Plaster Ratio 1 6 thickness 20
Qty for 100 Sqm
Volume of plaster ( Dry volume) 3.19 cum
Sand Qty 2.736 Cum
Cement Qty 0.456 cum
* 1 Bag = 0.0347 cum 13.1 Bag
Rate Analysis for plaster work
Sr. No. Item Description Unit Qty Rate Amount
A Material Cost
Sand M3 0.027 784 21.17
Cement Bag 0.131 280 36.68
Waterproofing compounding kg 0
57.85
B Labour Cost
Labour Rate Sqm 1 90 90
Scaffolding rate Sqm 1 0
90
Total A+B 147.85
Material Rate in MT Rate in Cum per Bag
mm Sand 560 784
cement 280