DAILY INSULATION WORK REPORT
Client : PT. JURONG ENGINEERING LESTARI
Sub-Cont : PT. REFRACKTORINDO GRAHA DINAMIKA Rev. : 2
Project Name : MUARA TAWAR CCPP BLOCK #2, #3, #4 ADD-ON (650MW) Report. No. : INS/JEL-RGD/IX/19/015
Location : Muara Tawar - Bekasi Date : Thurstday, 11 October 2019
Work Time Weather Time
Start Finish Sunny Cloudy Raining
07:00 WIB 18:00 WIB ✔
PROGRESS Remaining Progress
Volume
No. Description Insulation Cladding Unit Remark
PerDrawing Insulation Cladding
Pre. Day Today Total Pre. Day Today Total
1. HP SYSTEM PIPING INSULATION
1.1 - HP SH System 2.601,44 - - 2.601,44 2.601,44 M2
2.1 - HP Eva System 1.985,76 - - 1.985,76 1.985,76 M2
3.1 - HP Eco System 1.526,36 - - 1.526,36 1.526,36 M2
- -
2. HP SYSTEM PIPING INSULATION - -
1.2 - LP SH System 1.417,16 - - 1.417,16 1.417,16 M2
2.2 - LP Eva System 1.881,64 - - 1.881,64 1.881,64 M2
3.2 - LP Eco System 681,12 - - 681,12 681,12 M2
- -
3. HEATER SYSTEM - -
1.3 - Reheater System 3.376,04 - - 3.376,04 3.376,04 M2
2.3 - Preheater System 936,36 - - 936,36 936,36 M2
- - -
4. BLOWDOWN PIPING SISTEM - - -
1.4 - Blowdown Piping System 958,60 - - 958,60 958,60 M2
- - -
5. SERVICE SYSTEM N2 - - -
- - -
- - -
6. EQUIPMENT - - -
1.6 HP Drum 318,00 - - 318,00 318,00 M2
2.6 LP Drum 293,60 - - 293,60 293,60 M2
3.6 Blowdown Tank 155,20 - - 155,20 155,20 M2
- - -
7. EXHAUST STACK - - -
1.7 Main Stack 4.032,00 - - 4.032,00 4.032,00 M2
8. SUPPORT RING
1.8 Plate Bar 30x3mm Carbon 23.722,00 140,00 210,00 350,00 23.372,00 Kg
2.8 Plate Bar 30x3mm SS304 11.983,00 - 11.983,00 11.983,00 Kg
Sub. Total 55.868,28 - 55.868,28 55.868,28 M2
Today Tools
MANPOWER Qty Pre. Day Total
Absent Come No. Description Stock Pre.Day Today Total Unit Remark
1. DIRECT 1 Imondasi 4 7 1 8 Ea
1.1 - Construction Manager 1 10 1 11 2 Lockformer 4 7 1 8 Ea
2.1 - Site Manager 1 10 1 11 3 Banding Machine 4 7 1 8 Ea
3.1 - Admin - - - 4 Roller Machine 4 7 1 8 Ea
4.1 - Quality Control 1 14 1 15 5 Travo weld 10 13 1 14 Ea
5.1 - Supervisior 1 14 1 15 6 Grinding Machine 20 26 2 28 Ea
6.1 - Safety Cordinator 1 2 1 3 7 Cutting Weld 10 13 1 14 Ea
- - - 8 Drilling Machine 4 7 1 8 Ea
2. INDIRECT - - - 10 Driling Charger 0 - - Ea
1.2 - Foreman 3 26 3 29 11 Scissor 8 14 2 16 Ea
2.2 - Fabricator 1 10 1 11 12 Gun Silicone 0 - - Ea
3.2 - Fitter 1 14 1 15 13 Compass 4 7 1 8 Ea
4.2 - Skill Insulation 2 20 2 22 14 Hummer 8 14 2 16 Ea
5.2 - Scafolder 5 23 5 28 15 Rachet 40 52 4 56 Ea
6.2 - Helper 5 10 5 15 16 Meashuring Tape 20 26 2 28 Ea
7.2 - Driver 1 14 1 15 17 Cable Power 20 26 2 28 Ea
8.2 - Welder 2 10 2 12 18 Ruler 8 14 2 16 Ea
Total Manpower 25 177 - 25 202 19 Plier 4 7 1 8 Ea
20 Adjustable Spaner 8 14 2 16 Ea
Safety Tool & Tranport 21 Raight Angkle 8 14 2 16 Ea
No. Description Qty Pre. Day Today Total 22 Water Level 10 13 1 14 Ea
1 - Body Harness 30 147 25 172 23 Saw 0 - - Ea
2 - Safty Shoes 30 196 25 221 24 0 - -
3 - Safety Helmet 30 196 25 221
4 - Safety Glass 50 189 25 214 Consumable & Accessories Stock Pre.day Today Total Unit Remaining
5 - Safety Gogle 2 28 2 30 1 Stone Disk 4" 20 52 4 56 Ea - 36
6 - Safety Gogle Weld 2 28 2 30 2 Stone Disk 14" 20 13 1 14 Ea 6
7 - Fire Extinguishers 1 14 1 15 3 Electrode Weld 60 9 3,0 12,0 Ea 48,00
8 - Ear Plug - - 4 Hand Glove 300 195 15 210 Set 90
9 - Vehicel 1 14 1 15 5 Self drilling 4.8 87.000 - - Ea 87.000
6 Self drilling 4.2 103.000 - - Ea 103.000
Work Plan For Tummorow 7 Seal Gal' Band 13 8900 - - Ea 8.900
1 - Continue pabricated Jacketing & support ring for Satack 2.1&2.1 8 Seal Gal' Band 19 5800 - - Ea 5.800
2 - Installation Support Ring for HRSG Stack Block 2.1 9 Plate Bar 30 x 3 8000 662,40 80,00 742,40 Kg 7.257,60
3 - Repair Scaffolding for Stack HRSG 2.1 10 Cladding 0,4mm 595 0 - M2 595,00
11 Cladding 0,5mm 0 - M2 -
12 Cladding 0,6mm 500 16,1 16,10 M2 483,90
13 Cladding 0,8mm 645 291,386 7 298,39 M2 346,61
Prepaired by, Witness by, Approved by,
PT. RGD PT. JEL PT. JEL
INSULATION WORK REPORT
Client : PT. JURONG ENGINEERING LESTARI Rev. : 2
Sub. Cont : PT. REFRACKTORINDO GRAHA DINAMIKA Report. No. : INS/JEL-RGD/IX/19/015
Project Name : MUARA TAWAR CCPP BLOCK #2, #3, #4 ADD-ON (650MW) Date : Thurstday, 11 October 2019
Location : Muara Tawar - Bekasi
Fabricated Material Ring Box for Stack Block 2.1 & 2.2 Fabricated Material Support Ring for Stack Block 2.1 & 2.2
Erecting & modifed Scaffolding For Stack HRSG 2.1 Installing Of Support Ring For Stack HRSG 2.1
Prepaired by, Witness by, Approved by,
PT. RGD PT. JEL PT. JEL