Standard Forms for Subcontractors
Standard Forms for
Subcontractors
A Practical Approach
RANDOLPH J.B. TAYLOR
This book was typeset by Ark Imaging for
Blackhall Publishing
33 Carysfort Avenue
Blackrock
Co. Dublin
Ireland
e-mail: info@blackhallpublishing.com
www.blackhallpublishing.com
© Randolph J.B. Taylor, 2007
ISBN: 978 1 84218 125 6
A catalogue record for this book is available from the British Library.
All rights reserved. No part of this publication may be reproduced, stored in a
retrieval system or transmitted in any form or by any means, electronic,
mechanical, photocopying, recording or otherwise, without the prior, written
permission of the publisher.
This book is sold subject to the condition that it shall not, by way of trade
or otherwise, be lent, resold, hired out, or otherwise circulated without the
publisher’s prior consent in any form of binding or cover other than that in
which it is published and without a similar condition including this condition
being imposed on the subsequent purchaser.
Printed in Ireland by ColourBooks Ltd
Contents
Preface vii
Introduction xi
Table of Forms and Notes xiii
Section 1: Contractual 1
Section 2: Financial 69
Section 3: Document and Information Control 111
Section 4: Site Matters Management 143
Appendix: Check Sheets 195
v
Disclaimer
The author and publishers assume no responsibility for any outcome fol
lowing the use of the documents contained in this book.
Preface
The aim of this book is to assist wherever possible all subcontractors
involved in the construction industry who consider that they have been
treated unfairly or are being treated unfairly by a main contractor and who
do not want to be treated in a similar fashion now or in the future. This
document has not been sanctioned by any of the professional institutions
nor has it been approved by any union’s workers, representative bodies or
contractor’s organisations. I would like to thank the directors of P.J. Walls
Ltd and The BDL Group for granting permission for me to use the tem
plate forms and letters that follow.
There are many courses and seminars held throughout the industry giving
advice to subcontractors on everything from how to get paid to how to
draft a letter and so I believe that I should explain why I felt it necessary
to produce this book.
In 1989 I returned to England from working in the Middle East where I had
been employed in the offices of a well-known international professional
quantity surveying practice since 1981. During this eight year period
I came across many forms of contract, some novel and some bastardised
versions of “standard forms of contract”. These novel contracts carried
with them risks far greater than any contained in the “standard forms”.
However standard forms incorrectly employed or applied carry risks of
their own. Standard forms of contract used without amendment are of
course a rarity. Nearly every standard form of contract entered into has
been tampered with in some way; clauses have been altered, added to or
deleted by one party, normally to ensure that a better deal is achieved by
that party, whether it is in terms of time or money or some other benefit.
Upon my return in 1989 I was employed by a leading internal fit-out sub
contractor based in London. I was given the task of creating a commercial
manual for that company. Over the next two years I learned how that par
ticular marketplace functioned and about the nature of the relationship
between main contractors and subcontractors. I was astounded to discover
just how dictatorial and uncompromising main contractors could be
towards subcontractors.
vii
Preface
During this period I created a manual which that company still uses to this
day, albeit upgraded to suit the passage of time. I stayed with them for a
further three years developing and upgrading the manual. As a part of the
manual I composed standard memoranda which the foremen site managers
and surveyors were to use to ensure that documentation was produced to
comply with the contract, primarily to protect my employer’s position.
During my time in England my company was appointed by nearly all of
the major main contractors at one time or another and we were subjected
to the same treatment from most of them. The subcontract was always
used as if it was a tool solely for the use and benefit of the main contrac
tor. For example, the subcontract would always refer to the conditions of
the main contract and the subcontractor was always expected to have read
and accepted the conditions of the main contract, despite rarely being
afforded the opportunity of reviewing the main contract conditions. These
situations are created by inefficient main contractors requesting tender
returns under pressure and appointing subcontractors quickly in order to
meet programme deadlines. Once on site, information is rarely forthcom
ing, at least not in a timely fashion. Despite this, programme deadlines are
always expected to be met and so on.
When I had finalised the aforementioned manual we started to operate the
memoranda and found after a very short time that we became more
respected and that the main contractors began to realise we were not only
professional at producing a high quality product for them but that we were
also acquainted with the world of contract and were no longer willing to
sit back and wait for their correspondence to overwhelm us.
In 1995 I relocated to Ireland and commenced working for one of the top
ten main contractors in the Republic. After six years with this company
as a senior surveyor and their assistant chief surveyor, I joined a younger
and smaller main contractor as their chief surveyor. I gained a massive
amount of invaluable knowledge and experience from these two employ
ers and one of the imperatives I learned from them – totally contrary to
my experiences in England – was that subcontractors have to be treated
fairly, provided they are performing well. During my time with these com
panies I met and created good and long lasting relationships with many
subcontractors.
viii
Preface
However, having been a subcontractor’s surveyor for six years, I also
know that subcontractors can be treated unfairly by main contractors
and that if, for whatever reason, the main contractor decides that he is
not going to pay, then the subcontractors will not be paid; or they will
only get paid what the main contractors decide to pay. This creates
mayhem, particularly within individual projects, and also throughout the
industry as a whole and leads to frustration, stress and the breakdown of
relationships. In many cases subcontractors are forced into issuing let
ters from solicitors and paying out for the solicitor’s time and service
with the possibility of no recovery. In worst cases subcontractors verge
on or fall into bankruptcy as their cash flows dry up and entitlements fail
to materialise.
I have written this book to help equip subcontractors with the material
they might need to carry out their contractual obligations in a structured
manner, and ultimately to give the subcontractor a legal foothold in their
relationship with the main contractor. I understand that the Irish construc
tion market is relatively small and that paths cross more often than not.
However the market is fast, furious and changing and care should be exer
cised by all operating within it. I also know and understand that the
construction industry operates very much on a personal relationship-by
relationship basis and much work is found and lost on that basis. Letters
and memoranda therefore do not have to be confrontational or written in
a strictly contractual manner by making reference to “clause this” or
“clause that” in order to set a record of events. However if the contract
requires that written notice of an event or foreseeable event must be given
and it is not, then the exposure and liability could and probably would be
laid at the doorstep of the offender.
The reasons I give for the writing of such records are as follows:
● To assist the main contractor in controlling the project by providing
information and requesting information on time.
● To assist the main contractor by ensuring that he provides informa
tion to the subcontractor at the appropriate time in order to meet the
programme.
● To ensure that the subcontractor complies with the terms and con
ditions of the main and subcontract in writing and by doing so pro
ix
Preface
tects his rights and position: “a verbal contract is worth the paper it
is written on.”
● To force the main contractor to think and act. Failure to do so when
a written request has been made is suicidal (as many subcontractors
know to their cost).
Three very enlightened men each gave me a piece of advice during differ
ent periods of my career. I pass them on here as I have found each, at
various times, to be absolutely priceless.
1. Always enter into a contract as though it is going to end in arbitration.
2. Documentation, documentation, documentation.
3. Try not to put the first letter on file but always ensure that a response
is given to every letter received.
The third point seems to contradict the case I have been trying to make.
However when you consider the fact that the construction industry is rela
tionship-based (in Ireland in particular), you can understand that the tim
ing and/or need for documentation to be presented is one of choice not
chance.
It is worth noting that a new form of public sector contract is to be intro
duced in 2007. This will set down different ground rules to those existing
in the industry up to this point and subcontractors should make themselves
aware of those differences and apply any new rules to the documents in
this book.
With the fast-growing pace of the construction industry in Ireland, I
believe that economics and contract law as well as pressure on the larger
companies to turn in profits at higher and higher levels to placate share
holders will force subcontractors into using a more structured approach to
protect their rights.
And remember main contractors cannot function without subcontractors.
x
Introduction
The following forms have been grouped into four separate sections:
1. Contractual
2. Financial
3. Information and Document Control
4. Site Matters Management
The forms are designated with the capital letter of each subsection, i.e.
Form C1 or F1 or I1 or SM1.
Some notes about the text that follows:
Note 1: These memos have been written over a period of years and the
background of contracts relating to their creation vary slightly.
Note 2: The subcontractor or indeed anyone or any company using these
forms or intending to use these forms must fully understand the clauses of
the contract under which they are operating at that time and refer to the
conditions of that contract and adopt these forms to suit.
Note 3: Throughout the text memos and notes regarding or referring to
time periods are used to indicate that, under normal circumstances, the
notification of, or action within, time periods is a prerequisite for contrac
tual compliance.
Note 4: These notes referring to time periods are italicised and ** is used
to indicate that the subcontractor should ensure that periods used in letters
reflect the requirement of the contract under which he/she is currently
employed.
Note 5: If no time limits are set down in the contract for particular issues
then reasonable deadlines/time limits should be used.
xi
Introduction
Note 6: On some of the following forms a number of choices are given as
to the type of text to use but these are samples only and any one or com
bination of these may be used; additional selections may be made to suit
the circumstances prevailing at time of writing.
xii
Table of Forms and Notes
Reference Nr Title Page Nr
Contractual Forms and Notes
C2 Compliance Documentation 7
C4 Main Contract Conditions 9
C6 Notification to Commence the Works 11
C8 Secure Storage 13
C10 Main Contractor’s Insurances 15
C12 Submission of Level
Survey/Data/Dilapidation Survey 17
C14 Out of Sequence Working 21
C16 Out of Sequence Working 23
C18 Notification of Possible Delay to
Programme – Projected Completion 25
C20 Programme Update 27
C22 Request for an Extension of
Time – Imminent Overrun 29
C24 Request for an Extension of
Time – Contract Overrun 33
C26 Extension of Time Extended
Period – Imminent Overrun 37
C28 Request for an Extension of Time –
Extended Period Overrun 41
C30 Out of Sequence Working –
Disruption Costs 45
C32 Request for Approval to Assign the Works 49
C34 Instruction to Assign the Works 51
C36 Costs Associated with Assigning the Works 53
C38 Suspension of the Works due to Non-Payment 55
C40 Determination of the Contract
of Employment due to Non-Payment
57
xiii
Table of Forms and Notes
C42 Main Contractor in Bankruptcy –
Request for Clarification
59
C44 Determination of Contract of
Employment due to Main Contractor
in Bankruptcy 61
C46 Conciliation 63
C48 Arbitration 65
C50 Request for Release of Final Certificate
and Second Moiety of Retention 67
Financial Forms and Notes
F2 Variations Assessment of Costs and Time 73
F4 Variations Assessment of Costs 75
F6 Update of Time and Costs Expended 77
F8 Loss and Expense Arising from Instruction 79
F10 Loss and Expense – Estimated Costs
Arising from Instruction 81
F12 Loss and Expense – Final Costs
Arising from Instruction 83
F14 Valuation and Payment Dates –
Request for Clarification 85
F16 Submission of Valuation 87
F18 Query on Adjustment to Valuation 89
F20 Query on Certified Values in Valuation 91
F22 Rejection of Set-off Monies 93
F24 Rejection of Set-off – Loss and Expense 95
F26 Rejection of Set-off – No Notification 97
F28 Failure to Advise of and/or Pay Sums
Included in Certificates 99
F30 Non-Payment of Sums Certified 101
F32 Letter to Employer – Non-Payment by
Main Contractor 103
F34 Interest on Late Payment 105
F36 Request for Release of Second
Moiety of Retention 107
F38 Request for Release of Second
Moiety of Retention Reminder 109
xiv
Table of Forms and Notes
Document Control Forms and Notes
I2 Daywork Sheets Issue Log 115
I4 Daywork Sheets – Request for Return
of Submitted Sheets 117
I6 Information Received from Third Party 119
I8 Drawing Register Incoming 123
I10 Drawing Register Outgoing 125
I12 Schedule of Information Required 127
I13 Schedule of Information Required 128
I15 Site Diary 133
I17 Request for Information 135
I19 Electronic Mail Register Issue Log 137
I21 Two Week Look Ahead Programme 139
I23 Purchasing List 141
Site Matters Forms and Notes
SM2 Abnormal Hazardous Operations 147
SM4 Confirmation of Verbal Instruction 149
SM6 Confirmation of Verbal Instruction Reminder 151
SM8 Confirmation of Adequacy of
Information Received from Others 153
SM10 Confirmation of Adequacy of
Information Received Reminder 157
SM12 Suitability of Previous Works/Backgrounds 159
SM14 Suitability of Previous
Works/Backgrounds Reminder 161
SM16 Request for Approval to Proceed –
Interface Trades 163
SM18 Completion of Work Stages 165
SM20 Completion of Work Stages Reminder 167
SM22 Damage to Work by Others 169
SM24 Completion of Rectification Work 171
SM26 Request for Approval to Proceed to Meet
Programme 173
SM28 Information Received from Third Party 175
SM30 Repairs to Damaged Works –
Confirm Verbal Instruction 179
xv
Table of Forms and Notes
SM32 Notice of Materials Delivery 181
SM34 Notice of Materials Delivery Turned
Away – Cost of Reordering/Redelivery 183
SM36 Notice of Reordered Material Delivery 185
SM38 Confirmation of Receipt of Instruction 187
SM40 Submission of Check Sheets/Test Results 189
SM42 Submission of Check Sheets Register/Test
Results Register/Log 191
SM44 Completion of Snags 193
SM45 Inspection and Check Sheets 194
xvi
Section 1: Contractual
Table of Contractual Forms and Notes
Reference Nr Title Page Nr
C2 Compliance Documentation 7
C4 Main Contract Conditions 9
C6 Notification to Commence the Works 11
C8 Secure Storage 13
C10 Main Contractor’s Insurances 15
C12 Submission of Level
Survey/Data/Dilapidation Survey 17
C14 Out of Sequence Working 21
C16 Out of Sequence Working 23
C18 Notification of Possible Delay to
Programme – Projected Completion 25
C20 Programme Update 27
C22 Request for an Extension of
Time – Imminent Overrun 29
C24 Request for an Extension of
Time – Contract Overrun 33
C26 Extension of Time Extended
Period – Imminent Overrun 37
C28 Request for an Extension of Time –
Extended Period Overrun 41
C30 Out of Sequence Working – Disruption Costs 45
C32 Request for Approval to Assign the Works 49
C34 Instruction to Assign the Works 51
C36 Costs Associated with Assigning the Works 53
C38 Suspension of the Works due to Non-Payment 55
C40 Determination of the Contract
of Employment due to Non-Payment
57
C42 Main Contractor in Bankruptcy –
Request for Clarification
59
3
Standard Forms for Subcontractors
C44 Determination of Contract of Employment
due to Main Contractor in Bankruptcy 61
C46 Conciliation 63
C48 Arbitration 65
C50 Request for Release of Final Certificate
and Second Moiety of Retention 67
Standard Forms for Subcontractors
Note C1
Re: Compliance Documentation
To be used when issuing quotation.
To show the main contractor that you are compliant and efficient.
These documents are the minimum required and if others are requested by
the main contractor subsequently they should be added to the list and sent
in good time.
To ensure that main contractors do not have an excuse for not paying any
amounts due in first interim claims.
To ensure that main contractors do not withhold monies as a result of
incomplete documentation, e.g. for insurances.
Contractual
Memo C2
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Compliance Documentation
Please find enclosed the following:
1. Insurance details: PL/EL/All risks
2. Tax forms, completed RCT1 etc.
3. C2 copy
4. Confirmation of pension scheme
5. Confirmation of union membership
If successful and our quotation is accepted we shall furnish Safety and
Method Statements at time of appointment prior to start on site.
Yours truly,
The Subcontractor
Standard Forms for Subcontractors
Note C3
Re: Main Contract Conditions
To be used prior to issue of quotation and before acceptance of award of
contract.
To enable a defence if there is no reply to the letter advising of amend
ments and conditions are contradictory between subcontract and main
contract.
Contractual
Memo C4
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Main Contract Conditions
Please confirm that the main contract conditions are the latest edition of
the RIAI/GDLA (or other form) conditions and that those conditions
remain unaltered.
Should the main conditions have been altered or amended in any way
please let us have copies of those alterations in order to ensure that we are
compliant prior to the signing of the subcontract.
Yours truly,
The Subcontractor
Standard Forms for Subcontractors
Note C5
Re: Notification to Commence the Works
To be used upon receipt of instruction to commence work in order to
acknowledge date of instruction and actual start on site in case of delayed
start/future delays/late issue of information by the client and others
preventing you from progressing the works.
To be completed using the time period agreed on appointment for the
completion of the subcontract works.
Notification to commence must be given in writing by the main contrac
tor and, once given in writing, all endeavours must be used by the subcon
tractor to complete as agreed;
or
to be used when works cannot commence due to circumstances outside
your control, preventing a productive safe start on site.
10
Contractual
Memo C6
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Notification to Commence the Works
We acknowledge receipt of your verbal instruction/letter/memorandum/
facsimilie/e-mail/order reference …………, dated …………, to proceed
with the works.
We confirm that we are mobilising in order to meet this date which
will give a projected completion date of …………;
or
we have inspected the site/works/area …………… and advise that the site/
works/area is/are not ready for us to commence for the following reasons:
a)
b)
c)
Please have these areas/issues corrected/made good/prepared/altered and
advise us in order that we may mobilise.
We will advise you of any impact that this may have on our programme
upon receipt of your revised start date.
Yours truly,
The Subcontractor
11
Standard Forms for Subcontractors
Note C7
Re: Secure Storage
To be used to protect subcontractor insurances and rights against theft.
To be requested at time of agreeing contract conditions prior to appointment.
To prevent the main contractor from later stating that materials brought to
site are solely the subcontractor’s responsibility.
To show that the subcontractor was aware of the need for secure storage
and asked for assistance and, if none was forthcoming, that the main
contractor neglected responsibility.
12
Contractual
Memo C8
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Secure Storage Requirements
Please arrange to provide secure accommodation/storage areas for storage
of materials and equipment brought to site for the permanent works.
Once our materials are on site we are unable to ensure that they will be
protected at all times and therefore request your assistance in this matter.
Please advise where on site our materials/equipment are to be stored.
Yours truly,
The Subcontractor
13
Standard Forms for Subcontractors
Note C9
Re: Main Contract Insurances
Most subcontracts require that conditions comply with or are no less than
main contract conditions. To be used to ensure compliance with the main
contractor’s policies is not onerous. To be requested at time of agreeing
contract conditions prior to appointment.
To be reviewed and agreed prior to agreeing price as conditions may incur
added costs.
To enable a defence if there is no reply to the letter advising of amend
ments and subcontractor insurances are later found to be non-compliant.
14
Contractual
Memo C10
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Main Contractor’s Insurances
Please provide us with a copy of your insurances for this project in order
that we may ensure we are compliant.
We shall pass these on to our brokers for confirmation and, should there
be any requirement to alter our insurances in order to ensure compliance,
we will advise you of those conditions immediately.
This may result in additional costs which we shall pass on to you as an
extra to the contract unless you are willing to cover those amendments
under your own policies and provide us with confirmation of cover.
Yours truly,
The Subcontractor
15
Standard Forms for Subcontractors
Note C11
Re: Submission of Level Survey/Data/Dilapidation Survey
To be issued after checking surveys or data issued by the architect or
anyone authorised to issue.
To be issued to the main contractor immediately on completion of survey.
To be issued prior to starting any permanent work.
To preserve rights.
To establish a start point for re-measure.
To record existing values/points/structure/integrity.
16
Contractual
Memo C12
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Submission of Level Survey/Data/Dilapidation Survey
Please find enclosed our level survey/data sheets/dilapidation survey,
including photographs for the following locations:
Area/Location Date of Survey
a)
b)
c)
d)
e)
These surveys have been carried out in order to determine the exact start
points of our works for record purposes and we would be pleased to
receive your acknowledgement and acceptance of same;
or
we have checked the surveys/information issued to us referenced
………………, dated ………………, for the following areas:
Area/Location Date of Survey
a)
b)
c)
d)
e)
17
Standard Forms for Subcontractors
The surveys are correct and we confirm that we are in agreement with the
data provided;
or
we have checked the surveys/information issued to us referenced
…………………, dated ………………, for the following areas:
a)
b)
c)
and found the following errors/anomalies/conflicts:
a)
b)
c)
Please issue your instructions on how to proceed. Until we have resolved
these errors/anomalies/conflicts we are unable to commence the works.
Yours truly,
The Subcontractor
18
[Blank]
19
Standard Forms for Subcontractors
Note C13
Re: Out of Sequence Working
To be issued prior to carrying out the disrupted works.
To put on record the fact that the programme is not on target.
To make the main contractor responsible for delays if any follow.
To preserve rights to seek costs.
20
Contractual
Memo C14
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Out of Sequence Working
We write to record that we are progressing with our work as per your
instructions/requirements/as agreed on ……………… in the following
areas:
Area Date
a)
b)
c)
d)
e)
Please note that we consider that this is contrary to previously agreed and
programmed sequences and we have to provide resources contrary to our
intended plan of work and that this may therefore incur additional costs.
We are monitoring the situation as it develops and we will advise you
accordingly or as soon as it becomes reasonably apparent.
In the meantime our labour/plant/equipment day sheets will be maintained
to illustrate our resources and actual hours spent in undertaking these tasks.
Yours truly,
The Subcontractor
21
Standard Forms for Subcontractors
Note C15
Re: Out of Sequence Working Costs
To be issued as soon as costs are incurred.
To be monitored and issued on a regular basis until complete.
To be presented to main contractor and signed off.
To be included in valuations.
22
Contractual
Memo C16
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Out of Sequence Working
Further to Memo C14 dated ………………, we write to advise that we
have incurred additional costs following your instructions as detailed
below.
Description Area Cost e
a)
b)
c)
d)
e)
We enclose copies of our daywork sheets/work record sheets in support of
this claim and would appreciate receiving your early approval of same.
In the meantime we will include these items in our valuations for
reimbursement purposes.
Yours truly,
The Subcontractor
23
Standard Forms for Subcontractors
Note C17
Re: Notification of Possible Delay to Programme – Projected Completion
To be issued as soon as it becomes apparent that there is likely to be a
delay caused by others.
To put on record the fact that the programme is unlikely to achieve target.
To make the main contractor responsible for delays if any follow.
To preserve rights to seek costs.
To protect against liquidated damages.
24
Contractual
Memo C18
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Notification of Possible Delay to Programme – Projected Completion
In accordance with the terms and conditions of our contract we write to
advise that for the reasons outlined below, reasons outside our control,
we believe that the contract date for completion is likely to be/will be
overrun.
Cause Estimated Effect in Days/Weeks
a)
b)
c)
d)
e)
We would be grateful to receive your earliest possible response and
instruction as to how you would wish us to proceed.
In the meantime our labour/plant/equipment day sheets will be maintained
to illustrate our resources and actual hours spent in undertaking these
tasks.
Yours truly,
The Subcontractor
25
Standard Forms for Subcontractors
Note C19
Re: Programme Update
To be issued as soon as possible after issue of C18 and/or when informa
tion is received that is likely to have a knock-on effect on the programme.
To put on record the fact that the programme is in jeopardy.
To make the main contractor responsible for delays.
To preserve rights to seek costs.
To protect against liquidated damages.
26
Contractual
Memo C20
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Programme Update
Further to our Memo C18, dated ………………, please find enclosed our
revised programme based on our best estimate as to how long we shall
take to carry out the tasks outlined in the aforementioned memo and based
on additional information received by us outlined below.
Document Reference Date Issued
a)
b)
c)
d)
e)
We trust that the above and enclosed is to your approval and that the
enclosed will assist you in overall programming and control.
Yours truly,
The Subcontractor
27
Standard Forms for Subcontractors
Note C21
Re: Request for an Extension of Time
To be issued as soon as possible after issue of C20;
or
to be issued as soon as it becomes reasonably apparent that the contract
will be overrun as a result of failure by others.
To preserve right as early notification is required.
To seek redress costs and time.
To protect against liquidated damages.
28
Contractual
Memo C22
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Request for and Extension of Time – Imminent Overrun
In accordance with the terms and conditions of our contract and further to
our memoranda C18 ................... and C20, dated ………………, we write
to advise that the contract date for completion is likely to be overrun.
This situation has arisen through circumstances beyond our control,
namely:
Relevant Event Contract Clause Effect/Weeks
a)
b)
c)
d)
e)
The total time effect in weeks is ………………
We would be grateful to receive your acknowledgement of the foregoing
and your earliest possible instruction advising us on how you wish us to
proceed.
29
Standard Forms for Subcontractors
In the meantime we shall proceed using our best endeavours to carry out
the works and to mitigate any further delay and minimise any costs asso
ciated with this overrun.
Yours truly,
The Subcontractor
30
[Blank]
31
Standard Forms for Subcontractors
Note C23
Re: Request for an Extension of Time – Contract Overrun
To be issued as soon as possible after issue of C22 if it transpires that
events which occur will definitely impact on the programme;
or
to be issued as soon as it becomes reasonably apparent that the contract
will be overrun as a result of failure by others.
To preserve right as early notification is required.
To provide a defence against the levying of liquidated damages.
32
Contractual
Memo C24
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Request for an Extension of Time – Contract Overrun
In accordance with the terms and conditions of our contract and further to
our memorandum C22, dated ………………, we herewith make applica
tion for an extension of time and to advise that the contract date for
completion of ………………. will now be overrun.
This situation arose through circumstances entirely beyond our control as
previously advised namely:
Relevant Event Contract Clause Effect/Weeks
a)
b)
c)
d)
e)
f)
The total time effect is ……………… weeks.
We would be pleased to receive your acknowledgement of these events
and an official extension of time in due course along with your revised
programme allowing us to resource accordingly, covering these events.
33
Standard Forms for Subcontractors
We further advise that as a result of the foregoing we have incurred and
are likely to incur further loss and expense as a result of the works having
been and continuing to be affected by those causes listed.
We shall monitor the effects of this delay and will in due course ascertain
the cost and time ramifications of the foregoing and submit these to you
for recompense.
In the meantime we shall proceed using our best endeavours to carry on
the works and to mitigate any further delay.
Yours truly,
The Subcontractor
34
[Blank]
35
Standard Forms for Subcontractors
Note C25
Re: Extension of Time Extended Period – Imminent Overrun
To be issued as soon as possible after issue of C24 if it transpires that the
extended period is insufficient and is likely to be overrun as a result of
failure by others.
To preserve right as early notification is required.
To provide a defence against the levying of liquidated damages.
36
Contractual
Memo C26
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Extension of Time Extended Period – Imminent Overrun
In accordance with the terms and conditions of our contract and further to
our memorandum C24, dated ………………, we write to advise that the
extended period granted for an extension of time is likely to be/has been
overrun.
This situation has arisen through circumstances entirely beyond our
control as previously advised, namely:
Relevant Event Contract Clause Effect/Weeks
a)
b)
c)
d)
e)
f)
The total time effect is ……………… weeks.
We would be pleased to receive your acknowledgement of these events
and an official further extension of time in due course along with your
revised programme allowing us to resource accordingly covering these
events.
37
Standard Forms for Subcontractors
We further advise that as a result of the foregoing we have incurred and
are likely to incur further loss and expense as a result of the works having
been and continuing to be affected by those causes listed.
We shall monitor the effects of this delay and will in due course ascertain
the cost and time ramifications of the foregoing and submit these to you
for recompense.
In the meantime we shall proceed using our best endeavours to carry on
the works and to mitigate any further delay.
Yours truly,
The Subcontractor
38
[Blank]
39
Standard Forms for Subcontractors
Note C27
Re: Request for an Extension of Time – Extended Period Overrun
To be issued as soon as possible after issue of C26 if it transpires that
delays occur;
or
to be issued as soon as it becomes reasonably apparent that the contract
will be overrun as a result of failure by others.
To preserve right as early notification is required.
To provide a defence against the levying of liquidated damages.
40
Contractual
Memo C28
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Request for an Extension of Time – Extended Period Overrun
In accordance with the terms and conditions of our contract and further to
our memorandum C26, dated ………………, we herewith make applica
tion for a further extension of time and to advise that the extended
contract date for completion of ……………… has now been overrun.
This situation arose through circumstances entirely beyond our control as
previously advised namely:
Relevant Event Contract Clause Effect/Weeks
a)
b)
c)
d)
e)
f)
The total time effect is ……………… weeks.
We would be pleased to receive your acknowledgement of these events
and another extension of time in due course along with your revised
programme allowing us to resource accordingly covering these events.
41
Standard Forms for Subcontractors
We further advise that as a result of the foregoing we have incurred and
are likely to incur further loss and expense as a result of the works having
been and continuing to be affected by those causes listed.
We shall monitor the effects of this delay and will in due course ascertain
the cost and time ramifications of the foregoing and submit these to you
for recompense.
In the meantime we shall proceed using our best endeavours to carry on
the works and to mitigate any further delay.
Yours truly,
The Subcontractor
42
[Blank]
43
Standard Forms for Subcontractors
Note C29
Re: Out of Sequence Working – Disruption Costs (Alternative to Memo C16)
To be issued as soon as possible after issue of C14 if it transpires that dis
ruption costs are being incurred.
To be issued within the week following the week in which work is done
for signature.
To be followed up with I2 five days later.
To preserve right for reimbursement and to give early notification.
44
Contractual
Memo C30
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Out of Sequence Working – Disruption Costs
Further to our memorandum C14, dated ………………., we write enclos
ing copies of daywork sheets which we have raised to date regarding the
works outlined in C14.
We shall be claiming for all those hours expended over and above those
originally planned and allowed for in our tender.
In the meantime we continue to carry out your instructions as required and
we would appreciate your confirmation that this is acceptable/an indica
tion from you as to how we are to record the extras.
In the meantime we are carrying out the works on a daywork basis and
will forward our record sheets to you for signature in the week following
the week in which the work is done.
Daywork Sheet Nr Extra Over Hours Rate Total
a)
b)
c)
d)
45
Standard Forms for Subcontractors
e)
f)
----------
----------
Yours truly,
The Subcontractor
46
[Blank]
47
Standard Forms for Subcontractors
Note C31
Re: Request for Approval to Assign the Works
To be issued prior to subletting any or all of the contracted work.
To be requested as and when it is necessary to sublet in order to, for exam
ple, maintain programme/minimise costs.
To comply with contract.
48
Contractual
Memo C32
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Request for Approval to Assign the Works
We write to request your written approval/instruction permitting us to
assign the following works.
Section/area/element ………………….. (give description).
We request this in order to maintain/meet the contract programme/ensure
compliance with the specification ……………… (give reason).
We propose to use Messrs ……………… (give name address etc.).
All our obligations under the terms of the subcontract with you will be
passed on to our subcontractor and they will be required to comply with
those conditions.
Yours truly,
The Subcontractor
49
Standard Forms for Subcontractors
Note C33
Re: Instruction to Assign the Works
To be issued prior to subletting any or all of the contracted work.
To be used as and when it is necessary to sublet in order to, for example,
maintain programme/minimise costs.
To be used where assignment is called for in order for you to increase
resources to make up time as a result of delays by others.
To be used where assignment is instructed in order for you to increase
resources to make up time as a result of delays by others.
To comply with contract.
50
Contractual
Memo C34
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Instruction to Assign the Works
We write to confirm receipt of your written instruction directing us to
assign the following works.
Section/area/element ……………… (give description).
This instruction is given in order to maintain/meet the contract
programme/ensure compliance with the specification ………… (give
reason).
We propose to use Messrs ……………………………………. (give name
address etc.).
All our obligations under the terms of the subcontract with you will be
passed on to our subcontractor and they will be required to comply with
those conditions.
Yours truly,
The Subcontractor
51
Standard Forms for Subcontractors
Note C35
Re: Costs Associated with Assigning the Works
To be written only if the additional costs arise as a result of assignment
being made because of issues outside your control, e.g. delay by others
and request to accelerate/instruction by architect.
To be issued after obtaining approval for subletting any or all of the
contracted work.
To be written after issue of Memo C34.
To be written immediately upon estimation/calculation of costs.
52
Contractual
Memo C36
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Costs Associated with Assigning the Works
Further to our Memo C34, dated ………………, we write to confirm the
costs associated with your instruction to assign the works in the following
areas. Section/area/element ……………… (give description).
The costs arising are broken down as follows (send details):
Plant
Labour
Materials
Overheads
or
Attached quotation from Messrs ………………;
or
Bill rates � Quantity ………………
Yours truly,
The Subcontractor
53
Standard Forms for Subcontractors
Note C37
Re: Suspension of the Works Due to Non-Payment
To be used if payment is not received from the contractor;
or
to be used if payment is not received within **seven days after the main
contractor receives payment;
or
to be used within **twenty eight days of the date of issue of the
architect/engineer’s certificate which incorporates the amount due;
or
to be used within or on pay periods agreed between subcontractor and main
contractor.
54
Contractual
Memo C38
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Suspension of the Works Due to Non-Payment
Further to our memorandum F30 we are writing to advise that we have
still not received payment of monies certified in certificate nr …………/
monies due and included in valuation nr ………………
If after **seven days from the date of this letter we have still not received
these monies we will have no alternative but to suspend the works.
Please note that for each day of this suspension we will be entitled to have
the contract period extended by an additional **two days and we will
charge all additional overhead and preliminary costs arising therefrom.
If after a further fourteen day period, that is **twenty one days from the
date of this letter, we have still not received monies due we will consider
determination of this subcontract.
Yours truly,
The Subcontractor
55
Standard Forms for Subcontractors
Note C39
Re: Determination of the Contract of Employment due to Non-Payment
To be used **fourteen days after notification of suspension if:
monies have not been paid by employer directly;
monies have not been paid by the main contractor.
56
Contractual
Memo C40
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Determination of the Contract of Employment due to Non-Payment
Further to our memorandum C38, dated ………………, we are writing to
advise that, as a direct result of your failure to reimburse us in accordance
with the terms of our contract, we have no alternative but to determine our
contract of employment with you.
We are proceeding to remove from the site all our temporary offices, plant
and machinery appliances, goods and materials – excluding those already
paid for and/or installed.
We have advised our solicitors who will be writing to you directly.
Yours truly,
The Subcontractor
57
Standard Forms for Subcontractors
Note C41
Re: Main Contractor in Bankruptcy Request for Clarification
To be used where the main contractor has been declared in bankruptcy.
To be used where a receiver has been appointed to oversee the main
contractor’s business.
To be used where court judgments have been passed down on the main
contractor.
58
Contractual
Memo C42
To: The Main Contractor Reference……………………......
From: The Subcontractor Project name/number………….
Date: ………………
Re: Main Contractor in Bankruptcy – Request for Clarification
We have been informed that your Company is filing for bankruptcy/liqui
dating/has had a receiver appointed/has had a judgment registered against
you.
Please confirm that this is/is not the case and that we are to proceed/are
not to proceed in the execution of the Works.
Yours truly,
The Subcontractor
59
Standard Forms for Subcontractors
Note C43
Re: Determination of Contract of Employment due to Main Contractor in
Bankruptcy
To be used after C42.
To be used where the main contractor is in bankruptcy.
To be used where a receiver has been appointed to oversee the main
contractor’s business.
To be used where court judgments have been passed down on the main
contractor.
To be used where the main contractor has suspended the work or
unreasonably delayed the subcontract.
60
Contractual
Memo C44
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Determination of Contract of Employment due to Main Contractor in
Bankruptcy
Further to our memorandum C42 we write to advise that we have received
confirmation of your company’s current position and we are proceeding
to remove from the site all our temporary offices, plant and machinery
appliances, goods and materials – excluding those already paid for and/or
installed.
We have advised our solicitors who will be writing to you directly.
Yours truly,
The Subcontractor
61
Standard Forms for Subcontractors
Note C45
Re: Conciliation
To be used where permitted under the contract.
To be used where a dispute arises and no agreement is forthcoming, for
example:
1. Monies withheld in valuations.
2. Refusal to agree costs or time issues.
3. Refusal to meet.
62
Contractual
Memo C46
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Conciliation in the matter of
We are writing to advise that it is our intention to refer the above matter
to conciliation as it would appear unlikely that we will reach agreement
on ……....…………/it is impossible that we can reach agreement on
………………/we cannot reach agreement on ………………
We will follow the procedures outlined by the Construction Industry
Federation in this regard and will contact you in due course.
Yours truly,
The Subcontractor
63
Standard Forms for Subcontractors
Note C47
Re: Arbitration
To be used where permitted under the contract.
To be used where conciliation fails.
64
Contractual
Memo C48
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Arbitration in the matter of
If conciliation has been tried first:
Further to our memorandum C46 dated in the matter of the unsuccessful
conciliation in the attempted resolution of ………………, we are
writing to advise that it is our intention to refer the above matter to
arbitration within the meaning of the Arbitration Acts 1954 and 1998
(or any most recent Act amending same).
If conciliation has not been attempted first:
As it appears increasingly unlikely that we will be able to resolve the
differences between us in regard to the above we are writing to advise that
it is our intention to refer the above matter to arbitration within the
meaning of the Arbitration Acts 1954 and 1998 (or most recent).
We propose Mr ……………… of ……………… to act in this matter and
would be pleased to receive your nomination or acceptance.
Yours truly,
The Subcontractor
65
Standard Forms for Subcontractors
Note C49
Re: Request for Final Certificate
To be used one month before the date of issue of the final certificate is
reached.
Diaries should be marked twelve months ahead to remind accounts/sur
veyors of due date for release of retention.
66
Contractual
Memo C50
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Request for Release of Final Certificate and Second Moiety of
Retention Released on that Date
We write to request that the final certificate for the works be issued as
we are now approaching the end of the period of maintenance/defects
liability period.
We would also be pleased if you would arrange to have the second
moiety of retention released on that date.
Yours truly,
The Subcontractor
67
68
Section 2: Financial
70
Table of Financial Forms and Notes
Reference Nr Title Page Nr
F2 Variations Assessment of Costs and Time 73
F4 Variations Assessment of Costs 75
F6 Update of Time and Costs Expended 77
F8 Loss and Expense Arising from Instruction 79
F10 Loss and Expense – Estimated Costs
Arising from Instruction 81
F12 Loss and Expense – Final Costs
Arising from Instruction 83
F14 Valuation and Payment Dates –
Request for Clarification 85
F16 Submission of Valuation 87
F18 Query on Adjustment to Valuation 89
F20 Query on Certified Values in Valuation 91
F22 Rejection of Set-off Monies 93
F24 Rejection of Set-off – Loss and Expense 95
F26 Rejection of Set-off – No Notification 97
F28 Failure to Advise of and/or Pay Sums
Included in Certificates 99
F30 Non-Payment of Sums Certified 101
F32 Letter to Employer – Non-Payment by
Main Contractor 103
F34 Interest on Late Payment 105
F36 Request for Release of Second
Moiety of Retention 107
F38 Request for Release of Second
Moiety of Retention Reminder 109
71
Standard Forms for Subcontractors
Note F1
Re: Variations Assessment of Costs and Time
To be used where any variation is instructed whether written or oral.
To be issued to the main contractor no later than **five days after receipt
of variation.
Where verbal, subcontractor has to confirm within **five days of receipt
and main contractor must respond **five days thereafter. If not rescinded
in writing in the **ten day period then verbal instruction is usually
deemed to be written and subcontractor can proceed.
To include all variations whether works were carried out on them or
not in order to keep the main contractor QS aware of forthcoming costs
(see F16 section 2).
72
Financial
Memo F2
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Variations Assessment of Costs and Time
Please find listed hereunder our estimated cost and time requirements for
the carrying out of the variations instructed to date.
Item Description/ Estimate e Estimated
Instruction Nr Duration
a)
b)
c)
d)
Wherever possible, we will endeavour to absorb the time required to carry
out these works within our contract programme and to mitigate any delay
and/or further costs.
We shall advise you as soon as it becomes apparent that reimbursement of
further costs and/or an extension of time is required as a result of the
above.
These variations will be listed in our valuations and as work is carried out
we will apply for payment of relative values.
Yours truly,
The Subcontractor
73
Standard Forms for Subcontractors
Note F3
Re: Variations Assessment of Costs
To be used where any variation is instructed whether written or oral.
To be issued to the main contractor no later than **five days after receipt
of variation.
Where verbal (see SM4), subcontractor has to confirm within **five days
of receipt and main contractor must respond **five days thereafter. If not
rescinded in writing in the **ten day period then verbal instruction is
deemed to be written and subcontractor can proceed.
To include all variations whether works were carried out on them or
not in order to keep the main contractor QS aware of forthcoming costs.
74
Financial
Memo F4
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Variations Assessment of Costs
Please find listed hereunder our estimated cost for the carrying out of the
variations instructed to date.
Item Document Date Received Description Estimate of
Reference Cost e
a)
b)
c)
d)
These variations will be listed in our valuations and as work is carried out
we will apply for payment of relative values.
We trust that the above meets with your approval and look forward to
receiving your confirmation in due course.
Yours truly,
The Subcontractor
75
Standard Forms for Subcontractors
Note F5
Re: Update of Time and Costs Expended
To be used when final figures are assessed relative to previously advised
variations.
To be issued prior to submission of valuations which include the works or
part of the works listed.
To show final subcontractor figures, not necessarily final agreed figures.
76
Financial
Memo F6
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Update of Time and Costs Expended
Further to our memorandum F2, dated ………………, indicating the
estimated costs and time of variations/instructions, we present below our
final figures for your approval.
Item Description/Instruction Nr Time Impact Cost e
a)
b)
c)
d)
These figures will be included in our valuations and final account in part
or in whole as the works are carried out and as figures are agreed.
In connection with the requirement for an extension of time we refer you
to our letter reference C21, dated ………………
Yours truly,
The Subcontractor
77
Standard Forms for Subcontractors
Note F7
Re: Loss and Expense Arising from Instruction
To be confirmed as soon as it becomes reasonably apparent that the
issuing of any instruction, written or verbal, confirmed as before is likely
to have a cost impact on the contract over and above measured rates.
Bringing more resources back to site to do minor works or disproportionate
prelim/overhead costs, for example.
To allow the main contractor the opportunity to include valid claims in his
reports submissions to the client.
78
Financial
Memo F8
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Loss and Expense Arising from Instruction
We write to confirm that further to our receipt of your verbal/written
instruction in connection with the following issues:
Description of Work Instruction Nr/Verbal Instruction dated
a)
b)
c)
Having reviewed the resources which will be required to carry out these
works, we are likely to incur additional preliminary/overhead/unforeseen
costs in the execution of these works.
We shall be required to provide additional craneage/supervision/extended
working hours etc.
It is our intention to evaluate these costs and to pass them on to you for
reimbursement.
Please confirm that this meets with your approval.
Yours truly,
The Subcontractor
79
Standard Forms for Subcontractors
Note F9
Re: Loss and Expense – Estimated Costs Arising from Instruction
To be issued as soon as tasks are planned and costs are estimated.
To allow the main contractor the opportunity to include valid claims in his
reports submissions to the client.
80
Financial
Memo F10
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Loss and Expense – Estimated Costs Arising from Instruction
Further to our memorandum F8, dated ………………, advising you of the
likelihood that additional costs would be incurred in the carrying out
of your instruction nr ………………, verbal instruction dated
………………, confirmed by us in writing on ………………, we write to
advise you of our assessment of same.
The additional costs we estimate as arising are outlined below and on
attached calculation sheets:
Description of Work Reason Estimate of cost e
a) Leave crane 5 days Unload tanks for client 1500
b) Return visit engineer Level and set up tanks 500
c) ……………… ……………… ………………
Please confirm that these costs are acceptable.
We will advise you of the final costs of the above, if they should change,
upon completion for reimbursement.
Yours truly,
The Subcontractor
81
Standard Forms for Subcontractors
Note F11
Re: Loss and Expense – Final Costs Arising from Instruction
To be issued as soon as tasks are planned and costs are estimated.
To allow the main contractor the opportunity to include valid claims in his
reports submissions to the client.
82
Financial
Memo F12
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Loss and Expense – Final Costs Arising from Instruction
Further to Memo F10, dated ………………, we write to advise that the
final additional costs of carrying out your instructions listed below is as
follows:
Description of Work Reason Estimate of cost e
a) Leave crane 5 days Unload tanks for client 1500
b) Return visit engineer Level and set up tanks 500
c) ……………… ……………… ………………
Breakdown of costs is as outlined below and on attached calculation
sheets.
We will include these costs in our forthcoming valuation for reimburse
ment;
or
we will issue our invoice for these works in due course.
Yours truly,
The Subcontractor
83
Standard Forms for Subcontractors
Note F13
Re: Valuation and Payment Dates – Request for Clarification
To be issued as early in the contract as possible and before valuation nr 1.
Submission dates have to be met by the subcontractor every time.
Cycle to be checked against appropriate contract clause and against
conditions of main contract.
To be used in agreement with the main contractor to establish cycle
acceptable to all.
To be used to monitor timing of payments by the main contractor for
possible loss of interest claim if payments delayed.
84
Financial
Memo F14
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Valuation and Payment Dates – Request for Clarification
We write to request that you provide us with the dates by which you
require our interim valuations to be submitted and for confirmation of the
certification and payment dates applicable to those valuations for our
records and action.
Yours truly,
The Subcontractor
85
Standard Forms for Subcontractors
Note F15
Re: Submission of Valuation Nr , Dated
To be issued with each valuation.
To be issued in accordance with the terms of the contract applicable;
or
to be issued in accordance with dates agreed on payment and valuation
schedules, see F14.
To illustrate your compliance.
When contractors do not reciprocate and payments/certification are late
thereby affecting subcontractor cash flow, this can be used to illustrate
grounds for claim.
86
Financial
Memo F16
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Submission of Valuation Nr , Dated
Please find enclosed our valuation nr ……………… in the gross sum of
e…………. and (in words) …………………… for works executed up to
the end of (month) ……………… (year) ………………
Summarised as follows:
1. Preliminaries e………….
2. Measured Work e………….
3. Variations e………….
4. Materials on Site e………….
5. Materials off site e………….
6. Dayworks e………….
7. Claims e………….
Total Gross e………….
We trust that the enclosed is to your satisfaction and meets with your
approval and that you will include this valuation in full in your applica
tion to the client/architect for prompt payment.
However should you have any queries in regard to the enclosed, we would
appreciate it if you would contact us that we may review these observa
tions and agree same with you prior to submission to the client.
Yours truly,
The Subcontractor
87
Standard Forms for Subcontractors
Note F17
Re: Query on Adjustment to Valuation Nr
To be issued upon receipt of every valuation which is not paid in full of
claim made and for which no explanation as to deductions made is given.
To illustrate if necessary where contractors deduct monies due without
explanation thereby, if entitled and proven to be so at a later date, reduc
ing cash flow to the subcontractor with all consequences, i.e. borrowing
interest charges etc.
88
Financial
Memo F18
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Query on Adjustment to Valuation Nr , Dated
We write to request that you provide us with your detailed analysis of
the reasons for the adjustments which you have made to our valuation
nr ………………
We require these in order that we may agree/disagree and/or make neces
sary comments to prevent adjustments/inclusion in future valuations of
those items affected.
As we had agreed/discussed the scope and content of our valuation with
you prior to submission we are surprised to note the shortfall.
Yours truly,
The Subcontractor
89
Standard Forms for Subcontractors
Note F19
Re: Query on Adjustment to Valuation Nr
To be issued after F18 has been sent and a response received.
To be issued upon receipt of back up of certified figures which the main
contractor has received from the architect and which are unacceptable.
To illustrate if necessary where contractors deduct monies due without
explanation thereby, if entitled and proven to be so at a later date, reduc
ing cash flow to the subcontractor with all consequences, i.e. borrowing,
interest charges, inability to procure materials etc.
90
Financial
Memo F20
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Query on Certification of our Valuation Nr , Dated
Further to your response to our memorandum F18 in which you
advised us of the reasons why deductions had been made to our valuation
nr ………………
We write to advise that we are unhappy with the amounts certified by the
architect and we request that you allow us to commence legal proceedings
against the architect and that you will support us in our representation.
Yours truly,
The Subcontractor
91
Standard Forms for Subcontractors
Note F21
Re: Rejection of Set-off Monies
To be issued immediately upon being notified of set off which has not
been agreed whether from the valuation or retention monies.
To illustrate where main contractors deduct monies due without explanation.
To illustrate where the main contractor has deducted monies without
giving opportunity for the subcontractor to make good work.
92
Financial
Memo F22
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Rejection of Set-off Monies
We write to advise that we do not accept the unilateral deduction of con
tra charges/set-off/sums of monies from our account. We request that,
until you provide us with your detailed analysis of the reasons for the
adjustments made and we agree to those figures, you reinstate those
deductions.
At this point in time we have not agreed to any deductions.
If you do not reinstate these monies into our account as requested then
we shall proceed under contract to pursue our rights and entitlements as
appropriate.
We require your confirmation that monies deducted will be reinstated
by ………………
As we had agreed/discussed the scope and content of our valuation with
you prior to submission we are surprised to note these deductions.
Yours truly,
The Subcontractor
93
Standard Forms for Subcontractors
Note F23
Re: Rejection of Set-off Loss and Expense
To be issued immediately upon becoming aware of set-off which has not
been agreed between you and the main contractor whether from the valu
ation or retention monies.
To illustrate where contractors deduct monies due without explanation
thereby preventing cash flow to the subcontractor with all consequences,
i.e. borrowing, interest charges etc.
This form will be of value at a later date in substantiation of any claim
made for loss of profit etc.
94
Financial
Memo F24
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Rejection of Set-off – Loss and Expense
We write to advise that we do not accept the unilateral deduction of
set-off/sums of monies from our account which you allege arise out of
claims for loss and expense.
You have not provided/We require fully detailed records and justification
for this deduction and we request that, until you provide us with your
detailed analysis of the reasons for the adjustments made and we agree to
those figures, you reinstate those deductions.
At this point in time we have not agreed to any deductions for loss and
expense.
If you do not reinstate these monies into our account as requested then
we shall proceed under contract to pursue our rights and entitlements as
appropriate.
We require your confirmation that monies deducted will be reinstated
by ………………
As we had agreed/discussed the scope and content of our account with
you prior to submission we are surprised to note the shortfall.
Yours truly,
The Subcontractor
95
Standard Forms for Subcontractors
Note F25
Re: Rejection of Set-off – No Notification
To be issued when monies are deducted but no advanced written notifica
tion has been given.
To be issued immediately upon receiving returned valuations/claims
which show set-off which has not been agreed, either from the valuation
or retention monies.
To illustrate where contractors deduct monies due without explanation
thereby preventing cash flow to the subcontractor with all consequences,
i.e. borrowing, interest charges etc.
This form will be of value at a later date in substantiation of any claim
made for loss of profit etc.
96
Financial
Memo F26
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Rejection of Set-off – No Notification
We write to advise that you failed to give written notification of your
intention to set off monies against our account and we will not accept this
set-off.
Furthermore, you have failed to provide us with any details regarding this
claim/you have not given us the opportunity to view or rectify alleged
defective work and we again will not accept your claim.
Please reinstate these monies into our account immediately or we will
have no alternative but to seek redress through the contract.
Yours truly,
The Subcontractor
97
Standard Forms for Subcontractors
Note F27
Re: Failure to Advise of and/or Pay Sums Included in Certificates
To be used when main contractor fails to advise of sums included in
certificates.
To be used when **fourteen days have expired from the issue of the
certificate.
To indicate time at which point cash flow is being affected by claims.
98
Financial
Memo F28
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Failure to Advise of and/or Pay Sums Included in Certificates
We understand that the architect’s certificate nr ……………… was issued
to and received by you **14 days ago and to that extent we are
concerned that you have not advised us of the amounts included within
that certificate which are due to us.
Please furnish us with written details of amounts included within valuation
nr ………………/certificate nr ………………
You have not advised us of any deductions from our application
nr ……………… and we therefore conclude that our last claim for
payment is to be paid in full.
If we do not hear from you within **five days of the date of this letter then
we will have no recourse but to write directly to the architect/engineer
explaining the situation and requesting that payment be made directly.
In doing so we will furnish him with a detailed statement of our work
carried out to date.
Yours truly,
The Subcontractor
99
Standard Forms for Subcontractors
Note F29
Re: Letter to Employer – Non-Payment
To be used when the main contractor fails to pay in accordance with
contract period or agreed schedule.
100
Financial
Memo F30
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Non-Payment of Sums Certified
We are writing to confirm that we contend that you have failed and
continue to fail to pay us monies due and included in certificate
nr ……………… within the periods set out in the contract/our agreed
schedule of payment dates.
We have decided to write directly to the employer to advise him of the
current situation requesting that a direct payment be made to us.
We will be sending a detailed statement of works carried out to date
and sums due to us to the client for his consideration, approval and
payment.
We further advise that, as a result of your failure to pay monies included
in certificate nr ………………, we consider that you are in breach of
contract and we are taking all necessary steps to recover our entitlement
under contract.
Yours truly,
The Subcontractor
101
Standard Forms for Subcontractors
Note F31
Re: Letter to Employer – Non-Payment
To be used when the main contractor fails to pay in accordance with
contract period or agreed schedule.
102
Financial
Memo F32
To: Employer/Architect Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Letter to Employer – Non-Payment by Main Contractor
We are writing to you directly to confirm that the main contractor Messrs
……………… have failed to pay us monies due and included in architect’s
certificate nr ……………… within the periods set out in the contract/an
agreed schedule of payments which was set up at the start of our contract.
Having exhausted all efforts with the main contractor we have no alternative
but to write to you to seek direct payment as permitted by our subcontract
with Messrs ………………, in particular **Clause 11.
We enclose a detailed statement of works carried out to date and sums due
to us from the main contractor and note that there has been no deduction
made from our claim or notification of any deduction to be made. We are
anxious to carry on the works under our existing contract. However we
further advise that, as a result of the main contactor’s failure to pay
monies included in certificate nr ………………, we consider that they are
in breach of contract and we are taking all necessary steps to recover our
entitlement under contract.
Yours truly,
The Subcontractor
103
Standard Forms for Subcontractors
Note F33
Re: Interest on Late Payment
To be used as soon as it is evident that the main contractor has received
the architect’s certificate and that monies included in that certificate and
due to the subcontractor have not been paid.
To be used after any incidence of late payment particularly where sums
involved are large.
104
Financial
Memo F34
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Interest on Late Payment
Further to our earlier memos advising you of non-payment of
valuations/underpayment in valuations.
Please be advised that without prejudice to other rights and remedies
which we may pursue we consider that we are now entitled to claim for
interest on amounts included in certificate nr ……………… for which we
have not been paid.
We will assess the interest due on the basis of current bank lending
rates/agreed rates.
We will present our calculation and claim in our next valuation.
Yours truly,
The Subcontractor
105
Standard Forms for Subcontractors
Note F35
Re: Request for Release of Retention
To be used one month before the end of defects liability period is reached.
Diaries should be marked twelve months ahead to remind accounts
surveyors of due date for release of retention.
106
Financial
Memo F36
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Request for Release of Second Moiety of Retention
We write to advise that the period of maintenance/defects liability period
is due to expire on ………………
We would be pleased if you would arrange to have the second moiety of
retention on that date.
Yours truly,
The Subcontractor
107
Standard Forms for Subcontractors
Note F37
Re: Request for Release of Retention
To be used as soon as the end of defects liability period is reached.
Diaries should be marked twelve months ahead to remind accounts
surveyors of due date for release of retention.
108
Financial
Memo F38
To: The Main Contractor Reference: ………………
From: The Subcontractor Project Name/Number: …………
Date: ………………
Re: Request for Release of Second Moiety of Retention Reminder
We write to advise that the period of maintenance/defects liability period
has now expired.
Please arrange to have the second moiety of retention released immediately.
Yours truly,
The Subcontractor
109
110
Section 3: Document and Information Control
112
Table of Document Control Forms and Notes
Reference Nr Title Page Nr
I2 Daywork Sheets Issue Log 115
I4 Daywork Sheets – Request for Return
of Submitted Sheets 117
I6 Information Received from Third Party 119
I8 Drawing Register Incoming 123
I10 Drawing Register Outgoing 125
I12 Schedule of Information Required 127
I13 Schedule of Information Required 128
I15 Site Diary 133
I17 Request for Information 135
I19 Electronic Mail Register Issue Log 137
I21 Two Week Look Ahead Programme 139
I23 Purchasing List 141
113
Standard Forms for Subcontractors
Note I1
Re: Daywork Sheets Issue Log
To be issued with all dayworks attached and submitted to the main con
tractor in the week following the week in which dayworks are carried out.
To allow the main contractor time to incorporate figures/variations in his
valuations to clients to cover this work item.
To determine early on the main contractor’s willingness to accept properly
documented and executed dayworks.
To establish entitlement as early as possible.
114
Document and Information Control
Memo I2
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Daywork Sheets Issue Log
Please find enclosed our daywork sheets numbers ………………/
………………, referenced ……………….
Item Description
a)
b)
c)
d)
Please return your signed copies for our records and costing as soon as
possible.
These priced dayworks will form part of our next and forthcoming
valuation submissions.
Yours truly,
The Subcontractor
115
Standard Forms for Subcontractors
Note I3
Re: Daywork Sheets Request for Return of Submitted Sheets
To be issued one week after submission and weekly thereafter until all
sheets returned.
This to be done to illustrate the main contractor’s response, particularly
where sheets are not signed or are ignored or are unfairly treated.
To support a claim if necessary at a later date.
116
Document and Information Control
Memo I4
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Daywork Sheets – Request for Return of Submitted Sheets
Further to our memorandum I2, dated ………………, we write to request
the return of our daywork sheets signed or commented upon in order that
we may include these in our forthcoming valuation. The outstanding
sheets are as follows:
Item Date Submitted Description Cost e
a)
b)
c)
d)
In the meantime, given that we have received no reply, we will apply for
all dayworks in full as though they have been agreed by you.
Please return your signed copies for our records as soon as possible.
Yours truly,
The Subcontractor
117
Standard Forms for Subcontractors
Note I5
Re: Information Received from Third Party
To be issued immediately upon receipt of any information from third
parties.
Not to be acted upon unless instructed by the main contractor or
unless there is an instruction of overriding authority, e.g. Garda, ESB,
for emergency purposes.
118
Document and Information Control
Memo I6
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Information Received from Third Party
Please find enclosed information received from Messrs ………………
We are taking this as “for information purposes only” but note that, should
this information become an instruction from you, it will affect our works
in the following way:
a)
b)
c)
or
will not affect our works in any way.
We would be pleased to receive your immediate written confirmation that
the information documentation referred to/enclosed meets your approval
and can be used by us in progressing the works and/or preparing our own
submittal information and/or preparing our contract programme.
We are unable to proceed on the basis of the information referred to above
without your written instruction covering these issues.
In order to mitigate delays to the programme and in order to minimise any
possible costs we would be pleased to receive your instructions.
119
Standard Forms for Subcontractors
We will advise you of the cost and time effect upon receipt of your
instructions.
Please issue your instructions.
Yours truly,
The Subcontractor
120
[Blank]
121
Standard Forms for Subcontractors
Note I7
Re: Drawing Register Incoming
To be issued at least monthly.
To ensure that information being used is current and correct.
To ensure that the main contractor takes responsibility for such assurance.
122
Document and Information Control
Memo I8
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Drawing Register Incoming
Please find enclosed our most current drawing registers/schedules dated
………………, sheet nrs. …………./……………/…………. etc. Please
confirm that these are the most recent issues of drawings to date.
We include drawings received from all parties including nominated
subcontractors/domestic subcontractors/third parties/statutory bodies and
so on.
Should you find that you have issued drawings which do not appear on
these schedules please send us the current drawings.
Should you find that drawings which appear on these schedules have
been superceded please send us the correct drawings immediately for our
records and action.
Should you find that drawings which appear on these schedules are
irrelevant, e.g. from third parties, please let us know and we will discard
them.
Yours truly,
The Subcontractor
123
Standard Forms for Subcontractors
Note I9
Re: Drawing Register Outgoing
To be issued at least monthly.
To ensure that information being used is current and correct and that the
main contractor is aware of all information provided and cannot say
otherwise at a future time.
To be used for as-builts and working drawings.
124
Document and Information Control
Memo I10
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Drawing Register Outgoing
Please find enclosed our most current drawing submittal register dated
………………, sheet nrs …………./…………./…………. etc.
Please confirm that you have received these most recent issues of
drawings to date.
Should you find that you have not received any of the issued drawings
which appear on this schedule please advise us and we shall send the
correct drawings immediately for your records and action.
Yours truly,
The Subcontractor
125
Standard Forms for Subcontractors
Note I11
Re: Schedule of Information Required
To be submitted as soon as contract is awarded and as early as possible
into the project.
To be prepared jointly with own QS and site manager etc., studying all
drawings specifications and estimators’ notes.
To put pressure on the main contractor/design team to get all information
at the appropriate time.
To be prepared in conjunction with own programme dates or agreed dates
if using the main contractor programme.
To set foundation for delay claim for lack of or delay in provision of
information.
To be used to request architectural, structural and for services installation
queries, wherever interface or lack of detail exists or may occur.
126
Document and Information Control
Memo I12
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Schedule of Information Required
Please find enclosed our schedule of information required, reference
………………, dated ………………
Please provide the information requested by the dates shown which are in
accordance with your programme/the agreed programme/our programme
reference ………………, dated ………………
Should you have any comments on the attached or require clarification
of any of the issues raised please let us know in order that we may take
necessary action.
Yours truly,
The Subcontractor
127
Form I13: ARCHITECTURAL
Project Name:…………………
SCHEDULE OF INFORMATION REQUIRED
Project Nr:……………… Subcontractor Ltd
Schedule Nr:………………
Date:……………
Ref. Description of Information Planned Latest Date Ref. Comments
Required ARCHITECTURAL Start Date Received Nr
Date Req’d
1
2
3
4
5
6
128
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Form I13: STRUCTURAL
Project Name:……………………
SCHEDULE OF INFORMATION REQUIRED
Project Nr: ………………… Subcontractor Ltd
Schedule Nr:…………
Date:………………
Ref. Description of Information Planned Latest Date Ref. Comments
Required STRUCTURAL Start Date Received Nr
Date Req’d
1
2
3
4
5
6
129
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Form I13: MECHANICAL
Project Name:…………………
SCHEDULE OF INFORMATION REQUIRED
Project Nr:……………… Subcontractor Ltd
Schedule Nr:………………
Date:……………
Ref. Description of Information Planned Latest Date Ref. Comments
Required MECHANICAL Start Date Received Nr
Date Req’d
1
2
3
4
5
6
130
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Form I13: ELECTRICAL
Project Name:…………………
SCHEDULE OF INFORMATION REQUIRED
Project Nr:……………… Subcontractor Ltd
Schedule Nr:………………
Date:……………
Ref. Description of Information Planned Latest Date Ref. Comments
Required ELECTRICAL Start Date Received Nr
Date Req’d
1
2
3
4
5
6
131
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Standard Forms for Subcontractors
Note I14
Re: Site Diary
Every contract, no matter what size, should maintain a site diary.
These sheets are excellent for recording events as they occur and for use
in the preparation of claims as necessary.
To be completed by site foreman and copied and issued by post or e-mail
to head office every day.
To be reviewed by the QS and senior management to extract variations
delays etc.
To be filed on site in A4 lever arch file.
132
Subcontractor Ltd Form I15: Daily Site Diary
Project Nr: Job: Day: Date:
Weather: T° am = T° pm = Rain/Sunshine/Wind/Snow/Hail
Labour Subcontractor Plant on Plant on
on Site Labour Site Hired Site owned
Total number on site today =
Activities Underway:
Instructions/Variations Received:
Drawings Issued/Received:
By No. Rev. By No. Rev. By No. Rev. By No. Rev.
Delays & Disruption:
What Happened Effect Time
Significant Events:
Recorded By :
Standard Forms for Subcontractors
Note I16
Re: Request for Information
To be used after the original and schedule of information (see Form I13)
has been raised.
To be used throughout contract to completion.
To be completed by site foreman/QS/contracts manager whenever
information supplied is inadequate or in need of clarification.
To be dated on sending and when reply is received, the form must be
completed and dated.
To be filed on site in A4 lever arch file.
To be sent to QS for variations and time extension review.
To be cross-referenced to agreed programme for dates required and task
identification.
134
SUBCONTRACTOR Ltd
Form I17: REQUEST FOR INFORMATION NO.: 000
Project Name: ……………………… Project Nr: …………
Issued to: Fax/E-mail Cc. to: Fax/E-mail
1 1
2 2
3 3
4 4
Further to issue of our Schedule of Information Required, dated…………, we request
the following additional information in order to assist us in meeting our programmed
target dates:
Ref. Task Information Required Date Required Date Received
01
02
03
04
05
06
07
08
09
10
11
12
Requested by: ……………………… Issue Date: …………
135
Standard Forms for Subcontractors
Note I18
Re: Electronic Mail Register Issue Log
With the advent of e-mail it is a good idea to, at least once monthly, issue
a log of all e-mail received in that month to the main contractor to ensure
that all intended mail has been received.
To allow the main contractor to ensure that all information is passed on.
To identify where information is not received on time.
136
Document and Information Control
Memo I19
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Electronic Mail Register Issue Log
Please find below our most current e-mail registers/schedules.
Please confirm that these are the most recent issues of e-mail to date.
E-mail Reference Date Received Subject
E-mail Reference Date Issued Subject
Yours truly,
The Subcontractor
137
Standard Forms for Subcontractors
Note I20
Re: Two Week Look Ahead Programme
To be produced fortnightly in relation to the contract programme.
To be produced by QS and site foreman.
To identify materials required in advance to maintain the programme.
To identify labour resources required in advance to maintain the
programme.
To identify plant resources required in advance to maintain the
programme.
To protect against causing delays.
To organise the workforce on other contracts as well as this.
To identify where there may be delays and to attempt to prevent same or
to enable early advice to the main contractor.
138
Project Name: ______________ Subcontractor Ltd
Form I21: Two Week Look Ahead Programme
Project Nr: ________ Month: ________
Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Item Activity Day M T W T F S S M T W T F S S M T
Date
139
Standard Forms for Subcontractors
Note I22
Re: Purchasing List
To be produced at the beginning of the contract on receipt of programme
of works.
To be produced by QS and site foreman.
To identify materials required in advance to maintain the programme.
To identify labour resources required in advance to maintain the
programme.
To identify plant resources required in advance to maintain the
programme.
To protect against causing delays.
To organise workforce on other contracts as well as this.
To identify where there may be delays and to attempt to prevent same or
to enable early advice to the main contractor.
To identify where there are long lead delivery issues to enable early
advice to the main contractor.
To be monitored daily by QS and Foreman until all resources are on site.
140
Form I23
Project Name:…………………
Project Nr:……………… PURCHASING LIST Subcontractor Ltd
Date:…………… List Nr:………………
Ref. Item Ordered Date Supplier Tel. Nr Date Delivery Status
Required Date
1
2
3
4
5
6
7
8
141
9
10
11
12
13
14
15
16
17
18
19
20
142
Section 4: Site Matters Management
144
Table of Site Matters Forms and Notes
Reference Nr Title Page Nr
SM2 Abnormal Hazardous Operations 147
SM4 Confirmation of Verbal Instruction 149
SM6 Confirmation of Verbal Instruction Reminder 151
SM8 Confirmation of Adequacy of
Information Received from Others 153
SM10 Confirmation of Adequacy of
Information Received Reminder 157
SM12 Suitability of Previous Works/Backgrounds 159
SM14 Suitability of Previous
Works/Backgrounds Reminder 161
SM16 Request for Approval to Proceed –
Interface Trades 163
SM18 Completion of Work Stages 165
SM20 Completion of Work Stages Reminder 167
SM22 Damage to Work by Others 169
SM24 Completion of Rectification Work 171
SM26 Request for Approval to Proceed to Meet
Programme 173
SM28 Information Received from Third Party 175
SM30 Repairs to Damaged Works –
Confirm Verbal Instruction 179
SM32 Notice of Materials Delivery 181
SM34 Notice of Materials Delivery Turned
Away – Cost of Reordering/Redelivery 183
SM36 Notice of Reordered Material Delivery 185
SM38 Confirmation of Receipt of Instruction 187
SM40 Submission of Check Sheets/Test Results 189
SM42 Submission of Check Sheets Register/Test
Results Register/Log 191
SM44 Completion of Snags 193
SM45 Inspection and Check Sheets 194
145
Standard Forms for Subcontractors
Note SM1
Re: Abnormal Hazardous Operations
To be used where operations are instructed which were not known at time
of tender.
Where such operations were known at time of tender any additional
premiums which may be required for insurance purposes are the
subcontractor’s liability.
To be sent at least **ten days prior to commencement of operations to
give the main contractor sufficient notice of costs.
146
Site Matters
Memo SM2
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Abnormal Hazardous Operations
Further to your instruction to carry out the following works, it is our
intention to commence these operations as detailed below. (Date to be
given must be at least **ten days from date of memorandum.)
Description of Work Proposed Start Date
We are in the process of mobilising resources to carry out your instruction.
Please find enclosed our risk assessment and method statement for this
operation.
These works constitute abnormal hazardous operations in our opinion and
we are required to advise our insurers and seek appropriate cover.
This may result in additional costs which we shall pass on to you as an
extra to the contract unless you are willing to cover these operations under
your own policies and provide us with confirmation of cover.
If, as a result of the possibility of additional costs arising, you do not wish
us to proceed please advise us by return.
Yours truly,
The Subcontractor
147
Standard Forms for Subcontractors
Note SM3
Re: Confirmation of Verbal Instruction
To be used immediately upon receipt of verbal instruction.
To be sent to the main contractor within **5 days of receipt of verbal
instruction.
To be used prior to carrying out any verbally instructed works of any kind
unless they are of an emergency or safety nature.
148
Site Matters
Memo SM4
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Confirmation of Verbal Instruction
We acknowledge receipt of your verbal instruction given on ………… by
your Mr/Ms ………… to our Mr/Ms ………… to carry out the following
works.
Item Description
a)
b)
c)
d)
As requested we intend to carry out theses works on the ……………/
immediately and we would appreciate your written confirmation of this
verbal instruction.
If we do not receive contradictory written instruction prior to the date of
execution we shall proceed as though a written instruction has been issued
to cover this verbal request.
Yours truly,
The Subcontractor
149
Standard Forms for Subcontractors
Note SM5
Re: Confirmation of Verbal Instruction Reminder
To be used **five days after issue of SM4.
To be written to indicate that, whilst verbal instructions will be taken,
proper written confirmation is required.
To note that **five days have passed and no written dissention has been
received, thereby conferring that the verbal instruction is deemed to be in
writing.
To be written to indicate that written instructions permit faster reaction
time as contractually subcontractors do not have to act immediately upon
receipt of verbal instructions but could wait for the **ten days to pass
prior to acting.
150
Site Matters
Memo SM6
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Confirmation of Verbal Instruction Reminder
Further to our memorandum SM4, dated ………………, we write to
confirm that, as we have not yet received written confirmation of your
verbal instructions regarding the items listed below and as **five days
have now passed since the verbal instruction was given, we consider that
these verbal instructions are now deemed to be in writing.
Item Description
a)
b)
c)
d)
Please note that we would prefer written instructions as they permit us to
act immediately upon receipt, whereas verbal instructions do necessitate
written confirmation by ourselves and final confirmation by you.
Yours truly,
The Subcontractor
151
Standard Forms for Subcontractors
Note SM7
Re: Confirmation of Adequacy of Information Received from Others
To be issued immediately upon receipt of information.
To record the date of receipt and to let the contractor know that they are
equally responsible for the accuracy and acceptance of information.
The main contractor is responsible for overall coordination unless the
subcontractor has agreed to and is being paid for coordination.
To preserve rights.
152
Site Matters
Memo SM8
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Confirmation of Adequacy of Information Received from Others
Please find enclosed copies of …………………… information/docu
ments/details direct from Messrs ………………
We acknowledge receipt of the following …………… information/docu
ments/details direct from Messrs ………………
These documents were received by us on the ………………
Item Description of Document/Information Received
a)
b)
c)
d)
We would be pleased to receive your immediate written confirmation that
the documentation referred to/enclosed meets your approval and can be
used by us in progressing the works and/or preparing our own submittal
information and/or preparing our contract programme.
We are unable to proceed on the basis of the information referred to above
without your written instruction covering these issues.
In order to mitigate delays to the programme and in order to minimise any
possible costs we would be pleased to receive your instructions.
153
Standard Forms for Subcontractors
We will advise you of the cost and time effect upon receipt of your
instructions.
Yours truly,
The Subcontractor
154
[Blank]
155
Standard Forms for Subcontractors
Note SM9
Re: Confirmation of Adequacy of Information Received Reminder
To be issued no later than one week after SM8 and weekly thereafter until
confirmation or rejection received.
To remind the main contractor that there is a possibility of them creating
an untenable situation for themselves, possible delays to the works and
that they are responsible for the accuracy of information.
The main contractor is responsible for coordination unless the subcontractor
has agreed to and is being paid for coordination.
To preserve rights.
156
Site Matters
Memo SM10
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Confirmation of Adequacy of Information Received Reminder
Further to our memorandum SM8, dated ………………, we write to
remind you that we await your reply.
It is imperative that we receive your immediate written instructions
concerning these issues and how we are to proceed in order to prevent
any possible delay or conflict from arising. The items in question are as
follows:
Item Description of Document/Information Received
a)
b)
c)
d)
Any further delay in responding on your part will/may cause delays to our
works and to those of follow-on trades and we may have no recourse but
to charge any additional and unforeseen costs to your account.
Yours truly,
The Subcontractor
157
Standard Forms for Subcontractors
Note SM11
Re: Suitability of Previous Works/Backgrounds
To be issued immediately upon identifying that previous backgrounds are
unacceptable or will cause added expense (e.g. more dubbing out for
plastering/packing or shimming to level roof trusses).
To be used particularly if the previous background’s poor quality will
reflect upon finished quality of own product (e.g. carpet/vinyl).
To preserve rights.
To place onus on the main contractor for early release of information and
coordination.
To be used in conjunction with inspection check sheets, see SM45.
158
Site Matters
Memo SM12
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Suitability of Previous Works/Backgrounds
We write to advise you that it is our opinion that the previous work surfaces
in the following areas/locations are not suitable/complete to allow our
works to proceed and we would appreciate your written confirmation on
and instructions concerning these areas in order to mitigate any delay.
Item Area/Location Work Affected Reason
a)
b)
c)
d)
We would be grateful to receive your earliest response to enable us to
proceed/reprogramme our works and minimise delay and costs.
Yours truly,
The Subcontractor
159
Standard Forms for Subcontractors
Note SM13
Re: Suitability of Previous Works/Backgrounds Reminder
To be issued not more than **five days after SM12 or in a time period
which reflects the status and conditions of site works; if urgent send two
days after SM12, for example.
To preserve rights.
To place onus on the main contractor for early release of information and
coordination.
160
Site Matters
Memo SM14
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Suitability of Previous Works/Backgrounds Reminder
Further to our memorandum SM12, dated ………………, regarding the
above.
Please note that we have had no reply to the above memo and, in order to
prevent further/possible delay to the programme, would you please
confirm that we should commence/continue our works all in accordance
with earlier instructions/agreed programme/work schedules/sequences
and that this is acceptable and complies with your requirements.
Alternatively please instruct us on how to proceed.
Should any additional or abortive costs result from these instructions we
shall advise you as soon as they become reasonably apparent.
Yours truly,
The Subcontractor
161
Standard Forms for Subcontractors
Note SM15
Re: Request for Approval to Proceed – Interface Trades
To be issued in order to ensure that interface trades are complete prior to
burying or closing up.
To preserve rights.
To make the engineer responsible for checking previous trades.
To prevent possible abortive work or redoing work.
To place onus on the main contractor for early release of information and
coordination.
Inspection check sheets may be used here (see SM45).
162
Site Matters
Memo SM16
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Request for Approval to Proceed – Interface Trades
Please confirm that all preceding trades have completed their works and
that all pipe conduits or any works passing through or to be contained or
integrated within our works in the following areas can be buried/built
in/closed up.
Area/Location/Wall Date our Works to Proceed
a)
b)
c)
d)
If you wish to carry out joint inspections we shall be pleased to visit the
site with you at your convenience.
Yours truly,
The Subcontractor
163
Standard Forms for Subcontractors
Note SM17
Re: Completion of Work Stages
To be issued where works have to be carried out in stages, for example
first fix drylining and second fix drylining, and where other trades inter
face between stages.
To preserve rights.
To make the main contractor foreman/engineer take responsiblilty for
checking previous trades and instructing that all works are complete.
To prevent possible abortive work or redoing work, which is in everyone’s
interest.
164
Site Matters
Memo SM18
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Completion of Work Stages
We are pleased to advise that we have completed our works up to the
first/second/third/final stage in the following areas on the dates noted.
Area/Location/Wall Stage Date our Works Complete Permit to Proceed
a)
b)
c)
d)
e)
We would be pleased to receive your earliest confirmation that our works
have been completed to your satisfaction.
If you wish to carry out joint inspections we shall be pleased to visit the
site with you at your convenience.
Note – where first second or third stage is incomplete, the following
paragraph is included:
Please confirm by return when we are able to proceed with the next stage of
our works and that any follow-on trades passing through to be contained in
or buried in or integrated within our works have been installed/are complete.
Yours truly,
The Subcontractor
165
Standard Forms for Subcontractors
Note SM19
Re: Completion of Work Stages Reminder
To be issued not more than **five days after SM18 or in a time period
which reflects the status and conditions of site works; if urgent send two
days after SM18, for example.
To preserve rights.
To make the main contractor’s foreman/engineer responsible for checking
previous trades.
To prevent possible abortive work or redoing work.
To cover you in case someone else causes damage to preceding trades
work before you proceed.
To be issued where the programme is in jeopardy.
166
Site Matters
Memo SM20
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Completion of Work Stages Reminder
Further to our memorandum SM18, dated ………………, we write to
advise that we have had no reply to date and intend to continue our works
in order to complete our works productively and in accordance with your
programme.
Areas in question, as per our memorandum SM18, are listed below:
Area/Location/Wall Final Stage
a)
b)
c)
d)
e)
Please confirm by return that you have no objection to this course of
action.
Yours truly,
The Subcontractor
167
Standard Forms for Subcontractors
Note SM21
Re: Damage to Own Work by Others
To be issued immediately on detection of damaged work.
To preserve rights.
To allow the main contractor to seek monies from the person who
damaged work.
Take dated photographs and submit with letter.
Advise where possible of person/persons/trade that caused damage.
168
Site Matters
Memo SM22
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Damage to Work by Others
Further to our memoranda SM18 and SM20, dated ……………… and
……………… respectively, we write to advise that previously completed
works have been damaged by other trades/Messrs …….....…… /persons
unknown.
The damages were caused to the following locations and we have
photographed the areas and attach copies for your records.
Area/location/Wall Damage Caused
a)
b)
c)
d)
e)
We would be pleased to receive your instructions to carry our repairs to
those areas affected which repairs will be carried out on a dayworks basis;
or
our price for carrying out repairs to these works is e………………. We
await your instruction to carry out remedial works.
Yours truly,
The Subcontractor
169
Standard Forms for Subcontractors
Note SM23
Re: Completion of Rectification Work
To be issued immediately on completion of repairs to damaged work.
To preserve rights.
To allow the main contractor to seek monies from person who damaged
work.
To make sure dayworks sheets are submitted quickly, use covering letter
and dayworks log memoranda I2 and I4.
170
Site Matters
Memo SM24
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Completion of Rectification Work
Further to our memorandum SM22, dated ……………, we write to advise
that works previously damaged by other trades/Messrs ………………
have been repaired.
The damaged works were repaired in the following locations.
Area/Location/Wall Repair Carried Out
a)
b)
c)
d)
e)
These works have been carried out in strict accordance with your
specification on an agreed price/dayworks basis and we shall submit
our daywork sheets to you within one week of the works having been
completed/include our price for these works with our next valuation.
Yours truly,
The Subcontractor
171
Standard Forms for Subcontractors
Note SM25
Re: Request for Approval to Proceed to Meet Programme
To be issued in order to establish entitlement and rights for extension of
time.
To be issued giving sufficient time for the main contractor to instruct.
To make the main contractor foreman/engineer responsible for delays if
any follow.
To reinforce the fact that previous stages of work are complete to your sat
isfaction and specification and the main contractor has not approved
same.
172
Site Matters
Memo SM26
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Request for Approval to Proceed to Meet Programme
We write to confirm that we are required by your instructions/programme,
dated ………………, to commence our works/the second stage/third
stage/final stage of our works in the following areas on the dates noted.
Area/Location/Wall Date our Works to Proceed
a)
b)
c)
d)
Please confirm that we may proceed/that the previous stages of our works
have been completed to your satisfaction as we have not received a
reply to our memoranda SM18 and SM20, dated ……………… and
……………… respectively.
Yours truly,
The Subcontractor
173
Standard Forms for Subcontractors
Note SM27
Re: Information Received from Third Party
To be issued immediately upon receipt of any information from third
parties.
Not to be acted upon unless instructed by the main contractor or
unless there is an instruction of overriding authority, e.g. Garda, ESB, for
emergency purposes.
174
Site Matters
Memo SM28
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Information Received from Third Party
Please find enclosed copies of information received from Messrs
………………
We are taking this for information purposes only but note that, should this
information be come an instruction from you, it will affect our works in
the following ways:
a)
b)
c)
or
will not affect our works in any way.
We would be pleased to receive your immediate written confirmation that
the information documentation referred to/enclosed meets your approval
and can be used by us in progressing the works and/or preparing our own
submittal information and/or preparing our contract programme.
We are unable to proceed on the basis of the information referred to above
without your written instruction covering these issues.
In order to mitigate delays to the programme and in order to minimise any
possible costs we would be pleased to receive your instructions.
175
Standard Forms for Subcontractors
We will advise you of the cost and time effect upon receipt of your
instructions.
Please issue your instructions.
Yours truly,
The Subcontractor
176
[Blank]
177
Standard Forms for Subcontractors
Note SM29
Re: Repairs to Damaged Works – Confirm Verbal Instruction
To be issued prior to carrying out the works.
To put on record the fact that the work cannot be measured.
To make the main contractor foreman/engineer responsible for instruction
and recovery of costs from others.
To be used in lieu of memorandum SM18/20 if required, or use SM18/20.
178
Site Matters
Memo SM30
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Repairs to Damaged Works – Confirm Verbal Instruction
We confirm having received your verbal instruction, dated
………………, requesting that we proceed to repair those areas of our
works which had been damaged by other trades.
We are now carrying out that instruction.
We would be pleased to receive your written confirmation of that verbal
instruction noting that, within **five days of the date of this letter,
the verbal instruction will be deemed in writing unless countered by
yourselves.
In the meantime we are preparing a written report with photographs for
your information and records on the damaged areas, the causes and the
remedial works required.
We shall submit this to you along with our daywork sheets/time/materials
record sheets and we trust that, given the nature of the work, you will
agree to reimburse us on this basis.
Yours truly,
The Subcontractor
179
Standard Forms for Subcontractors
Note SM31
Re: hrs Notice of Materials Delivery
To be issued where site is congested and problems may occur due to
access.
To be issued where attendances need to be booked ahead of deliveries.
To be issued giving the main contractor sufficient notice to provide
attendance.
To be used to put pressure on the main contractor to provide attendances
in order to facilitate programme.
To indicate, where necessary, when attendances are not provided thereby
causing delays.
180
Site Matters
Memo SM32
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: hrs Notice of Materials Delivery
We write to advise that in accordance with your requirements/programme
we have ordered the following materials/equipment:
a)
b)
c)
d)
e)
f)
These will be delivered to site on ………………/as agreed on the
……………….
We will require/will not require the use of craneage/hoisting facilities for
approximately …………. hours.
Please confirm that this is acceptable.
Please note that any delay to this delivery may impact on your programme.
Yours truly,
The Subcontractor
181
Standard Forms for Subcontractors
Note SM33
Re: Notice of Materials Delivery Turned Away – Cost of Reordering/
Redelivery
To be issued when previously agreed delivery times for materials are not
met by the main contractor.
To be used when materials are turned away by the main contractor repre
sentative immediately upon occurrence.
To be used to show delay.
182
Site Matters
Memo SM34
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Notice of Materials Delivery Turned Away – Cost of Reordering/
Redelivery
We write further to our memorandum SM32, dated ………………, to
confirm that materials/equipment delivered to site as agreed were not
off-loaded as a result of your instruction/congested load-out areas/
non-availability of hoist or crane facilities and were turned away.
As a result the cost and time implications of reordering/delivering these
goods will be monitored/evaluated and will be submitted to you in due
course.
Yours truly,
The Subcontractor
183
Standard Forms for Subcontractors
Note SM35
Re: Notice of Materials Delivery Turned Away – Time and Cost Impact
To be issued when previously agreed delivery times for materials are not
met by the main contractor.
To be used when materials are turned away by the main contractor repre
sentative immediately upon occurrence.
To be used to show delay.
To be used once reconfirmed delivery times are firmed up which impact
on programme and work on site.
184
Site Matters
Memo SM36
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: hrs Notice of Reordered Materials Delivery
Further to our memorandum SM34, dated ………………, we write to
advise that we have reordered/rescheduled the following materials/equip
ment previously ordered but turned away:
a)
b)
c)
d)
e)
f)
These will be delivered to site on ………………/as agreed on the
………………
We will require/will not require the use of craneage/hoisting facilities for
approximately …………. hours.
Please confirm that this is acceptable.
There is a knock-on effect to our programme resulting from this event and
we will advise you of the time and cost impact under separate cover.
Yours truly,
The Subcontractor
185
Standard Forms for Subcontractors
Note SM37
Re: Confirmation of Receipt of Instructions
To be issued upon receipt of instruction.
To record the date of receipt (date on instruction may be different from
date of receipt).
To let the contractor know that assessment of time and costs will follow.
To preserve rights.
186
Site Matters
Memo SM38
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Confirmation of Receipt of Instruction
We acknowledge receipt of your instruction/direction/drawing as
follows:
Item Document Reference Date Received Description
a)
b)
c)
d)
We are proceeding with the works.
We will advise you, upon checking the content of the above, of any
ambiguities or cost or time effects or other implications and submit these
to you (if any) for your consideration and approval at the earliest possible
opportunity.
Yours truly,
The Subcontractor
187
Standard Forms for Subcontractors
Note SM39
Re: Submission of Check Sheets/Test Results
To be submitted as soon as work is checked or tested.
To be submitted to indicate that works are installed in accordance with
specification/good practice/instruction.
To record when works are completed and handed over in stages.
To protect against unwarranted or heavy handed snagging.
To verify works accepted and to ensure payment forthcoming in case of
later damage.
See Memo SM45 for sheets.
188
Site Matters
Memo SM40
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Submission of Check Sheets/Test Results
Please find enclosed our most current check sheet/test result sheet, dated
………………, sheet nrs. …………. /…………. /…………. etc.
The check sheets attached have been signed by your representative to
confirm that our works are in accordance with specification and are to
your satisfaction;
or
please return signed copies of these record sheets for our files if you are
satisfied with the works done/test results recorded.
Should you have any comments on the attached or are not satisfied with
any of the attached please let us know in order that we may take necessary
action.
Yours truly,
The Subcontractor
189
Standard Forms for Subcontractors
Note SM41
Re: Submission of Check Sheets Register/Test Results Register/Log
To be submitted regularly monthly at the latest to ensure the main contractor
is in possession of all records.
To be submitted to indicate that works are installed in accordance with
specification/good practice/instruction.
To record when works are completed and handed over in stages.
190
Site Matters
Memo SM42
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Submission of Check Sheets Register/Test Results Register/Log
Please find enclosed our most current check sheet/test result register/log,
dated ………………, sheet nrs. …………./…………./………….
Please confirm that you have received these most recent issues to date.
Should you find that you have not received any of the sheets which appear
on this schedule please advise us and we shall send the missing items
immediately for your records and action.
Yours truly,
The Subcontractor
191
Standard Forms for Subcontractors
Note SM43
Re: Completion of Snags
To be used upon completion of snags which were advised by the main
contractor.
Snags to be completed as soon as possible to allow release of final valua
tion or retention monies and to prevent the main contractor using these as
a reason for withholding monies.
192
Site Matters
Memo SM44
To: The Main Contractor Reference: …………
From: The Subcontractor Project Name/Number: …………
Date: ……………..
Re: Completion of Snags
Please find enclosed snag list reference ………………, dated
………………, reporting that all snags are now complete.
Please arrange to verify and sign off these lists at your earliest conven
ience.
Yours truly,
The Subcontractor
193
Standard Forms for Subcontractors
Note SM45
Re: Inspection and Check Sheets*
A selection of check sheets which can be modified to suit different trades.
To be issued to advise of previous backgrounds being unacceptable.
To be issued when work sections are complete.
To be issued to confirm that works are being carried out in accordance
with specifications.
To be used when surveys etc. are necessary prior to starting work or work
sections.
To be issued where main contractors are being stringent and require doc
umentation ISO.
To be issued as a matter of course to obtain agreement that works are
acceptable and to minimise snagging at a later date.
To encourage good discipline in own workforce in following specifications
and manufacturer recommendations.
To protect against future damage by others and to cover revisit charges.
*See Appendix
194
Appendix: Check Sheets
196
Table of Check Sheets
Subcontractor Ltd.
Title Page Nr
Blank Report Format 199
Excavation/Hardcore/Stone Fill/Earthworks 200
External Drainage 201
Fire Main/Water Main 202
Gas Main 203
Manholes 204
Internal Drainage 205
Concrete (Pre-Pour) 206
Concrete (Post-Pour) 207
Brickwork and Blockwork 208
Pre-cast Units: Frames 210
Joinery/Ironmongery 212
Metal Cladding Units 213
Stone Cladding Units etc. 214
Structural Steel and Metalwork 215
Roofing 216
Windows and Curtain Walling 217
Partitions and Drylining 219
Plasterwork and Rendering 220
Suspended Ceilings 221
Raised Floors 222
Hard Tiling 223
Floor Covering 224
Decoration 225
197
198
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Work Element Comment/Details Yes No Note OR n/a
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
199
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
EXCAVATION/HARDCORE/STONE FILL/EARTHWORKS
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Setting Out
Check of Underground Services
Width/Depth of Trench/Pit
Formation Level Approval
Formation Bearing Approval
Grade of Fill
Plain Concrete Fill Specification
Material Data Sheet Specification
Supplier Product
Compaction
Final Gradings
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
200
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
EXTERNAL DRAINAGE
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Trench Depth and Width
Bed Type and Thickness
Pipe Type
Line
Level
Gradient
Test
Test Certificate Reference
Pipe Haunching/Surrounding
Thickness
Compaction
Backfill
Type
Compaction
Lean Mix Grade
Depth Cover
Cleaned Out
On Drawing
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
201
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
FIRE MAIN/WATER MAIN
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Trench Depth and Width
Level of Trench Bottom
Bed Type and Thickness
Surround Type and Thickness
Pipe Type:
Size
Line
Level
Falls
Joints
Thrust Blocks
Pressure Test
Test Cert. Ref.
Accessories: Hydrants/Covers/
Depth Marker
Valves/Covers
Meter Identification
Marker Post Locations
Cleaned Out
On Drawing
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
202
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
GAS MAIN
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Trench Depth and Width
Level of Trench Bottom
Bed Type and Thickness
Surround Type and Thickness
Pipe Type:
Size
Line
Level
Falls
Joints
Thrust Blocks
Pressure Test
Test Cert. Ref.
Accessories: Hydrants/Covers/
Depth Marker
Valves/Covers
Meter Identification
Marker Post Locations
Cleaned Out
On Drawing
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
203
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
MANHOLES
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Location
Set-out
Size
Materials
Steps Irons
Benching
Plastering: Internally
Externally
Cover Frame: Level
Sea
Duty
Manhole Sealing
Pressure Test
Test Cert. Ref.
Accessories: Hydrants/Covers/
Depth Marker
Valves/Covers
Meter Identification
Marker Post Locations
Cleaned Out
On Drawing
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
204
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
INTERNAL DRAINAGE
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Trench Depth and Width
Bed Type and Thickness
Pipe Type
Line
Level
Gradient
Test
Test Certificate Reference
Pipe Haunching/Surrounding
Thickness
Compaction
Backfill
Type
Compaction
Lean Mix Grade
Depth Cover
Cleaned Out
On Drawing
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
205
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
CONCRETE (PRE-POUR)
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Concrete Mix
Cube Reference
Setting Out (Line & Level)
Quality/Type of Forms
Propping Adequate
Formwork Line
Formwork Level
Re-Bar: State Cover
Fixing: Tying Wire
Chairs
Spacings: State Centres
Starter Bars
Cleanliness
Openings
Cores
Water Bar
Fixings/Abbey Slot/Bolts
Pipes in Place
Waterstop
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
206
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
CONCRETE (POST-POUR)
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Level
Line
Plumb
Surface Finish
Class of Finish Specified
Compliance
Curing Method
Joints
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
207
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
BRICKWORK AND BLOCKWORK
(part 1)
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Approved Sample in Place
Load-Bearing: Yes/No
Fair-Faced: Yes/No
Materials
Brick/ Block Type: Finish
Mortar Mix: Site Mixed
Trowel Ready
Supplier
Dockets Attached
Set Out
Line
Coursing: Brick Rules
Opes: Doors
Windows
Services
Support System
In Place in Line & Level
Type
Grade of Steel
Wall Ties
Type
Vertical Spacing
Horizontal Spacing
Around Openings Spacing
Closed Up
Soldier Courses
Patterns Correct Symmetrical
208
BRICKWORK AND BLOCKWORK
(part 2)
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment/Detail Yes No Note OR n/a
D.P.C
Cavity Trays
Reinforcement
Contraction Joints
Expansion Joints
Wall Insulation
Clean Cavities
Cills, Copings
Brick, Block Specials
Finish/Cleanliness
Pointing
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
209
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
PRE-CAST UNITS: FRAMES
(part 1)
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
Sub-Contractor/Manufacturer Drawing Nr: ……… Rev Nr: ………………
Sub-Contractor/Manufacturer Drawing Approved Yes …… Date: ………
No …… Date: ………
Approved Sample in Place?
Is Preliminary Off-Site Testing Required?
If Required, have you Received a Satisfactory Test Report?
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Starter Bars and Links
Bearing Support
Bed Thickness
Handling/Lifting Methods
Set-Out: Line
Level
Thickness
Length
Width
Squareness
Edge-Details
Steel Edge Supports/Angles
Line
Level
Camber
Location/Dimensions of Service
Opes
Restraining Dowels
Brackets
Fixings
Joint Width
Joint Fillers/Sealants
Finish / Visual Appearance
210
PRE-CAST UNITS: FRAME
(part 2)
DRAWING CHECKLIST
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Are service opes in accordance
with builder’s work information?
Are other opes provided for?
Is standard of finish to all
surfaces clearly defined?
Is finish suitable for following
trades:
1
2
3
Is camber of beam, slab units
defined?
Is sequence of erection defined?
Is handling of units defined?
Is the P.C. manufacturer
responsible for the erection of
same, including craneage?
Have the manufacturer’s working
drawings been approved by
the structural engineer/design
team?
Is system of propping clearly
defined and responsibility
detailed?
Has screed weight and thickness
been coordinated with units,
floor finishes etc.?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
211
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
JOINERY/IRONMONGERY
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Approved Sample in Place?
Set-Out: Line
Level
Materials: Type
Quality
Ironmongery
Is Timber Primed?
Site Workmanship/Quality
Fire Rating: Checked
Fire Certification
Finish/Visual Appearance
Does the Finished Work Require
Protection?
Protection in Place
Glazing Agreed
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
212
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
METAL CLADDING UNITS
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
Sub-Contractor/Manufacturer Drawing Nr: ………… Rev Nr: …………………
Sub-Contractor/Manufacturer Drawing Approved Yes ……… Date:………
No ………. Date:………
Approved Sample in Place?
Is Preliminary Off-Site Testing Required?
If Required, have you Received a Satisfactory Test Report?
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Handling/Lifting Methods
Set-Out: Line
Level
Secondary Support System
DPC/Flashing
Brackets/Fixings
Cladding Units
Dimensional Accuracy: Line
Level
Opes: Doors/Windows/Services
Insulation
Joints: Widths
Fillers, Sealants, Compatibility
Finish/ Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
213
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
STONE CLADDING UNITS etc.
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
Sub-Contractor/Manufacturer Drawing Nr: ………… Rev Nr: …………………
Sub-Contractor/Manufacturer Drawing Approved Yes ……… Date: ………
No ………. Date: ………
Approved Sample in Place?
Is Preliminary Off-Site Testing Required?
If Required, have you Received A Satisfactory Test Report?
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Support Structure
Handling/Lifting Methods
Set-Out: Line
Level
Secondary Support System
DPC/Flashing
Brackets/Fixings
Cladding Units
Dimensional Accuracy: Line
Level
Opes: Doors/Windows/Services
Insulation
Joints: Widths
Fillers, Sealants, Compatibility
Finish/ Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
STRUCTURAL STEEL AND METALWORK
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: ..................
Manufacturer Drawing Nr: .................. Rev Nr: ..................
Manufacturer Drawing Approved Yes ……. Date: ..................
No ……. Date: ..................
Working Drawings Nr: .................. Rev Nr: ..................
Working Drawings Approved Yes ……. Date: ..................
No ……. Date: ..................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Shot Blasted
Primer
Off-Site Paint-Finish
Erection:
Line
Level
Plumb
Bolted Connections Complete
Site Welding Complete
Grouting Under Base Plates
Fire Proofing
Paint Finish
Joints: Widths
Fillers, Sealants, Compatibility
Finish/ Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
ROOFING
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Materials: Type
Colour
Profile
Laps and Sealants
Fixings
Opes/Upstands
Flashings
Fittings: Vents
Louvres
Rooflights
Others
Stacks, Flues
Insulation
Finish/ Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
216
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
WINDOWS AND CURTAIN WALLING
(part 1)
Project Nr: .................. Date: .................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
Sub-Contractor/Manufacturer Drawing Nr .................. Rev Nr: ..............
Sub-Contractor/Manufacturer
Drawing Approved Yes ……. Date: ..................
No …...... Date: ..................
Approved Sample in Place?
Is Preliminary Off-Site Testing Required?
If Required, have you Received a Satisfactory Test Report?
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Framing
Support Structure
Handling/Lifting Methods
Set-Out: Line
Level
Secondary Support System
DPC/Flashing
Brackets/Fixings
Aluminium Units
Dimensional Accuracy: Line
Level
Opes: Doors/Windows/Services
Insulation
Joints: Mitres
Glazing Type: Single
Double
Thickness
Lamination
Colour
Glazing Seals
Glazing Gasket
Obscuration/Tint
Handling /Lifting Methods
217
WINDOWS AND CURTAIN WALLING
(part 2)
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment/Detail Yes No Note OR n/a
Flashings, Cover Strips
Drainage
Joints: Widths
Junction to Other Works
Fillers, Sealants, Compatability
On-Site Testing
Finish, Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
218
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
PARTITIONS AND DRYLINING
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Set Out: Line
Level
Stud: Type/Material
Dimensions
Fixings
Opes
Plumb
Services: Installed
Tested
Insulation: Heat
Insulation: Sound
Joints: Scrimmed
Joints: Filled
Abutment to Other Finish
Expanded Metal Joints
Sheeting Material
Fire Rating
Finish/Visual Appearance
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
219
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
PLASTERWORK AND RENDERING
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Approved Sample in Place?
Internal or External
Plaster Type
Background Type
Dubbing Out, Polybond
Other Trades: First Fix Completed
Joint Locations Defined
Ceiling Level Defined
Plaster: Type
Locations/Line/Level/Plumb
Joint-Widths
Background Preparation (Keying
and Bonding)
No. of Coats
Are Specified Times Between
Coats Observed?
Finished Work: Line
Plumb
Surface Finish/Visual Appearance
Does Work Require Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
220
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
SUSPENDED CEILINGS
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Approved Sample in Place?
Ceiling Void Confirmed
Above Ceiling Services Completed
Mechanical Services Tested
Electrical Services Tested
Is Access Required For:
1. Commissioning
2. Maintenance
Hangers/Support: Fixing
No. per Area
Grid System: Fixings
Type
Colour
Level
Line
Tiles Type
Board Type
Access Points Provided
Light Fittings Framing
Other Electrical Fittings
Ventilation Grilles
Other Mechanical Fittings
Finish/ Visual Appearance
Is Protection Required?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
RAISED FLOORS
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Raised Floor Type/System
Approved Sample in Place?
Floor Void Confirmed
Handling (to be Agreed in
Advance)
Material Type
Galvanised
Set-Out Positions of Legs
Underfloor Services Completion
Underfloor Services Tested
Dustproofing Complete
Floor Void Cleaned Out
Adjustable Leg Adhesion
Mechanical Fixings In
Level/Rocking
Perforated Panels
Cut-Outs for Services
Access Positions Agreed
Self-Finished
Applied Finished
Finish/Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
HARD TILING
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Raised Floor Type/System
Approved Sample in Place?
Floor Void Confirmed
Handling (to be Agreed in
Advance)
Material Type
Galvanised
Set-Out Positions of Legs
Underfloor Services Completion
Underfloor Services Tested
Dustproofing Complete
Floor Void Cleaned Out
Adjustable Leg Adhesion
Mechanical Fixings In
Level /Rocking
Perforated Panels
Cut-Outs for Services
Access Positions Agreed
Self-Finished
Applied Finished
Finish/Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
FLOOR COVERING
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Approved Sample in Place
Compliance with Manufacturer
Recommendation
Levelling Compound
Beds and Backings
Moisture Content
Surface Finish Texture
Slip Resistance Agreed
Type of Joint Agreed
Adhesive & Primer Agreed
Setting Time Observed
Laying Conditions Approved
Floor Material: Type/Colour
Pattern Agreed
Method of Installation
Finish/Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
224
SUBCONTRACTOR LTD
CHECK SHEET
ELEMENT/TRADE
DECORATION
Project Nr: .................. Date: ..................
Drawing Nr: ..................
Revision Nr: ..................
Instruction Nr: ..................
Area of Operation: .....................................
% Complete on Checking: .................. %
Do the following elements comply with drawings and specification? (please tick)
Work Element Comment Yes No Note OR n/a
Approved Sample in Place
Compliance with Manufacturer
Recommendation
Background
Beds and Backings
Moisture Content
Preparation: Filling
Sanding
Material: Paint/Paper Reference
Colour/Pattern
No. of Coats
Preparation Between Coats
Dry Film Thickness (DFT)
Pattern Agreed
Method of Installation
Finish/Visual Appearance
Does the Finished Work Require
Protection?
Is it Protected?
Signed as Checked/Compliant Subcontractor's Representative
Date
Signed as Approved Main Contractor
Date
Comments:
225
226