PORTABATCH CORP.
San Isidro, Bunawan, Davao City
ESTIMATEC COST FOR PROCESSING OF THREE (3) BLDG. PERMITS
DRAWING PLAN (30 SHEETS) P 30,000.00
PRIVATE ENGINEER
CIVIL 10,000.00
ELECTRICAL 10,000.00
PLUMBER 6 ,000.00
MECHANICAL 6,000.00
ELECTRONIC 8,000.00
DOLE 10,000.00
STRUCTURAL ANALYSIS (civil engineer) (P20.00/sqm) ,
BILL OF MATERIALS and SPECIFICATIONS
BLDG. 1 ( 900 sqm) 18,000.00
BLDG. 2 (1800 sqm) 36,000.00
SKECTH PLAN (2 title) 1,400.00
ZONING FEE (bill of materials)
BLDG. 1 3,900.00 (w/ OR)
BLDG. 2 4,900.00 (w/ OR)
BLDG. 3 3,100.00 (w/ OR)
PROCESSING FEE 25,000.00
Total ------------ P172,300.00
PESOS : ONE HUNDRED SEVENTY-TWO THOUSAND THREE HUNDRED only
n.b. above estimate cost does not include gov’t fees of the ff:
Office of the City Engineer (OBO) --- application and penalty
ESTIMATE ---- gov’t fees plus 100% …… 10,000 – existing structure ……. 8,000.00 – occupancy penalty gov’t fees
plus 100%
ZONING ------------------------- penalty ( P500.00/day since start of construction…for nego)
Submitted by:
Ma. Theresa Solideo