Construction Productivity

The document provides productivity rates for various construction tasks over an 8 hour work day. Rates are given for excavation in soft and hard soils, backfilling, concrete protection works like priming and screeding, reinforcement works for footings and slabs, shuttering, concrete works, block works, plastering, painting, partitions, ceilings, tile works, and marble/granite works. Resource requirements are also listed for each task.

Uploaded by

catherine faith
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
927 views10 pages

Construction Productivity

The document provides productivity rates for various construction tasks over an 8 hour work day. Rates are given for excavation in soft and hard soils, backfilling, concrete protection works like priming and screeding, reinforcement works for footings and slabs, shuttering, concrete works, block works, plastering, painting, partitions, ceilings, tile works, and marble/granite works. Resource requirements are also listed for each task.

Uploaded by

catherine faith
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 10

CONSTRUCTION PRODUCTIVITY

All the productivity rates are for working 8 hours/day

DESCRIPTION QTY RATE


Earthworks Excavation work in soft soil 120 m3/day
Excavation work in hard soil 50 m3/day
In layer of 150mm thickness with 95%
Backfilling + Compaction 150 m2/day
MDD value

Concrete Protection Works


Bitumen Priming Works Including surface preparation 200 m2/day
Bitustic works Horizontal/Vertical Surface 150 m2/day
Protection Works (torch applied) Horizontal/Vertical Surface 80 m2/day
Concrete Binding Works 75/100 mm thick Binding Works 120 m2/day
Screed Works 40/50 mm thick C/S Screed 200 m2/day
75/100 mm thick screed with welded steel 120 m2/day
fabric

Reinforcement Works
Isolated/Strap Footing Up to 16mm Ø bars 200 kg
Above 16mm Ø bars 300 kg
Column/Corewall/Staircase 200 kg
Slab with beam/raft Up to 12mm 300 kg
16mm and above 400 kg
Shuttering
Footing With ordinary plywood shutter 8 m2/day
Column/Core Wall/ Staircase With ordinary plywood shutter 6 m2/day
Slab With ordinary plywood shutter 12 m2/day
Concrete Pumping Works
Placing with concrete pump 60 m3/hr
Boom Placer 40 m3/hr
Concrete works
Footings Concrete Placing and Trowel Finishing 160 m3/day
Staircase Concrete Placing and Trowel Finishing 60 m3/day
Slab Concrete Placing and Trowel Finishing 150 m3/day
Placing Precast/Hollow Core Slab Placing in line and level 400 m2/day
Block Works 10/15/20 cm thick block works 10 m2/day
Plaster Works 15mm thick Plaster works with acc. 12 m2/day
20mm thick plaster works with acc. 10 m2/day
Ordinary Painting
Priming works Including Surface Preparation works 150 m2/day
Putty Works 75 m2/day
Painting Works 1st coat 250 m2/day
2nd coat 350 m2/day
Epoxy Paint Surface Prep + Priming 50 m2/day
Painting 100 m2/day
Gypsum Partition Works Frame + Gypsum Partition Installation 120 m2/day
False Ceiling Frame + False Ceiling Fixing 30 m2/day
Tile Works On floor 15 m2/day
On walls 12 m2/day
Marble/Granite Works On floor 20 m2/day
RESOURCE
excavator
rock breaker

1-skilled, 4-unskilled

1-shovel, 1-roller compactor

1-skilled, 1-unskilled
1-skilled, 1-unskilled
1-skilled, 1-unskilled
1-mason, 2-helper
1-mason, 2-helper
1-mason, 2-helper

1-steelman, 1-helper
1-steelman, 1-helper
1-steelman, 1-helper
1-steelman, 1-helper
1-steelman, 1-helper

1-carpenter, 1-helper
1-carpenter, 1-helper
1-carpenter, 1-helper

1-mason, 3-helper
1-mason, 2-helper
2-mason, 3-helper
2-rigger, 1-mason, 2-helper
1-mason, 1-helper
1-plaster mason, 1-helper
1-plaster mason, 1-helper

1-painter, 1-helper
1-painter, 1-helper
1-painter
1-painter
1-painter, 1-helper
1-painter, 1-helper
1-carpenter, 1-helper
1-carpenter, 1-helper
1-mason, 1-helper
1-mason, 1-helper
2-mason, 1-helper