User Instructions: Installation Operation Maintenance
User Instructions: Installation Operation Maintenance
Page 2 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 3 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 4 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
run-up process (See section 5 Commissioning, condition these are extremely dangerous and skin
startup, operation and shutdown). contact must be avoided.
NEVER RUN THE PUMP DRY GUARDS MUST NOT BE REMOVED WHILE
PUMP IS OPERATIONAL
INLET VALVES TO BE FULLY
OPEN WHEN PUMP IS RUNNING THERMAL SHOCK
Running the pump at zero flow or below the Rapid changes in the temperature of the liquid within
recommended minimum flow continuously will cause the pump can cause thermal shock, which can result
damage to the seal. in damage or breakage of components and should be
avoided.
DO NOT RUN THE PUMP AT
ABNORMALLY HIGH OR LOW FLOW RATES NEVER APPLY HEAT TO REMOVE
Operating at a flow rate higher than normal or at a IMPELLER
flow rate with no back pressure on the pump may Trapped lubricant or vapour could cause an
overload the motor and cause cavitation. Low flow explosion.
rates may cause a reduction in pump/bearing life,
overheating of the pump, instability and HOT AND COLD PARTS
cavitation/vibration. If hot or freezing components or auxiliary heating
supplies can present a danger to operators, they
When ambient temperatures are must be shielded to avoid accidental contact. If
likely to drop below freezing point, the pump and any complete protection is not possible, the machine
cooling and flushing arrangements must be drained access must be limited to maintenance staff only.
or otherwise protected. Note: bearing housings must not be insulated and
drive motors and bearings may be hot.
HANDLING COMPONENTS If the temperature is greater than 68 °C (155 °F) or
Many precision parts have sharp corners and the below 5 °C (41 °F) in a restricted zone, or exceeds
wearing of appropriate safety gloves and equipment local regulations, action as above shall be taken.
is required when handling these components. To lift
heavy pieces above 25 kg (55 lbs) use a crane 1.6.4 Products used in potentially explosive
corresponding to the mass and in accordance with atmospheres
current local regulations.
Measures are required to:
• Avoid excess temperature
NEVER DO MAINTENANCE WORK WHILST THE • Prevent build up of explosive mixtures
UNIT IS CONNECTED TO POWER • Prevent the generation of sparks
• Prevent leakages
HAZARDOUS LIQUIDS • Maintain the pump to avoid hazard
When the pump is handling hazardous liquids care
must be taken to avoid exposure to the liquid by The following instructions for pumps and pump units
appropriate sitting of the pump, limiting personnel when installed in potentially explosive atmospheres
access and by operator training. If the liquid is must be followed to help ensure explosion protection.
flammable and/or explosive strict safety procedures Both electrical and non-electrical equipment must
must be applied. meet the requirements of European Directive
Gland Packing must not be used when pumping 94/9/EC.
hazardous liquids.
1.6.4.1 Scope of compliance
Page 5 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
An example of ATEX equipment marking is shown The temperature rise at the seals and bearings and
below. The actual classification of the pump will be due to the minimum permitted flow rate is taken into
engraved on the nameplate. account in the temperatures stated.
Page 6 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
To avoid potential hazards from fugitive emissions of To avoid potential explosion hazards during
vapour or gas to atmosphere the surrounding area maintenance, the tools, cleaning and painting
must be well ventilated. materials used must not give rise to sparking or
adversely affect the ambient conditions. Where there
1.6.4.5 Preventing sparks is a risk from such tools or materials, maintenance
must be conducted in a safe area.
It is recommended that a maintenance plan and
To prevent a potential hazard from mechanical
schedule is adopted (see section 6, Maintenance).to
contact the coupling guard must be non-sparking and
include the following.
anti-static.
a) Any auxiliary systems installed must be
To avoid the potential hazard from random induced
monitored, if necessary, to ensure they function
current generating a spark the earth contact on the
correctly.
baseplate must be used.
b) Gland packings must be adjusted correctly to
give visible leakage and concentric alignment of
Avoid electrostatic charge: do not rub non- the gland follower to prevent excessive
metallic surfaces with a dry cloth; ensure cloth is temperature of the packing or follower.
damp. c) Check for any leaks from gaskets and seals. The
correct functioning of the shaft seal must be
The coupling must be selected to comply with checked regularly
94/9/EC and correct alignment must be maintained. d) Check bearing lubricant level, and if the hours run
show a lubricant change is required.
1.6.4.5 Preventing leakage e) Check that the duty condition is in the safe
operating range for the pump.
f) Check vibration, noise level and surface
The pump must only be used to handle liquids temperature at the bearings to confirm
for which it has been approved to have the correct satisfactory operation.
corrosion resistance. g) Check dirt and dust is removed from areas
around close clearances, bearing housings and
Avoid entrapment of liquid in the pump and motors.
associated piping due to closing of suction and h) Check coupling alignment and re-align if
discharge valves, which could cause dangerous necessary.
excessive pressures to occur if there is heat input to
the liquid. This can occur if the pump is stationary or
running.
Page 7 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 8 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 9 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Sound pressure readings are for information only and are not subject to guarantee by Flowserve/IDP.
Decibel readings do not include driver or system noise.
Pump tested at 100% of the best efficiency point at max.impeller diameter with water.
dB correction for combining noises (pump+motor)
Difference between two
0 1 2 4 6 9 10
levels to be combined, dB
Add to the higher level to obtain 3 2.5 2 1.5 1 0.5 0
the combined noise level,dB
Note :
1) The values showed are measured at a distance of 1 mt. (horizontally) from major pump
surfaces and 1.5 mt. above the floor.
2) The values shown are expressed in dB (A)
3) For Noise Test Procedure refer to Works Standard L-109
4) The values shown have been derived from actual noise-test data and are based on the following conditions:
- Equipment is located in a free field above a reflecting plane in which the reductionin noise level
in all directions is 6db in each octave band for each doubling of distance.
- Background noise is 10dB minimum below all noise levels in each octave band.
- The values shown are at a distance of 1 meter (horizontally) from the major pump surface and
1,5 meters above the floor, using a standard pressure reference of 0,00002 newton per square meter.
- Overall noise level, dB(A) is determined at points of maximum noise level and the values of all
mid-band frequences are basis A scale readings.
When the required condition flow is outside the range of 75 to 125% BEP, a part load correction (PLC) must be
added to the noise level as follows:
Percent of BEP @
PLC in
required impeller
dB
diameter
74 to 62 or 126 to 136 +1
61 to 50 or 137 to 150 +2
49 to 38 +3
37 to 25 +4
Page 10 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
1.10 CE Declaration
Page 11 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
2.2 Handling Distance sleeves are only used for fixing the
base plate during transportation.
Boxes, crates, pallets or cartons may be unloaded
using fork lift vehicles or slings dependent on their
size and construction.
2.3 Lifting
A crane must be
used for all pump sets in
excess of 25 kg (55 lb).
Fully trained personnel
must carry out lifting, in
accordance with local
regulations. The driver and
pump weights are recorded
Page 12 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
3.0 DESCRIPTION
3.1 Configuration
The model WUC covers the highly engineered
specialty end of the Flowserve family of double
2.3.1 Lifting for preparation of insulation casing vertical turbine pumps. The pump line is
If the application is configured for cold applications based on a modular system, thus providing maximum
greater than -20°C, an insulation shall be provided on design and operating flexibility. This is combined with
the suction can. specific design features, including stiff shaft
The installation has to be performed in vertical lifted construction, a self-contained axial thrust bearing
position to ensure that no damage can occur during housing and pressure containing parts certified to
transportation. various international standards. Altogether, this
For detailed information refer to job related general makes the WUC the pump of choice for the most
arrangement drawing, page 2 (G215xxxMZ-00-A1). critical applications where space considerations or
marginal NPSHA values preclude the use of a
2.4 Storage horizontal multistage pump.
Liquid is flowing through the suction flange of the
If the pump will not be put immediately into service, it headstock and through the Can to the impellers. The
should be stored in a dry room. To avoid any damage last stage impeller is discharging the liquid via the
during the storage period, the influence of any low or column pipes, to the discharge flange. The thrust is
high frequency vibration must be totally inhibited. If balanced by back wearing rings and balancing holes.
the pump is delivered sealed in a plastic-wrapper, it is
Page 13 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
The headstock is equipped with a drain connection, are designed with 7 to 11 vanes to minimize the
which allows to flush the Can with Nitrogen before radial forces at part load operation. All impellers are
disassembly. slipped on the shaft and axially fixed by the impeller
A vent connection for the suction is standard. nut. The shaft is supported in the suction casing, in
every diffuser and in the discharge casing.
The sense of rotation of the pump is counter Optional the hydraulics can be fitted with an inducer
clockwise (CCW), looking from the coupling to the for low NPSH requirement.
shaft end of the pump.
3.3.4.2 Mixed flow hydraulics
3.2 Nomenclature The hydraulics consists of flanged bowls and a
suction casing. The impellers are hydraulically
Example: balanced by back wear rings and balancing holes.
The diffusers are designed with 7 to 11 vanes to
200WUC-2M-5+I minimize the radial forces at part load operation. All
impellers are slipped on the shaft and axially fixed by
200 Flow at BEP the impeller nut. The shaft is supported in the suction
casing and in each bowl.
WUC Pump type - Can Optional the hydraulics can be fitted with an inducer
WUJ = without Can for low NPSH requirement.
2 indicates speed 2–poles
3.3.4.3 10WUC-2H
4 = 4-poles
The hydraulic consists of bowls, which are pushed
M indicates hydraulic Medium Head together and hold by strong tie bolts. The impellers
L = Low Head are secured to the shaft by split rings. Due to the
H = High Head small size, the impellers are only equipped with front
R = Radial Flow wear rings and therefore unbalanced.
5 Number of stages
Optional the hydraulics can be fitted with an inducer
I indicates Inducer as option for low NPSH requirement.
D Dummy stage as option
DS double suction 3.3.4.4 20WUC-2L, 45WUC-2L, 80WUC-2L
P high pressure The hydraulics consists of flanged bowls and a
suction casing. The impellers are secured to the shaft
3.3 Design of major parts by split rings. Due to the small size, the impellers are
only equipped with front wear rings and therefore
unbalanced.
3.3.1 Motor stool
The motor stool supports the thrust bearing. On top Optional the hydraulics can be fitted with an inducer
the driver is mounted. for low NPSH requirement.
Page 14 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
4.3 Foundation
The foundation shall be located on a place that
allows a minimum of pipe work and that is easily
accessible for inspection during operation. According
to the environment the foundation may consist of
concrete or of steel. It must be rigid and heavy
enough to absorb normal vibrations and shocks. The
flange of the Can must be supported on the whole
surface. It should be at least 20 – 30 mm
(0.8 – 1.2 in) higher than the surrounding to avoid the
deposit of dust and humidity.
4.3.2 Steel foundation 4.3.4 Final assembly for not complete assembled
pumps
When the pump unit is mounted directly on structural
steel frame, it shall be well supported by constructural Pumps exceeding a total length of approximately 6 m
beams. It is recommended to check the natural (19.7 ft) are delivered in various components and
frequency of the steel frame, because it shall not must be assembled on site. The main parts are:
coincide with the pump speed. The flange of the Can hydraulic bowls section - various line shafts and
has to be fixed on a flat surface with studs or hex column pipes - headstock and thrust bearing.
screws, the exact horizontal alignment is very To install the pump in the Can, clamps for the column
important! pipes are delivered with the pump.
4.3.3 Concrete foundation 1) Mount the first rising main column pipe [1350.3]
and line shaft to the already assembled hydraulic
A concrete foundation must have an exact horizontal section.
alignment and must be placed on solid ground. First
a basic foundation shall be built with square shaped
holes for embedding the foundation bolts. After 1350.3
Page 15 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
second clamp
clamp
Page 16 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
6591
Page 17 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
4.4 Initial alignment a) Parallel Offset: The median lines run parallel. The
The adjustment of motor and pump must be checked maximum allowable parallel offset depends on
(if necessary, make a new adjustment) before first the size of coupling and is indicated in the
start up of the unit. instruction manual of manufacturer of coupling
The motor flange is equipped with adjustment-screws b) Axially Offset: Another offset is the displacement
on the motorstand. (Values for adjustment are of one or both of the shafts. A typical example is
specified in the coupling instruction manual). thermal expansion.
Page 18 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
4.5.1 General
Protective covers are fitted to the pipe connections to
prevent foreign particles entering during
transportation and installation. Ensure that these
covers are removed from the pump before
connecting any pipes.
Maximum forces and moments allowed on the pump
flanges vary with the pump size and type. To
minimize these forces and moments which may
cause misalignment, hot bearings, worn couplings,
vibration and a possible failure of the pump, the
following points shall be strictly followed:
4.5.3 Vent
The extent of venting requirements depends on the
application and installation requirements.The
following instructions may be used as a guide insofar
as they apply to the pump as delivered. For type,
position and dimensions of the vent connections
please see GA drawing.
Page 19 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
design
Do not mix up connections. After N1 Suction nozzle
laying the pipes (and also after repairs), check the N2 Discharge nozzle
pipe runs.
N3 Connection for venting of can
4.5.3.1 General recommendation N5 Connection for venting of M.S
Vent valves are generally installed at one or more
high points of the pump casing waterways. They are M.S Mechanical seal
used to facilitate priming of the pump and to prevent F Flushing API Plan 13
trapping of air or vapor in the casing during operation.
Pumps handling flammable, toxic, or corrosive fluids
require vent piping connected in such a way that the
safety of operating personnel and the installation is
ensured (i.e. to the suction tank). The suction vents
of pumps taking liquids from a closed vessel must be
piped to the gas phase of the suction tank.
Fig. 2
Standard Description
Page 20 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Table 1.
Fig. 3
To ensure positive venting, all vent lines must
be connected to the gas phase of the suction tank.
4.5.4 Recommended venting for flashing liquid
Flashing liquids are medium that vaporize at
atmospheric pressure and ambient temperature.
Gases can be liquefied by pressurization and/or
cooling.
Page 21 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Fig.4
Shall the vent line of the CAN (N3) be led to the flare instead of the suction tank, a restricted orifice
shall be installed in this line in order to reduce the volumetric losses.
Page 22 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Fig.5
Page 23 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 24 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
c) During filling the pump shall reach the specified 2000 service hours or at least every 6 month.
temperature, so pumps for hot liquids (T > 100 °C
(212 °F)) shall be warmed up by preflushing with a 5.2.3 Oil level
rate of 50 °C (78 °F) per hour. Unless otherwise The correct oil level is in the middle of the oil sight glass
specified the external temperature of the pump and shall be checked when pump is not in operation.
must be within 30 °C (54 °F) of the temperature Periodically check if the lubricating oil is mixed with any
of the liquid to be pumped at that time.Cryogenic condensed water. Careful opening of the oil drain
pumps must be cooled down. The lower part of the during a stop of the pump will show any water.
seal gland, the gascofferdam and the headstock
must be completely coated with ice. The ice has
good isolating properties and limits the heat input During operation the level will decrease
from the ambient. due to circulation of the oil through the bearings.
d) Check the sense of rotation of the pump (Coupling
spacer dismantled). A too high oil level will result in higher bearing
Sense of rotation is counter clockwise viewed to temperatures and therefore poorer lubrication.
the drive end of the pump.
e) The pump rotor and the shaft seal must be in 5.2.4 Oil quality
correct axial position. Mounting plates of Oil used for lubrication should only be of high quality.
mechanical seal must be locked at the seal gland The viscosity of the oil at working temperature must
in open position. Drive-collar of the mechanical be at least 10 cSt. The pouring point of the oil must
seal sleeve must be tightened. be in accordance with the lowest expected
f) Check the readiness of all auxiliary systems (seal temperature of the bearing housing during a stop of
sys., lubrication sys.,...) for start up. the pump. For recommended lubricating oils refer to
g) All pipe work, including the internal and the the lubrication table.
auxiliary pipe work, must be connected correctly Having selected the corresponding oil quality the
and must be absolutely tight. Check the tightness actual oil temperature at the bearing housing must be
of all connections of the auxiliary pipe work. The checked after two service hours of the pump.
suction valve must be open, the discharge valve Considering this measured oil temperature the actual
shall be closed. viscosity must be determined by using the data sheet
h) Turn the pump by hand, if required with the help of of the oil, to verify the minimum required viscosity of
a lever, to check the free rotation of the rotor. The 10 cSt. Do not forget, the oil temperature in the
rotor must turn uniformly and noiselessly. Some bearing itself is about 10 °C (Δ 18 °F) higher than the
resistance may be felt due to friction in bearings oil temperature at the bearing housing. On the
and seals. following table the oil viscosity is given at 40 °C (104
i) Check the readiness of the driver for start up. Refer °F). Determining the correct lubricating oil one must
to the manual of the driver (preheating for take into consideration that all bearings will have
explosion proof E-motor). higher temperatures during the first 20 service hours.
In constant operation the bearing temperature will
5.2 Pump Lubricants decrease about 10 °C (50 °F). The oil temperature
shall be lower than 85 °C (185 °F) after this running-
5.2.1 Lubrication in time. The bearing outer race temperature should
not exceed 95°C (203°F). If the temperature is
The bearing housing shall be filled with proper
higher, the reason may be a wrong oil quality, wrong
lubricating oil prior to start up. If the pump will be
oil level or overload of the pump because of
started after a longer storage period, the bearing
excessive wear.
housing should be first flushed and cleaned with
If the humidity at the site is high, the roller bearings
gasoline. It is not necessary to remove the
become easily rusty during stand still periods. To
preservation oil as this will mix up thoroughly with the
avoid that, we recommend to mix the lubricating oil
lubrication oil.
with a corrosion inhibitor contact your lubrication oil
Lubrication is provided by the pumping effect of the
supplier for proper additives inhibitors.
rotating ball bearings. Maintaining the correct oil level
(middle of the oil sight glass) ensures that the lower
ball bearing is covered with oil. 5.2.5 Oil quantity
For recommended lubricating oils refer to the Bearing size is shown on the nameplate of the pump,
lubrication table 5.2.6 and with this the correct thrust bearing frame can be
selected according to the following table.
5.2.2 Oil change
After first start up, the oil shall be changed after 200 Thrust bearing No. Oil quantity l (Fl.oz.) Bearing size
service hours. 0N 0.5 (16.9) 7210 BECBJ (M)
Every further oil change shall take place after about 1N 1.5 (50.7) 7313 BECBJ (M)
Page 25 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 26 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
OMV OMV turb HTU 32** OMV turb HTU 46** OMV turb HTU 68 -
* Note that it normally takes 2 hours for bearing temperature stabilize and the final temperature will depend on the ambient, r/min, pumpage temperature and pump size.
Viscosity index shall be at least 95.
** For ambient temperature from -12°C (10 °F) upwards
For temperatures below -5 °C (-23 °F) use lubrication oil class SAE 5W-50 or API-SJ.
The sequence of the suppliers of the lubricants does not represent any indication of their superiority.
¹ Viscosity at 40 °C (104 °F) in cSt [mm²/s] DIN 51562
Page 27 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
5.2.7 Hydrodynamic thrust bearing lubrication 5.2.10.1 Adjusting of TRICO Constant Level
If the pump is equipped with a hydrodynamic thrust Oiler
bearing refer to bearing manufacturer’s IOM for all If the pump is fitted with a Constant Level Oiler type
data related to the thrust bearing lubrication. „TRICO“, the correct oil level has to be checked after
fitting the pump!
5.2.8 Lubrication
The bearing housing shall be filled with proper
lubricating oil prior to start up. If the pump will be
started after a longer storage period, the bearing
housing should be first flushed and cleaned with
gasoline. It is not necessary to remove the
preservation oil as this will mix up thoroughly with the
lubrication oil.
Lubrication is provided by the pumping effect of the
rotating ball bearings. Maintaining the correct oil level
(middle of the oil sight glass) ensures that the lower
ball bearing is covered with oil.
For recommended lubricating oils refer to the
lubrication table 5.2.6
Page 28 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 29 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Bearing Reclassifier at
Frame Manifold
0N 1 x 0.18 SCFM
1N 1 x 0.30 SCFM
3N 2 x 0.30 SCFM
4N 2 x 0.30 SCFM
5N 2 x 0.30 SCFM
6N 2 x 0.30 SCFM
7N 2 x 0.45 SCFM
8N 2 x 0.30 SCFM
Page 30 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
5.2.16 Lubrication
The bearing housing shall be filled with proper The pressure in the bearing housing shall be 0,05
lubricating oil prior to start up. If the pump will be bar (0,74 psi) (20 inches of water column). A
started after a longer storage period, the bearing continuous oil mist lubrication should be occur
housing should be first flushed and cleaned with during operation and stand by.
gasoline. It is not necessary to remove the
preservation oil as this will mix up thoroughly with the
lubrication oil. After start up the bearing temperature
Lubrication is provided by the pumping effect of the must be observed carefully. The temperature at the
rotating ball bearings. Maintaining the correct oil level bearing housing should not exceed 85°C.
(middle of the oil sight glass) ensures that the lower
ball bearing is covered with oil.
For recommended lubricating oils refer to the Refer to the GA-drawing regarding the
lubrication table 5.2.7. connections to the supply systems.
Page 31 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
c) Open screws from the clamping unit, located on 5.3.2 Adjusting of the rotor for pump type
the end of the shaft sleeve (refer to shaft seal 10 WUC-2H, 20, 45 & 80 WUC – 2L
drawing).
d) Loose and remove socket head cap screws a) Remove coupling spacer, coupling hub on pump
[6579.1] from the shaft nut [2910]. shaft and fan [8161] (when delivered).
e) Turn shaft nut upside till the rotor moves in the
lowest position and cannot turned by hand.
f) Measure the dimension from the shaft nut to the Use an anaerobic adhesive for
end of the shaft. securing the socket set screw for reassembly.
g) Now lift the rotor by turning the shaft nut in the b) Fix the position of the mechanical seal by putting
other direction till it is in the highest position. the assembly jigs, mounted on the seal end plate,
into the groove in the shaft sleeve.
c) Open screws from the clamping unit, located on
For heavy pumps the end of the shaft sleeve (refer to shaft seal
(rotor weight > 150 kg (331 lb.)) we recommend drawing).
the following practice. The rotor is already in its d) Loose and remove socket head cap screws
lowest position. Screw in an Eyebolt into the [6579.1] from the shaft nut [2910].
thread at the top of the shaft. Use a lever or a e) Turn shaft nut upside till the rotor moves in the
crane to lift the shaft (do it slowly, the axial lowest position and cannot turned by hand.
clearance is only a few millimeters). f) Now lift the rotor by turning the shaft nut in the
h) Measure again the dimension from the shaft nut other direction till it is in the highest position.
to the end of the shaft.
i) Take the mean value of the two dimensions and
adjust the rotor to this value by turning the shaft For heavy pumps
nut. (rotor weight > 150 kg (331 lb.)) we recommend
j) Fix the shaft nut with the socket head cap the following practice. The rotor is already in its
screws. lowest position. Screw in an Eyebolt into the
k) Fix the shaft sleeve with the clamping unit and thread at the top of the shaft. Use a lever or a
turn the assembling jigs out of the groove from crane to lift the shaft (do it slowly, the axial
the shaft sleeve and fix them on the seal end clearance is only a few millimeters).
plate. g) Turn the shaft nut 180° in opposite direction to
l) Check if the shaft can be turned easy by hand slip down the shaft 1mm (0.04 in) from its highest
m) Mount fan (when delivered) coupling hub and position.
spacer again. h) Fix the shaft nut with the socket head cap
screws.
i) Fix the shaft sleeve with the clamping unit and
If the pump is fitted with a rigid turn the assembling jigs out of the groove from
spacer type coupling ensure that the coupling is the shaft sleeve and fix them on the seal end
completely assembled and all screws are fixed. plate.
j) Check if the shaft can be turned easy by hand
k) Mount fan (when delivered) coupling hub and
For pumps with a setting length spacer again.
above 5 m (16.4 ft) (distance between centerline
discharge and pump suction) all the tolerances of the 5.4 Direction of rotation
line shafts must be considered.
Therefore put rotor to its lowest position. Then lift
rotor to its highest position. Now lower the rotor 3 mm The sense of rotation of the
(0.12 in.) to its final axial position. pump is counter clockwise (CCW); looking from the
3 mm (0.12 in.) axial setting applies also for rigid coupling to the shaft end of the pump.
spacer type couplings.
The rotation of the driver shall be checked.
If the pump is delivered disassembled or
if the fluid temperature is below -100°C (-148°F) or 5.5 Guarding
above 150 °C (302°F), adjusting of the rotor is Be sure that the coupling guards are mounted
necessary prior to the first start up. Rotor adjusting is correctly at the thrust motor stool prior to start up.
necessary after each pump maintenance.
5.6 Priming and auxiliary supplies
The pump must be completely primed prior to start up
by using the vent connections as shown in the
general arrangement drawing.
Page 32 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 33 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
5N 7318 BECBJ (M) 10 m³/h (44 gpm) d) Check the mechanical seal against any leakage.
6N 7322 BECBM 11 m³/h (48.4 gpm)
Right after start up a minor leakage
7N 7326 BCBM 12 m³/h (52.8 gpm)
of the mechanical seal is quite normal. Normally
8N 7232 / 7330 BCBM 12 m³/h (52.8 gpm) this leakage disappears after few minutes of
operation.
These flow rates shall be used for the piping design.
5.9 Operation
If the pump is equipped with a) Verify that the pump is operating within the
hydrodynamic thrust bearing expected balance flow specified limits, min/max flow, pressure,
rate is 12m³/h (52.8 gpm). temperature, vibration, power
b) The bearing housing temperature shall not exceed
Design and manufacturing of the balance 80 °C (176 °F). If higher bearing temperature are
line is not within the responsibility of FPD. observed, check the viscosity grade of the used
lubrication oil.
5.8 Starting the pump
a) Start the driver according to the specification. If the pump is equipped with
(Refer to driver IOM) hydrodynamic thrust bearing refer to bearing
manufacturer´s IOM and to recommendation for
maximum bearing temperature.
Pumps are usually started against
closed discharge valve
b) Check the discharge and suction pressure gauge The minimum viscosity is
to verify the pumps delivered head. Open the 10 cSt at the expected oil temperature.
discharge valve slowly, until the pump reaches the (Oil temperature = bearing gland temperature
specified operation point. The pump must operate + 10 °C (50 °F))
smoothly, and the vibration must be below 5 mm/s c) From time to time check the pump shaft seal.
(0.2 in./sec) (API 610 vibration limits). Leakage of 5ml/hour is also with a mechanical
shaft seal unavoidable.
d) Check the correct venting of the Can and the
The discharge valve must be opened headstock by opening the valve in the vent line for
within 30 sec. after start up. Longer operation short time. When the condition of service is near
against closed discharge valve will damage the the boiling point, a permanent vent line with a 3
pump. If a minimum flow valve is installed, take mm ( 0.12 in.) orifice (to inhibit the exit of too much
pressure gauge readings to verify the correct liquid) must be installed back to the suction tank.
operation. This will ensure that any suction and NPSH
problems can be avoided during normal service.
If the backpressure of the discharge e) Observe the power consumption of the pump to
pipe is sufficient, pumps can be started against detect excessive wear.
open valve.
5.10 Stopping and Shutdown
Ensure that your driver is capable deliver a) Close the outlet valve, but ensure that the pump
the higher torque required by starting against runs in this condition for no more than a few
open valve. seconds.
b) Stop the pump.
To prevent the pump from reverse rotation c) Switch off flushing and/or cooling/ heating liquid
after shut down, the installation of a check valve supplies at a time appropriate to the process.
is recommended. d) For prolonged shutdowns and especially when
Although the pump is not affected by reverse ambient temperatures are likely to drop below
rotation because of special coupling design , it can freezing point, the pump and any cooling and
be an issue with the driver. flushing arrangements must be drained or
Check the discharge and suction pressure gauge otherwise protected.
to verify the pumps delivered head.
The pump must operate smoothly, and the For automatic start/stop operation of the
vibration must be below 5 mm/s (0.2 in./sec) (API pump, ensure that all steps described in chapter 5.6,
610 vibration limits). 5.7, 5.8 and 5.9 are implemented in the control logic.
If a minimum flow valve is installed, take pressure
gauge readings to verify the correct operation. 5.11 Hydraulic, mechanical and electrical
c) Check the pipe system against any leakage. duty
Page 34 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 35 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Never clean equipment with inflammable solvents or hours since last recharge of grease or complete
carbon tetrachloride. Protect yourself against toxic grease change.
fumes when using cleaning agents. e) Check any auxiliary supplies eg. heating/cooling
(if fitted) are operating correctly.
6.2 Maintenance schedule f) Refer to the manuals of any associated
equipment if routine checks needed.
6.2.1 Routine Inspection (daily/weekly) If you need the wear rings oversized or undersized,
please indicate, otherwise the wear rings will be
delivered with standard size.
The following checks should be
made and the appropriate action taken to remedy any
To ensure continuous satisfactory operation,
deviations.
replacement parts to the original design specification
a) Check operating behavior; ensure noise,
should be obtained from Flowserve.
vibration and bearing temperatures are normal.
Any change to the original design specification
b) Check that there are no abnormal fluid or
(modification or use of a non-standard parts) will
lubricant leaks (static and dynamic seals) and
invalidate the pump’s safety certification.
that any sealant systems (if fitted) are full and
operating normally.
c) Check that shaft seal leaks are within acceptable 6.3.2 Storage of spares
limits. Spares should be stored in a clean dry area away from
d) Check the level and condition of lubrication oil. vibration. Inspection and retreatment of metallic
On grease lubricated pumps, check running
Page 36 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 37 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
M27 1193 (880) 1050 (774) 284 (209) 379 (280) 1496 (1103)
M30 1614 (1190) 1420 (1047) 386 (285) 515 (380) 2033 (1500)
M33 2191 (1616) 1928 (1422) 523 (386) 697 (514) 2747 (2026)
M36 2820 (2080) 2482 (1831) 672 (496) 897 (662) 3535 (2607)
M39 3645 (2689) 3208 (2366) 870 (642) 1160 (856) 4569 (3370)
M42 3920 (2891) 3980 (2936) 1146 (845) 1447 (1067) 5670 (4182)
M45 4875 (3596) 4950 (3651) 1425 (1051) 1800 (1328) 7050 (5200)
M48 5899 (4351) 5990 (4418) 1724 (1272) 2178 (1606) 8530 (6292)
M64 14083 (10388) 14300 (10548) 4117 (3037) 5201 (3836) 20370 (15025)
M68 16998 (12538) 17260 (12731) 4969 (3665) 6277 (4630) 24580 (18130)
M76 25230 (18610) 8270 (6100)
A193 B8/B8M,
Size of S32760, S31803,
A193 B8M Cl2 A4-70, A2-70 A193 B8MA (NACE) N08825
Screw 1.4462
A2-50, A4-50
[Nm] [lbf.ft] [Nm] [lbf.ft] [Nm] [lbf.ft] [Nm] [lbf.ft] [Nm] [lbf.ft]
M4 2.1 (1.5) 3.2 (2.4) 1.9 (1.4) 0.9 (0.7) 1.1 (0.8)
M5 4.1 (3) 6.4 (4.7) 3.6 (2.7) 1.6 (1.2) 2.2 (1.6)
M6 7.1 (5.2) 10.9 (8) 6.3 (4.6) 2.9 (2.1) 3.7 (2.7)
M8 17 (12.5) 27 (19.9) 15 (11.2) 7.1 (5.2) 9.1 (6.7)
M10 34 (25) 52 (38) 30 (22) 14 (10.3) 18.3 (13)
M12 59 (44) 91 (67) 51 (38) 24 (17.7) 31 (23)
M14 94 (69) 143 (105) 82 (60) 38 (28) 50 (37)
M16 145 (107) 222 (164) 126 (93) 58 (43) 76 (56)
M18 201 (148) 308 (227) 176 (130) 82 (60) 106 (78)
M20 283 (209) 434 (320) 247 (182) 115 (85) 150 (111)
M22 387 (285) 473 (349) 337 (249) 157 (116) 202 (149)
M24 487 (359) 595 (439) 426 (314) 198 (146) 257 (190)
M27 716 (528) 716 (528) 602 (444) 292 (215) 379 (280)
M30 968 (714) 968 (714) 817 (603) 397 (293) 515 (380)
M33 1315 (970) 1008 (744) 1112 (820) 536 (395) 697 (514)
M36 1692 (1248) 1297 (957) 1428 (1053) 690 (509) 897 (662)
M39 2187 (1613) 1849 (1364) 890 (656) 1160 (856)
M42 2714 (2002) 2287 (1687) 1067 (787) 1447 (1067)
M45 3375 (2489) 1800 (1328)
M48 4084 (3012) 2178 (1606)
M64 9750 (7192) 5201 (3836)
M68 11768 (8680) 6277 (4630)
M76
Above mentioned torques are for all screwed unions, which works under dynamical load. For all other
connections you can use a corresponding smaller torque.
Page 38 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
PN 6571: for tie bolts made of material marked with (1) the torque value has to be reduced by 50%.
PN 6572.4: for all material classes the torque value has to be reduced by 40%.
Anchor bolts are usually made of 4.6 material. Tightening torques indicated in above table shall not be
exceeded.
Page 39 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
If the pump is fitted with an inducer Take care of the coupling shell splits
[2215], it has to be pulled off instead of the [7240].
spacer sleeve. Pull off the bearing housing [3200]. Loose the
12) Open the tie bolt and hexagon nut [6571, 6581.10] studs [6572.2] and pull off the mechanical seal
and remove the suction casing [1130] and suction cartridge.
bell [1310].
Page 40 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 41 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
can be disconnected from the top or intermediate 7) Loose the studs [6572.1], take off the bearing
shaft [2130.1 or 2120.1]. cover [3260.1] and remove the key [6700.2].
11) Open the tie bolt and hexagon nut [6571,
6581.10] and remove the suction casing [1130]. Take care of the springs [4260].
12) Remove the circlip [6544.2] and pull off the Pull off the bearing housing [3200]. Loose the
impeller [2200.1]. studs [6572.2] and pull off the mechanical seal
cartridge.
If the pump is fitted with an inducer
[2215], it has to be pulled off instead of the To disassemble only the hydraulic
spacer sleeve. section start with point 11.
13) Remove now the key [6700.3] and the next 8) Open the hexagon head bolts [6577.4] and
retaining ring. disconnect the first column pipe from the
headstock [1141].
Take care of the O-ring [4610.5]. 9) Pull out the complete bowl assembly together with
14) Pull off the pump bowl [1170.1], so you have shafts and column pipes. Disconnect the first
access to the next stage impeller. column pipe.
15) Repeat step 12, 13 and 14 until you reach the 10) Open the socket head cap screws [6579.2] and slip
last stage. upwards the shaft coupling [7020]. Remove the
16) Open the hexagon head bolts [6577.6], which coupling shell splits [7240]. Now the shafts are
connects the column pipe with the pump bowl uncoupled and you can proceed the same way
[1170.2] and remove it. with the next column pipe until the bowl assembly
can be disconnected from the top or intermediate
Pump bowl [1170.1] can be splitted in the shaft [2130.1 or 2120.1].
stage casing [1160] and the diffuser [1410.1]. Refer
to sectional drawing. For 20 WU pump the pump shaft
[2110] is especially coupled to the first
6.7.4 Dismantling of 20, 45 & 80WUC-2L intermediate shaft [2120.2] by a screwed
1) Completely drain the pump by using the drain coupling. Unscrew the intermediate shaft [2120.2]
connection. By pumping explosive or toxic media, from the coupling sleeve [7250]. Now unscrew
flush it with Nitrogen. the coupling sleeve [7250] from the pump shaft
2) Uncouple the pump from the motor and remove the [2110].
motor after disconnecting it from the electrical net.
3) Pull off the coupling hub from the pump shaft Both shafts have a left hand thread.
[2110] and take out the key [6700.1]. 11) Open the hexagon head bolts [6577.7] and pull off
4) Secure the mechanical seal by putting the tool into the suction casing [1130].
the groove of the shaft sleeve. Loose the shrunk
ring, and disconnect the seal piping. Take care of the O-ring [4610.5].
12) Remove the circlip [6544.2] and pull off the
Drain the seal system, if impeller [2200.1].
applicable.
5) Drain the oil from the bearing housing using the If the pump is fitted with an inducer
plug [6569.1]. Loose the studs [6572.4] and pull out [2215], it has to be pulled off instead of the
the pump from it´s can. spacer sleeve.
6) Loose the socket head cap screw [6579.1] and slip 13) Remove now the key [6700.3] and the next
down the rotor by turning the shaft nut [2910] and retaining ring.
remove it. 14) Open the hexagon head bolts [6577.7] and pull
off the pump bowl [1170.1], so you have access
If applicable pull off the fan [8161] to the next stage impeller.
after loosing the grub screw [6814.3].
Use an anaerobic adhesive for securing the Take care of the O-ring [4610.5].
socket set screw for reassembly. 15) Repeat step 12,13 and 14 until you reach the last
stage.
If the pump is equipped with a rigid 16) Open the hexagon head bolts [6577.6], which
spacer coupling open the socket head cap connects the column pipe with the last pump
screws [6579.3] move the coupling half [7200], bowl [1170.2] and remove it.
remove the intermediate coupling [7021], Pull off the second intermediate bearing sleeve
coupling ring splits [7415], coupling half [7200] [3400.2] from the pump shaft [2110].
and keys [6700.8].
Page 42 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
6.7.5 Dismantling of the thrust bearing 20 WU-2L 64 (2.5) 0.3 - 0.5 (0.012-0.020)
20 WU-2R 112 (4.4) 0.4 - 0.6 (0.016-0.024)
Thrust bearing No. Bearing size 25 WU-2R 115 (4.5) 0.4 - 0.6 (0.016-0.024)
0N 7210 BECBJ (M) 30 WU-2R 112 (4.4) 0.4 - 0.6 (0.016-0.024)
35 WU-2R 112 (4.4) 0.4 - 0.6 (0.016-0.024)
1N 7313 BECBJ (M) 40 WU-2H 95 (3.7) 0.4 - 0.6 (0.016-0.024)
3N 7315 BECBJ (M) 45 WU-2L 87 (3.4) 0.3 - 0.5 (0.012-0.020)
45 WU-2R 112 (4.4) 0.4 - 0.6 (0.016-0.024)
4N 7317 BECBJ (M) 50 WU-2R 112 (4.4) 0.4 - 0.6 (0.016-0.024)
5N 7318 BECBJ (M) 50 WU-2M 85 (3.3) 0.4 - 0.6 (0.016-0.024)
50 WU-2H 140 (5.5) 0.5 - 0.7 (0.020-0.028)
6N 7322 BECBM 60 WU-2M 85( 3.3) 0.4 - 0.6 (0.016-0.024)
7N 7326 BCBM 60 WU-2R 112 (4.4) 0.4 - 0.6 (0.016-0.024)
65 WU-2R 148 (5.8) 0.5 - 0.7 (0.020-0.028)
7232 BCBM 80 WU-2L 103 (4.1) 0.4 - 0.6 (0.016-0.024)
8N
7330 BCBM 80 WU-2H 148 (5.8) 0.5 - 0.7 (0.020-0.028)
90 WU-2R 148 (5.8) 0.5 - 0.7 (0.020-0.028)
100 WU-2R 148 (5.8) 0.5 - 0.7 (0.020-0.028)
6.7.5.1 Bearing housing 3N – 8N 100 WU-2M 120 (4.7) 0.5 - 0.7 (0.020-0.028)
1) Remove the bearing assembly consisting of the 125 WU-2L 120 (4.7) 0.5 - 0.7 (0.020-0.028)
thrust ball bearing [3013.1], bearing adaptor 150 WU-2R 169 (6.7) 0.5 - 0.7 (0.020-0.028)
150 WU-2M 125 (4.9) 0,5 - 0.7 (0.020-0.028)
sleeve [2471], spacer ring [2510] and the bearing
180 WU-2L 135/171(5.3/6.7) 0.5 - 0.7 (0.020-0.028)
lock nut [3712] as a cartridge. 200 WU-2M 160 (6.3) 0.5 - 0.7 (0.020-0.028)
2) Open the bearing lock nut [3712] and pull off the 200 WU-2L 160 (6.3) 0.5 - 0.7 (0.020-0.028)
thrust ball bearing [3013.1] 200 WU-2R 169 (6.7) 0.5 - 0.7 (0.020-0.028)
200 WU-2H 140/165(5.5/6.5) 0.5 - 0.7 (0.020-0.028)
6.7.5.2 Bearing housing 0N – 1N 200 WU-4M 180 (7.1) 0.5 - 0.7 (0.020-0.028)
250 WU-4H 200 (7.9) 0.6 - 0.8 (0.024-0.032)
1) Remove the bearing assembly consisting of the 275 WU-2M 160 (6.3) 0.5 - 0.7 (0.020-0.028)
thrust ball bearing [3013.1], bearing adaptor 300 WU-2R 183 (7.2) 0.5 - 0.7 (0.020-0.028)
sleeve [2471] and the bearing lock nut [3712] as 300 WU-4H 230(9.1) 0.6 - 0.8 (0.024-0.032)
a cartridge. 0.5 - 0.7 / 0.6 - 0.8 (0.020-
300 WU-4M 190/230(7.5/9.1)
2) Open the bearing lock nut [3712] and pull off the 0.028 / 0.024-0.032)
thrust ball bearing [3013.1]. 300 WU-2L 160/190(6.3/7.5) 0.5 - 0.7 (0.020-0.028)
400 WU-4R 236 (9.3) 0.6 - 0.8 (0.024-0.032)
400 WU-4M 240 (9.5) 0.6 - 0.8 (0.024-0.032)
For the hydrodynamic thrust bearing 400 WU-4H 240 (9.5) 0.6 - 0.8 (0.024-0.032)
dismantling, refer to bearing manufacturer´s IOM. 450 WU-2R 183 (7.2) 0.5 - 0.7 (0.020-0.028)
500 WU-2L 191 (7.5) 0.5 - 0.7 (0.020-0.028)
600 WU-4M 265 (10.4) 0.6 - 0.8 (0.024-0.032)
6.8 Examination of parts 0.5 - 0.7 / 0.6 - 0.8 (0.020-
650 WU-2L 190/230(7.5/9.1)
1) Check the intermediate bearing sleeves and 0.028 / 0.024-0.032)
bushings against any wear. The diametrical 700 WU-4H 265 (10.4) 0.6 - 0.8 (0.024-0.032)
800 WU-4M 300 (11.8) 0.6 - 0.8 (0.024-0.032)
clearance between sleeves and bushings must
900 WU-4M 265 (10.4) 0.6 - 0.8 (0.024-0.032)
not exceed twice the value in new condition. 900 WU-4H 300 (11.8) 0.6 - 0,8 (0.024-0.032)
2) Check the casing wear ring and the impeller wear 1000 WU-4H 300 (11.8) 0.6 - 0,8 (0.024-0.032)
ring against any wear. The diametrical clearance 1200 WU-4H 330 (13.0) 0.7 - 0.9 (0.028-0.035)
between the rings must not exceed twice the 1200 WU-4L 330 (13.0) 0.7 - 0.9 (0.028-0.035)
value in new condition. 1400 WU-4M 354 (13.9) 1 - 1.2 (0.039-0.047)
3) Check all parts against corrosion and erosion. 1500 WU-4L 339 (13.4) 0.7 - 0.9 (0.028-0.035)
4) Carefully check the coupling against any wear. 1600 WU-4M 339 (13.4) 0.7 - 0.9 (0.028-0.035)
2000 WU-4L 360 (14.2) 1 - 1.2 (0.039-0.047)
5) Rotate the angular contact bearing by hand, to
2000 WU-4M 360 (14.2) 1 - 1.2 (0.039-0.047)
check against abnormal sound. Check the 2250 WU-4L 388 (15.3) 1 - 1.2 (0.039-0.047)
bearing cages against any wear and the outer
and inner race against running marks. Check the
runout of the shafts. TIR (Total Indicated Runout)
shall not exceed 0.04 mm/m (0.0005 in./ft) of
length. TIR shall not exceed 0.08 mm (0.003 in.)
over total shaft length.
Wear ring
Radial clearances
Pump size diameter mm
mm (in)
(in)
10 WU-2H 64 (2.5) 0.3 - 0.5 (0.012-0.020)
Page 43 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Bearing Sleeve Pipe Bearing Housing 6.9.2 Assembly of mixed flow impeller pump
Radial
Outside Bushing Inner types (Francis type)
clearance
diameter diameter
mm (in.)
mm (in.) mm (in.)
31.9 (1.24) 32 (1.25)
0.10÷0.12 Assembly is done preferably in vertical position.
(0.0039÷0.0047)
0.10÷0.12
51.9 (2.02) 52 (2.03)
(0.0039÷0.0047) 1) Put the interstage sleeve [2410.3] and the last
0.11÷0.13 stage casing over the pump shaft [2110], and slip
59.9 (2.34) 60 (2.34)
(0.0043÷0.0051) on the impeller [2200.1]. After putting the O-ring
0.11÷0.13 [4610.5] to the next pump bowl [1170.1], slip it on
71.9 (2.80) 72 (2.80)
(0.0043÷0.0051)
0.12÷0.15
to the last pump bowl [1170.2] and tight the
109.9 (4.29) 110 (4.29) hexagon head bolts [6577.7].
(0.0047÷0.0059)
0.12÷0.15 2) Slip on the interstage sleeve [2410.1]. Put in the
119.9 (4,68) 120 (4.68)
(0.0047÷0.0059) key [6700.3] and slip on the impeller [2200.1].
3) Repeat step 1 and 2 until you have mounted the
6.9 Assembly first stage impeller. If the pump is fitted with
To assemble the pump consult the sectional double suction impeller, move directly to step 8)
drawings. and follow procedure until step 15).
4) Slip on the interstage sleeve [2410.1] and put on
Ensure threads, gasket and O-ring mating faces are the suction casing [1130] including the O-ring
clean. Apply thread sealant to non-face sealing pipe [4610.5]. Tight the hexagon head bolts [6577.7].
thread fittings. 5) Put on the distance sleeve [2460] or inducer
[2215] and secure the assembly by tightening the
impeller nut [2912] just by hand.
After complete assembly with 6) Loose the impeller nut [2912] to the next location
headstock and bearing housing the rotor must be for securing it with a grub screw [6814.2].
lifted!, see section 5 .3 Impeller clearance 7) For further pump assembly follow reverse
disassembly procedure.
6.9.1 Assembly of radial flow impeller pump types 8) Secure the assembly by tightening the impeller
Assembly is done preferably in vertical position. nut [2912.1] just by hand.
1) Put the last stage diffuser [1410.2] into the 9) Loose the impeller nut [2912.1] to the next
discharge casing [1140]. Insert the O-ring location for securing it with a grub screw [6814.2].
[4610.5]. Repeat this with all the stage casings 10) Put the bearing sleeve [3400.5] over the pump
[1160], diffusers [1410.1] and O-rings [4610.5]. shaft [2110]. Place the o-ring [4610.5] on the
2) Put the discharge casing [1140] over the pump diffusor suction casing [1410] and put them
shaft [2110]. together over the pump shaft [2110]. Tighten the
3) Put in the key [6700.3] in the keyway and slip on hexagonal head bolts [6577.7].
the interstage sleeve [2410.2], the last stage 11) Put in the key [6700.11] and slip on the impeller
impeller [2200.1] and the interstage sleeve [2200.3] over the pump shaft [2110].
[2410.1] to the shaft. 12) Put the bearing sleeve [3400.3] on the pump
4) Put on the next stage casing assembly. Put the shaft [2110] and assemble the suction casing
key [6700.3] in the keyway and slip on the [1130] including the o-ring [4610.7]. Tighten the
impeller [2200.1] and the interstage sleeve hexagonal head bolts [6577.11].
[2410.1] to the shaft. 13) Put the key [6700.12] on the pump shaft [2110].
5) Repeat step 4 until you reach the first stage. After Put on the distance sleeve [2460] and secure the
slipping on the first stage impeller [2200.2] and assembly by tightening the impeller nut [2912.2]
the interstage sleeve [2410.2] you can put on the just by hand.
suction casing [1130]. 14) Loose the impeller nut [2912.2] to the next
6) Fix the hydraulic assembly by tightening the tie location for securing it with a grub screw [6814.2].
bolts [6571]. 15) For further pump assembly follow reverse
disassembly procedure.
This must be done croswise
6.9.3 Assembly of 10WUC-2H
with required torques.(refer to section 6,
Maintenance) Assembly is done preferably in vertical position.
7) Put on the distance sleeve [2460], or inducer 1) Put the last stage casing over the pump shaft
[2215] and secure the assembly by tightening the [2110]. After putting the O-ring [4610.5] to the
impeller nut [2912] just by hand. next pump bowl [1170.1], slip it on to the pump
8) Loose the impeller nut [2912] to the next location bowl [1170.2].
for securing it with a grub screw [6814.2]. 2) Put the circlip [6544.2] and the key [6700.3] on to
9) For further pump assembly follow reverse the shaft and slip on the impeller [2200.1].
disassembly procedure.
Page 44 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
3) Secure the impeller with the retaining ring and 6.9.5 Assembly of the thrust bearing
put on the next pump bowl [1170.1] including an Thrust bearing No. Bearing size
O-ring [4610.5].
4) Repeat step 2 and 3 until you have mounted the 0N 7210 BECBJ (M)
first stage impeller. 1N 7313 BECBJ (M)
5) Put on the suction casing [1130] including the 3N 7315 BECBJ (M)
O-ring [4610.5] and tighten the tie bolt and
hexagon nut [6571, 6581.10]. 4N 7317 BECBJ (M)
6) For further pump assembly follow reverse 5N 7318 BECBJ (M)
disassembly procedure.
6N 7322 BECBM
7N 7326 BCBM
Pump bowl [1170.1] can be splitted in the
stage casing [1160] and the diffuser [1410.1]. Refer 7232 BCBM
8N
to sectional drawing. 7330 BCBM
Page 45 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Try to turn the rotor by hand.If Try to turn the rotor by hand.If the
the rotor cannot be turned readjust it following rotor cannot be turned readjust it following procedure
procedure in section 5.3.1 Adjusting of the rotor. in section 5.3.1 Adjusting of the rotor.
The mechanical seal requires no adjustment The mechanical seal requires no adjustment
anymore. Check if the mounting plates are anymore. Check if the mounting plates are already
alreadyswung out. swung out.
Page 46 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 47 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Plan 53 pressurized dual seal systems are used in Drain the seal system, if
services where no leakage to atmosphere can be applicable.
tolerated. A Plan 53a system consists of dual 3) Loose the socket head cap screw [6579.1] and slip
mechanical seals with a liquid barrier fluid between down the rotor by turning the shaft nut [2910].
them. The barrier fluid is contained in a seal pot
which is pressurized to a pressure of approximately
1.5 bar (23 psi) greater than the pump seal chamber. If applicable pull off the fan [8161]
Inner seal leakage will be barrier fluid leakage into after loosing the grub screw [6814.3].
the product. There will always be some leakage Use an anaerobic adhesive for securing the
(max.5 ml/hour). socket set screw for reassembly.
The leakage rate is monitored by monitoring the seal 4) Open the socket head cap screws [6579.3] move
pot level. The gas coffer dam ensures that the the coupling half [7200] and remove the
product is not contaminated with barrier fluid. The intermediate coupling [7021].
seal pot pressure must be maintained at the proper 5) Now remove the coupling ring split [7415], the
level. If the seal pot pressure drops, the system will coupling half [7200] and the key [6700.8].
begin to operate like a Plan 52, or unpressurized dual 6) Loose the studs [6572.2] and pull off the
seal, which does not offer the same level of sealing mechanical seal cartridge.
integrity. Specifically, the inner seal leakage direction 7) For assembly follow the reverse procedure.
will be reversed and the barrier fluid will, over time,
become contaminated with the process fluid with the
problems that result, including possible seal failure.
Page 48 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 49 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
Page 50 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
FAULT SYMPTOM
Pump overheats and seizes
⇓ Bearings have short life
⇓ Pump vibrates or is noisy
⇓ Mechanical seal has short life
⇓ Mechanical seal leaks excessively
⇓ Pump requires excessive power
⇓ Pump loses prime after starting
⇓ Insufficient pressure developed
⇓ Insufficient capacity delivered
⇓ Pump does not deliver liquid
⇓ PROBABLE CAUSES POSSIBLE REMEDIES
Incorrect type of mechanical seal for operating
Consult Flowserve
conditions.
Check misalignment and correct if necessary.
Shaft running off centre because of worn
If alignment satisfactory check bearings for
bearings or misalignment.
excessive wear
Impeller out of balance resulting in vibration. Check and consult Flowserve
Abrasive solids in liquid pumped. Check and consult Flowserve
Check mechanical seal condition and source
Mechanical seal was run dry.
of dry running and repair
Internal misalignment due to improper repairs Check method of assembly, possible damage
causing impeller to rub. or state of cleanliness during assembly
Excessive thrust caused by a mechanical Check wear condition of Impeller, its
failure inside the pump. clearances and liquid passages
Excessive grease in ball bearings. Check method of regreasing
Check hours run since last change of
Lack of lubrication for bearings.
lubricant, the schedule and its basis
Check method of assembly, possible damage
Improper installation of bearings or state of cleanliness during assembly and
type of bearing used
Check contamination source and replace
Damaged bearings due to contamination.
damaged bearings
C. ELECTRICAL TROUBLES
Wrong direction of rotation. Reverse 2 phases on motor terminal box
Motor running too slow, Check motor terminal box connections
Page 51 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
9.0 CERTIFICATION
Certificates determined from the contract
requirements are provided with these instructions
where applicable. Examples are certificates for CE
marking, ATEX marking etc. If required, copies of
other certificates sent separately to the Purchaser
should be obtained from the Purchaser for retention
with these User Instructions.
Reference 2:
Pump Handbook, 2nd edition, Igor J. Karassik et al,
McGraw-Hill Inc., New York, 1993.
Reference 3:
ANSI/HI 1.1-1.5
Centrifugal Pumps - Nomenclature, Definitions,
Application and Operation.
Reference 4:
ANSI B31.3 - Process Piping.
Page 52 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
10.4 Abbreviations
Rotational
revs per minute r/min
Speed
Newton/square
Stress N/mm² 145.0 pounds/in.² psi
millimetre
degrees degrees
Temperature °C (1.8 x °C) + 32 °F
Celsius Fahrenheit
millimetre/ inches/
Vibration 3
second mm/s 0.03937 second in./sec
1
multiply the ISO unit by the multiplication factor to obtain US units
2 where pressure is not stated to be absolute it is gauge
3 where not stated to be peak it is r.m.s.
4 sound pressure level LpA, re 1m - 20microPa, or sound power level LwA re 1 pW when sound power is
applicable
Page 53 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
AFTERMARKET DIRECTORY
OUR ADRESS
Flowserve (Austria) GmbH Tel: +43 / 2236 / 31530
Industriestraße B/6 Fax: +43 / 2236 / 33430
A-2345 Brunn/Geb., AUSTRIA Mail: flowserve-brunn@flowserve.com
IMPORTANT NOTES:
RECOMMENDATION:
Page 54 of 55
WUC USER INSTRUCTIONS ENGLISH - 05/16
FLOWSERVE REGIONAL
Your Flowserve factory contacts: SALES OFFICES:
Latin America
Flowserve Corporation
Martín Rodriguez 4460
B1644CGN-Victoria-San
Fernando
Buenos Aires, Argentina
Telephone: +54 11 4006 8700
Telefax: +54 11 4714 1610
Asia Pacific
Flowserve Pte. Ltd.
10 Tuas Loop
Singapore 637345
Telephone: +65 6771 0600
Telefax: +65 6862 2329