Energy Efficiency in Solapur Textiles
Energy Efficiency in Solapur Textiles
ON
   AUTO LOOM / RAPIER LOOM (4 Nos)
     (SOLAPUR TEXTILE CLUSTER)
We have received very encouraging feedback for the BEE SME Program in various SME
Clusters. Therefore, it was decided to bring out the DPR for the benefits of SMEs. We sincerely
thank the officials of BEE, Executing Agencies and ISTSL for all the support and cooperation
extended for preparation of the DPR. We gracefully acknowledge the diligent efforts and
commitments of all those who have contributed in preparation of the DPR.
                                                       Contents
List of Annexure                                                                                                                  vii
List of Tables                                                                                                                    vii
List of Figures                                                                                                                  viii
List of Abbreviation                                                                                                             viii
Executive summary                                                                                                                 ix
About BEE’S SME program                                                                                                            x
1        INTRODUCTION ........................................................................................................ 1
1.1      About the solapur textile cluster .................................................................................. 1
1.1.1    Production process ..................................................................................................... 1
1.2      Energy performance in solapur textile cluster .............................................................. 4
1.2.1    Specific energy consumption of final product .............................................................. 4
1.3      Proposed equipment to be upgrade ............................................................................ 4
List of Tables
Table 2.1 Benefits of Rapier loom over conventional power loom .................................... 10
                                                                                                                               vii
List of Figures
List of Abbreviations
                                                                                                                              viii
                                   EXECUTIVE SUMMARY
Zenith Energy Services Pvt. Ltd is executing BEE-SME program in Solapur textile cluster,
supported by Bureau of Energy Efficiency (BEE) with an overall objective of improving the
energy efficiency in cluster units.
Solapur textile cluster is one of the largest textile clusters in India; accordingly this cluster
was chosen for energy efficiency improvements by implementing energy efficient
measures/technologies, so as to facilitate maximum replication in other textile clusters in
India.
The main energy forms used in the cluster units are electricity and fuel such as wood and
other biomass product. Electricity is mostly used in power looms, winding machines,
doubling machines, warping machines, hang dyeing machine, blowers, hydro extractor,
small pumps and lighting.
Retrofitting of power looms with rapier/auto looms will reduces the power consumption &
production cost and also increases the rate of production.
Project implementation i.e. installation of four rapier/auto loom in place of sixteen conventional
power loom will lead to reduction in electricity consumption by 18720 (4680 x 4) kWh per
annum however; this intervention will not have any effect on the existing consumption pattern of
fuel.
Total investment, debt equity ratio for financing the project, monetary savings, Internal rate of
return (IRR), Net present value (NPV),Debt service coverage ratio (DSCR), Return on
investment (ROI) etc. for implementing energy efficient economizer is furnished in Table below:
                                                                                                  ix
                              ABOUT BEE’S SME PROGRAM
The energy use technology studies would provide information on technology status, best
operating practices, gaps in skills and knowledge on energy conservation opportunities,
energy saving potential and new energy efficient technologies, etc for each of the sub sector
in SMEs.
In most of the cases SME entrepreneurs are dependent on the locally available
technologies, service providers for various reasons. To address this issue BEE has also
undertaken capacity building of local service providers and entrepreneurs/ Managers of
SMEs on energy efficiency improvement in their units as well as clusters. The local service
providers will be trained in order to be able to provide the local services in setting up energy
efficiency projects in the clusters
The objective of this activity is to facilitate the uptake of energy efficiency measures through
innovative financing mechanisms without creating market distortion
                                                                                              x
                                                                  Auto loom/Rapier Loom (4 No.)
1 INTRODUCTION
The products manufactured in Solapur Textile Cluster are cotton terry towels and bed
sheets. The towels and bed sheets are renowned in the country and have good market in
India. The main raw material for the units is cotton yarn, which is procured from local
spinning mills and agents. The cost of energy (electrical and thermal energy) as percentage
of manufacturing cost varies between 8 and 10%.
Majority of the cluster units are of integrated type, where the raw material yarn is processed
in-house to the final product. The energy cost is second to the raw materials cost. Majority of
the units in the cluster are dependent on local/ run of the mill technologies of low end and
with little investment initiatives and technology up-gradation.
The main energy forms used in the cluster units are grid electricity, wood, and small quantity
of coal. The electricity is used for power looms, doubling machines, winding machines, hydro
extractors, warping machines and lighting. Wood is used as fuel for boilers, thermic fluid
heaters, and chulhas for hot water generation. The details of annual energy consumption of
a typical unit having a production capacity of 1, 20,000 kg of final product of the cluster are
furnished in the Table 1.1 below:
Production process
The main operational process for production of towels and bed sheets in cluster units are:
Doubling
In the Doubling process, thin single yarn is converted to double yarn for strengthening the
yarn by using doubling machine.
Yarn dyeing
Initially, the yarn is soaked in soap water for 24 hours to remove the dirt and other foreign
materials and after soaking, the yarn is taken for bleaching. Bleaching is carried out by
                                                                                               1
                                                              Auto loom/Rapier Loom (4 No.)
soaking the yarn in tanks mixed with bleaching agents and after completion of the process;
the yarn is washed with normal water.
The hang dyeing machine tanks are filled with required quantity of normal water and
required chemicals and dyeing agents are added. The temperature of the water is raised by
oil circulation or direct steam injection. Fire wood is used as fuel. The required colors are
added to the yarn and the dyeing process takes about 90 to 120 minutes per batch. After
dyeing, the yarn is washed with normal water, and the yarn is taken for soaping for colour
fixation in hot water for about 20 minutes in hang dyeing machines. The water is drained to
the waste drainage lines. The wet yarn is taken to hydro extractors for removing the water in
the yarn and taken for drying in the natural sunlight.
Winding
The yarn after drying is taken for winding in which the yarn is wounded to bobbins and
cones. The winded yarn is taken for further process.
Warping
In warping, the winded yarn is wound to beams according to designed pattern (customized
designs). Then the beams are taken for Weaving.
Weaving
The beams, which are wound with yarn are taken and placed in power looms where the
designed pattern is already set. In power looms, the yarn is converted to final product (Towel
or bed sheets) by weaving. The product obtained from weaving is taken for stitching and
packing. The general process flow diagram of a typical unit for production of towels and bed
sheets is furnished in Figure 1.1.
                                                                                            2
                                                              Auto loom/Rapier Loom (4 No.)
SINGLE YARN
(Raw material)
DOUBLING MACHINES
REALING MACHINES
                                              DYEING
     CHULHA                          MANUAL DYEING IN HOT
                                                                        Drained water
                                           WATER
                                       HYDRO EXTRACTORS
      FUEL                                                                       OPEN
(Wood)
WINDING MACHINES
                                                                                 To Drain
                                        WARPING MACHINES
POWER LOOMS
DISPATCH
The production process as depicted above is similar for all textile units in Solapur textile
cluster. However, depending on type of product and product quality, the above stated
process flow varies as per the requirement of the industry.
                                                                                            3
                                                              Auto loom/Rapier Loom (4 No.)
Majority of the industries located in solapur are engaged in manufacturing of towels and bed
sheets. The main energy sources for Solapur cluster units are electricity and fuels such as
Wood & briquettes. The wood and GN husk briquettes are used as fuel for boilers, thermic
fluid heaters and chulhas for hot water generation and electricity is used for operation of
prime movers of doubling machine motors, ID & FD fans, pumps, hank dyeing machine
drives, power loom drives, winding machine motors, etc. Majority of the units in the Solapur
textile cluster are using wood for thermal energy generation due to easy availability and
economical point of view.
In a typical textile manufacturing unit annual consumption of electrical energy and wood is
1,97,784 kWh and 144 tonnes respectively for average production capacity of 1,20,000 kg of
final product.
Specific electrical and thermal energy consumption in textile unit depends upon the final
product manufactured in that unit. The electrical and thermal energy consumption of typical
textile unit is 1.65 kWh per kg of final product and 1.20 kg of wood per kg of final product
respectively (includes all colours dyeing in cold water, medium temperature water and high
temperature water)
During energy audit studies in various textile industries in Solapur textile cluster, it was
observed that about 1200 power loom in Solapur Textile cluster. All power looms are of
shuttle type and are too old. These power looms are used for weaving terry towels and bed
sheets.
In the present conventional shuttle looms, it is necessary to pass a shuttle weighing around
half a kilogram through the warp shed to insert a length of weft yarn which weighs only few
grams. The shuttle has to be accelerated rapidly at the starting of picking cycle and also to
be decelerated, stopped abruptly at the opposite end. This process creates heavy noise and
shock and consumes considerable energy. Beat-up is done by slay motion which again
weighs a few hundred kilograms. The wear life of the picker and checking mechanism is also
limited due to heavy shock. Due to the above reasons smooth sequence of weaving is
disturbed which affects the maximum running speed and hence machine production. In multi
                                                                                             4
                                                                Auto loom/Rapier Loom (4 No.)
colour weft insertion, Drop box motion is attached which is also further limits the speed of the
machine. The small weft package in the shuttle requires frequent replenishments and for
each loom stoppage there is a possibility of one defect. The probability of weft way fabric
defects are high to the tune of 70% in shuttle looms. Even in automatic shuttle looms there is
a chance of transfer failures and weft lashing in defects.
The power looms are one of the most important equipment in producing of cotton terry
towels and bed sheets. The power looms are used for weaving the dyed yarn to towels and
bed sheets.
Present electricity consumption in power loom machine is 33.6 kWh and connected with 1.0
HP motor. The average production is 48 kg per day per machine. The power loom machines
are operated in two shifts in a day.
Production cost for various power loom machine of three typical units in the cluster are
separately furnished in Table 1.2 below:
                                                                                                  5
                                                                  Auto loom/Rapier Loom (4 No.)
The technology and innovations in SMEs are generally different from that of large firms.
Technology in the SME sector has an increasingly complex or combinative character, most
of the SMEs units in Solapur cluster are labour intensive and utilize local resources. The
SME entrepreneurs are generally not willing to invest in state-or-art technology. Major
barriers in the up-gradation of technology in the cluster are non availability of technology;
distrust on technology supplier, lack of awareness about energy efficiency among small and
medium enterprises, prevents them from adoption of energy efficient technologies.
The major technical barriers that prevented the implementation of Rapier loom are
• Lack of awareness and information about the rapier loom and its benefit
Implementation of the proposed project activity requires investment of ` 27.68 lakh per unit.
Such investment is not commonly seen in the cluster units for energy efficiency
improvement. Further, from the business perspective of SMEs, it is more viable, assured,
and convenient to invest on project expansion for improving the production capacity or
quality, rather than make piecemeal investment in retrofit and replace options for energy
savings. In view of this and given the limited financial strength of the textile mills, it is evident
that the owners would not like to take the risk and invest in energy efficiency measures.
However, the financial attractiveness of the project activity may motivate the owners to move
forward in taking up initiatives in energy conservation and efficiency.
The non-availability of skilled manpower having awareness about energy efficiency and
related issues in the cluster is one of the major barriers. Lack of skilled manpower for
operation and maintenance of the rapier looms is also one of the major barriers that
prevented the implementation.
The recent recession in European and other Asian countries and reduction in market trend
for the products in national and international markets was also one of the major barriers for
the proposed technology.
                                                                                                   6
                                                                Auto loom/Rapier Loom (4 No.)
The rapier looms offer unparalleled versatility when it comes to yarns. From the finest counts
of cotton to the thickest Industrial yarns and can handle anything thrown at its negative
rapier head. The soft-pick gear system enables smooth transition of even highly fancy yarns
like embroidery and slub. The rapier loom is upgrade from shuttle-looms to the world of
modern weaving system and shutte-less weaving. Rapier looms has been designed to
replace the old shuttle looms without any major changes to the existing infrastructure. The
Immediate benefits of selecting rapier looms are
        •   20% subsidy under TUFS on our certified looms in addition to State Government
        Incentives.
        •   Step-by-Step consultancy by our engineers to help you upgrade, install & adapt
        to new machines.
                                                                                            7
                                                                  Auto loom/Rapier Loom (4 No.)
Speed
The normal speed of the conventional power looms is around 120 RPM, where as in rapier
looms, the speeds upto 220 RPM (actual) can be attained and coupled with high efficiencies
of upto 95%, this machine gives upto 3 times more productivity than the conventional power
looms.
Rapier looms offers up to 8 Color Pick-at-Will weft insertions, so that weave the fanciest of
fabrics can be attained. The pick-at-will system is computerised and microprocessor
controlled, hence letting the programme sequences of more than 1, 00,000 picks. Such
technological edge will definitely give you an edge in the market.
Rapier looms realises the most delicate need of rapier users to prevent start-marks in
weaving. The custom designed ‘HT-Drive’ motor of the machine supplies more than 150%
torque for the first-pick to successfully prevent the start marks.
Considering 3 times more productivity with same space and even lesser amount of man
power along with lower power consumption, it is quite obvious that rapier looms can offer
lower production costs compared to conventional power-looms or even rapier-shuttle change
machines. Moreover continuous weft-insertion eliminates the need for investing in pirn-
winding machines or even extra operators.
Lower Maintenance
Due to lower vibrations, there’s less wear-n-tear of rotating components and bearings
resulting in lower maintenance costs. Also, centralised lubrication offered on the looms gives
single-point lubrication for the complete machine, thus further reducing the headaches of
maintenance
Shedding
The rapier loom has the flexibility and can easily add and attach any of the shedding motions
available in the market including:
• Dobby
• Jacquard
• Cam Shedding
• Positive Cam: for Heavy plain fabrics (bolting cloth, tirecord cloth etc.)
                                                                                             8
                                                                 Auto loom/Rapier Loom (4 No.)
Take-Up
Universal 7-wheel Wretchet-n-Pawl semi-positive take-up is the most widely used and well
established Take-Up system offered in rapiers around the world. The well designed take-up
is capable of handling a weft-density of 4-120 picks per Inch.
Let-Off
The capability of rapier looms to weave any and all kinds of fabrics has been created due to
3 different let-off options available with the machine depending on your fabric.
Ruti-Type
For weavers of regular cotton-fabrics who’ve been used to highly versatile Ruti-Type let-off.
Microprocessor Controller
The heart of the complete control system, this microprocessor is one of the most powerful
control systems offered today for crank-type rapier looms. The system can be programmed
to output any kinds of pick programs. The standard functions include:
• Constant monitoring of weft and warp yarn for breakages Cloth Length Counter
• Pick-programming
• Weft-Controller
Exclusive Feature
For all power loom users, investing in Rapier looms normally require them to erect a
completely new building infrastructure. But, with AWT-250EX, we’re proud to say that we are
the only rapier-loom manufacturer in the world whose machines can fit in the regular ’16-feet
sheds’, thus eliminating the need for any additional investment and hence brings down the
up-gradation costs considerably. In Solapur Textile Cluster units, majority of the units has
power looms, Considering the above facts and benefits of the rapier loom and for reducing
the overall production cost, it is suggested to replace power looms with rapier looms. The
details of production cost per kg in power looms is provided in Annexure 1
The Rapier loom suppliers are available in Pune, which is 200 km from Solapur city and M/s
Laxmi Shuttleless loom is also planning to appoint a dealer at Solapur.
The service providers are available in Pune. Details of service providers are given in
Annexure 6.
                                                                                               9
                                                                          Auto loom/Rapier Loom (4 No.)
Benefits of rapier loom over power loom machine are shown in Table 2.1 below.
 Max. 110 RPM (eff. 70 RPM due to lower               Max. 220 RPM (eff. 200 RPM due to Higher Efficiency)
 efficiency)
 Lower Output per shift                               Upto 2.5 times more output per shift
Lower Output per operator Upto 2.5 times more output per operator
 ‘Kandi / Shuttle / Pirn-Winder’ machine & operator   Shuttle less (No Kandi, No Pirn, No Pirn Machine
 required                                             Operator)
 High Maintenance because of extremely high           Extremely Low vibration, hence lower maintenance
 vibration
 Higher & Faster Wear-n-Tear of components            Lower vibration leads to better & longer life
 Light-Weight leading to shorter life and higher      Heavy-Duty Structure to reduce vibration thus leading
 vibrations                                           to longer life
 Lower Output per unit area of floor space            3 times more output per unit area of floor space
As discussed above, the production cost per kg of final product i.e., towels or bed sheets is
high due to low production per loom, more breakdowns, more power consumption, more
manpower cost and also the quality is poor compared with the product produced in rapier
looms.
                                                                                                          10
                                                                Auto loom/Rapier Loom (4 No.)
• More colours in weft direction (upto 12) by Pick and Pick method.
Terms of payment
50% advance with purchase order, and remaining 50% along with taxes and duties against
Performa invoice before dispatch.
The quoted prices are exclusive of all taxes, duties, levies such as excise duty, central/local
sales tax, octroi, etc. as are applicable at the time of dispatch or imposed by any statutory
authorities subsequently or paid by us, shall be paid by you extra at actual. However CVD is
charged at 8% plus 4% on the unit price plus 3% education cess and VAT is charged at 5%.
Warranty
The supplier shall repair or replace at free of cost, on ex – works basis the whole or any
portion of material which under normal and proper use and maintenance proves defective in
material and/or workmanship within 12 months from the date of commissioning or 18 months
from the date of shipment of equipment whichever is earlier, provided prompt notice is given
of such defects.
                                                                                            11
                                                                     Auto loom/Rapier Loom (4 No.)
The process down time is envisaged as installation of Rapier loom will take 10 days for
installation.
Reed Space 200, 230, 250, 260, 280 cm Driving Motor 1.5 kW, 960 RPM
 Weft Insertion        Both Side Flexible Rapier     Applicable Yarn          Cotton, All Man Made
                       System                                                 Yarns
 Weft Colours          * Up to 6 Colors              Terry Loop               By Movable Reed
                                                                              Operated By Solenoid.
 Weft Detection        By Piezo Electronic Slide     Terry Loop Height        0-10 mm
                       Sensor
 Shedding Motion       * Electronic Dobby /          Cramming Motion          Electronic
                       Jacquard
 Cloth Roll dia.       400 mm                        Control Panel            LCD System With
                                                                              Keypad For
                                                                              Programming of Dobby
 Selvedge              Independent Positive Leno -   Beam Flange Dia.         Ground Beam: 600 mm
                       Flase Selvedge Motion                                  Top Beam: 750 mm
 Warp Yarn zetection   2 Row Electrical Type For     Lubrication              Centralised Lubrication
                       Top Beam & Ground Beam.                                System
                                                                              Electronically Operated
 Braking System        By Electromagnetic Brake      Letting Off Motion       for Ground / Pile
                                                                              Beam.
                                                                                                     12
                                                                          Auto loom/Rapier Loom (4 No.)
Total electricity saving would be about 18720 kWh per year by the installation of proposed
four rapier loom equipment.
Proposed equipment has significant impact in improving the quality of the product.
The proposed equipment increased in production is almost 2.5 to 3 times per loom.
Raw material consumption is reduces due to reduction in breakages of the yarn in shuttle
power loom.
The monetary savings due to installation of one rapier looms is ` 3,20,700 per year hence
for 4 rapier looms, the monetary benefit works out at ` 12,82,800. The monetary savings are
due to result of power savings, less manpower cost, improved quality, low maintenance,
more output/machine etc. Detail monetary benefit is given in Table 3.1 below:
                                                                                                       13
                                                                Auto loom/Rapier Loom (4 No.)
As installation of Rapier loom eliminates Mechanical shock, Vibration and sound etc., this
may less the breakdowns and working environment may improved.
The technology selected for the implementation is new and energy efficient. The technology
implemented will create awareness among the workforce about energy saving.
The major GHG emission reduction source is CO2 and this equipment will reduce electricity
consumption. The total emission reductions are estimated as 16 tonne of CO2 per annum
due to implementation of the project activity.
                                                                                             14
                                                                   Auto loom/Rapier Loom (4 No.)
The total cost for installation of 4 nos Rapier loom is estimated at `.26.00 lakh, which
includes, Panel, switches, cabling etc.
The total cost of implementation of the proposed rapier loom is estimated at ` 27.68 lakh.
The above cost includes cost of equipment/machinery, cost of fabrication (and/or)
commissioning charges and the details are furnished in Table 4.1 below:
The total cost of the proposed technology is estimated at ` 27.68 lakh. The entrepreneur’s
contribution is 25% of total project cost, which is ` 6.92 lakh.
The term loan is 75% of the total project, which is ` 20.76 lakh. As the overall energy
efficiency in the project is more than 15% it qualifies for subsidy of 25% of the project cost as
per the NMCP scheme of Ministry of MSME, GoI. 25 % of the project cost in this case works
out to ` 6.92 lakh. As the subsidy is normally available after implementation of the project the
same has not been taken in the project cost and means of finance. On receipt of subsidy
from Ministry of MSME, GoI through the nodal agency the amount of subsidy is generally set
off [reduced] from the loan outstanding by the lending bank. Availability of this subsidy will
make the project economically more attractive
The interest rate is considered at 10.00% which is SIDBI'S Lending rate for energy efficiency
projects. The loan tenure is assumed 5 years and the moratorium period is 6 months.
                                                                                                   15
                                                               Auto loom/Rapier Loom (4 No.)
Considering the above mentioned assumptions, the net cash accruals starting with ` 8.64
lakh in the first year operation and gradually increases to ` 25.79 lakh at the end of sixth
year.
The total project cost of the proposed equipment is ` 27.68 lakh and monetary savings due
to reduction in electricity consumption is ` 12.83 lakh and the simple payback period works
out to be 2.15 years (26 months).
The Net present value of the investment at 10.00% works out to be ` 12.04 lakh.
The after tax Internal Rate of Return of the project works out to be 25.25% thus the project is
financially viable.
The average return on investment of the project activity works out at 29.78% for an
investment of ` 27.68 lakh.
A sensitivity analysis has been carried out to ascertain how the project financials would
behave in different situations like there is an increase in electricity savings or decrease in
electricity savings. For the purpose of sensitive analysis, two scenarios are considered are.
                                                                                               16
                                                                  Auto loom/Rapier Loom (4 No.)
In each scenario, other inputs are assumed as constant. The financial indicators in each of
the above situation are indicated along with standard indicators.
Details of sensitivity analysis for different scenario are furnished in Table 4.3 below:
As could be seen from the above table, though the project is highly sensitive to electricity
savings, DSCR works out to be 2.77 times in worst scenario, which indicates the strength of
the project.
The project is expected to be completed in 8-10 weeks from the date of financial closure.
The detailed schedule of project implementation is furnished in Annexure 5.
                                                                                                 17
                                                                   Auto loom/Rapier Loom (4 No.)
                                                Conventional                       Monetary
S. No                  Parameter                                     Auto looms
                                                Power looms                                 `)
                                                                                   Benefit (`)
1 No. of Looms 4 1 0
7 Manpower 4 1 3
                                                                                                 18
                                                     Auto loom/Rapier Loom (4 No.)
Yarn
Doubling Yarn
Drying
Winding
Warping
Power looms
Stitching
Finished Product
                                                                               19
                                                               Auto loom/Rapier Loom (4 No.)
In the conventional shuttle looms, it is necessary to pass a shuttle weighing around half a
kilogram through the warp shed to insert a length of weft yarn which weighs only few grams.
The shuttle has to be accelerated rapidly at the starting of picking cycle and also to be
decelerated, stopped abruptly at the opposite end. This process creates heavy noise and
shock and consumes considerable energy. Beat-up is done by slay motion which again
weighs a few hundred kilograms. The wear life of the picker and checking mechanism is also
limited due to heavy shock. Due to the above reasons smooth sequence of weaving is
disturbed which affects the maximum running speed and hence machine production. In multi
colour weft insertion, Drop box motion is attached which is also further limits the speed of the
machine. The small weft package in the shuttle requires frequent replenishments and for
each loom stoppage there is a possibility of one defect. The probability of weft way fabric
defects are high to the tune of 70% in shuttle looms. Even in automatic shuttle looms there is
chance of transfer failures and weft lashing in defects.
                                                                                             20
                                                                           Auto loom/Rapier Loom (4 No.)
WDV Depreciation
      Particulars / years         1          2                  3             4            5             6
 Plant and Machinery
 Cost                             27.68          5.54               1.11       0.22         0.04           0.01
 Depreciation                     22.14          4.43               0.89       0.18         0.04           0.01
 WDV                               5.54          1.11               0.22       0.04         0.01           0.00
                                                                                                               21
                                                                Auto loom/Rapier Loom (4 No.)
Projected Profitability
         Particulars / Years    1         2          3             4         5            6
  Revenue through Savings
  Fuel savings                  12.83     12.83      12.83         12.83    12.83         12.83
 Total Revenue (A)              12.83     12.83      12.83         12.83    12.83         12.83
  Expenses
  O & M Expenses                 1.11      1.16       1.22          1.28     1.35          1.41
  Total Expenses (B)             1.11      1.16       1.22          1.28     1.35          1.41
  PBDIT (A)-(B)                 11.72     11.67      11.61         11.55    11.48         11.42
  Interest                       1.88      1.81       1.47          1.04     0.55          0.07
  PBDT                           9.84      9.85      10.14         10.51    10.93         11.34
  Depreciation                   1.46      1.46       1.46          1.46     1.46          1.46
  PBT                            8.38      8.39       8.67          9.04     9.47          9.88
  Income tax                        -      1.84       3.14          3.51     3.70          3.85
 Profit after tax (PAT)          8.38      6.55       5.53          5.53     5.77          6.03
 Computation of Tax
                                                                                    ` (in lakh)
        Particulars / Years      1        2          3             4        5            6
Profit before tax                  8.38       8.39       8.67       9.04     9.47          9.88
Add: Book depreciation             1.46       1.46       1.46       1.46     1.46          1.46
Less: WDV depreciation            22.14       4.43       0.89       0.18     0.04          0.01
Taxable profit                  (12.30)       5.42       9.25      10.33    10.90         11.33
Income Tax                            -       1.84       3.14       3.51     3.70          3.85
 Assets
 Gross Fixed Assets              27.68    27.68      27.68         27.68    27.68         27.68
 Less: Accm. Depreciation         1.46     2.92       4.38          5.84     7.31          8.77
 Net Fixed Assets                26.21    24.75      23.29         21.83    20.37         18.91
 Cash & Bank Balance              8.64    13.35      16.34         18.74    20.86         25.79
 TOTAL ASSETS                    34.85    38.10      39.63         40.57    41.23         44.70
 Net Worth                       15.30    21.85      27.38         32.91    38.68         44.70
 Dept equity ratio                2.83     2.35       1.77          1.11     0.37          0.00
                                                                                                  22
                                                                                 Auto loom/Rapier Loom (4 No.)
NPV 12.04
                                                                                                                              23
                                                         Auto loom/Rapier Loom (4 No.)
 Return on Investment
                                                                                ` (in lakh)
     Particulars / Years      1          2       3       4           5       6       Total
Net Profit Before Taxes        8.38       8.39    8.67    9.04       9.47    9.88     53.84
Net Worth                     15.30      21.85   27.38   32.91      38.68   44.70    180.81
                                                                                    29.78%
Debt
Interest on Term Loan             1.88   1.81     1.47       1.04    0.55    0.07     6.83
Repayment of Term Loan            1.20   3.30     4.00       4.60    5.10    2.56    20.76
Total (N)                         3.08   5.11     5.47       5.64    5.65    2.63    19.31
Average DSCR (M/N)                2.77
                                                                                        24
                                                                  Auto loom/Rapier Loom (4 No.)
                                                                    days
S. No.                    Activities
                                                    1    2    3       4          5    6/7   8/9
                                                                                                  25
                                                               Auto loom/Rapier Loom (4 No.)
                                                                                         26
                                              Auto loom/Rapier Loom (4 No.)
                                                                        27
Auto loom/Rapier Loom (4 No.)
                          28
                 Standard application form for financial assistance to existing units
                                 (upto and including Rs. 50 lakh)
 I         Applicant details
           1     Name of Unit
           2     Address for correspondence
           3     Constitution
           4     SSI Registration. No.
           5     Date of Incorporation
           6     Date of Commencement of Operations
           7     Activity / Industry
II Promoters/Directors
           Bio-data of all the             promoters/directors of the unit (Preferably make separate sheet for each
           promoter/director)
                                               Promoter/Director
       Name
       Full Address( incl Tel no./ mobile no)
       Age
       Passport No.
       Father's / husband's name
       Qualification
       Experience
       Functional responsibility in the unit
       Relationship with Chief Promoter
       Shareholding in the unit
       Net worth
Pl. furnish details of any other shareholder having more than 5% in the unit.
Sl. No.       Product          Installed capacity         Present capacity utilisation      End use of product       Export orientation
                                       p.a.
                                                                                                                          Yes/ No
                                                                   Page 1 of 7
                                                                                                                                              Application form for
                                                                                                                              Loans upto and including Rs. 50 lakh
Facilities enjoyed :
        Nature of facility                               Amount (Rs. lakh)                          Rate of       Nature of Security and value
          (bankwise)                                                                                interest
                                          Sanctioned              Outstanding as on ___ ___
Fund based
Basedkfjdffkldkfjdfkjdfkjdfkdjfkdjf
-Term Loan
-Working capital
Non Fund Based
                                                                      Page 2 of 7
                                                                                                                                       Application form for
                                                                                                                       Loans upto and including Rs. 50 lakh
            6          Taxes(CST)
            7          Contigency                                                                                                                  -
                                                                                                   TOTAL                                       27.68
* Details of Plant and machinery/ Misc. fixed assets at Annexure II and III
                Indicate details of expenditure already incurred, if any and how the expenditure was financed ?
6.3.            Means of Finance
                                                                                                                                      (Rs. Lakh)
    S. No. No.                                                   Details                                                 Total
        1             Additional share capital / Internal accruals                                                                              6.92
        2             Interest free Unsecured Loans                                                                                                -
        3             Term Loan proposed from SIDBI / Banks inclusive of subsidy ####                                                          20.76
                                                                   Total                                                                       27.68
# ### In terms of existing guidelines of Ministry of MSME , GoI the subsidy amount is received on implementation of the project
Say within 3 months therefore the amount of subsidy is included in the term laon amount as bridge loan and funded by the bank
On receipt of the subsidy from the GoI it is adjusted towards the loan amount.
#
6.4             Whether additional Working Capital required for the unit. If yes, amount and arrangements proposed may
                be indicated:
6.5 Technology
    S. No.                                               Item
       1          Any Technical collaboration? If yes, details
        2         Details of main technical professionals employed
        3         Any quality certification obtained ? If yes enclose certificate.
    1       Raw material
            (Details, arrangement,          sources      and
            distance)
    2       Power                                                Connected Load
Utilised load
                                                                      Page 3 of 7
                                                                                                                    Application form for
                                                                                                    Loans upto and including Rs. 50 lakh
6.9 Others
                                              Items
 Please indicate the various licenses / consents for the project / unit already obtained from the
 respective authorities
 Please indicate licenses / consents for the project / unit that are yet to be obtained.
 Category as per pollution control dept. If polluting, pollution control measures taken
 Whether the project is entitled for any govt. subsidy, tax exemptions. Details thereof
 Repayment period (in months) sought including repayment holiday requested, if any,
 Details of Collateral security offered and value (basis).
 List of guarantors for the proposed loan
            Enclose documents as indicated in the check list at Annexure V.
 6.10        Strengths / Weaknesses of the borrower (such as market standing, product/ service differentiation,
             technical expertise, infrastructure facilities etc.)
 Strengths
Weaknesses
                                                        DECLARATION
 I/We certify that all information furnished by me/ us above and in the appendix/ annexures/ statements and other
papers enclosed is true; I/we have no borrowing arrangements for the unit with any bank / FI except as indicated in
the application; that there are no overdues / statutory dues/government enquiry/proceedings/prosecution against
the unit/associate concerns/ promoters/directors except as indicated in the application; that no legal action has
been/ is being taken against the unit/associate concerns/promoters/directors; that I/ we shall furnish all other
information that may be required by SIDBI in connection with my/our application and I/ We have no objection to
your furnishing the information submitted by me/ us to any agency as you may deem fit in connection with
consideration of the assistance. We have no objection to SIDBI/ its representatives making suitable enquiries while
considering the application.
 Place :                                                            Signature
 Date                                                               Name & Designation
                                                           Page 4 of 7
                                                                                                                                         Application form for
                                                                                                                         Loans upto and including Rs. 50 lakh
                                                                                                                        Annexure I
                                              Details of Associate Concerns
    Name , Address & products      Existing       Name & Address of existing Banker        Facilities Enjoyed        Share holding of the
         manufactured               since                       (s)                                                  main promoter(s) of
                                                                                                                        applicant unit
Annexure II
  Name of                 Name of manufacturer,               Lead time        Invoice      Purpose /use           Basis of                  Remark
 machinery,                  contact person,                 for delivery     price (for     of machine           selection of                s reg.
  (model /                   e-mail address                       of        indigenous                             supplier                    after
specification)                telephone no.                   machinery     machinery) /                                                       sale
                                                                              CIF price                                                      service
                                                                                 (for                                                          etc.
                                                                             imported )
                                                                             (Rs. lakh)
Rapier            Laxmi shuttleless loom Pvt limited        3 Weeks         24.59          Weaving              Crediability
machines          21, Punmaji Industrial Estate,                                           of cloths            of the
                  Shahpur, Dhobighat,                                                                           Technolgy
                  Ahmedabad – 380004 Gujarat,                                                                   Provider
                  INDIA
                  Phone: 91 (79) 2562-2510 / 2562-
                  4393 / 2562-0604
                  Fax: 91 (79) 2562-2845
   Furnish competitive quotations, catalogues / invoice for each machinery proposed to be acquired
   In case of second hand /fabricated machinery, indicate the need / reasons for acquiring such machinery. Also enclose
Chartered Engineer's certificate regarding residual value and life in respect of second hand machinery.
                                                                                                                          Annexure III
                                  Details of Misc. Assets / equipment Proposed
                                                            Page 5 of 7
                                                                                                                                    Annexure IV
                                                     Profitability projections for the Unit/ Company as a whole*
  S.No.      Item                                               Actuals for     Y1          Y2      Y3      Y4      Y5      Y6        TOTAL
                                                                 previous
                                                                   year
    1        Total Income                                                        12.83      12.83   12.83   12.83   12.83   12.83         76.97
    2        Raw materials
             Power and fuel
             Wages and salaries
             Selling expenses
             Other expenses                                                       1.11       1.16    1.22    1.28    1.35    1.41          7.53
             Total Cost                                                           1.11       1.16    1.22    1.28    1.35    1.41          7.53
    3        Profit before depreciation, Interest and
                                                                                 11.72      11.67   11.61   11.55   11.48   11.42         69.44
             taxes (PBDIT) (2 - 1)
    4        Interest on Term Loan                                                1.88       1.81    1.47    1.04    0.55    0.07          6.83
    5        Interest on Working Capital
    6        Interest on unsecured loans
    7        Depreciation                                                         1.46       1.46    1.46    1.46    1.46    1.46          8.77
    8        Profit before Tax (3 - 4 - 5 - 6 - 7)                                8.38       8.39    8.67    9.04    9.47    9.88         53.84
    9        Tax                                                                  0.00       1.84    3.14    3.51    3.70    3.85         16.05
    10       Profit after Tax (8 - 9)                                             8.38       6.55    5.53    5.53    5.77    6.03         37.79
    11       Dividends/ Withdrawals
    12       Cash Accruals ( 10 - 11 + 7)                                         9.84       8.01    6.99    6.99    7.23    7.49         46.56
    13       Repayments of all term liabilities
                                                                                  1.20       3.30    4.00    4.60    5.10    2.56         20.76
             (Principal)
    14       Debt Service Coverage Ratio                                          3.81       1.92    1.55    1.42    1.38    2.87          2.77
             ((10+7+4)/(13+4))
    15       Average DSCR (Total of 10+7+4 for
             projected period/(Total of 13+4 for
             projected period)                                                                       2.77
* Please give projections for the entire tenure of SIDBI / Bank loan.
                                                                              Page 6 of 7
                                                                   Annexure V
                                                  CHECK LIST of documents to be
                                                submitted along with the application
*****
                                                                     Page 7 of 7
                Bureau of Energy Efficiency (BEE)
                (Ministry of Power, Government of India)
                4th Floor, Sewa Bhawan, R. K. Puram, New Delhi – 110066
                Ph.: +91 – 11 – 26179699 (5 Lines), Fax: +91 – 11 – 26178352
                Websites: www.bee-india.nic.in, www.energymanagertraining.com
Zenith Energy Services Pvt. Ltd                 India SME Technology Services Ltd
10-5-6/B, My Home Plaza, Masab                  DFC Building, Plot No.37-38,
Tank HYDERABAD, AP 500 028                      D-Block, Pankha Road,
Phone: 040 23376630, 31,                        Institutional Area, Janakpuri, New Delhi-110058
Fax No.040 23322517                             Tel: +91-11-28525534, Fax: +91-11-28525535
Website: www.zenithenergy.com                   Website: www.techsmall.com