A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
71 201 18 DH 0682 Inspection department
B07.2 C70
Heat AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
71 201 18 DH 0682 Inspection department
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
71 201 18 DH 0682 Inspection department
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
71 201 18 DH 0682 Inspection department
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C10-C29 Zugversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C10 C11 C12 C13 C14-C15
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. A A
Nr. Nr. Proben-Nr. GR.C MPA % %
RP02 REH RM L0=5D L0=8IN
01 465142 16871 K4 Q 400 246
K4 Q RT 412 430 558 34 25
F4 Q RT 410 422 552 32 23
01 465142 16872 K4 Q RT 410 429 556 31 23
F4 Q RT 407 423 557 34 24
01 465142 16874 K4 Q RT 424 441 561 35 25
F4 Q RT 413 434 560 29 21
02 465142 16882 K4 Q RT 423 440 573 31 23
F4 Q RT 414 429 563 33 25
04 465144 17053 K4 Q RT 389 405 547 32 25
F4 Q RT 386 400 548 30 24
05 465144 17065 * K4 Q 400 246
C40-C49 Kerbschlagbiegeversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C41 C40 C44 C46 C45 C42 C43
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. Proben- Proben- Prüfverfahren Energie Einzelwerte Mittelwert
Nr. Nr. Proben-Nr. GR.C breite form Joule AV=J
01 465142 16871 K4 LV -46 1/2 CHP-V 600 AV 8 86 98 97 94
K4 QO -50 5,0 CHP-V 750 AV 2 62 75 71 69
F4 QO -50 5,0 CHP-V 750 AV 2 46 48 46 47
01 465142 16872 K4 LV -46 1/2 CHP-V 600 AV 8 102 107 100 103
K4 QO -50 5,0 CHP-V 750 AV 2 52 43 57 51
F4 QO -50 5,0 CHP-V 750 AV 2 36 41 42 40
01 465142 16874 K4 LV -46 1/2 CHP-V 600 AV 8 102 101 90 98
K4 QO -50 5,0 CHP-V 750 AV 2 78 46 49 58
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C40-C49 Kerbschlagbiegeversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C41 C40 C44 C46 C45 C42 C43
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. Proben- Proben- Prüfverfahren Energie Einzelwerte Mittelwert
Nr. Nr. Proben-Nr. GR.C breite form Joule AV=J
01 465142 16874 F4 QO -50 5,0 CHP-V 750 AV 2 52 57 39 49
02 465142 16882 K4 LV -46 3/4 CHP-V 600 AV 8 146 183 161 163
K4 QO -50 7,5 CHP-V 750 AV 2 110 68 100 93
F4 QO -50 7,5 CHP-V 750 AV 2 83 101 100 95
04 465144 17053 K4 LV -46 3/4 CHP-V 600 AV 8 230 208 169 202
K4 QO -50 7,5 CHP-V 750 AV 2 93 113 77 94
F4 QO -50 7,5 CHP-V 750 AV 2 150 178 138 155
C66-C68 Sonstige Prüfungen an Proben
POSITION-NR.: 01-02,04-05
VERWECHSLUNGSPRUEFUNG DURCH STUECKANALYSE: OHNE FEHLERBEFUND.
C70-C99 Chemische Zusammensetzung % - Schmelzenanalyse
B07.2 C70
Schmelze C SI MN P S N CU MO NI CR V NB TI B
465142 Y 0,171 0,378 1,441 0,010 0,0007 0,0054 0,045 0,007 0,030 0,040 0,001 0,017 0,002 0,0000
465144 Y 0,169 0,381 1,449 0,008 0,0007 0,0057 0,031 0,011 0,038 0,040 0,001 0,018 0,002 0,0001
B07.2 C70
Schmelze AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
B07.2 C70
Coulée AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
71 201 18 DH 0682 Inspection department
B07.2 C70
Heat AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
71 201 18 DH 0682 Inspection department
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
71 201 18 DH 0682 Inspection department
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
71 201 18 DH 0682 Inspection department
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C10-C29 Zugversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C10 C11 C12 C13 C14-C15
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. A A
Nr. Nr. Proben-Nr. GR.C MPA % %
RP02 REH RM L0=5D L0=8IN
01 465142 16871 K4 Q 400 246
K4 Q RT 412 430 558 34 25
F4 Q RT 410 422 552 32 23
01 465142 16872 K4 Q RT 410 429 556 31 23
F4 Q RT 407 423 557 34 24
01 465142 16874 K4 Q RT 424 441 561 35 25
F4 Q RT 413 434 560 29 21
02 465142 16882 K4 Q RT 423 440 573 31 23
F4 Q RT 414 429 563 33 25
04 465144 17053 K4 Q RT 389 405 547 32 25
F4 Q RT 386 400 548 30 24
05 465144 17065 * K4 Q 400 246
C40-C49 Kerbschlagbiegeversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C41 C40 C44 C46 C45 C42 C43
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. Proben- Proben- Prüfverfahren Energie Einzelwerte Mittelwert
Nr. Nr. Proben-Nr. GR.C breite form Joule AV=J
01 465142 16871 K4 LV -46 1/2 CHP-V 600 AV 8 86 98 97 94
K4 QO -50 5,0 CHP-V 750 AV 2 62 75 71 69
F4 QO -50 5,0 CHP-V 750 AV 2 46 48 46 47
01 465142 16872 K4 LV -46 1/2 CHP-V 600 AV 8 102 107 100 103
K4 QO -50 5,0 CHP-V 750 AV 2 52 43 57 51
F4 QO -50 5,0 CHP-V 750 AV 2 36 41 42 40
01 465142 16874 K4 LV -46 1/2 CHP-V 600 AV 8 102 101 90 98
K4 QO -50 5,0 CHP-V 750 AV 2 78 46 49 58
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C40-C49 Kerbschlagbiegeversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C41 C40 C44 C46 C45 C42 C43
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. Proben- Proben- Prüfverfahren Energie Einzelwerte Mittelwert
Nr. Nr. Proben-Nr. GR.C breite form Joule AV=J
01 465142 16874 F4 QO -50 5,0 CHP-V 750 AV 2 52 57 39 49
02 465142 16882 K4 LV -46 3/4 CHP-V 600 AV 8 146 183 161 163
K4 QO -50 7,5 CHP-V 750 AV 2 110 68 100 93
F4 QO -50 7,5 CHP-V 750 AV 2 83 101 100 95
04 465144 17053 K4 LV -46 3/4 CHP-V 600 AV 8 230 208 169 202
K4 QO -50 7,5 CHP-V 750 AV 2 93 113 77 94
F4 QO -50 7,5 CHP-V 750 AV 2 150 178 138 155
C66-C68 Sonstige Prüfungen an Proben
POSITION-NR.: 01-02,04-05
VERWECHSLUNGSPRUEFUNG DURCH STUECKANALYSE: OHNE FEHLERBEFUND.
C70-C99 Chemische Zusammensetzung % - Schmelzenanalyse
B07.2 C70
Schmelze C SI MN P S N CU MO NI CR V NB TI B
465142 Y 0,171 0,378 1,441 0,010 0,0007 0,0054 0,045 0,007 0,030 0,040 0,001 0,017 0,002 0,0000
465144 Y 0,169 0,381 1,449 0,008 0,0007 0,0057 0,031 0,011 0,038 0,040 0,001 0,018 0,002 0,0001
B07.2 C70
Schmelze AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
B07.2 C70
Coulée AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 2/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 3/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
B07.2 C70
Heat AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 4/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 5
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Zertifiziert nach ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 ABNAHMEPRUEFZEUGNIS 3.1 NACH EN 10204:2004 A10 Versandanzeige-Nr. A08/ Werksauftrags-/ Blatt
und Datum A03 Bescheinigungs-Nr.
ABNAHMEPRUEFZEUGNIS 3.1 NACH ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 1/...
A05 Aussteller Abnahmeorgan A06 Besteller THYSSENKRUPP,DUESSEL A07.1 Nr. SKO-5404298965 B01 Erzeugnis
TUEV GROBBLECHE
Empfänger THYSSENKRUPP,DUESSEL A07.2 Nr.
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C40-C49 Kerbschlagbiegeversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C41 C40 C44 C46 C45 C42 C43
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. Proben- Proben- Prüfverfahren Energie Einzelwerte Mittelwert
Nr. Nr. Proben-Nr. GR.C breite form Joule AV=J
01 465142 16872 K4 QO -50 5,0 CHP-V 750 AV 2 52 43 57 51
F4 QO -50 5,0 CHP-V 750 AV 2 36 41 42 40
01 465142 16874 K4 LV -46 1/2 CHP-V 600 AV 8 102 101 90 98
K4 QO -50 5,0 CHP-V 750 AV 2 78 46 49 58
F4 QO -50 5,0 CHP-V 750 AV 2 52 57 39 49
02 465142 16882 K4 LV -46 3/4 CHP-V 600 AV 8 146 183 161 163
K4 QO -50 7,5 CHP-V 750 AV 2 110 68 100 93
F4 QO -50 7,5 CHP-V 750 AV 2 83 101 100 95
04 465144 17053 K4 LV -46 3/4 CHP-V 600 AV 8 230 208 169 202
K4 QO -50 7,5 CHP-V 750 AV 2 93 113 77 94
F4 QO -50 7,5 CHP-V 750 AV 2 150 178 138 155
C70-C99 Chemische Zusammensetzung % - Schmelzenanalyse
B07.2 C70
Schmelze C SI MN P S N CU MO NI CR V NB TI B
465142 Y 0,171 0,378 1,441 0,010 0,0007 0,0054 0,045 0,007 0,030 0,040 0,001 0,017 0,002 0,0000
465144 Y 0,169 0,381 1,449 0,008 0,0007 0,0057 0,031 0,011 0,038 0,040 0,001 0,018 0,002 0,0001
B07.2 C70
Schmelze AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 2/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 3/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
B07.2 C70
Coulée AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 4/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 5
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 1/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 2/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 3/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
B07.2 C70
Heat AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 4/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 5
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Zertifiziert nach ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 ABNAHMEPRUEFZEUGNIS 3.1 NACH EN 10204:2004 A10 Versandanzeige-Nr. A08/ Werksauftrags-/ Blatt
und Datum A03 Bescheinigungs-Nr.
ABNAHMEPRUEFZEUGNIS 3.1 NACH ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 1/...
A05 Aussteller Abnahmeorgan A06 Besteller THYSSENKRUPP,DUESSEL A07.1 Nr. SKO-5404298965 B01 Erzeugnis
TUEV GROBBLECHE
Empfänger THYSSENKRUPP,DUESSEL A07.2 Nr.
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C40-C49 Kerbschlagbiegeversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C41 C40 C44 C46 C45 C42 C43
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. Proben- Proben- Prüfverfahren Energie Einzelwerte Mittelwert
Nr. Nr. Proben-Nr. GR.C breite form Joule AV=J
01 465142 16872 K4 QO -50 5,0 CHP-V 750 AV 2 52 43 57 51
F4 QO -50 5,0 CHP-V 750 AV 2 36 41 42 40
01 465142 16874 K4 LV -46 1/2 CHP-V 600 AV 8 102 101 90 98
K4 QO -50 5,0 CHP-V 750 AV 2 78 46 49 58
F4 QO -50 5,0 CHP-V 750 AV 2 52 57 39 49
02 465142 16882 K4 LV -46 3/4 CHP-V 600 AV 8 146 183 161 163
K4 QO -50 7,5 CHP-V 750 AV 2 110 68 100 93
F4 QO -50 7,5 CHP-V 750 AV 2 83 101 100 95
04 465144 17053 K4 LV -46 3/4 CHP-V 600 AV 8 230 208 169 202
K4 QO -50 7,5 CHP-V 750 AV 2 93 113 77 94
F4 QO -50 7,5 CHP-V 750 AV 2 150 178 138 155
C70-C99 Chemische Zusammensetzung % - Schmelzenanalyse
B07.2 C70
Schmelze C SI MN P S N CU MO NI CR V NB TI B
465142 Y 0,171 0,378 1,441 0,010 0,0007 0,0054 0,045 0,007 0,030 0,040 0,001 0,017 0,002 0,0000
465144 Y 0,169 0,381 1,449 0,008 0,0007 0,0057 0,031 0,011 0,038 0,040 0,001 0,018 0,002 0,0001
B07.2 C70
Schmelze AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 2/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 3/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
B07.2 C70
Coulée AL-T
465142 Y 0,035
465144 Y 0,045
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 4/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 5
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 1/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 2/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 3/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
B07.2 C70
Heat AL-T
465142 Y 0,035
465144 Y 0,045
C94 Heat analysis Carbon equivalent / Alloying restrictions
B07.2
Heat
465142 FO-02= 0,43 FO-52= 0,02 FO-54= 0,09 FO-55= 0,12 FO-78= 0,05
465144 FO-02= 0,43 FO-52= 0,02 FO-54= 0,08 FO-55= 0,12 FO-78= 0,05
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 4/...
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 We hereby certify, that the above mentioned materials have been delivered in accordance AG der Dillinger Hüttenwerke A01
with the terms of order.
Postfach 1580, D-66748 Dillingen/Saar
Inspection department
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Certification as per ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 INSPECTION CERTIFICATE 3.1 AS PER EN 10204:2004 A10 Advice of dispatch No./ A08/ Manufacturer's order/ Sheet
Date of dispatch A03 Certificate No.
INSPECTION CERTIFICATE 3.1 AS PER ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 5
A05 Established Inspecting body A06 Purchaser THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Product
TUEV HEAVY PLATES
Final receiver THYSSENKRUPP,DUESSEL A07.2 No.
Z04 CE-marking
ITEM NO.: 01-02,04-05
EN 10025-1:2004
Elongation
Manufacturer's B. BALDAUF
mark Test House Manager Inspector's stamp Date 23.11.18 ML 1
QM-System: Zertifiziert nach ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 ABNAHMEPRUEFZEUGNIS 3.1 NACH EN 10204:2004 A10 Versandanzeige-Nr. A08/ Werksauftrags-/ Blatt
und Datum A03 Bescheinigungs-Nr.
ABNAHMEPRUEFZEUGNIS 3.1 NACH ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 1/...
A05 Aussteller Abnahmeorgan A06 Besteller THYSSENKRUPP,DUESSEL A07.1 Nr. SKO-5404298965 B01 Erzeugnis
TUEV GROBBLECHE
Empfänger THYSSENKRUPP,DUESSEL A07.2 Nr.
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C10-C29 Zugversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C10 C11 C12 C13 C14-C15
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. A A
Nr. Nr. Proben-Nr. GR.C MPA % %
RP02 REH RM L0=5D L0=8IN
01 465142 16871 K4 Q 400 246
K4 Q RT 412 430 558 34 25
F4 Q RT 410 422 552 32 23
01 465142 16872 K4 Q RT 410 429 556 31 23
F4 Q RT 407 423 557 34 24
01 465142 16874 K4 Q RT 424 441 561 35 25
F4 Q RT 413 434 560 29 21
02 465142 16882 K4 Q RT 423 440 573 31 23
F4 Q RT 414 429 563 33 25
04 465144 17053 K4 Q RT 389 405 547 32 25
F4 Q RT 386 400 548 30 24
05 465144 17065 * K4 Q 400 246
C40-C49 Kerbschlagbiegeversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C41 C40 C44 C46 C45 C42 C43
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. Proben- Proben- Prüfverfahren Energie Einzelwerte Mittelwert
Nr. Nr. Proben-Nr. GR.C breite form Joule AV=J
01 465142 16871 K4 LV -46 1/2 CHP-V 600 AV 8 86 98 97 94
K4 QO -50 5,0 CHP-V 750 AV 2 62 75 71 69
F4 QO -50 5,0 CHP-V 750 AV 2 46 48 46 47
01 465142 16872 K4 LV -46 1/2 CHP-V 600 AV 8 102 107 100 103
K4 QO -50 5,0 CHP-V 750 AV 2 52 43 57 51
F4 QO -50 5,0 CHP-V 750 AV 2 36 41 42 40
01 465142 16874 K4 LV -46 1/2 CHP-V 600 AV 8 102 101 90 98
K4 QO -50 5,0 CHP-V 750 AV 2 78 46 49 58
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C40-C49 Kerbschlagbiegeversuch
B14 B07.2 B07.1 B05 C01 C02/ C03 C41 C40 C44 C46 C45 C42 C43
Pos. Schmelzen- Walztafel-/ Referenz(wärme)behandlung C01 Temp. Proben- Proben- Prüfverfahren Energie Einzelwerte Mittelwert
Nr. Nr. Proben-Nr. GR.C breite form Joule AV=J
01 465142 16874 F4 QO -50 5,0 CHP-V 750 AV 2 52 57 39 49
02 465142 16882 K4 LV -46 3/4 CHP-V 600 AV 8 146 183 161 163
K4 QO -50 7,5 CHP-V 750 AV 2 110 68 100 93
F4 QO -50 7,5 CHP-V 750 AV 2 83 101 100 95
04 465144 17053 K4 LV -46 3/4 CHP-V 600 AV 8 230 208 169 202
K4 QO -50 7,5 CHP-V 750 AV 2 93 113 77 94
F4 QO -50 7,5 CHP-V 750 AV 2 150 178 138 155
C70-C99 Chemische Zusammensetzung % - Schmelzenanalyse
B07.2 C70
Schmelze C SI MN P S N CU MO NI CR V NB TI B
465142 Y 0,171 0,378 1,441 0,010 0,0007 0,0054 0,045 0,007 0,030 0,040 0,001 0,017 0,002 0,0000
465144 Y 0,169 0,381 1,449 0,008 0,0007 0,0057 0,031 0,011 0,038 0,040 0,001 0,018 0,002 0,0001
B07.2 C70
Schmelze AL-T
465142 Y 0,035
465144 Y 0,045
C94 Schmelzenanalyse C-Äquivalent / Legierungsbegrenzung
B07.2
Schmelze
465142 FO-02= 0,43 FO-52= 0,02 FO-54= 0,09 FO-55= 0,12 FO-78= 0,05
465144 FO-02= 0,43 FO-52= 0,02 FO-54= 0,08 FO-55= 0,12 FO-78= 0,05
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
C95 Schmelzenbehandlung
POSITION-NR.: 01-02,04-05
SCHMELZE DER ANGEGEBENEN POSITION: VAKUUM BEHANDELT
C95 Weitere Angaben zur Schmelzenbehandlung
POSITION-NR.: 01-02,04-05
VAKUUMBEHANDELT, VOLLBERUHIGT, FEINKORNHERSTELLUNG
C94 Formel C-Äquivalent / Legierungsbegrenzung
FO-02 = C+(MN/6)+(CR+MO+V)/5+(NI+CU)/15
FO-52 = V +NB+TI
FO-54 = CU+MO+CR
FO-55 = CU+MO+NI+CR
FO-78 = CR+MO
D01 Kennzeichnung, Identifizierung, Oberfläche, Form und Maße
POSITION-NR.: 01-02,04-05
PRUEFUNG VON KENNZEICHNUNG, OBERFLAECHE, FORM UND MASSEN: DIE ERGEBNISSE ENTSPRECHEN DEN ANFORDERUNGEN.
OBERFLAECHE NACH EN-10163-B3
DICKE NACH EN-10029:10-B
LAENGE UND BREITE NACH EN-10029:10
EBENHEIT NACH EN-10029:10-T4L
Z04 Umweltproduktdeklaration für Baustähle
POSITION-NR.: 01-02,04-05
Für Grobbleche aus Baustählen von Dillinger Hütte liegt eine validierte Umweltproduktdeklaration nach ISO 14025 und
EN 15804 vor: BFS-20130094-IBG1-DE+RC1. Weitere Informationen finden Sie unter www.dillinger.de/EPD-D/.
A04 Z01/Z02/Z03 Es wird bestätigt, dass die Lieferung den Vereinbarungen bei der Bestellung entspricht. AG der Dillinger Hüttenwerke A01
Z04 CE-Zeichen
POSITION-NR.: 01-02,04-05
EN 10025-1:2004
Dehnung
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 2/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 3/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
B07.2 C70
Coulée AL-T
465142 Y 0,035
465144 Y 0,045
C94 Analyse sur coulée Carbone équivalent / Limitation d'alliage
B07.2
Coulée
465142 FO-02= 0,43 FO-52= 0,02 FO-54= 0,09 FO-55= 0,12 FO-78= 0,05
465144 FO-02= 0,43 FO-52= 0,02 FO-54= 0,08 FO-55= 0,12 FO-78= 0,05
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 4/...
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
A04 Z01/Z02/Z03 Nous attestons que les produits livrés sont conformes aux stipulations de la commande. AG der Dillinger Hüttenwerke A01
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1
QM-Système: Certification selon ISO 9001
Erläuterungen siehe Rückseite/Explications voir au verso/See reverse for explanations (www.dillinger.de/certificate)
A02 CERTIFICAT DE RECEPTION 3.1 SELON EN 10204:2004 A10 Avis d'expédition No./ A08/ Référence usine/ Page
Date d'expédition A03 No. Certificat
CERTIFICAT DE RECEPTION 3.1 SELON ISO 10474:2013
MATERIAL TEST REPORT (MTR) 659655-23.11.18 440817-004 5
A05 Aut.du doc. Org. réception A06 Client THYSSENKRUPP,DUESSEL A07.1 No. SKO-5404298965 B01 Produit
TUEV TOLES FORTES
Destinataire THYSSENKRUPP,DUESSEL A07.2 No.
Z04 Marquage CE
POSTE NO.: 01-02,04-05
EN 10025-1:2004
Marque du B. BALDAUF
producteur Responsable Réception Poinçon récept. Date 23.11.18 ML 1