Product Manual For New Insulating Oils ACCORDING TO IS 335:2018

This document provides information on product testing and certification for new insulating oils according to the Indian Standard IS 335:2018. It lists the product and title, applicable tests, required test equipment, sampling guidelines, scope of licensing, and schemes for inspection and testing. Major tests included are viscosity, pour point, water content, breakdown voltage, dissipation factor, appearance, acidity, and sulfur content. Testing is required for each classification of oil, with sampling of 10 liters per control unit.

Uploaded by

Ajay Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
894 views8 pages

Product Manual For New Insulating Oils ACCORDING TO IS 335:2018

This document provides information on product testing and certification for new insulating oils according to the Indian Standard IS 335:2018. It lists the product and title, applicable tests, required test equipment, sampling guidelines, scope of licensing, and schemes for inspection and testing. Major tests included are viscosity, pour point, water content, breakdown voltage, dissipation factor, appearance, acidity, and sulfur content. Testing is required for each classification of oil, with sampling of 10 liters per control unit.

Uploaded by

Ajay Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

PM/ IS 335/ 1/ December 2018

PRODUCT MANUAL FOR


NEW INSULATING OILS
ACCORDING TO IS 335:2018

This Product Manual shall be used as reference material by all Regional/Branch Offices &
licensees to ensure coherence of practice and transparency in operation of certification under
Scheme-I of Bureau of Indian Standards (Conformity Assessment) Regulations, 2018 for
various products. The document may also be used by prospective applicants desirous of
obtaining BIS certification licence/certificate.

1. Product : IS 335:2018
Title : New Insulating Oils
No. of Amendments : Nil

2. Sampling Guidelines:
a) Raw material : __
Each Classification (as per clause 5.1 of IS 335:2018) of
b) Grouping guidelines :
New Insulating Oil shall be tested for GoL and CSoL.
c) Sample Size : 10 litres of New Insulating Oil

3. List of Test Equipment : Please refer ANNEX – A

Scheme of Inspection
4. : Please refer ANNEX – B
and Testing

5. Possible tests in a day : Please refer ANNEX – C

6. Scope of the Licence :


“Licence is granted to use Standard Mark as per IS 335:2018 with the following scope:
Name of the product New Insulating Oils
Classification As per clause 5.1 of IS 335:2018

BUREAU OF INDIAN STANDARDS


Manak Bhawan, 9, Bahadur Shah Zafar Marg,
New Delhi – 110002

Page | 1
PM/ IS 335/ 1/ November 2018

ANNEX A

List Of Test Equipment

Major test equipment required to test as per the Indian Standard

Sl. Tests Used in with


Test Equipment
No Clause reference

1 Hydrometer Cl. 6.16

2 Viscometer Cl. 6.1

3 Interfacial Tensiometer Cl. 6.8

4 Pensky Martens Flash Point Tester Cl. 6.15

5 Pour Point Test Apparatus Cl. 6.2

6 Corrosive Sulphur Test Oven along with copper strip Cl. 6.10

7 Tan Delta Apparatus with Test Cell Cl. 6.5

Oxidation Stability Test Apparatus, Burette with stand, Pipette,


8 Cl. 6.12
Measuring Cylinder

9 Karl Fischer Apparatus Cl. 6.3

10 Measuring Cylinder, Beakers Cl. 6.2

The above list is indicative only and may not be treated as exhaustive.

Page 2
PM/ IS 335/ 1/ December 2018
ANNEX B

Scheme Of Inspection And Testing

1. LABORATORY - A laboratory shall be maintained which shall be suitably equipped


(as per the requirement given in column 2 of Table 1) and staffed, where different tests given
in the specification shall be carried out in accordance with the methods given in the
specification.

1.1 The manufacturer shall prepare a calibration plan for the test equipment.

2. TEST RECORDS – The manufacturer shall maintain test records for the tests carried out
to establish conformity.

3. LABELLING AND MARKING – As per the requirements of IS 335:2018.

4.1 REPACKING OF NEW INSULATING OIL – If a firm is doing only re-packing of new
insulating oils at their premises, then each consignment of new insulating oil received shall be
accompanied by a certificate bearing the Standard Mark of the Bureau.

4.2 LEVELS OF CONTROL - The tests as indicated in column 1 of Table 1 and the levels
of control in column 3 of Table 1, shall be carried out on the whole production of the factory
which is covered by this plan and appropriate records maintained in accordance with
paragraph 2 above. In case a license is issued only for re-packing of new insulating oil, then
the tests as indicated in Table 2 of SIT and the levels of controls specified therein, shall be
applicable, instead of Table 1 of SIT.

5. CONTROL UNIT – For the purpose of Table 1 of this Scheme, each class of new insulating
oil produced in a day shall constitute a control unit.

6. REJECTIONS – Disposal of non-conforming product shall be done in such a way so as to


ensure that there is no violation of provisions of BIS Act, 2016.

Page 3
PM/ IS 335/1/December 2018

TABLE 1

(1) (2) (3)


Test Details Test equipment requirement Levels of Control
Cl. Requirement Test Methods R: required (or) S: Sub- No. of Frequency Remarks
Clause Reference contracting permitted Sample
6.1, Table 1, If the insulating oil fails in any
6.1 Viscosity IS 335 R 1 requirement, two more
Table 2
samples shall be drawn from
6.2, Table 1, the same control unit and
6.2 Pour Point IS 335 R 1
Table 2 Each control unit tested for those particular
6.3 Water Content 6.3, Table 2 IS 335 R 1 requirements and the control
unit shall be rejected if there is
6.4 Breakdown Voltage 6.4, Table 2 IS 335 R 1 any further failure. The
Once in three control unit so rejected may be
suitably re-processed and the
6.5 DDF at 90 ºC 6.5, Table 2 IS 335 S 1 months from each
defects rectified. Such
class of oil
re-processed control unit may
6.6 Appearance 6.6, Table 2 IS 335 R 1 be marked when tested again
in accordance with the
6.7 Acidity 6.7, Table 2 IS 335 R 1 Each control unit Scheme and found
Interfacial Tension conforming to the
6.8 6.8, Table 2 IS 335 R 1
(IFT) requirements of the
6.9 6.9, 7.1 Specification.
Sulphur Content IS 335 S 1
7.1 Table 2 Once in three
Corrosive Sulphur and months from each
6.10 Potentially Corrosive 6.10, Table 2 IS 335 S 1 class of oil
Sulphur
6.11 Additives 6.11, Table 2 IS 335 R 1 Each control unit
Once in six months
6.12 6.12, 7.1
Oxidation Stability IS 335 S 1 from each class of
7.1 Table 2
oil
Once in three
6.13 6.13, 7.3
Gassing Tendency IS 335 S 1 months from each
7.3 Table 2
class of oil

Page 4
PM/ IS 335/1/December 2018

TABLE 1

(1) (2) (3)


Test Details Test equipment requirement Levels of Control
Cl. Requirement Test Methods R: required (or) S: Sub- No. of Frequency Remarks
contracting permitted
Clause Reference Sample

6.14, 7.2 1 Once in six months If the insulating oil fails in any
6.14 Electrostatic Charging
Table 2 IS 335 S from each class of requirement, two more
7.2 Tendency (ECT)
oil samples shall be drawn from
the same control unit and
6.15 Flash Point 6.15, Table 2 IS 335 R 1 tested for those particular
Each control unit
6.16 Density 6.16, Table 2 IS 335 R 1 requirements and the control
unit shall be rejected if there is
Polycyclic Aromatics any further failure. The
6.17 6.17, Table 2 IS 335 S 1
(PCA) control unit so rejected may be
suitably re-processed and the
Polychlorinated
6.18 6.18, Table 2 IS 335 S 1 defects rectified. Such
Biphenyls (PCB)
re-processed control unit may
2-Furfural (2-FAL) and Once in six months be marked when tested again
6.19 Related Compounds 6.19, Table 2 IS 335 S 1 from each class of in accordance with the
Content oil Scheme and found
6.20 Particle Content 6.20, Table 2 IS 335 S 1 conforming to the
requirements of the
6.21 DBDS Content 6.21, Table 2 IS 335 S 1 Specification.

6.22 Stray Gassing of Oil 6.22 IS 335 S 1

Note- 1: Sub-contracting is permitted to a laboratory recognized by the Bureau or Government laboratories empanelled by the Bureau.

Note- 2: Levels of control given in column 3 are only recommendatory in nature. The manufacturer may define the control unit/batch/lot and submit his
own levels of control in column 3 with proper justification for approval by BO Head.

Page 5
PM/ IS 335/1/December 2018

TABLE 2

(FOR REPACKING UNIT)

(1) (2) (3)


Test Details Test equipment requirement Levels of Control
Cl. Requirement Test Methods R: required (or) S: Sub-contracting No. of Frequency Remarks
Clause Reference permitted Sample
6.1 Viscosity 6.1, Table 2 IS 335 R 1 If the insulating oil fails in any
6.2 Pour Point 6.2, Table 2 IS 335 R 1 requirement, two more
* samples shall be drawn from
6.3 Water Content 6.3, Table 2 IS 335 R 1
Breakdown
the same consignment and
6.4 6.4, Table 2 IS 335 R 1 tested for those particular
Voltage
Once in six months from requirements and the
6.5 DDF at 90 ºC 6.5, Table 2 IS 335 S 1 each class of oil received consignment shall be rejected
from each manufacturer if there is any further failure.
6.6 Appearance 6.6, Table 2 IS 335 R 1 The consignment so rejected
6.7 Acidity 6.7, Table 2 IS 335 R 1 may be returned to the supplier
*
Interfacial Tension for re-processing.
6.8 6.8, Table 2 IS 335 R 1
(IFT)
6.9 6.9, 7.1
Sulphur Content IS 335 S 1
7.1 Table 2 Once in six months from
Corrosive Sulphur each class of oil received
6.10 and Potentially 6.10, Table 2 IS 335 S 1 from each manufacturer
Corrosive Sulphur
6.11 Additives 6.11, Table 2 IS 335 R 1 *
6.12, 7.1 Once in a year from each
6.1 Table 2
Oxidation Stability IS 335 S 1 class of oil received from
7.1
each manufacturer
Once in six months from
6.1 6.13, 7.3
Gassing Tendency IS 335 S 1 each class of oil received
7.3 Table 2
from each manufacturer

Page 6
PM/ IS 335/1/December 2018

TABLE 2

(FOR REPACKING UNIT)

(1) (2) (3)


Test Details Test equipment requirement Levels of Control
Cl. Requirement Test Methods R: required (or) S: Sub-contracting No. of Frequency Remarks
permitted
Sample
Clause Reference
Electrostatic 6.14, 7.2 Once in a year from each If the insulating oil fails in any
6.14
Charging Tendency Table 2 IS 335 S 1 class of oil received from requirement, two more samples
7.2
(ECT) each manufacturer shall be drawn from the same
6.15 Flash Point 6.15, Table 2 IS 335 R 1 consignment and tested for
*
6.16 Density 6.16, Table 2 IS 335 R 1 those particular requirements
Polycyclic and the consignment shall be
6.17 6.17, Table 2 IS 335 S 1
Aromatics (PCA)
rejected if there is any further
Polychlorinated
6.18 6.18, Table 2 IS 335 S 1 failure. The consignment so
Biphenyls (PCB)
2-Furfural (2-FAL) rejected may be returned to the
and Related
Once in a year from each
6.19 6.19, Table 2 IS 335 S 1 supplier for re processing.
Compounds class of oil received from
Content each manufacturer
6.20 Particle Content 6.20, Table 2 IS 335 S 1
6.21 DBDS Content 6.21, Table 2 IS 335 S 1
6.22 Stray Gassing of Oil 6.22 IS 335 S 1

* From each class of New Insulating Oil produced in a day by each manufacturer, in each consignment received.

Note- 1: Sub-contracting is permitted to a laboratory recognized by the Bureau or Government laboratories empanelled by the Bureau.

Note- 2: Levels of control given in column 3 are only recommendatory in nature. The manufacturer may define the control unit/batch/lot and submit his
own levels of control in column 3 with proper justification for approval by BO Head.

Page 7
PM/ IS 335/1/December 2018

ANNEX C

Possible Tests in a day

(i) Appearance
(ii) Viscosity at 40 ºC
(iii) Viscosity at 0 ºC
(iv) Density at 20 ºC
(v) Flash Point
(vi) Interfacial Tension
(vii) Water content
(viii) Breakdown Voltage
(ix) Acidity

Page 8