NEW RADIOACTIVE WASTE MANAGEMENT FACILITY IN ROMANIA
Conference Paper · February 2001
DOI: 10.13140/RG.2.1.2098.3528
CITATIONS READS
0 116
3 authors:
Veronica Andrei Florian Glodeanu
Nuclearelectrica Kinectrics
46 PUBLICATIONS 26 CITATIONS 90 PUBLICATIONS 104 CITATIONS
SEE PROFILE SEE PROFILE
Rotaru Ioan
ROMATOM Romania
16 PUBLICATIONS 1 CITATION
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Nuclear Fuel Cycle in Romania View project
Research Project Title: Leadership and Management for an Effective Nuclear Security Culture in Nigeria View project
All content following this page was uploaded by Florian Glodeanu on 31 May 2014.
The user has requested enhancement of the downloaded file.
WM’01 Conference, February 25-March 1, 2001, Tucson, AZ
NEW RADIOACTIVE WASTE MANAGEMENT FACILITY IN ROMANIA
Veronica Andrei, Florin Glodeanu, Ioan Rotaru
Nuclearelectrica National Company
ABSTRACT
Romania has a single nuclear power plant (NPP) located at the Cernavoda site. This NPP
is CANDU 6, a Canadian type reactor design. At present, one single unit of the five that
are planned for is in operation, and a second plant is under construction. The plant is
owned and operated by Nuclearelectrica National Company (SNN). The currently
operating NPP has only the initial pretreatment step in its waste management system. As
it is described in specific documents of the International Atomic Energy (IAEA)
documents, this pretreatment consists of collection, segregation, decontamination (if
appropriate), precompaction and a period of on-site interim storage.
SNN has established a policy for the long-term management of its own waste. This
includes the identification of a destination for the wastes in accordance with legal
requirements and proven technologies, which will be acceptable to the regulatory body.
For short-lived low and intermediate level wastes, a near surface disposal facility is being
considered. For high- level wastes (mainly spent fuel), and long-lived low and
intermediate level wastes, interim storage followed by geological disposal represents the
most suitable option at this time. The top management of SNN has reviewed its strategy
and established the target objectives for implementing its policy on medium term. For the
next three years, priority will be given to constructing an independent spent fuel dry
storage facility at the Cernavoda NPP site. Based on the selection process being followed
in Romania, the supplier of the dry storage technology will be announced in early 2001.
This paper will present some aspects concerning future developments in radioactive waste
management at the NPP site and the principal aspects of licensing the spent fuel dry
storage facility by the Romanian safety and environmental authorities.
INTRODUCTION
Nuclearelectrica National Company (SNN), under the responsibility of the Romanian
Ministry of Industry and Trade, is the owner of the Nuclear Power Plant (NPP) located at
the Cernavoda site. At present, only one of the five CANDU 6- reactors in construction
on Cernavoda site is in operation. It produces more than 10% of the national electricity
demand. The Romanian Government made public its commitment to continue the
construction of a second unit, which is about 40% completed.
In Romania the largest producer of radioactive wastes is the nuclear power plant.
According to the basic national laws on nuclear safety and environmental protection,
SNN is responsible for management of its radioactive waste. In this respect, the company
developed a radioactive waste management policy, which incorporates the practice in the
country of the plant supplier (Canada) and the recommendations of International Atomic
Energy Agency (IAEA) and the European Commission (EC). The policy established
objectives and targets in accordance with the status of Cernavoda NPP project. For the
short term, the priority of the radioactive waste management policy is to extend the spent
WM’01 Conference, February 25-March 1, 2001, Tucson, AZ
fuel storage capacity using the dry storage technology. The supplier of the dry storage
technology will be announced early in 2001 based on a bidding process. In the absence of
a specific national regulatory framework, the nuclear safety and environmental licensing
processes of the spent fuel dry storage facility will follow the United States’ Nuclear
Regulatory Commission (NRC) approach and other European Union (EU) regulations.
EVOLUTION OF THE REGULATORY FRAMEWORK
In the centrally planned economy of Romania [1 ] during the communist era, all aspects of
nuclear activities were the responsibility of the state with no clear separation between
regulating and implementing functions. The nuclear law dealt with general principles,
referring mainly to the nuclear power plants and did not deal with radioactive waste or
decommissioning. After 1990, once the “iron curtain” installed by the communism was
removed, the regulatory systems were renewed by the new socio-political system. Reform
of the Romanian society included the establishment of national institutions and the
regulatory structure.
Two national authorities have the main responsibilities for regulating, licensing or
performing institutional control in nuclear activities including radioactive waste
management: the Ministry of Waters, Forests and Environmental Protection (MAPPM)
and the National Commission for Nuclear Activities Control (CNCAN). The institutional
reform will include also the settlement of a new organization in-charge with radioactive
waste management in the country. Romania is a candidate country for acceptance into the
European Union (EU). The harmonization of national legislation with EU legislation is
one condition in that direction.
The basic laws already passed or reviewed by the Parliament refer to the general
principles of nuclear safety and environmental protec tion applicable to all nuclear
practices including radioactive wastes and spent fuel management. Thus, according to
Law 137/1995 the environmental protection authorities conduct the licensing processes
and issue environmental agreements and licenses. The agreement is required for any new
investment and the license is required for the commissioning and operation of any new
facility. There are central and local environmental authorities; the central authority being
represented by MAPPM itself. The nuclear power plant and radioactive waste disposal
facilities are licensed by the central authority, and the radioactive waste storage including
spent fuel storage facilities are licensed by the local environmental authorities (called
Environmental Protection Agencie s). The licensing procedure is described by the Order
127/1996 issued by MAPPM. This order asks for an environmental impact study having a
similar content to those required by the European Union legislation. Public debate is also
required before issue of both environmental agreement and license.
The nuclear safety authority is represented by CNCAN organized under the Romanian
Government. The basic nuclear safety law is Law 111/1996, which stipulates the
licensing of nuclear installations, is issued in many steps: design, siting, construction,
commissioning, operation and decommissioning. In general, any nuclear operator has to
apply for a license in any important stage of a nuclear installation lifetime, including test
operation, operation and maintenance, repair or refurbishment, preservation or
decommissioning. A robust secondary legislation and formulation of management
policies and programs must strengthen this new basic legislation. In this respect, CNCAN
issued recently the Order 14/2000 approving the Fundamental Norm of Radiological
WM’01 Conference, February 25-March 1, 2001, Tucson, AZ
Safety. That norm establishes the requirements referring to the radiological safety of
workers, public and environment and is harmonized with the European Directive
96/29/EURATOM. Currently, CNCAN continues [2 ] the process to review the existing
national legal framework in the nuclear field against similar laws and regulations adopted
by European Commission in the fields of nuclear safety, radiological protection,
radioactive waste and spent fuel management, decommissioning of nuclear installations,
civil liabilities, physical protection and safeguards. However, the specific requirements
for licensing a spent fuel storage or disposal facility are still not available.
NEW RADIOACTIVE WASTE MANAGEMENT AT CERNAVODA NPP
The Cernavoda NPP operates facilities [3 ] for the proper collection, pretreatment and
storage of all low and intermediate radioactive wastes. The compactable and non-
compactable radioactive wastes are packaged in stainless steel drums and stored in the
concrete building of the Solid Radioactive Waste Intermediate Facility (SRWIF), located
within the inner fence of the plant. The spent filters cartridges, spent filters and other
large metallic items are stored in the holes of a special concrete structure belongin g to the
SRWIF. The design capacity of the SRWIF is for 18 years/reactor and it is planned to
accommodate the waste from the second reactor, too. The spent resins are stored in two
concrete vaults located in the service building. Each storage vault has a capacity of about
200 m3, together covering 15-20 years of the plant operation lifetime. The organic liquids
and other types of radioactive waste packaged in stainless steel drums are stored on the
service building basement. The spent fuel is stored in a pool with enough capacity for 8
years of operating the NPP (80% availability).
Taking into account the responsibility of its own waste management and the fact that the
current NPP’s waste management system addresses only the first step of the effective
management - “the pretreatment”, SNN established a long term policy for waste
management. For implementing the policy on medium term, target objectives were
established:
-a spent fuel dry storage facility, planned to be operational by the end of 2003;
-a near surface repository for low and intermediate level radioactive waste, planned to be
operational by the end of this decade.
Thus, by the end of the next decade the Cernavoda nuclear site will include two CANDU
reactors, an intermediate spent fuel storage facility and a LILW repository. The new
projects will be implemented according to the international applicable standards. From
the radiological protection point of view, each all-nuclear practice on the site will meet
the requirements of CNCAN Fundamental Norm for Radiological Safety (harmonized
with the EU Directive 96/29/EURATOM and International Commission of Radiological
Protection recommendations).
The current radioactive waste management program of SNN covers those measures
established to reach the following radioactive waste management objectives:
-to promote the new investment and construction of the spent fuel dry storage facility;
-to establish a methodology for the characterization of the raw radioactive wastes;
-to license the site of the fut ure LILW repository. In the short term, the priority of the
radioactive waste management program is represented by the construction of the
WM’01 Conference, February 25-March 1, 2001, Tucson, AZ
intermediate spent fuel dry storage facility
NUCLEAR AND ENVIRONMENTAL LICENSING OF THE NEW FACILITY
The licensing of the intermediate spent fuel storage facility is based on the two basic laws
no. 137/1995 for environmental protection and no. 111/1996 for Safe Deployment of
Nuclear Activities. Because the specific requirements for nuclear licensing of the
intermediate spent fuel dry storage have not been developed yet, CNCAN recommended
the use of the following approach:
- the license will be issued in three steps: siting (based on the Preliminary
Safety Assessment), construction (based on the Preliminary Safety Report)
and commissioning (based on the Final Safety Report).
- the licensing process will be based on the Romanian laws and regulation
supplemented with the US - NRC guides and regulations (10 CFR part 72,
NRC Regulatory Guide 3.48 and NUREG 1567 and 1536)
- the recommended design guides for the interim dry storage facility are
ANSI/ANS 57.9-1992 and CSA N 292.2.1996.
In order to shorten the licensing period of the dry storage technology, which will be
selected in the bidding process, it should be proven at industrial scale and licensed at least
in the country of the supplier.
As the new spent fuel dry storage will be built on the Cernavoda NPP’s site (a licensed
nuclear site) it is expected that the siting license will be obtained without any special
problems.
The second step in the licensing process will be implemented with the technical
assistance of the supplier. As part of delivery, the supplier is asked to provide a
Preliminary Safety Report which complies with NRC Regulatory Guide 3.48 - Standard
format and content for the safety analysis report for an independent spent fuel storage
installation (Dry storage). With some additions, this document will be used to support our
application for construction license issued by CNCAN.
The third step will be implemented also with technical assistance of the supplier. As the
project will be implemented on a turnkey basis, the supplier will be involved in pre-
operational tests, personnel training and commissioning of the facility. The application
for the commissioning license will be supported with the Final Safety Report prepared
with the technical assistance from the supplier.
In the licensing process, it is expected that difficulties may arise due to the very tight
schedule (3 years) and the need to have a perfect synchronization with NPP operation (the
plant modification can be done only during outages).
The environmental licensing will be implemented according to the Romanian Law
137/1995 for environmental protection. The environmental licensing procedure is
described in the MAPPM Order 125/1996 and consists of the main steps:
• an environmental agreement for promoting the new investment;
• an environmental license for operation of the facility.
WM’01 Conference, February 25-March 1, 2001, Tucson, AZ
The environmental agreement is issued by the local Environmental Agency based on the
project description, with the main information referring to the environmental impact, and
the Environmental Impact Study (EIS), which meets the requirements of the national
regulations. Referring to the content of EIS, the national legal requirements are
harmonized with the specific EU Directive 97/11/EC on the assessment of the effects of
certain public and private projects on the environment and are similar with specific
American regulations. The EIS will be prepared with the technical assistance of the
Supplier. A report on the EIS will be submitted to the local environmental authority for
approval. The approved report is subject to a public debate. Public debate is the last step
before the environmental authority’s final decision and refers to any of the following:
local announcement, mass-media publicity, public inquiry, as both the environmental
authority and the applicant have previously agreed to. Not later than one month
afterwards, the environmental authority takes the positive decision and announces it that
has to issue the agreement if no other official appeal exists.
The local Environmental Agency also issues the environmental license. The procedure for
issuing this license is similar with that for issuing the agreement, except that instead of
EIS an environmental balance has to be prepared based on the MAPPM Order 184/1997
and a report on this document has to be approved by the environmental authority
becoming subject to the public debate. The licensing procedure could last approximately
nine months.
SNN expects that both licensing processes of the new spent storage facility conducted by
the nuclear safety and environmental authorities will be difficult, at least for the reasons
of tight schedule and absence of specific requirements for licensing this type of facilities.
However, SNN will develop iterative processes with the different authorities, as a general
approach being confident that the experience gained during the licensing processes for
NPP, which was developed in similar conditions, is going to be a real advantage.
CONCLUSIONS
In Romania, the single reactor of the CANDU-6 type has been in operation since
December 1996 and a spent fuel dry storage facility is planned for commissioning by the
end of 2003. The latter facility is part of a designed larger nuclear complex on NPP’s site
including two similar nuclear units, the spent fuel storage facility and a near surface
disposal facility.
The supplier of the dry storage technology will be established based on a bidding process,
earlier in 2001.
As the regulatory framework is under review or development in Romania, specific
requirements for this type of technology are still not available, the applied requirements
for licensing will be based on national laws and regulations but also on specific EU
legislation and American regulations and standards, as the nuclear safety and
environmental authorities have recommended.
Even the owner of the power plant, SNN, expects that the licensing processes will be
difficult, and, based on its previous experience, it will develop iterative processes with the
authorities being trusty that the licenses will be issued in a proper time schedule.
WM’01 Conference, February 25-March 1, 2001, Tucson, AZ
REFERENCES
[1] S. Webster, “Radioactive waste management in the European Union applicant
countries,”, ENS – Topseal, 1999.
[2] Report CNCAN, The 11th Plenary Meeting of G-24 NUSAC, 2000.
[3] V. Andrei et.al., “Radioactive waste management policy in Romania, WM2K,
Tucson, 2000.