                                                                   Method Statement Form
PROJECT           :    MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
                       DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY :          MUHAMMAD SYAZWAN BIN JAMALUDDIN                                              DATE     :
ELEMENT     :          LANDSCAPING WORKS                                                            PAGE NO :
                                                                               MACHINERY /     MANPOWER /
NO.           TASK                QUANTITY         SEQUENTIAL DIAGRAM                                            OUTPUT            DURATION
                                                                                 TOOLS           LABOUR
 1    Excavate oversite to          1112 m2                                      2 Excavator    2 Operator    Labour constant:     17 ½ days
      formation level                                                                                         0.25hrs (15min) /
      commencing from                                                                                               1 m2
      reduce level, get out,
      load, wheel, spread,                                                                                   15min x 1112 m2
      levelled and                                                                                           = 34day 6hrs for 1
      consolidated directed                                                                                      excavator
      on site.
                                                                                                             35day / 2 excavator
                                                                                                                = 17day 4hrs
                     ONE EXCEL CONSTRUCTION SDN. BHD.
                     SURIA CITY, JALAN PJU 1/32, 47401
                     PETALING JAYA SELANGOR
                     NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
                     exceloneconstruct@gmail.com
                                                                  Method Statement Form
PROJECT          :    MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
                      DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY :         MUHAMMAD SYAZWAN BIN JAMALUDDIN                                              DATE     :
ELEMENT     :         LANDSCAPING WORK                                                             PAGE NO :
                                                                              MACHINERY /          MANPOWER /
NO.           TASK               QUANTITY         SEQUENTIAL DIAGRAM                                                 OUTPUT            DURATION
                                                                                TOOLS                LABOUR
 2    Compaction of all road       1112 m2                                    2 roller compactor    2 operator   Labour constant:       12 days
      formation levels as                                                                                        0.17hr (10min) /
      described before the                                                                                            1 m2
      commencement of any
      construction thereon.                                                                                       10min x 1112 m2
                                                                                                                 = 23day 1hr 22min
                                                                                                                     for 1 roller
                                                                                                                     compactor
                                                                                                                 23 ½ day / 2 roller
                                                                                                                    compactor
                                                                                                                   = 11.75 days
                     ONE EXCEL CONSTRUCTION SDN. BHD.
                     SURIA CITY, JALAN PJU 1/32, 47401
                     PETALING JAYA SELANGOR
                     NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
                     exceloneconstruct@gmail.com
                                                                  Method Statement Form
PROJECT          :    MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
                      DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY :         MUHAMMAD SYAZWAN BIN JAMALUDDIN                                              DATE     :
ELEMENT     :         LANDSCAPING WORK                                                             PAGE NO :
                                                                              MACHINERY /     MANPOWER /
NO.           TASK               QUANTITY         SEQUENTIAL DIAGRAM                                            OUTPUT            DURATION
                                                                                TOOLS           LABOUR
 3    Apply 200mm thick            1112 m2                                      2 Excavator    2 Operator    Labour constant:     17 ½ days
      (finished thickness)                                                                                   0.25hrs (15min) /
      bed of hardcore                                                                                              1 m2
      consolidated, watered
      and blinded with sand                                                                                 15min x 1112 m2
      to receive concrete                                                                                   = 34day 6hrs for 1
      paver                                                                                                     excavator
                                                                                                            35day / 2 excavator
                                                                                                               = 17day 4hrs
                     ONE EXCEL CONSTRUCTION SDN. BHD.
                     SURIA CITY, JALAN PJU 1/32, 47401
                     PETALING JAYA SELANGOR
                     NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
                     exceloneconstruct@gmail.com
                                                                  Method Statement Form
PROJECT          :    MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
                      DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY :         MUHAMMAD SYAZWAN BIN JAMALUDDIN                                              DATE     :
ELEMENT     :         LANDSCAPING WORK                                                             PAGE NO :
                                                                              MACHINERY /         MANPOWER /
NO.           TASK               QUANTITY         SEQUENTIAL DIAGRAM                                               OUTPUT           DURATION
                                                                                TOOLS               LABOUR
 4    Apply 50mm layer of          1112 m2                                      1 Excavator        2 Operator   Labour constant:     23 days
      sand blanket well rolled                                               1 Roller compactor                    Excavator
      and consolidated to                                                                                        0.08hr (5min) /
      falls and camber as                                                                                            1 m2
      described.
                                                                                                                 5min x 1112 m2
                                                                                                                = 11day 4hr 39min
                                                                                                                  for 1 excavator
                                                                                                                Labour constant:
                                                                                                                Roller compactor
                                                                                                                 0.08hr (5min) /
                                                                                                                      1 m2
                                                                                                                 5min x 1112 m2
                                                                                                                = 11day 4hr 39min
                                                                                                                    for 1 roller
                                                                                                                    compactor
                                                                                                                 Total = 23days
                     ONE EXCEL CONSTRUCTION SDN. BHD.
                     SURIA CITY, JALAN PJU 1/32, 47401
                     PETALING JAYA SELANGOR
                     NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
                     exceloneconstruct@gmail.com
                                                                  Method Statement Form
PROJECT          :    MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
                      DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY :         MUHAMMAD SYAZWAN BIN JAMALUDDIN                                              DATE     :
ELEMENT     :         LANDSCAPING WORK                                                             PAGE NO :
                                                                                MACHINERY /   MANPOWER /
NO.           TASK                QUANTITY         SEQUENTIAL DIAGRAM                                               OUTPUT           DURATION
                                                                                  TOOLS         LABOUR
 5    Construct and complete       1112 m2                                         1 bucket     1 skill labour   Labour constant:     12 days
      115mm thick brickwall                                                        1 shovel   4 general labour    0.08hr (5min) /
      with concrete base                                                           1 trowel                           1 m2
      including all necessary
      excavation, formwork                                                                                        5min x 1112 m2
      and reinforcement.                                                                                         = 11day 4hr 39min