Spo
Spo
Global Projects
Security classification: BP Internal
                                                   Organisation
 B01     Issued for Use                     Mike T Brown   18 Dec 2013 Michael Ho   18 Dec 2013   Mike T Brown   18 Dec 2013
 Rev     Reason for Issue                   Author         Date          Checked    Date          Approved       Date
                     Refresh Cycle Code (years) N/A               Expiry Date N/A
                         Retention Code (years) N/A               Delete Date N/A
 This document is copyright and shall not                                                                          Rev
 be reproduced without the permission of
 BP                                                                 GPO-EN-SPE-30256                               B01
                                                   Foreword
                   This document has been prepared in accordance with the BP
                   Standardisation Strategy. This document will be used in conjunction with
                   other standardisation initiatives to define the standardisation requirements
                   for equipment and components.
                   This is an interim issue of EP-GIS 30-256-1 pending formal ETP approval.
                   This GPO number has been allocated so that Projects use the same
                   document and Contractors start to see a consistent number on the
                   specifications.
                   This document will be removed from the GPO library as soon as this EP-GIS
                   is formally issued in the ETP Library.
                   It is intended that Contractors are provided with a version of this document
                   that shows the commentary text.
GPO-EN-SPE-30256
                                                   18 December 2013
                                        Engineering Technical Practice
                                                         Engineering
Specification for Contractor Instrumentation Installation Requirements
                                                      Table of Contents
                                                                                                                                           Page
1      Scope .................................................................................................................................... 5
2      Normative references............................................................................................................. 5
3      Terms and definitions............................................................................................................. 6
4      Symbols and abbreviations .................................................................................................... 7
5      Order of precedence .............................................................................................................. 8
6      Instruments............................................................................................................................ 8
       6.1    Scope of work ............................................................................................................. 8
       6.2    General....................................................................................................................... 9
       6.3    Piping flushing and hydrotesting ............................................................................... 10
       6.4    Hazardous areas....................................................................................................... 10
       6.5    Instrument location.................................................................................................... 11
       6.6    Instrument mounting ................................................................................................. 12
       6.7    Environmental protection .......................................................................................... 13
       6.8    Temperature instruments .......................................................................................... 13
       6.9    Pressure instruments ................................................................................................ 14
       6.10 Flow instruments....................................................................................................... 14
       6.11 Level instruments...................................................................................................... 16
       6.12 Weighing systems..................................................................................................... 17
       6.13 Fire and gas devices................................................................................................. 17
7      Valve installation.................................................................................................................. 18
       7.1    General..................................................................................................................... 18
       7.2    Control valves ........................................................................................................... 18
       7.3    Actuated block valves ............................................................................................... 18
8      Junction boxes, panels and enclosures................................................................................ 18
9      Instrument cabling and cable supports................................................................................. 19
       9.1    Cable tray and rack................................................................................................... 19
       9.2    Cable tray and rack installation requirements............................................................ 20
       9.3    Cable ........................................................................................................................ 20
       9.4    Penetrations.............................................................................................................. 23
       9.5    Cable glands............................................................................................................. 24
       9.6    Terminations ............................................................................................................. 25
       9.7    Markings ................................................................................................................... 25
                                                                Page 2 of 47                                            GPO-EN-SPE-30256
                                                                                                                         18 December 2013
Specification for Contractor Instrumentation Installation Requirements
List of Tables
                                                                 Page 3 of 47                                           GPO-EN-SPE-30256
                                                                                                                         18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                    Foreword
                           This Specification conforms to the BP Standardisation Strategy to transform GISs
                           into engineering technical specifications with no cross references to GPs.
                           At the date of publication, this Specification conforms to the Engineering Technical
                           Practices (ETPs) listed in the Bibliography and any approved deviations from these
                           ETPs.
                           This Specification together with other BP documents and project specific documents
                           defines the scope of supply for the equipment. The applicable BP and project
                           specific documents will be identified in the Purchase Order documentation.
                                                      Page 4 of 47                          GPO-EN-SPE-30256
                                                                                             18 December 2013
Specification for Contractor Instrumentation Installation Requirements
1 Scope
2 Normative references
       The following documents are referenced in one or more requirements in this document. For dated
       references, only the version cited applies. For undated references, the latest version of the referenced
       document (including any amendments) applies.
       Company documents
          EP-GIS 30-254-1              Specification for Contractor Instrument Design Requirements.
          GIS 06-602                   Specification for Coating and Painting of Supplier Equipment.
          GIS 12-159                   Specification for Electrical and Instrumentation Cable Glands (IEC).
          GIS 12-160                   Specification for Electrical and Instrumentation Cable Seals (NEMA).
          GIS 12-601                   Specification for Junction Boxes (IEC).
          GIS 12-602                   Specification for Junction Boxes (NEMA).
          GIS 30-251                   Specification for Instrument Tubing and Fittings - Metric Units.
          GIS 30-252                   Specification for Instrument Tubing and Fittings - Customary Units.
          GIS 30-253                   Specification for Field Instruments.
          GIS 36-320                   Material Specification for 22% Cr and 25% Cr Duplex Stainless Steel.
          GIS 64-021                   Specification for Gas Custody Transfer Measurement Package.
          GIS 64-022                   Specification for Liquid Custody Transfer Measurement Package.
                                                      Page 5 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
       Energy Institute
          Guidelines for the management, design, installation and maintenance of small bore tubing
          assemblies. 2nd edition, May 2013.
       NACE International
          NACE MR 0103                 Materials Resistant to Sulfide Stress Cracking in Corrosive Petroleum
                                       Refining Environments.
For the purpose of this Specification, the following terms and definitions apply:
       Armour
       Steel wire armour or wire braid incorporated in cable.
       Company
       BP p.l.c., an associate or subsidiary, or other organisation acting as owner, purchaser, or customer as
       designated in the Purchase Order.
       Computer floor
       Raised floor supported above a sub floor to allow cables to be routed into cabinets or panels.
       Commonly used within control and equipment rooms.
                                                      Page 6 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
       Contractor
       Entity entering into a contract with Company to provide overall engineering construction and
       installation.
       Design package
       The drawings and documentation generated during the design process defining the installation.
       Manufacturer
       Entity or sub-supplier producing the equipment item.
                           Severe service
                           Severe service includes high pressure gas, toxic service, gas with small molecules
                           (i.e., hydrogen, ethylene), high vibration and hydraulic service greater than
                           207 barg (3 000 psig), but will be defined by the project or facility.
       Supplier
       Entity entering into a contract with Company to provide materials, goods, supplies, equipment, or
       plant and includes the successors and (or) permitted assigns of such entity.
For the purpose of this Specification, the following symbols and abbreviations apply:
ID Internal diameter.
I/O Input/output.
IP Ingress protection.
IS Intrinsically safe.
LV Low voltage.
OD Outside diameter.
PTFE Polytetrafluoroethylene.
                                                      Page 7 of 47                          GPO-EN-SPE-30256
                                                                                             18 December 2013
Specification for Contractor Instrumentation Installation Requirements
PVC Polyvinylchloride.
5 Order of precedence
              a.    The order of precedence of the codes and standards quoted in the specifications shall be:
                    1.   International and local statutory regulations.
                    2.   Project data sheets.
                    3.   Project specifications.
                    4.   This Specification.
                    5.   Referenced Company documents.
                    6.   Referenced national and international codes.
              b.    Areas of apparent conflict between documents shall be brought to the attention of
                    Company for resolution.
              c.    In the event of a conflict between this document and a relevant law or regulation, the
                    relevant law or regulation shall be followed. If the document creates a higher obligation, it
                    shall be followed as long as this also achieves full compliance with the law or regulation.
              d.    Design, engineering, procurement, and construction for equipment shall comply with the
                    statutory laws and regulations of the final location of the asset. Refer to documents
                    identified in the Purchase Order for a list of these regulations.
              e.    For projects where the final location of the asset is in the EU:
                    1.   Products supplied shall be confirmed to comply with applicable EU directives.
                    2.   A Declaration of Conformity shall be provided.
                    3.   The CE mark shall be affixed to the package nameplate.
                    4.   Components supplied shall be listed together with the EU directives with which they
                         comply and the rationale by which compliance has been achieved.
                    5.   A Technical File in compliance with applicable EU directives shall be compiled and
                         retained for a period of 10 years.
6 Instruments
                                                      Page 8 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
6.2           General
              a.    Instruments shall be installed in conformance to the design specification, equipment
                    specification, approved drawings, and manufacturer’s specification.
              b.    If the installation cannot be carried out to 6.2a, Contractor shall present an alternative
                    proposal which shall be subject to agreement by Company responsible engineer.
                           Alternatives should be reviewed against the design and differences assessed for
                           impact on accuracy and reliability.
              c.    Contractor shall liaise with mechanical contractor to ensure flanged instruments and
                    valves, with particular attention to diaphragm seals, are installed to manufacturer’s
                    procedures and without damage.
              d.    During construction, Contractor shall protect instruments and panels from rain, dirt,
                    sandblast, weld splatter, grinding debris, paint, etc.
              e.    Manual handling of instruments shall be in conformance to the manufacturer’s
                    instructions.
              f.    Panel doors and instrument covers shall be kept closed except when being worked in, and
                    instrument connection openings shall remain plugged until final connections are made.
              g.    Material specification shall be confirmed to data sheets and drawings before installation
                    with particular attention to the following:
                    1.   Instrument parts exposed to process fluids containing hydrogen sulphide specified
                         and installed to conform to NACE MR0175, NACE MR 0103 or ISO 15156, as
                         specified on data sheets.
                    2.   Flanges of instruments and thermowells specified as duplex or super duplex made of
                         materials that conform to GIS 36-320.
                    3.   Copper, silver, mercury or alloys containing these metals (except Alloy 400) not in
                         contact with process fluids.
              h.    Sources of energy e.g. pneumatic, hydraulic etc. shall be identified as to service, flow
                    direction and function at the point of distribution.
              i.    Mounting materials shall be installed to minimise electrolytic corrosion by avoiding the
                    contact of dissimilar metals. Insulating materials shall be inserted between the contact
                    surfaces if the use of dissimilar metals is unavoidable.
              j.    Welding shall not be permitted to pressure-containing parts of pressure vessels.
              k.    Instruments, gauge glasses, sight flow glasses, etc., shall be protected from damage during
                    fabrication, painting, insulation, and other assembly and construction activities. Gauges
                    and glasses etc. shall be free of paint, insulation and other defacing material.
              l.    During sandblasting and painting operations, locally mounted instruments, gauges, glasses,
                    control valve stems, nameplates, and working surfaces shall be covered or removed as
                    applicable.
              m.    If an instrument is inadvertently covered by paint, the paint shall be removed so as to avoid
                    damaging the finish.
                                                      Page 9 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Page 10 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              c.    Contractor shall ensure that all certified electrical equipment has been labelled or marked
                    by supplier with the correct IP rating, category rating, Ex protection type, gas group, and
                    temperature classification where applicable and that the required certificate has been
                    supplied.
              d.    The apparatus sub-group and temperature classification shall be as stated in the project
                    documents.
              e.    Electrical apparatus for use in hazardous areas shall be installed in conformance to:
                    1.   Standard applicable to the project.
                    2.   Type of protection employed.
                    3.   Conditions stated on the apparatus certificates issued by the testing authority.
              f.    Only trained personnel (as detailed in Contractor’s quality management system) shall
                    undertake the installation of hazardous area certified equipment.
              g.    Barrier glands shall be used if specified in project documentation.
              h.    Approved sealing washers shall be used if required to maintain IP rating of equipment.
              i.    Painting of flameproof components, other than that applied by the manufacturer, shall not
                    be permitted.
              j.    Repairs to paintwork on instruments shall be carried out in conformance to the
                    manufacturer’s instructions.
              k.    Obstructions around the flanges of flameproof equipment shall not be permitted.
              l.    Where corrosion inhibiting grease is required, a proprietary non-hazardous material
                    suitable for use with Ex d apparatus shall be applied to the flame path of equipment.
              m.    No alterations or substitutions shall be made to equipment unless this is permitted in the
                    equipment certification.
              n.    The number and size of gland entries into certified enclosures shall not be modified.
                                                     Page 11 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              i.    Instruments, their supports, or connected tubing, piping, or cable shall not constitute a head
                    or tripping hazard.
              j.    Instruments shall be mounted with a clearance of at least 600 mm (2 ft) from equipment
                    with surface temperatures in excess of 40°C (104°F).
                                                     Page 12 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              q.    Instruments shall be tubed so that devices are removable by detaching only the associated
                    tubing and cable without disrupting the functionality of other devices.
              r.    Atmospheric vents, particularly from solenoid valves, shall be directed to avoid a hazard to
                    personnel or equipment and avoid the ingress of moisture and contaminants.
                           In exceptional circumstances it may be required to install a U bend on the vent to
                           achieve this, in agreement with Company responsible engineer. Note that equipment
                           should not be supplied vents facing up when installed correctly.
              s.    Tubing shall be installed in the vent connection, routed to provide a safely directed vent.
              t.    Instruments requiring a vent opening shall have a self-draining, bug proof, breather screen
                    to eliminate blockages.
6.7.1         General
              Protection will be specified if required to maintain instruments within the operating parameters
              defined by the manufacturer.
                                                     Page 13 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                    2.   Shielded, single triad or quad connecting cables with stranded copper conductor, as
                         defined on project drawings.
                    3.   Connected to terminal block or head mounted transmitter in RTD head.
              d.    Thermocouples without head mounted transmitters shall be connected with the correct type
                    of extension wire to eliminate sources of errors produced by dissimilar metal junctions.
              e.    Thermocouple extension wires shall conform to IEC 60584, Part 3, Class 1 or API RP 551,
                    as defined by project documentation.
              f.    Thermocouple heads connected to thermocouple sheaths shall be supported to protect
                    sheathed thermocouple elements from bending forces.
              g.    Temperature sensing elements using filled systems shall be installed with at least 600 mm
                    (24 in) of extra cable and capillary and coiled at the element to permit disconnection
                    without damage to the capillary tube.
              h.    Capillary tubing shall be supported throughout its length and not bent through a tighter
                    radius than 100 mm (4 in).
              i.    Spare capillary shall be coiled neatly, conforming to manufacturer’s guidance, secured and
                    supported to avoid mechanical damage. The coil shall not be less than 200 mm (8 in)
                    diameter.
              j.    Capillaries shall be protected from direct sunlight and sources of heat.
6.10.1        General
              a.    This Specification addresses requirements for non-fiscal flow measurement.
              b.    Custody transfer flow measurement installation is covered in GIS 64-021 for gas or
                    GIS 64-022 for liquid.
                                                     Page 14 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Page 15 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
6.11.1        General
              a.    Stand pipes and chambers shall be mounted vertically to a tolerance not exceeding
                    ±1 degree.
              b.    For instruments having coatings vulnerable to explosive decompression, care shall be
                    taken during venting following any pressure test.
                                                     Page 16 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
6.11.7        Switches
              Level switches shall be removable without the need to disconnect the cable.
6.11.8        Gauges
              a.    Level gauge glasses and magnetic gauges shall be installed and oriented so that they are
                    readable from operational areas.
              b.    Mechanical support for level gauges shall be reviewed to ensure gauges are supported in
                    conformance to manufacturer’s instructions.
                                                     Page 17 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
7 Valve installation
7.1           General
              a.    Contractor shall be responsible for:
                    1.   Liaising to ensure control and actuated on/off valves are handled and installed
                         correctly.
                    2.   Ensuring precautions are taken to avoid inner valve damage to weld end valves.
                    3.   Installing tubing and cabling when flange bolting assembly is complete.
              b.    Installation shall be in conformance to project hook up details, piping arrangements and
                    suppliers requirements.
              c.    The installation shall provide access for maintenance for both valve and actuator.
              d.    Diaphragm and piston-actuated valves shall be installed with their stems vertical and with
                    accessories able to be reached from grade or platform.
              e.    Valves shall be mounted with the flow indication arrow correctly orientated.
              f.    If positioner, position indicator, or actuator need to be changed at site this shall be carried
                    out in conformance to the manufacturer’s procedure and may be witnessed by Company
                    responsible engineer.
                                                     Page 18 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              c.    Equipment, control and I/O rooms, construction, painting, finishing, and clean-up work
                    shall be complete and ready for installing completed control panel, control console,
                    uninterruptible power supply, auxiliary racks, or other control and I/O room hardware.
              d.    HVAC systems shall also be complete and functioning or temporary heating and air
                    conditioning shall be located in the area and in operation to maintain environment to panel
                    supplier’s directions.
              e.    The following applies to panels, cabinets, equipment racks and other similar items, referred
                    to as “panels”:
                    1.   Panels designed for installation indoors shall only be installed when the main
                         structural work is complete including the roof and doors and the facility is dustproof,
                         watertight and air-conditioned.
                    2.   Before installation, Contractor shall check that:
                         a)    Panels are positioned to allow all doors to open fully.
                         b)    Panels and doors are positioned so that they do not impede emergency escape
                               routes.
                    3.   Panels shall be located in conformance to project drawings.
                    4.   Contractor shall provide mounting frames, if specified on project documents, to
                         support panels located in rooms with computer floors so that the base of the panel is
                         level with the finished floor.
                    5.   Mounting frames shall be constructed and finished in conformance to project
                         documents.
                    6.   Panels shall be lifted and moved in conformance to supplier’s procedure, using
                         designated lifting eyes, spreader beams etc. as directed.
                    7.   Removable lifting lugs shall be removed from panels after installation and final
                         positioning. Lifting lug holes shall be plugged by bolts or blanking plugs, supplied by
                         Contractor.
                    8.   Panels shall be bolted to the mounting frame.
                    9.   Instruments removed from panels for transportation or delivered separately, shall be
                         reinstalled and reconnected by the panel supplier or by Contractor under the panel
                         supplier’s supervision.
                    10. Panels bottom gland plates shall be sealed at the cable entry.
                    11. Panels shall not be powered up without authorisation from Company responsible
                        engineer.
                    12. Panel doors shall be locked after installation to prevent access by unauthorised
                        personnel. Key distribution shall be controlled by the Contractor.
                    13. After installation of panels, areas shall be restricted to authorised personnel.
                                                     Page 19 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                           Unistrut or similar.
              c.    Materials shall be in conformance to 6.6c.
              d.    Supports for cable tray runs shall be clamped, bolted or welded to steelwork as specified in
                    project drawings.
              e.    The spacing of cable ladder rack and tray supports shall be as specified on project design
                    drawings or in conformance to manufacturer’s recommendations.
9.3 Cable
9.3.1         General
              a.    Cables shall be installed to project design drawings and documents.
              b.    Cables shall be accurately measured prior to cutting or the cable pulled through a
                    calibrated measuring device.
              c.    Before installation, Contractor shall check that:
                    1.   Routes are accessible and available.
                    2.   The cable is designed for the environmental conditions and installation methods to be
                         used.
              d.    Cables shall not be attached to pipes or structural steel members.
              e.    Cables shall be:
                    1.   Installed clear of process and service pipes to allow for pipe coating and insulation.
                    2.   A minimum distance of 400 mm (16 in) from insulated lines.
                                                     Page 20 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              f.    Cable shall be routed as a continuous length from origin to destination without joints or
                    splices, except if specified otherwise on project design drawings.
              g.    Protection against mechanical damage shall be provided as detailed on the project design
                    drawings where cables pass vertically through floors, platforms, walkways, etc.
              h.    Cables shall be handled and installed so that damage is not caused by abrasion or by
                    tension outside of cable manufacturer’s recommendations.
              i.    Tension applied to cables during installation shall be monitored to prevent stresses being
                    applied that exceed the cable manufacturer’s recommendations.
              j.    Pulling methods shall be detailed in Contractor's procedure.
              k.    Cables shall be laid in smooth parallel formations. Twists, crossing or intertwining of
                    cables shall not be acceptable.
              l.    Cables shall not be bent to a radius below the minimum bending radius as specified by the
                    manufacturer.
              m.    Cables shall not be handled or installed in ambient temperatures lower than those specified
                    by the cable manufacturer.
              n.    Cables shall not be cut and left exposed to the environment for more time than is necessary
                    to complete cable glanding and terminating.
              o.    Cable ends that might be exposed for more than 24 hours shall be sealed using a
                    proprietary method.
              p.    If cable ends are coiled pending installation, cables shall be coiled individually, supported
                    and strapped together to avoid tangling. Armouring wire shall not be used for this purpose.
              q.    Cable coils shall be clearly and legibly identified using non-corrosive material.
              r.    Coils shall be arranged in sequence and for ease of accessibility during installation.
              s.    IS signal cables shall be segregated from NIS signal cables in conformance to the project
                    design documentation.
              t.    Contractor shall ensure that parallel routed electronic signal cables are separated from
                    power cables and lighting cables in conformance to EP-GIS 30-254-1 where installed to
                    project drawings or site run.
              u.    If intersection between groups is unavoidable, the different groups of cable(s) shall cross at
                    right angles without touching.
              v.    Electronic or electrical instrumentation shall be installed with a loop of cable at the device
                    to facilitate removal without causing stress on the cable, and with sufficient length of cable
                    to permit re-glanding in case of damage.
              w.    Top surface cable entries into externally located enclosures shall not be permitted.
                                                     Page 21 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              c.    Cables up to and including 40 mm (1 1/2 in) overall diameter shall be individually secured
                    along their length by EVA coated SS UV resistant, self locking proprietary cable ties.
              d.    Cables above 40 mm (1 1/2 in) overall diameter shall be individually secured along their
                    length by proprietary cable cleats.
              e.    Holding down clips, clamps or ties shall be of such dimensions that when tensioned for the
                    final installation they do not damage the cable sheath or substructure.
              f.    Cables shall be supported within 900 mm (3 ft) of termination points and where they pass
                    through floors, decks etc.
                                                     Page 22 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
9.4 Penetrations
                                                     Page 23 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Page 24 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
9.6           Terminations
              a.    Conductors shall be terminated with compression type lugs unless the equipment being
                    connected to is equipped with clamp type terminals.
              b.    Multi stranded cable conductors up to and including 2,5 mm2 (12 AWG) shall be
                    terminated via bootlace crimp ferrules.
              c.    Only crimping tools with a current calibration certificate shall be used for applying crimps.
              d.    No more than one conductor shall be connected to each terminal, except where detailed on
                    Contractor design drawings. In such cases the two wires shall be crimped together.
              e.    Multicore instrument signal cables or radials shall be protected by neoprene rubber sleeves
                    using a sleeve expander tool.
9.7           Markings
              a.    Cable numbering shall be in conformance to the project cable schedule.
              b.    Cable markers shall be located at each end of the cable and at both sides of cable transits,
                    bulkheads or where the cable enters or leaves a rack or tray.
              c.    Cable markers shall be clearly visible from the direction in which the cables would be
                    normally inspected.
              d.    Core identification, where specified, shall be provided in conformance to the design
                    drawings and be readable in the terminated position.
              e.    Each core of a cable entering an item of equipment shall be marked, using a proprietary
                    cable marking system, as specified in project documentation.
10.1          General
              a.    Combined thread sealant and lubricant shall be used on taper threads for instrument
                    connections, conforming to manufacturer’s instructions, as follows:
                    1.   Anaerobic based fluid sealing compounds on piping and tubing fittings up to
                         temperatures 175°C (350°F)
                    2.   High temperature anti-seize lubricant for services over 175°C (350°F).
              b.    PTFE tape shall not be used, except for analyser sample lines.
              c.    Analyser sample lines shall:
                    1.   Not use sealing compounds or lubricant.
                    2.   Use PTFE tape, applied in conformance to manufacturer’s instructions, without any
                         tape extending beyond or overhanging the first thread.
                           Anaerobic based fluid sealing compounds are not used on analyser sample lines as
                           the compounds affect gas analyser results. This also applies to any PTFE tape in
                           the flow stream.
              d.    Spare manifold ports shall be plugged with a similar metallurgy threaded pipe plug.
                                                     Page 25 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              a.    Impulse lines shall be installed with a minimum continuous slope of 1 in 12 and as few
                    changes in direction as possible.
              b.    Low and high spots shall be avoided but if this is not possible a drain valve at the lowest
                    point or vent valve at the highest point shall be provided.
              c.    Tubing runs shall be installed in conformance to design drawings. Exceptions shall be
                    highlighted in conformance to 6.2b.
              d.    Impulse tubing and piping shall be as short as possible. The length of tube between
                    process isolation valve and instrument should be less than 6 m (20 ft).
              e.    Impulse tubing routing shall be installed in conformance to the drawing provided as part of
                    the design package, where provided.
              f.    Impulse lines, if used, shall:
                    1.   Meet design rating and connection requirements of the process.
                    2.   Have a block valve within 1m (3ft) of the process line and a test and isolation
                         manifold with vents and drains integrated with the instrument.
              i.    Each instrument shall have an isolation valve at the air distribution point or manifold.
              j.    Air supply connections to instruments shall be made with unions or “reusable” tube fittings
                    and shall be supplied with a shutoff valve ahead of the connection.
              k.    Air sub-headers shall be installed with a minimum slope of 1 in 25 and drainage shall be
                    provided at the low points of the headers.
              l.    Filter regulators will be provided as required for individual air supplies to field mounted
                    instruments.
              m.    Air supplies shall be labelled with the tag number of the user at the header end.
                                                     Page 26 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
10.5          Tubing
              a.    Tubing supplied by Contractor shall be in conformance to GIS 30-251 or GIS 30-252
                    (version in the Purchase Order applies).
              b.    Tubing shall not be run in designated high fire risk areas.
              c.    Tubing shall be:
                    1.   Installed with a minimum number of joints.
                    2.   Free of residual mechanical strain.
                    3.   Located in instrument tray or routed to protect the tubing from mechanical damage,
                         liquid spills, or corrosive gasses.
              d.    Deformed or kinked bends shall not be permitted.
              e.    Thermal expansion bends shall be installed when routing straight runs of tubing.
              f.    Tubing shall be routed so that it does not interfere with access to or removal of facility
                    equipment.
              g.    Tubing shall not be installed where it could provide a convenient foothold or step.
              h.    Manufacturer approved cutting tools shall be used in conformance to the manufacturer’s
                    recommendations.
              i.    Tubing shall be de-burred inside and outside, checking that the tube is round and free from
                    burrs and distortions prior to installation.
              j.    Bends shall be used in place of fittings wherever possible.
              k.    The minimum bending radius shall be in conformance to manufacturer’s requirements.
                           Typical requirements are 6 times the outside diameter for l2 mm (1/2 in) and smaller
                           tube and 10 times the outside diameter for multi-tubes.
              l.    Tubing bends shall be made with correctly sized double roller style benders to avoid
                    defects introduced to tubing during the bending process.
                                                     Page 27 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Page 28 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Page 29 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
11.1          General
              a.    Earthing (grounding) and bonding associated with instrumentation systems shall be
                    installed.
              b.    Reference shall be made to project documentation with regard to earthing (grounding) and
                    bonding methods and requirements, in particular the instrument earthing (grounding)
                    philosophy diagrams.
                                                     Page 30 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              e.    Protection against vibration shall be provided, for example by heavy duty single coil spring
                    washers.
              f.    Instrument, fire and gas, and communications devices having metal non-current carrying
                    enclosures and mounted within non-conducting panel framework shall be electrically
                    bonded to an earth (ground) stud, which in turn shall be connected to earth (ground) in
                    conformance to the project drawings.
              g.    Earth (ground) connections shall be dedicated for this purpose and made utilising devices
                    and materials in conformance to requirements specified in project drawings and the codes
                    and standards referenced therein.
              h.    Cover screws and mounting bolts shall not be used as earth (ground) connections.
              i.    The earthing (grounding) system shall be installed in conformance to the project drawings.
              j.    Earthing (grounding) for intrinsically safe circuits shall be in conformance to
                    IEC 60079-14.
              k.    Wire and cable used to make earth (ground) connections shall be:
                    1.   Single core.
                    2.   At least 6 mm² (10 AWG) stranded tinned copper conductor.
                    3.   Sheathed green/yellow.
                    4.   Sized to suit earth (ground) fault load if required.
              l.    Instrument, fire and gas, and communications equipment mounted in a non-conducting
                    panel framework shall be electrically bonded to the nearest protective earth (ground)
                    connection.
11.3 Cabling
11.3.1        General
              a.    Cables shall have their metal armour connected to earth (ground) at both ends, unless
                    specified otherwise on the project drawings.
              b.    Cables shall be checked for roundness before installing glands.
              c.    If the Contractor is responsible for sizing earthing (grounding) cables, they shall be in
                    conformance to the IEE recommendations applicable to the installation.
              d.    Spare cores of multi-core or multi-pair electrical and instrumentation cables shall be
                    terminated into spare terminals and collectively earthed (grounded) within the termination
                    enclosure in conformance to project drawings.
              e.    Spare cores or pairs shall be marked in conformance to project drawings.
              f.    Glands shall be installed in conformance to manufacturer’s instructions by personnel
                    trained in the procedure.
                                                     Page 31 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              d.    Cable screens shall be sleeved and terminated on an isolated terminal in the instrument or
                    other device.
              e.    If a terminal is not available, a 70 mm (3 in) tail shall be sleeved, coiled and insulated for
                    testing purposes.
              f.    Cable screens shall be sleeved green/yellow, insulating tape shall not be permitted.
              g.    Screens and armouring shall be insulated from each other as defined on project drawings.
              h.    Screens in IS cables shall be connected to the IS earth (ground) bar in conformance to the
                    requirements of project drawings.
              i.    Screens in NIS cables shall be connected to the clean earth (ground) bar in conformance to
                    the requirements of project drawings.
              j.    Screens in cables to grounded junction type temperature measurement devices shall be
                    earthed (grounded) at the element end.
              k.    Glands screwed into an Ex d enclosure with removable gland plates that are not bolted to
                    the enclosure using captive nuts shall be fitted with external earth (ground) tags.
              l.    Glands for Ex e and Ex i certified equipment screwed into:
                    1.   A metal enclosure with unpainted gland plates and clearance hole entries shall have
                         internal lock nuts and a serrated shake proof washer fitted.
                    2.   A metal enclosure with painted gland plates and clearance holes entries shall have
                         internal lock nuts and a serrated shake proof washer. The serrated shake proof washer
                         shall be of a design to cut into the painted surface and electrically bond with the base
                         metal.
                    3.   Non metallic enclosures that are not fitted with internal continuity plates connected to
                         an earth (ground) point shall be fitted with external earth (ground) tags, internal lock
                         nuts and a serrated shake proof washer fitted.
              m.    If the material of the gland plate cannot be identified, glands shall have external earth
                    (ground) tags fitted.
              n.    If fitted, earth (ground) tags shall be "daisy-chained" together with a minimum 6 mm²
                    (10 AWG) earth (ground) cable and then connected to an internal earth (ground) point on
                    the enclosure.
                           Tapped holes in one-piece flameproof Ex d certified enclosures do not require a
                           serrated shake proof washer or earth (ground) tag, there being five contactable
                           threads by definition.
                           An Ex d enclosure with removable gland plates that are bolted to the enclosure
                           using captive nuts do not require earth (ground) tags.
                           Tapped holes in a metal enclosure with painted or unpainted gland plates that have
                           at least three threads in contact with the gland thread do not require earth (ground)
                           tags, however an internal lock nut shall be fitted.
                           Non metallic enclosures fitted with internal continuity plates connected to an earth
                           (ground) point do not require earth (ground) tags, but shall have internal lock nuts
                           and a serrated shake proof washer fitted.
                                                     Page 32 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
12.1          General
              a.    Contractor shall ensure that:
                    1.   Equipment and materials are labelled in conformance to project documents.
                    2.   Labels are protected during any local surface preparation work and painting.
              b.    Both equipment and the equipment location shall be labelled so that when equipment is
                    removed for testing or calibration its location remains identified.
              c.    Instrument identification tags shall be SS. Engraving or die stamp shall include the
                    instrument tag number in numerals at least 3 mm (1/8 in) high.
              d.    If SS screws or bolts are not available, tags shall be affixed using SS rivets.
              e.    If rivets, screws or bolts are not available, then identification tags for field instruments
                    shall be attached with SS wire at least 0,75 mm2 (AWG 18) diameter.
              f.    Fixings for labels shall not reduce the IP rating of equipment by, for example, junction
                    boxes fitted with “top hat” brackets.
              g.    Labels shall be manufactured with materials ensuring long service within aggressive
                    environments.
              h.    Abbreviations shall be standardised and consistent for all titles as specified in the project
                    specifications.
              i.    Plastic markers will be permitted on cables unless otherwise defined in project documents.
                                                     Page 33 of 47                               GPO-EN-SPE-30256
                                                                                                  18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                    2.   Service description.
                    3.   Warnings of live terminals.
                    4.   Requirement for remote isolation.
                    5.   Service voltage (power outlets only).
                    6.   Equipment certification details.
              g.    Plastic sandwich type labels shall be manufactured as follows:-
                    1.   Labels for normal NIS services shall be plastic sandwich type white-black-white.
                    2.   Labels for emergency and shutdown NIS services shall be plastic sandwich type
                         white-red-white.
                    3.   Labels for IS services shall be plastic sandwich type blue-white-blue.
                    4.   Labels for emergency and shutdown IS services shall be plastic sandwich type blue-
                         red-blue.
                    5.   Warning labels shall be plastic sandwich type yellow-black-yellow.
              h.    Minimum height of lettering and numbering on labels shall be 5 mm (0,2 in).
13.1          General
              a.    Contractor shall be responsible for:
                    1.   Taking delivery of "free issue" and "Company supplied" equipment and materials
                    2.   Secure storage of all items in environmentally controlled, vibration free conditions in
                         conformance to Contractor's procedure.
                    3.   Continuous stores monitoring and reporting equipment and material usage.
                    4.   Advising Company of any anticipated shortages to avert delays.
              b.    Upon receipt, instruments shall be checked for:
                    1.   Conformance to Purchase Order specifications.
                    2.   Correct tagging.
                    3.   Shipping damage.
                    4.   Relevant documentation (installation and handling instructions).
              c.    After inspection, instruments shall be:
                    1.   Replaced in their original factory boxes.
                    2.   Correctly tagged.
                    3.   Stored on shelves in a dry, enclosed area.
              d.    Prior to installation, instruments shall be stored in a protected and secure environment to
                    prevent ingress of moisture.
              e.    Integrity of sealed protective covers shall be maintained during storage.
              f.    Installed instruments shall be covered using polyethylene throughout construction
                    activities, except during actual work on the instrument.
              g.    Coverings shall be kept in place and integrity of protection maintained until final
                    commissioning in order to protect the device from environmental factors.
                                                     Page 34 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              h.    If equipment items require special treatment during storage, shipment and installation,
                    Contractor shall follow the specific manufacturer’s instructions.
              i.    After installation, vulnerable electrical, instrument, fire and gas, and communications
                    equipment shall be provided with temporary mechanical protection in order to avoid
                    damage to them during construction and activities prior to the commencement of
                    precommissioning and commissioning activities.
13.2          Instruments
              a.    Electronic instruments shall be stored in a dust-free room between 8°C and 45°C (45°F and
                    110°F) or in conformance to manufacturer’s procedure if more onerous.
              b.    Pneumatic instruments shall be stored in a dry area, protected from the elements.
              c.    Instruments shall be sealed and stored in plastic wrap, placed in a box with desiccant bags
                    outside the plastic wrapping, and stored indoors.
                           The desiccant bags should not contact any wiring, terminals, or electronic parts.
              d.    Heating and air conditioning shall be provided where required.
              e.    Rotating equipment shall be periodically rotated in conformance to manufacturer’s
                    instructions to prevent bearing damage.
              f.    Lifting or slinging of equipment shall be done using only manufacturer’s prescribed lifting
                    methods.
              g.    Supply and application of consumables (purging gas, dry air, nitrogen) required for the
                    correct storage and handling of equipment under the care of Contractor shall be the
                    responsibility of Contractor.
              h.    Desiccant bags shall be placed inside equipment enclosures during storage.
              i.    Pneumatic and electrical openings shall be weatherproofed using protective plastic port
                    plugs if storing instruments prior to and during installation.
              j.    Dial thermometers, pressure gauges, and gauge glasses shall be protected against physical
                    damage from construction activities.
              k.    Devices may require removal and storage in a dry, enclosed area for protection. In that
                    case, process connections shall be capped or plugged with metal or plastic caps or plugs
                    until the instruments are installed.
13.3          Panels
              a.    If labelling is not visible, packaging shall only be opened just enough for identification,
                    then resealed.
              b.    Desiccant bags shall be placed inside the packaging before resealing.
              c.    Panels shall be placed in a dry, enclosed or protected area with temperature between 8°C
                    and 45°C (45°F and 110°F) unless project documentation specifies otherwise.
              d.    Panels with internal heaters shall be energised during storage.
13.4          Tubing
              a.    Storage of tubing and fittings for the project shall be managed to avoid any danger of
                    mixing fittings or tube of the wrong size or type.
              b.    Only fittings and tubing in conformance to project requirements e.g. size, wall thickness,
                    customary or metric, manufacturer, shall be held in store.
              c.    Tubing packages shall be segregated and clearly marked by material, size and wall
                    thickness.
                                                     Page 35 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              d.    Tube that is deformed, scratched, scored or otherwise marked shall not be used.
                           These are safety critical requirements. It is crucial that only the correct fittings and
                           tubing are available. Mixing of fittings and sizing can be dangerous. To avoid
                           confusion, if tubing of different wall thicknesses are specified, consider only using
                           the higher rating tubing.
                                                     Page 36 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
14 Quality management
       The quality management system shall conform to ISO 9001, API Specification Q1, or other agreed
       internationally recognised standard to ensure that the products and services provided conform to the
       requirements for supplier quality identified in the Purchase Order.
15.3.1        Scope
              a.    The site inspection covers the mechanical completion checks that shall be carried out on
                    the installed equipment before it is put into service.
              b.    Contractor shall be aware that the mechanical completion checks are to establish that the
                    installation work has been carried out correctly to establish that the equipment is in a ready
                    to energise condition.
              c.    All checks shall be carried out in conformance to Company approved Contractor
                    procedures.
              d.    Contractor shall rectify any faults.
15.3.2        Safety
              Competent and qualified staff shall be provided by Contractor to operate the permit to work
              system.
                                                     Page 37 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
15.3.4        General
              a.    Prior to any testing, inspection or mechanical completion certification, Contractor shall
                    submit the following for Company approval:
                    1.   Procedures, complete with sample recording methods.
                    2.   Qualifications and CV for personnel proposed for inspection activities.
              b.    Procedures shall fully describe:
                    1.   Method to be employed for inspection of each type of equipment.
                    2.   Record sheets to be used.
                    3.   Maximum and minimum test values to be employed.
              c.    Accurate records shall be:
                    1.   Kept of all checks.
                    2.   Retained by Contractor.
                    3.   Handed to Company upon completion as a comprehensive mechanical completion
                         document.
              d.    Equipment required for any tests and mechanical completion activities shall be provided,
                    unless otherwise specified in the Purchase Order, including:
                    1.   Appliances.
                    2.   Instruments.
                    3.   Labour.
                    4.   Fuel.
              e.    Current certificates for all test equipment to be used shall be provided.
              f.    If specifically required, manufacturer’s representatives will be available for supervisory
                    guidance for the testing of major items of equipment. This shall not relieve Contractor
                    from responsibility for providing competent and qualified personnel.
                                                      Page 38 of 47                             GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Page 39 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
15.3.6.1      General
              a.    Piping and tubing shall be inspected for proper support in conformance to specified
                    requirements.
              b.    A mounting inspection test should be carried out for Coriolis metering installations:
                    1.   Test consists of unbolting one set of Coriolis meter flanges along with the piping
                         support fasteners on either side of the Coriolis meter
                    2.   If a shift is seen in the alignment between the unbolted Coriolis meter’s flange and
                         piping flange, it is not acceptable and Contractor shall liaise, in agreement with
                         Company responsible engineer, to rectify the installation.
              c.    Tubing connections shall be tight and in conformance to manufacturer’s specifications.
              d.    Tubing connectors (nuts, ferrules, and fittings) shall be from the same manufacturer and of
                    the same type.
              e.    Inside diameter of tubing and piping shall be verified.
                           Small amounts of dirt or cutting debris may affect hydraulic piping or tubing flow.
                           Also, tubing inside diameter is often reduced after cutting.
              f.    Evidence of leak testing shall be reviewed.
              g.    Field mounted electrical instruments using conduit shall have seals installed with sealant as
                    specified.
                                                     Page 40 of 47                             GPO-EN-SPE-30256
                                                                                                18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                         a)    At least 10% of the fittings in process service (primary tubing runs) shall be
                               disassembled for inspection.
                         b)    For each improperly made up fitting, an additional two fittings shall be inspected
                               by disassembly.
              b.    Inspection criteria for tubing compression fittings shall include:
                    1.   Cleanliness.
                    2.   Burrs or deep longitudinal scratches.
                    3.   Tube ends square.
                    4.   Galling of the ferrule or fitting seat.
                    5.   Tubing is out of round from bends being located too close to the fitting.
                    6.   Tube bottoms in fitting body.
                    7.   Ferrule adequately biting the tube and back from the tube end.
                    8.   Ferrule(s) fitted correct way round.
15.3.6.6      Instrument air sub header, manifold branch lines, and pneumatic signal lines
              a.    A leak test shall be carried out by charging with clean, dry, oil free air, or industrial
                    nitrogen to a pressure of 1 bar (15 psi) above the operating pressure (with individual users
                    capped at consumer end).
              b.    The pressure shall be maintained for 10 minutes and any leakage detected by means of
                    proprietary leak detection fluid.
                                                     Page 41 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Page 42 of 47                               GPO-EN-SPE-30256
                                                                                                  18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Page 43 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
              g.    The following shall be checked for dimension and material conformance to manufacturer
                    and project specifications:
                    1.   Flow orifice meter runs.
                    2.   Venturi tubes.
                    3.   Flow nozzles.
              h.    For orifice plates, bore shall be measured before installation for the following:
                    1.   Bore conforms to data sheet.
                    2.   Bore within tolerances shown in Table 2.
       If applicable, preparation of equipment for transportation shall conform to the packing, marking, and
       shipping instructions or other documents identified in the Purchase Order.
                                                     Page 44 of 47                              GPO-EN-SPE-30256
                                                                                                 18 December 2013
Specification for Contractor Instrumentation Installation Requirements
17 Deliverables
              a.    Technical data, registers, documents, and drawings that together define the scope of the
                    Purchase Order shall conform to the requirements for supplier information identified in the
                    Purchase Order.
              b.    “As Built” documents shall be provided, based on the “AFC” drawings included in the
                    design package supplemented by additional drawings if these are required to convey the
                    status of the project.
              c.    If these additional drawings are of the physical installation, they shall be drawn at the same
                    scale and use the same symbols and format as the design package.
                                                     Page 45 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
                                                     Annex A
                                                    (Normative)
                                           Welding qualification
                                                     Page 46 of 47                            GPO-EN-SPE-30256
                                                                                               18 December 2013
Specification for Contractor Instrumentation Installation Requirements
Bibliography
       BP
[1]     GP 12-15, Wire and Cable (3 December 2003).
[5] GP 30-10, Non-Fiscal Flow Instruments (Class 2 & 3) (29 April 2013).
[8] GP 30-35, Control Valves, Choke Valves, and Pressure Regulators (18 June 2013).
                           At the date of publication, this Specification conforms to the ETPs listed below and
                           any approved deviations from these ETPs:
                           •   GP 12-15, Wire and Cable (3 December 2003).
                           •   GP 12-75, Cable Trays and Raceways (12 December 2003)
                           •   GP 30-01, Temperature Instruments (27 May 2013).
                           •   GP 30-05, Pressure Instruments (07 May 2013).
                           •   GP 30-10, Non-Fiscal Flow Instruments (Class 2 & 3) (29 April 2013).
                           •   GP 30-15, Level Instruments (06 September 2012).
                           •   GP 30-25, Field Instruments - General (30 September 2012).
                           •   GP 30-35, Control Valves, Choke Valves, and Pressure Regulators (18 June
                               2013).
                                                     Page 47 of 47                           GPO-EN-SPE-30256
                                                                                              18 December 2013