progress.
                                                                                                   Switchyard:
                                                                                                   -132 KV GIS Building: Finishing work in progress.
                                                                                                   - 132 KV Switchyard take off & Bus tower raft & Pedestal
                                                                                                   completed. Other outdoor equipment foundation work in
                                                                                                   progress.
                                                                                                   - 400 KV GIS Building – 1st Lintel beam completed and
                                                                                                   cable trench work under progress and Take off tower -3/3
                                                                                                   nos. raft completed and 2nd lift of pedesatal is in progress.
                                                                                                   - 765 KV GIS Building –works up to up to plinth level
                                                                                                   completed. Backfilling works under progress. Tie beam
                                                                                                   work in progress.
                                                                                                   - ICT & Reactor Foundation rafts completed and 11 nos.
                                                                                                   pedestal/column up to plinth level completed. Fire wall
                                                                                                   works under progress. Backfilling works under progress.
                                                                                                   Cooling Towers: NDCT # 1,2,3 Civil works are under
                                                                                                   progress
                                                                                                   FGD: (GA4 Package)
                                                                                                   Tendering under progress.
 Critical issues
 Reasons for Delay
                                                                              44
                                                                 Commissioning Schedule
      Power evacuation         Through two No. S/C 220 kV transmission lines viz (i) BTPSE- Gajner
      system                   (ii) BTPSE-Bikaner, to be executed by RVPNL
      Water: Water supply agreement signed on 08/10/03 b/w Indira Gandhi Nahar Pariyojna, GoR
      and NLC
      Land: Land is in procession of NLC and the proposed plant is being constructed with in the
      existing 2x125MW Barsingsar TPP
      MOE&F clearance: EC for mines granted on 21/10/13. EC for thermal granted on 30/07/12
      Civil Aviation: NOC obtained on 23/01/2012
Critical Issues
      Reasons for delay        GoR had informed that due to increased project cost and time over run, Rajasthan Discom will not be in position to buy the
                              power from BTPSE. NLCIL had replied that delay is due to acquisition of land for linked mine by GoR and informed to review
                              the decision. Matter is pending with GoR. Project activities are under hold from 02/06/2017.
                                                                             45
                                                 Commissioning Schedule
      Power evacuation        Through three No. S/C transmission lines viz (i)
      system                  BLTPS-
                              Kolayat (ii) BLTPS-Nokha(iii)BLTPS-Bikaner to
                              be executed by RRVPNL.
      Water: Water supply agreement signed on 10/06/14 b/w Indira Gandhi
      Nahar Pariyojna, GoR and NLC
      Land: Private land-1088.20 ha in possession.
      Govt Land-Transfer in favour of NLC India is under progress at O/o
      Commissioner colonization, Bikaner
      Forest land- Transfer in favour of forest dept is under progress at O/o
      Commissioner colonization, Bikaner
      MOE&F clearance:EC for mines granted on 26/02/16. EC for thermal
      granted on 30/04/10 and validity extension is under progress.
      Civil Aviation: NOC obtained on 09/08/16
Critical Issues
Reasons for delay              GoR had informed that due to increased project cost and time over run, Rajasthan Discom will not
                              be in position to buy the power from BTPSE. NLCIL had replied that delay is due to acquisition of
                              land by GoR and informed to review the decision. Matter is pending with GoR.
                                                                46
 STATE
   &
PRIVATE
SECTOR
   47
NORTHERN
 REGION
   48
                        BROAD STATUS OF THERMAL POWER PROJECTS IN RAJASTHAN
Commissioning Schedule
                                                                          49
                                              Commissioning Schedule
                                 Capacity               Actual (A) / As
Sl.       PROJECT DETAILS                     Original                                                    Broad Status
                                  (MW)                  now Expected
No
                                             Syn.   COD Syn. COD
                                            Comm        Comm
State Sector
     Suratgarh Super Critical    1320                                          Unit-7
     TPP, RRVUNL,                                                               Boiler: Erection started on 26/03/14. Hydro test completed on
     Suratgarh (Distt Sri                                                       31/12/15. BLU completed on 24/02/17. Steam Blowing started on
2                                           06/16 09/16   12/18 03/19           09/06/18 and completed on 25/08/18. Unit synchronized on
     Ganga Nagar          U-
                                  660       07/16         03/19                 18.12.18 at 1140 hrs with 205MW max load.
      7
                                                                                TG: TG civil work started on 07/12/13. Condenser erection
                                  660       09/16 12/16   06/19 07/19           started on 29/04/15. TG erection started on 16/11/15. TG box up
                                            10/16         06/19                 done on 21/01/17. TG put on barring gear on 10/11/17.
                          U-8                                                   ESP: Erection completed. Insulation and cladding work also
      Original Estimated cost               Rs. 792000 lakh                     completed
      Latest Estimated cost                 Rs. 792000 lakhs
      Exp. during 2012-13                   Rs.   1736 lakhs                   Unit-8
      Exp. during 2013-14                   Rs. 55029 lakhs                      Boiler: Erection started on 25/06/14 HT completed on 15/03/16.
                                                                                 Boiler light up completed on 28/09/17. Boiler Hyd. Test (Non-
      Exp. during 2014-15                   Rs. 191874 lakhs                     Drainable) performed on 27/07/18.
      Exp. during 2015-16                   Rs. 252788 lakhs                   TG: Condenser Erection started on 28/06/15 and TG erection on
      Exp. during 2016-17                   Rs 165353 lakhs                    05/11/15. TG box up done on 09/11/17. Turbine boxed up on
      Exp. during 2017-18                   Rs 39264.22 lakhs                  09.11.17. Turbine oil Flushing completed on 18/08/2018.
      Exp. during 2018-19                   Rs 51516.23 lakhs                    ESP: Erection completed. Insulation work also completed.
      Total Expenditure (up to 02/19)       Rs 828510.54 Lakhs
      Type of fuel                          Coal                                 Availability of startup power made on 21/01/17.
      Zero date                             28/03/13                             BoP’s:
      Main Plant Order                      Order placed on 23/05/13 on
                                            M/s BHEL on EPC basis.                Chimney: Both the flue is ready.
                                            Blr-ALSTOM, TG-                       CHP:       Stacker cum Reclaimer & Reclaimer Unit 7&8-
                                            SIEMENS                               Mechanical erection almost completed. Electrical work of SCR
      Type of Fuel                          Coal                                  &SR unit #8 is u/p. Commissioning work started on 12/03/18 and
      Fuel linkage                          Approval accorded by MOC              in progress. Supply of conveyor package has completed. Wagon
                                                                                  tippler-2 erection work has been started.
                                            on 03/02/12 from Parsa East
                                                                               AHP: Bottom ash hopper of U-7 has completed with refractory
                                            & Kanta Basan coal bocks of
                                                                               work and equipment erection work. Erection and commissioning
                                            RVUNL                              work of ADL pipe line (L1 & L2) up to Ash dyke is completed.
      Power purchase agreement:             PPA made between RVUN              Bottom ash hopper of u-8 is u/p. Erection work of HP, LP and over
                                            and Jaipur, Ajmer, Jodhpur         flow piping around BAH is under progress.
                                            Vidyut Vitran Nigam Ltd. on
                                            18/05/10.                            NDCT: U-7: Commissioned 100%. U-8: Internal columns are
      Power evacuation system:              Through 4 x 400 kV                   99% completed.
                                            transmission line of RVPN.           U-8: For CT-8 raker columns and pond floor are completed. Shell
      Land:                                                                      is completed on 13/09/2017. Partition wall and hot water duct
                                                                                 columns are in progress.
      Possession of 672.873 ha of land for water system, construction of
                                                                                 CW System: Ready
      main power plant, residential colony on approach road taken.               DM Plant: Commissioned.
      Water:                                                                     FO system: Shell erection/fabrication completed. HFO unloading
      60 cusec of water from Indira Gandhi Canal is allocated on                 discharge pipe line work on ash handling pipe rack is under
      02/09/09.                                                                  progress.
      MOEF:                                                                      Switchyard: Back charging done from existing plant 400 KV
      Clearance obtained vide letter No. J-13012/14/2009 – IA. II (T)            switchyard on 21/1/2017. Progress of SSCTPS-BABAI Line-
      on 23/05/12                                                                Erection-676/676, stringing-197.245/245 km. 400 KV, DC,
      SPCBC:                                                                     SSCTPS- BIKANER transmission line is ready. SSCTPS-
      Clearance accorded by Rajasthan SPCB on 04/06/13.                          BIKANER transmission line charged on 28/07/18.
      Civil Aviation
                                                                               FGD Plant: - Feasibility Report cum DPR for implementation of
      NOC obtained from AAI on 26/4/10
                                                                               revised emission norms for the plant have received. Technical spec
                                                                               finalised.
                                                                          50
                      BROAD STATUS OF THERMAL POWER PROJECTS IN UTTAR PRADESH
      Fuel Linkage                            : Fuel supply agreement between PPGCL & NLC for 6.95            BOPS:
                                              MTPA has been executed on 29.08.2013.                          FGD: The order for FGD installation has been
      Associated Transmission System        Power is proposed to be evacuated at 765 KV and 400 KV            placed on M/S Tata Consultant Engineers
                                            level for which 765KV and 400 KV switchyards are proposed.        (TCE) at the cost of @ 1000Crs. There is no
                                            Responsibility of UPPCL & PPGCL. Work awarded to Isolux.          space constraint for installation of FGD
                                                                                                              system in the plant.
                                                                                                              Chimney: Awarded to Paharpur. 275 height
                                                                                                               achieved for both chimneys. Flue 1&2 completed.
                                                                                                               Chimney 2 completed.
       Land: :1468 acres of land for the project is in physical possession. Land for the facilities
                                                                                                              CHP: Package A awarded to L&T and Package B
       outside the plant area is being acquired. For land required for railway sliding about 32.71 Ha
                                                                                                               awarded to HEW. For Package A, WT4 & WT 3
       out of 35 Ha has been acquired. Lease deed executed and the process of taking physical
                                                                                                               commissioned. For U-1,2,3 bunker ready. Load
       possession of land is completed.
                                                                                                               trials carried out. For Package B, 1st stacker
                                                                                                               reclaimer commissioned.
       MOEF clearance: Obtained on 08.09.2009
                                                                                                               AHP: Awarded to Macawber Beekay. System
                                                                                                               ready for U-1,2 & 3 completed.
                                                                                                              NDCT: CT-1,2 &3 completed.
                                                                                                              PTP: PT plant commissioned
                                                                                                              DM Plant: DM plant commissioned
                                                                                                              FOS: ALL HFO and LDO storage & Day tanks
                                                                                                               completed. FOH pump house ready, LDO system
                                                                                                               commissioned.
                                                                                                              FPS: Ready for U-1,2 &3
                                                                                                              SWYRD: Work in 400 KV switchyard
                                                                                                               completed and charged one 765 kV line
      Critical Area                         Power Evacuation System: Responsibility of procurers as per the PPA and as per latest status, the work has been
                                            awarded to Ms. Isolux. Line is to be made ready for evacuation before synchronization date
                                                                              51
Sl.   PROJECT DETAILS               Capacity        Commissioning Schedule
No.                                  (MW)      Original         Actual (A) / As                                     Broad Status
                                                                now
                                                                Anticipated.
                                                Syn.    COD      Syn.     COD
                                               Comm             Comm
2     Harduaganj Expn.,-II          660                                                BTG Island Activities-Mechanical & Electrical Works:
      UPRVUNL                                                                             Boiler: 1st Pass & 2nd Pass pressure parts major erection work
      Distt.: Aligarh, U.P                                                                 completed.
                           Unit-1   660         09/19    01/20      10/19      07/20
                                                11/19               01/20                 Boiler: Pressure parts joints 90% completed. Attachments
      Original//Latest Cost         : Rs.482649 lakhs. Revised cost of Project due         welding under progress.
                                    inclusion of FGD SCR is Rs. 550098 lakhs.             Boiler & Aux: Main Boiler, Mill Bay & APH structure
      Exp. During 2015-16           : Rs. 30520 Lakhs                                      erection completed, SCR & Platform Str. work is in progress.
      Exp. During 2016-17           : Rs 11243 Lakhs
      Exp. During 2017-18           : Rs 45767 Lakhs
                                                                                          Boiler & Aux: Mills Erection work is under progress.
      Exp. During 2018-19           : Rs 112073 Lakhs                                     Boiler & Aux: APH-A & B erection is under progress.
                                                                                          Boiler & Aux: Critical piping erection is under progress.
      Cumulative Expd.              :Rs 199603 Lakh                                       Boiler & Aux: PA Fan A erection is under progress.
      (02/19)
                                                                                          Boiler & Aux: FGD erection is under progress
      Date of Financial Closure     : Achieved on 14.03.2012 (80% PFC Loan &
                                    20% government equity)                                Boiler & Aux: Air Duct & Gas Duct along Expansion Joints
      Type of fuel                  : Coal                                                 erection is under progress.
      Date of Main Plant            : M/s Toshiba JSW Systems Private Limited as a        TG & Aux: LP condenser tube insertion in progress.
      Order/BoPs                    single EPC basis on 08.09.2015                        TG & Aux: HP condenser tube insertion completed &
                                    Boiler: Doosan, India ; TG & Generator: Toshiba
                                    JSW Power Systems                                      expansion in progress.
      Zero date                     : 08.09.2015                                          TG & Aux: HP, IP & LP Turbine Upper outer Casing erection
      NTP (Notice to proceed)       : 08.09.2015                                           is in progress.
      date                                                                                TG & Aux: HP Heater, LP Heater, Deaerator erection
      PPA                           : Signed on 16.01.13                                   completed & further alignment & Piping is under progress.
       Fuel Linkage                 : From Saharpur-Jamarpani, Jharkhand coal
                                    Block allocated on 25.03.15.                          TG & Aux: ECW pipe pre-assembly work is under progress.
      Power Evacuation System       400kV Switchyard                                      ESP: Erection for Pass A, B, C, D, F is under progress. Pass C
                                                                                           is erection in in advance stage for ATT.
      Land: Not required being an Expansion Project.                                      CCR Building: HVAC & Ventilation Duct erection in
      MOEF clearance: Change order from MOEF issued. The Govt.of UP has
      approved the Installation & Construction of FDR & SCR Syatems in December
                                                                                           progress.
      2016 which will comply the MoEF circular dated 7/12/2015                            CCR Building: Electrical SWGR Panels erection & Light
      Water: Water Allocated on 03.12.11 from Upper Ganga Canal.                           conduit, Cable tray work is under progress.
      Civil Aviation Clearance: Civil Aviation Clearance granted on 11.07.12 from         Switchyard Control Room- Cable Tray & Ventilation Duct
      Airports Authority of India.                                                         erection work is under progress.
      Financial Closure: 80% PFC Loan & 20% Government Equity.
      Note: -                                                                          A) Main Plant Civil & Structural Works are under progress:
      The above dates are based on 58.7 months completion schedule.                    1. TG Building: TDBFP-A, B & MDBFP foundation casting
                                                                                          completed & handed over to mechanical.
      -    All the other BoP packages have also been awarded to various contracting
           agencies for execution.                                                     2. TG Building all floors Casting AB & BC bay completed.
                                                                                       3. TG Building: 0m: HP Vacuum Pumps, CPU fdn completed.
                                                                                          Balance equipment fdn & Grade slab civil work is in progress.
                                                                                       4. Transformer Yard: Foundation civil work is in progress.
                                                                                       5. ESP-Control Room: 1st slab casting completed. Civil work
                                                                                          above 1st floor level is in progress.
                                                                                       6. CCR Building: All floors slab casting completed and fronts
                                                                                          given to Electrical & mechanical for further work.
                                                                                       7. Pipe Rack: Civil foundations & Structural work in progress.
                                                                                       8. Duct support structure foundation from Boiler to ESP (LHS)
                                                                                          completed & further from ESP to Chimney in progress.
                                                                                       B) BOP areas : Civil works under progress :
                                                                                       1. Raw Water system: Raw water Reservoir-A & B completed,
                                                                                          RWI Pump House, and RWPH Civil work is in progress.
                                                                                       2. PT Plant: Chemical House, Chlorination building, CWST & PH
                                                                                          works is in progress.
                                                                                       3. Permanent Store: AB, BC Bay works completed, CD Bay civil
                                                                                          work is in progress.
                                                                                       4. GCW-06B: ER-2, 4, 1A Control Room civil work is under
                                                                                          progress.
                                                                                       5. ETP & ERS: CMB civil works completed, ERS: HRSCC & civil
                                                                                          works is in progress
                                                                                       6. EGD & Compressor House- Civil work is in progress
                                                                                       7. CHP: JT-01A base raft casting completed & further civil works
                                                                                          in progress.
                                                                                       8. CHP: Wagon Tippler, Track Hopper, ERH, Stacker Reclaimer,
                                                                              52
                                                                           JT and Conveyor civil work is in progress.
                                                                     9.    IDCT: 21/24 no fan deck & 11/24 no fan cylinder casting
                                                                           completed & other civil work is in progress.
                                                                     10.   CWPH: Control Room slab, Pump & Motor Floor, Forebay
                                                                           works completed. Balance civil work is in progress.
                                                                     11.   Chimney: Shell concreting work completed & Corbel civil
                                                                           work is in progress.
                                                                     12.   AHP: Ash Water Pump House Slab castings completed and
                                                                           further civil works in progress.
                                                                     13.   Ash Slurry Pump House, AHP Control Room, Compressor
                                                                           building, Ash Silo civil work for super structure is in progress.
                                                                     14.   Ash Pond civil works in progress.
                                                                     15.   Stacker Reclaimer-1B: Segment-90 % civil work completed.
                                                                           SR-1A: Foundation civil work is in progress.
                                                                     16.   400 KV Switchyard: Fire Pedestal, Fencing & Drain work is in
                                                                           progress.
                                                                     17.   Switchyard Control room: Battery Room, CRP & ACDB civil
                                                                           work completed, balance civil works in progress.
                                                                     18.   Pipe Rack foundation & Pipe Sleeper- Civil foundation &
                                                                           Structure work is under progress.
                                                                     C)     BOP areas : Mechanical & Electrical works under
                                                                            progress :
                                                                           CW pipe: CW & ACW Pipe erection & encasement work in
                                                                            progress. 80 % work completed.
                                                                           RWI System: Pumps erection in progress.
                                                                           Auxiliary Boiler- Mechanical erection work is in progress.
                                                                            Water & Steam Drum erected. Chimney erected.
                                                                           Yard piping fabrication work is in progress.
                                                                           Pipe Rack-1A, 1B erection completed & 1C-IV erection is in
                                                                           progress.
                                                                     FGD Plant:
                                                                     FGD Package is being executed by M/S Doosan. Absorber & GGH Area Civil
                                                                     Works completed. Building & balance Civil in progress. Absorber Tower
                                                                     erection commenced & in progress. Material receiving in progress.
Critical Areas/
Assistance Required
                      Late receipt of the MOEF&CC revised order by UPRVUNL with inclusion of FGD & SCR System in the project i.e. in
Reasons for Delay
                      December’2016.
                                                            53
Sl.    PROJECT DETAILS             Capacity       Commissioning Schedule
No.                                 (MW)         Original     Actual (A) / As                           Broad Status
                                                              now
                                                              Anticipated.
                                               Syn.    COD     Syn.     COD
                                              Comm            Comm
3      Obra-C TPP                    1320                                              SG Package by M/S DPSI & STG Package by M/S
       UPRVUNL                                                                         Alstom Forge Power Ltd.
       (Obra, Dist.                                                                  Work in Progress
       Sonebhadra),                                                                  Concrete work (RCC) for TG Building #1 Foundation
       U.P.                                                                           and Pedestal
                            U-1      660      08/20 12/20         02/21    06/21     Concrete work (RCC) for TG Building #2 Foundation
                                              09/20               04/21               and Pedestal
                            U-2      660     12/20    04/21      07/21     11/21     Concrete work (RCC) for STG #1 Pedestal (Main
                                             12/20               07/21                Column with Wall) Cleaning for concreting (PCC)
       Original/Latest Cost        : Rs.1041600 lakhs                                 work for Chimney foundation.
       Expenditure                                                                   Concrete work (RCC) for Condenser #1 pedestal
                         2016-17   42377 Lakha                                        Concrete work (RCC) for CW Pit #1 column with
                         2017-18   28623 Lakhs                                        wall
       Cumulative Expenditure      : Rs. 150248 Lakhs                                 Concrete work (RCC) for CEP Pit #1 Foundation &
       (up to 01/19)                                                                  wall
                                                                                     Concrete work (RCC) for STG #2 Pedestal (Main
       Date of Financial Closure    : 13.11.2013
                                                                                      Column with Wall)
                                    70% debt loaned from REC and 30% equity to
                                                                                     Concrete work (RCC) for Condenser #2 pedestal (2nd
                                    be borne by State Govt.
                                                                                      lift) Reinforcement & shuttering work for CW Pit #2
       Type of fuel                 : Coal
                                                                                      wall
       Fuel Linkage                 : From Saharpur Jamrpani, Jharkhand Coal         Concrete work (RCC) for CEP Pit #2 wall
                                    Block allocated to UPRVUNL with the project      Concrete Work (RCC) for 400kV GIS Building
                                    specified in the end use plants for the Block/    column & Top Slab.
                                    MoU with MMTC for imported Coal                  Concrete Work (RCC) for 765kV AIS Building.
       Date of Main Plant           : Order for main Plant Equipment (BTG)            Erection work of Cooling Water(CW) Pipe.
       Order/BoPs                   awarded to M/s. Doosan Power Systems             Erection work of Boiler #1 Steel Structure Tier 5
                                    India Pvt. Ltd. On 22.12.2016                     Erection of ESP #1 , Pass C
                                    SG package by M/s DPSI& STG package by           Erection of Ceiling Girder #1
                                    M/s Alstom Bharat Forge Power Ltd.               Erection of Boiler#2, Steel Structure tier 1
       Zero date                    : 22.12.2016                                     Assembly works of Condenser #1 – Water Chamber
       Land                         : Not required being an expansion Project         Erection works of Air Duct#1.
       PPA                          : Signed with UPPCL. on 16.01..2013               Erection of Main Steel Structure for TBN Building #1
       MoEF Clearance : :.Forest clearance obtained on 30.06.2016 and                 Erection of Main Steel Structure for CCB Building.
       Environmental clearance obtained on 21.06.2016                                 Main Grid Earthing work.
       Power Evacuation System: By UPPTCL at 765 KV                                  Excavation work in IDCT#2
       Water : Allocation of 54 cusec water by Govt. of UP from Rihand Reservoir     RCC Work for JT#11 Foundation
                                                                                     Purchase Order Placement Status:
                                                                                     PO issued for FGD -Limestone preparation system
                                                                                      (04-Jan-19)
                                                                                     PO issued for WTP – Tanks (04-Jan-19)
                                                                                     PO issued for Fire Fighting – Probe Type Heat
                                                                                      Detector (18-Jan-19)
      Critical Areas/Assistance
      Required
                                                                      54
Sl. No. PROJECT DETAILS             Capacity          Commissioning Schedule
                                     (MW)          Original     Actual (A) / As                                          Broad Status
                                                                now Anticipated.
                                                 Syn.    COD      Syn.     COD
                                                Comm             Comm
4     Jawaharpur STPP                  1320                                                 1. Status of Construction Activities
      JVUNL (100%                                                                           1.1 Completed activities
      subsidiary of                                                                         - Piling Work for FD Fan # 2
      UPRVUNL)                                                                              - Foundation work for DM water pump house
      Village: Malawan,                                                                     - Foundation work for Condensate storage pump house
      Dist. Etah), U.P                                                                      - Ground assembly welding for Primary re-heater coils
                              U-1       660       08/20 12/20          03/21      07/21     - Excavation of Lime stone loading & unloading house
                                                  09/20                03/21                - Excavation of Boiler Structure # 1
                                                                                            - Excavation of Junction Tower-5, 9, 12 & 13
                              U-2       660      12/20 04/21          07/21      11/21      2. Status of Completed activities
                                                 01/21               07/21                  - Foundation and erection of steel structure tier 1& tier 2 for Boiler # 1
       Original/Latest Cost          : Rs.1056627 lakhs                                     - Excavation, foundation and pedestal work for ESP, Transformer ,TG
       Cumulative Expenditure        : Rs. 102100 Lakhs                                     Pedestal & CEP/CW Pit#1
       (up to 01/19)                                                                        - Foundation and structure work for TG Building #1 and CCB
                                                                                            - Steel structure fabrication & erection work for TG building and CCB
       Type of fuel                  : Coal
                                                                                            - Pre-assembly work for pressure part # 1 and Air Duct # 1
       Date of Financial Closure     80% debt loaned from PFC & REC and 20%
                                                                                            - Pedestal, Raker column, Precast, Foundation Work for Basin (NDCT)
                                     equity to be borne by State Govt.
                                                                                            - Foundation work for Boiler # 2
       Date of Main Plant            : Order for main Plant Equipment (BTG)                 - Steel structure erection for Boiler # 2
       Order/BoPs                    awarded to M/s. Doosan Power Systems India             - Piling work unit #1 for Duct support structure (BLR ~ ESP), GGH &
                                     Pvt. Ltd. On 22.12.2016                                absorber
       Zero date                     : 22.12.2016                                           - Piling work unit # 2 for ESP, ID Fan, NDCT, Duct support structure
       PPA                           : Signed on 31.12..2016                                - Piling work in common area for Chimney, stacker & re-claimer, Fly ash
                                                                                            silo, Service
       Land : The land required is 865 acres and is in possession of JVUNL. No                building and Lime stone storage silo area
       wildlife and no archeological monument exist at the proposed project site.           - CW pipe encasement work in block 4 area
       MoEF Clearance : Received on date 26.10.2016                                         - CW pipe fit up & welding work in block 2 & 4 area
        Fuel Linkage : From Saharpur Jamrpani, Jharkhand Coal Block allocated.              - Column & rebar work for CW pump house electrical building & Lay
       Bridge Linkage for the project allocated vide letter No.23014/2/2016-CPD             down area
       dated 11.04.2016. MOU dated 25.03.2015                                               - Foundation & re-bar work for CW fore bay
       Water : 53 cusecs water allocated from Lower Ganga Canal by irrigation               - Preparation for Sand backfilling work for CS & DM Tank
       Department for the Project on 09.11.2009                                             - Foundation and wall structure work of LDO Dyke & LDO Tank and
                                                                                            potable tank
                                                                                            - Foundation work (Re-bar and foam work bottom slab) for Clarified
                                                                                            Structure
                                                                                            - Foundation RCC work & back filling work for Clarified water pump
                                                                                            House
                                                                                            - Plinth beam PCC casting & rebar work for DM pump House &
                                                                                            Condensate Storage
                                                                                              Transfer Pump House
                                                                                            - Foundation work for LDO Supply loading & unloading house & Lime
                                                                                            stone unloading house
                                                                                            - Excavation work for Reservoir -A & B
                                                                                            - Excavation work for Ash Dyke & ash Embankment
                                                                                            - Foundation & Back filling work for Crusher house & Junction Tower
                                                                                            - Piling for Stacker & Reclaimer & Crusher House
                                                                                            - Foundation & Back filling work for Track hopper & Wagon Tippler
                                                                                            - Excavation work for Emergency Reclaimer Hopper
                                                                                            - Steel structure fabrication work for Coal conveyor gallery
                                                                                            - Super structure work for 400kV GIS building and 765kV GIS Building
                                                                                            for Zone –A
                                                                                            - Super structure & finishing work for 220 KV GIS Building ,storage
                                                                                            yard building & Field
                                                                                              quality control Lab
                                                                                            - Foundation & Sub structure work for 765kV GIS building &
                                                                                            Interconnecting Auto Transformer
                                                                                              (765kV / 400kV)
                                                                                            - Sub structure work for switchyard equipment, Main Gate & Security
                                                                                            Complex
                                                                                            - Electrical Grounding work (MS Rod & GI Strip laying, Welding)
                                                                                            2. Payment Status to DPSI till 31.03.2018 (Advance)
                                                                                            Payment made to DPSI approx. 1200.00 Crore.
                                                                                            3. FGD: Order placed on M/S Doosan Power Systems India Pvt. Ltd.
                                                                                            (EPC Project).
     Critical Areas/Assistance       Delay in Unit 1 & 2 COF will be approx. 8 months as compared to the baseline schedule of 21st Dec. 2020. The efforts are
     required                        being made to catch up the baseline schedule with below catch-up activities:
                                     - Shorten the foundation work duration for TG pedestal.
                                     - Parallel work of foundation and steel structure erection for Boiler.
                                     - Acceleration effort for various work activities like
                                                Day & night shift work for piling and steel structure fabrication (TG & CCB)
                                                Working on Sundays and holidays
                                                Manpower increase for civil, mechanical & site fabrication activities
                                                Additional subcontractor for piling work
                                                                               55
Sl.                                   Capacity            Commissioning Schedule
No.    PROJECT DETAILS                 (MW)                                                                  Broad Status
                                                     Original        Actual(A) / As now
                                                                     Expected
                                                   Syn.      COD      Syn.       COD
                                                   com.               com
      State Sector
5.    Panki TPS Ext,                      660                       30.09.21   31.01.22   Unit-1:
      Distt. Kanpur,          U.P.
      (UPRVUNL)                                                                           Boiler:
                            U-1      660
           Original/Latest Cost : Rs / lakhs                                              TG:
            Exp.During 2018-19 :Rs 1600 lakhs
                               :                                                          BOPs:
MOE&F clearance:
                                      .
                     Critical Areas
              Reasons for Delay
                                                                        56
                  BROAD STATUS OF THERMAL POWER PROJECTS IN UTTARAKHAND
                                                                               57
                              Unit                 Commissioning Schedule
Sl.     Project Details              Capacity                                                               Broad Status
                                                 Original Actual(A)/ As
No.                                   (MW)
                                                              Expected
                                                Synch/ COD Sync/.     COD
                                                Comm       Comm
 Private Sector
 2. BETA CCPP,             GT-1         75       12/11 12/11       *               OPEN CYCLE
     Module-I, at                                12/11                             GT & GTG
     Kashipur              GT-2         75       12/11 12/11       *               Both the gas turbines (6FA, GE France) & generators supply
    (M/s BETA                                    12/11                       *     reached at site. Erection of both the GTs and GTGs has completed.
     INFRATECH                 ST       75       03/12 03/12       *               Oil flushing of both the GTs completed. Erection of GT exhaust
     PRIVATE LTD.),                              03/12                             duct completed. By pass stack erection completed. Erection of
     Udhamsingh Nagar                                                              diverter and damper completed. GT is ready to put on turning gear.
                                                                                   Commissioning in open cycle is possible within one month from
      (2GT +1ST=225MW)                                                             availability of gas
       Original /Latest Cost          : Rs. 93600 Lakhs / Rs. 125400 Lakhs
                                                                                   COMBINED CYCLE
      Expenditure during 2010-11     : Rs. 4649 Lakhs
                                                                                   HRSG-I &II
      Expenditure during 2011-12     : Rs. 74994 Lakhs
                                                                                   Both the HRSGs order have placed on M/s Thermax (India)
      Expenditure during 2012-13     : Rs. 20008 Lakhs
                                                                                   23/10/10. HRSG erection completed. HT of both HRSGs
      Expenditure during 2013-14     : Rs. 16000 Lakhs
                                                                                   completed. HRSG is ready for ABO.
      Expenditure during 2014-15     : Rs. 2913 Lakhs (upto 06/14)
       Total Expenditure             : Rs. 118564 Lakhs (Upto 06/14)
                                                                                   ST:
       Approval date:                : NA                                          ACC erection started on 01/05/12. ACC erection is under progress.
       Zero date:                    : 04/12/10                                    ST order has placed on M/s G.E. on 04/12/10 and completed. TG
       Notice To Proceed (NTP)       : 04/12/10                                    erection started 26/04/12. TG Box Up completed. ST
       Financial closure               : Achieved                                  synchronization is expected within two and half month from
       Main Plant Order                : 20/09/10, 04/12/10 And 23/10/10 on M/s    availability of gas. Combined cycle commissioning is expected
                                       BETA Infraprop (P) Ltd (EPC Basis)          within 3month from availability of gas.
                                       through ICB route.
                                                                                   BoPs:
       BTG Make                        GTGs# GE, France(6FA), HRSGs#
                                       Thermax (India).and STGs are from HTC
                                       China                                            All the BoPs are either already completed or nearing
                                                                                       completion.
       BOP Package                   : Reputed Indian Vendors
       Type of fuel                    : Natural Gas
       PPA                           Yet to be signed
       Source and supply of          Domestic Gas from D-6, KG Basin (Right
       Fuel                            now E-Bidding RLNG)
       Power Evacuation                 Connectivity of the plant with 220/132kV
       system                          Mahua Khera Ganj substation has been
                                       approved. LILO of 220kV circuit from
                                       400kV Kashipur to 220 kV Mahua Khera
                                       Ganj is nearing completion. Long Term
                                       Access (LTA) from 220kV/132kV Mahua
                                       Khera Ganj sub-station has been approved
                                       by PGCIL.
                                                                             58
Western
Region
   59
          BROAD STATUS OF THERMAL POWER PROJECTS IN CHHATTISGARH
                                  Unit                    Commissioning Schedule
Sl.         Project Details               Cap.      Original    Actual(A)/ As                                                           Broad Status
No.                                      (MW)                            Expected
                                                  Synch/   COD       Sync/.       COD
                                                 Comm               Comm
    Private Sector
1       Akaltara(Nariyara)                                                                           Unit-1 (U-3)
        TPP,                    U-1      600      02/12      04/12     18/05/13 (A) 14/08/13(A)      COD achieved on 14/08/13. Commissioned on 13/08/13. Synchronised on
        (Distt:       jangir-   (U-3)             04/12               13/08/13 (A)                   18/05/13.
        Champa)                                                                                       Boiler:
        M/s KSK Mahanadi                                                                                 Boiler erection started on 01/09/10. Boiler Drum lifted on 29/04/11. Boiler
        Power      Company          U-2       600       06/12     08/12 08/08/14(A) 26/08/14(A)          HT (Non-Drainable) completed on 06/07/12. BLU completed on 10/04/13.
        Ltd.(Formerly               (U-4)               08/12            22/08/14 (A)                    SBO completed on 24/04/13 Oil synch. Completed on 18/05/13.
        Wardha        Power                                                                          TG:
        Company Ltd)                U-3       600       10/12     12/12    12/17(A) 21/01/18(A)          TG Deck casting completed on 05/10/11. TG erection started on 16/04/12.
                                    (U-2)               12/12             18/01/18(A)                    TG boxed up on 06/11/12. TG oil flushing completed on 17/01/13.
                                    U-4       600       02/13     04/13       06/19         06/19    FGD: FGD plant expected in 6/22.
       (6x600MW=3600MW) (U-5)                           04/13                 06/19                  Unit-2 (U-4)
                                    U-5       600       06/13     08/13       09/19         09/19    COD achieved on 26/08/14. Commissioned on 22/08/14. synchronized on
                                    (U-1)               08/13                 09/19                  08/08/14.
                                    U-6       600       10/13     12/13       12/19         12/19    Boiler.
                                                        12/13                 12/19                      Boiler erection started on 01/12/10. Boiler Drum lifted 19/06/11. Boiler HT
         Orgiginal Cost /            : Rs.1619000 Lakh / Rs. 2708000 lakhs                               (Non-Drainable completed on 11/05/13.BLU completed on 17/05/14.SBO
         Latest Cost                                                                                     completed on 07/07/14.
                                                                                                     TG:
         Exp. During 10-11            : Rs. 45529.8 Lakh
                                                                                                        TG Deck casting completed on 20/02/12. TG erection started on 07/11/12.
         Exp. During 11-12            : Rs. 821600 Lakh
                                                                                                         TG boxed up on 30/06/14. TG oil flushing completed. TG Barring gear
         Exp. During 12-13            : Rs. 222416 lakhs
                                                                                                         completed in 07/14.
         Exp. During 13-14            : Rs 209517 lakhs
                                                                                                     FGD: FGD plant expected in 08/22.
         Exp. During 14-15            : Rs.164917 lakhs
                                                                                                     Unit-3 (U-2)
         Exp. During 15-16            : Rs. 90320 lakhs
                                                                                                     COD achieved on 21/01/2018. Commissioned on 18/01/18.
         Exp. During 16-17            : Rs. 318700 lakhs
                                                                                                      Boiler.
         Exp. During 17-18
                                                                                                        Boiler erection started on 01/04/11. Boiler Drum lifted on 29/04/12. Boiler
         Total Exp.( upto             :Rs. 1873000 Lakhs
                                                                                                         hydro Test(ND) is completed on 12/07/17. BLU completed on 18/11./17.
         12/16)
                                                                                                         SBO completed on 30/11/17.
         Approval date:               NA                                                             TG:
         Zero date:                : 21/04/09                                                            TG Deck casting completed. TG erection started on 05/01/17. TG Box Up is
         Financial closure         : Achieved on 30/03/10                                                done on 25/10/17
         EPC Order                 : EPC ordered on 21/01/09 on SEPCO (China)                        FGD: FGD plant expected in 10/22.
         Package(BTG)                  (Boiler-Shanghai Boiler Works, China),                        Unit-4 (U-5)
                                       (TG-Dongfang Electric Company, China)                       Boiler.
         Type of fuel                 Coal                                                               Boiler erection started on 08/12/11. Boiler Drum lifted on 31/08/16. Pressure
         PPA                          PPA: PPA signed with Gujarat Urja Vikas Nigam Ltd for 1010         parts and joints erection is in progress. Duct erection work is in progress.
                                      MW on 03/06/10.                                                    Boiler Hydro Test yet to be happen.
                                      PPA signed with APCPDCL for 400 MW on 31/07/12.                    TG:
                                      PPA signed with CSP Trade Co for 225 MW on 18/10/13                TG Deck casting completed on 06/10/12. Various level floor castingwork in
                                      PPA signed with TANGEDCO for 500 MW on 27/11/13                    progress.
                                      PPA signed with UPPCL for 1000 MW on 26/02/14                  FGD: FGD plant expected in 12/22.
         Power Evacuation             Power is to be evacuated to PGCIL pooling station through      Unit-5 (U-1)
         system                       400kV transmission system. Final bulk power transmission        Boiler.
                                      agreement signed with PGCIL on 25/02/10.                           Boiler erection started on 06/02/12. Foundation work is completed. Balance
                                                                                                         work in progress.
                     Land: Complete land for the project is under possession.                      TG:
                     MOE&F: Received on 19/10/09                                                    TG Deck casting is yet to be completed.
                      State Pollution Control Board: Chhattisgarh Environment Conservation Board     FGD: FGD plant expected in 02/23.
                      (CECB) granted “consent for Establishment” for 6x600 MW on 16/02/10.           Presently order was placed for techno-commercial feasibility study with
                      State pollution Control Board Clearance: Chhattisgarh Environment              black and veatch for all six units.
                      Conservation Board (CECB) has granted ‘Consent for Establishment for          Unit-6
                                                                                                    Boiler:
                      6x600 MW power plant of WPCLCG on 16/02/10.
                                                                                                    Boiler raft casting completed. Boiler erection yet to start. Foundation work is
                     Civil Aviation: NOC received on 12/05/09.                                     completed
                     Water: Water Resources Department, Govt., of Chhattisgarh has                 TG:
                      allocated 100 MCM of water /year from Mahanadi River from proposed             TG raft casting completed and column casting is in progress. Deck casting yet
                      anicut at Basantpur.                                                           to be completed.
                     Coal linkage: SECL (Tapering coal linkage to 3x600MW only) Letter of           FGD: FGD plant expected in 04/23.
                      Assurance(LOA) for tapering coal linkage to 3x600 MW has been granted          FGD draft report under review
                      by SECL on 11/06/09. FSA has been executed with SECL on 19/03/14 for         BoPs:
                      2 units. Tapering FSA for U-3 has been executed with Eastern Coalfields
                                                                                                     Chimney-: Chimney 3,4 & 2 are in service. Flue Cans Erection completed for
                      Ltd on 12/08/14.
                     As per the letter dated 18/10/16                                               all
                      Coal blocks of Gujarat and Goa linked to the power project for cancelled by    CHP: Ready in all respect
                      Supreme court. Tapering linkage granted for 1800 MW was also cancelled
                                                                                                   AHP: Ready
                      by the Ministry of Coal on 30/06/13. Long term coal linkage is required for
                                                                                                   Raw Water Supply System: Water Resources Department, Govt., of
                      the power project, for which policy is under formulation with GOI.
                                                                                                         Chhattisgarh has allocated 100 MCM of water /year from Mahanadi River
                                                                                                   PT/ DM Plant: Three streams are commissioned and in operation.
                                                                                                   CW System: majority of work has been completed. Only Connection
                                                                                                         between CW piping is pending for Unit #5 &6.
                                                                                                   IDCT: IDCT for U-1(3), 2(4) & U-3(2) are in service and for rest of unit’s erection
                                                                                                         works are in progress.
                                                                                                   FOPH: Fuel oil distribution system commissioned
                                                                                                   CCR Building is ready for all units.
                                                                                                  Switchyard: Back charging of 400kV switchyard completed on 27/08/2012.
                                                                                                       Control building is in service.
Critical issues                  Coal Linkage to remaining 3 units.
Reasons for Delay                Delay due to shortage of manpower and agitations by Villagers. Supply of material due to shortage of funds.
    * Unit numbering is given as per order of commissioning. Unit numbering given in brackets is as per original nomenclature.
                                                                                            60
                                              Unit                          Commissioning Schedule
 Sl. No.         Project Details                       Capacity                                                                         Broad Status
                                                        (MW)          Original        Actual(A)/ As
                                                                                              Expected
                                                                   Synch/ COD             Sync/.        COD
                                                                  Comm                    Comm
   2       Uchpinda TPP                       U-1        360       03/12         -    28/02/15 (A) 26/11/15(A)      Unit-1
           Unit-1(Ph-I)[]                                          05/12              28/10/15(A)                   COD achieved on 26/11/15. Commissioneed on
           Unit-2,3&4(Ph-II)                                                                                        28/10/15. synchronized on 28/02/15
                                              U-2        360       09/12         -    07/01/16 (A) 12/02/16(A)
           R.K.M Power, Janjgir                                                                                        Boiler: Boiler erection started on 03/09/11.
                                                                   11/12              28/01/16(A)
           Champa District,                                                                                            Boiler drum lifted on 22/04/12. HT test conducted
                                              U-3        360       12/12         -    31/08/17(A) 14/11/17(A)          on 07/09/13. BLU done on 08/11/14. SBO
           Chhattisgarh
                                                                   02/13              12/09/17(A)                      completed on 03/01/15. Unit. Consent to operate
         (4x360MW=1440MW)                        U-4       360        05/13       -           *              *         received on 17/07/15.
                                                                      07/13                                            TG: TG erection started in 10/12. TG box up
                                                                                                                       completed on 02/09/14. TG oil flushing completed
         Org.Est. cost / latest cost ( Ph-     : Rs. 665361 Lacs /1037733 lakhs/ 1178451                               07/14. TG barring gear on 09/12/14.
         I- 148750 lacs/ 263835 lacs                                                                                   Unit-2
         Ph-II – 516611 lacs / 914616                                                                                  COD achieved on 12/02/16. Commissioneed on
         lacs )                                                                                                        28/01/16. Synchronized on 07/01/16
         Exp. During 07-08                     : Rs. 1270 Lacs                                                         Boiler: Boiler erection started on 12/12/11.
         Exp. During 08-09                     :Rs. 12311 Lacs                                                         Boiler drum lifted on 30/04/12. HT conducted on
         Exp. During 09-10                     : Rs. 37363 Lacs                                                        07/11/13. Non drainable HT done on 27/03/14.
         Exp. During 10-11                     : Rs. 67641 lacs                                                        BLU done on 17/04/15. SBO completed on
          Exp. During 11-12                    : Rs. 153338 lacs                                                       25/10/15. Unit. Coal fired on 07/01/16.
         Exp. During 12-13                     : Rs. 277291 lacs                                                       TG: TG erection started on 16/03/14. TG boxed
         Exp. During 13-14                     : Rs. 255521 lacs                                                       up in 04/2015. TG Oil Flushing Completed in
         Exp. During 14-15                     : Rs. 119057 lacs                                                       07/15. TG on barring Gear in 07/15.
         Exp. During 15-16                     : Rs 99890 lacs                                                         Unit-3
         Exp. During 16-17                     : Rs 106584 lacs                                                        COD achieved on 14/11/17. Commissioneed on
         Exp. During 17-18                     : Rs 12476 lacs                                                         12/09/17. Synchronization on 31/08/17.
                                                                                                                       Boiler: Boiler erection started on 12/01/12.
         Cumm Exp. (Up to 10/17 )              : Rs.1141842 lacs                                                       Boiler drum lifted on 19/05/12. HT (drainable)
         Zero date:                          : 01/06/09                                                                completed on 31/01/14. BLU achieved on 19/
         Financial closure                     : 07/06/10 (Ph-II)                                                      07/17. SBO completed on16/08/17. Rolling done
                                                02/01/09 (Ph-I)                                                        on 25/08/17. Coal firing done on 31/08/17.
         Main Plant Order                      06/09. on M/s MIPP International.                                       TG: TG erection started on 11/10/14. HIP
                                               Boiler: China Western                                                   temporary box up completed and final box up
                                               TG: Harbin                                                              completed on 26/07/17. TG put on BG on
                                                                                                                       01/08/17.
                                                                                                                       Unit-4
         BOP Package                         GM technical services, Ph-1 & 2 18/01/2011
                                                                                                                       Boiler: Boiler erection started on 30/04/12.
                                             .
                                                                                                                       Boiler drum lifted on 30/12/12. HT conducted on
         Type of fuel                          Coal
                                                                                                                       20/01/15.ESP erection and commissioning
         PPA                                 : Signed with CSEB for 37.5% on 29/09/06 and PTC for sale of 300          completed.
                                               MW on 08/05/09. PPA for sale of 350 MW signed with UPPCL on             TG: condenser erection started on 20/2/15. TG
                                               15/03/16.                                                               erection started on 25/11/14. TG box up
         Power Evacuation system               BPTA signed with PGCL on 25/02/10. BG for Rs. 40.95 cr given to completed in 3/18. TG Oil Flushing completed
                                               PGCL.Detail route survey completed Route alignments completed.          on 22/03/2018.
                                               TSA agreement signed on 06/08/12                                        BoPs:
           Land: Total 900 acres’ land acquired. Govt. land: 104 acres & private land 645.51 acres. 94.17                  Chimney: Chimney-1 Shell construction
                    acres Govt. land allocated for green belt development.                                                   work completed (270m). Flue erection and
           MOE&F: Obtained on 26/08/08.                                                                                     insulation for U-1&2 completed.
           Civil Aviation: AAI issued NOC on 05/09/2008.                                                                    Chimney-2:      Shell construction        work
           Water: 44.83 MCM per annum.                                                                                      completed (270m). erection and insulation
           Coal linkage: FSA signed with SECL for Phase-I on 03/09/13 and phase-II on 23/09/13.                             for U-3&4 completed
                                                                                                                            CHP: Phase 1 & 2 completed in all respect.
                                                                                                                            AHP: BAHS for U-1,2,3&4 completed.
                                                                                                                            PT/ DM Plant: Three streams are
                                                                                                                             commissioned and in operation. Forth
                                                                                                                             stream commissioning to be done
                                                                                                                            CW System: CW pump house-1 civil work
                                                                                                                             completed CW pump house-2 civil work
                                                                                                                             completed and CW pumps erection is
                                                                                                                             completed. CW piping for unit-1,2,3&4 is
                                                                                                                             completed
                                                                                                                            Cooling Tower: Aready Commissioned.
                                                                                                                            FOPH: HFO & LDO storage tanks erected
                                                                                                                             and insulation completed
                                                                                                                            Switchyard: Completed in all respects.
                                                                                                                       FGD:
                                                                                                                       Vendor identification under process.
  Critical issues     Consent to Operate-Due to non availability of CTO, Developer is not able to commission the Unit 4. Tapering coal linkage has been cancelled by
                      SECL. BG to be issued to release FDR amounts paid customs. PPA issue- CSPTCL has expressed inability to offtake power as per PPA. Working
                      Capital required for starting operation of U-1 is 153 cr & for U-2,3,and 4 is 571 cr.Readiness of Railway siding(work delayed due to land acquition
                      because of new land acquition policy and funds)
  Reasons for         Work suffered due to agitation by villagers. Slow progress of work at site. Delay in readiness of BoPs. Delay in readiness of startup power. Delay due
  Delay               to financial problems. Balance land acquisition for Ash pond and railway line. Consent to operate for U-2,3&4.
                                                                                     61
                                              Unit                         Commissioning Schedule
Sl. No.           Project Details                     Capacity                                                                      Broad Status
                                                       (MW)          Original       Actual(A)/ As
                                                                                          Expected
                                                                  Synch/ COD          Sync/.       COD
                                                                 Comm                 Comm
3          Lanco Amarkantak Mega TPS            3     660          01/12        -         *          *        Unit-3
           ( Pathadi )                                             01/12                                       Boiler: erection started on 09/10. HT completed on
           (Distt. Korba )                                                                                      22/07/16. BLU delayed due to non-availability of start-
           M/s LAP Pvt. Ltd.                    4     660          03/12        -         *          *          up power.
           Phase-II                                                03/12
          (2x660MW=1320MW)                                                                                     TG: Condenser erection started on 1/05/11 and completed
                                                                                                                & partially tube leak test completed. TG erection started
           Original /Latest Cost              Rs.688600 Lakhs/ Rs770000 Lakhs/Rs. 1081524 lakhs                 on 11/10/11. TG Box up completed on 26/11/16.
          Expenditure during 2007-08           Rs. 189 lakhs                                                   ESP: Pass B ATT completed. Pass C ATT is also
          Expenditure during 2008-09           Rs. 209 lakhs                                                    completed.
          Expenditure during 2009-10           Rs. 9841 lakhs
          Expenditure during 2010-11           Rs.206364 lakhs
          Expenditure during 2011-12          Rs 262658 lakhs                                                 Work is held up at the site due to fund constraints
          Expenditure during 2012-13          Rs. 125739 Lakhs                                                since 07/17.
          Expenditure during 2013-14           Rs. 12500 Lakhs                                            
          Expenditure during 2014-15          Rs. 61445 Lakhs                                                 Unit-4
          Expenditure during 2015-16          Rs 165255 Lakhs                                                  Boiler: Boiler erection started on 1/12/10
           Expenditure during 2016-17         Rs 109579 Lakhs                                                  TG: Condenser erection started on 11/11/11. TG Deck
           Expenditure during 2017-18                                                                           casting completed & TG erection stared on 15/05/13
           Total Expenditure                  Rs. 953779 lakhs ( up to 12/16)                                  ESP: All 4 passes are under progress.
           Zero date:                          17/11/09
*Due to insolvency problem, project activities are on hold. The commissioning schedule will be decided after restart of work.
                                                                                     62
                                   Unit                     Commissioning Schedule
Sl.         Project Details               Capacity                                                                      Broad Status
                                                       Original Actual(A)/ As
No.                                        (MW)
                                                                         Expected
                                                     Synch/ COD     Sync/.        COD
                                                     Comm           Comm
 4 Salora TPP                      U-1      135       06/11  -   04/09/13(A) 01/05/14(A)                 Unit-1
   (Katghora Tal; Distt.                              06/11      10/04/ 14(A)                          COD achieved on 01/05/14. Commissioned on
    Korba)                         U-2      135       09/11  -    Uncertain    Uncertain               10/04/14. Unit synchronized on 04/09/13.
   M/s Vandana Vidyut Ltd                             09/11
                                                                                                          Boiler:
      (2x135=270MW)                                                                                    Erection of Boiler-1 started in 11/10. Boiler Drum
                                                                                                       lifted on 23/02/11. HT completed on 28/01/12. BLU
      Original / Latest Cost      :Rs 1458.44 Cr./ Rs. 1458.44 Crs.                                    completed on 06/03/13. SBO completed. TG: TG
      Exp. During 2009-10          :Rs 14441 lakhs                                                     erection started in 11/11and TG box-up completed
      Exp. During 2010-11          : Rs . 43617 lakhs                                                  in 07/12.
      Exp. During 2011-12          : Rs . 88942 lakhs
      Exp. During 2012-13          : Rs . 38000 lakhs                                                 Unit-2
      Exp. During 2013-14          : Rs . 38657 lakhs                                               Boiler:
      Exp. During 2014-15          : Rs.15032 lakhs                                                  Boiler erection started in 11/10 and drum lifted in
                                                                                                     04/11. HT completed in 10/12. BLU completed in
      Cumm. Exp. ( up to 03/15) : Rs.238689 lakhs                                                    09/14 and steam blowing completed in 10/14.
      BOP Package               LOA has been issued on 21/11/08 on M/s Cethar Vessels                Delay due to supply of boiler material & CHP
                                Ltd , Thiruchirapalli on BTG basis , Boiler : Cethar                 material by M/s Cethar Vessels Ltd.and delay in
                                Vessels Ltd, Turbine Genarator: M/s Harbine Turbine                  getting of startup power. Delay due to agitation by
                                Co.Ltd, China                                                        the villagers at project site.
      Power Evacuation system       PGCIL granted LTOA & BPTA executed on 24/02/10.                   Chimney: Flue can erection completed.
                                    LILO line construction is completed. Elect. Inspectorate          CHP: Under progress.
                                    ,CEA (WR) has given approval for LILO and 400 kV                  AHP: Under progress.
                                    switchyard on 04/08/12.                                           CW System: Under progress.
           Land: Land : Required 261 Ha , Possession : 260.899 Ha.
           MOE&F: obtained on 09/06/09.and State pollution clearance obtained on
               09/03/09
           Civil Aviation: clearance obtained on 24/04/09
           Water: 18 MCM Water allocated by WRD, Govt.of C.G from Hasdeo River
           Coal linkage: Allocation of coal is from Fatehpur East Coal Block ( Jointly)
               allotted by MOC and tapering coal linkage granted for 2x135 MW on 29/01/10
               from SLC, LT meeting of MOC, for 2nd phase of 1x270 MW under process
               with MoC. Carpet coal recommended for CEA for startup of 1 st unit.
Critical issues       Start up / carpet coal MOU is pending with SECL. FSA execution is pending with SECL
                      Turbine -2 was ready from last 9 months ( as on 09/14), Foe commissioning HEC/HTC Engineers are required. AVR Feed back
                      Card- pending from long time, LVDT replacement- All the LVDT are not working. Rotor stoppage alarm panel to be supplied,
                      supply of Technical data sheet of TG instruments and ISCAN-2 for Unit-2 as per letter dated in 09/14
Reasons for Delay     Delay in commissioning of U-1.Agitation by villagers at site. Delay in sullpy of BTG and CHP material. Non corporation of BTG
                      supplier in commissioning activities. Acquisition for railway siding and ash pond.
                                                                          63
                                               Unit                        Commissioning Schedule
Sl. No.            Project Details                     Capacity                                                            Broad Status
                                                        (MW)        Original   Actual(A)/ As
                                                                                      Expected
                                                                   Synch Comm     Syn.       Comm
                                                                                              COD
  5        Deveri TPP Raigarh TPP             U-1         600      06/13 08/13 Uncertain    Uncertain          Unit-1
           (Visa)                                                                                             Boiler:
          (VISA Raigarh STPP, Ph-I,)           U-2        660                     Uncertain   Uncertain        Boiler erection started on 30/09/11. 8th tier
          (Distt: Jangir Champa)                                                                               erection completed. Ceiling girder A, B, C, D,
           M/s VISA Power Ltd.                                                                                 E& F erection completed. Work held up due
                                                                                                               to financial Problems.
          (1x600+1x660=1260MW)
          Org. Est. cost for both the units :Rs. 619000 Lakh                                                   TG:
                Unit-1 cost                   : Rs. 261870 lakhs                                                TG deck raft completed and shuttering work
          Unit-1 Latest cost                  ; Rs. 393000 lakhs                                                final deck casting U/P. EOT crane erected
          Exp. During 10-11                   : Rs. 51763 lakhs                                                 and commissioned.
          Exp. During 11-12                   : Rs. 53457 Lakh                                                 ESP: Pass A casing erection work completed.
          Exp. During 12-13                   : Rs. 15481 Lakh                                                  Suspensions      for    electrodes   erection
          Exp. During 13-14                   : Rs. 47890 Lakh                                                  completed. Erection of collecting electrodes
          Exp. During 14-15                   : Rs. 36759 Lakh                                                  up to 10th field completed. Hopper top part
           Exp. During 15-16 ( Up          to : Rs. 2373 Lakh                                                   erection completed in all 10 fields.
          11/15)                                                                                              Pass B: Column erection work completed.
                                                                                                               Pass-C- electrode erection completed in all 10
              Cumm. Exp            (11/15)    : Rs. 207723 lakhs
                                                                                                               fields.
            Approval date:                                                                                    Pass D: Casing erection completed. electrode
            Zero date:                         09/08/10                                                   erection
           Financial closure                 Achieved for both the units
           Main Plant Order                 BTG Contract awarded on 28/06/10 to M/s BHEL (Boiler-
                                            BHEL) (TG- BHEL)                                               BoPs:
        BOP Package                        The order for all the BOPs on EPC basis including civil works
                                            have been placed on M/s L&T on 29/09/10. BHEL (Trichy)            Chimney: Foundation works completed and
                                            supplied 13031 MT for Boiler & BHEL(Ranipet) 7340MT for            shell casting work U/P. Chimney awarded to
                                            ESP up to 11/2014 out of which 5792 MT of Boiler & 3749            Bygging India Ltd on 15/01/15
                                            MT of ESP erected. BHEL (PSWR) supplied 3863 MT of                CHP: PCC in wagon tippler & TP-2 area is
                                            bunker structure material, out of which 2261 MT bunker             U/P.
                                            structure fabricated. BHEL piping center (Chennai) supplied        Coal Mill & Mill Bunker Building: All mill
                                            1235 MT                                                            foundation & bunker pedestal casting
        Type of fuel                        Coal                                                               completed. Bunker structure and shell
                                                                                                               fabrication under progress.
        PPA                                 PPA Signed with CSPTCL & WBSEDCL for 424 MW & 200
                                                                                                              Raw Water Supply System: Raw Water pipe
                                            MW and WBSEDCL for 200MW.
                                                                                                               line awarded to TATA Projects Ltd. On
                                            As per letter dated 14/01/14
                                                                                                               14/07/11
                                            PPA signed with WBSDCo. Ltd on 04/01/11 for 510 MW for
                                            20 years through MOU route with 3part tariff (Cap. Charges+       CW System: Raw Water pipe line awarded to
                                            energy Charges+ transportation charges). CSPTCo.Ltd an             TATA Projects Ltd. On 14/07/11
                                            authorised representative of GOCG to execute PPA with
                                            Developers on behalf of the GOCG. This PPA is in line with        IDCT: CT awarded to Paharpur cooling
                                            the implementation agreement executed with GOCG                    Towers 25/01/12. IDCT-I &2 excavation
        Power Evacuation system            Awarded the contract for construction of 400kV D/C                  work completed.
                                            transmission line on M/s KEC on 24/06/11. From PGCIL S/S at
                                            New Kotra. 400/765 Kv Pooling station for power evacuation –      Switchyard: Foundation works completed and
                                            bays construction given to Alstom T7D on 31/12/11.                 shell casting work U/P.
        BTPA                                24/02/10
                  Land: Delay in land acquisition & delay in placement of orders for BoPs.          Delay
                   in supply of boiler drum by BHEL. Work is on hold due to Financial crunch.
                  MOE&F: MOEF clearance obtained on 23/08/11
                   Amendment in MOEF clearance issued on 20/05/14 regarding the reduction in project
                   area of 780 acres to 637 acres.
                   Fatehpur coal block allocated to the Visa Power.
                  Civil Aviation: clearance from AAI received on 25/05/10.
                  Water: Water allocation received from WRD, Chhattisgarh for 35 MCM on 26/09/09
                  Coal linkage: Fatehpur East Coal Block jointly allotted. Domestic coal linkage
                   applied. FSA signed with Indonesian coal supplier (PT Kubara Bumi Lestari) for
                   supply of imported coal.
 Critical issues            Boiler Drum has not dispatched by the BHEL
 Reasons for Delay          Order of AHP,Fire protection system, AC & ventilation system,LT/Ht switchgear, cables, air compressor, LT transformers, station,
                            GT & unit transformer not yet placed. Work is on hold due to financial crunch.
                                                                                 64
                                          Unit                             Commissioning Schedule
 SI.          Project Details                         Capacity                                                             Broad Status
                                                                      Original         Actual(A)/ As
                                                       (MW)
                                                                                            Expected
                                                                  Synch/         COD     Sync/.     COD
                                                                 Comm                    Comm
 6        Singhitarai TPP                  U-1           600       10/14          -        *         *      Unit-1:
          ( DumatpalliTPP)                                         11/14                                    Boiler
          Janjgir (Vill)                   U-2           600       01/15     -             *         *           Boiler erection started in 29/07/12.
          Champa Distt.                                            02/15                                         Drum lifted on 07/04/13.
           (M/s Athena                                                                                           Non-Drainable HT done on 08/10/15.
          Chhattisgarh Power                                                                                     Work at site is on hold due to
          Ltd)                                                                                                   financial constraints.
          (2x600=1200MW)                                                                                    TG
          Original Cost/Latest cost   : Rs. 620000 lakhs/ Rs. 811900 lakhs (844379 l lakh further                TG erection started on 04/07/13.
                                      revised)                                                                   Condenser erection started on 16/05/13.
          Exp up to 03/2008            :Rs. 371 lakhs                                                            Work at site is on hold due to
          Exp 2008-09                  :Rs. 3509 lakhs                                                           financial constraints
          Exp 2009-10                  :Rs. 6690 lakhs                                                           .
          Exp. 2010-11                 :Rs. 56343 lakhs                                                     Unit-2:
          Exp. 2011-12                 :Rs. 50204 lakhs                                                     Boiler
          Exp. 2012-13                 :Rs: 92116 lakhs                                                          Boiler erection started on 24/12/12
          Exp. 2013-14                 :Rs: 129337 lakhs                                                         Drum lifted on 30/10/13.
          Exp. 2014-15                 :Rs: 154090 lakhs                                                         Work at site is on hold due to
          Exp. 2015-16                 :Rs: 62395 lakhs                                                          financial constraints
          Exp. 2016-17                 : Rs. 74611 lakhs                                                    TG
          Exp. 2017-18                 : Rs. 11181 lakhs                                                         TG erection started in 29/11/13.
                                                                                                                 Condenser erection started on 01/01/14.
          Cum.Exp. up to 05/17      :Rs. 640847 lakhs                                                            Work at site is on hold due to
          Zero date:                01/06/11 (NIT issued)                                                        financial constraints
          Financial closure       : Achieved (Common loan agreement signed on 30/03/11)                     BoPs:
          Main Plant Order        : Awarded on 21/12/09 to M/s DECL.
                                                                                                             Chimney: Erection of flue cans and stair
          BOP Package             M/s Abir infrastructure on 18/08/10
                                                                                                               case completed External painting
          Type of fuel              Coal                                                                       completed.
          PPA                     Long term and short term PPA signed with PTC. 444 MW signed with           CHP: Major Erection works completed.
                                    CSPT and 150 MW signed with Nepal electricity authority. For 300         AHP: Major Erection/construction works
                                    MW- LOI received & for 200 MW participated in Case-I bidding in            completed.
                                    RRVPN and 107.5MW praticipated in the case-I bid invited by MP           Raw Water Supply System: RWIS
                                    power mgmt. company ltd. For supply of 107.5MW power on the                from river Mahanadi to ACPL-contract
                                    long term bases.                                                           awarded on 16/05/11
          Power Evacuation          LTOA granted on 01/10/09. Signed BTPA with PGCIL for 683 MW                 Barrage construction completed &
          system                    24/02/10. ISTS approval received from PGCIL on                             finishing work in progress
                                    14/06/11.Approval received form MoP for construction of 400kV              NoC received from WRD, GoC for laying
                                    D/c dedicted line from ACPL to New Kotra(PGCIL). NOC for tower             of pipeline along the canal on 31/10/10.
                                    height clearance received for double and multiple circuit tower from       approval received for Nala crossing and
                                    AAI.                                                                       road crossing. RWIPH construction
                                    Test charging of 400kV transmission line-1 &2 completed.                   completed.
               Land: 927.275 acres of land in possession,25.96 Acres of Govt land leased to                 PT/ DM Plant: First stream commissioning
                 company..
               MOE&F: Obtained on 04/06/10.Amendment of EC received on 22/03/16                                done in auto mode successfully &
               Civil aviation: Clearence received from AAi, Mumbai on 09/04/09                                 commissioning of other streams are in
               Water: 35 MCM per annum allocated from Mahanadi.                                                progress.
               Coal linkage: FSA signed with SECL on 27/02/15 for supply of 2497242                         CW System: Erection of motor & pumps
                 Tonnes/annum.                                                                                  completed.
                                                                                                             CT: all works completed.
                                                                                                             FOHS: No load trail run of motors
                                                                                                               completed. Hydro test in progress for
                                                                                                               pipes.
                                                                                                             Switchyard: commissioning works are
                                                                                                               Completed.
Critical issues Delay in BTG erection work. Work at site is on hold due to financial constraints
Reasons for Delay Delay in Land Acquisition. Slow progress of boiler & TG erection. Delay due to financial problems
*Work at site is on hold due to financial constraints. The commissioning schedule will be decided after restart of work.
                                                                                 65
                                       Unit                     Commissioning Schedule
 Sl.         Project Details                  Capacity    Original      Actual(A)/ As                               Broad Status
 No.                                           (MW)                              Expected
                                                       Synch/ COD           Sync/.        COD
                                                      Comm                 Comm
7      Binjkote TPP                  U-1       300      08/13       -    26/01/17(A) 06/10/17(A) Unit-1:
       SKS power Gen. (Chhattis.)                       09/13            25/04/17(A)              COD achieved on 06/10/17. Full load
       Ltd                                                                                        achieved on 25/04/17. Syn on 26/1/17.
       Vill-Binjkote, Distt.:        U-2       300      11/13       -     12/17(A)    01/04/18(A) Boiler:
       Raigarh,                                         12/13            28/03/18(A)               Boiler erection started on 12/06/12. Boiler drum
       State-Chhattisgarh            U-3       300      02/14       -         *            *       lifted on 02/05/13. HT conducted on 27/06/14.
                                                        03/14                                      BLU completed on 09/07/16
       (4x300=1200MW)                U-4       300      05/14       -         *            *       TG :
                                                        06/14                                      Condenser erection started 04/14. TG erection
       Original Cost /Latest Cost:   : Rs. 505800 lakhs / Rs. 689000 lakhs / Rs. 794000 lakhs      started in 05/14. TG box up completed on
       Ph-I: 3787.2 Cr& Ph-II :                                                                    09/08/16.
       3106.8 Cr /Latest Cost : Ph-I
       : 5240Cr & Ph-II: 3200 Cr                                                                  Unit-2
       less 500 Cr                                                                                  COD achieved on 01/04/18. Full load
       Exp. During 2008-09            : Rs 4000 lakhs                                              achieved in 28/03/18. Syn is completed in
       Exp. During 2009-10            : Rs. 5225 lakhs                                             12/17.
       Exp. During 2010-11            : Rs. 21435 lakhs
       Exp. During 2011-12            : Rs. 55000 lakhs                                            Boiler :
       Exp. During 2012-13            : Rs. 126590 lakhs                                           Boiler erection started on 08/09/12. Boiler drum
       Exp. During 2013-14            : Rs. 46778 lakhs                                            lifted on 30/05/13. Boiler light up has
       Exp. During 2014-15            : Rs.112677 lakhs                                            completed on 27/03/17. EDTA cleaning done
       Exp. During 2015-16            : Rs. 11095 lakhs( up to 06/15)                              on 03/05/17 Steam blowing completed in 11/17.
                                                                                                   TG :
       Cumm. Exp Up to 06/15.         : Rs 382800 lakhs                                            Condenser erection started in 01/15. TG
       Approval date:                 SKS signed an MOU with Govt. of Chhattisgarh on              erection Started in 09/14. TG put on barring
                                      07/01/08.for setting up coal based TPS.                      gear on 30/08/17.
       Zero date:                    : 12/05/11
                                                                                                        Unit-3:
       Financial closure             : completed
                                                                                                        Work yet to start
       Main Plant Order              : M/s Cethar Ltd. On 02/03/11. Boiler- Cethar Ltd. trichy, India
                                       and TG - Harbin, China
                                                                                                        Unit-4:
       BOP Package                                                                                      Work yet to start
       Type of fuel                    Coal                                                             * The dates would be decided after start of
       PPA                             37.5% of 1200 MW with CSPTRADECO.                                Boiler erection start.
                                       550 MW with TPTCL. Participated for 100 MW in Case-I
                                       bidding in RVPN.                                                  BoPs:
       Power Evacuation system         Signed BPTA with PGCILon 24/02/10 for evacuation of               CHP: Ready in all respect.
                                       entire power from kotra sub-station.                              AHP: Ready in all respect.
                                                                                                         Raw Water Supply System: raw water intake
           Land: 568 acres of land acquired                                                              pump commissioned, raw water reservoir
                                                                                                          completed.
           MOE&F: obtained on 05/10/10 EC extended till 04/10/17                                        PT/ DM Plant: already commissioned.
           Civil Aviation: AAI issued NOC on 09/04/2009                                                 CW System: Ready.
          Water: 35 MCM from Mahanadi (44 Km pipeline).                                                 FOPH: Ready
          Coal linkage: Granted coal linkage for entire 1200 MW by SECL. FSA signed for U-              Switchyard: 440kV trans line charged on
                                                                                                          09/05/15. 20/6.6Kv line charged on 20/01/16
           1 &U-2 for 1.3 MTPA on 28/08/13 and 23/09/13 respectively.
Critical issues
Reasons for Delay              U-3&4: Work yet to start. Balance land acquisition for ash dyke. Commissioning schedule would be assessed after restart
                               of work.
                                                                            66
                                       Unit                         Commissioning Schedule
Sl.          Project Details                  Capacity                                                                 Broad Status
                                                            Original    Actual(A)/ As
No.                                            (MW)
                                                                                 Expected
                                                          Synch/     COD Sync/.          COD
                                                         Comm             Comm
7     Nawapara TPP (TRN TPP),          U-1       300       11/13      - 31/05/16(A) 19/08/16(A)        Unit-1
      (Distt: Raigarh)                                     12/13           14/08/16(A)                 COD achieved on 19/08/16. Commissioned on
      M/s TRN Energy Pvt Ltd.,                                                                         14/08/16. Synchronized with coal on 31/05/16.
                                       U-2       300        03/14      -   20/12/16(A)   01/05/17(A)
      Chhattisgarh                                                         18/04/17(A)
                                                                                                       Boiler
                                                            04/14                                       Boiler erection started on 01/10/12.
      (2x300=600MW)                                                                                     Boiler Drum lifted on 30/03/13.
      Org.Est. cost / Latest Cost      :Rs. 284400 Lakhs/ 372597 lakhs                                  Boiler HT completed on 28/03/14
                  Exp. During 11-12    : Rs. 27800 lakhs                                                BLU completed on 25/12/15
                                                                                                        Steam blowing completed on 07/01/16.
                    Exp during 12-13   : Rs. 40523 Lakhs
                                                                                                        Synchronized on 31/05/16
                    Exp during 13-14   : Rs. 121353 Lakhs
                                                                                                        Unit
                    Exp during 14-15   :Rs. 78824 Lakhs
                                                                                                       TG
                    Exp during 15-16   : Rs 35400 Lakhs                                                 Condenser erection started on 04/14.
                    Exp during 16-17   Rs. 42755 Lakhs                                                  TG erection started in 01/06/14.
                                                                                                        TG Boxed up on 08/ 12/15.
      Cumm. Exp ( 11/16)               : Rs 346655 lakhs
                                                                                                        TG put on barring gear in 12/15 insulation &
      Approval date:                                                                                    cladding work completed. Condenser charged.
      Zero date:                   27/06/11                                                        
      Financial closure            Achieved on 18/12/09                                              Unit-2
      Main Plant Order             : BTG Contract awarded on 27/01/11 to M/s China Western           COD achieved on 01/05/17. Commissioned on
                                     Power Co.Ltd.                                                   18/04/17. Synchronized on 20/12/16.
      BOP Package                     The order for main plant civil & structural work and all the
                                     BOPs on EPC basis have already been placed on M/s BGR           Boiler
                                     Energy Systems Ltd. on 09/06/11. The EPC contract covers         Boiler erection started in 06/03/13
                                     all the onshore supplies, civil works, erection and              Boiler Drum lifted on 21/09/13
                                     commissioning of the project.                                    Boiler HT completed on 28/08/15
                                                                                                      BLU completed on 23/10/16.
                                                                                                      SBO completed.
      Type of fuel                   Coal                                                            TG
                                                                                                       Condenser erection started on 08/07/15. TG
      PPA                            Entered with Chhattisgarh State Power Trading Company Ltd.
                                                                                                       erection started on 01/07/15. TG Boxed up on
                                     for 35% power in accordance with MOU with Govt. of
                                                                                                       20/11/16. TG oil flushing on 22/11/16. TG put
                                     Chhattisgarh. In case-1 bidding with UPPCL, TRN was in 2nd
                                                                                                       on Barring Gear on 24/11/16. Completed.
                                     position.(L2) for 390 MW. PPA is with PTC on take or pay
                                                                                                     BoPs:
                                     basis. As per Letter dated 13/01/14
                                     Signed back to back PPA with PTC for supply of 390 MW to
                                                                                                      Chimney: All work completed.
                                     UPPCL on 25/07/13 and 5% of net power i.e 30 MW to be
                                     signed with CSPTCo. Ltd.                                         CHP: All work completed.
                                     As per Letter dated 28/04/16                                     AHP: All work completed.
                                    Already signed PPA for sale of 5% of net power with
                                     C.S.P.T.Co on 26/05/15. Further, signed with UPPCL for sale  Raw Water Supply System: Ready
                                     of 390 MW .                                                      CW System: For both units completed.
      Power Evacuation system        BPTA has signed with PGCIL for Raigarh Pooling Station           IDCT-I: commissioned
                                     (Tamnar) on 11/04/11 for 400 MW.                                 IDCT-II: Work in progress
          Land: Land is in possession.                                                               PT & DM Plant: commissioned.
          MOE&F: clearance has been received on 18/03/11                                             FOHS: LDO & HFO system operational.
          Civil Aviation: Clearance received on 24/02/12                                             Switchyard: Switchyard charged.
          Water: 19 MCM has been allocated by W.R. Dept., Chhattisgarh.
          Coal linkage: FSA signed on 23/11/2013
Critical issues
Reasons for Delay       Delay in start of Civil works. Slow progress in erection works of Boiler and T.G. Manpower shortage.
                                                                            67
                          BROAD STATUS OF THERMAL POWER PROJECTS IN GUJARAT
                              Unit                     Commissioning Schedule
Sl.     Project Details                  Capacity                                                                      Broad Status
No.                                       (MW)        Original Actual(A)/ As
                                                                   Expected
                                                     Synch/ COD Synch/ COD
                                                    Comm        Comm
 State Sector
 1. Wanakbori TPS               8          800       07/18   10/18   03/19    03/19      Unit-8
     Extn.                                           10/18           03/19               Boiler
     GSECL,                                                                             Boiler civil works started on 17/10/15. Boiler erection started on
     Dist: Kheda                                                                        25/02/16. All the 7 ceiling Girders lifting completed on 17/01/17. Pressure
    Gujarat                                                                             parts erection is in progress. Drainable Hydro test completed on
                                                                                        12/01/2018. Boiler light up on 30/07/2018. Steam Blow Off completed
      (1x800=800MW)                                                                     on 31.01. 2019. Synchronisation is planned in March, 2019.
       Original /Latest Cost            : Rs.353651 Lakh / Rs 353651 Lakh               TG
      Expenditure during 2014-15      : Rs.12701 Lakh                                   TG civil works started on 21/12/15. Condenser erection started on
      Expenditure during 2015-16      : Rs.48760 Lakh                                   22/12/16 (outside assembly). TG Deck casting completed on 01/08/17.
      Expenditure during 2016-17      : Rs.150651 Lakh                                  TG erection started on 31/08/17. Main Turbine trial on barring gear
      Expenditure during 2017-18      : Rs.117495.59 Lakh                               carried out on 29.12.2018. TG Box Up is done on 28/12/18.
      Expenditure during 2018-19      : Rs 34297.24 Lakh
       (Upto 01/19)                                                                     BoPs:
       Total Expenditure                 : Rs. 363904.83 Lakhs (Upto 01/19)
                                                                                             Chimney: Chimney RCC works for Shell casting work completed.
       Approval date:                  ;NA
                                                                                              Beam erection completed. Flue erection completed. Outside
       Zero date:                    : 21/10/14                                               chimney painting work completed.
       Notice To Proceed (NTP)       :                                                       CHP: In this package order for Civil works is with Bridge & Roof
       Financial closure              Completed                                           (I) Pvt Ltd. The mechanical work is with M/s GMW. The contractors
                                                                                          have mobilized the site and civil –mech works are in progress. Rail
       Main Plant Order                 : 21/10/14. on M/s BHEL, EPC basis
                                        Boiler: Alstom Power INC                            lying work under progress.
                                        TG: Siemens AG Germany                               AHP: Order has been placed on M/s Macawber Beekay for
       BOP Package                    : BHEL, EPC                                           Mechanical and M/s GMW for structural work. The order for civil
                                                                                            works is with M/s Bridge & Roof (I) Pvt. Ltd. and is in progress.
       Type of fuel                   : Coal
                                                                                            Equipment supply started. All pumps erected. Piping work under
       PPA                            :PPA signed on 01/01/2011 with GUVNL.                 progress.
       Source and supply of Fuel      : Gare Plama Coal Block, Chhattisgarh                 Raw Water Supply System: Order placed to M/s Chembond
       Power Evacuation system                                                            Solenis Water Technologies Ltd for Erection & Commissioning.
         All mandatory clearances are available.                                           Fire Protection System: Fire water pump, jockey pump, hydrant
         BoPs orders placed by BHEL.                                                     spray pump and placed at site decouple trial taken. Foam system
         Power evacuation system readiness is expected 6 months before COD.              erected, trial pending.
         Topographical & Soil investigation work is completed.                                PT/ DM Plant: Order for DM plant has been placed on M/s. Aqua
         Order for Site grading work is placed by BHEL and work has been                   Design India Pvt. Ltd for Erection & Commissioning. PTP order is
           completed.                                                                       with M/s Pennar Enviro Ltd; DM building civil works are in progress.
           Work contracts for Material management, Storage yard Development                (initially treated water has to be arranged from existing plant) Filter
           and construction power distribution are awarded by BHEL.                         backwash sump completed.
         LOI for RCC Chimney placed on M/s Bygging India Ltd.on 11/06/15.                  CW System: The order has been placed on M/s Chembond Solenis
         BHEL issued order for civil work to M/s BJCL for Boiler to Chimney              Water Technology. CW treatment plant inside civil work completed
           area.                                                                          The work is progressing as per schedule.
                                                                                         NDCT: The order placed on M/s NBCC. Recker columns completed.
                                                                                          Shell casting started and further work in progress.
                                                                                         Switchyard: Order placed on M/s Teknow Overseas Private Ltd.
                                                                                          Civil work of Switch yard (400 KV Extn. & 400 KV switch yard
                                                                                          outside GIS) are in progress. AIS/GIS Switchyard Tie line -I and ST
                                                                                          charged through BUS-I.
                                                                                            Tender for EPC contract for FGD uploaded on 20/09/17; t
                                                                                               completed. 3 FGD Plant - Corrigendum –XVI issued: Price
                                                                                               Bid opened and further step under process.
                                                                                  68
               BROAD STATUS OF THERMAL POWER PROJECTS IN MADHYA PRADESH
                           Unit                          Commissioning Schedule
Sl.     Project Details            Capacity                                                                           Broad Status
No.                                 (MW)         Original     Actual(A)/ As
                                                                      Expected
                                                Synch/    COD    Synch/        COD
                                               Comm              Comm
 State Sector
 1. Shree Singaji           3         660        03/18    07/18 27/04/18(A)   18/11/18       Unit-3:
     TPP, Stage –II                              05/18          14/08/18(A)     (A)          COD achieved on 18/11/18. Commissioned on 14/08/18.
      (At Dongalia                                                                           Synchronisation done on 27/04/18.
     Distt. Khandwa),                                                                       Boiler: Boiler erection started on 18/06/15. Pressure parts erection
     MPPGCL                 4         660        07/18    11/18 27/12/18(A)       03/19     completed. Boiler HT completed on 31/03/17. BLU achieved on
       (2x660=1320MW)                            09/18             03/19                    24/01/18. Synchronisation done on 27/04/18. Full load achieved on
       Original /Latest Cost         : Rs.650000 lakhs / Rs.773800 lakhs                    14/08/2018.
      Expenditure during 2013-14   : Rs 117 lakhs                                           TG: TG deck casting completed on 30/04/16. Condenser erection
      Expenditure during 2014-15   : Rs 46488 lakhs                                         started on 11/07/16.TG erection started on 24/11/16. TG box up
      Expenditure during 2015-16   : Rs 56475 lakhs                                         completed on 30/11/17. TG put on BG in 12/17.
      Expenditure during 2016-17   : Rs 159878 lakhs
      Expenditure during 2017-18   : Rs 206337 lakhs                                        Unit-4:
      Expenditure during 2018-19   : Rs 116964 lakhs                                        Boiler: Boiler erection started on 27/10/15. Boiler HT (D)
       Total Expenditure             : Rs. 586259 lakhs                                     completed on 27/07/17. Boiler light up achieved on 24/10/2018.
       (Upto 01/19)                                                                         Steam Blowing started on 27/10/18 and completed on 25/11/18.
       Approval date:               : NA                                                    Test Synhronisation has been done on 27/12/18. Full Load has
                                                                                            been achieved on 26/02/19.
       Zero date:                   :31/12/14.
                                                                                            TG: TG deck casting completed. Condenser erection started on
       Notice To Proceed           :31/12/14                                                02/02/17. TG erection started on 30/05/17. TG boxed up on
       (NTP)                                                                                30/03/18. Over Speed Test of Turbine has been done on 27/12/18.
       Financial closure            : Achieved in 03/15                                     Safety Valve setting done successfully on 11.01.19.
       Main Plant Order              : EPC on M/s L&T on 31/12/14                           Availability of start up power is done on 29/08/17.
       BTG Make                      : L&T/MHI
       BOP on EPC basis            :M/s L&T on 31/12/14
                                                                                            BOPs:
       Type of fuel                  Coal
       PPA                         :With MPTradco (now known as MPPMC) on                       Chimney: Ready for both Units
                                     04/01/2011.                                                CHP: Equipments commissioning and trial run is in
       Source and supply of        : Gondbahera-Ujjaini coal block having 5.32 MT reserve        progress.
       Fuel                          to MPPGCL on 07/06/13.                                     AHP: Equipments erection and commissioning is in
       Power Evacuation                                                                          progress.
       system                                                                                   Raw Water Supply System: Functional.
           Land: Available.                                                                    PT/ DM Plant: Functional
           Mega Power Status: : Obtained on 05/07/12.                                          CW System: Civil work completion is in final stage and
           MoEF: : Received on 27/08/14.                                                        laying of CW pipeline completed. Unit # 3 CW system
           Project Consultant: M/s Lahmeyer International (I) Ltd, Gurgaon                      already charged.
           Design and Engineering works under progress.                                        NDCT: Unit#3 Functional, Unit#4 50% Functional and 50%
           Consent to Operate U-3 granted by MPPCB, Bhopal on 14/04/2018                        Ready.
                                                                                                FOPH: Ready.
                                                                                                Switchyard: Switchyard charged. Unit # 3 on load & Unit #
                                                                                                 4 Synchronized with grid on 27/12/18.
                                                                                                FGD: Present Project Consultant to be continued. Site
                                                                                                 selection made. Tender is invited on ICB basis & Published
                                                                                                 on 20th Jun'18. Pre bid conference held on 24th Sept. 2018.
                                                                                                 Due to closing of old E-Procurement Portal, a fresh tender is
                                                                                                 to be floated and under process. Date of Award expected by
                                                                                                 June 2019.
Critical issues       First stage Forestry clearance of Gonbahera Coal Block by MoE&F
                      Power evacuation is yet to be completed by MPPTCL.
Reasons for Delay
                                                                              69
                                Unit                             Commissioning Schedule
Sl.        Project Details               Capacity                                                                              Broad Status
No.                                       (MW)            Original    Actual(A)/ As
                                                                             Expected
                                                       Synch/     COD    Synch/       COD
                                                      Comm               Comm
 Private Sector
 1. Mahan TPP                     1         600          07/11    09/11 24/12/12 (A) 29/04/13 (A) Unit-1
     (Dist. Singrauli)                                   09/11          25/02/13 (A)              COD achieved on 29/04/13. Commissioned on 25/02/13.
    Essar Power MP Ltd.                                                                           Synchronized on 24/12/12.
      (2x600=1200MW)
                                  2         600          10/11    12/1107/17 (A) 06/10/18 (A) Boiler: Boiler erection started in 09/09. Boiler drum lifted on
                                                         12/11        26/09/18 (A)            21/06/10. HT done in 08/11. BLU done in 31/3/12. SBO
                                                                                              completion on 21/08/12.
       Original/Latest Cost               : Rs. 773800 Lakhs/ Rs. 773800 Lakhs                TG: TG erection started in 11/10. TG box up completed on
      Expenditure during 2006-07        : Rs      155 Lakhs                                   24/09/12. TG oil flushing completed in 11/12. TG on barring
      Expenditure during 2007-08        : Rs 36609 Lakhs                                      gear on 07/12/12.
      Expenditure during 2008-09        : Rs 38189 Lakhs
      Expenditure during 2009-10        : Rs 114755 Lakhs                                     Unit-2
      Expenditure during 2010-11        : Rs 335735 Lakhs                                     COD achieved on 06/10/18. Commissioned on 26/09/18.
      Expenditure during 2011-12        : Rs 12807 Lakhs                                      Synchronized in 07/17.
      Expenditure during 2012-13        : Rs 92434 Lakhs
      Expenditure during 2013-14        : Rs 8953 Lakhs                                       Boiler: Boiler erection started in 06/10. Boiler drum lifted in
      Expenditure during 2014-15        : Rs 110285 Lakhs                                     01/11. HT done in 02/12. BLU achieved on 14/05/17. SBO
      Expenditure during 2015-16        : Rs 55987 Lakhs                                      completed in 06/17. Full load achieved on 26/09/18.
      Expenditure during 2016-17        :Rs 18654 Lakhs                                       TG: Condenser erection started in 03/11. TG erection started in
      Expenditure during 2017-18        :Rs -       Lakhs                                     03/11. TG Box up completed in 07/17. TG oil flushing
                                                                                              completed in 07/17. Syn. achieved in 07/17. Coal firing is
       Total Expenditure                  : Rs 815610 Lakhs (Upto 03/17)                      completed in 08/17.
       Approval date:                     :NA                                                 BoPs:
       Zero date:                         :24/08/07                                                  As the unit-1 of the project has already been commissioned
       Notice To Proceed (NTP)          :24/08/07                                                    and BoPs are common for both the units.
       Financial closure                  : 21/01/2009
                                                                                                           Chimney: Already completed
       Main Plant Order                   :BTG order placed on M/s Harbin Power Co. Ltd,                   CHP: Second stream of the CHP is already ready
                                          China on 24/08/07.                                               AHP: U-2 AHP is ready
       BTG Make                           :Chinese                                                         Raw Water Supply System: Ready
       BOP Package                      : Reputed Indian Vendors                                           PT/ DM Plant: PT plant ready. DM Plant also
       Type of fuel                       :Coal                                                          commissioned.
       PPA                              : Long Term PPA with ESIL for 200 MW and 55.5 MW                   CW System: Ready
                                          with Govt. of MP (on variable charge basis). For tie up          CT: : Commissioned.
                                          of balance capacity of 855 MW, company is                        FOPH: Completed.
                                          participating in various competitive bids/merchant               Switchyard: Completed in all respects.
                                          power.
       Source and supply of Fuel          : Mahan Coal Block allotted jointly to ESSAR and
                                          Hindalco had been cancelled on 24/09/14.
                                        Essar has signed CMPDA with GOI on 2/3/2015 for
                                          Tokisud Coal Mine located in the State of Jharkhand
                                          post e-auction. Vesting order is awaited. As per
                                          present mining plan, peak capacity of production of
                                          the mine is 2.32 MTPA.
       Power Evacuation system             :1st unit commissioned by LILO (Temp arrangement).
                                           Long term open access granted by PGCIL through
                                           Mahan-Sipat line.
             MOEF clearance: 20/04/07
             Water: 0.058 MAF/year from Rihand Reservoir.
             SPCB: Obtained on 03/03/09.
             Civil Aviation Clearance: Obtained on 02/02/2007.
             Land: Physical possession of 185.81 Ha. Govt. Land is available.167.32 Ha. Pvt.
              Land in Viil. Bandhora, 150.31 in Nagwa Vill. 79.08 Ha in Kharahi. For 4th viilage
              Karsualal(100.17 Ha.) compensation distribution is in progress.
Critical issues          In lieu of cancellation of captive coal block, Coal linkage (5.5 MTPA) or any other coal sourcing is essential to run the plant. Return of
                         expenditure incurred on Mahan Coal Block.
Reasons for Delay           Delays primarily due to financial constraint with the developer.
                                                                                       70
                            Unit                 Commissioning Schedule
Sl.       Project Details          Capacity                                                               Broad Status
                                               Original Actual(A)/ As
No.                                 (MW)
                                                            Expected
                                              Synch/ COD Synch/     COD
                                              Comm       Comm
 Private Sector
 2. Gorgi TPP               1         660      05/13 07/13       Uncertain        Unit-1
    (Dist. Singrauli)                          06/13                              The site enabling activities like area grading etc has already
    DB Power (MP)                                                                 completed. Construction of administrative building and hostel
     Ltd.                                                                         facility also completed. Excavation work in water reservoir area
    (1x660=660MW)                                                                 and chimney also started. Erection yet to be started. Work is on
      Original/ Latest Cost          : Rs.394100 Lakhs / Rs.394100 Lakhs          hold at site due to Financial crunch being faced by the
                                     :                                            developer.
      Expenditure during 2008-09   : Rs. 349 Lakhs
      Expenditure during 2009-10   : Rs. 2303 Lakhs
      Expenditure during 2010-11   : Rs. 13487 Lakhs                              BoPs:
      Expenditure during 2011-12   : Rs. 21157 Lakhs
      Expenditure during 2012-13   : Rs. 4036 Lakhs                                  In BoPs work yet to start.
      Expenditure during 2013-14   : Rs. 4712Lakhs
      Expenditure during 2014-15   : Rs. 1614 Lakhs
      Expenditure during 2015-16   : Rs. 78 Lakhs (upto 09/15)
       Total Expenditure           : Rs 47579 lakhs
       (Upto 09/15)
       Approval date:               : NA
       Zero date:                   : 03/11
       Notice To Proceed (NTP)     :03/11
       Financial closure            Achieved in 03/2011 for unit-1
       Main Plant Order             BHEL on 03/11 (BTG).
       BTG Make                     BHEL
       BOP Order                   Indure Pvt. Limited.
       Type of fuel                 :Coal
       PPA                         35% with MPPMC from 2x660 MW
       Source and supply of        2.1048 MTPA available for unit-1.
       Fuel
       Power Evacuation             PGCIL has granted LTA and connectivity.
       system                       Power evacuation at vindhyachal pooling
                                    station.
          Consultant: Desein
          MOEF Clearance: Obtained in Sept.10 for 1st unit.
          Land : 735-acre land is acquired.
          Water: 25 MCM PA water from Gopad river for 2x660 MW.
          All the mandatory clearances are available for two units.
          The major part of total land acquired by the company in time but
           delay in granting government land which is significant stretches had
           affected the contiguity and due to which construction could not
           commence at desired time.
          PPA has been signed with MP Power Management Company (State
           Utility) for 35% capacity from both the 2x660 MW.
Critical issues        Acquisition of balance land.
Reasons for Delay        Financial Costraints
                                                                           71
                          Unit                 Commissioning Schedule
Sl.     Project Details          Capacity                                                             Broad Status
                                             Original Actual(A)/ As
No.                               (MW)
                                                          Expected
                                            Synch/ COD Synch/     COD
                                            Comm       Comm
 Private Sector
 3. Niwari TPP              2       45       04/14 05/14     Uncertain       Unit-2
     (Dist.                                  05/14                           Boiler erection started in 01/13. Drum lifted in 08/13. Presently
     Narsinghpur)                                                            work at site is on hold.
     BLA Power Ltd.
     (2x45=90 MW)                                                            * Assessed after restart of work.
     Original / Latest COst       : Rs.23249 Lakhs / Rs.25049 Lakhs
    Expenditure during 2010-11  : Rs. 5100 Lakhs                             BoPs:
    Expenditure during 2011-12  : Rs. 16880 Lakhs
    Expenditure during 2012-13  : Rs. 5164 Lakhs                                 Presently work at site has been put on hold.
    Expenditure during 2013-14  : Rs. 354 Lakhs
    Expenditure during 2014-15  : Rs. 1503 Lakhs (upto 03/15)
     Total Expenditure          : Rs. 29001 lakhs (Upto 03/15)
     Approval date:               : NA
     Zero date:                   : 04/11
     Notice To Proceed (NTP)    :04/11
     Financial closure            Achieved.
     Main Plant Order             Boiler(ISGEC) in 02/11.Turbine and
                                  Generator (Siemens) in 04/11.
      BTG Make                    Siemens
      BOP Order                 -
      Type of fuel                Coal
      PPA                       30% with MPPTCL and 5%with MP
                                  government on variable cost.
      Source and supply of         FSA signed with BLA industries Ltd. on
      Fuel                         25/04/11 for 350000 tonnes per annum.
                                   Amendment to fuel supply agreement
                                   signed with BLA industries on 26/03/13
                                   for the following quantities—
                                   U-1x45 MW=187000 tonnes/annum,
                                U-2x45 MW=374000 tonnes/Annum.
      Power Evacuation             PGCIL has granted LTA and connectivity.
      system                       Power evacuation at vindhyachal pooling
                                   station.
        MOEF Clearance: Obtained on 07/11/07.
        Land: 129.15 Acres of land is acquired for 3x45 MW.
        Water: 7 MCM PA water from Narmada river for 140 MW.
                                                                     72
                 BROAD STATUS OF THERMAL POWER PROJECTS IN MAHARASHTRA
                              Unit                 Commissioning Schedule
Sl.      Project Details             Capacity                                                                 Broad Status
                                                  Original Actual(A)/ As
No.                                   (MW)
                                                              Expected
                                                 Synch/ COD Synch/ COD
                                                Comm        Comm
 Private Sector
 1. Amravati TPP , Ph-II,      1       270         05/14 08/14     @        @       @: Work is on hold (since April,2012)
    (Distt: Amravati)                              07/14
    M/s RattanIndia            2          270      07/14 10/14     @        @       Unit-1
     Power                                         09/14                            Boiler
     Ltd.(Formermerly          3          270      09/14 12/14     @        @       1. Boiler erection started on 24/11/11.
     known as Indiabulls                           11/14                            2. Work is on hold.
     Power Ltd.)               4          270      11/14 02/15     @        @
    (5x270=1350 MW)                                01/15                            Unit-2
                               5          270      03/15 04/15     @        @       Boiler
       Original/Latest Cost          : Rs.664600 Lakh/: Rs.664600 Lakh              1. Boiler erection started in 01/12.
      Expenditure during 2011-12     : Rs. 49727 Lakhs                              2. Work is on hold
      Expenditure during 2012-13     : Rs.20866 Lakhs
      Expenditure during 2013-14     : Rs.3397 Lakhs                                Unit-3
      Expenditure during 2014-15     : Rs.2390 Lakhs                                Boiler
       Total Expenditure             :Rs 76380 Lakhs(Upto 03/15)                    Work is on hold.
       Approval date:                :NA
                                                                                    Unit-4
       Zero date:                    11/10/10
                                                                                    Boiler
       Notice To Proceed (NTP)       :11/10/10                                      Work is on hold.
       Financial closure               : Achieved on 01/02/11
       Main Plant Order                : BTG on EPC basis awarded to                Unit-5
                                         BHEL on 11/10/10.                          Boiler
       BTG Make                      BHEL                                           Work is on hold.
       Type of fuel                  Coal
                                                                                    BoPs:
       PPA                           No PPA
       Source and supply of          :With MCL & WCL in 11/10(LOA) .
                                                                                        Work is on hold.
       Fuel
       Power Evacuation            : Through 400kV/765KV Akola and Wardha
       system                        Substations of MSETCL through
                                     400KV/765KV D/C transmission line.
              FSA: Letter awaited.
              All clearances are available.
Critical issues
Reasons for Delay      Due to financial constraints project has been put on hold.
                                                                           73
                              Unit                           Commissioning Schedule
Sl.      Project Details                 Capacity                                                                           Broad Status
No.                                       (MW)        Original  Actual(A)/ As
                                                                       Expected
                                                     Synch/ COD    Synch/       COD
                                                    Comm           Comm
 Private Sector
     Nasik TPP, Ph-I             1         270       12/11    03/12 24/02/14(A) 29/03/14 (A)    Unit-1
     (Distt: Nasik)                                  02/12           25/02/14(A)                 COD achieved on 29/03/14. Commissioned on 25/02/14. synch.
    M/s Sinnar Thermal           2         270       02/12    05/12 21/03/16 (A)      -         achieved on 24/02/14.
     Power Ltd.                                      04/12           15/02/17(A)                Boiler:
     (Formerly known as          3         270       04/12    07/12 04/17(A)          -         Boiler erection started on 03/11/10. Boiler drum lifting completed on
     Indiabulls Realtech                             06/12          14/04/17(A)                 31/03/11. Boiler HT (D) completed on 28/03/12. BLU completed on
     Ltd.)                       4         270       06/12    09/12 05/17(A)          -         22/10/12. SBO completion achieved on 15/04/13. Unit normalization
      (5x270=1350 MW)                                08/12          19/05/17(A)                 completed in 04/13.
                                 5         270       08/12    11/12 05/17(A)          -         TG:
                                                     10/12         30/05/17(A)                  TG civil works started on 01/06/10. TG erection started on 25/09/11. TG
                                                                                                Box Up completed on 30/01/13. TG oil flushing completed on 15/04/13.
       Original /Latest Cost            : Rs.678900 lakhs / Rs.784898 lakhs                     TG on BG achieved on 31/05/13. Boiler lighted up for steam dumping
                                                                                                on 22/12/13. Steam dumping started on 22/12/13. Rolling completed on
      Expenditure during 03/10          :Rs. 30620 Lakhs
                                                                                                28/12/13. Oil synch. achieved on 05/02/14. Coal bunkering started on
      Expenditure during 2010-11        :Rs. 100000Lakhs
                                                                                                10/02/14.
      Expenditure during 2011-12        :Rs. 180309 Lakhs
      Expenditure during 2012-13        :Rs. 144526 Lakhs
                                                                                                Unit-2
      Expenditure during 2013-14        :Rs 107396 Lakhs
                                                                                                Commissioned on 15/02/17. synch. achieved on 21/03/16.
      Expenditure during 2014-15        :Rs 98461 Lakhs
      Expenditure during 2015-16        :Rs --
                                                                                                Boiler:
       Total Expenditure                :Rs. 661312 Lakhs (Upto 03/15)
                                                                                                Boiler erection started on 08/12/10. Boiler drum lifting completed on
       Approval date:                   : NA                                                    27/07/11. Boiler HT (D) completed on 03/07/12. BLU achieved on
       Zero date:                       : 24/11/09                                              27/11/13. EDTA completed in 02/14. SBO started on 28/02/14 and
       Notice To Proceed (NTP)          :211/09                                                 completed on 14/03/14.
                                                                                                TG
       Financial closure                 : Achieved on 30/06/10                                 TG erection started on 25/12/11. TG Box Up completed on 08/10/13.
       Main Plant Order                  : BTG on EPC basis awarded to BHEL on 24/11/09.        TG oil flushing completed on 31/12/13. TG put on BG on 10/03/14.
                                                                                                Rolling completed on 31/03/14. Readiness of Railway siding by 03/16.
       BTG Make                       BHEL                                                      GIS clearance received in 01/16. Clearance given to BHEL to start the
       BOP on EPC basis               Reputed Indian Vendors                                    work on 10/01/16. BHEL re-started work at site on 30/01/16.
       Type of fuel                   : Coal
       PPA                            No PPA                                                   Unit-3
                                                                                                Commissioned on 14/04/17.
       Source and supply of Fuel        : From SLC (LT) on 17/12/08.                           Boiler
       Power Evacuation system        : Through 400kV D/C quad Moose transmission line          Boiler erection started on 12/01/11. Boiler drum lifting completed on
                                        upto MSETCL sub-station at Bhubaneshwar.                12/12/11. Boiler HT completed on 30/10/13. BLU achieved on
                FSA: With MCL, SECL & WCL on 11/06/09. All clearances are available.           03/10/16.SBO completed on 06/12/16.
                Design & Engineering completed.                                               TG
                The BOPs are common for all the five units. All the BoPs are either already    TG erection started on 19/01/12. TG boxed up in 10/16. TG put on BG
                 completed or nearing completion.                                               on 27/01/17.TG rolling done on 04/03/17
                                                                                               Unit-4
                                                                                                Commissioned on 19/05/17.
                                                                                               Boiler
                                                                                                Boiler erection started on 16/05/11. Boiler drum lifting completed on
                                                                                                23/12/11. Boiler HT is completed in 11/16. BLU achieved on 30/12/16.
                                                                                                SBO completed on 13/02/17..
                                                                                               TG
                                                                                                TG erection started in 05/12. TG box up completed on 24/01/17. TG oil
                                                                                                flushing completed on 12/03/17. TG put on BG on 29/03/17.
                                                                                               Unit-5
                                                                                                Commissioned on 30/05/17.
                                                                                               Boiler
                                                                                                Boiler erection started on 16/06/11. Boiler drum lifting completed on
                                                                                                06/03/12.BLU achieved on 15/02/17. EDTA completed on 06/03/17.
                                                                                                SBO completed on 24/03/17.
                                                                                               TG
                                                                                                TG erection started on 30/04/16. TG Box Up completed on 13/02/17.
                                                                                                TG oil flushing completed on 17/04/17. TG put on BG on 28/04/17.
BoPs:
                                                                                    74
                              Unit                      Commissioning Schedule
Sl.      Project Details               Capacity                                                                          Broad Status
No.                                     (MW)         Original    Actual(A)/ As
                                                                      Expected
                                                    Synch/   COD   Synch/      COD
                                                   Comm            Comm
 Private Sector
     Nasik TPP , Ph-II          1         270       01/13 04/13         @        @        @: Work is on hold (May, 2012). Schedule will be decided after restart of
     (Distt: Nasik)                                 04/13                                 work at site.
     M/s Sinnar                 2         270       03/13 06/13         @        @
     Thermal Power                                  06/13                                 Unit-1
     Ltd. (Formerly             3         270       05/13 08/13         @        @        Boiler
     known as                                       08/13                                 Boiler erection started in 09/11. Work is on hold.
     Indiabulls                 4         270       07/13 10/13         @        @        Unit-2
     Realtech Ltd.)                                 10/13                                 Boiler
      (5x270=1350 MW)           5         270       09/13 12/13         @        @        Boiler erection started in 11/11. Work is on hold.
                                                    12/13                                 Unit-3
       Original /Latest Cost          : Rs.678900 lakhs / Rs.678900 lakhs                 Boiler
                                                                                          Work is on hold
      Expenditure during 03/10        : Rs.36805 Lakhs
                                                                                          Unit-4
      Expenditure during 2010-11      : Rs. 10000 Lakhs
                                                                                          Boiler
      Expenditure during 2011-12      :Rs. 5339 Lakhs
                                                                                          Work is on hold
      Expenditure during 2012-13      :Rs. 9615 Lakhs
                                                                                          Unit-5
      Expenditure during 2013-14      :Rs. 5022 Lakhs
                                                                                          Boiler
      Expenditure during 2014-15      :Rs. 4400 Lakhs
                                                                                          Work is on hold
       Total Expenditure              :Rs. 71181Lakhs
       (Upto 03/15)
                                                                                          BoPs:
       Approval date:                 : NA
       Zero date:                     : 24/11/09                                               Work at site has been put on hold since long back.
       Notice To Proceed (NTP)        : 24/11/09
       Financial closure                : Achieved on 30/06/10
       Main Plant Order                  : BTG on EPC basis awarded to BHEL on
                                         24/11/09
       BTG Make                        BHEL
       BOP on EPC basis                Reputed Indian Vendors
       Type of fuel                    Coal
       PPA                             No PPA
       Source and supply of Fuel         : From SLC (LT) on 17/12/08.
       Power Evacuation system         : Through 400kV D/C quad Moose transmission line
                                         upto MSETCL sub-station at Bhabaleshwar.
                FSA: With MCL, SECL & WCL on 11/06/09.
                All clearances are available.
                                                                                 75
                               Unit                   Commissioning Schedule
Sl.      Project Details              Capacity                                                                          Broad Status
No.                                    (MW)          Original   Actual(A)/ As
                                                                   Expected
                                                  Synch/     COD Synch/ COD
                                                 Comm            Comm
 Private Sector
    Lanco Vidarbha TPP           1       660       03/14     08/14      *         *      Unit-1
     (Distt: Wardha)                               07/14                                 Boiler
    M/s Lanco Vidarbha                                                                   Boiler erection started on 01/08/11. Main structure erection upto 6 th tier
    Thermal Power Ltd.           2       660       07/14     12/14      *         *      completed in 10/15. All the (5) Ceiling Girder (CG) erection work
       (2x660=1320 MW)                             11/14                                 completed. Pressure parts erection work started in 04/16.
       Original/Latest Cost           : Rs.693600 lakhs/ Rs.1043300 lakhs
      Expenditure during 03/11        : Rs 97600 lakh                                    TG
      Expenditure during 2011-12      : Rs 181100 lakh                                   TG Deck casting completed. TG handed over to mechanical department
      Expenditure during 2012-13      : Rs 67200 lakh                                    for erection. TG erection started in 05/16. EOT Crane (2 nos.) already
      Expenditure during 2013-14      : Rs 15200 lakh                                    commissioned.
      Expenditure during 2014-15      : Rs -     lakh
      Expenditure during 2015-16      : Rs 98900 lakh                                     Unit-2
      Expenditure during 2016-17      : Rs 73800 lakh                                    Boiler
      Expenditure during 2017-18      : Rs    -    lakh                                  Boiler erection started in 10/11. Main structure erection upto 6th tier
                                                                                         completed. All the (5) Ceiling Girder (CG) erection work completed.
       Total Expenditure                : Rs 533800 lakhs (Upto 04/17)                   Pressure parts erection work started in 08/16. HT is yet to be done.
       Approval date:                   : NA
       Zero date:                       : Achieved on 01/12/10.                          TG
                                                                                         TG raft completed and Mezzanine Floor work completed. Top deck
       Notice To Proceed (NTP)          : Achieved on 01/12/10.                          shuttering work also completed, final inspection work under progress. TG
       Financial closure                : Achieved on 01/12/10.                          erection work yet to start.
       Main Plant Order                 : EPC Contract awarded to M/s Lanco Infra        Presently work is on hold due to financial constraints.
                                        Tech Ltd.(LITL) through ICB Route in             BoPs:
                                        11/09. Boiler & Aux.: Dongfang, China
                                        TG & Aux.: Harbin, China,                               Chimney: Civil works for chimney are being done by M/s LITL.
       BTG Make                         Boiler & Aux.: Dongfang, China                       Chimney Raft completed. Chimney shell construction completed upto
                                      TG & Aux.: Harbin, China,                              30 mtr.upto 07/16.
       Type of fuel                   : Coal                                                    CHP: (Elecon Engg.Co. Ltd): Wagon Tippler excavation work
       PPA                            PPA for 680MW(Net)signed with MSEDCL.                  completed. Raft Completed in WT area and balance work is in
       Source and supply of Fuel        : SECL                                               progress. Civil works are being done by M/s LITL. In other parts of
                                                                                             CHP such as Stacker reclaimer , Crusher House, TPs and conveyors
       Power Evacuation system          : Grant of connectivity letter received at 765       civil works are in progress..
                                        kV from Wardha-Seoni line from PGCIL.                   AHP: (M/s LITL): Civil works for BA hoppers, Fly ash silo’s,
                                        Connectivity agreement is in progress.               AWPH, ASPH and ash dyke are in progress.
               All clearances are available. MOEF clearance received on                        Raw Water Supply System: Work is in progress.
                24/02/11.                                                                       PT/ DM Plant (DOshion Veolia water solution): Approx. 80%
               Design & Engineering completed.                                              civil works completed upto 09/16.
               Order for all BOPs have been placed and progressing as per                      CW System: Civil works are with M/s LITL and mechanical
                schedule.                                                                    works are with M/s Singrauli Associates Pvt. Ltd.. Civil works in CW
               FSA is in process.                                                           pump house, CW fore Bay and CW open channel are in progress. 85%
               PPA with MSEDCL for 680MW signed on 25/09/08.                                CW pipeline erection work completed upto 09/16. Balance erection
               Work was on hold since 01/2013.                                              work is under progress.
               Work at site restarted since April, 2015.                                       IDCT: Being done by M/s LITL. For both the IDCT- I: & IDCT-
               Work in all the BoPs is also progressing nicely.                             II: PCC and basin raft concreting completed. Pedestal work is in
                                                                                             progress.
                                                                                                FOPH: All civil works are in progress..
                                                                                                Switchyard: 95% switchyard foundations completed so far.
Critical issues      Financial crunch.
Reasons for Delay    # Work was on hold due to financial crunch. Work has now restarted since 04/15. Work progress is slow due to Financial
                     Costraint.
* Work on hold due to financial crunch. Schedule will be decided after restart of work.
                                                                                   76
                             Unit                  Commissioning Schedule
Sl.      Project Details            Capacity                                                                 Broad Status
No.                                  (MW)         OriginalActual(A)/ As
                                                             Expected
                                                Synch/ COD Synch/ COD
                                               Comm         Comm
 Private Sector
     Bijora Ghanmukh           1         300     10/16   01/17   Uncertain         Unit-1
     TPP,                                        12/16                             Boiler
     (Distt: Yavatmal)                                                             Boiler Civil works started in 09/15. Work at site put on hold due
     M/s Jinbhuvish            2         300     01/17   03/17   Uncertain
                                                 03/17                             to financial crunch.
     Power Generations
     Pvt. Ltd. (JPGPL)
       (2x300=600 MW)                                                              Unit-2
       Original/ Latest Cost        : Rs.318900 lakhs / Rs.345000 lakhs            Boiler
      Expenditure during 03/14      : Rs 37475 lakh                                Work at site put on hold due to financial crunch.
      Expenditure during 2014-15    : Rs 4752 lakh                                 TG
      Expenditure during 2015-16    : Rs -      lakh                               Work at site put on hold due to financial crunch.
       Total Expenditure              : Rs 42227 lakh (Upto 03/15)                 @: Work at site put on hold. Revised commissioning
       Approval date:                 :                                            schedule will be decided after re-start of work.
       Zero date:                     :
       Notice To Proceed (NTP)       :                                             BOPs
       Financial closure             : Achieved (REC &PFC)                          Work yet to start
       Date of Main Plant Order      : BTG on EPC basis Contract awarded to
       (Boiler &TG from CWPC,        M/s CWPC (China Western Power
       China)                        Corporation) (through ICB Route) on
                                     28/09/11.
       BTG Make
       BOP on EPC basis
       Type of fuel                   : Coal
       PPA                              : Signed with PTC India Ltd.
       Source and supply of Fuel        : WCL(1.851MMT)
       Power Evacuation system          : Final connectivity on LILO from PGCIL
                                        Wardha-Parli D/C transmission line.
               FSA: Coal Linkage LOA received from WCL, however FSA is
                yet to be signed
               Consent to Establish : Obtained from MPCB.
               All statutory clearances are available. MOEF clearance received
                on 30/07/12.
               Design & Engineering in progress.
               Order for all BOPs on EPC basis has already been placed on M/s
                AEMPL on 26/05/14. The process of subletting packagewise
                contract to reputed vendors was in progress.
               Site leveling and grading was in progress.
               Capacity revision from 2x250 MW to 2x300 MW accepted and
                issued letter on 19/03/14.
               FSA is in process. All the milestones required under the terms of
                LOA have been completed.
               PPA: MOA signed on 27/02/12 with PTC India Ltd. for sale of
                430 MW (75%) on Long Term Basis and remaining 25% on
                merchant power basis.
               Various site enabling works were in progress.
Critical issues        Financial Issue
Reasons for Delay         The schedule of implementation got revised due to change in capacity from 2x250 MW to 2x300 MW. Formal approval received on
                          19/03/14. Signing of FSA with WCL has to be expedited.
                                                                              77
                               Unit                          Commissioning Schedule
Sl.      Project Details                Capacity                                                                           Broad Status
No.                                      (MW)          Original    Actual(A)/ As
                                                                         Expected
                                                    Synch/     COD     Synch/     COD
                                                   Comm                Comm
 Private Sector
     Shirpur Power              1           150      12/14     02/15   09/17(A)       -       Unit-1:
     Private Ltd. Distt.                                               28/09/17(A)            Commissioning achieved on 28/09/17.
     Dhule,
     Maharashtra                2           150      02/15     04/15                          Unit-1 & 2:
                                                                              *           *   Steam blowing of the units completed. Main plant structural work
       (2x150=300 MW)                                                                         completed.
       Original / Latest Cost          : Rs.241300 lakhs / Rs. 241300 lakhs
      Expenditure during 2011-12       : Rs 3368 lakh
      Expenditure during 2012-13       : Rs 15821 lakh                                        Project is 96.7% complete.
      Expenditure during 2013-14       : Rs 74610 lakh
      Expenditure during 2014-15       : Rs 72102 lakh
      Expenditure during 2015-16       : Rs 34176 lakh
      Expenditure during 2016-17       : Rs 27686 lakh
       Total Expenditure                 :Rs 238385 lakhs                                     BoPs:
       (Upto 11/17)                                                                           Almost all BoPs are completed.
       Approval date:                   :NA
                                                                                                  CHP: coal feeding from emergency reclaim hopper to bunker
       Zero date:                       :
                                                                                                completed. Wagon tippler erection in progress.
       Notice To Proceed (NTP)          :                                                         AHP, Cooling tower, Chimney, PT plant, DM plant, CW
       Financial closure                : Achieved on 08/10/12                                  system completed.
                                                                                                  Fire detection system erection is in progress.
       Date of Main Plant Order         : BTG Contract awarded to BHEL on 22/11/2011.
       (Boiler &TG from BHEL)                                                                     Station transformer to be charged after back charging 220 Kv
                                                                                                Transmission line.
       BTG Make                        Boiler &TG from BHEL
       BOP on EPC basis
       Type of fuel                    : Coal
       PPA                             : 195 MW PPA done with private players in steel and
                                         textile sectors. For the rest, new customers like
                                         DISCOMs, Railways needs to be found out.
       Source and supply of Fuel         : SECL
       Power Evacuation system            Connectivity approval from MSETCL for 220 kV
                                            line at Amalner substation
                All clearances are available.
                Design & Engineering completed.
                Order for BOPs on EPC basis have been placed M/s Punj Lloyd on
                 03/08/10. In all the BOPs work already completed.
                                                                                     78
                             Unit                          Commissioning Schedule
Sl.      Project Details              Capacity                                                                      Broad Status
No.                                    (MW)          Original    Actual(A)/ As
                                                                       Expected
                                                   Synch/    COD     Synch/     COD
                                                  Comm               Comm
 Private Sector
     Bhusawal                  6          660      11/21                                  Unit-6:
     Thermal Power
     Project, Distt.
     Jalgaon,
     Maharashtra                                                                               LOA issued to M/s BHEL on single point responsibility EPC
                                                                                                Contract basis.
       (1x660 MW)                                                                              M/s BHEL has submitted Performance BG and Advance BG as
       Original / Latest Cost       : Rs.509700 lakhs                                           per terms of LOA
      Expenditure during 2018-19    : Rs lakh                                                  M/s BHEL has submitted the L1 schedule on 30.08.2018.
                                                                                               LOA is issued to M/s DCPL for consultancy work for Design,
                                                                                                Engineering, Implementation & Monitoring purpose.
       Total Expenditure              :Rs lakhs                                                Leveling & area grading work of M/s BHEL storage yard has
       (Upto 12/18)                                                                             been commenced from 06.09.2018.
       Approval date:                 :NA                                                      Supply of structural steel material has been commenced during
       Zero date:                     : 31/12/2018 (Revised)                                    mid September 2018.
                                                                                               Construction Power Supply Provided to M/s. BHEL as per
       Notice To Proceed (NTP)        : 31/12/2018
                                                                                                requirement.
       Financial closure              :
       Date of Main Plant Order       : LOA has been issued to M/s BHEL on single point
                                      responsibility EPC contract basis on 17.01.2018.
                                      Amendment to LOA issued to M/s BHEL dated
                                      31/12/18 for additional work of FGD, SCRand other
                                      scope of work.
       BTG Make
       BOP on EPC basis
       Type of fuel                     Coal
       PPA
       Source and supply of Fuel
       Power Evacuation system
       AAI issued NOC having the validity till 23 Feb 2022
       Water Allocation is already tied up with WRD
       MoE&F Environment clearance (EC) was granted till 26 Nov 2019.
Critical issues
Reasons for Delay
                                                                                79
Southern
 Region
   80
                BROAD STATUS OF THERMAL POWER PROJECTS IN ANDHRA PRADESH
                                                                Commissioning Schedule
Sl.          Project Details             Unit Capa-          Original    Actual(A)/ As                                     Broad Status
No.                                      No. city                            Expected
                                              (MW)
                                                          Syn.       COD    Syn.     COD
                                                         Comm             Comm
 State Sector
 1 Rayalaseema TPP St-IV                   6      600      07/14               07/17(A)     04/18     Boiler: Erection started on 04/02/2013. Boiler Drum
      (M/s. APGENCO)                                       08/14               03/18 (A)                 lifted on 30/11/13. 26952 MT/ 29730MT structural
      Distt.Cuddapah,                                                                                    materials erected till 10/17. Boiler air leak test
      Andhra Pradesh                                                                                     completed. BLU done on 29/12/16. EDTA cleaning
                                                                                                         completed on 26.02.17. Mill foundation on both
                  Original /Latest Cost : Rs. 302886 / 388043 Lakh
                                                                                                         sides completed. Bowl mill deck slabs completed for
    Expenditure during 2009-10             : Rs. 555.00 lakh                                             all mills. Unit Synchronized on 02.07.17. Full
    Expenditure during 2010-11             : Rs. 25833.00 lakh                                           Load achieved on 03/18.
    Expenditure during 2011-12             : Rs. 8155.00 lakh                                         TG: TG erection started on 04/03/16. TG box up done
    Expenditure during 2012-13             : Rs. 29331.00 lakh                                           in 02/17.
    Expenditure during 2013-14             : Rs. 80045.00 lakh                                        Chimney (M/s Gammon): Shell concreting
    Expenditure during 2014-15             : Rs. 52429.00 lakh                                           completed. A.R.Brick work completed up to (+) EL
    Expenditure during 2015-16             : Rs. 62341.00 lakh                                           135.30 M height.
    Expenditure during 2016-17             : Rs. 83576.96 lakh
                                                                                                      CHP: Work awarded to M/s Thyssenkrup.
    Expenditure during 2017-18             : Rs 69776..04 lakh ( 12/17)                               AHP: Vacuum pump house building, Silos, Bottom
                   Total Expenditure : Rs 412042 lakh (up to 12/2017)                                    ash hopper, Buffer hopper, ASPH etc. area civil
                             Zero date : 10/02/2011.                                                     works completed
                     Financial closure : Achieved on 19/03/10                                         RWR: Trimming of slopes of reservoir bund is in
                          Type of Fuel : Coal                                                            progress. In the raw water pump house RCC
                                                                                                         structure completed.
                 Main Plant Order          Placed on M/s BHEL for BTG on 18/11/10.
                                                                                                      PTP: clarifier works completed.
                        BOP Package Purchase order placed on the consortium led by M/s
                                           Tecpro Systems Ltd, including civil works on EPC basis  DM Plant: Roof slab work up to 183.10 ml
                                           on 15/12/10. Now it is led by VA Tech.                        completed. Vessels foundations ready. Vessels
                                                                                                         material available at site. Some vessels are placed in
        MOEF clearance obtained on 21/10/2010.
                                                                                                         position.
        PFC Sanctioned a loan of Rs. 2423 crores.
                                                                                                      CWS: raft work in CW pump house completed. All
        M/s Desein Pvt. Ltd is providing engineering consultancy services.                              walls raised up to pump floor. PCC works of fore
                                                                                                         bay in progress. CW pipe line fabrication is almost
                                                                                                         complete.
                                                                                                      NDCT (M/s Gammon): Shell erection 32 lifts
                                                                                                         completed &33rd in progress.
                                                                                                      FO System: M/s Xicon is executing these works Civil
                                                                                                         work almost completed. Tanks fabrication & erection
                                                                                                         in progress. Fuel oil transfer pump tank HFO and
                                                                                                         LDO day tank slab completed & handed over for
                                                                                                         erection work.
                                                                                                      Switchyard: Foundations of all equipment were
                                                                                                         completed and handed over for erection of
                                                                                                         equipment’s.
      Critical issues     1. Readiness of cooling tower, CHP & AHP.
  Reasons for Delay       1. Boiler erection start was delayed by 13 months due to initial land acquisition and civil works problems. Mill, ID, FD & PA fan
                             foundation work delayed.
                          2. Slow progress of Civil works and BOP works by the consortium led by VA Tech, Techpro and Gammon.
                          3. Delay in award of CHP& AHP by the consortium leader VA Tech.
                                                                                 81
                                                                          Commissioning Schedule
Sl. No.           Project Details             Unit      Capa-                                                         Broad Status
                                              No.        city         Original  Actual(A)/ As
                                                        (MW)                          Expected
                                                                  Syn.      COD    Syn.       COD
                                                                Comm              Comm
  State Sector
  2     Sri Damodaram Sanjeevaiah               1       800       02/19     04/19     06/19    10/19    Boiler:Boiler Erection started in 06/17. 74%
        TPP St-II (Krishnapatnam)                                 03/19               08/19              completed. 3. Hydro Test expected in 04/19.
        (APPDCL) Distt.Nellore,                                                                          ESP Erection 90% completed.
        Andhra Pradesh                                                                                  TG: TG raft, columns, deck casting and
            Original / Latest Estd. Cost    Rs. 4276.04 / 6034 Crs.                                      pedestal concreting completed. Condenser
                                                                                                         erection works started in 08/18. TG erection
            Expenditure during 2015-16      Rs. 199.20 Crs.                                              works started in 10/18. Works are in
                                                                                                         progress.
                                                                                                        BoPs.
                     Total Expenditure      Rs. 4186 Crs. (2/19)                                        CHP:      Structural     Steel   fabrication
                         Approval date:     14.12.2017 for revised cost                                  5800/5820 T completed. Structural Steel
                            Zero date:      15.12.2015                                                   erection     3790/5820      T    completed.
                       Financial closure                                                                 Structural steel erection for Conveyors and
                                                                                                         JNTs in progress.
                   Main Plant Order      BTG order placed on BHEL on 02.11.15.                         AHP: Works of Ash compressor house, Ash
                      Type of fuel/FSA Coal. Available                                                   water sump and pump house, Ash slurry
                Power Evacuation system Already in place                                                 pump house, Hydrobins, Clarifier, MMC,
                                 PPA    Available with 2 DISCOMS of A.P                                  Sludge pit, Vacuum pump house, Silo 1, Silo
                                                                                                         2, Utility building, Ash slurry line pedestals
                                                                                                         & Ash slurry line piping are in progress.
                                                                                                        Cooling Tower: 100% Racker columns
          Land Possession: Available.                                                                    completed. Shell up to 102nd lift completed..
          Water allocation: Available.                                                                   Main and secondary ducts are in progress.
          MOE&F clearance: Available                                                                    Chimney:       Brick     work      247/274mtr
          State Pollution Control Board Clearance: Available                                             completed. External platform works
          Civil Aviation clearance: Available                                                            completed. Insulation works are in progress,
                                                                                                         Landing platform works completed. Inside
                                                                                                         shell BT painting is in progress.Level corbel
                                                                                                         casting completed (27/27)
                                                                                                       All othe BOP works are in progress.
                                                                                                        FGD : Order not yet placed.
        Critical issues
     Reasons for Delay
                                                                                 82
                                                              Commissioning Schedule
Sl.         Project Details         Unit    Capacity                                                                 Broad Status
No.                                 No.      (MW)           Original  Actual(A)/ As
                                                                          Expected
                                                         Syn.     COD   Syn.     COD
                                                       Comm            Comm
State Sector
3     Dr. Narla Tata Rao             1         800      03/19     07/19   03/19    07/19   Boiler erection started on 22.05.2017. ESP erection started on
      TPP                                               06/19             06/19              15.03.2017. Drainable Hydraulic Test completed on 05.03.2019
      APGENCO                                                                              Pass I erection and Pass II erection works under progress.
      Distt. Vijayawada,                                                                   TG deck casting completed. TG and condenser erection started.
      Andhra Pradesh                                                                       BOPs.
      Original / Latest Cost      Rs. 5286.54 / 5515 Crs.                                  CHP: JT erfection works under progress. WAGON TIPPLER : Wall
                                                                                           raised upto RL 24.30 & Floor slab completed. Walls above FS
         Total Expenditure        Rs. 3932.12 Crs                                          109/109m 1st lift completed. Re bar tying & shuttering for wall in
           (1/19)                                                                          progress. pedestal completed.
         Approval date:                                                                    Track Hopper : Wall raised upto RL 24.30 & Floor slab completed.
         Zero date:               15/12/2015                                               Walls above FS 109/109m completed. Shuttering for hoppers is under
                                                                                           progress.
         Financial closure        Completed
                                                                                           AHP: Ash slurry pump house raft completed, pump foundations
              Main Plant          BTG order placed on BHEL on 28.10.15.                    under progress. Ash water pump house steel for roof beams is in
          Order                                                                            progress. Ash slurry pump house columns final lift completed.
         BOP Package              Tendering for BOP packages completed and order placed    Seal water sump walls final lift concrete completed. AHP & MRS
                                   on M/s. BGR energy Systems Ltd on 06/07/2016. (36       compressor house columns first lift above plinth beam under
                                   months for completion of BoP)                           progress. Vacuum pump house concreting of all roof beams is
         Type of fuel /FSA        Coal / Available                                         completed. Hydrobins 1,2&3 columns 3rd lift above plinth beam
         PPA                      Available with 4 DISCOMS before bifurcation of A.P. To   completed. Silo 1:columns 1st lift completed, silo 2 columns 3rd lift
                                   be revised with 2 DISCOMS of A.P                        completed. Silo utility building roof slab completed. Ash water sump
                                                                                           walls under progress. Ash slurry sump works under progress.
         Power Evacuation          Under progress                                          AHP & MRS compressor house : lintel beam & columns lift under
           system                                                                          progress. Equipment foundations & brick masonry under progress
         Land Possession: Available                                                        Cooling Towers: 174 /180 mtrs shell concreting completed.
         Water allocation: Available                                                       Chimney: 275/275 Mtrs Chimney shell construction completed on
         MOE & F clearance: Available                                                      25.02.2018. 24/27 elevations corbels erection under progress. AR
         State Pollution Control Board Clearance: Available                                brick lining work completed from 11 to 120 Mtrs and 150 Mtrs to
         Civil Aviation clearance: Available                                               275 Mtrs.
                                                                                           PT Plant: Mechanical erection completed for clarifier A & B.
                                                                                           Sludge thickener mechanical erection completed Raw water pumps
                                                                                           erection completed. Chemical Dosing pumps in PTP chemical house
                                                                                           erected.
                                                                                           CW System: 596/1100 mtrs CW pipeline erection completed.
                                                                                           145/400 ACW piping erection started. 40 T EOT crane mechanical
                                                                                           erection completed in CWPH. Hydrotest for 200 mts CW pipe
                                                                                           completed (Supply & Return line
                                                                                           Switch Yard: 100% Towers & Gantry erection, 100% of Equipment
                                                                                           structures, 95% of Equipment erection & 85% conductor stringing
                                                                                           completed.
                                                                                           50% of earthing in power block area & 95% of earthing in switchyard
                                                                                           area completed. 100% HT cable, 70% LT cable, 50% of
                                                                                           Transformers, 70% Cable Trays & Cable tray supports, 100% earth
                                                                                           rod and 90% earth flat received.
         Critical issues
      Reasons for Delay
                                                                              83
                                                                    Commissioning Schedule
Sl.             Project Details             Unit   Capa-                                                                     Broad Status
No.                                         No.     city       Original   Actual(A)/ As
                                                   (MW)                        Expected
                                                            Syn.      COD    Syn.       COD
                                                           Comm             Comm
Private Sector
4 Thamminapatnam TPP Ph-II                   3     350      01/12     06/12   2/18 (A)     4/19     Unit-3:
    (M/s Meenakshi Energy Pvt.Ltd.),                        05/12             4/18 (A)              Boiler: erection started on 16/11/11. Drum lifted in 16/05/14.
    Thamminapatnam                           4     350      03/12     09/12   3/19 4/19    4/19      Hangers & Headers erection almost completed. Panel and coil
    Distt.: SPSR Nellore,                                   08/12                                    erection in progress. Roof, LHS, RHS, Burner Panel erection
    Andhra Pradesh                                                                                   completed. Final SH and HTRH coils erection completed.
               Original /Latest Est. Cost    :Rs 312000 Lakhs ( 600 MW) / 500500 Lakhs (             Primary SH coil erection in progress Erection of flue gas duct
                                             700 MW)                                                 between ESP to ID fab to Chimney almost completed. ESP to
              Expenditure during 2008-09     :Rs     -NIL-                                           Boiler flue gas duct erection almost completed. Both sides
              Expenditure during 2009-10     :Rs 1157.00 Lakhs                                       RAPH erection nearing completion.ID fan #A & #B
              Expenditure during 2010-11     :Rs 42362.00 Lakhs                                      completed. Both side PA & FD fan erection completed. HT
             Expenditure during 2011-12      :Rs 53379.46 Lakhs                                      done on 31/10/15. Non-drainable HT completed on
             Expenditure during 2012-13      :Rs 21802.67 Lakhs                                      06.08.17. BLU Completed on 30.11.17. Steam Blowing
             Expenditure during 2013-14      :Rs 47833.82 Lakhs                                      completed on 20/12/17. Unit synchronized on 10.2.18. Full
             Expenditure during 2014-15      :Rs 81656.43 Lakhs                                      load achiebed on 15.4.18.
              Expenditure during 2015-16     :Rs. 98832.77 Lakhs                                    TG: Condenser erection started in 15/03/15 & TG erection
              Expenditure during 2016-17    :Rs. 86250.65 Lakhs                                      started in 04/07/15. LP & HP turbine final box up completed
              Expenditure during 2017-18    :Rs. 74715.67 Lakhs                                      on 14.02.17. Condenser front and rear water box erection
              Expenditure during 2018-19    :Rs 33450.49 Lakhs (2/19)                                completed. Final Boxed –up on 27.07.17 .TG oil flushing
          Total Expenditure(up to 2/19)     : Rs. 541440.96 Lakhs                                    completed on 27.11.17 and TG on barring gear.
                          Approval date:                                                              Unit-4:
                              Zero date:                                                             Boiler: erection started in 22/09/14. Drum lifted on 31.07.15
                                                                                                      .HT (Non drainable) completed in 5/18. SBO completed in
                        Financial closure : 01/10/2010
                                                                                                      01/19. Full load expected in 04/19.
                                            Loan agreement signed with REC, IBDI & other Banks,
                                            REC as lead lender                                        TG: Condenser erection stated on 13/07/15. TG erection
                                                                                                      started on 29/10/15. TG box up done in 3/18. TG oil
                        Main Plant Order: 10/12/2009
                                                                                                      flushing done in 06/18.
                                            Boiler –Cethar Vessels Ltd, Trichy, Tamil Nadu, India
                                            TG – China National Automotive International             Chimney: Ready for service.
                                            Corporation, China (Harbin)                              CHP: Awarded to EDAC Engineering Ltd., Chennai on
                           BOP Package                                                                18/06/10. Priority Stream-I trial run completed  Stream-II
                                                                                                      commissioning work in progress  Stacker & Reclaimer – I&
                            Type of fuel
                                                                                                      II – in operation mode.
                                     PPA : PPA signed with M/s PTC on 25/02/2010 for 600 MW.         AHP: Awarded to EDAC Engineering Ltd., Chennai on
                Power Evacuation system : 400 KV MEPL – Manubolu (PGCIL) 27 km line is                18/06/10. Unit#3 completed  Unit#4 Completed.
                                            completed by M/s Sujana Towers Hyderabad and             IDCT: Awarded to EDAC Engineering Ltd., Chennai on
                                            charged. Agreement for Long Term Open Access for          18/06/10. CT#3 Completed  CT#4 completed.
                                                                        nd
                                            1000 MQ with PGCIL on 2 January 2012.                    PTP: PT plant erection completed and commissioned.
          Land: 563.90 Acres of land acquired for entire 1000 MW.                                   DM Plant: DM plant in operation mode.
          MOE&F: Clearance obtained on 03/06/2009 & 19/10/09. Further extended up to                CW System: Unit#3 CW and ACW commissioning
           18/10/19 on 25/10/13.                                                                      completed.  Unit#4 CW and ACW commissioning
          SPCB: Consent for Establishment received vide letter dated May 2011 for 1000MW.            completed.
           Extension granted to 2021                                                                 FO System: LDO system completed and oil stored in tanks.
          Civil Aviation: NOC obtained on 28/02/11from AAI for 281 m height of chimney.             SW Yard: Switchyard charging completed on 31.05.17.
           Water:100 Cusec/day sea water from Kandaleru Creek accorded by Principal                  Switchyard Automation System (SAS) panels, Control Relay
           Secretary (FAC), Infrastructure & Investment (Ports-I), AP on 18/02/10.                    Panel (CRP) panel charging completed.
          Fuel Linkage: Letter of Assurance (LOA) dated 11th June 2009 obtained from
           Mahanadi Coalfields Ltd (MCL) for the supply of 2.023 MMTPA Grade “F” Coal.
           Fuel Supply Agreement dated 31 August, 2013 executed with Mahanadi Coalfields
           Ltd(MCL) for the supply of 1.0115MMTPA Grade “F” coal for Unit 3 (350 MW).
           Imported Coal Supply Agreement: Coal Supply and Transportation Agreement dated
           25 November, 2013 executed, with GDF Suez Energy Management Trading SCRL,
           34, boulevard Simon Bolivar, 1000 Brussels, Belgium. Coal Quantity : 2.50MMT per
           annum
          BPTA: BPTA signed with PGCIL for 300 MW on 24/02/2010 and for additional
           BPTA signed for 1000 MW on 02/01/12
          Mega Status: Achieved in 02/12
Critical issues
Reasons for Delay            Slow progress of Civil works. Due to financial problem, work at site remained closed for a long time. Change of stakeholders and
                             subsequent change in the completion of various milestone.
                                                                                 84
                                                                        Commissioning Schedule
Sl. No.            Project Details                Unit Capa-                                                                Broad Status
                                                  No.   city        Original    Actual(A)/ As
                                                       (MW)                         Expected
                                                                  Syn.      COD   Syn.      COD
                                                                Comm             Comm
  Private Sector
  5 Bhavanapadu TPP Ph-I                        1        660    08/13      12/13   Uncertain          Unit-1
      (M/s East Coast Energy Pvt. Ltd.) Distt.:                 10/13                                  Boiler: Boiler erection is started on 27/03/2014. 5th tier
       Srikakulam,                              2        660    01/14       05/14 Uncertain            erection completed. Girders are to be placed which are
      Andhra Pradesh                                            03/14                                  available at site.
                     Original /Latest Est. Cost    :Rs 657194.00 lakh (Equity:debt::25:75) /           ESP: Structures, hoppers erection is in progress.
                                                    934315.00 lakh (09/07/14)                          TG: Deck casting completed on 28/05/15. Power house
                                                                                                       erection (2nd tier) is in progress. EOT crane to be erected
                Expenditure during 2007-08         :Rs 1674.00 lakh
                                                                                                       Unit-2
                Expenditure during 2008-09         ;Rs 7018.00 lakh
                Expenditure during 2009-10         :Rs 27800.00 lakh                                   Boiler: Boiler erection started in 02/15. 2nd tier erection
                                                                                                       completed.
                Expenditure during 2010-11         :Rs 72100.00 lakh
                Expenditure during 2011-12         :Rs 22900.00 lakh                                   ESP: Piling completed.
                Expenditure during 2012-13         :Rs 29208.00 lakh                                   TG: Raft casted on 29/05/15. TG columns scaffolding
                Expenditure during 2013-14         :Rs 76300.00 lakh                                   work is in progress. Condenser erection yet to start.
                Expenditure during 2014-15         :Rs 82210.00 lakh                                      BoP’s
                Expenditure during 2015-16        : Rs. 53006.00 lakh                                  Chimney: Order placed on M/s. R S Pabla in Oct, 10.
              Total Expenditure (till 01/16)      :Rs 3785. 60 Crores                                    Shell casting completed. Flue can erection is in progress.
                            Approval date:                                                             CHP: Awarded to M/s BSBK. Piling completed. Dewall
                                                                                                         works in track hopper area completed.
                                Zero date: : 15/09/2010
                                                                                                       AHP: Order placement is in progress.
                          Financial closure : Achieved on 08/09/2010. Lead Financier - PFC             WTP: Engineering is in progress.
                            Main Plant Order: Order placed on 03/09/2009 on DEC China (BTG)            DM Plant: Engineering is in progress.
                                BOP Package : EPC of BOP & Main plant Civil works contract             CW System: Engineering is in progress.
                                               awarded to consortium of M/s NEC and M/s Abir           NDCT: Order placed on M/s Paharpur Cooling Towers.
                                               Infrastructure Pvt Ltd on 30/01/10.                     FPS: Engineering is in progress.
                                 Type of fuel                                                          FOS: Order placed on Delta P.D. Pumps on 14/05/12.
                                         PPA :Long term PPA signed with PTC India Ltd on                 Tank fabrication work completed.
                                               25/06/10 as an amendment of 06/05/09                    Switchyard: Engineering is in progress.
                    Power Evacuation system                                                            ATS: Award of contract to be done by ECEPL.
             Land: Total land of (2050 + 36.94 Colony) Acres is acquired.
             MoE&F: Clearance obtained on 09/04/2009 & revalidated on 20/08/14.
             Water: Permission for drawl of 168 cusec sea water from Govt. of AP is obtained on                Presently work held up at site
              10/06/2008.
             SPCB: clearance obtained from APPCB on 15/06/2009 revalidated on 30/12/14.                         due to financial issues.
             Civil Aviation: AAI clearance obtained vide lr. Dt. 04/03/08 & revalidated up to 3rd
              March 2020.
             Coal Linkage / FSA: LOA received from MCL for 4.273 MTPA on 11/06/2009.                  PPA details are as follows: Having PPA for 100 MW
              FSA to be signed. FSA signed with Global Fuels pvt Ltd Singapore for balance             with Kerala. Having LOI for 300 MW but in dispute
              quantity of coal on 23/04/09                                                             due to formation of Telangana. For 500 MW PPA with
             BPTA: BPTA signed with PGCIL on 21/09/12.                                                Andhra Pradesh, developer is L1.
                                                                                     85
                           BROAD STATUS OF THERMAL POWER PROJECTS IN TELANGANA
                                                                           Commissioning Schedule
Sl. No.              Project Details             Unit Capa-city                                                                     Broad Status
                                                 No.   (MW)           Original    Actual(A)/ As
                                                                                       Expected
                                                                    Syn.      COD   Syn.      COD
                                                                   Comm            Comm
  State Sector
  1     Kothagudem TPS –VII                       12     800       09/17      12/17        30.06.18   26/12/18  Boiler: Civil work started on 12/06/15 and erection
        (TSGENCO) Distt. Kammam,                                   11/17                   10/18      (A)        commenced on 24/01/2016 and is in progress 98.4%
        Telagana                                                                                                 completed. HT (Drainable) completed on 22.09.17.
                                                                                                                 BLU completed on 31.01.18. Unit Synchronised on
               Original Estd. Cost/Latest Cost    : Rs. 554844 lakhs / Rs. 554844 lakhs
                                                                                                                 30.06.18. Full load achieved on 05.10.18. COD on
                  Expenditure during 2014-15     : Rs. 199.60 lakhs                                              26/12/18.
                  Expenditure during 2015-16     : Rs. 54654.50 lakhs
                                                                                                                TG Deck: TG civil work started in 23/08/15. TG
                  Expenditure during 2016-17     : Rs. 170310.10 lakhs
                                                                                                                 erection started on 28.02.17. TG Boxed up in 06/18.
                  Expenditure during 2017-18     : Rs. 107615.42 lakhs
                  Expenditure during 2018-19     : Rs. 130783.19 lakhs (12/18)
                                                                                                      BOPs
               Total Expenditure(Up to 12/18)    : Rs. 466995.13 lakhs
                                                                                                     CHP: Civil work awarded to M/s. SNC on 12/02/16.
                               Approval date:                                                         94% completed. Wagon tippler side arm charger
                                    Zero date:     01/01/2015                                         works completed. Stacker cum reclaimer awarded to
                              Financial closure Tied up with REC on 17/01/2014                        M/s TRF on 12/08/15 commissioning of SCR-I
                              Main Plant Order (BTG on M/s BHEL)- LOI issued on 27/12/14.             completed. Conveyor system awarded to M/s.
                                                                                                      BEVCON on 22/08/15: Material received and
                                 BOP Package
                                                                                                      erection work under progress. Crusher, vibrating
                                   Type of fuel Coal, FSA: M/s Singareni Collieries Co. Ltd,          screens/peddle feeder awarded to M/s Elecon on
                                                   Kothagudem.                                        23.02.16- Material received Erection works in
                                           PPA PPA signed on 22/01/2013 and power evacuation system progress.
                                                   400 Kv by TSTRANSCO.                              AHP: Civil work Awarded M/s SNC on 12.02.16.
                     Power Evacuation system 400kV by TSTRANSCO                                       93% completed. Supply & Erection work awarded to
             LOI was issued to BHEL on 27/12/2014 (i.e Main plant equipment Boiler, Turbine &        M/s OSM : 95% material supplied.
              Generator-BTG)                                                                         Cooling Tower: Awarded to M/s. Paharpur cooling
             MOEF clearance obtained on 16/07/15.                                                    towers ltd. on 04/03/16, work started on 12/07/16
             SPCB clearance obtained on 12.11.15                                                     and 99.8% completed.
             SPCB: Applied for consent for establishment and approval awaited.                      Chimney: Awarded to M/s. BIL on
             REC has sanctioned a loan vide letter dated 17/01/14.                                   16/05/15.Chimney is completed.
             Water allocation available vide G.O.MS No.47, dated 24/12/14.                          PT Plant: Civil work Awarded to M/s. Punj Lloyd
             AAI clearance obtained vide letter no. AAI/SR/NOC/RHQ dt.15/10/12.                      Ltd (PLL) and 95% completed. Supply & erection
                                                                                                      awarded to M/s Clear water: 98% material supplied
                                                                                                      & 80% work completed.
                                                                                                     DM Plant: 98.5% completed.
                                                                                                     CW System: 98% civil works completed.
                                                                                                     Fuel Oil Handling System: 97% civil works
                                                                                                      completed.
                                                                                                      FGD: LOI issued to M/s BHEL for providing wet
                                                                                                      lime based FGD with completion period of 30
                                                                                                      months. Works yet to start.
 Critical issues
 Reasons for Delay
                                                                                      86
                                                                  Commissioning Schedule
Sl. No.            Project Details             Capa-city                                                                Broad Status
                                                (MW)           Original    Actual(A)/ As
                                                                                Expected
                                                             Syn.      COD     Syn.      COD
                                                            Comm              Comm
  State Sector
  2     Bhadradri TPP (TSGENCO)                    1080                                               Unit 1:
        Distt. Khammam,                                                                               Boiler: Boiler erection started on 15.09.17. Boiler drum
        Telangan                                                                                      lifted on 06.01.18.Boiler hydro test completed on
                                                                                                      17.08.18.
                                         U-1       270     01/17      03/17 03/19           04/19
                                                                                                      TG: TG civil work staretd on 06.11.15. Condenser
                                                           03/17              04/19
                                           U-2 270         03/17      05/17 05/19           05/19     erection started on 01.06.18.TG erection started on
                                                           05/17              06/19                   01.09.18.
                                           U-3 270         05/17      07/17 07/19           08/19     Unit 2:
                                                           07/17              08/19                   Boiler: Boiler erction started on 12.01.18.. Boilerr
                                           U-4 270         07/17      09/17 09/19           9/19      drumlifted on 28.03.18. Boiler hydro test completed on
                                                           09/17              10/19                   04.11.18.
                 Original Estd. Cost /Latest Cost Rs. 7290.60 Crs./ Rs.8536.98 Crs (including         TG: TG civil work staretd on 06.11.15. Condenser
                                                  FGD system)                                         erection started on 29.11.18. TG erection started on
                    Expenditure during 2015-16 Rs. 1000 Crs.
                                                                                                      10.01.19.
                    Expenditure during 2016-17 Rs.
                    Expenditure during 2017-18 Rs.                                                    Unit 3:
                    Expenditure during 2018-19 Rs.                                                    Boiler: Boiler erction started on 11.01.18... Boilerr
                             Total Expenditure Rs. 4505.49 Crs. ( 2/19)                               drumlifted on 28.03.18. Boiler hydro test completed on
                                  Approval date:                                                      26.11.18.
                                      Zero date: : 21.03.15                                           TG: TG civil work staretd on 04.12.15..
                               Financial closure    Power Finance Corporation Ltd sanctioned loan     Unit 4:
                                                    for an amount of Rs.5832.34 Cr. vide Letter       Boiler: Boiler erction started on 08.03.18.. Boilerr
                                                    dated- 03.06.2015                                 drumlifted on 21.08.18.
                             Main Plant Order       EPC order placed on BHEL on 21.03.15.             TG: TG civil work staretd on 04.12.15.
                                BOP Package
                                  Type of fuel      CoalMinistry of Coal sanctioned 4.2 MTPA for    BoPs:
                                                    BTPS                                             CHP: conveyer package-5% completed. Stacker
                                                                                                      Reclaimer-5% completed.
                                           PPA Yet to be entered and under process.
                                                                                                     AHP: 5% completed.
                       Power Evacuation system Shall be ready by January 2019.
                                                                                                     Cooling Tower: 72% completed.
            1.      State Government Permission: As directed by Govt. of Telangana State vide
                    letter from Chief Minister Office, i.e. Lr No. 177/PrlSCM/2014, Dt-1.12.2014     Chimney: 75% completed.
            2.      Water Allocation: State Govt. has allotted for drawl of 1.4 TMC of water per     PT Plant, DM Plant CW treatment plant: Works not
                    year@ 45 cusec from Godavari river vide G.O.Ms.No. 03, dt-07.01.2015              started.
            3.      Civil Aviation Clearance for Chimney: NOC issued by AAI vide Ref.No.             FGD: Agency not finalized yet.
                    AAI/SR/NOC/RHQ dt:11.12.2015
            4.      Environmental Clearance from MoE&F& CC, Gol.: EC obtained on Dt:
                    15.03.2017.
            5.      State PCB Pollution Clearance for water & Air (Consent for Establishment):
                    Obtained on 30.03.2017
 Critical issues
 Reasons for Delay             Work held up due to order from National Green Tribunal (NGT) and non-availability of MoE&F clearance
                                                                                  87
                                                                   Commissioning Schedule
Sl. No.              Project Details             Capa-city                                                               Broad Status
                                                  (MW)          Original    Actual(A)/ As
                                                                                 Expected
                                                              Syn.      COD     Syn.      COD
                                                             Comm              Comm
  State Sector
  3     Yadadri TPP (TSGENCO)                     4000                                                 Civil Works in progress. U #1 & 2 Boiler erection
        Distt. Nalgonda,                                                                              expected to start by 03/19.
        Telangan
                                                                                                        FGD: Included in the revised LOA placed on M/s.
                                           U-1    800      07/20     10/20        07/20       10/20
                                                                                                        BHEL. Scheduled completion of Unit with the new
                                                            09/20                 09/20
                                            U-2 800        07/20     10/20        07/20       10/20     norms is as follows: U-1 & 2 – 08/.20
                                                            09/20                 09/20                 U-3,4 – 04/21 and U-5 – 08/21
                                            U-3 800        03/21     6/21         03/21        6/21
                                                            05/21                 05/21
                                            U-4 800        03/21     6/21         03/21        6/21
                                                            05/21                 05/21
                                            U-5 800        07/21     10/21        07/21       10/21
                                                            09/21                 09/21
                  Original Estd. Cost /Latest Cost Rs. 29965.48 Crs.
                     Expenditure during 2015-16 Rs. 486 Crs
                     Expenditure during 2016-17 Rs.
                     Expenditure during 2017-18 Rs.
 Critical issues
 Reasons for Delay               Work held up due to order from National Green Tribunal (NGT) and non-availability of MoE&F clearance
                                                                                    88
                    BROAD STATUS OF THERMAL POWER PROJECTS IN KARANATAKA
                                     Unit                   Commissioning Schedule
Sl.          Project Details                Capacity     Original   Actual(A)/ As                           Broad Status
No.                                          (MW)                        Expected
                                                         Syn.   COD    Syn.      COD
                                                       Comm          Comm
State Sector
1. Yelahanka Combined Cycle           1     370                                 Unit 1:
     Power plant.                           GT         10/17          03/19             Main Plant: GT erection started on 1.03.17. GT
    Karnataka                                                                             and Generator erected, GTG Aux. erection is in
                                            ST         02/18           03/19              progress (90%). GT Aux. erection is in progress
       Original Cost / Latest Cost :Rs 1571.18 Crs / Rs. 1571.18 Crs                      (50%). STG HIP module, Generator erected. LP
      Exp. during 2016-17          : Rs 215.668 Crs                                       turbine erection under progress. ST Aux. erection
      Exp. during 2017-18          : Rs 932.1737 Crs                                      is in progress (45%). HRSG: Leak test
      Exp. during 2018-19            : Rs 114.38 Crs ( 2/19)                              completed, box up completed and insulation
                                                                                          work in progress. Cranking expected in 3/19.
       Total Expenditure           :Rs 1262.23 Crs (up to 2/19)
                                                                                          Syn expected in 4/19.
       Approval date:                                                                   STG building structural erection 92% completed.
       Zero date:                  : 09.11.2015                                           GTG building 92% completed. BFP/GBC – EOT
       Financial closure           :                                                      Crane girder and EOT erection works completed.
       Main Plant Order            : M/s BHEL                                           BOPs:
       HRSG Civil Work              M/s BHEL                                            Chimney: 23/23 Chimney shells erected up to
       Type of fuel                   Gas                                                 58.5-meter height (Full Height).
       PPA                         : PPA agreement is under review.                     CT:   Civil work is in progress. 95% completed.
                                                                                        CW system: CW piping pre assembly works is in
       Power Evacuation system        Power evacuation work is entrusted to M/s.KPTCL
                                                                                          progress (joint welding) of 139/139 joints and
                                      and work is nearing completion..                    CW pipe laying work is in progress(379/379mtr).
                                                                                        PTP: Civil works in progress.
         Land: 102.33 acres of land possessed by KPCL.                                 DM Plant: Commissioning of Equipments is in
         MOE&F: NOC obtained on 01/09/2015.                                              progress.
         SPCBC: NOC obtained on 02/12/2015.                                            Switch Yard: Bay 1,2 & 3 Tower / Equipment
         Gas allocation/FSA: KPCL & GAIL entered Gas Transport & Supply agreement erection work completed. Bay 1 & 2 equipment
            on 24.06.2017. M/s. GAIL have started piping works.                           testing, commissioning & civil works completed.
         Civil Aviation: NOC obtained from Airports Authority of India on 05/05/2015.    Bay 3 equipment erected, testing, commissioning
         Water: 15 MLD from Jakkur tertiary treated water plant.                         & civil works is in progress.
                                                                                        FPS: 1590/1700 mtrs fire hydrant pipes laid
                                                                                          underground. 20 mtrs hydraulic test under
                                                                                          progress. HVWS piping for seal oil pit
                                                                                          completed, erection of deluge valve & hydro test
                                                                                          pending.
                                                                                        Air Conditioning & Ventilation: Duct fabrication
                                                                                          work in progress. Supplies in progress.
                                                                                        Control & Instrumentation: Control panel erected
                                                                                          and cable laying work in progress.
                                                                                        LT Switch gears: panel erection work completed
                                                                                          and cable laying work in progress.
                                                                                        Cables(Power/Control): Cable tray erection works
                                                                                          is in progress.
                                                                                        Generator Transformers: GT/ST transformer
                                                                                          received and erection completed and testing in
                                                                                          progress..
                                                                                        Unit Transformers: UATs erected and testing of
                                                                                          UAT – completed. Testing of UAT-2 is in
                                                                                          progress.
                                                                       89
                         BROAD STATUS OF THERMAL POWER PROJECTS IN TAMIL NADU
                                                                          Commissioning Schedule
Sl. No.            Project Details              Unit     Cap-                                                                    Broad Status
                                                No.      acity     Original     Actual(A)/ As
                                                        (MW)                          Expected
                                                                  Syn.      COD    Syn.       COD
                                                                 Comm             Comm
  State Sector
  1     Ennore SEZ SCTPP                          1      660      01/18     03/18    06/20     08/20            Boiler (M/s BHEL): Design & Engineering work, site
        TANGEDCO (Distt. Thiruvallur)                             01/18              07/20                       leveling and site office work are in progress.
        Tamil Nadu                                   2     660    03/18       05/18  09/20        11/20         Due to Court case/ High Court order work held up at
                                                                 03/18               10/20                       site from 10/15 onwards. M/s TANGEDCO filed
                   Original Cost/ Latest Cost      : Rs. 9800 Crores (Includes cost of FGD, ECHS and             Special Leave Petition (SLP) in the Supreme Court of
                                                   IDC)                                                          India, hearing/arguments completed on 08/02/16.
                                                                                                                 However, judgment in favour of TANGEDCO came
          Total Expenditure (up to 1/19)         : Rs 3102.96 Cr.                                                on 18/10/16 only and work at site commenced with
                              Approval date:      : 12/12/2005                                                   effect from 02/11/16. Tripartite agreement between
                                 Zero date:       : 27/09/2014                                                   TANGEDCO, PFC( Lender),& M/s BHEL ( EPC
                                                                                                                 contractor) signed on 21.11.16. and Loan agreement
                           Financial closure       Six months from the date of Award.                            between PFC and TANGEDCO signed on 18.01.17.
                          Main Plant Order       : Order placed on M/s. BHEL (EPC- Rs. 7688 Crores)             Construction water supply available at site.
                                                  on 27/09/14.                                                  Compaction Piling work for Chimney, Boiler Unit-
                              BOP Package                                                                        I,II, T.G.Unit I,II, CT-I, II etc. completed.
                               Type of fuel      : Long term Coal Linnkage application submitted on             Material supply in progress
                                                26.02.2010 to Ministry of Coal/GoI/New Delhi for supply          Unit-I
                                                of coal. Coal allocation is yet to be received. However,         Boiler: Boiler erection started on 15.09.17. HT
                                                MoU has lready been signed beween MMTC &                         expected by 11/19. TG Civil works started in 5/17.
                                                TANGEDCO on 25.06.2012 for the supply of 100%                    Unit-II
                                                imported coal.                                                   Boiler: Boiler erection started on 08.06.18. HT
                                        PPA        N.A. State sector project. Entire power will be utilised by   expected by 11/19. TG Civil works started in 5/17.
                                                   Tamil nadu
                    Power Evacuation system        Power will be evacuated from the proposed thermal
                                                   power station through double circuit 400 KV
                                                   transmission lines i.e, through 2 Nos. Of 400 KV line
                                                   to 765 KV Pooling Station and 2 Nos. 400 KKV lines
                                                   to ETPS Expansion STPP.
             Land: Aquistion of land does not arise since own land of TANGEDCO ( Out of
              1100 acres available at Ash dyke of NCTPS, only 500 acres utilised for project
              development).
             MOE&F: NOC obtained on 07/01/2014.
             SPCBC: NOC obtained on 11/03/2014.
             Civil Aviation: NOC obtained from Airports Authority of India
 Critical issues
 Reasons for Delay
                                                                                     90
                                                                      Commissioning Schedule
Sl. No.           Project Details              Unit Capa-                                                               Broad Status
                                               No.   city       Original    Actual(A)/ As
                                                    (MW)                          Expected
                                                               Syn.     COD    Syn.       COD
                                                              Comm            Comm
  State Sector
  2     Uppur SCTPP TANGEDCO at                 1     800     02/19     04/19   02/20       09/20    BTG & allied civil work related to BTG as one EPC
        Distt. Ramnad, Tamil Nadu                             03/19             04/20                 package, order placed on BHEL on 27.02.16.
                                                2     800     06/19     11/19   08/20       02/21    Boiler Civil Works stated on 20.05.16. Boiler
                                                              07/19             10/20                 erection started in 01/17.
                  Original Cost /Latest Cost   : Rs. 12778 Crs. (BTG cost –Rs. 5580 Crs.)            BOP Packages (CHP/AHP/CT/Chimney/PT
                                                                                                      Plant/DM Plant/CW system/Switchyard/FPS/ACV &
                Expenditure during 2016-17     :Rs. 1674 Lakhs
                                                                                                      FO system) awarded to M/s. Reliance Infra Strucure
                Expenditure during 2017-18     :Rs. 20971 Lakhs
                                                                                                      Ltd, Mumbai on 21.2.2018.
                Expenditure during 2018-19     :Rs. 49382 Lakhs
             Total Expenditure (up to 2/19)    :Rs. 72027 Lakhs (up to 2/19)
                                                                                                    BTG package by M/s BHEL
                             Approval date:                                                         Geo Technical Investigation work completed on
                                 Zero date:    20.05.2016                                           05.12.2017.
                           Financial closure   Financial tie-up is proposed with M/s PFC.           Casting of test piling work commenced on 16.01.2017
                                                                                                    and completed on 19.07.2018.
                         Main Plant Order   : Order placed on M/s. BHEL (BTG- Rs.
                                                                                                    Design, Engineering, documents approval in progress.
                                            5580Crores) on 27/02/16.
                                                                                                    Storage yard Developed 1,60,000 sq.m
                            BOP Package : Awarded to M/s. Reliance Infra Strucure Ltd, Mumbai
                                                                                                    BTG Materials – BTG Materials – 85745 tonnes ;
                                            on 21.2.2018.
                                                                                                    Structural and reinforcement materials – 24940 tonnes
                              Type of fuel : COAL MoU entered with MMTC for supply of
                                                                                                    received at site.
                                           imported coal of 5.02 MTPA on 25.05.2015.
                                      PPA
                   Power Evacuation system 765 KVA
             Land: Out of 995.16 acres of land, Government Poromboke Land for 227.36                                               No. of      Balan
              acres and private patta lands of 767.80 acres. Around 192.36 acres of Govt. land                            Total      piles       ce to
                                                                                                               Locati
                                                                                                      Sl.No               No of    complete       be
              in BTG area has been handed over by TANGEDCO to M/s BHEL on 21.07.2016                            on
                                                                                                                          piles     d as on     compl
              for project preparatory works. The District Collector/ Ramnad has accorded                                            31.1.19      eted
              enter upon permission to the patta land not covered under litigation for an extent
              of 407.74 acres to TANGEDCO on 03.08.2017. Out of this, around 63 acres of                      Unit-I
              patta land in BTG area has been handed over by TANGEDCO to M/s BHEL on                    1.    ESP            665       665        -
              03.08.2017. 552 Acres of land handed over to M/s RIL, BOP contractor on                         Unit-I
              17.03.18. Balance land pending for enter upon due to litigation is around 354             2.                   778       660       118
                                                                                                              Boiler
              acres.                                                                                          Unit-II
           MOE&F: Ministry of Environment and Forest has accorded clearance for the                    3.                   665       665        -
                                                                                                              ESP
              above Project on 18.05.2016.                                                                    Unit-II
                                                                                                        4.                   778       622       156
           SPCBC: CRZ committee of MOEF recommended the Project on 28.1.16 and                               Boiler
              MOM published in web site on 8.2.16.
            Civil Aviation: NOC obtained from Airports Authority of India on 22.11.2012            Balance of Plant by M/s Reliance Infrastructure Ltd.,
               valid up to 21.11.2019.                                                              Topographical survey work commenced on 10.09.2018
           Water: Tamil Nadu Maritime Board has issued NOC for construction of Jetty for           and in progress.
              drawal and discharge of cooling water, vide 27.4.2015.                                Geo-technical Investigation work under progress.
 Critical issues
 Reasons for Delay
                                                                                 91
                                                                       Commissioning Schedule
Sl. No.            Project Details              Unit    Capa-                                                                   Broad Status
                                                No.      city       Original    Actual(A)/ As
                                                        (MW)                        Expected
                                                                   Syn.     COD    Syn.     COD
                                                                  Comm            Comm
  State Sector
  3     North Chennai TPP            St-      1     800    02/19 04/19                11/19      12/19     Boiler: Boiler erection works started on 30.08.17 All
        III by TANGEDCO (Distt.                           03/19                      12/19                  Ceiling girders and Silencer were erected. All Wall
        Thiruvallur), Tamil Nadu                                                                            beams erected. Air preheater Structural erection work is
                       Original Estd. Cost : Rs. 637600 Lakhs                                               in progress. So far 16631 MT erected. Pressure part
               Expenditure during 2009-10 : Rs 2.206 Lakhs                                                  erection started on 26.10.2018 and so far 2199 MT
               Expenditure during 2010-11 : Nil.                                                            erected. Bunker(LHS)&(RHS)- 4th tier erection
               Expenditure during 2011-12 : Nil.                                                            completed. Bunker shell fabrication is in progress. Boiler
               Expenditure during 2012-13 : Rs 20.59 Lakhs                                                  goods cum passenger lift erection upto 5th tier erected.
               Expenditure during 2013-14 : Rs 39.56 Lakhs                                                  ESP erection works commenced on 15.07.2017. So far
               Expenditure during 2014-15 : Rs 12.94 Lakhs                                                  8957 MT erected (78.16% ). ESP outlet flue gas duct
               Expenditure during 2015-16 : Rs 25.30 Lakhs                                                  guillotine gates erected.. HT expected in 07/19.
               Expenditure during 2016-17 : Rs 19808.75 Lakhs                                             TG: TG civil work completed. Deck cast completed on
               Expenditure during 2017-18 : Rs 92975.44 Lakhs                                               27.08.2018.Condenser A &B -Hot well erection and side
               Expenditure during 2018-19 : Rs 207048.00 Lakhs ( 2/19)                                      wall joint welding is in progress. Conderser B -front side
            Total Expenditure (up to 2/19) : Rs 319932.786 Lakhs                                            tube sheet erected in position. TG Flash tanks 2nos
                               Zero date: : 29/01/2016                                                      placement in position.Turbine component pre-
                                                                                                            assembly/checking is in progress. Bearing Pedestal
                         Main Plant Order : 29/01/16 (EPC) on M/s. BHEL- Rs.2759 Crores.                    centering &leveling under progress. TG hall EOT cranes
                                              Boiler: Alstom, TG & generator: Siemens & BHEL                (2Nos.) load test completed on 19.12.2018. Cranes are
                              BOP Package 28.10.2016 (EPC) on M/s BGRESL- Rs.2600 Crores.                   in operation. Generator stator reached site on 25.07.2018.
                                Type of fuel : COAL                                                         Generator anchor plate matching under progress.CW pipe
                                        PPA :Entire power is to be utilized by TANGEDCO.                    at condenser end- Return lines erected and encasing
                   Power Evacuation system : The power generated from this plant is proposed to             completed..
                                               be evacuated through a 765 KV DC feeder to the             BOPs
                                               proposed North Chennai Pooling Station and 765KV            BOP package was awarded to M/s.BGRESL, Chennai
                                               DC link line feeder to the proposed Ennore                   under EPC basis on 28.10.2016 at a total value of
                                               Replacement Power Plant which will be established            Rs.2600.02 Crs.
                                               by TANTRANSCO                                               CHP:        External       Conveyor-1C/1D,2A/2B,4A/4B,
             MOE&F Clearances obtained on 20/01/2016.                                                      5A/5B,6A/6B-Foundation work under progress. Column
                                                                                                            works upto plinth beam 10/10nos completed. Slab
             SPCB clearance obtained on 13.04.2017
                                                                                                            shuttering work in progress. Coal setting basin: Raft
             Civil Aviation: clearance obtained on 15/05/2013
                                                                                                            completed on 8.2.2019 and wall 43mtrs 1st lift
             Water allocation: Water requirement for the project will be met from existing fore bay of     completed. CHP- Stock yard paving &Drain work in
              NCTPS stage-II. The make-up water for cooling tower, boiler make-up & other sweet             progress. ICHS-Iternal Tower-9Nos.: All civil work
              water requirements are to be met from proposed desalination plant for this project.           completed. Internal Conveyor 1A/1B,2A/2B,3A/B- Civil
              Construction water from M/s.CMWSSB available to the contractor from 07.01.2017                work completed.Mechanical erection work under
             FSA: MOU has been entered with M/s. MMTC for supply of imported Coal of 2.51                  progress. For other ICHS conveyors-Civil works are in
              MTPA on 25.05.2015. Action is also being initiated for getting indigenous coal also.          progress.
                                                                                                           AHP: Fly ash silo-1: Raft completed, column &slab work
                                                                                                            upto 14.8m level completed.Lift wall completed.Piling
                                                                                                            completed. For Silo 2: Shell contruction under progress.
                                                                                                            Bottom Ash silo: Slab @14.8m level decking and rebar
                                                                                                            work is in progress. Dry Bottom ash system:Civil
                                                                                                            foundation work completed .Pedestal final lift works
                                                                                                            under progress.
                                                                                                           Cooling Tower: NDCT -Pond wall -100% completed.
                                                                                                            NDCT-Shell jump from 22nd lift completed.
                                                                                                           Chimney: Chimney shell 269 Mtr completed. 100%
                                                                                                            completed as on 7.7.2018. Platform & flue can fabrication
                                                                                                            erection workcompleted. Slab works completed.
                                                                                                           Switch Yard: 765KV GT bay Tower pedestal completed.
                                                                                                            765KV GIS side wall brick work under progress.
                                                                                                            230KV brick work completed & painting under
                                                                                                            progress. GIS rooms-Column cast work under progress.
                                                                                                           Considering the revised emission norms, In principle
                                                                                                            approval was given to M/s.BHEL for making in boiler
                                                                                                            modification to achieve the NOx reduction from 510
                                                                                                            mg/Nm3 to 300 mg/ Nm3 on 18.08.2016 and commercial
                                                                                                            acceptance was given on 31.03.2017.
                                                                                                           FGD is not included in the scope of both BTG and
                                                                                                            BOP package. Opininon of consultant sought for
                                                                                                            regarding the type of technology to be adopted for
                                                                                                            FGD and allied issues like water availability, disposal
                                                                                                            of gypsum etc.
 Critical issues
 Reasons for Delay
                                                                                      92
                                                                           Commissioning Schedule
Sl. No.               Project Details                Unit Capa-                                                                Broad Status
                                                     No. city        OriginalActual(A)/ As
                                                          (MW)                    Expected
                                                                    Syn. COD    Syn.       COD
                                                                   Comm        Comm
  State Sector
  4     Ennore SCTPP                                  1    660    10/17       01/18    05/19    -           Boiler (M/s Lanco): Civil work commenced on
        TANGEDCO (Distt. Thiruvallur),                             01/18               06/19                 16/02/15. Boiler erection started on 01/02/16
        Tamil Nadu                                                                                          TG & Condenser: Civil work commenced on
                 Original /Latest Cost   (03/2016)   :Rs 495600 / 542138 Lakh                                18/06/15. Condenser erection started on 20/07/16 & TG
                                                                                                             erection started on 11/08/16.
                      Expenditure during 2014-15 :Rs. 23970 Lakh                                             BOPs
                      Expenditure during 2015-16 :Rs. 288.91 Lakh                                           Chimney: Awarded to LITL, Gurgaon. Chimney raft
                      Expenditure during 2016-17 :Rs. 8656.09 Lakh                                           casting commenced on 22/07/2015. Shell concreting
                      Expenditure during 2017-18 : Rs.46225.0 Lakh                                           work started on 29/02/16, Shell casting completed in
                                                                                                             3/2/16.
               Total Expenditure (up to 12/2017) :Rs. 79140 Lakh
                                                                                                            CHP: Awarded to M/s. FL SMIDTH (P) Ltd. Chennai
                                  Approval date:
                                                                                                             on 23/04/15. 70:30 Imported: Domestic Coal. The soil
                                      Zero date: : 14/07/2014                                                investigation work commenced on 01/08/2015.
                                 Financial closure                                                           NOC/ROW (Statutory clearance) approval has been
                               Main Plant Order      : 30/05/2014 (EPC) on M/s LANCO and lanco in            obtained from PWD for routing ECHS from North
                                                     turn awarded the BTG to Dong Fang electric              Chennai to project site through Ennore Creek. The CE
                                                     corporation, China on 18/02/15. EPC cost                / PWD recommended the proposal for the waiver of
                                                     Rs.3921.55crs. (revised)                                track rent to Government on 18/11/2015 and Go TN
                                   BOP Package                                                               has not considered the case. LITL remitted the Lease
                                                                                                             rent & refundable caution deposit to PWD on 26/11/15.
                                    Type of fuel      : COAL (70:30 Imported: Domestic Coal)
                                                                                                            CW System: Awarded to Kirloskar Brothers Ltd and
                                           PPA        PPA does not arise as the entire power is to be        Sea water intake & outfall system-off shore to M/s
                                                      utilized by TANGEDCO.                                  Coastal Marine construction and Engineering Ltd,
                         Power Evacuation system Regarding Power Evacuation system is under                  Mumbai on 07/09/15. Intake pump house earth
                                                      TANRANSCO scope.                                       excavation under progress. The earth work excavation
             Letter of Acceptance for Main Plant Order (EPC) issued to M/s LANCO on 05/14 (27/02/14         in cooling water intake pump house was commenced
              asper lr dt 22/12/16). LANCO in turn placed order on Dong Fang Electric Corporation.,          on 07/09/2015 and in progress. LITL committed to
              China on 18/02/15.                                                                             complete the permanent marking along the route by
             MOE&F Clearances obtained on 18/09/2014.                                                       31/12/15.        Obtaining approval from various
             SPCB clearance obtained on 18/02/13.                                                           departments is a time consuming process hence M/s
              Civil Aviation: clearance obtained on 16/05/2008                                              LITL was requested to arrange statutory clearance from
             Water allocation: Sea water is available near the project. Cooling water consumption to be     Railways, Highways, Chennai Corporation, TNHB etc.,
              drawn from Sea is 1,33,896 m3/day.                                                             as early as possible.
                                                                                                            NDCT: Awarded to M/s Hamon Thermal Europe S.A
              Corporate Insolvency & Bankruptcy Process (CIRP) initiated against                             on 05/05/15. All the 768 piles casting completed on
              LITL(the EPC Contractor) by IDBI Bank from 07.08.2017 and interim                              08/02/16. The earth work excavation for pile cap
                                                                                                             commenced on 15/10/2015 and pile chipping
              resolution professional appointed on 10.08.2017 and hence the project has
                                                                                                             commenced on 16/12/15. Basin piling work under
              been stalled rom 07.08.2017. The CIRP process extended up to 04.05.2018.                       progress.
                                                                                                            FO System: Award to M/s General Mechanical Works
                                                                                                             Pvt. Ltd – Vadodara on 12/10/15.
                                                                                                            Switchyard: Switchyard and related electrical systems
                                                                                                             are yet to be awarded.
 Critical issues
 Reasons for Delay
                                                                                      93
                                                                       Commissioning Schedule
Sl. No.              Project Details                 Unit Capa-                                                              Broad Status
                                                     No. city        Original   Actual(A)/ As
                                                          (MW)                      Expected
                                                                    Syn.    COD   Syn.      COD
                                                                   Comm          Comm
  Private Sector
  5    TuiticorinTPP St-IV / M/s SEPC                 1    525      07/18   10/18       11/19   12/19    Boiler: EPC contractor is M/s MEIL, in turn they
       Power Pvt. Ltd.                                             09/18                12/19             awarded the BTG package to M/s BHEL on 30/10/15
       (Distt. Tuticorin), in Tamil Nadu                                                                  and main plant civil work to M/s L&T Geo Structures
                             Original /Latest Cost   : Rs. 351400 Lakh / Rs. 351400 Lakh                  Ltd. Boiler civil work started on 15/12/15 & erection
                                                                                                          started on 15/12/16. Boiler Drum lifted on 13.8.17.
                       Expenditure up to 2015-16     :: Rs.48079 Lakh                                     Hydro Test (drainable) done on 28.12.18.Bolier hydro
                      Expenditure during 2016-17     : Rs.24870 Lakh                                      Test(non drainable) completed on31.01.2019.
                      Expenditure during 2017-18     : Rs.82294 Lakh                                     TG civil work started on 01/06/016. TG erecction
                      Expenditure during 2018-19     : Rs.35322 Lakh (up to 02/ 2019)                     started on 8.9.17
                Total Expenditure (up to 2/ 2019)    :Rs. 190565 Lakhs                                    BOPs:
                                       Zero date     : 30/10/2015                                        CHP, AHP, CT, Chimney, PT and DM Plant, CW
                              Main Plant Order     : 18/01/2014 (EPC) on M/s MEIL & in turn BHEL          system, Fuel oil system and all other systems related to
                                                   for BTG.                                               power evacuation, switchyard including C&I, Fire
                                    Type of fuel : COAL Imported coal to be tied up in 6 months.          protection system, air-conditioning & ventilation etc.
                                            PPA :PPA signed with TANGEDCO and approved by                 are all awarded to M/s MEIL on 18/01/14. It is all the
                                                   TNERC                                                  part of EPC package.
                         Power Evacuation system  For power evacuation 2x400 Kv line has been           CHP: Awarded to M/s Lepton for Engineering
                                                      approved by TANGEDCO and is to be                   consultant & Monitoring agency for ICHS. Civil
                                                      implemented by TANGEDCO/                            foundation work is nearing completion. Mechanical
                                                      TANTRANSCO. The work is yet to be                   structural fabrication & erection under progress.
                                                      awarded.                                           AHP: Awarded to M/s Macwalber Beckay Civil
                                                                                                          foundation work is in progress. Mechanical structural
           Main Plant Package Awarded on EPC basis to M/s MEGHA Engg .and Infrastructures Ltd.
                                                                                                          fabrication erection under progress.
            (“MEIL”) on 18/01/14. M/s MEIL in turn awarded the BTG package to M/s BHEL on
            30/10/2015.                                                                                  Cooling Tower: M/s MEIL awarded the IDCT works
                                                                                                          to M/s Paharpur, civil works are nearing completion.
           CPCB & MOE&F Clearances obtained and valid up to 10/11/18 and 03/11/17 respectively.
            MOE & F clearance extended up to 3.11.2020                                                   Chimney: M/s MEIL awarded the chimney works to
                                                                                                          M/s Paharpur. Foundation works completed. Shell
           Civil Aviation: Clearances obtained and valid up to 17/12/2021
                                                                                                          concreting completed up to 275 mtrs. Inside brick wall
                                                                                                          work under progress.
                                                                                                         CW System: CW packages awarded to M/s Flowserve.
                                                                                                          Civil works are in progress.
                                                                                                         Switchyard: Civil work are nearing completion.
 Critical issues              1)Inter-connection & Transmission facilities are by TANGEDCO which is yet to be awarded. The COD is linked to the availability of
                              Start up Power. (2) Approval/NOC from Department of Forests, GoTN for pipeleine and conveyor crossing. (3) Fixation of revised
                              date of availability of start up Power and accordingly the SCOD at TNERC. (4) Approval of Coal Supply, Transport and Handling
                              Agreements by TANGEDCO and TNERC.
 Reasons for Delay
                                                                                    94
                                                                           Commissioning Schedule
Sl. No.              Project Details               Unit   Capa-                                                          Broad Status
                                                   No.     city      Original     Actual(A)/ As
                                                          (MW)                         Expected
                                                                    Syn.      COD    Syn.       COD
                                                                   Comm             Comm
  Private Sector
  6    Tuticorin TPP in Tamil Nadu                  1     660      03/12      05/12    06/19   19-20     Boiler: All civil work completed & Boiler
       (Ind. Barath Power Limited)                                 05/12               19-20              erection started.
                                                                                                         ESP: All civil foundation work completed.
                           Original /Latest Cost : Rs.359500 Lakh / Rs.359500 Lakh                        Erection started.
                                                                                                         TG: All civil foundation work completed.
                     Expenditure during 2010-11     : Rs. 17000 Lakh                                      Condenser & TG erection works yet to start.
                     Expenditure during 2011-12     : Rs 2000 Lakh
                     Expenditure during 2012-13     : Rs 31000 Lakh                                       BOPs
                     Expenditure during 2013-14     : Rs. 9000 Lakh                                      Chimney: Awarded to simplex Infrastructure.
                     Expenditure during 2014-15     : Rs. 91000 Lakh                                      Foundation raft concreting is in progress.
                     Expenditure during 2015-16     : Rs. 500 Lakh                                       CHP: Order placed on Sokeo Power.
              Total Expenditure(Up to 05/2015)       : Rs. 2000.00 Crores                                AHP: Order placed on Sokeo Power. Drawings
                                 Approval date:        : 10/09/2007                                       under finalization.
                                     Zero date:       : 25/03/2010 / April 2012                          ACC: Order placed on HAC China. Drawings
                               Financial closure       : Achieved on 24/02/2011                           under finalization. ACC foundation works in
                                                                                                          progress.
                             Main Plant Order          : 28/05/2010 (BTG) on M/s Shandong Runch Power
                                                                                                         M/s Consolidated Construction Consortium
                                                       Plant Engg and Technology Limited.
                                                                                                          Limited have been awarded main plant civil &
                                      Type of fuel : COAL
                                                                                                          structural work on 14/12/10. Civil work started
                                              PPA : Participating in the Bids                            WTP:         Order placed on Sokeo Power.
                         Power Evacuation system : BPTA signed with PGCIL on 24/02/2010. LTOA             Engineering works in progress.
                                                       signed with PGCIL on 12/06/2013.                  DM Plant:         Technical discussions are in
             Land: Total land of 880 acre acquired                                                       progress.
             Water: Agreement between IBPML and South Ganga was signed on 03/04/10.                     CW system: Order placed on Sokeo Power.
             MOEF: clearance obtained on 12/07/2010.                                                     Technical specification verification is in
             SPCB: Consent obtained on 17/10/2013.                                                       progress.
             Civil Aviation: clearance obtained on 24/08/10                                             FO system: Engineering is under progress.
             PPA: To be executed through case –I bidding.                                               FPS: Foundation works completed. Erection
             BPTA: signed with PGCIL on 24/02/2010                                                       works to start from 01/16.
                                                                                                         Switchyard: Engineering in progress.
 Critical issues              Work held up due to no PPA in the market.
 Reasons for Delay
                                                                                  95
                                                                        Commissioning Schedule
Sl. No.            Project Details              Unit    Cap-                                                              Broad Status
                                                No.     acity    Original     Actual(A)/ As
                                                       (MW)                         Expected
                                                                 Syn.     COD    Syn.       COD
                                                                Comm            Comm
  State Sector
  1     Udangudi STPP                            1      660     12/20     03/21    12/20       03/21    Preliminary works Engineering activities, Geo
        TANGEDCO (Distt. Thoothukudi)                           02/21              02/21                Technical works, Approach road works,
        Tamil Nadu                               2      660     12/20     03/21    02/21       05/21    Topographical survey , Jungle clearences and
                                                                02/21              04/21
                                                                                                        Temporary weigh Bridge Construction are
                   Original Cost/ Latest Cost   : Rs. 13076.70 Crores (Includes cost of Pollution       completed.
                                                Control Equipments & IDC)                                *Site levelling and Grading work under progress.
          Total Expenditure (up to 2/19)     : Rs 332.8515 Cr.                                          *Boiler foundation earthwork excavation started
                              Approval date: :                                                          and base concreting under progress.
                                 Zero date: :                                                           *Chimney earthwork excavation under progress.
                                                                                                        Captive Coal Jetty for Udangudi Power Project
                           Financial closure .
                                                                                                        *Topographical Survey,Land investigation,
                        Main Plant Order : Order placed on M/s. BHEL on 07/12/17. (EPC                  Bathymetry Survey, Marine investigation and
                                             Contract)
                                                                                                        Construction enabling activities completed.
                            BOP Package
                                                                                                        *Approach Pile and Pile cap construction
                              Type of fuel : COAL. MMTC clearance obtained on 19.11.2012
                                                                                                        activities are under progress in the off shore for
                                           (Import coal)
                                      PPA N.A. State sector project. Entire power will be utilised by   about 1 Km from shore are completed.
                                             Tamil nadu                                                 *Approach Pile and Pile cap construction activities
                   Power Evacuation system                                                              are started in the off shore from 4 Km
             Land: Out of 1040 acres of land, Government Poromboke Land is of 760 acres                from shore as a next reach.
              and private patta lands of 280 acres. Around 760 acres of Govt. land and 135              *Casting of PSC Girders and Accropode Pre casting
              acres of private land had been handed over by TANGEDCO to M/s. BHEL on                    are under progress.
              15.12.2017 for project preparatory works. Almost all 280 acres of private land            *Pre casting of deck slab are under progress.
              are inpossession of TANGEDCO except 11 acres which are under court case. 66               *Brake water construction and Construction of
              acres of land has been handed over to M/s. ITD cementation India Ltd. EPC                 compound wall work under progress
              contractor for Captive Coal Jetty.                                                        Unit-2 has a phase difference of 2 months
             MOE&F: CRZ clearance dt. 06.06.2011. Environmental clearance-14.10.2013
             Water: Intake of 21000 m3/hr and outfall discharge of 13500 m3/hr as perCRZ               Appointment of Consultants (For Plant) - Project
              clearance dt.6.6.2011                                                                     Management Consultancy LOA was issued to
                                                                                                        M/s.TATA Consulting Engineers Ltd., on
                                                                                                        19.02.2019 for engaging Project Management
                                                                                                        Consultancy services in the post award of EPC
                                                                                                        contracts till completion of
                                                                                                        entire project and consultancy services for
                                                                                                        preparation of tender specification, analysis of bid,
                                                                                                        award and post award PMC services until
                                                                                                        completion of the FGD & SCR.
                                                                                                        For Captive Coal Jetty - TANGEDCO Board has
                                                                                                        approved the proposed of consultancy services
                                                                                                        through IIT Madras on nomination
                                                                                                        basis and the same was approved by GOTN on
                                                                                                        07.02.2019.
 Critical issues
 Reasons for Delay
                                                                                   96
Eastern
Region
   97
                            BROAD STATUS OF THERMAL POWER PROJECTS IN BIHAR
                                               Unit                   Commissioning Schedule
Sl. No.            Project Details                    Capacity                                                                   Broad Status
                                                       (MW)        Original    Actual(A)/ As
                                                                                    Expected
                                                                  Synch    COD     Syn.      COD
                                                                 Comm             Comm
  State Sector
  1.    Barauni Extn TPS                        8     250         02/14           14.11.17(A)   05/18    Unit-8
        P.O.: Barauni,                                            05/14           11.01.18(A)            Full load achieved on 11.01.18.
        Dist: Begusarai Bihar
        (BSPGCL)                                                                 31.03.18(A)              Boiler: Boiler erection started on 10.12.12. Drum lifted on
                                                9     250         04/14          31.03.18(A) 06/18
                                                                                                          05/09/13. Erection of pressure part, ID/FD/PA Fans, APH,
           (2x250 = 500 MW)                                       07/14
                                                                                                          piping completed. HT done on 21/08/14. Non drainable Hydro
                                                                                                          Test completed. Boiler Light Up with LDO on 18.06.2017,
           Original /Latest Cost               :Rs 3666.06 Cr. / Rs. 5308.07 Cr                           SBO completed on 04.09.17. Synchronized on 14.11.17ESP:
          Expenditure during 2008-09           Rs 25.00 lakhs                                             Mechanical erection completed and one stream is ready
          Expenditure during 2009-10          :Rs 00.00 lakhs                                             for use. Another stream of ESP is in progress. Insulation
          Expenditure during 2010-11          :Rs 12500.00 lakhs                                          & cladding is under progress
          Expenditure during 2011-12          :Rs 25958.00 lakhs                                         TG: Erection of Condenser & TG started on 26/08/14 and
          Expenditure during 2012-13          :Rs 67706.00 lakhs                                          25/08/14 respectively. TG Boxed up on 31/12/15 .TG oil
          Expenditure during 2013-14          Rs 145630.00 lakhs                                          flushing completed in 12/16.
          Expenditure during 2014-15          :Rs 77058.00 lakhs
          Expenditure during 2015-16          Rs 87030.00 lakhs
          Expenditure during 2016-17           Rs 64041.00 lakhs                                         Unit-9
           Total Expenditure                  :Rs 479951 Lakhs (up to 03/17)                             Full Load achieved on 31/3/18.
           Approval date:
           Zero date:                         : 11.03.2011                                               Boiler: Erection started on 02-12-12, Drum lifted on 15.09.13.
           Financial closure                  : Achieved in 2015 with PFC                                 HT(D) done on 21.09.14. Boiler stage-1 hydro test of unit 9
           Main Plant Order                     The order for EPC was awarded to M/s BHEL on              was successfully completed on 21.09.2014. Non Drainable
                                                nomination basis on 11.03.2011                            Hydro Test completed on10.08.17. BLU done on 29.08.2017,
           BOP Package                          Order for BOP’s placed on                                ESP: Mechanical erection completed. Other works are in
                                               M/s Mc Nally Bharat Engg. Co. Ltd. for CHP on             progress.
                                                15.05.12.                                                TG: Condenser & TG erection started on 26/08/14. TG Boxup
                                               M/s Mc Nally Bharat Engg. Co. Ltd. for AHP on             completed 30.06.2016.
                                                15.05.12.
                                               M/s Gannon Dunkerley & Co. Ltd. for Chimney on
                                                19.04.12                                                 BoPs:
                                               M/s Paharpur Cooling tower for CT on 10.08.13.    Chimney: Completed in all respect including aviation light.
                                                                                                  CT: Erection of water distribution system, drift eliminators and
           Type of fuel                      Coal                                                  equipment completed for IDCT of unit#8 and unit#9.
           PPA                               Dt 31.12.2010                                        CW System: EOT crane erected. Erection of pumps and
                                                                                                   motors completed. Trail run is also under progress.
           Power Evacuation system        LILO at Barauni of Begusarai-Biharsarif 220KV D/C      CHP: The work of WT is on hold. WT civil work 60%
                                             done. Power evacuation system expected to be ready completed. Geo-Teck survey completed in wagon tipler, M/s
                                             by Dec-2015.                                          BHEL started the isolation of affected structure by cutting
             Land: Land acquired. except land required for ash dyke and intake water system       through M/s HILTI.Cutting work completed.Revisied layout
             Water Allocation: Approval for 60 cusec water from River Ganga has been obtained drawing is under approval of railway authority.
              from Irrigation Department, Govt. of Bihar. Approval for 45 cusec water from River  AHP: Order for civil work placed on M/s McNally Bharat.
                                                                                                   Vacuum pump house equipment erection completed. ASPH
              Ganga has also been received from Central Water Commission.
                                                                                                   building is ready and Ash slurry pumps erection completed.
             MOE&F Clearance: MoE&F clearance obtained on 08.05.14.                               Erection of ash silo under progress. Land for ash dyke acquired
             Civil Aviation Clearance: Aviation clearance obtained from AAI on03-08-09.           and possession of the same is u/p.Erection of ash pipe rack
                                                                                                   work is in progress. Contingency arrangement made for ash
                                                                                                   disposal in HFCL Pond (Ash Dyke) completed.
                                                                                                  PT Plant: Ready in service. Intake water system ready with
                                                                                                   temporary arrangement at Ganga.
                                                                                                         DM plant: Ready in service.
                                                                                                         FOS: HFO & LDO tanks erection completed. Insulation is
                                                                                                          pending.
                                                                                                         Switchyard: 220 kv switchyard charged on 03.03.2016. Station
                                                                                                          transformer of unit 8 & 9 erection, testing completed and got
                                                                                                          charged. 132Kv switchyard ICT -1&2 testing work u/p.GT of
                                                                                                          U8 erection completed and for U9 erection is u/p.
                                                                                                         FGD: Revised estimate for tender towards appointment of
                                                                                                          Project Management Consultant for “Feasibility study, selection
                                                                                                          of implementing agency and supervision of installation ,
                                                                                                          commissioning, testing & inspection till completion of project
                                                                                                          for installation of FGD ,SCR etc at 2X250MW extension
                                                                                                          project of Barauni TPS, Begusarai as per revised emission
                                                                                                          norms declared by MoEF&CC is under consideration
 Critical issues               1.   Construction of Ash dyke, Railway siding, Readiness of CHP, Intake Water System.
                               2.   Heavy water percolation in WT pit so work is on hold.
 Reasons for Delay             1.   Acquisition of land for laying water pipeline from river Ganga to power plant and Ash Dyke area
                               2.   Drainage facility for seepage water from Wagon Tippler area
                               3.   Readiness of Raw Water System and DM plant
                                                                                  98
                                               Unit                       Commissioning Schedule
Sl. No.           Project Details                     Capacity                                                              Broad Status
                                                       (MW)         Original    Actual(A)/ As
                                                                                      Expected
                                                                  Synch     COD     Syn.      COD
                                                                 Comm              Comm
  Private Sector
  2.   Siriya TPP                               U-1   660         08/14             Uncertain             Unit-1:
       (JAS INFRA)                                                                                        Boiler: Civil foundation of boiler, ESP & Chimney
       Village.: Siriya,                        U-2   660         12/14             Uncertain             completed.      Civil foundation of PHB & Mill-
       Dist.: Banka Bihar                       U-3   660         04/15             Uncertain             Bunker building under progress.          2730 MT
                                                                                                          Structural Steel in PHB erected. Fabrication of
           (4x 660 = 2640 MW)                   U-4   660         08/15             Uncertain
                                                                                                          9000MT Structural steel completed.
           Original Estd. Cost              :Rs 11,120.00 Cr.
           Latest Est. Cost                : Not Avialable                                                Unit-2:
          Expenditure during 2013-14                                                                      Boiler: Boiler foundation work was started.
          Expenditure during 2014-15           Not Avialable
          Expenditure during 2015-16                                                                      Unit-3: Civil works yet to start.
           Total Expenditure               : Not Avialable
           Approval date:                                                                                 Unit-4: Civil works yet to start
           Zero date:                      : 30.03.2011
           Financial closure               :
                                                                                                          Presently no work is in progress
           Main Plant Order                    M/s Dongfang Electric Corporation Ltd., China
           BOP Package
                                                                                                          at site.
           Type of fuel                        Coal
           PPA
           Power Evacuation system
              MOE&F Clearance: MOE&F Clearance received vide letter NO. J-13012/89/2008-IA.
               II(T) dated 29.06.2011
              SPCB Clearance: NOC for consent to establishment obtained from BSPCB.
              Civil Aviation Clearance: Aviation Clearance has been obtained from Airport Authority of
               India.
 Critical issues
 Reasons for Delay
                                                                                 99
                               BROAD STATUS OF THERMAL POWER PROJECTS IN JHARKHAND
                                               Unit                         Commissioning Schedule
Sl. No.           Project Details                      Capacity                                                                   Broad Status
                                                        (MW)           Original   Actual(A)/ As
                                                                                        Expected
                                                                   Synch      COD    Syn.       COD
                                                                  Comm              Comm
  Private Sector
  1.    Matri Shri UshaTPP                     U-1     270          03/12     05/12 Uncertain                       Phase-I
        M/s Corporate Power Ltd.                                    04/12
                                                                                                                 Unit-1:
        Distt. Latehar
                                                                                                                Boiler: Erection started on 05/10/10. Boiler
        Jharkhand                              U-2     270          04/12     06/12 Uncertain
                                                                                                                 drum lifted on 31/03/11. HT done on 28/12/11.
                                                                    05/12
                                                                                                                 Erection of 3/6 bunker completed.
            (4 x 270 = 1080 MW)
                                               U-3     270          09/12     10/12 Uncertain                   ESP: ESP is ready
                                                                    10/12                                       TG: condenser erection started on 25/05/11,
                                                                                                                 Turbine erection started 15/6/11. TG boxed up
                                                                                                                 in 10/12.
                                               U-4     270          12/12     01/13 Uncertain
                                                                    01/13
                                                                                                                 Unit-2:
                                                                                                                Boiler: Erection started on 19/12/10. Boiler drum
           Original Cost /Latest Cost          Ph.-I: Rs. 2900.00 Cr, Ph.-II: Rs.3182.00 Cr                      lifted on 19/07/11. HT completed on 10/12.
          Expenditure during 2008-09                                                                            ESP: ESP is ready
          Expenditure during 2009-10
          Expenditure during 2010-11
                                              Ph-I - .312000 Lakh Rs ( upto 11/12)
                                              Ph-II – 220700 Lakh Rs. ( upto 9/12)
                                                                                                                TG: condenser erection started on 24/08/11, Tube
                                                                                                                    insertion is under progress Turbine erection
          Expenditure during 2011-12
          Expenditure during 2012-13                                                                                started 13/10/11. HPT & IPT placed on the deck.
 Critical issues               1.Associated Transmission System for a short distance is to be taken up after Stage-II forest clearance is obtained.
 Reasons for Delay             Work held up due to payment issue with BHEL since 11/12. Commissioning Schedule
                               will be assessed after restart of work.
                                                                                  100
                                            Unit                           Commissioning Schedule
Sl. No.           Project Details                    Capacity                                                                    Broad Status
                                                      (MW)
                                                                      Original          Actual(A)/ As
                                                                                               Expected
                                                                 Synch         COD          Syn.       COD
                                                                Comm                       Comm
  Private Sector
  2    Tori TPP      Essar Power            Ph-I                                                                  Phase-I
                                             1        600         05/12      07/12       Uncertain                Unit-1:
           (Jharkhand) Ltd.
           Distt. Angarha                                         07/12                                            Boiler: Boiler erection started in 04/12.
                                                                                                                   ESP: Foundation work completed.
           Latehar Jharkhand
                                                                  08/12                  Uncertain                 TG Civil work started in 15.12.11; hall
                                              2       600         09/12        10/12                                  foundation completed. TG building
           (3x660=1980 MW)                                                                                            structural fabrication completed.
                                            Ph-II
                                            3                     10/15                  Uncertain
                                                                             12/15                                Unit-2
                                                      600        12/15
                                                                                                                   Boiler: Erection started in 15/12/13
           Original /Latest Cost          : Rs.570000 Lakh    Rs. 250000 Lakh                                      ESP: Foundation work completed.
                                               Phase-I            Phase-II                                         TG: TG civil work started on 15/12/13.
          Expenditure during 2009-10      : Rs 10641 Lakh     Rs. Nil
          Expenditure during 2010-11      : Rs. 42437 Lakh    Rs. 2825 Lakh
          Expenditure during 2011-12      : Rs.162489 Lakh    Rs. 13845 Lakh                                      Phase-II
                                                                                                                  Unit-3 –Work not yet started.
          Expenditure during 2012-13      : Rs. 32446 Lakh    Rs. 3172 Lakh
          Expenditure during 2013-14      : Rs. 96502 Lakh    Rs. 4760 Lakh
          Expenditure during 2014-15      : Rs. 37649 Lakh    Rs.    63 Lakh                                      BoPs:
          Expenditure during 2015-16        Rs. 66430 Lakh    Rs.    ---
          Expenditure during 2016-17        Rs. 23265 Lakh    Rs.    ---                                      Chimney: Order placed on M/s Essar
                                                                                                                 Projects India Ltd.. Windshield work
                                                                                                                 completed. Flue can fabrication 60%
           Total Expenditure             Ph-I: Rs.4718.59 Cr. (till 12/16)
                                                                                                                 completed.
                                         Ph_II: Rs.246.65 Cr(till 3/15)
           Approval date:                                                                                     CHP: Order placed on M/s Elecon engg
           Zero date:                                                                                            & Mcnally Bharat Engg.Co
           Financial closure             Achieved                                                             AHP:  Basic engineering completed.
                                                                                                              CT: Order placed on M/s SPIG Cooling
           Main Plant Order                Ph-I:
                                           18/08/2008 - Main plant Civil & Structural work on Essar Projects     Tower India Pvt. Ltd.
                                           (I) Ltd.                                                           PT & DM Plant: 40% material received.
                                            BTG on M/s Harbin Power (HPE) Engineering, China in 11/ 2008  FPS: Order placed on M/s Brijbasi Hi-
                                           Ph-II:                                                                tech Udyog Ltd on 15.11.10.
                                           Main plant Civil works on EPI Ltd on 26/02/2010 BTG on HPE         Switchyard: Order placed on M/s
           BOP Package                      Order for BOP’s placed on
                                                                                                                 Alstom T&D on 22/12/10
                                          M/s Mc Nally Bharat Engg. Co. Ltd. And Elecon Engg. For CHP on
                                           22.09.10 & 31.08.10.
                                          M/s Mc Nally Bharat Engg. Co. Ltd. for AHP on 15.09.11.           Presently no work is in
                                          M/s Essar Projects India Ltd. for Chimney on 18.08.10                 progress              due        to
                                          M/s SPIG Cooling tower India Pvt. Ltd for CT on 19.11.10.
           Type of fuel                    COAL
                                                                                                                      financial constraints
           PPA                               1.450MW+300MW with BSEB
                                             2.PPA signed with JSEB for 12% of the total power generated at
                                             variable cost under MoU route
                                             3. Draft PPA submitted to JUVNL for 13% of the total power generated
                                             at JSERC rates under MoU route.
        Power Evacuation system                BPTA signed with PGCIL and bay agreement executed. PGCIL is
                                               setting up 400KV substation near the project.
            Land 1210 acres of land required for both the Phases 1&II of (2x600 +1x600 MW) is available.
            BOPs are common for both units.
            MOEF clearance already available for U-I of Phase-I. Clearance for U-2 of Phase-I and U-3 Phase-II
             received vide MOEF letter dated 14.11.2013.
            Civil Aviation Clearance: NOC for height of chimney is valid tilltill 21.07.2020
            SPCB: Clearance obtained from JSPCB is valid till 31.03.2016
            Coal: Due non availability of MOEF clearance for the Chakla & Ashok Karkatta coal block
             allotted to this project it is proposed to import coal from Indonesia & Australia for the time being.
            Water Source of water is from Damodar and Amanat rivers which are 20 &30 KMs from the
             site.
 Critical issues            Mega Power Project status is yet being issued from MoP due to which 97% imported main plant equipment are lying at site/ Port.
                            Tapering coal linkage.
 Reasons for Delay           Reasons for Delay:- Delay in MoE&F Clearance` (14.11.2013 for U2 & U3), Change of design in water cooled condenser to air
                             cooled condenser due to water availability issue, Law & order issue, delay in grant of Mega power project status, cancellation of coal
                             block and non-availability of tapering / long term coal linkage etc.
                                                                             101
                       BROAD STATUS OF THERMAL POWER PROJECTS IN ODISHA
                                           Unit                   Commissioning Schedule
Sl. No.        Project Details1                   Capacity                                                                Broad Status
                                                   (MW)        Original   Actual(A)/ As
                                                                               Expected
                                                              Synch   COD    Syn.      COD
                                                             Comm           Comm
  State Sector
  1. Ib Valley TPP                          3      660        08/17   09/17      01/19   03/19 Unit-3:
      Village : Banaharpalli, Dist:                           08/17              02/19          Boiler: Chemical cleaning completed on 17-Dec-18, Steam
        Jharsaguda                                                                                Blowing is in progress.
      (OPGC)                                4      660       12/17 01/18     12/18      01/19  ESP 3: Mechanical Erection completed, Commissioning in
                                                             12/17          01/19                 progress.
      (2x660 = 1320 MW)                                                                         TG Unit-3: Barring Gear achieved.
        Original / Latest Cost           :Rs 1196500 Lakhs                                      Unit-4:
                                                                                                Boiler: All major work completed, synchronization on oil
       Expenditure during 2013-14        Rs         68690 lakhs                                   achieved.
       Expenditure during 2014-15       :Rs         56887 lakhs                                 ESP4: All field charged, commissioning completed.
       Expenditure during 2015-16       :Rs        108659 lakhs                                 TG Unit-4: Oil synchronization achieved.
       Expenditure during 2016-17       :Rs        208889 lakhs                                  There is an incident occurred where LP Turbine blade
       Expenditure during 2017-18       :Rs        63758 lakhs                                   failed at 3000 RPM before synchronization (on coal) so
        Total Expenditure (up to        :Rs       506883 lakhs                                   there is anticipation that COD Unit 4 might shift from
        06/17)                                                                                   Feb 19 to mar 19.
        Approval date:                                                                          Unit-3 Auxiliary Equipment:
        Zero date:                      : 26.03.2014                                             All major drives commissioning completed .
        Financial closure               : Achieved on 23.11.2012 (PFC and REC)                   Commissioning in Progress: TD BFP
                                                                                                Main Plant Civil & Structural Work: All major civil
        Main Plant Order                : NTP issued in 03/2014                                  work completed.
        BOP Package                      BTG order placed on M/s BHEL                           FGD Plant: Consultant finalized, Tender for EPC contract
                                                                                                 is published & Bidding in progress.
        Type of fuel                      Coal                                                   BoPs:
        PPA                               : PPA: 50% of the power generated shall be sold to  Chimney: Work completed.
                                          GRIDCO through a long term PPA based on CERC  CHP: 1 stream commissioning completed on 31-Jan-19,
                                          norms and balance 50% will be sold through mix of       coal filling is done in Unit 4, Unit 3 system is also ready to
                                          long term PPA (Case-1 bids) and short / medium term     receive coal.
                                          sales.                                                AHP: Unit 3;
        Power Evacuation system           Power evacuation through 2xD/C 400KV transmission       Bottom Ash erection completed, Fly ash erection and
                                          lines, one going to OPTCL’s 400kV substation at         pipe laying is in progress.
                                          Lapang and other to PGCIL’s 400KV pooling station.      Unit 4:
                                          Signed on 11.09.2013                                    Bottom Ash Commissioned, Fly Ash System-vaccum
        LAND: Required land is in possession of OPGC except the 97 acre of land for MGR          conveying system commissioned, Fly Ash conveying
            work.                                                                                 system commissioned, Silo commissioning in progress.
        MOEF: EC was granted on 04.02.2010, amended on 22.01.2014 and validity extended          Ash Pond:
            on 16.1.2015.                                                                         Phase 1 about to complete
        Coal linkage: Coal will be sourced from Manoharpur & Dip side Manoharpur allocated       Phase 2 work in progress.
            to OCPL, A JV subsidiary company of OPGC.                                           Cooling Towers: Commissioning of IDCT 3 & IDCT 4
        WATER: Agreement signed with water resource department on 26.08.2013                     completed.
        SPCB: Consent to establish was granted from OSPCB on 04.02.2010 and revalidation  PT Plant: Raw water and PT Plant both steam
            was done on 27.11.15                                                                  Commissioned
        CIVIL Aviation: Clearance obtained from AAI on 15.03.2010                              DM Plant: DM plan one stream commissioned.
                                                                                                CW System: All CW pumps commissioning complected.
                                                                                                  CW chlorination commissioning completed.
                                                                                                F P System: Pump House Commissioning work is
                                                                                                  Completed. Fire hydrant and spray pipe laying major work
                                                                                                  completed.
                                                                                                FO System:          LDO & HFO system Commissiong
                                                                                                  Completed.
                                                                                                Switchyard: Unit#3 and Unit#4. Switchyard back charged
                                                                                                  and under operation.
 Critical issues
 Reasons for Delay
                                                                           102
                                             Unit                 Commissioning Schedule
Sl.               Project Details                   Capacity                                                                Broad Status
No.                                                  (MW) Original Actual(A)/ As
                                                                              Expected
                                                             Synch COD     Syn.       COD
                                                             Com          Comm
                                                             m
 Private Sector
 2. Ind Barath TPP                            1     350   07/11 10/11 18.06.15(A) 20.07.16(A) Unit-1:
      M/s     Ind-Barath            Energy                09/11        25.02.16(A)            Full load achieved on 25.02.16. COD declared on
      (Utkal) Ltd.                                                                            20.07.2016.
     (Distt-Jharsuguda)                    2     350      10/11 12/11 Stressed
                                                          12/11                                Boiler: Boiler erection started in 01/11, Erection of
      (2x350 700 MW)                                                                            feeders & tripper, all bunkers & Liners erection and mills
       Original / Latest Cost           :Rs 3150.00 Cr. / 4001.00 Cr                            completed. SBO completed on 15.12.14. Drum lifted on
      Expenditure during 2010-11        Rs 100000 lakhs                                         30.5.11, HT completed on 24.05.12. BLU completed on
      Expenditure during 2011-12       :Rs 85000 lakhs                                          9.01.15.
      Expenditure during 2012-13       :Rs 110000 lakhs                                        ESP: work completed
      Expenditure during 2013-14       :Rs 47000 lakhs                                         TG: TG erection commenced in 5/12. TG boxed up on
      Expenditure during 2014-15       :Rs 54800 lakhs                                          23.05.14, Oil flushing completed on 10.10.14. Unit
      Expenditure during 2015-16       :Rs 26200 lakhs
                                                                                                synchronized on 18.06.15
      Expenditure during 2016-17       :Rs      2300 lakhs
      Expenditure during 2017-18       Rs        100 lakhs
       Total Expenditure               :Rs        4254.00 Cr (up to 04/17)                    Unit-2:
                                         29.03.2010                                            Boiler: Boiler erection started in 05/11, Drum lifted on
       Approval date:
                                                                                                26.12.11. HT(D) completed on 20.05.14.
       Zero date:                      : 16.05.2009
                                                                                               ESP: Erection completed insulation & cladding of ESP and
       Financial closure               : FC achieved on 14.05.2008 with M/s Axis Bank Ltd.      hot gas ducts is in progress.
       Main Plant Order                : Cethar Vessel(16.05.2009) Chinese                     TG: TG erection started in 09/12.Erection of TG &
       BOP Package                      Awarded to punj Lloyd on 07.01.2010                     condenser completed.TG boxed up to be re-inspected and
                                                                                                final Box up is in progress.
       Type of fuel                      Coal and Fuel Linkage MCL
       PPA                               PPA signed with GRIDCO on 14.9.09 & TNEB on BoPs:
                                         8.8.13.
       Power Evacuation system           Bulk Power Transmission Agreement (BPTA) with
                                                                                               Chimney: Completed for both the units.
                                         PGCIL in 24.02.2010
                                                                                               CHP: structural erection completed and electrical work in
            Land: Required land acquired
                                                                                                progress, Track hopper completed, Bunker, coal feeder and
            MOEF: Clearance of MOEF has been obtained on 30.11.2009                            mills erection completed. Tripper erection completed
            Water: Approval to draw water from Mahanadi river obtained on 23.02.2008          AHP: U-2 BAH expected in 12/17 and F/A system work is
            SPCB: Clearance obtained from Orissa SPCB on 13.08.2010                            in progress.
            Civil Aviation: Clearance obtained from AAI on 14.07.09                           CT: completed for U-1 and that for U-2 is in progress.
                                                                                                       PT Plant: completed
                                                                                                       DM plant: Ready to use., already functional for U-1.
                                                                                                       CW system: Already functioning for U-1.
                                                                                                       FO System: for U-1 & U-2 completed.
                                                                                                       Switchyard: completed in all respect and is being used for
                                                                                                        evacuation of power for U-I.
Critical issues              1.Non readiness of CHP & AHP and ATS for Unit-2
                             2. Completion of bottom ash hopper
Reasons for Delay            1. Very slow progress of civil work
                             2. Supply of main Plant material
                             3. Readiness of power evacuation system
                             4. Completion of firing guns/burners due to technical problem in design.
                             5. Mainly financial constraints due to non-disbursement of funds by financer.
                                                                             103
                                              Unit                      Commissioning Schedule
Sl. No.            Project Details                    Capacity                                                               Broad Status
                                                       (MW)          Original   Actual(A)/ As
                                                                                     Expected
                                                                  Synch     COD    Syn.       COD
                                                                 Comm             Comm
  Private Sector
  3. Lanco Babandh TPP                         1      660          02/13    05/13   Stressed             Unit-1
       (Distt-Dhenkanal)                                           04/13                                Boiler: Boiler erection started in 05/11. Main
       (M/s Lanco Babandh Power                                                                          structural erection completed. Boiler Pressure parts
       Ltd.)                                     2      660          06/13 09/13 Stressed                erection, Enclosure wall erection are in progress.
      (2x660 = 1320 MW)                                             08/13                                Burner erection completed.
                                                                                                        ESP: 58% structural erection completed. All
           Original / Latest Cost             :Rs 6930.00 Cr. / Rs. 10430.00 Cr                          hoppers erected. Pass-A collecting electrode
                                                                                                         erection completed and Pass B electrode erection
                                                                                                         was in progress. Pass-A outlet and Inlet funnel
          Expenditure during 2010-11          Rs        135000 lakhs
                                                                                                         erection completed.
          Expenditure during 2011-12         :Rs        214100 lakhs
          Expenditure during 2012-13         :Rs        78400 lakhs                                     TG: Deck casting completed. Both EOT cranes
          Expenditure during 2013-14         :Rs        54700 lakhs                                      commissioned.TG erection started in 11/15. HPT,
          Expenditure during 2014-15         :Rs        62200 lakhs                                      IPT & LPT are not received at site. HPH & LPH
          Expenditure during 2015-16         :Rs       128000 lakhs                                      erection completed. Foundations of MDBFP#1 &
          Expenditure during 2016-17         :Rs        89100 lakhs                                      CEP#1 completed.
           Total Expenditure                 :Rs        7615.00 Cr(up to 03/17)                          Unit-2
                                                                                                        Boiler: Erection started in 9/11. All ceiling girders
           Approval date:
                                                                                                         erected. Handrails and Platforms work completed at
           Zero date:                        : 17.11.2009                                                various levels. Burner erection was in progress.
           Financial closure                 : Achieved on 08.09.2010                                    Preparatory work for Pressure part erection yet to
           Main Plant Order                    Main plant order placed on Lanco Infaratec Ltd. On        complete.
                                               17/11/2009, Boiler: DEC China, TG: HEC China.            ESP: 41% of structural erection completed. Hopper
           BOP Package                        BOPs to LTTL                                               erection is in progress. Pass A-2/9 Collecting
                                                                                                         electrode erection completed. Pass C- hopper
           Type of fuel                        Coal
                                                                                                         assembly erection and casing wall assembly work
           PPA                                 Revised PPA signed with GRIDCO, Odisha for 25% power completed.
                                               sale on 4.01.11. LBPL signed PPA with UPPCL for TG: EOT crane commissioned. Columns upto deck
                                               454MW on 08.08.13 & with RVPNL for 374MW on bottom                    completed,     MDBFP#2         foundation
                                               01.11.13.                                                 completed. CEP & CW Pit #2 raft completed.
           Power Evacuation system             BPTA signed with PGCIL for 1600 MW on 24.02.10(Revised MDBFP#2 foundation completed.
                                               to 800MW as per CERC order). 25KM of transmission line is BoPs:
                                               planned for power evacuation from LBPL project to PGCIL  Chimney:         252/270m       shell    construction
                                               Angul pooling station. The power shall be evacuated at      completed. Flue can fabrication was in progress.
                                               400KV level through 1 D/C quad Moose transmission          CT: FRP Cooling tower awarded to Paharpur.
                                               conductor. Section 68 and Section 164 approval received     IDCT#1 305/454 raft footing work completed.
                                               from MoP.                                                   275/481 nos column completed. Excavation upto
                Land: 889 acres out of 933 acres’ land acquired. (95%)                                    70% completed for IDCT#2 and raft footing work
                                                                               st
                 MoE&F: Clearances obtained on 17.02.10 and is valid upto 31 Mar 2017                      was in progress.
                Forest: II-Stage clearance received on 31.12.13 from MoEF                                CHP: Track hopper raft and both side walls
                Water: Principle approval received for 40 cusecs water for U-1 &U-2 on 07.02.09.          completed. Crusher house foundation work
                 Renewal received on 18th Jan’16                                                           completed. Stacker reclaimer footing raft
                Coal linkage: Coal linkage for U-1 received on 29.12.08 for 2.83MTPA. FSA has been        completed.. JTs foundation work completed.
                 executed with MCL on 26.04.16.                                                            Crusher house civil work completed.
                SPCB: NOC obtained on 20.05.09 from Odisha SPCB and it is valid till 19.05.19            AHP: RCC of BAH#1 completed. Raft footing
                Civil Aviation: NOC obtained on 03.09.08 and valid till 02.09.2020                        completed and wall final lift is in progress for
                                                                                                           ASPH. Ash silo raft#1 completed. 8/26 nos.
                                                                                                           footing completed for Ash compressor house
                                                                                                           building
                                                                                                          PT/DM plant: Foundation work completed. DM
                                                                                                           building structure erection completed and
                                                                                                           equipment erection in progress. Clarifloculator
                                                                                                           ring wall in progress. DM tank-1 erection
                                                                                                           completed.
                                                                                                          FO system: 2LDO + 2HFO fuel oil tanks erection
                                                                                                           completed. LDO-2 water fill test completed.
                                                                                                          Switch yard: Erection of 23 nos. towers & 18 nos.
                                                                                                           of beam completed. S/Y equipment received at
                                                                                                           site. Control room building brick work completed
                                                                                                           and preparation for slab casting has started.
                                                                           104
                                             Unit                         Commissioning Schedule
Sl. No.           Project Details                     Capacity                                                         Broad Status
                                                       (MW)        Original     Actual(A)/ As
                                                                                      Expected
                                                                  Synch     COD    Syn.       COD
                                                                 Comm             Comm
  Private Sector
  4. Malibrahmani TPP                             1   525         10/12     01/13 Uncertain* ----   Unit-1:
      M/s Monnet Ispat (Distt-Angul)                              12/12
      (2x525 = 1050 MW)                                                                              Boiler: Erection started on 18.08.11. Erection of
                                                  2   525        12/12 03/13 Uncertain* ----           pressure part is in progress, welding of HP joints
                                                                 02/13                                 is in progress. Feeder floor casted, 4 mills
           Original /Latest Cost             :Rs 5093.00 Cr./ Rs. 6330.00 Cr                           installed and 4 mills are yet to be installed.
          Expenditure during 2010-11         Rs     63300 lakhs                                      Drum lifted on 21.03.12., HT completed on 3.4.13
          Expenditure during 2011-12        :Rs     78292 lakhs                                        Boiler light up expected after restart of work.
          Expenditure during 2012-13        :Rs     143681 lakhs                                     ESP: All 4 passes completed and air test done.
          Expenditure during 2013-14        :Rs     126817 lakhs                                       Control room completed, panel erection and
          Expenditure during 2014-15        :Rs      120885 lakhs                                      cabling done.
           Total Expenditure                :Rs       5329.75 Cr (up to 12/2014)                     TG: Condenser erection started on 01.08.12,
           Approval date:                                                                              Turbine erection started on 28.01.13. Generator
           Zero date:                       : 12.06.2009                                               stator erected, TG box up yet to be done.
           Financial closure                : Achieved on 23.08.2010                                Unit-2:
           Main Plant Order                  Main plant order placed on M/s BHEL
           BOP Package                                                                               Boiler: Erection started on 10.10.11, 4 out of 8
           Type of fuel                     Coal                                                       mills are installed, foundation of PA and FD fans
           PPA                              PPA signed with GRIDCO for 117MW for 400 MW with           completed. Drum lifted 21.07.12. HT & BLU
                                            West Bengal through PTC.                                   may be assessed after start of work.
           Power Evacuation system          400KV double circuit transmission line up to proposed    ESP: Erection of pass B, C & D done and pass A
                                            PGCIL pooling station, which is 31km away from power       yet to be done.
                                            plant.                                                   TG: Condenser erection started on 7.02.13 and
              Land: 770 acre acquired out of 995 acre required.                                       TG erection started in 08/2015, TG box up may
              MOEF: Clearance of MOEF has been obtained                                               be assessed after restart of work.
              Water: Water allocation done                                                         BoPs:
              Coal linkage: Mandakini captive coal mines.
              SPCB: Clearance obtained from Orissa SPCB.                                            Chimney: Chimney shell casting completed flue
              Civil Aviation: Clearance obtained from AAI                                             can erection for U-I completed, for U-II two top
                                                                                                       segments erected.
                                                                                                     CHP: Fabrication and erection of CHP structure
                                                                                                       are in progress along with equipment erection
                                                                                                       could be completed after restart of work.
                                                                                                     AHP: Civil work for ash slurry sump, pump
                                                                                                       house, ash water pump house and silos
                                                                                                       completed. Pipe erection was in progress.
                                                                                                     IDCT: Orders placed to M/s Indure 0n
                                                                                                       22.02.2010. Construction of cooling tower for
                                                                                                       both the units are completed in all respect,
                                                                                                       mechanical and electrical erection work not
                                                                                                       completed.
                                                                                                     DM Plant: Civil & structural work is completed
                                                                                                       mechanical and electrical erection not completed.
                                                                                                     PT Plant: Civil work completed, mechanical and
                                                                                                       electrical erection to be done.
                                                                                                     CW System: Pump house completed. Pumps and
                                                                                                       associated pipe lines erection are to be erected.
                                                                                                     FO System: Pump house, tank erection, pipe rack
                                                                                                       work is yet to be completed.
                                                                                                     Fire Protection: Fire water pump house civil
                                                                                                       construction is completed and mechanical &
                                                                                                       electrical erection yet to be done.
                                                                                                     Switchyard:           Construction        completed.
                                                                                                       Commissioning and testing work not completed.
 Critical issues
 Reasons for Delay             Paucity of fund.
                                                                             105
                                              Unit                         Commissioning Schedule
Sl. No.           Project Details                      Capacity                                                                Broad Status
                                                        (MW)        Original     Actual(A)/ As
                                                                                       Expected
                                                                   Synch     COD     Syn.      COD
                                                                  Comm              Comm
  Private Sector
  5.   KVK Nilachal TPP, Ph-I                  1       350         10/11     01/13   Uncertain   …..
           Kandarei, Odisha                                        12/11                                   Unit-1:
          (Distt-Dhenkanal)                                                                                     Boiler: Boiler erection started on 20.06.11,
                                               2       350         01/12     03/13   Uncertain -----             structural erection started. Drum lifting may be
          M/s KVK Nilanchal Ltd.
                                                                   02/12                                         completed after restart of work.
          (3x350 = 1050 MW)
                                                                                                                ESP: Foundation work completed, structural
                                               3       350          01/12   03/13    Uncertain                   erection completed upto hopper level.
                                                                    02/12                        -----          TG: Deck casting partially completed, Foundation
           Original / Latest Cost            :Rs     4990.00 Cr./ Rs. 6000.00 Cr                                 of all three MDBFPs completed.
          Expenditure during 2008-09         Rs         11974.41 lakhs
          Expenditure during 2009-10        :Rs         20861.15 lakhs
          Expenditure during 2010-11        :Rs         35187.00 lakhs                                     BoPs:
          Expenditure during 2011-12        :Rs         75226.00lakhs
          Expenditure during 2012-13        :Rs          15740.00lakhs                                          Chimney: 90 mtr. Chimney shell completed.
          Expenditure during 2013-14        :Rs           5847.00 lakhs
          Expenditure during 2014-15        :Rs             6000.00 lakhs
           Total Expenditure                :Rs       1708.36 Cr (up to 03/15)
           Approval date:
           Zero date:                       : 09.11.2009
           Financial closure                : Achieved for Ph-I(1X350MW) in 07/08 and Ph-II
                                              (2X3501MW) in 08/10
           Main Plant Order
                                                                                                           Note: No work is under progress
                                              BTG-Harbin, China, 09.11.09
           BOP Package                                                                                       presently.
           Type of fuel                       Coal
           PPA                                PPA signed for (1000MW)
           Power Evacuation system            Bulk Power Transmission Agreement (BTPA) with
                                              PGCIL
              Land: Required land acquired.
              MOEF: Clearance obtained vide letter no.J-13011/51/20008-IA.II(T) DT.18/02/2009
              Water: Allocated by GoO vide letter irr-ii-wrc-73/08/15032 dt. 15..04.20008 for 48 cusecs
               from Mahanadi.
              SPCB: Clearance obtained for SPCB Orissa vide letter no..26748/Ind-II-NOC-5065
               dt.19.12.2008
              Civil Aviation: Received AAI vide letter No. AAI/20012/131/2007-AR(NOC)
 Critical issues
 Reasons for Delay             1.Law and order problem
                               2. Work held-up due to stay by honorable HC of Odisha. From 18.05.12 to 05/2015
                                                                               106
                  BROAD STATUS OF THERMAL POWER PROJECTS IN WEST BENGAL
                                              Unit                       Commissioning Schedule
Sl. No.             Project Details                  Capacity                                                                    Broad Status
                                                      (MW)        Original Actual(A)/ As
                                                                                   Expected
                                                                 Synch COD     Syn.         COD
                                                                Comm          Comm
  Private Sector
  1. Hiranmaye Energy TPP                       1     150        10/15
                                                                   11/15 19/03/17 (A) 13/08/17(A) Unit-1
        (3x150MW)                                                11/15     07/06/17 (A)            COD achieved on 13/08/17. Full load achieved on
      Hiranmaye Energy Limited                                                                     07/06/2017. Unit Synchronized on 19/03/17.
                                            2    150       01/16 02/16 31/12/17 (A)                 Boiler: Boiler erection started on 25.03.14. Drum lifted on
          PO-Shibramnagar, Haldia, Dist.-                   2/16           31/12/17(A) 31/12/17(A)   04.12.14. HT completed on 16/09/2015. BLU completed on
          Purba Medinipur-721635, West                                                               21.08.16. SBO completed 10.12.16. Unit synchronized on
          Bengal                                                                                     19-03-17.
                                            3    150       05/16 05/16          *            *      TG: TG erection started on 16.08.15 Box up completed on
          (3 x 150 = 450 MW)                               05/16                                     20/05/16. TG oil flushing completed on 14.10.16. Unit
                                                                                                     synchronized on 19-03-17.
           Original /Latest Cost           :Rs 2656.00 Cr./ Rs. 3307.00 Cr
           Latest Est. Cost               :                                                        Unit-2
          Expenditure up to 2010-11       : Rs       107 lakh                                      COD achieved on 31/12/17. Full load achieved on
          Expenditure during 2013-14      : Rs    111527 lakh                                      31/12/17. Unit Synchronized on 31/12/17.
          Expenditure during 2014-15      : Rs     46764 lakh                                       Boiler: Boiler erection started on 25.06.14, Drum lifted in
          Expenditure during 2015-16      : Rs     86968 lakh                                        23.02.15. 2218/2526 MT structural erection completed.
          Expenditure during 2016-17      : Rs      76130 lakh                                       HT(D) done on 16.09.16. BLU done on 10.07.17.
          Expenditure during 2017-18      : Rs       4809 lakh                                      ESP: 2153/2158 MT structural erection completed. Hopper
                                                                                                     erection is in progress.
           Total Expenditure              Rs    326305 lakhs (up to 10/17)                          TG: Deck casting completed.TG erection started on
                                                                                                     05/05/16. TG box up done 15.10.17, TG Oil Flushing done
           Approval date:
                                                                                                     on 18.10.17.
           Zero date:                     28-11-2013
           Financial closure                  Achieved on 22.12.2011 with REC                             Unit-3
           Main Plant Order                  Placed to BHEL 29.09.2010                                     Boiler: Boiler erection started on 15.05.15. 1320/3274MT
                                                                                                            structural erection completed. Drum lifted on 14.01.16.
           BOP Package                         Order for BOP’s placed on                                    Piling of 2/4 mill completed. Excavation for ID/FD/PA has
                                              M/s Shristi Infrastructural Development Corp. Ltd &          completed.
                                               Scorpio Engg Pvt. Ltd. for CHP on 20.12.13.                 ESP: Foundation completed. 567/2158 MT structural
                                              M/s Shristi Infrastructural Development Corp. Ltd &          erection completed.
                                               Energo Engg. Project. Ltd. For AHP on 10.01.14.             TG: TG deck raft casting completed. Water has logged in
                                              M/s Simplex Infrastructural Ltd. for Chimney on 09.05.12     this area. Presently no work is going on in this site.
                                              M/s Paharpur Cooling tower for CT on 24.03.14.
           Type of fuel                        Coal                                                        BoPs:
           PPA                               : For 300MW with WBSEDCL                                      Chimney: Civil work for chimney completed. Flue can
                                                                                                            erection for U#1, 2 &3 completed. Platform erection
           Power Evacuation system             220KV Transmission line of length from plant to new          completed
                                               haldia sub-station of WBSETCL.                              CT: IDCT-1&2 has completed in all respect. CT#3: Pile
             Land: Complete land acquired 213.71 acre, 198 from Haldia Development authority and           work was in progress. Presently no work is going on in this
               rest from private.                                                                           site
             MoE&F: Clearances extended on 30.08.15 upto 12.04.2017 vide letter No. J-                    CW System: CWPH building completed. All Four CW
               13213/16/2014-IA. I(T)                                                                       pump commissioned. Laying of CW pipe completed for all
             Water: 15 MGD water is available from Haldia Development authority.                           the three units. Forebay and cold water channels
             SPCB: NOC received from GoWB.                                                                 completed.
             Coal linkage: Long term coal supply agreement No: SNRL/IPC(H)L/FSA 2015-16                   CHP: Structural erectionand floor casting of srusher house
               between M/s Swaymbhu natural resources private limited and M/s India Power                   is completed.Stacker cum reclaimer has installed. Erection
               Corporation (Haldia) Ltd.                                                                    of galleries from coal stack yard to TP-1&2 is completed.
             Civil Aviation: NOC vide letter No.AAI/20012/82/2010-ARI(NOC) date 23.10.2010 for             Gallery from TP-2 to bunkers of U-1 is completed.
               construction of chimney extended upto 22.06.2022.                                            Conveyor belt laid upto U-1 bunkers for one stream.MCC
                                                                                                            room completed.
                                                                                                           AHP: Civil work of Ash Silo, Dewatering Bin, Ash slurry
                                                                                                           pump house, ash water pump house and control room
                                                                                                           building are completed. Construction of Slurry sump is
                                                                                                           completed. Erection of Ash water pumps and transport air
                                                                                                           compressors completed. MCC room is completed. Control
                                                                                                           room is ready.
                                                                                                           PT Plant: Raw water reservoir completed. RGF
                                                                                                            commissioned and system is operational.
                                                                                                           DM plant: DM plant is RO type. Erection of 2nos DM
                                                                                                            tank and 3nos.CST completed. DM plant commissioned.
                                                                                                           FO system: 2 LDO tanks and necessary pumping system
                                                                                                            ready.
                                                                                                           Switch yard: Structural erection of 220KV equipment in
                                                                                                            switchyard is completedin all respect.
                                                                                                           FGD: detailing of feasibility report is under process.
 Critical issues
 Reasons for Delay             Construction activity was stalled from beginning of 2011 to Sept 2014 due to following reasons:
                               1. Fresh clearance from Pollution Control Board for 3x150MW (Earlier it was acquired for 3x135MW)
                               2. MOEF moratorium for no construction activity in Haldia & Asansol industrial area in West Bengal
                                                                                 107
North –
Eastern
Region
   108
                  BROAD STATUS OF THERMAL POWER PROJECTS IN ASSAM
                                                          109
Sl.                                  Cap
                                     Commissioning Schedule
No.    PROJECT DETAILS              (MW)
                                    Original     Actual(A) / As                                           Broad Status
                                                 now Expected
                               Syn.       COD    Syn.        COD
                               comm              comm
I     PROJECT UNDER CONSTRUCTION
      State Sector
1.    Namrup Replacement                                                                  GT>G:
      Power Project                   98.40                                               GT      synchronized     on    03.01.17    and
      Distt:Dibrugarh                                                                     Commissioned on 11.01.17 (open cycle).
      (Assam) APGCL                                                                        GT was put on barring gear on 01.03.2016 and
                      GT              62.25   08/11      01/12    03.01.17(A              cranking was completed on 05.08.16. FSNL
                                              09/11                    )                  achieved on 3.1.17.
                                                                  11.01.17(A              ST:
                                                                       )                  TG Hall roof collapsed 09.07.2018. Roof
                            ST        36.15   11/11     01/12       09/19    2019-20      structure     restoration    work      started.
                                              01/12                 10/19                 Assessment of damage to STG is being done
      Date of sanction of the project         17.03.2007                                  at site. ST synchronization is likely to be
                                                                                          delayed.
      Project sanctioning Authority           Govt of Assam                               TG erection started in October’16. Oil Flushing
                                                                                          was STG in progress. ST synchronization and
      Date of Investment Approval             17.03.2007
                                                                                          commissioning is expected in 10/19 (Combined
      Org. Est. cost                          Rs 41100 Lakhs                              cycle). COD is expected in 03/19.
      Latest cost                             Rs 69373 Lakhs
      Exp. During 2007-08                     Rs       23 Lakhs                           HRSG: HRSG work started in 01/12 and
      Exp. During 2008-09                     Rs 1816 Lakhs                               insulation work nearing completion. LP/IP/HP
                                                                                          Hydro test completed. BFP no load test
      Exp. During 2009-10                     Rs 1799 Lakhs                               completed. Chemical cleaning was in progress
      Exp. During 2010-11                     Rs 2159 Lakhs                               at the time of accident
      Exp. During 2011-12                     Rs 12363 Lakhs
      Exp. During 2012-13                     Rs 10640 Lakhs                              30 Acres of land required for the project.
      Exp. During 2013-14                     Rs 2105 Lakhs                               Work for erection, commissioning, PG Test
      Exp. During 2014-15                     Rs 2005 Lakhs                                and all BOPs (ordering and execution) has been
      Exp. During 2015-16                     Rs 12870 Lakhs                               allotted to M/s NBPPL (Joint venture of NTPC
      Exp. During 2016-17                     Rs 2950 Lakhs                                & BHEL) on nomination basis with approval of
      Exp. During 2017-18                     Rs 2450 Lakhs                                APGCL.
      Exp. During 2018-19 (06/18)             Rs 4727 Lakhs                               Earlier BHEL requested for provisional time
      Cumulative exp. up to(06/18)            Rs 58148 Lakhs                               extension up to Dec., 2013. APGCL approved
      Date of Main Plant Order (LOA)          : 31.12.2008 ( EPC ) on M/s BHEL             formal extension up to Aug., 12 and
      Zero date of the project                : 09.02.2009                                 provisional extension up to 2013.
      Type of fuel                            Natural Gas                                 Main plant civil works was awarded to M/s.
                                                                                           Ramky and work was started in 4/10.
      Fuel Source                             Gas supply agreement made with Oil
                                              India Limited for 0.66 MMSCMD of            BHEL/NBPPL terminated the civil contractor
                                              natural gas. Gas Transportation              M/s. Ramky on 05/09/13 & BHEL terminated
                                              agreement with Assam Gas Company             M/s. NBPPL on 22.11.13 for their poor
                                              Ltd. through existing Gas supply line to     performance.
                                              NTPS.                                       Tender for new civil contractor for balance
                                                                                           civil work floated by BHEL on 18.12.13. Civil
                                                                                           contract awarded on 13.03.14 to M/s Power
      Power Evacuation                        LILO to connect with the existing            Mech Projects & work was started on 05.05.14.
                                              Namrup – Tinsukia 220 kV D/C line.
                                                                 110
                            LIST OF ABBREVIATIONS
Sl.No        Abbreviation            Description
         1   AHP                     Ash Handling Plant
         2   BAH                     Bottom Ash Hopper
         3   BFP                     Boiler Feed Pump
         4   BG                      Barring Gear
         5   BLU                     Boiler Lightup
         6   BOP                     Balance of Plant
         7   BTG                     Boiler Turbine Generator
         8   C&I                     Control & Instrumentation
         9   CF                      Coal Fire
        10   CHP                     Coal Handling Plant
        11   COD                     Commercial Operation Date
        12   CRH                     Cold Re Heat
        13   CW System               Cooling Water System
        14   DM Plant                De Mineralisation Plant
        15   EDTA                    Ethyle Diamine Tetraacetic Acid
        16   EPC                     Erection Procurement & Commissioning
        17   ESP                     Electro Static Precipitator
        18   FC                      Financial Closure
        19   FD Fan                  Forced Draft Fan
        20   FGD                     Flue Gas De-sulphurisation
        21   FL                      Full Load
        22   FO System               Fuel Oil System
        23   FSA                     Fuel Supply Agreement
        24   GCB                     Generator Circuit Breaker
        25   GT                      Generator Transformer
        26   HCSD                    High Concentrated Slurry Disposal
        27   HPT                     High Pressure Turbine
        28   HRH                     Hot Re Heat
        29   HT                      Hydraulic Test
        30   ID Fan                  Induced Draft Fan
        31   IDCT                    Induced Draft Cooling Tower
        32   IPT                     Intermediate Pressure Turbine
        33   LOA                     Letter of Award
        34   LPT                     Low Pressure Turbine
        35   MDBFP                   Motor Driven Boiler Feed Pump
        36   MGR                     Merry Go Round
        37   MOE&F                   Ministtry of Environment & Forests
        38   MSL                     Main Steam Line
        39   NDCT                    Natural Draft Cooling Tower
        40   NTP                     Notice To Proceed
        41   PA Fan                  Primary Air Fan
        42   PHB                     Power House Building
        43   PPA                     Power Purchase Agreement
        44   PTP                     Pre Treatment Plant
        45   ROW                     Right Of Way
        46   SBO                     Steam Blowing Operation
        47   SCR                     Selective Catalytic Reduction
        48   SG                      Steam Generator
        49   ST                      Station Transformer
        50   SVF                     Safety Valve Floating
        51   Synch.                  Synchronisation
        52   TDBFP                   Turbine Driven Boiler Feed Pump
        53   TG                      Turbine Generator
        54   WT                      Wagon Tippler
        55   WT Plant                Water Treatment Plant
111