Fiscal Management
Fiscal Management
Introduction
Definition:
Feature of budget
1
Purposes of budget
Importance of budget
Budget is needed for planning for future course of action and to have a control
over all activities in the organization
Budget facilities co coordinating operation of various departments and sections for
realizing organizational objectives.
Budget serves as a guide for action in the organization
Budget helps one to weigh the values and to make decision when necessary on
whether one is of a greater value in the programme than the other
Principles of Budget
2. Budget should focus on objectives and policies of the organization. It must flow from
objectives and give realistic expression to the way of realizing such objectives.
3. Budget should ensure the most effective use of scarce financial and non financial resources.
5. Budgetary process requires consistent delegation for which fixed duties and
responsibilities are required to be allocated to managers at different level for framing and
executing budget.
6. Budgeting should include coordinating efforts of various departments establishing
frame of reference for managerial decisions, and providing a criterion for evaluating
managerial performance.
7. Setting budget target requires an adequate checks and balance against the adoption of
too high or too low estimate. Utmost care is a must for fixing targets.
8. Budget period must be appropriate to the nature of business or service and to the type
of budget.
9. Budget is prepared under the direction and supervision of the administrator or finance officer.
11. Budget necessitates a review of the performance of the previous year and an evaluation
of its adequacy both in quantity and quality.
12. While developing a budget, the provision should be made for its flexibility.
STEPS IN BUDGETING
FORECAST YEAR
CHANGRS
Take into consideration your payroll deductions (health insurance or other group
benefits, income taxes, union dues, pension) and other sources of income.
– Add together all income, less deductions. On a piece of paper record the
resulting figure as VALUE A.
Such as housing, utilities, food and transportation. Remember to allocate funds for
clothing, medical care, child care, personal expenses, recreation and emergencies/repairs.
income”
– By subtracting your total expenses (B) from your total net income (A).
• The monthly payments and the balances. If you don‘t know your exact debt
amount, now is the time to determine it.
discretionary income
• If this figure is a negative number, you are not ready for Step 6 – setting
goals. Consult a personal financial counsellor and work on getting this
figure into the positive numbers
• Determine the requirements: inputs from all levels of hierarchy must be obtained
• Review the budget appropriation and actual expenditure for the current year
• Contemplated changes
• Salary fixation
• Requirement estimation
• Review of budget
• Ascertain changes
• Preparing requirements
Disadvantages
It may be considered as a punishment to professional group.
Medico- legal importance- They feel that they will be used in court of law as any
document can be called for in a court law.
Many components may make analysis difficult.
It is time consuming
It requires a team of trained auditors.
COST ACCOUNTING AND COST ANALYSIS
Introduction
Cost effectiveness and cost accounting are important aspects in the managerial
level. If these factors are not being monitored properly the profit of the organization may
be drastically affected. So each administrator should be aware of this. Thus it forms an
important aspect in the part of administration.
Cost accounting has long been used to help managers understand the costs of
running a business. Modern cost accounting originated during the industrial revolution,
when the complexities of running a large scale business led to the development of systems
for recording and tracking costs to help business owners and managers make decisions.
In the early industrial age, most of the costs incurred by a business were what
modern accountants call "variable costs" because they varied directly with the amount of
production. Money was spent on labor, raw materials, power to run a factory, etc. in direct
proportion to production. Managers could simply total the variable costs for a product and
use this as a rough guide for decision-making processes.
Some costs tend to remain the same even during busy periods, unlike variable
costs, which rise and fall with volume of work. Over time, the importance of these "fixed
costs" has become more important to managers. Examples of fixed costs include the
depreciation of plant and equipment, and the cost of departments such as maintenance,
tooling, production control,
purchasing, quality control, storage and handling, plant supervision and engineering. In
the early twentieth century, these costs were of little importance to most businesses.
However, in the twenty-first century, these costs are often more important than the
variable cost of a product, and allocating them to a broad range of products can lead to
bad decision making. Managers must understand fixed costs in order to make decisions
about products and pricing.
Definition
Cost accounting
Cost accounting is the process that supports the budget reporting system and the
agency efforts for cost containment.
Cost accounting is a set of techniques for associating costs with the purpose for
which obtained.
1. Raw materials
2. Labor
3. Indirect expenses/overhead
Elements of cost
In modern cost accounting, the concept of recording historical costs was taken
further, by allocating the company's fixed costs over a given period of time to the items
produced during that period, and recording the result as the total cost of production. This
allowed the full cost of products that were not sold in the period they were produced to
be recorded in inventory using
variety of complex accounting methods, which was consistent with the principles of
GAAP (Generally Accepted Accounting Principles). It also essentially enabled managers
to ignore the fixed costs, and look at the results of each period in relation to the "standard
cost" for any given product.
Classification of costs
Classification of cost means, the grouping of costs according to their common characteristics.
The important ways of classification of costs are:
A company can use the resulting activity cost data to determine where to focus
their operational improvements. For example, a job-based manufacturer may find that a
high percentage of its workers are spending their time trying to figure out a hastily written
customer order. Via ABC, the accountants now have a currency amount pegged to the
activity of "Researching Customer Work Order Specifications". Senior management can
now decide how much focus or money to budget for resolving this process deficiency.
Activity-based management includes (but is not restricted to) the use of activity-based
costing to manage a business.
While ABC may be able to pinpoint the cost of each activity and resources into
the ultimate product, the process could be tedious, costly and subject to errors.
As it is a tool for a more accurate way of allocating fixed costs into product, these
fixed costs do not vary according to each month's production volume. For example, an
elimination of one product would not eliminate the overhead or even direct labor cost
assigned to it. ABC better identifies product costing in the long run, but may not be too
helpful in day-to-day decision- making.
Lean accounting
Lean accounting has developed in recent years to provide the accounting, control,
and measurement methods supporting lean manufacturing and other applications of lean
thinking such as healthcare, construction, insurance, banking, education, government, and
other industries.
There are two main thrusts for Lean Accounting. The first is the application of lean
methods to the company's accounting, control, and measurement processes. This is not
different from applying lean methods to any other processes. The objective is to eliminate
waste, free up capacity, speed up the process, eliminate errors & defects, and make the
process clear and understandable. The second (and more important) thrust of Lean
Accounting is to fundamentally change the accounting, control, and measurement
processes so they motivate lean change & improvement, provide information that is
suitable for control and decision-making, provide an understanding of customer value,
correctly assess the financial impact of lean improvement, and are themselves simple,
visual, and low-waste. Lean Accounting does not require the traditional management
accounting methods like standard costing, activity-based costing, variance reporting, cost-
plus pricing, complex transactional control systems, and untimely & confusing financial
reports. These are replaced by:
This method is used particularly for short-term decision-making. Its principal tenets are:
Revenue (per product) − variable costs (per product) = contribution (per product)
Total contribution − total fixed costs = (total profit or total loss)
Thus, it does not attempt to allocate fixed costs in an arbitrary manner to different
products. The short-term objective is to maximize contribution per unit. If constraints exist
on resources, then Managerial Accounting dictates that marginal cost analysis be
employed to maximize contribution per unit of the constrained resource
Throughput Accounting
Advantages
Disadvantages
It is the fact that it is difficult for a manager to justify the cost of a nursing care programme.
Cost effectiveness
Cost-effectiveness analysis
It is a tool with great potential for the decision maker so long as he or she
recognises the difficulty in determining the true costs and benefits of various alternatives.
This tool can be especially useful when trying to decide between alternative expenditure
of money.
A cost benefit ratio (z) is defined as the ratio of the value of benefits of an
alternative to the value of alternative cost.
Cost benefit analysis is designed to consider the social costs and benefit
attributable to the project. The benefits are expressed in monetary terms to determine
whether a given programme is economically sound and to select the best out of several
programmes.
CRITICAL PATHWAY
Clinical Pathways were introduced in the early 1990s in the UK and the USA, and
are being increasingly used throughout the developed world. Clinical Pathways are
structured, multidisplinary plans of care designed to support the implementation of clinical
guidelines and protocols. They are designed to support clinical management, clinical and
non-clinical resource management, clinical audit and also financial management. They
provide detailed guidance for each stage in the management of a patient (treatments,
interventions etc.) with a specific condition over a given time period, and include progress
and outcomes details.
Clinical Pathways have four main components (Hill, 1994, Hill 1998):
1. A timeline
Select a Topic .
Select a Team .
In this step, data, rather than anecdotal reports, are key to understanding current
variation. For systems with electronic medical records, this process may be more
automated. For other systems, a careful review of medical records is necessary to identify
the critical intermediate outcomes, rate-limiting steps, and high-cost areas on which to
focus.
Evaluate Medical Evidence and External Practices .
After key rate-limiting steps have been identified, the critical pathway team must
evaluate the literature to identify evidence of best practices. For most rate-limiting steps,
there are few data available to define optimal processes of care. The critical pathway
development team will often lack answers to specific questions such as appropriate
observation period or length of stay. In the absence of evidence, comparison with other
institutions, or "benchmarking," is the most reasonable method to use.
The format of the pathway may vary widely. Important features include a task-
time matrix in which specific tasks are specified along a timeline. There is a spectrum of
pathways that range from a form that takes the place of the medical record to a simple
checklist. A reduction in charting that may occur with more complicated pathways is a
benefit. However, if the pathway format is too difficult to follow, it will not be used.
Critical pathways have become widely available in electronic format, where electronic
charting and pathway compliance are obtained simultaneously. One disadvantage to this
method is the absence of a standard medical record. This may result in duplication of
efforts and possible noncompliance with the pathway. This is particularly true among
physicians who are likely to be resistant to novel charting methods. For some systems, a
simple checklist at the front of the paper chart may be an optimal method for implementing
the pathway. These checklists would have areas to be filled in by different staff members
active in patient care.
Variances are patient outcomes or staff actions that do not meet the expectation of
the pathway. In general, variance in clinical pathways is a result of the omission of an
action or the performance of an action at an inappropriate (often, a late) time period.
Because the critical pathway is a series of time-associated actions, this analysis of variance
can be overwhelmed by multiple data points. Computer-assisted pathway analysis can
help with this issue. Another approach is for the pathway team to concentrate on a few
critical items in the pathway that have been identified in advance, such as extubation time
after cardiac surgery or length of stay in the intensive care unit. These are critical
intermediate outcomes that may have a substantial number of important contributory
factors. Arguably, the selection of areas to analyze and the analysis of variance are among
the most important processes in the critical pathway. Identification of factors that
contribute to variance and interventions to improve those factors are the key features in
process improvement.
Critical Path Analysis and PERT Chart
Critical Path Analysis and PERT are powerful tools that help you to schedule and
manage complex projects. They were developed in the 1950s to control large defense
projects, and have been used routinely since then.
As with Gantt Charts, Critical Path Analysis (CPA) or the Critical Path Method
(CPM) helps you to plan all tasks that must be completed as part of a project. They act as
the basis both for preparation of a schedule, and of resource planning. During management
of a project, they allow you to monitor achievement of project goals. They help you to see
where remedial action needs to be taken to get a project back on course.
Within a project it is likely that you will display your final project plan as a Gantt
Chart (using Microsoft Project or other software for projects of medium complexity or an
excel spreadsheet for projects of low complexity).The benefit of using CPA within the
planning process is to help you develop and test your plan to ensure that it is robust.
Critical Path Analysis formally identifies tasks which must be completed on time for the
whole project to be completed on time. It also identifies which tasks can be delayed if
resource needs to be reallocated to catch up on missed or overrunning tasks. The
disadvantage of CPA, if you use it as the technique by which your project plans are
communicated and managed against, is that the relation of tasks to time is not as
immediately obvious as with Gantt Charts. This can make them more difficult to
understand.
A further benefit of Critical Path Analysis is that it helps you to identify the
minimum length of time needed to complete a project. Where you need to run an
accelerated project, it helps you to identify which project steps you should accelerate to
complete the project within the available time. .
PERT is a variation on Critical Path Analysis that takes a slightly more skeptical
view of time estimates made for each project stage. To use it, estimate the shortest possible
time each activity will take, the most likely length of time, and the longest time that might
be taken if the activity takes longer than expected.
Use the formula below to calculate the time to use for each project
-----------------------------------------------------------
6
Importance
• Task priorities.
CPM models the activities and events of a project as a network. Activities are depicted as
nodes on the network and events that signify the beginning or ending of activities are
depicted as arcs or lines between the nodes. The following is an example of a CPM
network diagram:
CPM Diagram
From the work breakdown structure, a listing can be made of all the activities in the project.
This listing can be used as the basis for adding sequence and duration information in later
steps.
Once the activities and their sequencing have been defined, the CPM diagram can be
drawn. CPM originally was developed as an activity on node (AON) network, but some
project planners prefer to specify the activities on the arcs.
The time required to complete each activity can be estimated using past experience or the
estimates of knowledgeable persons. CPM is a deterministic model that does not take into
account variation in the completion time, so only one number is used for an activity's time
estimate.
The critical path is the longest-duration path through the network. The significance of the
critical path is that the activities that lie on it cannot be delayed without delaying the
project. Because of its impact on the entire project, critical path analysis is an important
aspect of project planning.
The critical path can be identified by determining the following four parameters for
each activity:
• ES - earliest start time: the earliest time at which the activity can start given that
its precedent activities must be completed first.
• EF - earliest finish time, equal to the earliest start time for the activity plus the time
required to complete the activity.
• LF - latest finish time: the latest time at which the activity can be completed
without delaying the project.
• LS - latest start time, equal to the latest finish time minus the time required to
complete the activity.
The slack time for an activity is the time between its earliest and latest start time,
or between its earliest and latest finish time. Slack is the amount of time that an activity
can be delayed past its earliest start or earliest finish without delaying the project.
The critical path is the path through the project network in which none of the
activities have slack, that is, the path for which ES=LS and EF=LF for all activities in the
path. A delay in the critical path delays the project. Similarly, to accelerate the project it
is necessary to reduce the total time required for the activities in the critical path.
As the project progresses, the actual task completion times will be known and the
network diagram can be updated to include this information. A new critical path may
emerge, and structural changes may be made in the network if project requirements
change.
CPM Limitations
CPM was developed for complex but fairly routine projects with minimal uncertainty in
the project completion times. For less routine projects there is more uncertainty in the
completion times, and this uncertainty limits the usefulness of the deterministic CPM
model. An alternative to CPM is the PERT project planning model, which allows a range
of durations to be specified for each activity.
Benefits
There are many issues in critical pathway development and implementation that are of
concern to practitioners who care for patients with cardiovascular disease.
The first issue is that critical pathways address processes in the "ideal" patient and
in some cases do not address issues in the majority of patients who enter the path.
Identification of appropriate patients to enter the pathway is an important issue in
implementation. In general, critical pathways are more applicable to patients with
uncomplicated illnesses who are undergoing procedures or surgery. For patients
treated with medical conditions such as acute coronary syndromes, it is difficult to
define "appropriate" treatment for the majority of patients. Therefore, critical
pathways will tend to identify a great deal of variance in the care of these patients
that may or may not wasteful or potentially harmful. The goal of placing most
patients within pathways may not benefit the individual patient.
A second issue is how to evaluate critical pathways as an effective tool in
improving patient care. As we have mentioned, little controlled research has been
performed on the effectiveness of pathways. One reason for this is that at any one
medical center, "pathway" care cannot be easily differentiated from "usual" care
because of contamination from the pathway intervention. Randomized trials with
the unit of randomization at the medical center would be the optimal evaluation
method.
The real impact of critical pathways and appropriateness protocols is their use as
tools for collection of information. Pathways can serve as a screening test for
inefficient care. The danger is that a pathway with too many critical areas under
review will be too sensitive, resulting in the review of a large number of marginally
appropriate cases.Review of critical pathway data should be focused on the
highest-impact areas in terms of either cost, quality of care, or, preferably, both.
Health care reform is a general rubric used for discussing major health policy
creation or changes—for the most part, governmental policy that affects health care
delivery in a given place. Health care reform typically attempts to:
Broaden the population that receives health care coverage through either public
sector insurance programs or private sector insurance companies
Expand the array of health care providers consumers may choose among
Improve the access to health care specialists
Improve the quality of health care
Give more care to citizens
Decrease the cost of health care
We need a different approach to healthcare reforms in India
Goal
The goal of healthcare reform is to make healthcare more accessible and available
to all citizens. Currently, millions remain uninsured due to job loss, or because healthcare
premiums would simply be too costly. Ideally, healthcare reform would enable more, to
become insured, and also decrease the cost of healthcare. However, this is a goal that is not
so easily obtained, due to the complexities of the healthcare system , and the quality of care
provided here.
The Ministry of Health and Family Welfare is the Indian government ministry
charged with health policy in India. It is also responsible for all government programs
relating to family planning in India.
The Minister of Health and Family Welfare holds cabinet rank as a member of the
Council of Ministers. The current minister is Shri. Ghulam Nabi Azad, who is assisted by
a Minister of States for Health and Family Welfare, Shri. Dinesh Trivedi & Shri. S.
Gandhiselvan.
1 Department of Health
2 Department of Family
Welfare
3 Department of AYUSH
\
1. Department of Health
The Department of Health deals with health care, including awareness campaigns,
immunization campaigns, preventive medicine, and public health. Bodies under the
administrative control of this department are:
10) National Vector Borne Disease Control Programme (NVBDCP) (vector-born disease)
11) Pilot Programme on Prevention and Control of Diabetes, CVD and Stroke (diabetes,
cardiovascular disease, stroke)
19) All India Institute of Physical Medicine and Rehabilitation (AIIPMR), Mumbai
25) National Vector Borne Disease Control Programme (NVBDCP) (vector-born disease)
26) Pilot Programme on Prevention and Control of Diabetes, CVD and Stroke
(diabetes, cardiovascular disease, stroke)
34) All India Institute of Physical Medicine and Rehabilitation (AIIPMR), Mumbai
The Department of Family Welfare (FW) is responsible for aspects relating to family
welfare, especially in reproductive health, maternal health, pediatrics, information,
education and communications; cooperation with NGOs and international aid groups; and
rural health services. The Department of Family Welfare is responsible for:
3. Department of AYUSH
Healthcare in India
India has a universal health care system run by the local (state or territorial)
governments. Government hospitals, some of which are among the best hospitals in India,
provide treatment at taxpayer expense. Most essential drugs are offered free of charge in
these hospitals. However, the fact that the government sector is understaffed,
underfinanced and that these hospitals maintain very poor standards of hygiene forces
many people to visit private medical practitioners.
The charges for basic in-hospital treatment and investigations are much less
compared to the private sector. The cost for these subsidies comes from annual allocations
from the central and state governments. For example, an outpatient card at AIIMS (one of
the best hospitals in India) costs a one-time fee of 10 rupees (around 20 cents U.S.) and
thereafter outpatient medical advice is free. In-hospital treatment costs depend on financial
condition of the patient and facilities utilized, but are usually much less than the private
sector. For instance, a patient is waived treatment costs if their income is below the poverty
line. Another patient may seek an air-conditioned room for an additional fee.
Primary health care is provided by city and district hospitals and rural primary
health centres (PHCs). These hospitals provide treatment free of cost. Primary care is
focused on immunization, prevention of malnutrition, pregnancy, child birth, postnatal
care, and treatment of common illnesses.[citation needed] Patients who receive
specialized care or have complicated illnesses are referred to secondary (often located in
district and taluk headquarters) and tertiary care hospitals (located in district and state
headquarters or those that are teaching hospitals).
Now organizations like Hindustan Latex Family Planning Promotional Trust and
other private organizations have started creating hospitals and clinics in India, which also
provide free or subsidized health care and subsidized insurance plans.
In India, reforms can develop on sound principles on the basis of the learning of all
available systems, our strengths and needs. To make the common man healthy in the
Indian scenario, we need a different approach.
Funding models
Universal health care in most countries has been achieved by a mixed model of
funding. General taxation revenue is the primary source of funding, but in many countries
it is supplemented by specific levies (which may be charged to the individual and/or an
employer) or with the option of private payments (either direct or via optional insurance)
for services beyond that covered by the public system.
Almost all European systems are financed through a mix of public and private
contributions. The majority of universal health care systems are funded primarily by tax
revenue (e.g. Portugal, Spain, Denmark and Sweden). Some nations, such as Germany,
France and Japan employ a multi-payer system in which health care is funded by private
and public contributions. However, much of the non-government funding is by defined
contributions by employers and employees to regulated non-profit sickness funds. These
contributions are compulsory and vary according to a person's salary, and are effectively
a form of hypothecated taxation.
A distinction is also made between municipal and national healthcare funding. For
example, one model is that the bulk of the healthcare is funded by the municipality,
speciality healthcare is provided and possibly funded by a larger entity, such as a
municipal co-operation board or the state, and the medications are paid by a state agency.
Single payer
The term single-payer health care is used in the United States to describe a funding
mechanism meeting the costs of medical care from a single fund. Although the fund holder
is usually the government, some forms of single-payer employ a public-private system.
Public
Some countries (notably the United Kingdom, Italy, Spain and the Nordic
countries) choose to fund health care directly from taxation alone. Other countries with
insurance-based systems effectively meet the cost of insuring those unable to insure
themselves via social security arrangements funded from taxation, either by directly
paying their medical bills or by paying for insurance premiums for those affected.
Compulsory insurance
Private insurance
In some countries with universal coverage, private insurance often excludes many
health conditions which are expensive and which the state health care system can provide.
For example in the UK, one of the largest private health care providers is BUPA which
has a long list of general exclusions even in its highest coverage policy. In the USA (which
tried to transition towards universal health care, but is being challenged through the court
systems as unconstitutional, because of the mandatory purchasing requirement) dialysis
treatment for end stage renal failure is generally paid for by government and not by the
insurance industry. Persons with privatized Medicare (Medicare Advantage) are the
exception and must get their dialysis paid through their insurance company, but persons
with end stage renal failure generally cannot buy Medicare Advantage plans.
HEALTH INSURANCE
Health insurance is insurance against the risk of incurring medical expenses. By
estimating the overall risk of health care expenses, an insurer can develop a routine finance
structure, such as a monthly premium or payroll tax, to ensure that money is available to
pay for the health care benefits specified in the insurance agreement. The benefit is
administered by a central organization such as a government agency, private business, or
not-for-profit entity.
Difficulty:
Challenging
Instructions
Revenue can come from patient payments, tax dollars, donations, insurance credits.
Be sure to deduct a percentage of the patient bills that will remain
uncollected, the charity work expected by the hospital and the pro bono
work it does.
4. Add all medical equipment costs, ongoing and expected expansion or replacement
of new diagnostic equipment.
How many staff hours are spent on each bed, occupied or not.
Use this figure as an average to get a cost per patient year.
Add to that the non medical costs per bed.
Include every possible cost that keeps that bed in the hospital.
Don't forget replacement costs per annum for any and all patient needs.
9. Write in an emergency expense fund. Disasters occur and the hospital must be
prepared for them when they arrive.
School should have a separate budget, i.e. principal in charge of the school of
nursing should be the drawing and disbursing officer and empowered to plan for
operating the funds in all different heads (as per government rules and regulations and as
seemed necessary for running an educational institutions).
Both the school/college and hospital should have separate budget. The budget for
the school or college is annually planned by the nursing director, principal and general
manager and approved by the managing director.
1. Revenue: It includes assets, fixed deposits, investments, loan, advances and income.
2. Expenditure: It includes capital, recurring annual mandatory and non recurring.
- Rent
- Salary
- Stationary items
- Contingency
- Guest relation
- House keeping indent
- Pharmacy indent
- AV aids
- Journals
- Books
- Maintenance: Repair, Replacement, Electricity, Phone, Drinking Water, Sewage
Disposal.
Non recurring expenditure includes:
- DME endowment
Endowment Fund (property or income left to someone like insurance) Rs
20,00,000/- in two installments (before one year 10,00,000/ and second year
Rs.10,00,000/) which is paid to the DME office.
- Security fixed deposit Rs.10,00,000/ with the joint account of registrar of the
university and trustees.
- Solvency certificate(state of having more money than one owes) for Rs. 30,00,000/
from nationalized bank for a period of 5 years.
- University endowment
Approximately the Revenue is Rs. 21,24,000/ and where as the Expenditure is Rs. 20,52,859/
Annual auditing is done to plan for the next year budget and to evaluate the current
year budget.