University of Nevada, Reno
Campus Design & Construction Standards
APPENDIX L
ELECTRICAL METHOD OF
PROCEDURE
The following appendix includes information and standard drawings
that are diagrammatic and are used only to convey intent.
ELECTRICAL METHOD OF PROCEDURE (MOP)
UNR requires a Method of Procedure (MOP) whenever there will be an electrical
shutdown of our transmission and distribution system(s). The purpose of the MOP is:
Increase Safety.
Minimize shut down time by planning properly.
Coordinate duties between all parties involved in the shutdown process.
Improve communication and provide a clear understanding of the process.
Ensure proper PPE is used.
Have communication between the University and any contractor working the
shut-down.
MOPS should include the following:
Pre-work briefing with all that are present for the shutdown.
Include safety discussion, all potential hazards.
Job description – what will be done, when it will be done, the voltages and
location of the equipment will all need to be included.
The steps that will be followed.
Emergency procedures and collection points.
Location of emergency exits.
The levels of PPE required for each step.
Include steps for pre-use inspection of PPE.
Steps to take for Lock-out/Tag-out.
Steps for verification of voltage / rotation or other tasks to be accomplished.
How you will control access into the work area based on arc flash boundaries.
Type of meter being used for voltage verification and max voltage rating.
Lighting considerations.
Facilities Services Department Page 1 of 4
Revised July 2018 Appendix L – Electrical Method of Procedure
University of Nevada, Reno
Campus Design & Construction Standards
THE FOLLOWING IS AN EXAMPLE OF AN ACTUAL MOP EXECUTED ON
CAMPUS:
MOP 7-23-2016
Ross Hall and Jones Center shut down.
Work to be performed: UNR to replace wire to main switch gear for new water heater,
tighten and clean gear and panels in Ross Hall and Jones Center.
Contractor Contact - John Doe – 775-321-1234
UNR Contact – Project Coordinator – 775-987-6789
Proper PPE
Category 2 and 4 / 8 cal. and 40 cal.
Fluke volt meter
Lock out tag out, lock out tag out tree
Equipment
LED lights
Socket sets
Rags
5-point sockets
Torque Wrenches
Portable Generators
Cords
Vacuums
Torque specs.
Hot Sticks
Rope with a hook
Morning meeting at 6:30 am in Electric shop Saturday 7-23-2016
Review Project with UNR MOP
Facilities Services Department Page 2 of 4
Revised July 2018 Appendix L – Electrical Method of Procedure
University of Nevada, Reno
Campus Design & Construction Standards
Verify Rotation at 120/208 volt disconnect on main transformer with Category 2/8
cal2 gear (James and Steve).
Power shut down 7:00 am with Joe from Contractor X on site in case switch does
not work
UNR Open Main breakers in Ross and Jones and LOTO (Steve and James).
UNR open PB- 13, open, close, open 4160-volt switch to Ross and Jones with
Category 4/40 cal2 gear (Steve and James).
Close vault lid, LOTO PB-13.
UNR Verify power is de-energized to Ross and Jones with Category 2/8 cal2 gear
(Steve and James).
If PB- 13 switches correctly, Joe from Contractor X can leave.
7:00 to 3:00 pm.
UNR to pull wire for water heater @ Ross Hall (Brent and Cimothy).
UNR torque and cleaning switch gear @ Ross Hall (Brent and Cimothy).
Check all Emergency lights in Ross and Jones (James, Steve).
UNR to torque and clean panels @ Ross Hall and Jones (James, Steve, Brent,
and Cimothy).
UNR clean and torque transformer (not the porcelain bushings) T- RHJV.
UNR exercise all breakers in both buildings.
Make drawing of conduits in PB-13 for FS Electrical Engineer.
Re-energize power 3:30 pm or sooner
UNR contact control shop (997-9652) before we re-energize
UNR remove LOTO from PB-13
UNR close switch at PB-13 with Category 4/40 cal2 gear (James and Steve)
UNR Verify three phase power Ross and Jones with Category 2/8 cal2 gear
(James and Steve).
UNR close Main breakers @ Ross and Jones with Category 2/8 cal2 gear (James
and Steve).
UNR confirms power is restored to both buildings.
Facilities Services Department Page 3 of 4
Revised July 2018 Appendix L – Electrical Method of Procedure
University of Nevada, Reno
Campus Design & Construction Standards
Clean up and put away all tools and equipment.
If Switch fails Joe from Contractor X is on standby to bypass switch.
Joe (775) 555-1234
END OF ELECTRICAL METHOD OF PROCEDURE