DEPARTMENT OF FOREIGN AFFAIRS and BANGKO                                                o     BCA: DFA failed to perform its reciprocal
SENTRAL NG PILIPINAS v. HON. FRANCO T. FALCON                                                  obligation to issue to BCA a certificate of
          GR No. 176657 | September 01, 2010                                                      acceptance of Phase 1 within 14 days which was
                                                                                                  required by the Amended BOT. Furthermore, it
Petitioner: DFA & BSP | Respondent: Judge Falcon & BCA                                            alleged that every new appointee to the position of
International Corporation                                                                         DFA secretary wanted to review the award to BCA
                                                                                                  that’s why it took 3 years for DFA to issue said
SHORT FACTS:                                                                                      Certificate.
DFA and BCA entered into an agreement for the implementation                          DFA sent a Notice of Termination to BCA and PPC due to
of machine readable passport and visa project.                                         their alleged failure to submit proof of financial capability to
 Dispute arose between DFA and BCA/PPC (BCA’s                                         complete the entire MRP/V Project in accordance with the
    assignee) due to alleged breaches by both parties.                                 financial warranty under Section 5.02(A) of the Amended
 DFA terminated its contract with BCA. BCA sent a notice                              BOT Agreement. DFA likewise demanded for liquidated
    of default against DFA.                                                            damages.
 BCA filed for arbitration with PDRCI. During the pendency                           BCA sent a letter to the DFA demanding that it immediately
    of the Request for Arbitration, DFA and BSP entered into an                        reconsider and revoke its previous notice of termination,
    agreement for the latter to provide passports compliant with                       otherwise, BCA would be compelled to declare the DFA in
    international standards (E-Passports).                                             default pursuant to the Amended BOT Agreement.
 BCA thereafter filed for a Petition for Interim Relief with the                     When the DFA failed to respond to said letter, BCA issued
    RTC of Pasig. TRO and thereafter a writ of preliminary                             its own Notice of Default against the DFA, stating that if the
    injunction were issued by RTC directed against DFA.                                default is not remedied within 90 days, BCA will be
 DFA filed the instant case alleging that TC committed grave                          constrained to terminate the MRP/V Project and hold the
    abuse of discretion.                                                               DFA liable for damages.
                                                                                      BCA filed its Request for Arbitration with the Philippine
FACTS:                                                                                 Dispute Resolution Center (PDRCI) pursuant to Section
DFA needed to implement the Machine Readable Passport                                  19.02 of the Amended BOT Agreement. BCA’s request for
and Visa Project under the Build-Operate-and-Transfer (BOT                             Arbitration sought for the following reliefs
scheme).                                                                                    o Judgment nullifying the Notice of Termination by
 Thus, the PBAC (Prequalification, Bids and Awards                                               DFA including the demand to pay liquidated
    Committee) published an invitation to prequalify and bid for                                  damages.
    the supply of the needed machine readable passports and                                 o Judgment confirming the Notice of Default issued
    visas, and conducted the public bidding for the MRP/V                                         by BCA and ordering DFA to comply with its
    Project.                                                                                      obligations under the Amended BOT.
 PBAC found BCA International Corporation’s bid to be the                                  o A judgment ordering DFA to pay damages to
    sole complying bid; hence, it permitted the DFA to engage                                     BCA in the amount of 50M representing lost
    in direct negotiations with BCA.                                                              business opportunities, financing fees, etc.
 BCA, in compliance with the Notice of Award (NOA),                                  Thereafter, the DFA and the BSP entered into a
    incorporated a project company, the Philippine Passport                            Memorandum of Agreement for the latter to provide the
    Corporation (PPC) to undertake and implement the MRP/V                             former passports compliant with international standards.
    Project.                                                                           The BSP then solicited bids for the supply, delivery,
 A Build-Operate-Transfer Agreement (BOT Agreement)                                   installation and commissioning of a system for the
    between DFA and PPC was signed. The BOT Agreement                                  production of Electronic Passport Booklets or e-Passports
                                                                                      Thus, BCA filed a Petition for Interim Relief under Section
    was later amended to include the following changes.1
                                                                                       28 of the Alternative Dispute Resolution Act of 2004 (R.A.
         o An Assignment Agreement was executed by BCA                                 No. 9285), with the Regional Trial Court (RTC) of Pasig
              and PPC whereby BCA assigned its rights arising                          praying for the issuance of TRO restraining DFA and BSP
              from the Amended BOT Agreement to PPC.                                   from awarding a new contract to implement the Project or if
         o MRP/V Project was divided into 6 phases,2 with                              such contract has been awarded, from implementing such
              each phase having a different set of timeline and                        projects.
              due dates.                                                              DFA filed an Opposition (to the Application for Temporary
                                                                                       Restraining Order and/or Writ of Preliminary Injunction
DFA and BCA impute breach of the Amended BOT Agreement                                 alleging that:
against each other.                                                                         o BCA has no cause of action: MRP/V is not the
 DFA: Delay of project is due to the submission of deficient                                     same as the contract with BSP which is for the
    documents as well as intervening issues regarding BCA’s                                       supply of electronic passports.
    financial incapacity.                                                                   o RTC is prohibited from issuing a TRO pursuant
                                                                                                  to RA 8975.
Section 9.05. The PPC has posted in favor of the DFA the performance security     Project Completion dates were likewise changed which set the completion of
required for Phase 1 of the MRP/V Project and shall be deemed, for all intents    the implementation phase of the project within 18 to 23 months from date of
and purposes, to be full compliance by BCA with the provisions of this Article    effectivity of the Amended BOT agreement.
9.
Section 20.15. It is clearly and expressly understood that BCA may assign, cede   2
                                                                                    Phase 1: Project Planning Phase; Phase 2: Implementation of MRP/V
and transfer all of its rights and obligations under this Amended BOT             Project at the Central Facility; Phase 3: Implementation of MRP/V
Agreement to PPC, as fully as if PPC is the original signatory to this Amended    Project at the Regional Consular Offices; Phase 4: Full Implementation,
BOT Agreement, provided however that BCA shall nonetheless be jointly and         including Foreign Service Posts; Phase 5: In Service Phase; Phase 6:
severally liable with PPC for the performance of all the obligations and          Transition/Turnover
liabilities under this Amended BOT Agreement.
   The TC, after summarily hearing the parties’ oral arguments                     the BOT are enumerated under Sec. 2 of RA 6957,
    on BCA’s application for TRO, TC ordered the issuance of                        as amended, otherwise known as the BOT Law.
    the TRO. DFA filed an MR.                                                       Notably, it includes “information technology
   After notice and hearing, an order granting BCA’s                               networks and database infrastructure.” In relation
    application for preliminary injunction was issued by TC.                        to information technology projects, infrastructure
   DFA and BSP filed the instant Petition for Certiorari and                       projects refer to the “civil works components”
    prohibition with a prayer for issuance of TRO and/or a writ                     thereof.
    of preliminary injunction, imputing GAD on the trial court            We cannot uphold the theory of BCA and the trial court
    when it granted interim relief to BCA and issued the WPI.              that the definition of the term “infrastructure project” in
         o Main allegation: RTC is prohibited under RA                     Republic Act No. 91843 should be applied to the BOT Law.4
              8975 Section 3 to issue a TRO and a writ of                       o Section 5 of Republic Act No. 9184 prefaces the
              preliminary injunction against national government                    definition of the terms therein, including the term
              projects such as ePassport project.                                   “infrastructure project,” with the following phrase:
   TRO prayed for by DFA and BSP was granted.                                      “For purposes of this Act”
                                                                                o There is no legal or rational basis to apply the
Issues:                                                                             definition of the term “infrastructure project” in one
1. Whether an information and communication technology                              statute (RA 9184) to another statute enacted years
    project (such as ePassport Project), which does not                             before (BOT law) and which already defined the
    conform to our traditional notion of the term “infrastructure,”                 types of projects it covers.
    is covered by the prohibition on the issuance of court                There is a legislative intent to treat information technology
    injunctions found in Republic Act No. 8975? NO                         projects differently under the BOT Law and the Government
2. Whether the trial court’s issuance of writ of injunction was            Procurement Reform Act.
    proper? NO                                                                  o Under the BOT Law, wherein the projects are to
                                                                                    be privately funded, the entire information
Ratio:                                                                              technology project, including the civil works
1. Section 3 of RA 8975 provides that court, aside from the                         component and the technological aspect
    Supreme Court, may enjoin a “national government                                thereof, is considered an infrastructure or
    project” unless the matter is one of extreme urgency                            development project and treated similarly as
    involving a constitutional issue such that unless the act                       traditional “infrastructure” projects. All the rules
    complained of is enjoined, grave injustice or irreparable                       applicable to traditional infrastructure projects are
    injury would arise.                                                             also applicable to information technology projects.
   “National government project” has three types under                         o In contrast, under Republic Act No. 9184 or the
    Section 2(a) of RA 8975:                                                        Government Procurement Reform Act, which
         a. Current and future national government                                  contemplates projects to be funded by public
             infrastructure projects, engineering works and                         funds, the term “infrastructure project” was limited
             service contracts, including projects undertaken                       to only the “civil works component” of
             by      government-owned      and      –controlled                     information technology projects.
             corporations;                                                                    Civil works are subject to the provisions
         b. All projects covered by R.A. No. 6975, as                                          on infrastructure projects.
             amended by R.A. No. 7718, or the                                                 Technological are covered by the
             BuildOperateandTransfer (BOT) Law; and                                         provisions of procurement of goods.
         c. Other related and necessary activities, such as               Petitioners presented no proof that the ePassport Project
             site acquisition, supply and/or installation of               was a BOT project. On the contrary, evidence adduced by
             equipment and materials, implementation,                      both sides tended to show that the ePassport Project was a
             construction, completion, operation, maintenance,             procurement contract under Republic Act No. 9184
             improvement repair and rehabilitation, regardless                  o Being a government procurement contract under
             of the source of funding.                                              Republic Act No. 9184, only the civil works
                                                                                    component of the e-Passport Project would be
Is the ePassport project covered under (b) projects covered                         considered an infrastructure project that may not
under BOT laws? NO                                                                  be the subject of a lower court-issued writ of
     SC pointed out that DFA represented to TC that ePassport                      injunction under Republic Act No. 8975
     Project is a BOT project but in their Petition before the SC,
     DFA merely claims that the project is a national government      Is the ePassport project covered under (a) “engineering
     project under RA 8974.                                           works or a service contract” or as “related and necessary
          o The TC, relying on the representation of DFA and          activities”? NO
               agreeing with the contention of BCA, ruled as              Service contract” refers to “infrastructure contracts entered
               follows: “The prohibition against issuance of TRO           into by any department, office or agency of the national
               and/or writ of preliminary injunction under RA 8975         government with private entities and nongovernment
               applies     only     to   national      government          organizations for services related or incidental to the
               infrastructure project covered by the BOT Law.              functions and operations of the department, office or
               The national government projects covered under              agency concerned.”
3                                                                     4
  RA 9184: infrastructure projects include the construction,            RA 7718 (amended RA 6957): private sector infrastructure or
improvement, rehabilitation, demolition, repair, restoration or       development projects are those normally financed and operated by
maintenance of roads and bridges…civil works components of            the public sector but which will now be wholly or partly implemented by
information technology projects xxx                                   the private sector, including but not limited to…information
                                                                      technology networks and database infrastructure xxx
    On the other hand, the phrase “other related and necessary                                urgent and paramount necessity for the writ to
     activities” obviously refers to activities related to a                                   prevent serious damage.
     government infrastructure, engineering works, service                                o An injury is considered irreparable if it is of such
     contract or project under the BOT Law                                                     constant and frequent recurrence that no fair and
    In other words, to be considered a service contract or                                    reasonable redress can be had therefor in a court
     related activity, petitioners must show that the e-Passport                               of law, or where there is no standard by which their
     Project is an infrastructure project or necessarily related to                            amount can be measured with reasonable
     an infrastructure project                                                                 accuracy, that is, it is not susceptible of
          o DFA failed to do this. There is nothing on record to                               mathematical computation. It is considered
               indicate that the ePassport Project has a civil                                 irreparable injury when it cannot be adequately
               works component or is necessarily related to an                                 compensated in damages due to the nature of the
               infrastructure project.                                                         injury itself or the nature of the right or property
          o Within the context of Republic Act No. 9184—                                       injured or when there exists no certain pecuniary
               which is the governing law for the e-Passport                                   standard for the measurement of damages.
               Project—the said Project is not an infrastructure                    In this case, whether this is a termination by the DFA alone
               project that is protected from lower court issued                     without fault on the part of BCA or a termination due to
               injunctions under Republic Act No. 8975, which, to                    default on the part of either party, the BOT Law and the
               reiterate, has for its purpose the expeditious and                    Amended BOT Agreement lay down the measure of
               efficient implementation and completion of                            compensation to be paid under the appropriate
               government infrastructure projects.                                   circumstances.
                                                                                    Significantly, in BCA’s Request for Arbitration with the
In short: The prohibition in Republic Act No. 8975 is inoperative                    PDRCI, it prayed for, among others,“a judgment ordering
in so far as the ePassport is concerned, since petitioners failed                    respondent [DFA] to pay damages to Claimant [BCA],
to prove that the e-Passport Project is national government                          reasonably estimated at P50M. All the purported damages
project as defined therein.                                                          that BCA claims to have suffered by virtue of the DFA’s
                                                                                     termination of the Amended BOT Agreement are plainly
2.   With respect to petitioners’ contention that BCA will suffer                    determinable in pecuniary terms and can be “reasonably
     no grave and irreparable injury so as to justify the grant of                   estimated” according to BCA’s own words.
     injunctive relief, the Court finds that this particular argument
     merits consideration.                                                       Other points noted by SC [dahil bibo yung nagsulat ng
    Under the BOT Law and the Amended BOT Agreement, in                         kaso]:
     the event of default on the part of the government (in this                    In seeking to enjoin the government from awarding or
     case, the DFA) or on the part of the proponent, the non                         implementing a machine readable passport project or any
     defaulting party is allowed to terminate the agreement,                         similar electronic passport or visa project and praying for
     again subject to proper compensation in the manner set                          the maintenance of the status quo ante pending the
     forth in the agreement. T                                                       resolution on the merits of BCA’s Request for Arbitration,
          o Even if we hypothetically accept BCA’s contention                        BCA effectively seeks to enjoin the termination of the
                that the DFA terminated the Amended BOT                              Amended BOT Agreement for the MRP/V Project. There is
                Agreement without any default or wrongdoing on                       no doubt that the MRP/V Project is a project covered by the
                BCA’s part, it is not indubitable that BCA is                        BOT Law and, in turn, considered a “national government
                entitled to injunctive relief.                                       project” under Republic Act No. 8795.
    BOT Law expressly allows the government to terminate a                               o As national government project, TCs are
     BOT agreement, even without fault on the part of the project                              prohibited from issuing a TRO or WPI against the
     proponent, subject to the payment of the actual expenses                                  government to restrain or prohibit the termination
     incurred by the proponent plus a reasonable rate of return.                               or    rescission     of     any     such      national
    Time and again, this Court has held that to be entitled to                                contract/project.5
     injunctive relief the party seeking such relief must be able                                       For if a project proponent is allowed to
     to show grave, irreparable injury that is not capable of                                            enjoin the termination of its contract on
     compensation.                                                                                       the ground that it is contesting the validity
          o WPI is resorted to only when there is a pressing                                             of said termination, then the government
                necessity to avoid injurious consequences which                                          will be unable to enter into a new contract
                cannot be remedied under any standard                                                    with any other party while the controversy
                compensation                                                                             is pending litigation. Obviously, a court’s
          o Two requisites are necessary if a preliminary                                                grant of injunctive relief in such an
                injunction is to issue, namely:                                                          instance is prejudicial to public interest
                         the existence of a right to be protected                                       since government would be indefinitely
                          and                                                                            hampered in its duty to provide vital
                         the facts against which the injunction is to                                   public goods and services in order to
                          be directed are violative of said right.                                       preserve the private proprietary rights of
          o It must be shown that the invasion of the right                                              the project proponent.
                sought to be protected is material and                                    o Although BCA did not specifically pray for the trial
                substantial, that the right of complainant is                                  court to enjoin the termination of the Amended
                clear and unmistakable and that there is an                                    BOT Agreement and thus, there is no direct
5Relax. Ung discussion na mahaba sa taas refers to “ePassport.” Itong sinasabi
ng SC dito refers to MRP/V Project. Pero sana ito nalang sinabi nila agad para
tapos na kanina pa.
              violation of Republic Act No. 8795, a grant of
              injunctive relief as prayed for by BCA will
              indirectly contravene the same statute.
   BCA contends that if no injunctive relief will be issued in its
    favor, the award of ePassport project would be tantamount
    to a violation of property without due process of the law.
         o The relationship of DFA to BCA is primarily
              contractual and their dispute involves the
              adjudication of contractual rights. The propriety of
              the DFA’s acts, in relation to the termination of the
              Amended BOT Agreement, should be gauged
              against the provisions of the contract itself
   BCA’s petition for interim relief before the trial court is
    essentially a petition for a provisional remedy ancillary
    to its Request for Arbitration in PDRCI. BCA specifically
    prayed that the trial court grant it interim relief pending the
    constitution of the arbitral tribunal in the said PDRCI case.
    Unfortunately, during the pendency of this case, PDRCI
    Case was dismissed for lack of jurisdiction, in view of the
    lack of agreement between the parties to arbitrate before
    the PDRCI
         o The dismissal of the principal action thus results in
              the denial of the prayer for the issuance of the writ.
              x x x.” In view of intervening circumstances, BCA
              can no longer be granted injunctive relief and the
              civil case before the trial court should be
              accordingly dismissed