5.
Project Title: Multifunctional Satellite Project
Explanation Per Project
General Information 1. Title: Government Multifunctional Satellite
2. Project Value: IDR 7,16 trillion
3. Project Manager for Cooperation: -
4. Location: 149.400 public sites around Indonesia
5. Sector: Telecommunication
6. Status: Submission of Proposal Stage 1 (Administrative & Technical
Proposal) at 12th December 2018
Project Objective Over 149.400 public sites (schools, hospitals, state/local government,
defense & security administration) around Indonesia are lack of
connectivity, satellite system is the only feasible access technology to cost-
effectively remote locations
Address
Relevant image / visual
display
Assignment Minister of Recourse Agreement
Communication
PPP
BAKTI PPP Agreement IIGF
Scope
AP Payment and
other financial
Obligation
Special Purpose
Company* Guarantee Agreement
Service
Appointment
Service Partner
Service
Service Payment (if any)
User
(such as Government Institutions)
*Special Purpose Company (SPC)
established by the winning bidder
Advisors appointed 1. Institution Involved:
- Direktorat Jenderal Pengelolaan Pembiayaan dan Risiko (“DJPPR”)
- PT Penjaminan Infrastruktur Indonesia (Persero) (“PII”)/ Indonesia
Infrastructure Guarantee Fund (“IIGF”).
2. Consultants:
- Transaction Consultant: PT Sarana Multi Infrastruktur (Persero)
- Financial Consultant: PT Deloitte Consulting Indonesia
- Technical Consultant: PT Tritech Consult Indonesia, ArgoSat
Consulting, LLC.
- Legal Consultant: ANG Law Firm, Jones Day Law Firm
About project Over 149.400 public sites (schools, hospitals, state/local government,
defense & security administration) around Indonesia are lack of
connectivity, satellite system is the only feasible access technology to
cost-effectively remote locations
Address
Return Scheme using Availability Payment (“AP”), paid in flat payment
over the concession period (15 years)
1. Project Scope:
Blue = Responsibilies of SPC (Bidder)
Red = Responsibilies of Service Partner
(outside of this contract)
Note: System must be able to support multiple hub technologies within the
same Gateway
No Scope of Works SPC GCA
1 Financing of the Project √
2 Securing the satellite orbit √ Support
3 Acquiring the gateway location √ Support
4 Acquiring the earth station location √ Support
5 Manufacturing the satellite √
6 Construction and Operation of gateway √
and Satellite Control Center
7 Launching the satellite √
8 Obtaining insurances for the Project √
9 Operation and maintenance of the √
satellite, gateway and earth station
10 Construction and Operation of IP √
Processing Hub, Network Operations
Center (NOC), Network Management
System (NMS)
11 Monitoring and evaluation of the Project √
12 AP Payment √
2. Indicative Return Scheme: Availability Payment (“AP”) paid in flat
payment over the concession period.
3. Expected Construction Time: 2019 – 2022 (3 years)
4. Indicative Concession Period: 15 years
Government Support -
Potential (if any)
Prequalification 1. PQ Announcement / Indication of the start of the auction process:
24th July 2018
2. Who submit the bidding document:
- Konsorsium BAKTI UNTUK NEGERI
- Konsorsium Indosat – Lintasarta – JSAT – Teleglobal
- Konsorsium Satelit Nasional
- Viasat, Inc
- Eutelsat S. A.
- Konsorsium PT Satelit Multimedia Indonesia dan APT Satellite
Company Limited
- Konsorsium PSN
- PT Kacific Indonesia Corpora
- Konsorsium Dharma Bakti
3. Who passed the PQ:
- Konsorsium BAKTI UNTUK NEGERI
- Konsorsium Indosat – Lintasarta – JSAT – Teleglobal
- Viasat, Inc
- Eutelsat S. A.
- Konsorsium PT Satelit Multimedia Indonesia dan APT Satellite
Company Limited
- Konsorsium PSN
- Konsorsium Dharma Bakti
Request for Proposal 1. Who Place the Offer: could not specified yet
2. Auction Winner: not specified yet, January 2019 (expected)
Public Private February 2019 (expected)
Partnership (PPP)
Agreement
Financing Agreement August 2019 (expected)
Construction 2019 – 2022
Operation 2022