Muara Tawar Insulation Work Report

The report provides details of insulation work completed on September 11, 2019 at the Muara Tawar CCPP Block #2, #3, #4 Add-On project location in Bekasi, Indonesia, including progress on insulating various piping systems and equipment, with no work completed but over 55,000 square meters remaining. It also lists the manpower involved and tools used each day.

Uploaded by

supriyanto
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
169 views2 pages

Muara Tawar Insulation Work Report

The report provides details of insulation work completed on September 11, 2019 at the Muara Tawar CCPP Block #2, #3, #4 Add-On project location in Bekasi, Indonesia, including progress on insulating various piping systems and equipment, with no work completed but over 55,000 square meters remaining. It also lists the manpower involved and tools used each day.

Uploaded by

supriyanto
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

DAILY INSULATION WORK REPORT

Client : PT. JURONG ENGINEERING LESTARI


Sub-Cont : PT. REFRACKTORINDO GRAHA DINAMIKA Rev. : 2
Project Name : MUARA TAWAR CCPP BLOCK #2, #3, #4 ADD-ON (650MW) Report. No. : INS/JEL-RGD/IX/19/015
Location : Muara Tawar - Bekasi Date : Thurstday, 11 October 2019
Work Time Weather Time
Start Finish Sunny Cloudy Raining
07:00 WIB 18:00 WIB ✔
PROGRESS Remaining Progress
Volume
No. Description Insulation Cladding Unit Remark
PerDrawing Insulation Cladding
Pre. Day Today Total Pre. Day Today Total
1. HP SYSTEM PIPING INSULATION
1.1 - HP SH System 2.601,44 - - 2.601,44 2.601,44 M2
2.1 - HP Eva System 1.985,76 - - 1.985,76 1.985,76 M2
3.1 - HP Eco System 1.526,36 - - 1.526,36 1.526,36 M2
- -
2. HP SYSTEM PIPING INSULATION - -
1.2 - LP SH System 1.417,16 - - 1.417,16 1.417,16 M2
2.2 - LP Eva System 1.881,64 - - 1.881,64 1.881,64 M2
3.2 - LP Eco System 681,12 - - 681,12 681,12 M2
- -
3. HEATER SYSTEM - -
1.3 - Reheater System 3.376,04 - - 3.376,04 3.376,04 M2
2.3 - Preheater System 936,36 - - 936,36 936,36 M2
- - -
4. BLOWDOWN PIPING SISTEM - - -
1.4 - Blowdown Piping System 958,60 - - 958,60 958,60 M2
- - -
5. SERVICE SYSTEM N2 - - -
- - -
- - -
6. EQUIPMENT - - -
1.6 HP Drum 318,00 - - 318,00 318,00 M2
2.6 LP Drum 293,60 - - 293,60 293,60 M2
3.6 Blowdown Tank 155,20 - - 155,20 155,20 M2
- - -
7. EXHAUST STACK - - -
1.7 Main Stack 4.032,00 - - 4.032,00 4.032,00 M2
8. SUPPORT RING
1.8 Plate Bar 30x3mm Carbon 23.722,00 140,00 210,00 350,00 23.372,00 Kg
2.8 Plate Bar 30x3mm SS304 11.983,00 - 11.983,00 11.983,00 Kg
Sub. Total 55.868,28 - 55.868,28 55.868,28 M2

Today Tools
MANPOWER Qty Pre. Day Total
Absent Come No. Description Stock Pre.Day Today Total Unit Remark
1. DIRECT 1 Imondasi 4 7 1 8 Ea
1.1 - Construction Manager 1 10 1 11 2 Lockformer 4 7 1 8 Ea
2.1 - Site Manager 1 10 1 11 3 Banding Machine 4 7 1 8 Ea
3.1 - Admin - - - 4 Roller Machine 4 7 1 8 Ea
4.1 - Quality Control 1 14 1 15 5 Travo weld 10 13 1 14 Ea
5.1 - Supervisior 1 14 1 15 6 Grinding Machine 20 26 2 28 Ea
6.1 - Safety Cordinator 1 2 1 3 7 Cutting Weld 10 13 1 14 Ea
- - - 8 Drilling Machine 4 7 1 8 Ea
2. INDIRECT - - - 10 Driling Charger 0 - - Ea
1.2 - Foreman 3 26 3 29 11 Scissor 8 14 2 16 Ea
2.2 - Fabricator 1 10 1 11 12 Gun Silicone 0 - - Ea
3.2 - Fitter 1 14 1 15 13 Compass 4 7 1 8 Ea
4.2 - Skill Insulation 2 20 2 22 14 Hummer 8 14 2 16 Ea
5.2 - Scafolder 5 23 5 28 15 Rachet 40 52 4 56 Ea
6.2 - Helper 5 10 5 15 16 Meashuring Tape 20 26 2 28 Ea
7.2 - Driver 1 14 1 15 17 Cable Power 20 26 2 28 Ea
8.2 - Welder 2 10 2 12 18 Ruler 8 14 2 16 Ea
Total Manpower 25 177 - 25 202 19 Plier 4 7 1 8 Ea
20 Adjustable Spaner 8 14 2 16 Ea
Safety Tool & Tranport 21 Raight Angkle 8 14 2 16 Ea
No. Description Qty Pre. Day Today Total 22 Water Level 10 13 1 14 Ea
1 - Body Harness 30 147 25 172 23 Saw 0 - - Ea
2 - Safty Shoes 30 196 25 221 24 0 - -
3 - Safety Helmet 30 196 25 221
4 - Safety Glass 50 189 25 214 Consumable & Accessories Stock Pre.day Today Total Unit Remaining
5 - Safety Gogle 2 28 2 30 1 Stone Disk 4" 20 52 4 56 Ea - 36
6 - Safety Gogle Weld 2 28 2 30 2 Stone Disk 14" 20 13 1 14 Ea 6
7 - Fire Extinguishers 1 14 1 15 3 Electrode Weld 60 9 3,0 12,0 Ea 48,00
8 - Ear Plug - - 4 Hand Glove 300 195 15 210 Set 90
9 - Vehicel 1 14 1 15 5 Self drilling 4.8 87.000 - - Ea 87.000
6 Self drilling 4.2 103.000 - - Ea 103.000
Work Plan For Tummorow 7 Seal Gal' Band 13 8900 - - Ea 8.900
1 - Continue pabricated Jacketing & support ring for Satack 2.1&2.1 8 Seal Gal' Band 19 5800 - - Ea 5.800
2 - Installation Support Ring for HRSG Stack Block 2.1 9 Plate Bar 30 x 3 8000 662,40 80,00 742,40 Kg 7.257,60
3 - Repair Scaffolding for Stack HRSG 2.1 10 Cladding 0,4mm 595 0 - M2 595,00
11 Cladding 0,5mm 0 - M2 -
12 Cladding 0,6mm 500 16,1 16,10 M2 483,90
13 Cladding 0,8mm 645 291,386 7 298,39 M2 346,61

Prepaired by, Witness by, Approved by,

PT. RGD PT. JEL PT. JEL


INSULATION WORK REPORT

Client : PT. JURONG ENGINEERING LESTARI Rev. : 2


Sub. Cont : PT. REFRACKTORINDO GRAHA DINAMIKA Report. No. : INS/JEL-RGD/IX/19/015
Project Name : MUARA TAWAR CCPP BLOCK #2, #3, #4 ADD-ON (650MW) Date : Thurstday, 11 October 2019
Location : Muara Tawar - Bekasi

Fabricated Material Ring Box for Stack Block 2.1 & 2.2 Fabricated Material Support Ring for Stack Block 2.1 & 2.2

Erecting & modifed Scaffolding For Stack HRSG 2.1 Installing Of Support Ring For Stack HRSG 2.1

Prepaired by, Witness by, Approved by,

PT. RGD PT. JEL PT. JEL