CHECKLIST FOR TRANSFORMER ERECTION
REPORT NO & DATE : /ELE/003 Date:
PROJECT: CONTRACTOR:
TRANSFORMER TAG NO:
RATING PLATE DETAILS:
LAY OUT DRAWING NO:
TRANSFORMER DWG NO:
TEST DATE : AMB TEMP:
Sr No CHECK POINTS CONT RIBO CUST Observations
1 Manufacturer's Installation Manual is available for reference
2 Suitable capacity of Hydra / Crane used for the Erection
3 Slings used in Erection are approved by Safety officer
4 No Dent, Crack & Damage observed on Transformer during
Lifting, Handling & other Erection activities.
5 All the H/W for the Wheels / Rollers assembled & Tightened
as per the Torque requirement.
6 Transformer is placed on the Rail / Channel as per Lay out
dwg
7 Transformer wheels / Rollers are locked on both Sides after
fixing final location
8 Top Plate Level is checked by Water Level & Satisfactory
9 Testing of all transformer Earthing pit is complete &
satisfactory
10 All the Earthing Connections on the Body / Neutral of
transformer are connected by suitable h/w.
All Accessories like Radiators, Bushings, CT's, Bucholz Relay,
Conservator, Breather, OSR, MOLG, POLG, Fans, PRD, Rapid
11 Pressure Relay, Terminal Boxes, NGR, Level Gauges, Valves,
Pipes, Supports, Jumpers, Leads, H/w, and Gaskets etc. are
installed as per the drawing.
Cabling & Termination of Transformer accessories such as
12 fans, Relays, CT's, OTI / WTI, MOLG, NGR, Pumps, etc. are
pg. 1
complete as per the scheme & Loop checked.
13 Earthing of Radiators, Marshalling Boxes, Fans, Terminal
Boxes, NGR etc. are completed
14 Oil filling: Oil is filled to the Transformer through Filtration kit
and Time Vs. Temperature Vs. BDV is monitored.
15 Oil is filled as per the Levels specified in the drawing.
16 Positions of all valves are kept as per the Valve Schedule
Plate.
Air is released through all the Air Release Plugs of OLTC
17 Tank, Main Tank, Radiators, Conservator, Buchholz relay, etc.
as per the drawing for 2 -3 times in 24 hrs. after the Oil
Filling.
18 Breather is installed along with oil seal & Dry Silica gel.
19 Control cabling & loop check completed as per cable schedule
20 Power Cables, Bus ducts & Overhead lines (as applicable) are
connected as per the Drawing and checked for Tightness
Conclusion: The Transformer Erection is complete as per Manufacturer's Erection Manual and
cleared for Pre-commissioning Checks (Y /N):
Observations:
Contractor Ribo Customer
Name
Sign
Date
pg. 2